geotechnical investigation report retaining wall
TRANSCRIPT
Prepared for:
The Corporation of the County of Prince Edward
332 Picton Main Street
Picton, Ontario K0K 2T0
December 3, 2020
Redstone Engineering Inc.
1086 Hayes Line, Kawartha Lakes, ON L0A1C0
Mail: 1086 Hayes Line, Cavan, ON L0A1C0
www.redstoneeng.ca
GEOTECHNICAL INVESTIGATION REPORT
RETAINING WALL REPLACEMENT - MUNICIPAL PARKING LOT AT 47 MARY STREET
PICTON, COUNTY OF PRINCE EDWARD, ONTARIO
REDSTONE PROJECT NO. 20R103
TABLE OF CONTENTS
Page
1.0 INTRODUCTION ......................................................................................................................................................... 1
2.0 PURPOSE AND SCOPE................................................................................................................................................ 1
3.0 FIELD AND LABORATORY PROCEDURES .................................................................................................................... 2
4.0 SITE LOCATION AND SURFACE CONDITIONS ............................................................................................................. 3
5.0 SUBSURFACE CONDITIONS ........................................................................................................................................ 4
5.1 GENERAL ................................................................................................................................................... 4
5.2 TOPSOIL AND ORGANICS ........................................................................................................................... 4
5.3 ASPHALT .................................................................................................................................................... 4
5.4 PAVEMENT GRANULARS ........................................................................................................................... 5
5.5 MIXED EARTH FILL ..................................................................................................................................... 5
5.6 NATIVE SOILS (SAND, SILTY SAND) ............................................................................................................ 5
5.7 BEDROCK (INFERRED) ................................................................................................................................ 6
5.8 GROUNDWATER & BOREHOLE CAVE-IN .................................................................................................... 6
5.9 CHEMICAL ANALYSIS ................................................................................................................................. 6
6.0 DISCUSSION AND RECOMMENDATIONS ................................................................................................................... 9
6.1 SITE PREPARATION, EXCAVATION, AND BACKFILL .................................................................................. 10
6.2 PRELIMINARY CHEMICAL CHARACTERIZATION ....................................................................................... 11
6.3 CORROSIVITY POTENTIAL AND CEMENT TYPE ........................................................................................ 12
6.4 WALL FOUNDATIONS .............................................................................................................................. 13
6.5 LATERAL EARTH PRESSURES .................................................................................................................... 15
6.6 PAVEMENT REINSTATEMENT .................................................................................................................. 16
6.7 GENERAL CONSTRUCTION-STAGE RECOMMENDATIONS ....................................................................... 17
6.7.1 Subsoil Sensitivity .................................................................................................................... 17
6.7.2 Test Pit During Tendering ........................................................................................................ 18
6.7.3 Winter Construction ................................................................................................................ 18
6.7.4 Design Review and Construction Inspections .......................................................................... 18
7.0 CLOSURE AND STATEMENT OF LIMITATIONS ......................................................................................................... 19
TABLES
TABLE 1: SUMMARY OF METAL AND INORGANIC ANALYSES RESULTS ............................................................................ 7
TABLE 2: SUMMARY OF VOC AND PHC ANALYSES RESULTS ............................................................................................ 7
TABLE 3: SUMMARY OF PAH ANALYSES RESULTS ............................................................................................................ 8
TABLE 4: SUMMARY OF PCB ANALYSES RESULTS ............................................................................................................. 8
TABLE 5: SUMMARY OF TCLP ANALYSIS RESULTS ............................................................................................................ 9
TABLE 6: SUMMARY OF ANSI/AWWA SOIL CORROSIVITY POTENTIAL RATING & SULPHATE CONTENT ........................ 13
TABLE 7: DEPTH TO COMPETENT STRATA FOR FOUNDATIONS ..................................................................................... 13
TABLE 8: BEARING CAPACITIES FOR WALL FOUNDATIONS ............................................................................................ 14
TABLE 9: PAVEMENT STRUCTURE .................................................................................................................................. 16
FIGURES
FIGURE 1 BOREHOLE LOCATION PLAN
APPENDICES
APPENDIX A BOREHOLE LOGS
APPENDIX B PHYSICAL LABORATORY DATA
APPENDIX C CHEMICAL LABORATORY DATA
Redstone Engineering Inc.
1086 Hayes Line, Kawartha Lakes, ON L0A1C0
Mail: 1086 Hayes Line, Cavan, ON L0A1C0
705-768-9042 redstoneeng.ca
Hydrogeological Geotechnical Environmental
GEOTECHNICAL INVESTIGATION REPORT
RETAINING WALL REPLACEMENT - MUNICIPAL PARKING LOT AT 47 MARY STREET
PICTON, COUNTY OF PRINCE EDWARD, ONTARIO
REDSTONE PROJECT NO. 20R103
1.0 INTRODUCTION
This report describes the results of a geotechnical investigation performed for the proposed
design and construction of a new retaining wall to replace an existing wall located along the
east side of a municipal parking lot with civic address 47 Mary Street in Picton, Ontario.
Redstone Engineering Inc. (Redstone) was retained by the Corporation of the County of Prince
Edward (the County) to conduct this investigation, and provide geotechnical engineering
conclusions and recommendations relevant to design and construction of the new retaining
wall. The work conducted for this investigation was carried out under the authorization of Mr.
Garrett Osborne, C.E.T., Project Manager, Engineering Division, representing the County.
Based on the County’s RFQ for this investigation, a maximum 500m3 of excess soils is expected
to be generated during construction. The new parking lot’s grade in the area of the new wall
may be raised by up to 1m in height. Regarding the new wall design, it is Redstone’s
expectation that it will be suitably designed/engineered by others to be internally stable, based
on geotechnical parameters provided herein.
The County’s RFQ outlined specifications for this project including the number and depth of
boreholes, number of soil samples and parameters for chemical testing.
2.0 PURPOSE AND SCOPE
The purpose of Redstone’s work for this project is to obtain subsurface information regarding
the soil and groundwater conditions at the boreholes, and based on these findings, provide
geotechnical engineering opinions and recommendations relevant to design and reconstruction
of the retaining wall including earthworks, bearing capacity for foundations, frost depth, lateral
earth pressures, and parking lot (pavement structure) reconstruction. This report includes an
analysis of a soil sample for its corrosivity-related parameters and sulphate concentration, and
preliminary chemical characterization of selected soil samples to assist in management of
excess soils generated during construction. This scope does not include a pavement life cycle
costing analysis, or any hydrogeological or environmental assessments.
The following scope of work was performed as part of this investigation.
1. Boreholes were located in relation to the existing wall and parking lot.
2. Underground utility services were located and cleared prior to advancing the boreholes.
Geotechnical Investigation Report Redstone Engineering
Retaining Wall Replacement – Municipal Parking Lot at 47 Mary Street
Picton, County of Prince Edward, Ontario Project No. 20R103
2
3. As requested, the subsurface conditions were explored by advancing, sampling and logging
a total of three (3) boreholes to a depth of 5.2 metres below existing grade (mbeg) or
practical refusal. In addition to these boreholes, three (3) further boreholes (bedrock
refusal probes) were advanced, and two (2) handholes were advanced. See Figure 1 (Test
Hole Location Plan) for the location of these Test holes. Groundwater observations were
obtained from the open boreholes immediately following drilling.
4. The ground at each Test hole was reinstated as close as possible to its original condition
upon completion of the fieldwork.
5. The ground surface elevation at each Test hole was measured using a grade laser, based on
survey and control point information provided by Jewell Engineering (Jewell).
6. Laboratory analyses of representative soil samples was performed, consisting of the
following:
a. Physical: moisture content testing on all recovered samples, and grain size
distribution testing on two (2) samples.
b. Chemical (as requested):
i. one (1) sample of soil was tested for corrosivity-related parameters
(resistivity, pH, redox potential, sulphides), and soluble sulphate.
ii. three (3) soil samples (one from each borehole) were tested for the following
O.Reg.406/19 parameters: metals and inorganics (including pH, electrical
conductivity [EC], and sodium adsorption ratio [SAR]), volatile organic
compounds (VOCs), petroleum hydrocarbons (PHC F1-F4 fractions), polycyclic
aromatic hydrocarbons (PAHs), and polychlorinated biphenyls (PCBs).
iii. one (1) soil sample was subjected to TCLP testing per O.Reg 558 for metals
and inorganics, VOCs, and PCBs.
7. Geotechnical engineering analysis of acquired field and laboratory data, and preparation of
this report summarizing our findings and recommendations.
3.0 FIELD AND LABORATORY PROCEDURES
A field investigation was conducted under the supervision of Redstone staff on November 16,
2020. The work consisted of subsurface exploration by means of advancing, sampling and
logging a total of six (6) exploratory boreholes (three of which were bedrock refusal probes that
did not sample or confirm the overburden), and two (2) handholes. Detailed logs of the
boreholes and handholes (Test holes) were maintained, and representative samples of the
materials encountered were obtained. The location of each Test hole is illustrated on the
attached Test Hole Location Plan (Figure 1).
Geotechnical Investigation Report Redstone Engineering
Retaining Wall Replacement – Municipal Parking Lot at 47 Mary Street
Picton, County of Prince Edward, Ontario Project No. 20R103
3
The boreholes were advanced using a truck-mounted drill rig equipped with approximately
130mm (5”) Outside Diameter (O.D.) solid stem augers and 51 mm O.D. split-spoon samplers.
Redstone’s senior geotechnical engineer supervised the drilling, who logged and sampled the
boreholes. Soil samples were recovered and retained in labeled air-tight containers for
subsequent review and laboratory testing as required.
The depth to groundwater and/or borehole “cave-in” was measured in the open boreholes
upon completion of drilling. The boreholes were backfilled immediately after completion with
a mixture of soil cuttings and bentonite chips. Compacted cold-mix asphalt was used to restore
the boreholes.
Borehole logs detailing the subsurface profiles are provided in Appendix A. Ground surface
elevations at each borehole location were measured using a grade laser and utilizing surveyed
control point information provided by Jewell, as shown on the attached Figure 1. Ground
surface elevations are provided on the borehole logs. Elevations contained in this report are
strictly for engineering analytical purposes only; they must be considered approximate, and
should be verified prior to finalizing any design or contract parameters upon which they are
based.
Physical (geotechnical) laboratory testing consisted of performing moisture content testing on
all recovered samples, and two grain size distribution analyses. The results of the moisture
content tests are presented on the borehole logs, while the grain size distribution analysis
results are attached in Appendix B.
Chemical testing was performed on soil samples as outlined in Section 2 Item 6b of this report.
This testing was performed by Paracel Laboratories Ltd (Paracel), their certificates of analyses
are attached in Appendix C.
4.0 SITE LOCATION AND SURFACE CONDITIONS
The site is located along the easterly side of the County’s municipal parking lot at civic address
47 Mary Street, Picton. The existing retaining wall appears to be a concrete poured in place
wall with some amount of surficial degradation apparent on its vertical face. This investigation
cleared underground utilities from the area of the Test holes advanced, however did not
confirm or identify the location of all utilities at all locations or for the purpose of the project’s
design or construction.
Geotechnical Investigation Report Redstone Engineering
Retaining Wall Replacement – Municipal Parking Lot at 47 Mary Street
Picton, County of Prince Edward, Ontario Project No. 20R103
4
5.0 SUBSURFACE CONDITIONS
5.1 GENERAL
The site is located within a physiographic region known as the Prince Edward Peninsula
(Chapman, L.J. and Putnam, D.F. “The Physiography of Southern Ontario”, 3rd Edition, 1984).
This area is generally identified as having relatively shallow overburden soils over limestone
bedrock.
Following is a summary of the subsurface conditions encountered in the Test holes. Details of
the subsurface conditions encountered at the site are presented graphically on the logs (see
Appendix A). It should be noted that the boundaries between the strata have been inferred
from Test hole observations and non-continuous samples. They generally represent a transition
from one soil type to another, and should not be inferred to represent an exact plane of
geological change. Further, conditions may vary between and beyond the Test holes. Following
is a summarized account of the subsurface conditions encountered in the Test holes.
Based on the information gathered during this investigation, this site’s subsurface stratigraphy
generally consists of a surficial layer of asphalt (or topsoil and organics in the very southern
portion of the site), over pavement gravel over mixed earth fill over inferred bedrock, or over
native sandy soils (in the southern portion of the wall). None of the open boreholes exhibited
groundwater seepage and/or accumulation during drilling operations.
The following sections describe the major soil strata and subsurface conditions encountered
during this investigation in more detail.
5.2 TOPSOIL AND ORGANICS
A layer of material consisting of topsoil and roots (organics) with some amount of gravel
(appearing to be a surficial fill material) was encountered at handholes HH-1 and HH-2. These
holes were advanced to practical refusal on what appeared to be a buried layer of asphalt
pavement (see handhole logs and pictures in Appendix A). The overlying topsoil and organics
with gravel was about 0.21 to 0.33m thick.
5.3 ASPHALT
A surface layer of asphalt was encountered in boreholes BH-1 to BH-6, and ranged in thickness
from about 40mm (in BH-1 and BH-3) to 255mm (in BH-2).
A buried layer of asphalt pavement was exposed in handholes HH-1 and HH-2 at respective
depths of 0.33 and 0.21 mbeg.
Geotechnical Investigation Report Redstone Engineering
Retaining Wall Replacement – Municipal Parking Lot at 47 Mary Street
Picton, County of Prince Edward, Ontario Project No. 20R103
5
5.4 PAVEMENT GRANULARS
A layer of pavement granular fill was encountered immediately beneath the surficial asphalt in
boreholes BH-1 to BH-6. Its thickness ranged from about 60mm (BH-1 and BH-3) to almost
negligible in BH-2. Due to its poor quality and similarity to the underlying earth fill material,
distinguishing this layer from the underling earth fill (and the transition depth from one to the
next) was not clear in each borehole.
5.5 MIXED EARTH FILL
Mixed earth fill was encountered beneath the pavement granulars in the boreholes. It is also
likely present beneath the buried asphalt in the area of handholes HH-1 and HH-2.
The earth fill extended to the bedrock in BH-1 and BH-2 (respective depths of 1.5 and 2.6
mbeg), and to the native silty sand in BH-3 (depth of 2.3 mbeg). This fill contained a mixture of
various colourations (reddish brown to brown to grey to black mottled) and materials (sand and
silt with gravel and trace organics, occasional cinders, occasional bricks). It is noted that the
boreholes and sampling procedures provided only limited intersections of the fill, and due to its
uncontrolled and variable/random nature, contents of the fill may differ between and beyond
the boreholes. The boreholes encountered fill that was in a damp to moist condition, and
generally exhibited a loose in-situ state of relative density.
Moisture content tests performed on recovered samples of the fill yielded values ranging from
about 2 to 32 % moisture by dry weight. A grain size distribution test performed on sample BH-
2 SS-4 yielded the following distribution: 52% gravel, 35% sand, and 13% silt and clay. (Note
this sample was obtained across the interface between the fill and underlying weathered
bedrock; the relative % of gravel shown in the grain size testing may be elevated as a result.)
Chemical testing was performed on three (3) samples of this fill. Section 5.9 of this report
presents the results of this chemical testing.
5.6 NATIVE SOILS (SAND, SILTY SAND)
A layer of native subgrade soil consisting of silty sand grading to sand was encountered beneath
the fill in borehole BH-3. In BH-3, silty sand was first observed at a depth of 2.3 mbeg, and
extended to a depth of about 4.4 mbeg, where the soil graded to a sand that extended to the
full depth of investigation in this borehole (5.2 mbeg).
The silty sand was fine to medium-grained, and exhibited a brown colouration, with a damp,
loose state of relative density extending to about 3.5 mbeg. At this depth, the silty sand began
exhibiting a brown/dark brown layering, and the relative density increased to compact. At
about 4.4 mbeg, the silty sand graded to a sand with silt that exhibited a medium-grained
texture, brown colouration, in a damp condition, and a compact state of relative density.
Geotechnical Investigation Report Redstone Engineering
Retaining Wall Replacement – Municipal Parking Lot at 47 Mary Street
Picton, County of Prince Edward, Ontario Project No. 20R103
6
Moisture content tests conducted on sample of these soils yielded values of about 7 to 15 %
moisture by dry weight. A grain size distribution test performed on a sample of this soil yielded
the following composition: 0 % gravel, 76 % sand, and 24 % silt and clay-sized particles.
5.7 BEDROCK (INFERRED)
The presence of bedrock (and some amount of overlying weathered bedrock) was inferred from
practical refusal to further auger advancement encountered in BH-1, BH-2, BH-4, BH-5, and BH-
6 at depths ranging from 1.1 to 2.9 mbeg. No diamond coring or test pitting was performed to
confirm the bedrock as part of this investigation. Based on published literature for the area,
the bedrock is expected to consist of limestone.
The depth at which practical refusal was encountered was interpreted by Redstone as being the
depth of competent bedrock for the purpose of logging the boreholes. However, it is noted
that bedrock typically exhibits a certain degree of weathering and fracturing in its upper zone,
some of which is shown on the borehole logs. This weathering effect can increase significantly
in shale and limestone. It is possible that some of the material shown as being soil in the logs
may be highly weathered/fractured/fragmented bedrock that was penetrated by the drilling
prior to practical refusal occurring.
5.8 GROUNDWATER & BOREHOLE CAVE-IN
No groundwater accumulation was observed to the full depth of any of the boreholes
advanced. No groundwater monitoring wells were installed as part of this investigation.
Boreholes BH-1 to BH-6 remained effectively open to their full depth throughout the drilling
operations, with only nominal amounts of slough or cave-in (i.e. less than 0.1m) noted at the
bottom of each borehole upon their completion.
5.9 CHEMICAL ANALYSIS
Three (3) selected soil samples (one sample per borehole) were analyzed for general Metals
and Inorganic parameters under Ontario Regulation O.Reg.406/19. Test results were compared
to the Ministry of the Environment, Conservation and Parks (MECP) standards listed in Table 1
(Full Depth Background Site Condition Standards) for Residential/ Parkland/ Institutional/
Industrial/ Commercial/ Community (RPIICC) Property Use, Table 3.1 (Full Depth Excess Soil
Quality Standards in a Non-Potable Ground Water Condition) for Residential/ Parkland/
Institutional (RPI) and Industrial/ Commercial/ Community (ICC) Property Uses, and Table 2.1
(Full Depth Excess Soil Quality Standards in a Potable Ground Water Condition) for Agriculture
or other (AG) Property Use as per O.Reg.406/19. The tested soil samples met the respective
MECP standards, with the exceptions listed in Table 1. A copy of the laboratory certificate of
analysis is provided in Appendix C.
Geotechnical Investigation Report Redstone Engineering
Retaining Wall Replacement – Municipal Parking Lot at 47 Mary Street
Picton, County of Prince Edward, Ontario Project No. 20R103
7
Table 1: Summary of Metal and Inorganic Analyses Results
TESTED
SAMPLE I.D.
PARAMETER EXCEEDANCES
MECP
Table 1 RPIICC
MECP
Table 3.1 RPI
MECP
Table 3.1 ICC
MECP
Table 2.1 AG
BH-1 SS-2 Mercury, Lead Mercury, Lead Mercury, Lead Mercury, Lead
BH-2 SS-2 EC, SAR, Mercury EC, SAR, Mercury Mercury EC, SAR, Mercury,
Lead
BH-3 SS-4 SAR None None None
Note: SAR and EC denote Sodium Adsorption Ratio and Electrical Conductivity respectively.
The above noted three (3) soil samples were analyzed for Volatile Organic Compounds (VOC)
and petroleum hydrocarbon (PHC, F1 to F4 fraction) parameters under O.Reg.406/19. Test
results were compared to the MECP standards listed in Table 1 (Full Depth Background Site
Condition Standards) for Residential/ Parkland/ Institutional/ Industrial/ Commercial/
Community (RPIICC) Property Use, Table 3.1 (Full Depth Excess Soil Quality Standards in a Non-
Potable Ground Water Condition) for Residential/ Parkland/ Institutional (RPI) and Industrial/
Commercial/ Community (ICC) Property Uses, and Table 2.1 (Full Depth Excess Soil Quality
Standards in a Potable Ground Water Condition) for Agriculture or other (AG) Property Use as
per O.Reg.406/19. The tested soil samples met the respective MECP standards, with the
exceptions listed in Table 2. A copy of the laboratory certificate of analysis is provided in
Appendix C.
Table 2: Summary of VOC and PHC Analyses Results
TESTED
SAMPLE I.D.
PARAMETER EXCEEDANCES
MECP
Table 1 RPIICC
MECP
Table 3.1 RPI
MECP
Table 3.1 ICC
MECP
Table 2.1 AG
BH-1 SS-2 Xylenes None None None
BH-2 SS-2 None None None None
BH-3 SS-4 None None None None
The above noted three (3) soil samples were analyzed for Polycyclic Aromatic Hydrocarbons
(PAH) parameters under O.Reg.406/19. Test results were compared to the MECP standards
listed in Table 1 (Full Depth Background Site Condition Standards) for Residential/ Parkland/
Institutional/ Industrial/ Commercial/ Community (RPIICC) Property Use, Table 3.1 (Full Depth
Excess Soil Quality Standards in a Non-Potable Ground Water Condition) for Residential/
Parkland/ Institutional (RPI) and Industrial/ Commercial/ Community (ICC) Property Uses, and
Geotechnical Investigation Report Redstone Engineering
Retaining Wall Replacement – Municipal Parking Lot at 47 Mary Street
Picton, County of Prince Edward, Ontario Project No. 20R103
8
Table 2.1 (Full Depth Excess Soil Quality Standards in a Potable Ground Water Condition) for
Agriculture or other (AG) Property Use as per O.Reg.406/19. The tested soil samples met the
respective MECP standards, with the exceptions listed in Table 3. A copy of the laboratory
certificate of analysis is provided in Appendix C.
Table 3: Summary of PAH Analyses Results
TESTED
SAMPLE I.D.
PARAMETER EXCEEDANCES
MECP
Table 1 RPIICC
MECP
Table 3.1 RPI
MECP
Table 3.1 ICC
MECP
Table 2.1 AG
BH-1 SS-2 Naphthalene None None Methylnaphthalene
(1&2)
BH-2 SS-2 Acenaphthylene Acenaphthylene Acenaphthylene Acenaphthylene,
Anthracene
BH-3 SS-4 None None None None
The above noted three (3) soil samples were analyzed for Polychlorinated Biphenyl (PCB)
parameters under O.Reg.406/19. Test results were compared to the MECP standards listed in
Table 1 (Full Depth Background Site Condition Standards) for Residential/ Parkland/
Institutional/ Industrial/ Commercial/ Community (RPIICC) Property Use, Table 3.1 (Full Depth
Excess Soil Quality Standards in a Non-Potable Ground Water Condition) for Residential/
Parkland/ Institutional (RPI) and Industrial/ Commercial/ Community (ICC) Property Uses, and
Table 2.1 (Full Depth Excess Soil Quality Standards in a Potable Ground Water Condition) for
Agriculture or other (AG) Property Use as per O.Reg.406/19. The tested soil samples met the
respective MECP standards, with the exceptions listed in Table 4. A copy of the laboratory
certificate of analysis is provided in Appendix C.
Table 4: Summary of PCB Analyses Results
TESTED
SAMPLE I.D.
PARAMETER EXCEEDANCES
MECP
Table 1 RPIICC
MECP
Table 3.1 RPI
MECP
Table 3.1 ICC
MECP
Table 2.1 AG
BH-1 SS-2 None None None None
BH-2 SS-2 None None None None
BH-3 SS-4 None None None None
Geotechnical Investigation Report Redstone Engineering
Retaining Wall Replacement – Municipal Parking Lot at 47 Mary Street
Picton, County of Prince Edward, Ontario Project No. 20R103
9
One (1) composite soil sample was formed by combining representative portions of samples
BH-1 SS-3, BH-2 SS-3, BH-2 SS-4, BH-3 SS-2, BH-3 SS-3a and BH-3 SS-3b. This composite sample
is identified herein as “CS-2”. This sample was analyzed for Metals and Inorganic parameters,
PCBs, and VOCs by Toxicity Characteristic Leaching Procedure (TCLP) extraction. Test results
were compared to Schedule 4 of O.Reg.558. The tested soil sample met the relevant guidelines
as presented in Table 5 below. A copy of the laboratory certificate of analysis is provided in
Appendix C.
Table 5: Summary of TCLP Analysis Results
TESTED
SAMPLE I.D.
PARAMETER EXCEEDANCES
Metals & Inorganics VOCs PCBs
BH-1 SS-2 None None None
BH-2 SS-2 None None None
BH-3 SS-4 None None None
Section 6.2 of this report presents a discussion of these test results.
6.0 DISCUSSION AND RECOMMENDATIONS
Supporting data upon which our recommendations are based have been presented in the
foregoing sections of this report. The following recommendations are governed by the physical
properties of the subsurface materials that were encountered at the site and assume that they
are representative of the overall site conditions. It should be noted that these conclusions and
recommendations are intended for use by the designers only. Contractors bidding on or
undertaking any work at the site should examine the factual results of the assessment, satisfy
themselves as to the adequacy of the information for construction, and make their own
interpretation of this factual data as it affects their proposed construction techniques,
equipment capabilities, costs, sequencing, and the like. Comments, techniques, or
recommendations pertaining to construction must not be construed as instructions to the
contractor.
The boreholes generally encountered a surficial layer of asphalt (or topsoil/organics in the
southerly portion of the site), over pavement granulars, over mixed earth fill over either
bedrock, or native sandy soil (in the southern portion of the site). Groundwater seepage and
accumulation was not observed in any of the open boreholes.
Details regarding our conclusions and recommendations are outlined in the following sections.
Geotechnical Investigation Report Redstone Engineering
Retaining Wall Replacement – Municipal Parking Lot at 47 Mary Street
Picton, County of Prince Edward, Ontario Project No. 20R103
10
6.1 SITE PREPARATION, EXCAVATION, AND BACKFILL
It is recommended that any and all vegetation, topsoil, asphalt, fill, organic and organic-bearing
materials be stripped and removed from the retaining wall area prior to commencing
earthwork construction. Due to the anticipated variable depth of existing fill material requiring
removal during construction, it is recommended the construction tender require a provisional
per-unit line item for excavation and removal of existing materials, which can be applied should
actual quantities of removal exceed estimated quantities.
Excavations should be carried out to conform to the manner specified in Ontario Regulation
213/91 and the Occupational Health and Safety Act and Regulations for Construction Projects
(OHSA). All excavations above the water table not exceeding 1.2m in depth may be constructed
with unsupported slopes. The soils encountered during this investigation are classed by OHSA
as Type 3. As such, unsupported walls of excavations in this soil must maintain a gradient of 1
horizontal to 1 vertical (1H:1V) or flatter to the base of the excavation. All neighbouring
structures must be protected from disturbances during construction, including (if necessary)
underpinning and/or shoring.
The subexcavated surfaces must be proof rolled and/or approved by Redstone prior to
placement of fill or foundations.
Groundwater was not encountered within the full depth of the open boreholes advanced
during this investigation; subsequent groundwater depth monitoring was not performed as part
of this investigation. Based on the groundwater conditions observed in the open boreholes,
and the anticipated excavation depths for the project, significant groundwater infiltration into
open excavations is not expected. In general, any groundwater or surficial water infiltration
into open excavations above the groundwater table is expected to be controlled by pumping
from sump(s) to an acceptable outlet. Should more significant groundwater infiltration be
encountered, the use of filtered pumps, sheet piling, or other forms of groundwater control
may be required in which case it would be recommended the contractor retain the services of a
qualified dewatering specialist.
The excavated asphalt, organics, and fill materials are not expected to be suitable for reuse as
any form of structural-related back-fill. See Section 6.2 regarding preliminary chemical
characterization of the fill materials and further commentary regarding handling and
movement/disposal of such materials offsite during construction. Topsoil and other suitable
organic materials may be considered for reuse as surficial topsoil material in landscaped and
non-structural areas. Any excavated native sand may be suitable for reuse as backfill behind
the wall, provided the moisture content is adequate for compaction and workability. Final
review and approval to reuse any soils should be made during construction, based on the
materials exposed and prevailing conditions at that time.
It is recommended that free draining backfill to the retaining wall be provided. Backfill behind
the wall should be accomplished using well graded Granular “B” Type 1 material complying with
Geotechnical Investigation Report Redstone Engineering
Retaining Wall Replacement – Municipal Parking Lot at 47 Mary Street
Picton, County of Prince Edward, Ontario Project No. 20R103
11
OPSS 1010. Compaction of such backfill is recommended to be a minimum of 100% of its
Standard Proctor Maximum Dry Density, (SPMDD).
It is understood the final grade may be raised by up to 1m in the area behind the new wall.
Where the fill is placed on bedrock subgrade, the resulting consolidation settlement of the
bedrock subgrade will be negligible. Where the backfill is placed on native sandy soil subgrade,
the nature of such soils means consolidation settlement caused by the backfill grade raise will
occur relatively quickly (i.e. during construction), and therefore only negligible effective
settlements will be experienced at the surface once final grading is achieved at the end of
construction. In addition to any short-term consolidation settlements occurring in the
subgrade, the designer must also be aware of self-weight settlement of the backfill material
itself; engineered fill consisting of Granular B material compacted to 100% SPMDD will settle
under its own weight approximately 0.3% to 0.5% of the final fill thickness. For example, where
the granular fill thickness is 3m in height, the settlement of such fill under its own weight is
expected to be in the range of about 9mm to 15mm. For engineered fill consisting of Granular
B material compacted to 100% SPMDD, a major portion (at least 80%) of the self-weight
settlement should occur during construction. To accommodate such settlements, it is
recommended that the construction project include a stage near the end of the project that
performs final fine grading to ensure the design grade is accomplished.
6.2 PRELIMINARY CHEMICAL CHARACTERIZATION
Three (3) soil samples of the existing fill (one from each borehole) were collected during drilling
and placed into laboratory-provided containers for environmental testing. Soil samples were
analyzed for general Metals and Inorganics (including pH, EC, and SAR), VOCs, PHCs (F1-F4
fractions), PAHs, and PCB parameters per O.Reg.406/19. One (1) soil sample was also analyzed
for TCLP (metals and inorganics, PCBs and VOCs) under O.Reg.558.
Test results were compared to the MECP standards listed in Table 1 (Full Depth Background Site
Condition Standards) for Residential/Parkland/Institutional/Industrial/Commercial/Community
(RPIICC) Property Use, Table 3.1 (Full Depth Excess Soil Quality Standards in a Non-Potable
Ground Water Condition) for Residential/Parkland/Institutional (RPI) and
Industrial/Commercial/Community (ICC) Property Uses, and Table 2.1 (Full Depth Excess Soil
Quality Standards in a Potable Ground Water Condition) for Agriculture or other (AG) Property
Use, as per O.Reg.406/19. Section 5.9 of this report presents these tabulated comparisons.
Note that MECP Table 3 (ICC) criteria are generally used to assess soil quality in municipally
serviced areas. However, for soil to be exported to another property as “clean fill”, it is
advisable that the quality may need to meet MECP Table 1 (RPIICC) criteria. The potential
receiving site’s MECP designation in this regard would be assessed by that site’s Qualified
Person (QP, as defined by the MECP), in accordance with O.Reg.406.
Geotechnical Investigation Report Redstone Engineering
Retaining Wall Replacement – Municipal Parking Lot at 47 Mary Street
Picton, County of Prince Edward, Ontario Project No. 20R103
12
While one sample of the existing fill only yielded one parameter exceedance (of SAR) in
comparison to Table 1 RPIICC, the other two samples yielded exceedances across a number of
parameters when compared to Tables 1, 2, and 3 excess soil quality standards (see Section 5.9
of this report). These results do not support movement of excess soils represented by these
samples to Types 1, 2, or 3 sites.
TCLP testing was performed on a representative sample of the fill - see Section 5.9 for detailed
results. The TCLP testing results are below the Leachate Quality Criteria (O. Reg. 558/00) for all
parameters tested, and hence excess soil generated from the proposed construction activities
can be considered as “non-hazardous and non-registrable” waste for disposal at a suitably-
licensed landfill facility.
Due to the expected predominance of existing fill in the excess soils generated during
construction, the sampling and testing conducted as part of this investigation remained focused
on this material. If the design requires increasing amounts of the underlying native sandy soils
to be removed, then it is expected that such soil could either remain onsite (as backfill in some
appropriate form if approved as such from a physical-property perspective), or removed offsite
to a suitable receiving site pending confirmatory testing.
The final volume of excess soil to be generated and shipped offsite during construction, and the
potential receiving site(s) have not been identified at this stage. The number of samples and
chemical parameters tested were as specified in this project’s RFP. The test results and related
commentary herein are provided as preliminary chemical characterization for the purposes of
supporting excess soil management during construction; however the number of samples,
and/or the analytical parameters tested, may not be sufficient to meet the requirements of the
intended receiving site(s). Further sampling and testing may be required depending on the
types and volume of material generated, the handling option(s), receiving site(s) under
consideration, and other relevant information that becomes available over time.
Furthermore, in addition to the requirement for soil receiving sites, planning requirements
including testing, tracking, hauling, reporting and registration are specified under O.Reg. 406/19
On-site and Excess Soil Management. Any new contracts entered into after January 1, 2021
must consider the new planning rules under O.Reg.406/19.
6.3 CORROSIVITY POTENTIAL AND CEMENT TYPE
One (1) soil sample (identified as “CS-1”) was formed by combining soil from the following
samples into one composite sample: BH-1 AS-1, BH-2 AS-1, BH-3 SS-1. This composite sample
was then submitted to Paracel for laboratory analyses of its pH, resistivity, redox potential,
sulphide and soluble sulphate concentrations to determine the corrosive potential of the soil.
The following Table 6 summarizes the ANSI/AWWA rating for the tested soil sample for the
potential for corrosion towards buried grey or ductile cast iron pipe. Points assigned for each
Geotechnical Investigation Report Redstone Engineering
Retaining Wall Replacement – Municipal Parking Lot at 47 Mary Street
Picton, County of Prince Edward, Ontario Project No. 20R103
13
parameter based on this scoring system are shown in parentheses - a total of 10 points or more
indicates potential for corrosion.
Table 6: Summary of ANSI/AWWA Soil Corrosivity Potential Rating & Sulphate Content
Sample I.D. RESISTIVITY
(ohms-cm) pH
REDOX
POTENTIAL
(mV)
SULPHIDE
(%)
MOISTURE
CONTENT
(%)
Sulphate
Content
(µg/g)
TOTAL
POINTS
CS-1 3390 (0) 7.78 (0) 353 (0) 0.09 (1) 5.5, fair
drainage (1) 82 2
Based on the results and associated rating, the corrosivity potential of the tested soil sample is
considered low to negligible. It should be noted that there are other factors which may
influence the corrosion potential, such as; the nature of effluent conveyed, the application of
de-icing salts on the site and subsequent leaching into the subsoils, and stray currents.
Soil sample CS-1 was also submitted for laboratory analysis of its soluble sulphate level to
assess the potential for degradation of buried concrete in contact with the encountered soil.
The soluble sulphate concentration of the tested sample was 82 ug/g (82 ppm or 0.0082%).
Based on this result, the potential for sulphate attack on concrete is considered “negligible”
based on CSA Standard A23.1, Concrete Materials and Methods of Concrete Construction. It
should, however, be noted that the final selection of the type of concrete should be made by
the Engineer taking into account all design considerations.
6.4 WALL FOUNDATIONS
For the purpose of foundation design for the wall, such foundations should be placed directly
on either bedrock, or native compact soil (sand or silty sand), or on engineered fill placed
directly on such materials. Suitably competent bedrock or native soils were encountered at the
following depths in the boreholes:
Table 7: Depth to Competent Strata for Foundations
Borehole I.D. Depth (mbeg) Borehole I.D. Depth (mbeg)
BH-1 1.7 BH-4 2.9
BH-2 2.7 BH-5 1.1
BH-3 3.5 BH-6 1.4
Geotechnical Investigation Report Redstone Engineering
Retaining Wall Replacement – Municipal Parking Lot at 47 Mary Street
Picton, County of Prince Edward, Ontario Project No. 20R103
14
For design purposes, it is recommended that the wall’s footings constructed on the bedrock or
competent native soils or on engineered fill placed directly on such materials be proportioned
using the following bearing capacities:
Table 8: Bearing Capacities for Wall Foundations
Parameter
Bearing Capacity (kPa)
Sound Bedrock Undisturbed Native Soil
(Sand or Silty Sand) Engineered Fill(2)
Factored Bearing Capacity at ULS (1) 750
150 180
Bearing Capacity at SLS 100 120
Notes:
(1) Resistance factor Φ =0.5 applied to the ULS bearing pressure for design purposes.
(2) At least 0.3m of Granular B per OPSS 1010. Quality of material is to be approved prior to use as engineered fill.
Any engineered fill upon which the footings are placed must be a minimum thickness
corresponding to the notes that accompany the above table. The following is recommended
for the construction of any engineered fill for the footings:
1. Remove any and all existing vegetation, topsoil, asphalt, fill, disturbed earth, organics, and
organic-bearing soils to the competent, undisturbed bedrock or native soil from within the
area of the proposed engineered fill.
2. The area of the engineered fill should extend horizontally 1m beyond the outside edge of
the proposed wall foundations and then extend downward at a 1:1 slope to the competent
native soil.
3. The base of the engineered fill area must be approved by a member of Redstone prior to
placement of any fill, to ensure that all unsuitable materials have been removed, that the
materials encountered are similar to those observed during this investigation, and that the
subgrade is suitable for the engineered fill.
4. All engineered fill material is to be approved by Redstone or other qualified geotechnical
engineer at the time of construction.
5. Place approved engineered fill, in maximum 200 mm loose lifts, compacted to 100% of its
SPMDD.
6. Full time testing and inspection of the engineered fill will be required, to ensure compliance
with material and compaction specifications.
For frost protection purposes, the retaining wall’s footings must be covered by at least 1.2m of
earth in all directions, or be treated with an equivalent frost protection (such as suitable
insulation). Backfill should be accomplished using non-frost susceptible Granular B material.
Geotechnical Investigation Report Redstone Engineering
Retaining Wall Replacement – Municipal Parking Lot at 47 Mary Street
Picton, County of Prince Edward, Ontario Project No. 20R103
15
Under no circumstances should the foundations be placed above organic materials, loose,
frozen subgrade, construction debris, or within ponded water. Prior to forming, all foundation
excavations must be inspected and approved by a member of Redstone. This will ensure that
the foundation bearing material has been prepared properly at the foundation subgrade level
and that the soils or bedrock exposed are similar to those encountered during this
investigation.
For design purposes this site is classed as Site Class C for Seismic Site Response, in accordance
with the Ontario Building Code (OBC).
6.5 LATERAL EARTH PRESSURES
It is recommended that free draining backfill to retaining walls be provided. As no groundwater
was encountered during this investigation, the new retaining wall is expected to be located
above the groundwater table. Walls located above the groundwater table and utilizing free
draining Granular B backfill compacted to 100% SPMDD may be designed for lateral earth
pressures using the following equation:
p = k (w h + q),
where:
• p = the lateral earth pressure in kPa acting on the subsurface wall at depth h;
• ka = the coefficient of active earth pressure;
o ( = 0.33 for walls restrained from the bottom only);
o ( = 0.5 for walls restrained at the top and bottom*);
• kp = the coefficient of passive earth pressure ( = 3.0);
• ko = the coefficient of at-rest earth pressure (= 0.5);
• w = the granular or native soil bulk density in kN/m3;
o ( = 21.0 kN/m3 for well compacted, OPSS-approved Granular "B");
• h = the depth (in metres) below the exterior grade at which the earth pressure is being
calculated; and
• q = the equivalent value of any surcharge (in kN/m3) acting on the ground surface
adjacent to the walls.
(*) This value is recommended for rigid walls retaining compacted backfill.
Geotechnical Investigation Report Redstone Engineering
Retaining Wall Replacement – Municipal Parking Lot at 47 Mary Street
Picton, County of Prince Edward, Ontario Project No. 20R103
16
The recommended value for the coefficient for sliding friction between the subgrade (soil or
bedrock) and the concrete is 0.4. In addition to the above, hydrostatic forces must be taken
into account in the design where the walls extend below the groundwater table. Also, any
additional surcharge loading that will influence the wall must be taken into account in its
design.
Water accumulation in the backfill behind the retaining wall must be prevented by means of an
appropriate drainage system that may consist of a properly filtered perforated drainage pipe
installed at the base of the fill and appropriately gravity-drained to a frost-free outlet.
6.6 PAVEMENT REINSTATEMENT
It is expected that the removal of the existing wall and construction of new wall will also require
the removal and reconstruction of the adjoining pavement surface. The new (reconstructed)
pavement structure should, as a minimum, match the immediately adjacent remaining
pavement structure. Boreholes BH-1 to BH-3 encountered asphalt ranging from about 40 to
255mm in thickness, over pavement granulars whose thickness ranged from about 60mm to
negligible.
For design purposes, and based on the anticipated vehicles loadings and frequencies on this
pavement being typical of a municipal parking lot (i.e. passenger vehicles with very occasional
larger vehicles in the form of service trucks), the following pavement structure is
recommended:
Table 9: Pavement Structure
Profile Material Minimum Thickness (mm) Per OPSS
Asphalt Surface H.L. 3 or 4 40 1150
Asphalt Base H.L. 8 50
Granular Base Granular A 150 1010
Granular Subbase Granular B Type I 300
The following procedures should be implemented to reconstruct these portions of parking lot
pavement.
1. Remove existing materials as required for the new wall’s reconstruction (see Section 6.1 of
this report). Place granular backfill for wall as previously recommended. Remove any
remaining asphalt, earth fill, free organic topsoil, organics and organic-bearing materials,
loam, frozen earth, and/or boulders larger than 150 mm in diameter within the full area of
new pavement construction.
Geotechnical Investigation Report Redstone Engineering
Retaining Wall Replacement – Municipal Parking Lot at 47 Mary Street
Picton, County of Prince Edward, Ontario Project No. 20R103
17
2. Proof roll the subgrade for the purpose of detecting possible zones of overly wet or soft
subgrade. Any deleterious areas thus delineated should be replaced with granular material
(utilizing a suitable frost taper to the adjacent original granulars), compacted to a minimum
of 100 % of its Standard Proctor maximum dry density (SPMDD).
3. Contour the subgrade surface to prevent ponding of water during the construction and to
promote rapid drainage of the subbase and base course granular materials.
4. Fill material should be placed in uniform lifts not exceeding 200 mm in thickness before
compaction. It is suggested that all granular material used as fill should have an in-situ
moisture content within 2 % of their optimum moisture content. All granular materials
should be compacted to 100 % SPMDD. Granular materials should consist of Granular “A”
and “B” Type I conforming to the requirements of OPSS Form 1010 or equivalent.
5. To maximize drainage potential and ensure satisfactory pavement performance, granular
material should extend across the pavement construction area and should be deep enough
to allow granular material to drain.
6. Construct transitions between varying depths of granular base materials at a rate of 1H:10V
minimum.
7. All asphaltic concrete courses should be placed, spread and compacted conforming to OPSS
Form 310 or equivalent. All asphaltic concrete should be compacted to at least 92.0 % of
their respective laboratory maximum relative densities (MRD).
It should be noted that the recommended pavement structure is for the end use of the project.
During construction of the project the recommended granular depths may not be sufficient to
support loadings encountered.
6.7 GENERAL CONSTRUCTION-STAGE RECOMMENDATIONS
6.7.1 Subsoil Sensitivity
The native subgrade soils are susceptible to strength loss or deformation if saturated or
disturbed by construction traffic. Therefore, where the subgrade consists of approved soil, care
must be taken to protect the exposed subgrade from excess moisture and from construction
traffic. If there is site work carried out during periods of wet weather, then it can be expected
that the subgrade will be disturbed unless a suitable working surface is provided to protect the
integrity of the subgrade soils from construction traffic. Subgrade soil preparation work cannot
be adequately accomplished during overly wet weather, and the project must be scheduled
accordingly.
Geotechnical Investigation Report Redstone Engineering
Retaining Wall Replacement – Municipal Parking Lot at 47 Mary Street
Picton, County of Prince Edward, Ontario Project No. 20R103
18
6.7.2 Test Pit During Tendering
It is recommended that at least one test pit be excavated at a representative location of this
site (consider the eastern portion, off the existing parking lot area) during the construction
tendering phase, with mandatory attendance of interested contractors. This will allow them to
make their own assessments of the soil and any groundwater and bedrock conditions at the
site, and how these will affect their proposed construction methods, techniques and schedules.
6.7.3 Winter Construction
The subgrade soil encountered at this site can be frost-susceptible, and freezing conditions may
cause problems to the new wall structure. As preventive measures, the following
recommendations are presented:
1. During winter construction, exposed subgrade soil surfaces intended to support foundations
must be protected against freezing by means of loose straw and tarpaulins, heating, etc.
2. Because of the frost heave potential of the soils during winter, it is recommended that the
longitudinal excavation for the wall be excavated with shallow transition slopes in order to
minimize any abrupt changes in density and gradation between different soil types present
within the newly-backfilled wall areas and the adjacent unexcavated parking lot areas
(which generally contains mixed and variable earth fill beneath that will exhibit variable and
unpredictable frost susceptibilities as a result).
6.7.4 Design Review and Construction Inspections
Due to the preliminary nature of the design details at the time of this report, Redstone must be
allowed to review the foundation design and proposed grading plan prior to their finalization.
In addition, we strongly recommend that our firm be retained to review the related earthworks
specifications when they are available.
Geotechnical inspection and review of foundation excavations and compaction procedures
must be carried out by a qualified geotechnical engineer or representative to ensure
consistency with this investigation’s findings and compliance with Redstone’s
recommendations.
Geotechnical Investigation Report Redstone Engineering
Retaining Wall Replacement – Municipal Parking Lot at 47 Mary Street
Picton, County of Prince Edward, Ontario Project No. 20R103
19
7.0 CLOSURE AND STATEMENT OF LIMITATIONS
The recommendations made in this report are in accordance with our present understanding of
the project. The subsurface investigation was performed in accordance with current, generally
accepted guidelines. However, should any conditions at the site be encountered which differ
from those at the borehole locations, it is requested that Redstone be notified immediately in
order to permit a reassessment of our recommendations in light of the changed conditions and
exact project details. Redstone requests that they be permitted to review the
recommendations of this report after the drawings and specifications are complete, or if the
final project details should differ from that mentioned in this report.
The attached Statement of Limitations is an integral part of this report. Should questions arise
regarding any aspect of this report, please contact our office.
Sincerely yours,
Garnet Brenchley, P.Eng.
Principal Engineer
Redstone Engineering Inc.
Geotechnical Investigation Report Redstone Engineering
Retaining Wall Replacement – Municipal Parking Lot at 47 Mary Street
Picton, County of Prince Edward, Ontario Project No. 20R103
20
STATEMENT OF LIMITATIONS
This report is intended solely for the Corporation of the County of Prince Edward and other parties
explicitly identified in the report and is prohibited for use by others without Redstone’s prior written
consent. This report is considered Redstone’s professional work product and shall remain the sole
property of Redstone. Any unauthorized reuse, redistribution of or reliance on the report shall be at the
Client and recipient’s sole risk, without liability to Redstone. Client shall defend, indemnify and hold
Redstone harmless from any liability arising from or related to Client’s unauthorized distribution of the
report. No portion of this report may be used as a separate entity; it is to be read in its entirety and
shall include all supporting drawings and appendices.
The recommendations made in this report are in accordance with our present understanding of the
project, the current site use, ground surface elevations and conditions, and are based on the work scope
approved by the Client and described in the report. The services were performed in a manner
consistent with that level of care and skill ordinarily exercised by members of geotechnical engineering
professions currently practicing under similar conditions in the same locality. No other representations,
and no warranties or representations of any kind, either expressed or implied, are made. Any use which
a third party makes of this report, or any reliance on or decisions to be made based on it, are the
responsibility of such third parties.
All details of design and construction are rarely known at the time of completion of a geotechnical
study. The recommendations and comments made in the study report are based on our subsurface
investigation and resulting understanding of the project, as defined at the time of the study. We should
be retained to review our recommendations when the drawings and specifications are complete.
Without this review, Redstone will not be liable for any misunderstanding of our recommendations or
their application and adaptation into the final design.
By issuing this report, Redstone is the geotechnical engineer of record. It is recommended that
Redstone be retained during construction of any and all foundations, and during earthwork operations
to confirm the conditions of the subsoil are actually similar to those observed during our study. The
intent of this requirement is to verify that conditions encountered during construction are consistent
with the findings in the report and that inherent knowledge developed as part of our study is correctly
carried forward to the construction phases.
It is important to emphasize that a soil investigation is, in fact, a random sampling of a site and the
comments included in this report are based on the results obtained at the six (6) borehole and two (2)
handhole locations only. The subsurface conditions confirmed at these 8 locations may vary at other
locations. The subsurface conditions can also be significantly modified by construction activities on site
(ex. excavation, dewatering and drainage, blasting, pile driving, etc.). These conditions can also be
modified by exposure of soils or bedrock to humidity, dry periods or frost. Soil and groundwater
conditions between and beyond the test locations may differ both horizontally and vertically from those
encountered at the test locations and conditions may become apparent during construction which could
not be detected or anticipated at the time of our investigation. Should any conditions at the site be
encountered which differ from those found at the test locations, we request that we be notified
immediately in order to permit a reassessment of our recommendations. If changed conditions are
identified during construction, no matter how minor, the recommendations in this report shall be
considered invalid until sufficient review and written assessment of said conditions by Redstone is
completed.
Geotechnical Investigation Report Redstone Engineering
Retaining Wall Replacement - Municipal Parking Lot at 47 Mary Street
Picton, County of Prince Edward, Ontario Project No. 20R103
FIGURES
1086 Hayes Line Orientation Scale
Cavan, Ontario
705-768-9042
www.redstoneeng.ca
Figure #:By
Project #:Date
1
20R103TEST HOLE LOCATION PLAN
GEOTECHNICAL INVESTIGATION
MARY STREET RETAINING WALL - PICTON, ON
Drawing Title
see dimension
bar
17-Nov-20
GB
Source: portion of drawing by JewellEngineering entitled "Prince EdwardCounty, Mary Street, Retaining Wall -Control Points", dated Nov 20, 2020.
Geotechnical Investigation Report Redstone Engineering
Retaining Wall Replacement - Municipal Parking Lot at 47 Mary Street
Picton, County of Prince Edward, Ontario Project No. 20R103
APPENDIX A
BOREHOLE LOGS
BOREHOLE LOG EXPLANATION FORM
This explanatory section provides the background to assist in the use of the borehole logs. Each of the headings used on the borehole log, is briefly explained.
DEPTH
This column gives the depth of interpreted geologic contacts in metres below ground surface.
STRATIGRAPHIC DESCRIPTION
This column gives a description of the soil based on a tactile examination of the samples and/or laboratory test results. Each stratum is described according to the following classification and terminology.
Soil Classification* Terminology Proportion
'trace" (e.g. trace sand) some" (e.g. some sand) adjective (e.g. sandy) "and" (e.g. and sand)
noun (e.g. sand)
Silt & ClaySandGravelCobblesBoulders
<10% 10% - 20% 20% - 35% 35% - 50%
>50%
< 0.075 mm 0.075 to 4.75 mm 4.75 to 75 mm 75 to 300 mm
>300 mm
* Extension of USCS Classification system unless otherwise noted.
The use of the geologic term "till" implies that both disseminated coarser grained (sand, gravel, cobbles or boulders) particles and finer grained (silt and clay) particles may occur within the described matrix.
The compactness of cohesionless soils and the consistency of cohesive soils are defined by the following:
COHESIONLESS SOIL COHESIVE SOIL
Standard Penetration Resistance "N", Blows / 0.3 m
Standard Penetration Resistance "N", Blows / 0.3 m
ConsistencyCompactness
Very Soft0 to 4 4 to 10 10 to 30 30 to 50 Over 50
0 to 2 2 to 4 4 to 8
8 to 15 15 to 30 Over 30
Very Loose Loose Compact Dense Very Dense
SoftFirmStiff
Very StiffHard
The moisture conditions of cohesionless and cohesive soils are defined as follows.
COHESIONLESS SOILS COHESIVE SOILS
Drier Than Plastic Limit About Plastic Limit Wetter Than Plastic Limit Much Wetter Than Plastic Limit
Dry DTPLMoistWet
Saturated
APLWTPLMWTPL
Relative Density
STRATIGRAPHY
Symbols may be used to pictorially identify the interpreted stratigraphy of the soil and rock strata.
MONITOR DETAILS
This column shows the position and designation of standpipe and/or piezometer ground water monitors installed in the borehole. Also the water level may be shown for the date indicated.
I* ^Standpipe Geotextile Material / Liner Granular Backfillo±£L
Borehole Seal (Bentonite Grout)
A Piezometer Granular (Filter) Pack
gd Native Soil Backfill / Cave / Slough
Screened Interval Cement Seal
Borehole Seal (Peltomte, Bentonite or Hole Plug)ESEI
Where monitors are placed in separate boreholes, these are shown individually in the "Monitor Details" column. Otherwise, monitors are in the same borehole. For further data regarding seals, screens, etc., the reader is referred to the summary of monitor details table.
SAMPLE
These columns describe the sample type and number, the "N" value, the water content, the percentage recovery, and Rock Quality Designation (RQD), of each sample obtained from the borehole where applicable. The information is recorded at the approximate depth at which the sample was obtained. The legend for sample type is explained below.
Split SpoonThin Walled Shelby Tube Auger Flight Sample Continuous Core
Grab Sample Channel Sample Wash Sample Rock Core
SS GSST CSAS WSCC RC
Length of Core Recovered Per Run x 100 Total Length of Run
% Recovery
Where rock drilling was carried out, the term RQD (Rock Quality Designation) is used. The RQD is an indirect measure of the number of fractures and soundness of the rock mass. It is obtained from the rock cores by summing the length of core recovered, counting only those pieces of sound core that are 100 mm or more in length. The RQD value is expressed as a percentage and is the ratio of the summed core lengths to the total length of core run. The classification based on the RQD value is given below.
RQD Classification RQD (%)
Very poor quality Poor quality Fair quality
Good quality Excellent quality
< 2525 - 50 50 - 75 75 - 90
90 - 100
TEST DATA
The central section of the log provides graphs which are used to plot selected field and laboratory test results at the depth at which they were carried out. The plotting scales are shown at the head of the column.
Dynamic Penetration Resistance - The number of blows required to advance a 51 mm diameter, 60Q steel cone fitted to the end of 45 mm OD drill rods, 0.3 m into the subsoil. The cone is driven with a 63.5 kg hammer over a fall of 750 mm.
Standard Penetration Resistance - Standard Penetration Test (SPT) "N" Value - The number of blows required to advance a 51 mm diameter standard split-spoon sampler 300 mm into the subsoil, driven by means of a 63.5 kg hammer falling freely a distance of 750 mm. In cases where the split spoon does not penetrate 300 mm, the number of
xBlowsblows over the distance of actual penetration in millimetres is shown asmm
Water Content - The ratio of the mass of water to the mass of oven-dry solids in the soil expressed as a percentage.
Plastic Limit of a fine-grained soil expressed as a percentage as determined from the Atterberg Limit Test.
WP -
Liquid Limit of a fine-grained soil expressed as a percentage as determined from the Atterberg Limit Test.
WL-
REMARKS
The last column describes pertinent drilling details, field observations and/or provides an indication of other field or laboratory tests that were performed.
a) Cohesive Soils(*)
Undrained Shear Strength (kPa)
SPT "N" ValueConsistency
Very soft <12 0-2Soft 12-25
25-5050-100100-200>200
2-4FirmStiffVery stiff Hard
4-88-1515-30>30
(*) Hierarchy of Shear Strength prediction1. Lab triaxial test2. Field vane shear test3. Lab. vane shear test4. SPT "N" value5. Pocket penetrometer
Notes on Sample Descriptions
1. All sample descriptions included in this report generally follow the Unified Soil Classification. Laboratory grain size analyses provided by WSP also follow the same system. Different classification systems may be used by others, such as the system by the International Society for Soil Mechanics and Foundation Engineering (ISSMFE). Please note that, with the exception of those samples where a grain size analysis and/or Atterberg Limits testing have been made, all samples are classified visually. Visual classification is not sufficiently accurate to provide exact grain sizing or precise differentiation between size classification systems.
2. Fill: Where fill is designated on the borehole log it is defined as indicated by the sample recovered during the boring process. The reader is cautioned that fills are heterogeneous in nature and variable in density or degree of compaction. The borehole description may therefore not be applicable as a general description of site fill materials. All fills should be expected to contain obstruction such as wood, large concrete pieces or subsurface basements, floors, tanks, etc., none of these may have been encountered in the boreholes. Since boreholes cannot accurately define the contents of the fill, test pits are recommended to provide supplementary information. Despite the use of test pits, the heterogeneous nature of fill will leave some ambiguity as to the exact composition of the fill. Most fills contain pockets, seams, or layers of organically contaminated soil. This organic material can result in the generation of methane gas and/or significant ongoing and future settlements. Fill at this site may have been monitored for the presence of methane gas and, if so, the results are given on the borehole logs. The monitoring process does not indicate the volume of gas that can be potentially generated nor does it pinpoint the source of the gas. These readings are to advise of the presence of gas only, and a detailed study is recommended for sites where any explosive gas/methane is detected. Some fill material may be contaminated by toxic/hazardous waste that renders it unacceptable for deposition in any but designated land fill sites; unless specifically stated the fill on this site has not been tested for contaminants that may be considered toxic or hazardous. This testing and a potential hazard study can be undertaken if requested. In most residential/commercial areas undergoing reconstruction, buried oil tanks are common and are generally not detected in a conventional preliminary geotechnical site investigation.
3. Till: The term till on the borehole logs indicates that the material originates from a geological process associated with glaciation. Because of this geological process the till must be considered heterogeneous in composition and as such may contain pockets and/or seams of material such as sand, gravel, silt or clay. Till often contains cobbles (60 to 200 mm) or boulders (over 200 mm). Contractors may therefore encounter cobbles and boulders during excavation, even if they are not indicated by the borings. It should be appreciated that normal sampling equipment cannot differentiate the size or type of any obstruction. Because of the horizontal and vertical variability of till, the sample description may be applicable to a very limited zone; caution is therefore essential when dealing with sensitive excavations or dewatering programs in till materials.
Redstone
0.5
1
1.5
2
2.5
3
3.5
4
4.5
5
5.5
AU
AS-1
SS-2
SS-3
7
>100
80
50
5.3
17.3
18.9
Asphalt (40mm)Fill - dark brown Sand and Gravel withSilt, trace organics, dampMixed Fill - brown/grey/black mottledSand and Silt with Gravel and traceOrganics, occasional bricks, damp tomoist, loose
Weathered Bedrock (inferred fromgrinding and underlying refusal)Borehole terminated at refusal tofurther augering - presence of bedrockinferred
0.1
1.5
1.7Borehole remainedopen (no cave-in),and no groundwateraccumulationobserved
85
85.5
86
86.5
87
87.5
88
88.5
89
89.5
90
90.5
BOREHOLE NO. BH-1
PROJECT NUMBER 20R103PROJECT NAME Mary Street Retaining WallCLIENT County of Prince EdwardADDRESS 47 Mary Street, Picton, OntarioDRILLING DATE November 16, 2020LICENCE NO. 7085 (Well Contractor)
DRILLING COMPANY G.E.T. DrillingDRILLERDRILL RIG Truck-mountedDRILLING METHOD Auger, split spoon samplerTOTAL DEPTH 1.68mDIAMETER 5" (127mm)
COORDINATESCOORD SYSSURFACE ELEVATION 90.85mWELL TOC n/aLOGGED BY GBCHECKED BY GB
COMPLETION Nov 16, 2020 CASING nil SCREEN nil
COMMENTS
Dep
th (m
)
Dril
ling
Met
hod
Sam
ple
Inte
rval
and
Sam
ple
Type
SPT
(N) v
alue
Rec
over
y (%
)
Moi
stur
e C
ont (
%)
Gro
undw
ater Well
MonitorDetails
Stra
tigra
phy
Stratigraphic Description
Dep
th (m
) AdditionalObservations &
Remarks
Elev
atio
n (m
)
Disclaimer This log must be read in conjunction with the entirety of its parent report Page 1 of 1
produced by ESlog.ESdat.net on 01 Dec 2020
0.5
1
1.5
2
2.5
3
3.5
4
4.5
5
5.5
AU
AS-1
SS-2
SS-3
SS-4
4
5
>100
80
80
60
3.2
13.1
14.8
20.2
Asphalt (255mm)
Mixed Fill - brown/grey/black mottledSand and Silt with Gravel and traceOrganics, occasional bricks, damp tomoist, loose
Mixed Fill - brown/grey mottled SandyGravel with Silt, moist, loose
Weathered Bedrock (inferred fromgrinding and underlying refusal)Borehole terminated at refusal tofurther augering - presence of bedrockinferred
0.3
2.3
2.62.7
SS-4: Gr 52%, Sa35%, Sil & Cl 13%
Borehole remainedopen (no cave-in),and no groundwateraccumulationobserved
85
85.5
86
86.5
87
87.5
88
88.5
89
89.5
90
90.5
BOREHOLE NO. BH-2
PROJECT NUMBER 20R103PROJECT NAME Mary Street Retaining WallCLIENT County of Prince EdwardADDRESS 47 Mary Street, Picton, OntarioDRILLING DATE November 16, 2020LICENCE NO. 7085 (Well Contractor)
DRILLING COMPANY G.E.T. DrillingDRILLERDRILL RIG Truck-mountedDRILLING METHOD Auger, split spoon samplerTOTAL DEPTH 2.74mDIAMETER 5
COORDINATESCOORD SYSSURFACE ELEVATION 90.84mWELL TOC n/aLOGGED BY GBCHECKED BY GB
COMPLETION Nov 16, 2020 CASING nil SCREEN nil
COMMENTS
Dep
th (m
)
Dril
ling
Met
hod
Sam
ple
Inte
rval
and
Sam
ple
Type
SPT
(N) v
alue
Rec
over
y (%
)
Moi
stur
e C
ont (
%)
Gro
undw
ater Well
MonitorDetails
Stra
tigra
phy
Stratigraphic Description
Dep
th (m
) AdditionalObservations &
Remarks
Elev
atio
n (m
)
Disclaimer This log must be read in conjunction with the entirety of its parent report Page 1 of 1
produced by ESlog.ESdat.net on 01 Dec 2020
0.5
1
1.5
2
2.5
3
3.5
4
4.5
5
5.5
AU
SS-1
SS-2
SS-3a
SS-3b
SS-4
SS-5
SS-6
SS-7
SS-8
7
3
7
4
4
26
17
90
80
80
60
90
90
90
10.0
32.1
15.0
2.2
13.2
12.4
6.7
6.6
14.6
Asphalt (40mm)Fill - brown Sand and Gravel, dampMixed Fill - reddish brown Sand(fine-grained) with trace Silt, damp,compactMixed Fill - grey/black mottled Sandand Gravel with occasional cinders,damp to moist, looseMixed Fill - brown/grey mottled SiltySand with Gravel, occasional bricks,moist, loose
Silty Sand (fine-grained tomedium-grained), brown, damp, loose
Brown/dark brown layering exhibited,compact
Sand with Silt, medium-grained,brown, compact, damp
Borehole terminated
0.1
0.60.8
2.3
3.5
4.4
5.2
SS-7: Gr 0%, Sa76%, Si & Cl 24%
Borehole remainedopen (no cave-in),and no groundwateraccumulationobserved
85
85.5
86
86.5
87
87.5
88
88.5
89
89.5
90
90.5
BOREHOLE NO. BH-3
PROJECT NUMBER 20R103PROJECT NAME Mary Street Retaining WallCLIENT County of Prince EdwardADDRESS 47 Mary Street, Picton, OntarioDRILLING DATE November 16, 2020LICENCE NO. 7085 (Well Contractor)
DRILLING COMPANY G.E.T. DrillingDRILLERDRILL RIG Truck-mountedDRILLING METHOD Auger, split spoon samplerTOTAL DEPTH 5.18mDIAMETER 5" (127mm)
COORDINATESCOORD SYSSURFACE ELEVATION 90.53mWELL TOC n/aLOGGED BY GBCHECKED BY GB
COMPLETION Nov 16, 2020 CASING nil SCREEN nil
COMMENTS
Dep
th (m
)
Dril
ling
Met
hod
Sam
ple
Inte
rval
and
Sam
ple
Type
SPT
(N) v
alue
Rec
over
y (%
)
Moi
stur
e C
ont (
%)
Gro
undw
ater Well
MonitorDetails
Stra
tigra
phy
Stratigraphic Description
Dep
th (m
) AdditionalObservations &
Remarks
Elev
atio
n (m
)
Disclaimer This log must be read in conjunction with the entirety of its parent report Page 1 of 1
produced by ESlog.ESdat.net on 01 Dec 2020
0.5
1
1.5
2
2.5
3
3.5
4
4.5
5
5.5
AU
Overburden (including surficialasphalt)
Weathered bedrock (inferred)Borehole terminated at refusal tofurther augering - presence of bedrockinferred
2.72.9
Borehole remainedopen (no cave-in),and no groundwateraccumulationobserved
85
85.5
86
86.5
87
87.5
88
88.5
89
89.5
90
90.5
BOREHOLE NO. BH-4
PROJECT NUMBER 20R103PROJECT NAME Mary Street Retaining WallCLIENT County of Prince EdwardADDRESS 47 Mary Street, Picton, OntarioDRILLING DATE November 16, 2020LICENCE NO. 7085 (Well Contractor)
DRILLING COMPANY G.E.T. DrillingDRILLERDRILL RIG Truck-mountedDRILLING METHOD Auger, split spoon samplerTOTAL DEPTH 2.90mDIAMETER 5" (127mm)
COORDINATESCOORD SYSSURFACE ELEVATION 90.93mWELL TOC n/aLOGGED BY GBCHECKED BY GB
COMPLETION Nov 16, 2020 CASING nil SCREEN nil
COMMENTS Borehole drilled as a refusal (inferred Bedrock) depth probe, no sampling or definition of overburden stratigraphy
Dep
th (m
)
Dril
ling
Met
hod
Sam
ple
Inte
rval
and
Sam
ple
Type
SPT
(N) v
alue
Rec
over
y (%
)
Moi
stur
e C
ont (
%)
Gro
undw
ater Well
MonitorDetails
Stra
tigra
phy
Stratigraphic Description
Dep
th (m
) AdditionalObservations &
Remarks
Elev
atio
n (m
)
Disclaimer This log must be read in conjunction with the entirety of its parent report Page 1 of 1
produced by ESlog.ESdat.net on 01 Dec 2020
0.5
1
1.5
2
2.5
3
3.5
4
4.5
5
5.5
AU
Overburden (including surficialasphalt)
Weathered bedrock (inferred)
Borehole terminated at refusal tofurther augering - presence of bedrockinferred
0.8
1.1Borehole remainedopen (no cave-in),and no groundwateraccumulationobserved
85
85.5
86
86.5
87
87.5
88
88.5
89
89.5
90
90.5
BOREHOLE NO. BH-5
PROJECT NUMBER 20R103PROJECT NAME Mary Street Retaining WallCLIENT County of Prince EdwardADDRESS 47 Mary Street, Picton, OntarioDRILLING DATE November 16, 2020LICENCE NO. 7085 (Well Contractor)
DRILLING COMPANY G.E.T. DrillingDRILLERDRILL RIG Truck-mountedDRILLING METHOD Auger, split spoon samplerTOTAL DEPTH 1.07mDIAMETER 5" (127mm)
COORDINATESCOORD SYSSURFACE ELEVATION 90.99mWELL TOC n/aLOGGED BY GBCHECKED BY GB
COMPLETION Nov 16, 2020 CASING nil SCREEN nil
COMMENTS Borehole drilled as a refusal (inferred Bedrock) depth probe, no sampling or definition of overburden stratigraphy
Dep
th (m
)
Dril
ling
Met
hod
Sam
ple
Inte
rval
and
Sam
ple
Type
SPT
(N) v
alue
Rec
over
y (%
)
Moi
stur
e C
ont (
%)
Gro
undw
ater Well
MonitorDetails
Stra
tigra
phy
Stratigraphic Description
Dep
th (m
) AdditionalObservations &
Remarks
Elev
atio
n (m
)
Disclaimer This log must be read in conjunction with the entirety of its parent report Page 1 of 1
produced by ESlog.ESdat.net on 01 Dec 2020
0.5
1
1.5
2
2.5
3
3.5
4
4.5
5
5.5
AU
SS-1 >100 100 4.6
Overburden (including surficialasphalt)
Weathered bedrock (inferred)
Borehole terminated at refusal tofurther augering - presence of bedrockinferred
1.1
1.4Borehole remainedopen (no cave-in),and no groundwateraccumulationobserved
85
85.5
86
86.5
87
87.5
88
88.5
89
89.5
90
90.5
BOREHOLE NO. BH-6
PROJECT NUMBER 20R103PROJECT NAME Mary Street Retaining WallCLIENT County of Prince EdwardADDRESS 47 Mary Street, Picton, OntarioDRILLING DATE November 16, 2020LICENCE NO. 7085 (Well Contractor)
DRILLING COMPANY G.E.T. DrillingDRILLERDRILL RIG Truck-mountedDRILLING METHOD Auger, split spoon samplerTOTAL DEPTH 1.37mDIAMETER 5" (127mm)
COORDINATESCOORD SYSSURFACE ELEVATION 90.85mWELL TOC n/aLOGGED BY GBCHECKED BY GB
COMPLETION Nov 16, 2020 CASING nil SCREEN nil
COMMENTS Borehole drilled as a refusal (inferred Bedrock) depth probe, limited sampling and no definition of overburden stratigraphy
Dep
th (m
)
Dril
ling
Met
hod
Sam
ple
Inte
rval
and
Sam
ple
Type
SPT
(N) v
alue
Rec
over
y (%
)
Moi
stur
e C
ont (
%)
Gro
undw
ater Well
MonitorDetails
Stra
tigra
phy
Stratigraphic Description
Dep
th (m
) AdditionalObservations &
Remarks
Elev
atio
n (m
)
Disclaimer This log must be read in conjunction with the entirety of its parent report Page 1 of 1
produced by ESlog.ESdat.net on 01 Dec 2020
From To
0.00 0.10 90 to 100mm of Topsoil and Sod
0.10 0.33 Organic Fill - dark brown Silty Sand and Gravel with Organics and roots throughout, moist
Asphalt. Borehole terminated at refusal. No groundwater observed. See picture (below)
0.00 0.10 90 to 100mm of Topsoil and Sod
0.10 0.21 Organic Fill - dark brown Silty Sand and Gravel with Organics and roots throughout, moist
Asphalt. Borehole terminated at refusal. No groundwater observed. See picture (below)
Notes:
(1)
89.94HH-1
89.74HH-2
metres below existing grade
HANDHOLE LOGS
GEOTECHNICAL INVESTIGATION REPORT
MARY STREET RETAINING WALL RECONSTRUCTION - 47 MARY STREET, PICTON, ONTARIO
REDSTONE ENGINEERING PROJECT NO. 20R103
Handhole
No.
Depth (mbeg)(1)
Description
0.33
Elevation
(m)
0.21
Page 1 of 1
Geotechnical Investigation Report Redstone Engineering
Retaining Wall Replacement - Municipal Parking Lot at 47 Mary Street
Picton, County of Prince Edward, Ontario Project No. 20R103
APPENDIX B
PHYSICAL LABORATORY DATA
Project No.:
Location:
Sample No.: Depth:
Sampled By: Date:
COARSE
FINE COARSE
Sand Class.
35 GM
Doughty Aggregates Form LS-702NSRevision 3 - May 23, 2019
BH-2 SS-4 7.5 - 9.5'
Sample No.Moisture
Content
Sandy GRAVEL some silt 20.2
Silt & Clay
GRAIN SIZE DISTRIBUTION CHART
BH-2 SS-4
Client:
Project:
Garnet Brenchley - Redstone Engineering
20R103
November 17, 2020
Prince Edward County
Mary Street Retaining Wall Picton, Ontario
52
SILT
GravelDescription
CLAY & SILT (<0.075mm)FINE
7.5 - 9.5'
GRAVEL (>4.75mm)
COARSEMEDIUM
SAND (<4.75 to 0.075mm)
UNIFIED SOIL CLASSIFICATION SYSTEM
13
VERY FINE MEDIUM FINE
GRAVEL
U.S. BUREAU OF SOILS CLASSIFICATION
FINE
CLAYSAND
GRAVEL
Depth
0
10
20
30
40
50
60
70
80
90
1000
10
20
30
40
50
60
70
80
90
100
0.001 0.01 0.1 1 10 100
PE
RC
EN
T
R
ET
AIN
ED
PE
RC
EN
T
PA
SS
ING
DIAMETER (mm)
Project No.:
Location:
Sample No.: Depth:
Sampled By: Date:
COARSE
FINE COARSE
Sand Class.
76 SM
Doughty Aggregates Form LS-702NSRevision 3 - May 23, 2019
BH-3 SS-7 12.5 - 14.5'
Sample No.Moisture
Content
Silty SAND 14.6
Silt & Clay
GRAIN SIZE DISTRIBUTION CHART
BH-3 SS-7
Client:
Project:
Garnet Brenchley - Redstone Engineering
20R103
November 17, 2020
Prince Edward County
Mary Street Retaining Wall Picton, Ontario
0
SILT
GravelDescription
CLAY & SILT (<0.075mm)FINE
12.5 - 14.5'
GRAVEL (>4.75mm)
COARSEMEDIUM
SAND (<4.75 to 0.075mm)
UNIFIED SOIL CLASSIFICATION SYSTEM
24
VERY FINE MEDIUM FINE
GRAVEL
U.S. BUREAU OF SOILS CLASSIFICATION
FINE
CLAYSAND
GRAVEL
Depth
0
10
20
30
40
50
60
70
80
90
1000
10
20
30
40
50
60
70
80
90
100
0.001 0.01 0.1 1 10 100
PE
RC
EN
T
R
ET
AIN
ED
PE
RC
EN
T
PA
SS
ING
DIAMETER (mm)
Geotechnical Investigation Report Redstone Engineering
Retaining Wall Replacement - Municipal Parking Lot at 47 Mary Street
Picton, County of Prince Edward, Ontario Project No. 20R103
APPENDIX C
CHEMICAL LABORATORY DATA
www.paracellabs.com
1-800-749-1947
Ottawa, ON, K1G 4J8
300 - 2319 St. Laurent Blvd
Attn: Garnet Brenchley
Cavan, ON L0A1C0
1086 Hayes Line
Redstone Engineering
Certificate of Analysis
This Certificate of Analysis contains analytical data applicable to the following samples as submitted:
Paracel ID Client ID
Order #: 2047193
Order Date: 17-Nov-2020
Report Date: 23-Nov-2020
Client PO:
Custody: 55732
Project: 20R103
2047193-01 CS-1
2047193-02 BH-1 SS-2
2047193-03 BH-2 SS-2
2047193-04 BH-3 SS-4
Any use of these results implies your agreement that our total liabilty in connection with this work, however arising, shall be limited to the amount paid by you for
this work, and that our employees or agents shall not under any circumstances be liable to you in connection with this work.
Approved By:
Page 1 of 14
Lab Supervisor
Mark Foto, M.Sc.
Order #: 2047193
Project Description: 20R103
Certificate of Analysis
Client:
Report Date: 23-Nov-2020
Order Date: 17-Nov-2020
Client PO:
Redstone Engineering
Analysis Summary Table
Analysis Method Reference/Description Extraction Date Analysis Date
EPA 300.1 - IC, water extraction 20-Nov-20 20-Nov-20Anions
MOE (HWE), EPA 200.7 - ICP-OES 20-Nov-20 20-Nov-20Boron, available
MOE E3056 - Extraction, colourimetric 17-Nov-20 20-Nov-20Chromium, hexavalent - soil
MOE E3138 - probe @25 °C, water ext 21-Nov-20 21-Nov-20Conductivity
MOE E3015 - Auto Colour, water extraction 17-Nov-20 19-Nov-20Cyanide, free
EPA 7471B - CVAA, digestion 20-Nov-20 23-Nov-20Mercury by CVAA
SW846 8082A - GC-ECD 18-Nov-20 19-Nov-20PCBs, total
EPA 150.1 - pH probe @ 25 °C, CaCl buffered ext. 19-Nov-20 19-Nov-20pH, soil
CWS Tier 1 - P&T GC-FID 19-Nov-20 20-Nov-20PHC F1
CWS Tier 1 - GC-FID, extraction 17-Nov-20 20-Nov-20PHCs F2 to F4
EPA 6020 - Digestion - ICP-MS 20-Nov-20 20-Nov-20REG 153: Metals by ICP/MS, soil
EPA 8270 - GC-MS, extraction 17-Nov-20 20-Nov-20REG 153: PAHs by GC-MS
EPA 8260 - P&T GC-MS 19-Nov-20 20-Nov-20REG 153: VOCs by P&T GC/MS
EPA 120.1 - probe, water extraction 21-Nov-20 21-Nov-20Resistivity
Calculated 20-Nov-20 23-Nov-20SAR
Gravimetric, calculation 18-Nov-20 19-Nov-20Solids, %
Page 2 of 14
Order #: 2047193
Project Description: 20R103
Certificate of Analysis
Client:
Report Date: 23-Nov-2020
Order Date: 17-Nov-2020
Client PO:
Redstone Engineering
Client ID: CS-1 BH-1 SS-2 BH-2 SS-2 BH-3 SS-4
Sample Date: 16-Nov-20 12:0016-Nov-20 12:0016-Nov-20 12:0016-Nov-20 12:00
2047193-01 2047193-02 2047193-03 2047193-04Sample ID:
MDL/Units Soil Soil Soil Soil
Physical Characteristics
% Solids 88.687.883.693.20.1 % by Wt.
General Inorganics
SAR 3.377.450.98-0.01 N/A
Conductivity 424825238-5 uS/cm
Cyanide, free <0.03<0.03<0.03-0.03 ug/g dry
pH 7.597.837.637.780.05 pH Units
Resistivity ---33.90.10 Ohm.m
Anions
Chloride ---425 ug/g dry
Sulphate ---825 ug/g dry
Metals
Antimony <1.0<1.0<1.0-1.0 ug/g dry
Arsenic 1.72.45.9-1.0 ug/g dry
Barium 44.562.8185-1.0 ug/g dry
Beryllium <0.5<0.5<0.5-0.5 ug/g dry
Boron <5.06.511.2-5.0 ug/g dry
Boron, available <0.5<0.5<0.5-0.5 ug/g dry
Cadmium <0.5<0.50.6-0.5 ug/g dry
Chromium 12.117.321.0-5.0 ug/g dry
Chromium (VI) <0.2<0.2<0.2-0.2 ug/g dry
Cobalt 3.45.25.3-1.0 ug/g dry
Copper 7.818.534.7-5.0 ug/g dry
Lead 36.2100406-1.0 ug/g dry
Mercury 0.20.73.0-0.1 ug/g dry
Molybdenum <1.0<1.01.1-1.0 ug/g dry
Nickel 5.79.59.4-5.0 ug/g dry
Selenium <1.0<1.0<1.0-1.0 ug/g dry
Silver <0.3<0.30.3-0.3 ug/g dry
Thallium <1.0<1.0<1.0-1.0 ug/g dry
Uranium <1.0<1.0<1.0-1.0 ug/g dry
Vanadium 20.827.024.5-10.0 ug/g dry
Zinc 26.642.2196-20.0 ug/g dry
Volatiles
Acetone <0.50<0.50<0.50-0.50 ug/g dry
Benzene <0.02<0.02<0.02-0.02 ug/g dry
Page 3 of 14
Order #: 2047193
Project Description: 20R103
Certificate of Analysis
Client:
Report Date: 23-Nov-2020
Order Date: 17-Nov-2020
Client PO:
Redstone Engineering
Client ID: CS-1 BH-1 SS-2 BH-2 SS-2 BH-3 SS-4
Sample Date: 16-Nov-20 12:0016-Nov-20 12:0016-Nov-20 12:0016-Nov-20 12:00
2047193-01 2047193-02 2047193-03 2047193-04Sample ID:
MDL/Units Soil Soil Soil Soil
Bromodichloromethane <0.05<0.05<0.05-0.05 ug/g dry
Bromoform <0.05<0.05<0.05-0.05 ug/g dry
Bromomethane <0.05<0.05<0.05-0.05 ug/g dry
Carbon Tetrachloride <0.05<0.05<0.05-0.05 ug/g dry
Chlorobenzene <0.05<0.05<0.05-0.05 ug/g dry
Chloroform <0.05<0.05<0.05-0.05 ug/g dry
Dibromochloromethane <0.05<0.05<0.05-0.05 ug/g dry
Dichlorodifluoromethane <0.05<0.05<0.05-0.05 ug/g dry
1,2-Dichlorobenzene <0.05<0.05<0.05-0.05 ug/g dry
1,3-Dichlorobenzene <0.05<0.05<0.05-0.05 ug/g dry
1,4-Dichlorobenzene <0.05<0.05<0.05-0.05 ug/g dry
1,1-Dichloroethane <0.05<0.05<0.05-0.05 ug/g dry
1,2-Dichloroethane <0.05<0.05<0.05-0.05 ug/g dry
1,1-Dichloroethylene <0.05<0.05<0.05-0.05 ug/g dry
cis-1,2-Dichloroethylene <0.05<0.05<0.05-0.05 ug/g dry
trans-1,2-Dichloroethylene <0.05<0.05<0.05-0.05 ug/g dry
1,2-Dichloropropane <0.05<0.05<0.05-0.05 ug/g dry
cis-1,3-Dichloropropylene <0.05<0.05<0.05-0.05 ug/g dry
trans-1,3-Dichloropropylene <0.05<0.05<0.05-0.05 ug/g dry
1,3-Dichloropropene, total <0.05<0.05<0.05-0.05 ug/g dry
Ethylbenzene <0.05<0.05<0.05-0.05 ug/g dry
Ethylene dibromide (dibromoethane, 1,2-) <0.05<0.05<0.05-0.05 ug/g dry
Hexane <0.05<0.05<0.05-0.05 ug/g dry
Methyl Ethyl Ketone (2-Butanone) <0.50<0.50<0.50-0.50 ug/g dry
Methyl Isobutyl Ketone <0.50<0.50<0.50-0.50 ug/g dry
Methyl tert-butyl ether <0.05<0.05<0.05-0.05 ug/g dry
Methylene Chloride <0.05<0.05<0.05-0.05 ug/g dry
Styrene <0.05<0.05<0.05-0.05 ug/g dry
1,1,1,2-Tetrachloroethane <0.05<0.05<0.05-0.05 ug/g dry
1,1,2,2-Tetrachloroethane <0.05<0.05<0.05-0.05 ug/g dry
Tetrachloroethylene <0.05<0.05<0.05-0.05 ug/g dry
Toluene <0.05<0.05<0.05-0.05 ug/g dry
1,1,1-Trichloroethane <0.05<0.05<0.05-0.05 ug/g dry
1,1,2-Trichloroethane <0.05<0.05<0.05-0.05 ug/g dry
Trichloroethylene <0.05<0.05<0.05-0.05 ug/g dry
Page 4 of 14
Order #: 2047193
Project Description: 20R103
Certificate of Analysis
Client:
Report Date: 23-Nov-2020
Order Date: 17-Nov-2020
Client PO:
Redstone Engineering
Client ID: CS-1 BH-1 SS-2 BH-2 SS-2 BH-3 SS-4
Sample Date: 16-Nov-20 12:0016-Nov-20 12:0016-Nov-20 12:0016-Nov-20 12:00
2047193-01 2047193-02 2047193-03 2047193-04Sample ID:
MDL/Units Soil Soil Soil Soil
Trichlorofluoromethane <0.05<0.05<0.05-0.05 ug/g dry
Vinyl chloride <0.02<0.02<0.02-0.02 ug/g dry
m,p-Xylenes <0.05<0.05<0.05-0.05 ug/g dry
o-Xylene <0.05<0.050.07-0.05 ug/g dry
Xylenes, total <0.05<0.050.07-0.05 ug/g dry
4-Bromofluorobenzene Surrogate - 99.6% 101% 101%
Dibromofluoromethane Surrogate - 104% 105% 105%
Toluene-d8 Surrogate - 119% 119% 120%
Hydrocarbons
F1 PHCs (C6-C10) <7<7<7-7 ug/g dry
F2 PHCs (C10-C16) <4<4<4-4 ug/g dry
F3 PHCs (C16-C34) <8<8<8-8 ug/g dry
F4 PHCs (C34-C50) <6<6<6-6 ug/g dry
Semi-Volatiles
Acenaphthene <0.02<0.02<0.02-0.02 ug/g dry
Acenaphthylene <0.020.150.02-0.02 ug/g dry
Anthracene <0.020.110.04-0.02 ug/g dry
Benzo [a] anthracene <0.020.130.08-0.02 ug/g dry
Benzo [a] pyrene 0.030.280.10-0.02 ug/g dry
Benzo [b] fluoranthene 0.020.280.10-0.02 ug/g dry
Benzo [g,h,i] perylene 0.020.220.06-0.02 ug/g dry
Benzo [k] fluoranthene <0.020.150.05-0.02 ug/g dry
Chrysene <0.020.130.11-0.02 ug/g dry
Dibenzo [a,h] anthracene <0.020.05<0.02-0.02 ug/g dry
Fluoranthene 0.030.150.14-0.02 ug/g dry
Fluorene <0.02<0.02<0.02-0.02 ug/g dry
Indeno [1,2,3-cd] pyrene <0.020.180.05-0.02 ug/g dry
1-Methylnaphthalene <0.02<0.020.11-0.02 ug/g dry
2-Methylnaphthalene <0.02<0.020.16-0.02 ug/g dry
Methylnaphthalene (1&2) <0.04<0.040.28-0.04 ug/g dry
Naphthalene <0.01<0.010.12-0.01 ug/g dry
Phenanthrene <0.020.090.18-0.02 ug/g dry
Pyrene 0.030.180.13-0.02 ug/g dry
2-Fluorobiphenyl Surrogate - 84.4% 86.4% 76.5%
Terphenyl-d14 Surrogate - 77.5% 83.4% 73.0%
PCBs
PCBs, total <0.05<0.05<0.05-0.05 ug/g dry
Page 5 of 14
Order #: 2047193
Project Description: 20R103
Certificate of Analysis
Client:
Report Date: 23-Nov-2020
Order Date: 17-Nov-2020
Client PO:
Redstone Engineering
Client ID: CS-1 BH-1 SS-2 BH-2 SS-2 BH-3 SS-4
Sample Date: 16-Nov-20 12:0016-Nov-20 12:0016-Nov-20 12:0016-Nov-20 12:00
2047193-01 2047193-02 2047193-03 2047193-04Sample ID:
MDL/Units Soil Soil Soil Soil
Decachlorobiphenyl Surrogate - 91.3% 115% 107%
Page 6 of 14
Order #: 2047193
Project Description: 20R103
Certificate of Analysis
Client:
Report Date: 23-Nov-2020
Order Date: 17-Nov-2020
Client PO:
Redstone Engineering
Method Quality Control: Blank
Analyte ResultReporting
Limit UnitsSource
Result %REC
%REC
Limit RPDRPD
Limit Notes
Anions
Chloride ND 5 ug/g
Sulphate ND 5 ug/g
General Inorganics
Conductivity ND 5 uS/cm
Cyanide, free ND 0.03 ug/g
Resistivity ND 0.10 Ohm.m
Hydrocarbons
F1 PHCs (C6-C10) ND 7 ug/g
F2 PHCs (C10-C16) ND 4 ug/g
F3 PHCs (C16-C34) ND 8 ug/g
F4 PHCs (C34-C50) ND 6 ug/g
Metals
Antimony ND 1.0 ug/g
Arsenic ND 1.0 ug/g
Barium ND 1.0 ug/g
Beryllium ND 0.5 ug/g
Boron, available ND 0.5 ug/g
Boron ND 5.0 ug/g
Cadmium ND 0.5 ug/g
Chromium (VI) ND 0.2 ug/g
Chromium ND 5.0 ug/g
Cobalt ND 1.0 ug/g
Copper ND 5.0 ug/g
Lead ND 1.0 ug/g
Mercury ND 0.1 ug/g
Molybdenum ND 1.0 ug/g
Nickel ND 5.0 ug/g
Selenium ND 1.0 ug/g
Silver ND 0.3 ug/g
Thallium ND 1.0 ug/g
Uranium ND 1.0 ug/g
Vanadium ND 10.0 ug/g
Zinc ND 20.0 ug/g
PCBs
PCBs, total ND 0.05 ug/g
Surrogate: Decachlorobiphenyl 0.0869 86.9 60-140ug/g
Semi-Volatiles
Acenaphthene ND 0.02 ug/g
Acenaphthylene ND 0.02 ug/g
Anthracene ND 0.02 ug/g
Benzo [a] anthracene ND 0.02 ug/g
Benzo [a] pyrene ND 0.02 ug/g
Benzo [b] fluoranthene ND 0.02 ug/g
Benzo [g,h,i] perylene ND 0.02 ug/g
Benzo [k] fluoranthene ND 0.02 ug/g
Chrysene ND 0.02 ug/g
Dibenzo [a,h] anthracene ND 0.02 ug/g
Fluoranthene ND 0.02 ug/g
Fluorene ND 0.02 ug/g
Indeno [1,2,3-cd] pyrene ND 0.02 ug/g
1-Methylnaphthalene ND 0.02 ug/g
2-Methylnaphthalene ND 0.02 ug/g
Methylnaphthalene (1&2) ND 0.04 ug/g
Naphthalene ND 0.01 ug/g
Phenanthrene ND 0.02 ug/g
Pyrene ND 0.02 ug/g
Surrogate: 2-Fluorobiphenyl 1.18 88.6 50-140ug/g
Page 7 of 14
Order #: 2047193
Project Description: 20R103
Certificate of Analysis
Client:
Report Date: 23-Nov-2020
Order Date: 17-Nov-2020
Client PO:
Redstone Engineering
Method Quality Control: Blank
Analyte ResultReporting
Limit UnitsSource
Result %REC
%REC
Limit RPDRPD
Limit Notes
Surrogate: Terphenyl-d14 1.27 95.4 50-140ug/g
Volatiles
Acetone ND 0.50 ug/g
Benzene ND 0.02 ug/g
Bromodichloromethane ND 0.05 ug/g
Bromoform ND 0.05 ug/g
Bromomethane ND 0.05 ug/g
Carbon Tetrachloride ND 0.05 ug/g
Chlorobenzene ND 0.05 ug/g
Chloroform ND 0.05 ug/g
Dibromochloromethane ND 0.05 ug/g
Dichlorodifluoromethane ND 0.05 ug/g
1,2-Dichlorobenzene ND 0.05 ug/g
1,3-Dichlorobenzene ND 0.05 ug/g
1,4-Dichlorobenzene ND 0.05 ug/g
1,1-Dichloroethane ND 0.05 ug/g
1,2-Dichloroethane ND 0.05 ug/g
1,1-Dichloroethylene ND 0.05 ug/g
cis-1,2-Dichloroethylene ND 0.05 ug/g
trans-1,2-Dichloroethylene ND 0.05 ug/g
1,2-Dichloropropane ND 0.05 ug/g
cis-1,3-Dichloropropylene ND 0.05 ug/g
trans-1,3-Dichloropropylene ND 0.05 ug/g
1,3-Dichloropropene, total ND 0.05 ug/g
Ethylbenzene ND 0.05 ug/g
Ethylene dibromide (dibromoethane, 1,2-) ND 0.05 ug/g
Hexane ND 0.05 ug/g
Methyl Ethyl Ketone (2-Butanone) ND 0.50 ug/g
Methyl Isobutyl Ketone ND 0.50 ug/g
Methyl tert-butyl ether ND 0.05 ug/g
Methylene Chloride ND 0.05 ug/g
Styrene ND 0.05 ug/g
1,1,1,2-Tetrachloroethane ND 0.05 ug/g
1,1,2,2-Tetrachloroethane ND 0.05 ug/g
Tetrachloroethylene ND 0.05 ug/g
Toluene ND 0.05 ug/g
1,1,1-Trichloroethane ND 0.05 ug/g
1,1,2-Trichloroethane ND 0.05 ug/g
Trichloroethylene ND 0.05 ug/g
Trichlorofluoromethane ND 0.05 ug/g
Vinyl chloride ND 0.02 ug/g
m,p-Xylenes ND 0.05 ug/g
o-Xylene ND 0.05 ug/g
Xylenes, total ND 0.05 ug/g
Surrogate: 4-Bromofluorobenzene 8.64 108 50-140ug/g
Surrogate: Dibromofluoromethane 8.95 112 50-140ug/g
Surrogate: Toluene-d8 7.82 97.7 50-140ug/g
Page 8 of 14
Order #: 2047193
Project Description: 20R103
Certificate of Analysis
Client:
Report Date: 23-Nov-2020
Order Date: 17-Nov-2020
Client PO:
Redstone Engineering
Method Quality Control: Duplicate
Analyte Result
Reporting
Limit UnitsSource
Result %REC
%REC
Limit RPDRPD
Limit Notes
Anions
Chloride 46.0 5 ug/g dry 42.3 208.4
Sulphate 89.4 5 ug/g dry 82.5 208.1
General Inorganics
SAR 10.6 0.01 N/A 10.6 300.5
Cyanide, free ND 0.06 ug/g dry ND 35 GEN09NC
pH 7.15 0.05 pH Units 7.20 2.30.7
Resistivity 35.9 0.10 Ohm.m 33.9 205.7
Hydrocarbons
F1 PHCs (C6-C10) ND 7 ug/g dry ND 40NC
F2 PHCs (C10-C16) 9 4 ug/g dry 9 306.1
F3 PHCs (C16-C34) 73 8 ug/g dry 74 300.8
F4 PHCs (C34-C50) 137 6 ug/g dry 162 3016.7
Metals
Antimony ND 1.0 ug/g dry ND 30NC
Arsenic 4.1 1.0 ug/g dry 3.8 307.1
Barium 183 1.0 ug/g dry 179 301.8
Beryllium ND 0.5 ug/g dry ND 30NC
Boron, available ND 0.5 ug/g dry ND 35NC
Boron 9.4 5.0 ug/g dry 7.6 3021.3
Cadmium 0.6 0.5 ug/g dry 0.6 303.5
Chromium (VI) ND 0.2 ug/g dry ND 35NC
Chromium 18.7 5.0 ug/g dry 17.3 307.7
Cobalt 4.9 1.0 ug/g dry 4.7 304.7
Copper 28.6 5.0 ug/g dry 27.9 302.3
Lead 9.1 1.0 ug/g dry 8.4 307.7
Mercury 0.290 0.1 ug/g dry 0.236 3020.4
Molybdenum 1.8 1.0 ug/g dry 1.4 3023.5
Nickel 15.4 5.0 ug/g dry 14.4 306.8
Selenium 2.8 1.0 ug/g dry 2.5 308.1
Silver ND 0.3 ug/g dry ND 30NC
Thallium ND 1.0 ug/g dry ND 30NC
Uranium 3.4 1.0 ug/g dry 3.1 309.4
Vanadium 26.3 10.0 ug/g dry 24.7 306.4
Zinc 50.1 20.0 ug/g dry 47.5 305.2
PCBs
PCBs, total ND 0.05 ug/g dry ND 40NC
Surrogate: Decachlorobiphenyl 0.128 ug/g dry 107 60-140
Physical Characteristics
% Solids 73.6 0.1 % by Wt. 75.5 252.6
Semi-Volatiles
Acenaphthene 0.031 0.02 ug/g dry 0.021 4039.5
Acenaphthylene 0.125 0.02 ug/g dry 0.077 40 QR-0447.2
Anthracene 0.246 0.02 ug/g dry 0.115 40 QR-0472.8
Benzo [a] anthracene 0.794 0.02 ug/g dry 0.404 40 QR-0465.2
Benzo [a] pyrene 0.970 0.02 ug/g dry 0.486 40 QR-0466.4
Benzo [b] fluoranthene 1.12 0.02 ug/g dry 0.584 40 QR-0462.6
Benzo [g,h,i] perylene 0.611 0.02 ug/g dry 0.295 40 QR-0469.8
Benzo [k] fluoranthene 0.582 0.02 ug/g dry 0.337 40 QR-0453.3
Chrysene 0.756 0.02 ug/g dry 0.381 40 QR-0466.0
Dibenzo [a,h] anthracene 0.160 0.02 ug/g dry 0.079 40 QR-0467.6
Fluoranthene 1.08 0.02 ug/g dry 0.560 40 QR-0463.1
Fluorene 0.050 0.02 ug/g dry 0.035 4035.7
Indeno [1,2,3-cd] pyrene 0.551 0.02 ug/g dry 0.277 40 QR-0466.2
1-Methylnaphthalene ND 0.02 ug/g dry ND 40NC
2-Methylnaphthalene 0.027 0.02 ug/g dry ND 40NC
Page 9 of 14
Order #: 2047193
Project Description: 20R103
Certificate of Analysis
Client:
Report Date: 23-Nov-2020
Order Date: 17-Nov-2020
Client PO:
Redstone Engineering
Method Quality Control: Duplicate
Analyte Result
Reporting
Limit UnitsSource
Result %REC
%REC
Limit RPDRPD
Limit Notes
Naphthalene 0.285 0.01 ug/g dry 0.053 40 QR-04137.0
Phenanthrene 0.563 0.02 ug/g dry 0.243 40 QR-0479.5
Pyrene 0.996 0.02 ug/g dry 0.513 40 QR-0464.0
Surrogate: 2-Fluorobiphenyl 1.44 ug/g dry 81.4 50-140
Surrogate: Terphenyl-d14 1.22 ug/g dry 69.4 50-140
Volatiles
Acetone ND 0.50 ug/g dry ND 50NC
Benzene ND 0.02 ug/g dry ND 50NC
Bromodichloromethane ND 0.05 ug/g dry ND 50NC
Bromoform ND 0.05 ug/g dry ND 50NC
Bromomethane ND 0.05 ug/g dry ND 50NC
Carbon Tetrachloride ND 0.05 ug/g dry ND 50NC
Chlorobenzene ND 0.05 ug/g dry ND 50NC
Chloroform ND 0.05 ug/g dry ND 50NC
Dibromochloromethane ND 0.05 ug/g dry ND 50NC
Dichlorodifluoromethane ND 0.05 ug/g dry ND 50NC
1,2-Dichlorobenzene ND 0.05 ug/g dry ND 50NC
1,3-Dichlorobenzene ND 0.05 ug/g dry ND 50NC
1,4-Dichlorobenzene ND 0.05 ug/g dry ND 50NC
1,1-Dichloroethane ND 0.05 ug/g dry ND 50NC
1,2-Dichloroethane ND 0.05 ug/g dry ND 50NC
1,1-Dichloroethylene ND 0.05 ug/g dry ND 50NC
cis-1,2-Dichloroethylene ND 0.05 ug/g dry ND 50NC
trans-1,2-Dichloroethylene ND 0.05 ug/g dry ND 50NC
1,2-Dichloropropane ND 0.05 ug/g dry ND 50NC
cis-1,3-Dichloropropylene ND 0.05 ug/g dry ND 50NC
trans-1,3-Dichloropropylene ND 0.05 ug/g dry ND 50NC
Ethylbenzene ND 0.05 ug/g dry ND 50NC
Ethylene dibromide (dibromoethane, 1,2-) ND 0.05 ug/g dry ND 50NC
Hexane ND 0.05 ug/g dry ND 50NC
Methyl Ethyl Ketone (2-Butanone) ND 0.50 ug/g dry ND 50NC
Methyl Isobutyl Ketone ND 0.50 ug/g dry ND 50NC
Methyl tert-butyl ether ND 0.05 ug/g dry ND 50NC
Methylene Chloride ND 0.05 ug/g dry ND 50NC
Styrene ND 0.05 ug/g dry ND 50NC
1,1,1,2-Tetrachloroethane ND 0.05 ug/g dry ND 50NC
1,1,2,2-Tetrachloroethane ND 0.05 ug/g dry ND 50NC
Tetrachloroethylene ND 0.05 ug/g dry ND 50NC
Toluene ND 0.05 ug/g dry ND 50NC
1,1,1-Trichloroethane ND 0.05 ug/g dry ND 50NC
1,1,2-Trichloroethane ND 0.05 ug/g dry ND 50NC
Trichloroethylene ND 0.05 ug/g dry ND 50NC
Trichlorofluoromethane ND 0.05 ug/g dry ND 50NC
Vinyl chloride ND 0.02 ug/g dry ND 50NC
m,p-Xylenes ND 0.05 ug/g dry ND 50NC
o-Xylene ND 0.05 ug/g dry ND 50NC
Surrogate: 4-Bromofluorobenzene 9.47 ug/g dry 101 50-140
Surrogate: Dibromofluoromethane 10.3 ug/g dry 110 50-140
Surrogate: Toluene-d8 11.3 ug/g dry 122 50-140
Page 10 of 14
Order #: 2047193
Project Description: 20R103
Certificate of Analysis
Client:
Report Date: 23-Nov-2020
Order Date: 17-Nov-2020
Client PO:
Redstone Engineering
Method Quality Control: Spike
Analyte ResultReporting
Limit UnitsSource
Result%REC
%REC
LimitRPD
RPD
Limit Notes
Anions
Chloride 136 42.3 93.4 82-118ug/g 5
Sulphate 180 82.5 97.6 80-120ug/g 5
General Inorganics
Cyanide, free 0.243 ND 80.8 70-130ug/g0.03
Hydrocarbons
F1 PHCs (C6-C10) 205 ND 102 80-120ug/g7
F2 PHCs (C10-C16) 90 9 95.7 60-140ug/g4
F3 PHCs (C16-C34) 277 74 97.9 60-140ug/g8
F4 PHCs (C34-C50) 301 162 107 60-140ug/g6
Metals
Antimony 50.3 ND 100 70-130ug/g 1.0
Arsenic 51.6 1.5 100 70-130ug/g 1.0
Barium 128 71.8 112 70-130ug/g 1.0
Beryllium 54.4 ND 109 70-130ug/g 0.5
Boron, available 4.12 ND 82.4 70-122ug/g 0.5
Boron 52.6 ND 99.2 70-130ug/g 5.0
Cadmium 49.0 ND 97.5 70-130ug/g 0.5
Chromium (VI) 0.1 ND 54.5 70-130 QM-05ug/g0.2
Chromium 60.6 6.9 107 70-130ug/g 5.0
Cobalt 53.7 1.9 104 70-130ug/g 1.0
Copper 60.4 11.2 98.5 70-130ug/g 5.0
Lead 50.1 3.4 93.5 70-130ug/g 1.0
Mercury 2.04 0.236 120 70-130ug/g 0.1
Molybdenum 51.0 ND 101 70-130ug/g 1.0
Nickel 56.3 5.7 101 70-130ug/g 5.0
Selenium 47.5 1.0 92.9 70-130ug/g 1.0
Silver 41.2 ND 82.4 70-130ug/g 0.3
Thallium 47.9 ND 95.8 70-130ug/g 1.0
Uranium 49.9 1.3 97.2 70-130ug/g 1.0
Vanadium 64.3 ND 109 70-130ug/g 10.0
Zinc 67.8 ND 97.6 70-130ug/g 20.0
PCBs
PCBs, total 0.425 ND 88.8 60-140ug/g0.05
Surrogate: Decachlorobiphenyl 0.116 97.3 60-140ug/g
Semi-Volatiles
Acenaphthene 0.143 0.021 55.3 50-140ug/g0.02
Acenaphthylene 0.201 0.077 56.3 50-140ug/g0.02
Anthracene 0.263 0.115 67.4 50-140ug/g0.02
Benzo [a] anthracene 0.530 0.404 57.0 50-140ug/g0.02
Benzo [a] pyrene 0.617 0.486 59.1 50-140ug/g0.02
Benzo [b] fluoranthene 0.745 0.584 72.9 50-140ug/g0.02
Benzo [g,h,i] perylene 0.429 0.295 61.0 50-140ug/g0.02
Benzo [k] fluoranthene 0.474 0.337 62.0 50-140ug/g0.02
Chrysene 0.518 0.381 62.4 50-140ug/g0.02
Dibenzo [a,h] anthracene 0.211 0.079 59.6 50-140ug/g0.02
Fluoranthene 0.112 ND 67.5 50-140ug/g0.02
Fluorene 0.160 0.035 56.6 50-140ug/g0.02
Page 11 of 14
Order #: 2047193
Project Description: 20R103
Certificate of Analysis
Client:
Report Date: 23-Nov-2020
Order Date: 17-Nov-2020
Client PO:
Redstone Engineering
Method Quality Control: Spike
Analyte ResultReporting
Limit UnitsSource
Result%REC
%REC
LimitRPD
RPD
Limit Notes
Indeno [1,2,3-cd] pyrene 0.399 0.277 55.4 50-140ug/g0.02
1-Methylnaphthalene 0.167 ND 75.5 50-140ug/g0.02
2-Methylnaphthalene 0.188 ND 85.3 50-140ug/g0.02
Naphthalene 0.253 0.053 90.6 50-140ug/g0.01
Phenanthrene 0.127 ND 76.4 50-140ug/g0.02
Pyrene 0.645 0.513 59.7 50-140ug/g0.02
Surrogate: 2-Fluorobiphenyl 1.24 70.4 50-140ug/g
Surrogate: Terphenyl-d14 1.13 63.9 50-140ug/g
Volatiles
Acetone 8.85 ND 88.5 50-140ug/g0.50
Benzene 2.85 ND 71.3 60-130ug/g0.02
Bromodichloromethane 2.78 ND 69.4 60-130ug/g0.05
Bromoform 4.92 ND 123 60-130ug/g0.05
Bromomethane 5.36 ND 134 50-140ug/g0.05
Carbon Tetrachloride 4.52 ND 113 60-130ug/g0.05
Chlorobenzene 3.68 ND 92.0 60-130ug/g0.05
Chloroform 3.67 ND 91.8 60-130ug/g0.05
Dibromochloromethane 4.58 ND 115 60-130ug/g0.05
Dichlorodifluoromethane 5.09 ND 127 50-140ug/g0.05
1,2-Dichlorobenzene 3.35 ND 83.6 60-130ug/g0.05
1,3-Dichlorobenzene 3.39 ND 84.9 60-130ug/g0.05
1,4-Dichlorobenzene 3.52 ND 87.9 60-130ug/g0.05
1,1-Dichloroethane 3.20 ND 80.0 60-130ug/g0.05
1,2-Dichloroethane 4.18 ND 104 60-130ug/g0.05
1,1-Dichloroethylene 3.00 ND 75.0 60-130ug/g0.05
cis-1,2-Dichloroethylene 2.96 ND 74.0 60-130ug/g0.05
trans-1,2-Dichloroethylene 3.08 ND 77.0 60-130ug/g0.05
1,2-Dichloropropane 2.84 ND 71.1 60-130ug/g0.05
cis-1,3-Dichloropropylene 3.74 ND 93.6 60-130ug/g0.05
trans-1,3-Dichloropropylene 4.19 ND 105 60-130ug/g0.05
Ethylbenzene 3.52 ND 87.9 60-130ug/g0.05
Ethylene dibromide (dibromoethane, 1,2-) 3.52 ND 88.0 60-130ug/g0.05
Hexane 3.71 ND 92.8 60-130ug/g0.05
Methyl Ethyl Ketone (2-Butanone) 8.91 ND 89.1 50-140ug/g0.50
Methyl Isobutyl Ketone 7.31 ND 73.1 50-140ug/g0.50
Methyl tert-butyl ether 6.91 ND 69.1 50-140ug/g0.05
Methylene Chloride 3.14 ND 78.4 60-130ug/g0.05
Styrene 3.66 ND 91.6 60-130ug/g0.05
1,1,1,2-Tetrachloroethane 4.61 ND 115 60-130ug/g0.05
1,1,2,2-Tetrachloroethane 3.56 ND 89.1 60-130ug/g0.05
Tetrachloroethylene 3.86 ND 96.5 60-130ug/g0.05
Toluene 3.54 ND 88.4 60-130ug/g0.05
1,1,1-Trichloroethane 4.14 ND 103 60-130ug/g0.05
1,1,2-Trichloroethane 2.89 ND 72.2 60-130ug/g0.05
Trichloroethylene 3.47 ND 86.8 60-130ug/g0.05
Trichlorofluoromethane 4.88 ND 122 50-140ug/g0.05
Vinyl chloride 5.52 ND 138 50-140ug/g0.02
m,p-Xylenes 7.29 ND 91.1 60-130ug/g0.05
o-Xylene 3.89 ND 97.2 60-130ug/g0.05
Surrogate: 4-Bromofluorobenzene 7.53 94.1 50-140ug/g
Page 12 of 14
Order #: 2047193
Project Description: 20R103
Certificate of Analysis
Client:
Report Date: 23-Nov-2020
Order Date: 17-Nov-2020
Client PO:
Redstone Engineering
Method Quality Control: Spike
Analyte ResultReporting
Limit UnitsSource
Result%REC
%REC
LimitRPD
RPD
Limit Notes
Surrogate: Dibromofluoromethane 8.63 108 50-140ug/g
Surrogate: Toluene-d8 7.15 89.4 50-140ug/g
Page 13 of 14
Order #: 2047193
Project Description: 20R103
Certificate of Analysis
Client:
Report Date: 23-Nov-2020
Order Date: 17-Nov-2020
Client PO:
Redstone Engineering
Qualifer Notes:
Login Qualifers :
Sample - One or more parameter received past hold time - Redox Potential
Applies to samples: CS-1
QC Qualifers :
Elevated detection limits due to the nature of the sample matrix.GEN09 :
The spike recovery was outside acceptance limits for the matrix spike due to matrix interference.QM-05 :
Duplicate results exceeds RPD limits due to non-homogeneous matrix.QR-04 :
Sample Data Revisions
None
Work Order Revisions / Comments:
None
Other Report Notes:
MDL: Method Detection Limit
n/a: not applicable
Source Result: Data used as source for matrix and duplicate samples
%REC: Percent recovery.
RPD: Relative percent difference.
ND: Not Detected
NC: Not Calculated
Soil results are reported on a dry weight basis when the units are denoted with 'dry'.
Where %Solids is reported, moisture loss includes the loss of volatile hydrocarbons.
CCME PHC additional information:
- The method for the analysis of PHCs complies with the Reference Method for the CWS PHC and is validated for use in the
laboratory. All prescribed quality criteria identified in the method has been met.
- F1 range corrected for BTEX.- F2 to F3 ranges corrected for appropriate PAHs where available.
- In the case where F4 and F4G are both reported, the greater of the two results is to be used for comparison to CWS PHC criteria.
- The gravimetric heavy hydrocarbons (F4G) are not to be added to C6 to C50 hydrocarbons.
- When reported, data for F4G has been processed using a silica gel cleanup.
Page 14 of 14
Subcontracted Analysis
1086 Hayes Line
Cavan, ON L0A1C0
Attn: Garnet Brenchley
Tel: (705) 768-9042
Fax: -0
Paracel Report No 2047193
Client Project(s): 20R103
Client PO:
CoC Number: 55732
Reference: #20-920 Redstone - 20R103
Order Date: 17-Nov-20
Report Date: 23-Nov-20
Sample(s) from this project were subcontracted for the listed parameters. A copy of the subcontractor’s report is attached
Paracel ID Client ID
Redstone Engineering
www.paracellabs.com
1-800-749-1947
Kingston, ON, K7P 2R9
637 Norris Court, Unit 1
Analysis
2047193-01 CS-1 Redox potential, soil
Sulphide, solid
Client: Dale Robertson Work Order Number: 417427Company: Paracel Laboratories Ltd.- Ottawa PO #:Address: 300-2319 St. Laurent Blvd. Regulation: O.Reg 153 Table 1 Soil Stringent Criteria
Ottawa, ON, K1G 4J8 Project #: 2047193Phone/Fax: (613) 731-9577 / (613) 731-9064 DWS #:Email: [email protected] Sampled By:
Date Order Received: 11/18/2020 Analysis Started: 11/25/2020Arrival Temperature: 10 °C Analysis Completed: 11/25/2020
Sample Description Lab ID Matrix Type Comments Date Collected Time Collected
CS-1 1599832 Soil None 11/16/2020 12:00 PM
WORK ORDER SUMMARY
ANALYSES WERE PERFORMED ON THE FOLLOWING SAMPLES. THE RESULTS RELATE ONLY TO THE ITEMS TESTED.
Method Lab Description Reference
RedOx - Soil (T06) Mississauga Determination of RedOx Potential of Soil Modified from APHA-2580B
METHODS AND INSTRUMENTATION
THE FOLLOWING METHODS WERE USED FOR YOUR SAMPLE(S):
This report has been approved by:
Brad Halvorson, B.Sc.
Laboratory Director
Date of Issue: 11/26/2020 16:28 7 Margaret Street, Garson, ON, P3L 1E1Phone: (705) 693-1121 Fax: (705) 693-1124 Web: www.testmark.ca
Page 1 of 2
CERTIFICATE OF ANALYSIS
WORK ORDER RESULTS
Sample Description CS - 1
Sample Date 11/16/2020 12:00 PM
Lab ID 1599832
General Chemistry Result MDL UnitsCriteria: O.Reg
153 Table 1 Soil Stringent Criteria
RedOx (vs. S.H.E.) 353 N/A mV ~
LEGENDDates: Dates are formatted as mm/dd/year throughout this report.
[rr]: After a parameter name indicates a re-run of that parameter. If multiple re-runs exist they are suffixed by a number. Sample may not have been handled according to the recommended temperature, hold time and head space requirements of the method after the initial analysis.
MDL: Method detection limit or minimum reporting limit.
~: In a criteria column indicates the criteria is not applicable for the parameter row.
Quality Control: All associated Quality Control data is available on request.
Field Data: Reports containing Field Parameters represent data that has been collected and provided by the client. Testmark is not responsible for the validity of this data which may be used in subsequent calculations.
Sample Condition Deviations: A noted sample condition deviation may affect the validity of the result. Results apply to the sample(s) as received.
Date of Issue: 11/26/2020 16:28 7 Margaret Street, Garson, ON, P3L 1E1Phone: (705) 693-1121 Fax: (705) 693-1124 Web: www.testmark.ca
Page 2 of 2
CERTIFICATE OF ANALYSIS
Paracel Laboratories Ltd.- Ottawa Work Order Number: 417427
Paracel Laboratories Attn : Dale Robertson
300-2319 St.Laurent Blvd.Ottawa, ONK1G 4K6, Canada
Phone: 613-731-9577Fax:613-731-9064
02-December-2020
Date Rec. : 18 November 2020 LR Report: CA13594-NOV20 Reference: Project#: 2047193
Copy: #1
CERTIFICATE OF ANALYSIS
Final Report Sample ID Sample Date &
TimeSulphide(Na2CO3)
%
1: Analysis Start Date 02-Dec-202: Analysis Start Time 14:473: Analysis Completed Date 02-Dec-204: Analysis Completed Time 15:005: QC - Blank < 0.046: QC - STD % Recovery 119%7: QC - DUP % RPD ND8: RL 0.029: CS-1 16-Nov-20 16:00 0.09
RL - SGS Reporting LimitND - Not Detected
__________________________
Kimberley DidsburyProject Specialist,Environment, Health & Safety
SGS Canada Inc. P.O. Box 4300 - 185 Concession St. Lakefield - Ontario - KOL 2HO Phone: 705-652-2000 FAX: 705-652-6365
OnL
ine
LIM
S 0002338194
Page 1 of 1 Data reported represents the sample submitted to SGS. Reproduction of this analytical report in full or in part is prohibited without prior written approval. Please refer to SGS
General Conditions of Services located at https://www.sgs.ca/en/terms-and-conditions (Printed copies are available upon request.) Test method information available upon request. “Temperature Upon Receipt” is representative of the whole shipment and may not reflect the temperature of individual samples. SGS Canada Inc. Environment-Health & Safety statement of conformity decision rule does not consider uncertainty when analytical results are compared to a specified standard or
regulation.
www.paracellabs.com
1-800-749-1947
Ottawa, ON, K1G 4J8
300 - 2319 St. Laurent Blvd
Attn: Garnet Brenchley
Cavan, ON L0A1C0
1086 Hayes Line
Redstone Engineering
Certificate of Analysis
This Certificate of Analysis contains analytical data applicable to the following samples as submitted:
Paracel ID Client ID
Order #: 2048187
Order Date: 24-Nov-2020
Report Date: 30-Nov-2020
Client PO:
Custody: 55732
Project: 20R103
2048187-01 CS-2
Any use of these results implies your agreement that our total liabilty in connection with this work, however arising, shall be limited to the amount paid by you for
this work, and that our employees or agents shall not under any circumstances be liable to you in connection with this work.
Approved By:
Page 1 of 8
Lab Supervisor
Mark Foto, M.Sc.
Order #: 2048187
Project Description: 20R103
Certificate of Analysis
Client:
Report Date: 30-Nov-2020
Order Date: 24-Nov-2020
Client PO:
Redstone Engineering
Analysis Summary Table
Analysis Method Reference/Description Extraction Date Analysis Date
TCLP EPA 6020 - Digestion - ICP-MS 27-Nov-20 27-Nov-20Metals, ICP-MS
MOE E3015- Auto Colour 27-Nov-20 27-Nov-20REG 558 - Cyanide
EPA 340.2 - ISE 27-Nov-20 27-Nov-20REG 558 - Fluoride
EPA 7470A - Cold Vapour AA 27-Nov-20 27-Nov-20REG 558 - Mercury by CVAA
EPA 300.1 - IC 27-Nov-20 27-Nov-20REG 558 - NO3/NO2
EPA 608 - GC-ECD 27-Nov-20 27-Nov-20REG 558 - PCBs
EPA 624 - P&T GC-MS 26-Nov-20 26-Nov-20REG 558 - VOCs
Gravimetric, calculation 27-Nov-20 30-Nov-20Solids, %
Page 2 of 8
Order #: 2048187
Project Description: 20R103
Certificate of Analysis
Client:
Report Date: 30-Nov-2020
Order Date: 24-Nov-2020
Client PO:
Redstone Engineering
Client ID: CS-2 - - -
Sample Date: ---16-Nov-20 12:00
2048187-01 - - -Sample ID:
MDL/Units Soil - - -
Physical Characteristics
% Solids ---84.40.1 % by Wt.
EPA 1311 - TCLP Leachate Inorganics
Fluoride ---0.240.05 mg/L
Nitrate as N ---<11 mg/L
Nitrite as N ---<11 mg/L
Cyanide, free ---<0.020.02 mg/L
EPA 1311 - TCLP Leachate Metals
Arsenic ---<0.050.05 mg/L
Barium ---0.660.05 mg/L
Boron ---<0.050.05 mg/L
Cadmium ---<0.010.01 mg/L
Chromium ---<0.050.05 mg/L
Lead ---<0.050.05 mg/L
Mercury ---<0.0050.005 mg/L
Selenium ---<0.050.05 mg/L
Silver ---<0.050.05 mg/L
Uranium ---<0.050.05 mg/L
EPA 1311 - TCLP Leachate Volatiles
Benzene ---<0.0050.005 mg/L
Carbon Tetrachloride ---<0.0050.005 mg/L
Chlorobenzene ---<0.0040.004 mg/L
Chloroform ---<0.0060.006 mg/L
1,2-Dichlorobenzene ---<0.0040.004 mg/L
1,4-Dichlorobenzene ---<0.0040.004 mg/L
1,2-Dichloroethane ---<0.0050.005 mg/L
1,1-Dichloroethylene ---<0.0060.006 mg/L
Methyl Ethyl Ketone (2-Butanone) ---<0.300.30 mg/L
Methylene Chloride ---<0.040.04 mg/L
Tetrachloroethylene ---<0.0050.005 mg/L
Trichloroethylene ---<0.0040.004 mg/L
Vinyl chloride ---<0.0050.005 mg/L
4-Bromofluorobenzene Surrogate 112% - - -
Dibromofluoromethane Surrogate 103% - - -
Toluene-d8 Surrogate 108% - - -
EPA 1311 - TCLP Leachate Organics
PCBs, total ---<0.0030.003 mg/L
Page 3 of 8
Order #: 2048187
Project Description: 20R103
Certificate of Analysis
Client:
Report Date: 30-Nov-2020
Order Date: 24-Nov-2020
Client PO:
Redstone Engineering
Client ID: CS-2 - - -
Sample Date: ---16-Nov-20 12:00
2048187-01 - - -Sample ID:
MDL/Units Soil - - -
Decachlorobiphenyl Surrogate 104% - - -
Page 4 of 8
Order #: 2048187
Project Description: 20R103
Certificate of Analysis
Client:
Report Date: 30-Nov-2020
Order Date: 24-Nov-2020
Client PO:
Redstone Engineering
Method Quality Control: Blank
Analyte ResultReporting
Limit UnitsSource
Result %REC
%REC
Limit RPDRPD
Limit Notes
EPA 1311 - TCLP Leachate Inorganics
Fluoride ND 0.05 mg/L
Nitrate as N ND 1 mg/L
Nitrite as N ND 1 mg/L
Cyanide, free ND 0.02 mg/L
EPA 1311 - TCLP Leachate Metals
Arsenic ND 0.05 mg/L
Barium ND 0.05 mg/L
Boron ND 0.05 mg/L
Cadmium ND 0.01 mg/L
Chromium ND 0.05 mg/L
Lead ND 0.05 mg/L
Mercury ND 0.005 mg/L
Selenium ND 0.05 mg/L
Silver ND 0.05 mg/L
Uranium ND 0.05 mg/L
EPA 1311 - TCLP Leachate Organics
PCBs, total ND 0.003 mg/L
Surrogate: Decachlorobiphenyl 0.0096 95.7 62-138mg/L
EPA 1311 - TCLP Leachate Volatiles
Benzene ND 0.005 mg/L
Carbon Tetrachloride ND 0.005 mg/L
Chlorobenzene ND 0.004 mg/L
Chloroform ND 0.006 mg/L
1,2-Dichlorobenzene ND 0.004 mg/L
1,4-Dichlorobenzene ND 0.004 mg/L
1,2-Dichloroethane ND 0.005 mg/L
1,1-Dichloroethylene ND 0.006 mg/L
Methyl Ethyl Ketone (2-Butanone) ND 0.30 mg/L
Methylene Chloride ND 0.04 mg/L
Tetrachloroethylene ND 0.005 mg/L
Trichloroethylene ND 0.004 mg/L
Vinyl chloride ND 0.005 mg/L
Surrogate: 4-Bromofluorobenzene 0.803 117 83-134mg/L
Surrogate: Dibromofluoromethane 0.700 102 78-124mg/L
Surrogate: Toluene-d8 0.710 103 76-118mg/L
Page 5 of 8
Order #: 2048187
Project Description: 20R103
Certificate of Analysis
Client:
Report Date: 30-Nov-2020
Order Date: 24-Nov-2020
Client PO:
Redstone Engineering
Method Quality Control: Duplicate
Analyte Result
Reporting
Limit UnitsSource
Result %REC
%REC
Limit RPDRPD
Limit Notes
EPA 1311 - TCLP Leachate Inorganics
Fluoride 0.24 0.05 mg/L 0.24 200.3
Nitrate as N ND 1 mg/L ND 20NC
Nitrite as N ND 1 mg/L ND 20NC
Cyanide, free ND 0.02 mg/L ND 20NC
EPA 1311 - TCLP Leachate Metals
Arsenic ND 0.05 mg/L ND 29NC
Barium 0.221 0.05 mg/L 0.202 349.2
Boron ND 0.05 mg/L ND 33NC
Cadmium ND 0.01 mg/L ND 33NC
Chromium 0.064 0.05 mg/L 0.060 326.8
Lead 0.129 0.05 mg/L 0.122 325.6
Mercury ND 0.005 mg/L ND 30NC
Selenium ND 0.05 mg/L ND 28NC
Silver ND 0.05 mg/L ND 28NC
Uranium ND 0.05 mg/L ND 27NC
EPA 1311 - TCLP Leachate Organics
PCBs, total ND 0.003 mg/L ND 30NC
Surrogate: Decachlorobiphenyl 0.010 mg/L 100 62-138
EPA 1311 - TCLP Leachate Volatiles
Benzene ND 0.005 mg/L ND 25NC
Carbon Tetrachloride ND 0.005 mg/L ND 25NC
Chlorobenzene ND 0.004 mg/L ND 25NC
Chloroform ND 0.006 mg/L ND 25NC
1,2-Dichlorobenzene ND 0.004 mg/L ND 25NC
1,4-Dichlorobenzene ND 0.004 mg/L ND 25NC
1,2-Dichloroethane ND 0.005 mg/L ND 25NC
1,1-Dichloroethylene ND 0.006 mg/L ND 25NC
Methyl Ethyl Ketone (2-Butanone) ND 0.30 mg/L ND 25NC
Methylene Chloride ND 0.04 mg/L ND 25NC
Tetrachloroethylene ND 0.005 mg/L ND 25NC
Trichloroethylene ND 0.004 mg/L ND 25NC
Vinyl chloride ND 0.005 mg/L ND 25NC
Surrogate: 4-Bromofluorobenzene 0.808 mg/L 117 83-134
Surrogate: Dibromofluoromethane 0.717 mg/L 104 78-124
Surrogate: Toluene-d8 0.695 mg/L 101 76-118
Physical Characteristics
% Solids 91.5 0.1 % by Wt. 91.4 250.0
Page 6 of 8
Order #: 2048187
Project Description: 20R103
Certificate of Analysis
Client:
Report Date: 30-Nov-2020
Order Date: 24-Nov-2020
Client PO:
Redstone Engineering
Method Quality Control: Spike
Analyte ResultReporting
Limit UnitsSource
Result%REC
%REC
LimitRPD
RPD
Limit Notes
EPA 1311 - TCLP Leachate Inorganics
Fluoride 0.65 0.24 82.8 70-130mg/L0.05
Nitrate as N 10 ND 105 81-112mg/L1
Nitrite as N 10 ND 96.4 76-107mg/L1
Cyanide, free 0.037 ND 74.2 60-136mg/L0.02
EPA 1311 - TCLP Leachate Metals
Arsenic 49.9 0.540 98.8 83-119mg/L0.05
Barium 70.0 20.2 99.7 83-116mg/L0.05
Boron 47.8 2.84 89.8 71-128mg/L0.05
Cadmium 44.3 0.045 88.6 78-119mg/L0.01
Chromium 56.9 6.02 102 80-124mg/L0.05
Lead 56.7 12.2 89.0 77-126mg/L0.05
Mercury 0.0324 ND 108 70-130mg/L0.005
Selenium 42.8 0.122 85.3 75-125mg/L0.05
Silver 44.2 ND 88.4 70-128mg/L0.05
Uranium 47.7 ND 95.4 70-131mg/L0.05
EPA 1311 - TCLP Leachate Organics
PCBs, total 0.046 ND 116 86-145mg/L0.003
Surrogate: Decachlorobiphenyl 0.010 101 62-138mg/L
EPA 1311 - TCLP Leachate Volatiles
Benzene 0.326 ND 94.8 55-141mg/L0.005
Carbon Tetrachloride 0.326 ND 94.7 49-149mg/L0.005
Chlorobenzene 0.350 ND 102 64-137mg/L0.004
Chloroform 0.323 ND 93.8 58-138mg/L0.006
1,2-Dichlorobenzene 0.352 ND 102 60-150mg/L0.004
1,4-Dichlorobenzene 0.338 ND 98.2 63-132mg/L0.004
1,2-Dichloroethane 0.347 ND 101 50-140mg/L0.005
1,1-Dichloroethylene 0.342 ND 99.5 43-153mg/L0.006
Methyl Ethyl Ketone (2-Butanone) 0.646 ND 75.1 26-153mg/L0.30
Methylene Chloride 0.330 ND 95.9 58-149mg/L0.04
Tetrachloroethylene 0.370 ND 108 51-145mg/L0.005
Trichloroethylene 0.336 ND 97.8 52-135mg/L0.004
Vinyl chloride 0.378 ND 110 31-159mg/L0.005
Surrogate: 4-Bromofluorobenzene 0.719 105 83-134mg/L
Surrogate: Dibromofluoromethane 0.695 101 78-124mg/L
Surrogate: Toluene-d8 0.710 103 76-118mg/L
Page 7 of 8
Order #: 2048187
Project Description: 20R103
Certificate of Analysis
Client:
Report Date: 30-Nov-2020
Order Date: 24-Nov-2020
Client PO:
Redstone Engineering
Qualifer Notes:
None
Sample Data Revisions
None
Work Order Revisions / Comments:
None
Other Report Notes:
MDL: Method Detection Limit
n/a: not applicable
Source Result: Data used as source for matrix and duplicate samples
%REC: Percent recovery.
RPD: Relative percent difference.
ND: Not Detected
NC: Not Calculated
Soil results are reported on a dry weight basis when the units are denoted with 'dry'.
Where %Solids is reported, moisture loss includes the loss of volatile hydrocarbons.
Page 8 of 8