GPB Updates. Asec. Blesila A. Lantayona Harold’s Hotel, Cebu City July 2, 2014. OUTLINE. GPB Report Card Agency-wide Per Island Group By Region Implementation Plan Issues and Concerns Approval of GPB Projects Amounting to P1M above up to P9.999M Proposed GPB Coordinating Committee. - PowerPoint PPT PresentationTRANSCRIPT
GPB UpdatesAsec. Blesila A. Lantayona
Harold’s Hotel, Cebu CityJuly 2, 2014
OUTLINEA. GPB Report Card
1) Agency-wide2) Per Island Group3) By Region
B. Implementation PlanC. Issues and ConcernsD. Approval of GPB Projects Amounting to P1M above
up to P9.999ME. Proposed GPB Coordinating Committee
A. DTI BuB Report CardAs of May 2014
DEFINITIONS• Proposed - The project has been proposed under the
program but still has to undergo validation by the implementing agency
• Pipelined - The project has been validated by the agency and is undergoing preparatory activities for project implementation
• On-going - The implementation of the project has started and there is an already verifiable physical accomplishment
• To be determined - The project will not be implemented by the implementing agency and may be subject to project replacement
• Completed - The project has been physically completed
5
PHYSICAL
No. of Projects (2014) 882 912No. of Project Implemented 29 83
COMPLETED 4 0ONGOING 25 83
Implementation Rate 3.29% 9.10%Completion Rate 0.45% 0.00%Time Elapsed 25% 33%
FINANCIAL
Total BuB Budget 548,534,000Operations 532,557,000
M&E 15,977,000
Total Obligations 50,637,053.50 Budget Utilization Rate
Obligations BuR 9.23%Disbursement BuR
Note:
Red figures Total no. of projects based on feedback from regions. No supporting documents yet.
1. Agency Wide
2. Per Island Group
6
Implementation rate
Completion rate
NL 1.45% 0%SL 17.10% 0%
3.20% 0%13.80% 0%9.10% 0%
Luzon
VisayasMindanao
Area
DTISL: as of May 30SL: as of 30 May 2014; others as of 30 April 2014
7
NATIONAL CAPITAL REGION
PHYSICAL
No. of Projects (2014) 1 1No. of Project Implemented 0 0
COMPLETED
ONGOING
Implementation Rate 0% 0%Completion Rate 0% 0%Time Elapsed 25% 33%
FINANCIAL
Total BuB Budget 1,841,000Operations 1,787,000
M&E 54,000
Total Obligations 0Utilization Rate
Obligation/Allotment
Disbursement/Obligation
3. By Region
8
CORDILLERA ADMINISTRATIVE REGION
PHYSICAL
No. of Projects (2014) 45 61No. of Project Implemented 0 3
COMPLETED 0ONGOING 3
Implemention Rate 0% 4.92%Completion Rate 0% 0.00%Time Elapsed 25% 33%
FINANCIAL
Total BuB Budget 21,491,000Operations 20,865,000
M&E 626,000
Total Obligations 0Utilization Rate
Obligation/Allotment
Disbursement/Obligation
9
REGION 1
PHYSICAL
No. of Projects (2014) 78 76No. of Project Implemented 0 0
COMPLETED
ONGOING
Implementation Rate 0% 0%Completion Rate 0% 0%Time Elapsed 25% 33%
FINANCIAL
Total BuB Budget 51,275,000Operations 49,782,000
M&E 1,493,000
Total Obligations 0Utilization Rate
Obligation/Allotment
Disbursement/Obligation
10
REGION 2
PHYSICAL
No. of Projects (2014) 44 44No. of Project Implemented 0 0
COMPLETED
ONGOING
Implementation Rate 0% 0%Completion Rate 0% 0%Time Elapsed 25% 33%
FINANCIAL
Total BuB Budget 41,164,000Operations 39,965,000
M&E 1,199,000
Total Obligations 0Utilization Rate
Obligation/Allotment
Disbursement/Obligation
11
REGION 3
PHYSICAL
No. of Projects (2014) 25 25No. of Project Implemented 0 0
COMPLETED 0ONGOING
Implementation Rate 0% 0%Completion Rate 0% 0%Time Elapsed 25% 33%
FINANCIAL
Total BuB Budget 5,713,000Operations 5,547,000
M&E 166,000
Total Obligations 0Utilization Rate
Obligation/Allotment
Disbursement/Obligation
12
REGION 4A
PHYSICAL
No. of Projects (2014) 39 44No. of Project Implemented 0 4
COMPLETED 4 0ONGOING 4
Implementation Rate 10.26% 9.1%Completion Rate 10.26% 0.00%Time Elapsed 25% 42%
FINANCIAL
Total BuB Budget 23,063,000 Operations 22,391,000
M&E 672,000
Total Obligations 34,800Budget Utilization Rate
Obligations BuR 0.15%Disbursement BuR
13
REGION 4B
PHYSICAL
No. of Projects (2014) 83 91No. of Project Implemented 7 18
COMPLETED 0 0ONGOING 7 18
Implementation Rate 8.43% 19.8%Completion Rate 0% 0.00%Time Elapsed 25% 42%
FINANCIAL
Total BuB Budget 51,024,000 Operations 49,538,000
M&E 1,486,000
Total Obligations 0Budget Utilization Rate
Obligations BuR
Disbursement BuR
14
REGION V
PHYSICAL
No. of Projects (2014) 52 52No. of Project Implemented 0 10
COMPLETED 0 0ONGOING 0 10
Implementation Rate 0% 19.2%Completion Rate 0% 0.00%Time Elapsed 25% 42%
FINANCIAL
Total BuB Budget 38,468,000 Operations 37,348,000
M&E 1,120,000
Total Obligations 0Budget Utilization Rate
Obligations BuR
Disbursement BuR
15
REGION VI
PHYSICAL
No. of Projects (2014) 110 109No. of Project Implemented 0 4
COMPLETED 0 0ONGOING 0 4
Implementation Rate 0% 3.7%Completion Rate 0% 0.00%Time Elapsed 25% 33%
FINANCIAL
Total BuB Budget 48,563,000 Operations 47,149,000
M&E 1,414,000
Total Obligations 18,386,753.50 Budget Utilization Rate
Obligations BuR 37.86%Disbursement BuR
16
REGION VII
PHYSICAL
No. of Projects (2014) 50 47No. of Project Implemented 0 2
COMPLETED 0 0ONGOING 0 2
Implementation Rate 0% 4.3%Completion Rate 0% 0.00%Time Elapsed 25% 33%
FINANCIAL
Total BuB Budget 35,144,000 Operations 34,120,000
M&E 1,024,000
Total ObligationsBudget Utilization Rate
Obligations BuR
Disbursement BuR
17
REGION VIII
PHYSICAL
No. of Projects (2014) 64 65No. of Project Implemented 0 1
COMPLETED 0 0ONGOING 0 1
Implementation Rate 0% 1.5%Completion Rate 0% 0.00%Time Elapsed 25% 33%
FINANCIAL
Total BuB Budget 41,163,000 Operations 39,964,000
M&E 1,199,000
Total Obligations 0Budget Utilization Rate
Obligations BuR
Disbursement BuR
18
REGION IX
PHYSICAL
No. of Projects (2014) 11No. of Project Implemented 0
COMPLETED 0ONGOING 0
Implementation Rate 0%Completion Rate 0%Time Elapsed 25%
FINANCIAL
Total BuB Budget 11,018,000 Operations 10,697,000
M&E 321,000
Total Obligations 0Utilization Rate
Obligation/Allotment
Disbursement/Obligation
19
REGION X
PHYSICAL
No. of Projects (2014) 61 63No. of Project Implemented 0 5
COMPLETED 0 0ONGOING 0 5
Implementation Rate 0% 7.94%Completion Rate 0% 0.00%Time Elapsed 25% 33%
FINANCIAL
Total BuB Budget 44,596,000 Operations 43,297,000
M&E 1,299,000
Total Obligations 6,015,500.00 Utilization Rate
Obligation/Allotment 13.49%Disbursement/Obligation
20
REGION XI
PHYSICAL
No. of Projects (2014) 22 26No. of Project Implemented 0 1
COMPLETED 0 0ONGOING 0 1
Implementation Rate 0% 3.85%Completion Rate 0% 0%Time Elapsed 25% 33%
FINANCIAL
Total BuB Budget 10,834,000 Operations 10,518,000
M&E 316,000
Total Obligations 8,465,000Utilization Rate
Obligation/Allotment 78.13%Disbursement/Obligation
21
REGION XII
PHYSICAL
No. of Projects (2014) 67 67No. of Project Implemented 0 1
COMPLETED 0 0ONGOING 0 1
Implementation Rate 0% 1.49%Completion Rate 0% 0.00%Time Elapsed 25% 33%
FINANCIAL
Total BuB Budget 32,580,000 Operations 31,631,000
M&E 949,000
Total ObligationsUtilization Rate
Obligation/Allotment
Disbursement/Obligation
22
REGION CARAGA
PHYSICAL
No. of Projects (2014) 130 130No. of Project Implemented 18 35
COMPLETED 0 0ONGOING 18 35
Implementation Rate 13.85% 26.92%Completion Rate 0% 0%Time Elapsed 25% 33%
FINANCIAL
Total BuB Budget 90,597,000 Operations 87,958,000
M&E 2,639,000
Total Obligations 17,735,000Utilization Rate
Obligation/Allotment 19.58%Disbursement/Obligation
B. Implementation PlanPipelined On-Going Completed
NCR 1 1 0 0 0.25 25%CAR 61 54 3 0 23 38%1 76 73 0 0 36 47%2 44 42 0 0 28 64%3 25 25 0 0 15.83 63%4A 44 39 4 0 4 9%4B 91 73 18 0 10 11%5 52 42 10 0 0 0%6 109 44 4 0 18 17%7 47 45 2 0 2 4%8 65 46 1 0 17 26%9 11 11 0 0 1 9%10 63 58 5 0 14 22%11 26 25 1 0 3 12%12 67 50 1 0 15 22%CARAGA 130 87 35 0 7 5%Total 912 715 84 0 194 21%
REGIONNo. of
Projects
As of April Completed by end of June
Completion rate by End
of June
C. Issues and Concerns
TOP 1O ISSUES AND CONCERNS1. Late submission of documents by LGUs2. No LGU focal person in charge of BuB/GPB3. No Project proposals (DTI need to prepare)4. Guidelines (delayed issuance, too many issuances)5. DTI not invited to LPRAT meetings6. Lack of information and understanding on GPB/BuB7. MOOE/CO concerns (realignment issues)8. Funding issues (fund transfer, lack of info on GPB
funds)9. Lack of DTI manpower to implement BuB10. Replacement projects
OTHER ISSUES AND CONCERNS
1. LPRAT ( No CSO, no meetings, schedule issues)
2. Menu of DTI projects not clear3. No DTI GPB team4. Political (SB resolutions not issued, new
CSOs)5. Delay of processing documents in Head
office6. Lack of technical expertise by LGU 7. LGUs not aware of BuB/GPB8. Low priority of LCE on DTI BuB projects9. DTI other priorities - Yolanda/SSF
• DTI dependence • audit • geographical constraints• inter agency coordination between NGAs in
the regional level • lack of DTI planning • lack of interest from LGU• reportorial requirements• signing authority of RDs limited, need to
bring to HO• slow procurement • who will implement
OTHER CONCERNS
D. Approval of GPB Projects Amounting to P1M above up to P9.999M
Regions to send GPB MOAs for signature together with the necessary documentary
requirements
ROG checks for completeness of
documents (within the day of receipt)Incomplete Docs
Legal Service reviews GPB documents.
(may take at least 5 working days)
ROG-Asec. signs cleared documents by Legal Service (within 1-3 days upon receipt
from LS)
For corrections/actions
Regions
• Signed MOA/Voucher• Confirmation of Intent
of the LGU to implement the project
• Seal of Good Housekeeping (2012)
• Proof of municipality’s implementation of Public Financial Mgt. Improvement Plan
• LGU org. chart• List of personnel
assigned to the project• Approved project’s
Work and Financial Plan
E. Creation of DTI Coordinating Committee on the Grassroots Participatory Budgeting (GPB)Chairperson : Assistant Secretary Blesila A. Lantayona, ROG
Members : Director Mary Jean T. Pacheco, CPSDirector Ireneo V. Vizmonte, FMSProject Manager Manuel B. Abad, CARP PMOA/Director Jerry T. Clavesillas, BSMED
Secretariat : Bureau of Small and Medium Enterprise Development (BSMED)
* Status – signed by U/ZCM, currently with U/NKT for signature
Creation of DTI Coordinating Committee on the Grassroots Participatory Budgeting (GPB)The functions of the Committee include, but are not limited to the following:
1. Recommend to the ROG Undersecretary strategic direction to guide and direct the implementation of GPB.
2. Evaluate the implementation of GPB, and recommend best courses of action that may be adopted to improve project implementation.
3. Ensure DTI’s prompt compliance to the M & E requirements of the oversight agencies.
4. Submit reports to ROG and MSG Undersecretaries on a regular basis.5. Conduct regular meetings to review and coordinate project activities6. Attend to meetings set by the oversight agencies.
Creation of DTI Coordinating Committee on the Grassroots Participatory Budgeting (GPB)A Regional GPB Focal Person and a Provincial GPB focal person shall be designated by the Regional Director/Provincial Director. Under the supervision of the Regional/Provincial Director, the focal persons are expected to:
1. Coordinate the timely and efficient implementation of GPB.2. Consolidate and submit reports to the regional office in case of the
Provincial focal person and to the Secretariat cc the GPB Committee Chair in case of the Regional focal person.
3. Inform the Secretariat of the issues and concerns arising from the implementation.
4. Relay to the LGUs matters regarding GPB project implementation coming from Head Office.
Thank you.