Page 1: GLAST LAT ProjectMarch 24, 2003 6F Tracker Peer Review, WBS 4.1.4 1 GLAST Large Area Telescope: Tracker Subsystem WBS 4.1.4 6F: Tray assembly A. Brez I.N.F.N

GLAST LAT Project March 24, 2003

6F Tracker Peer Review, WBS 4.1.4 1

GLAST Large Area Telescope:GLAST Large Area Telescope:

Tracker SubsystemWBS 4.1.4

6F: Tray assembly

A. BrezI.N.F.N. Pisa

[email protected]

Gamma-ray Large Gamma-ray Large Area Space Area Space TelescopeTelescope

Page 2: GLAST LAT ProjectMarch 24, 2003 6F Tracker Peer Review, WBS 4.1.4 1 GLAST Large Area Telescope: Tracker Subsystem WBS 4.1.4 6F: Tray assembly A. Brez I.N.F.N

GLAST LAT Project March 24, 2003

6F Tracker Peer Review, WBS 4.1.4 2

MCM Assembly on Trays and Test (INFN)

Procedure doc: LAT-PS-01802MCM incoming test: • Read out tests • Noise level• Noisy channels• HV test

MCM assembly with glue and screws Scotchweld 2216 A/B grayGlue thickness .1mmPattern of glue lines to avoid air trapping

Area occupancy 50% ∼ ⇨ Δt 0.1≲ 0CMCM final test: • Read out tests • Noise level• Noisy channels• HV test

The tray is put in the tray-storage box and is delivered to the ladder assembly center

Page 3: GLAST LAT ProjectMarch 24, 2003 6F Tracker Peer Review, WBS 4.1.4 1 GLAST Large Area Telescope: Tracker Subsystem WBS 4.1.4 6F: Tray assembly A. Brez I.N.F.N

GLAST LAT Project March 24, 2003

6F Tracker Peer Review, WBS 4.1.4 3

Integration of SSD Ladders onto Tracker TraysIntegration of SSD Ladders onto Tracker Trays

Assembly in G&A Engineering

Assembling stepsAssembling steps• Tray position study, Z adjustment• The ladders are aligned on the

alignment jig• The ladders are vacuum kept by the

bridges• The glue drops are deposited on the

tray• The tray is placed again on the tool• The ladders are positioned on the tray

by means of the bridges• Glue cure (at RT for more than 6 hours)• Ladder metrology• Microbonding• MCMs fast test to check bondings• Encapsulation• The tray is placed in the tray-storage

box for delivery to test labs

• Tray position study, Z adjustment• The ladders are aligned on the

alignment jig• The ladders are vacuum kept by the

bridges• The glue drops are deposited on the

tray• The tray is placed again on the tool• The ladders are positioned on the tray

by means of the bridges• Glue cure (at RT for more than 6 hours)• Ladder metrology• Microbonding• MCMs fast test to check bondings• Encapsulation• The tray is placed in the tray-storage

box for delivery to test labs

Procedure doc: LAT-PS-01801

Page 4: GLAST LAT ProjectMarch 24, 2003 6F Tracker Peer Review, WBS 4.1.4 1 GLAST Large Area Telescope: Tracker Subsystem WBS 4.1.4 6F: Tray assembly A. Brez I.N.F.N

GLAST LAT Project March 24, 2003

6F Tracker Peer Review, WBS 4.1.4 4

The toolsThe tools

Jig of ladders alignment

Ladders vacuum kept on the bridges

Jig of tray alignment

Reference dowels

Alignment micrometers

C.M.M. with touch head and optical head

All the assembly operations under C.M.M.Glue spots deposition with automatic dispenserMicrobonding with automatic wedge bonder

Page 5: GLAST LAT ProjectMarch 24, 2003 6F Tracker Peer Review, WBS 4.1.4 1 GLAST Large Area Telescope: Tracker Subsystem WBS 4.1.4 6F: Tray assembly A. Brez I.N.F.N

GLAST LAT Project March 24, 2003

6F Tracker Peer Review, WBS 4.1.4 5

Assembly phasesAssembly phases

Tray positioning

Ladder positioning

Microbonding

1 assembly chain ready5 assembly chains in constructionMax assembly rate : 15 trays/weekForeseen assembly rate: 10 trays/week

Page 6: GLAST LAT ProjectMarch 24, 2003 6F Tracker Peer Review, WBS 4.1.4 1 GLAST Large Area Telescope: Tracker Subsystem WBS 4.1.4 6F: Tray assembly A. Brez I.N.F.N

GLAST LAT Project March 24, 2003

6F Tracker Peer Review, WBS 4.1.4 6

Connector savers

Fixation screws

The tray storage box

This robust Aluminum box allows safe and clean shipping.The tray can be tested in the closed box, connecting the MCMs through the connector savers.

Connector saver protections

Page 7: GLAST LAT ProjectMarch 24, 2003 6F Tracker Peer Review, WBS 4.1.4 1 GLAST Large Area Telescope: Tracker Subsystem WBS 4.1.4 6F: Tray assembly A. Brez I.N.F.N

GLAST LAT Project March 24, 2003

6F Tracker Peer Review, WBS 4.1.4 7

First resultsFirst results

ladder alignemnt

0

0.5

1

1.5

2

2.5

3

3.5

4

4.5

m

=14m

TG02 dw

-0.2

-0.1

0

0.1

0.2

0.3

0.4

0 100 200 300 400

Y (mm)

Z (m

m)

x=47

x=231

x=404

glue pads 5mmcure time 6h

Planarity

Requirements:Alignment error < 40mPlanarity 100m

Page 8: GLAST LAT ProjectMarch 24, 2003 6F Tracker Peer Review, WBS 4.1.4 1 GLAST Large Area Telescope: Tracker Subsystem WBS 4.1.4 6F: Tray assembly A. Brez I.N.F.N

GLAST LAT Project March 24, 2003

6F Tracker Peer Review, WBS 4.1.4 8

ConclusionsConclusions

• The tray assembly has been successfully tested: the alignment and planarity of the ladders are in specification with possible improvements.

• The number of tools in production will allow an assembly rate of 40 trays/month (2 towers/month) that well matches with the test rate of the trays and towers.