gas european network code implementation

7
Gas European Network Code Implementation May 2013 Lisa Martin

Upload: keely-robles

Post on 31-Dec-2015

33 views

Category:

Documents


0 download

DESCRIPTION

Gas European Network Code Implementation. May 2013 Lisa Martin. What has happened so far?. Ofgem open letter on Congestion Management Procedures (CMP) implementation. Included question on impact of change in the Gas Day. Individual TSO process on CMP implementation: - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Gas European Network Code Implementation

Gas European Network Code Implementation

May 2013

Lisa Martin

Page 2: Gas European Network Code Implementation

2

• Ofgem open letter on Congestion Management Procedures (CMP) implementation. – Included question on impact of change in the Gas Day.

• Individual TSO process on CMP implementation:– NGG consults on Bacton/Moffatt - Ofgem approval– IUK consulting (published 30 April) on its I/C – Ofgem/CREG

approval– BBL consults on its I/C- Ofgem/ACM approval– Ireland still under discussion

What has happened so far?

Page 3: Gas European Network Code Implementation

3

Summary of responses on change to Gas Day

• Very consistent tone of responses (non-confidential will be made available on Ofgem website).

• Avoid underestimating the scale of the task.• Preference for early consultation on how it will be implemented

and coordinated approach.• Preference for early decision on a fixed implementation date.• Recognition that change will be felt from offshore to customer

meter, with not all parties under Ofgem jurisdiction.

Page 4: Gas European Network Code Implementation

4

CAM Requirements

• Implementation 1 November 2015• Capacity to be auctioned as bundled, standard products• Applies to interconnector points (Bacton & Moffat) – may also apply to

entry and exit points to and from third countries (subject to relevant NRA decision)

• Applies to capacity that is available to be sold & contracted capacity once it becomes available, e.g. – BBL – capacity that is currently unsold & any that becomes available

through Oversubscription or Surrender (CMP), further capacity from 2016

– IUK – Oversubscription or Surrender, all capacity from 2018– & to relevant capacity at Bacton & in Belgium & Netherlands– So stepwise approach to implementation

• Implementation needs to meet obligations of CAM• There are options for implementation

Page 5: Gas European Network Code Implementation

5

Key Issues to be considered

GB issues Shared issues

Capacity identification e.g. how to calculate capacity at Bacton?

How to bundle capacity?

Should changes apply to all entry/exit points in GB or just interconnection points?

What booking platform to use (PRISMA ) & how this should be governed?

How do we go about changing the gas day?

Interaction between capacity/ allocation & nominations (within-day)?

Ensuring standardised capacity products are sold

TSO cooperation

Package approach at cross-border points - look at CAM, nominations in balancing, charging etc

Page 6: Gas European Network Code Implementation

6

Process

Ofgem NGGCREG Fluxys

IUK

Working groups (GB/ Bel/ NL) ?

Ofgem NGGACM GTS

BBL

Shared issues Shared issues

GB issues

Need to consider with Irish NRAs- Moffat

Page 7: Gas European Network Code Implementation

7