Page 1: Grid connected Solar Rooftop

Grid Connected Roof Top Solar Power Plant

Page 2: Grid connected Solar Rooftop

Solar Photovoltaic

• PV system, is a power system designed to supply usable solar power by means of photovoltaic's. It consists of an arrangement of several components, including solar panels to absorb and convert sunlight into electricity, a solar inverter to change the electric current from DC to AC, as well as mounting ,cabling and other electrical accessories to set up a working system.

Page 3: Grid connected Solar Rooftop

Crystalline Solar Cells

Poly Crystalline Cell Mono Crystalline Cell

Page 4: Grid connected Solar Rooftop

On Grid Application

Page 5: Grid connected Solar Rooftop

State Designated for Roof Top Model

• Uttar Pradesh • Delhi • Haryana • Himachal Pradesh • Punjab • Kolkata• Tamil Naidu• Andhra Pradesh• Rajasthan• Gujarat• Maharashtra• Orissa

Page 6: Grid connected Solar Rooftop

Net Meter• Net metering is a billing mechanism that credits

solar energy system owners for the electricity they add to the grid. For example, if a residential customer has a PV system on the home's rooftop, it may generate more electricity than the home uses during daylight hours. If the home is net-metered, the electricity meter will run backwards to provide a credit against what electricity is consumed at night

Page 7: Grid connected Solar Rooftop
Page 8: Grid connected Solar Rooftop
Page 9: Grid connected Solar Rooftop

What is Net Metering

Net metering is the process through which you attain a “dual-benefit “by installing a solar power plant on the roof, open space, walls of the building to generate electricity.

Generated power is first used in the building as per the requirement and the surplus power is fed to the grid of utility.

Page 10: Grid connected Solar Rooftop

WHO CAN INSTALL

• Consumers of electricity having minimum sanctioned load of 1.25KW and maximum of 12.50 MW who intend to generate their own electricity and desire to contribute towards environmental protection can install Solar PV plants on Roof-Tops/ Walls/Open area of Individual households, Industries, commercial establishments, institutions, residential complexes, Schools, Colleges, Hospitals, sheds, cold stores, govt. and semi-govt. buildings, etc.

Page 11: Grid connected Solar Rooftop

The maximum capacity of solar power plant to be installed in a building would be 80% of the sanctioned electricity load of that building.

Page 12: Grid connected Solar Rooftop

What is the Procedure for Net Metering1.Submission of Application

• For installation of solar power plant the applicant has to register/apply online at any one the sites with copy of latest electricity bill and available shadow free area at the top of roof/ walls/ open space within the compound.

Period of Time ::3 weeks

Page 13: Grid connected Solar Rooftop

Approval For Installation

• After verification, Discom will give online approval to the applicant for installation of required capacity Solar Power Plant.

• Period of Time: 30 days

Page 14: Grid connected Solar Rooftop

Processing Fee & Signing of Agreement with Discom

• The consumer intending to setup Roof Top solar power plant shall deposit  the processing fee of Rs. 50 per KVA or part there of subject to maximum of Rs.10000 in the concerned DS/ Sub Division office of Discom on first come first serve basis. The consumer shall also sign supplementary agreement with Discom 

Page 15: Grid connected Solar Rooftop

Installation of Solar Power Plant

• After approval from Discom, applicant will contact Medors to install solar power plant and submit online work completion report along with photograph of the system and single line diagram of the synchronizing and protection arrangements.

Page 16: Grid connected Solar Rooftop

Installation of Bi-directional Meter

• After receiving project completion report, Bi-directional meter would be installed at the premises of the beneficiary by Discom. For this, applicant has to deposit prescribed fee of Bi-Directional meter at Sub Divisional Office  of Discom.

Page 17: Grid connected Solar Rooftop

Release of  Subsidy

• After installation of Bi-directional meter the plant shall be treated as commissioned and the beneficiary will apply online for release of subsidy to SNA along with the work completion report duly verified by Discom

• Subject to availability of MNRE,GOI funds at the rate of INR 12 Per Watt .

Page 18: Grid connected Solar Rooftop

Banking Mechanism And Billing

• Discom shall take energy meter readings for import or drawl and export or injection of power and work out the net energy flow quantum from or to the consumer. In case the net flow is towards the Discom i.e. the consumer has injected/exported the net surplus energy to the Discom system, such quantum will be treated as energy banked by the consumer with Discom in the current billing cycle

Page 19: Grid connected Solar Rooftop

Discom Tariff

• The Energy Bill for import will be prepared as per the retail supply tariff as approved by the CERC for the category to which the consumer belongs. The energy exported to Discom from the rooftop Solar PV system shall be set-off against the energy imported from the Discom grid at the CERC approved retail supply tariff applicable to the particular consumer category.

Page 20: Grid connected Solar Rooftop

Delhi First Net Meter Bill

Page 21: Grid connected Solar Rooftop

Economics & Pay Back Period of Solar Roof Top Power Plant

Page 22: Grid connected Solar Rooftop

Case Study On Solar Power Plant 10 kw

Page 23: Grid connected Solar Rooftop

Scope Of Work

• 10000 wp Solar P.V Plant • European On Line Inverter 10 kW• Galvanized Mounting Structure • Application & Agreement• Approval for Net Metering • Installation & Commissioning

Page 24: Grid connected Solar Rooftop

Power Production Per day • 10000 wp solar P.V array • 250 wp x 40 panel = 10000 wp • Module type Crystalline • Hourly out put : 10000 wp at 1000 w/h/mt2 sun

radiance • Perfect Sun hours average 4.5 hrs per day • Per day power output will be 4.5 x 10 = 45 kWh• Yearly production will be 45x 365 = 16425 kWh

Page 25: Grid connected Solar Rooftop

Yearly Gross Saving Comparison From Grid

• The Cost of one kWh will be Inr 8 inclusive of taxes so daily saving will be Inr 360/-

• Yearly Saving will be : 16425 kWh x 8 = 1,31,400/-

Page 26: Grid connected Solar Rooftop

Pay back period in comparison with grid

• The Cost of the System :- 7,50,000 /-• Subsidy Amount : 1,20,000/-• Saving with Grid :- 1,31,400/- Per Year

• Pay back period with grid is = 4 years

Page 27: Grid connected Solar Rooftop

Green Calculation with Grid

• For Producing 1 Unit of Electricity their is emission of 0.6 kg of Co2in atmosphere.

• You Contribute to reduce Co2 from atmosphere by

16425x.06 = 9855 kg per year 9855 kg

Page 28: Grid connected Solar Rooftop

Financial Benefits for Installing Solar Roof Top Model

• Accelerated Depreciation in Income Tax• Subsidy form Government Rs. 12 Per Watt • Power Sell Agreement with your Discom• Pay Back Period is 3.5 Years• Life of System is 25 yrs • A Gift to Nation

Page 29: Grid connected Solar Rooftop

Individual Benefits :-

Consumer becomes generator for his own electricity requirements.

Reduction in electricity Bills.Elimination of minimum monthly charges.Generation during the day time when

demand is high.

Page 30: Grid connected Solar Rooftop

Solar On P.C.R

Page 31: Grid connected Solar Rooftop

Finance Minister of India Residence 9.6 Kw Solar Power Plant

Page 32: Grid connected Solar Rooftop

Delhi Chief Minister’s Residence12.5kw On Grid Solar System

Page 33: Grid connected Solar Rooftop

Delhi Deputy Chief Minister’s Residence 6.5kw

Page 34: Grid connected Solar Rooftop

Roof Top Elevated Structure

Page 35: Grid connected Solar Rooftop

Roof Top Elevated Structure

Page 36: Grid connected Solar Rooftop

Roof Top Elevated Structure

Page 37: Grid connected Solar Rooftop

Fronius Technical Team

Page 38: Grid connected Solar Rooftop

Car Parking With Solar Roof Top

Page 39: Grid connected Solar Rooftop

Open Storage for Food Items

Page 40: Grid connected Solar Rooftop

Building Integrated P.V

Page 41: Grid connected Solar Rooftop

Building Integrated P.V

Page 42: Grid connected Solar Rooftop

Building Integrated P.V

Page 43: Grid connected Solar Rooftop

On Line Monitoring of Solar Power Plant

Page 44: Grid connected Solar Rooftop
Page 45: Grid connected Solar Rooftop

Screen Shot For Mobile App

Page 46: Grid connected Solar Rooftop

Screen Shot For Mobile App

Page 47: Grid connected Solar Rooftop

Screen Shot For Mobile App

Page 48: Grid connected Solar Rooftop

Technology Partner

Page 49: Grid connected Solar Rooftop

Certification

Page 50: Grid connected Solar Rooftop

Thanks

www.medors.in