ground improvement techniques
TRANSCRIPT
GROUND IMPROVEMENT TECHNOLOGY- STONE COLUMN TECHNOLOGY- BAND DRAIN TECHNOLOGY
Sravan MVEngineer
ALTERNATIVES FOR INADEQUATE GROUND?
Abandon the site and locate the structure elsewhere
Design deep foundations to carry the weight of the structure to competent stratum
Redesign the structure according to the ground conditions
Improve the properties of the ground prior to construction
BASIC PRINCIPLE OF GROUND IMPROVEMENT
Densification of the ground , E.g.: Compaction Accelerate the consolidation, E.g.: Vertical drains Usage of geo synthetics, E.g.: Geotextiles Usage of admixtures, E.g.: Cement stabilization Preloading Mechanical Stabilization
Ground improvement is the modification of the ground properties in order to achieve the required ground conditions for the particular use of the ground.
STONE COLUMN TECHNOLOGY
STONE COLUMN TECHNOLOGY It is also known as Vibro replacement
or Vibro displacement Compacted aggregates form as a
vertical columns to improve the soil conditions.
Resulting in considerable increase in vertical load capacity and to an extent contribute to as drains to dissipate pore water pressure.
Two methods of stone columns:
Wet / Top Feed Method
Dry / Bottom Feed Method
STONE COLUMN TECHNOLOGY
STONE COLUMN : WET / TOP FEED METHOD
Step 1 : Penetration of probe Step 2 : Backfilling of aggregate and
compacting Step 3 : Consolidation of granular fill and
finishing the column
Vibro Probe
STONE COLUMN : DRY / BOTTOM FEED METHOD
Step 1 : Penetration of probe Step 2 : Installation of aggregate through
separate duct along the vibro probe Step 3 : Consolidation of granular fill and
finishing the column
Technically and potentially economical alternative for deep compaction.
Alternative for dynamic compaction, deep blasting etc.,
Quicker than preloading the site It increases the bearing capacity,
reduces the settlements, liquefaction potential.
STONE COLUMN : ADVANTAGES
CASE STUDY: Four Lane National Highway Connectivity to ICTT – Vallarpadam, Kochi
Connects NH - 47 and NH - 17. Project cost was revised from 329.46 cr to 571.20 cr due
to ground improvement, bridges and retaining walls. Road Length – 17.2km, total length of bridges – 2.93km. Ground improvement works – 10km. Wet /Top method of installation was used. Stone columns where installed in 15 locations
between Ch, 0.245 and 16.210
CASE STUDY: INSTALLATION
CASE STUDY : INSTALLATION
CASE STUDY :STONE COLUMN Quantity of stone aggregate used : 28,774 cum. Geo grid consumed: 35,536. 12 sq.m Bulk density considered : 1.8 MT/m3
App. Quantity of aggregate for one column : 35MT
Total number of stone columns : 22,166 no's Time required for each stone column : 60 min No. of stone columns installed per day : 15 no's Total running meter of all the columns :
91,641 Rm
BAND DRAIN TECHNOLOGY
BAND DRAIN TECHNOLOGY - PVD Used in loose, compressible and water
saturated clay and silty clays. Soils are characterized by very loose
skeleton and a large pore sizes filled with water
Requires about ten or more years to consolidate on preload.
PVD – Prefabricated Vertical Drain.
WHAT IS VERTICAL DRAIN? Consolidation takes
place in only one direction
Vertical drainage path may be substantially longer
It may take 10+ years to consolidate Pore water will flow laterally
Pore water pressure dissipates as the layer drains and water is conveyed through vertical drains
It takes only about 6months or so to consolidate
COMPONENTS OF PVD? Core : It is called drained body
corrugated, flexible and made of polypropylene, designed to provide high discharge capacity, high tensile and compressive strength.
Filter Jacket: Non – woven ,thermically bonded polypropylene wrapped around the core. Acts as the filter to allow ground water to the core.
Filter
Core
ADVANTAGES OF BAND DRAIN TECHNOLOGY:
Minimum disturbance to the soil layers during installation
High water discharge capacity High tensile strength prevents the
collapse of flow path. Fast and easy installation Deep installation up to 40m.
CASE STUDY: Four Lane National Highway Connectivity to ICTT – Vallarpadam, Kochi
Connects NH- 47 and NH – 17. Project cost was revised from 329.46 cr to 571.20 cr
due to ground improvement, bridges and retaining walls.
Road Length – 17.2km, total length of bridges – 2.93km.
Ground improvement works – 10km. PVD were installed in 8 locations between
Chainage 8.400 – 15.000
CASE STUDY: INSTALLATION EQUIPMENT
Hydraulic Stitcher Mandrel Base Hydraulic Machine
CASE STUDY: BAND DRAIN INSTALLATION
CASE STUDY: BAND DRAIN INSTALLATION
Total length of band drains : 56,21,780 Rm Total Granular blanket : 1,23,386 Cum Total Geotextiles used : 3,90,714 sq.m Time taken for install one band drain of 25m :
1min Time taken for splicing the wick : 1 min
CASE STUDY: BAND DRAIN TECHNOLOGY
After the installation of band drains, Casagrande peizometer and plate type settlement recorders where installed in order to check the settlements
CASE STUDY: BAND DRAIN TECHNOLOGY
Description ValuesCumulative Heights Stage 1 : 3.0m ( i.e., 1.0m above
the top of reclamation)Stage 2 : 5.5m ( includes 1.5m of additional surcharge)
Waiting period of each stage Stage 1 : 6.0 monthsStage 2 : 6.0 months
CASE STUDY: BAND DRAIN TECHNOLOGY
The water coming out of the vertical drains is collected in temporary ditch. The water collected is regularly dewatered to the adjoining area.
THANK YOU!