GLAST LAT Project March 24, 2003 6G Tracker Peer Review, WBS 4.1.4 1 GLAST Large Area GLAST Large Area Telescope: Telescope: Tracker Subsystem WBS 4.1.4 6G: Tower module assembly A. Brez I.N.F.N. Pisa [email protected] Gamma-ray Large Gamma-ray Large Area Space Area Space Telescope Telescope

Upload: donald-sanders

Post on 05-Jan-2016

219 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: GLAST LAT ProjectMarch 24, 2003 6G Tracker Peer Review, WBS 4.1.4 1 GLAST Large Area Telescope: Tracker Subsystem WBS 4.1.4 6G: Tower module assembly A

GLAST LAT Project March 24, 2003

6G Tracker Peer Review, WBS 4.1.4 1

GLAST Large Area Telescope:GLAST Large Area Telescope:

Tracker SubsystemWBS 4.1.4

6G: Tower module assembly

A. BrezI.N.F.N. Pisa

[email protected]

Gamma-ray Large Gamma-ray Large Area Space Area Space TelescopeTelescope

Page 2: GLAST LAT ProjectMarch 24, 2003 6G Tracker Peer Review, WBS 4.1.4 1 GLAST Large Area Telescope: Tracker Subsystem WBS 4.1.4 6G: Tower module assembly A

GLAST LAT Project March 24, 2003

6G Tracker Peer Review, WBS 4.1.4 2

Tower module assembly flow downTower module assembly flow down

• LAT tower module assembly follows this block diagram (see LAT-PS-01854 and LAT-PS-01855 and for details)

Page 3: GLAST LAT ProjectMarch 24, 2003 6G Tracker Peer Review, WBS 4.1.4 1 GLAST Large Area Telescope: Tracker Subsystem WBS 4.1.4 6G: Tower module assembly A

GLAST LAT Project March 24, 2003

6G Tracker Peer Review, WBS 4.1.4 3

Tray assembly system successfully tested during pre-engineering tower test.Fast (<1day) accurate and safe stacking of the trays.

Reference pins

Fixation holes

Safety pins

Cable opening

Fixture

Pre-engineering tower ready for transportation and tests

Lift system

LAT-PS-01854

Page 4: GLAST LAT ProjectMarch 24, 2003 6G Tracker Peer Review, WBS 4.1.4 1 GLAST Large Area Telescope: Tracker Subsystem WBS 4.1.4 6G: Tower module assembly A

GLAST LAT Project March 24, 2003

6G Tracker Peer Review, WBS 4.1.4 4

Cosmic ray test

Cosmic ray flux in Pisa INFN labs:∼10 Hz/tray surfaceIn one day∼500 events/stripDeep and complete tower understanding time 1 week∼

LAT-PS-01855

Page 5: GLAST LAT ProjectMarch 24, 2003 6G Tracker Peer Review, WBS 4.1.4 1 GLAST Large Area Telescope: Tracker Subsystem WBS 4.1.4 6G: Tower module assembly A

GLAST LAT Project March 24, 2003

6G Tracker Peer Review, WBS 4.1.4 5

ConclusionsConclusions

• With the help of a reference system made with precise aluminum walls, the stack of the trays is fast and safe.

• Complete functional test of the tower system before sidewalls fixation.• The sidewalls are then added. Each tray is referred to precision holes in the sidewalls

that allow a good alignment without the pileup of the tolerances.• The system has been tested. The tolerance was below the maximum allowable

(0.3mm). The process is fast (<1 day to mount a tower).• The tower is a good cosmic rays telescope. The cosmic rays flux allows a complete

and deep understanding at the single channel level in a short time (1 week)