gulf energy development public company limited · 2019. 5. 21. · in thailand’s power industry,...
TRANSCRIPT
-
Gulf Energy Development Public Company Limited
Q1 2019 Analyst Meeting
May 2019
-
2
Business Updates
-
3
Bidding submission of Map
Ta Phut Industrial Port Phase 3 project
Key events in Q1 2019
Jan 1 Jan 25 Mar 29Feb 1 Feb 15 Mar 1 Mar 6
7,500 million baht debentures allotment
GNLL2 (127 MW) COD GNPM (135 MW) COD
Bidding submission
of Laem Chabang Port Phase 3 project
TTCIZ-01 (69 MW) COD
Increased stake in TTCIZ-02 from 49% to 90%
-
4
Key activities in Q2 – Q4 2019
APR MAY DECJUN JUL SEP OCT NOVAUG
JUL 1:
GNRV2 (128 MW) SCOD
GPD (2,500 MW)
financial close
MAY 1:
GNRV1 (128 MW) COD
NGD4 SCOD
(2,000,000 mmbtu/year)
APR 19:
TTCIZ-02 (50 MW) COD
APR 25:
Signed SPA and SHA to
increase stake from 49%
to 95% in Mekong
Project (Solar & Wind in
Vietnam)
Tie-line program fully integrated
(GNLL & GNLL2, GNK2 & GNPM,
and GNRV1 & GNRV2)
Plant A Plant B
100% 100%
Turbine Turbine
100%
Turbine Turbine
Mekong Wind Farm
(Phase I: 30 MW)
commences
construction
Mekong Wind Farm
(Phase II: 49 MW)
commences
construction
-
5
Business Overview
-
6
Business overview
Gas-fired Business Renewable Business Other Business
▪ 2 IPPs and 7 SPPs
▪ 4,237 MW
▪ COD: 2013-2015
40%Ownership
▪ 12 SPPs
▪ 1,563 MW
▪ COD: 2017-2019
70%Ownership
70%Ownership
(75% dividend)
75%Ownership
100%Ownership
▪ 4 Rooftop-solar VSPPs
▪ 0.6 MW
▪ COD: 2014-2015
▪ 1 Biomass project
▪ 25 MW
▪ COD: 2020
▪ 2 IPPs
▪ 5,300 MW
▪ COD: 2021-2024
Solar power projects49-95%Ownership
▪ 3 Solar projects
▪ 149 MW
▪ COD: [2019-2020]
▪ Natural Gas Distribution
• 2 NGD projects
• 4,000,000 mmbtu/year
• COD in 2018-2019
▪ Investment
• 8.38% in SPCG
• 0.46% in EDL-Gen
11,426 MW
35%Ownership
WHA MT
Thailand
Overseas
484 MW
▪ 1 Independent power
and water project
▪ 326 MW
▪ COD: 2020-2022
45%Ownership
Duqm Power
Company (“DPC”)
Wind power project95%Ownership
▪ 1 Wind project
▪ 310 MW
▪ COD: 2021-2023
-
7
Power business
Preparing for or
under construction/
development
33 Power projects
in 3 countries
With over 20 years of continued experience in Thailand’s Power industry, Gulf has become one of the
largest power companies in the country, operating in all
types of power producers – IPP, SPP and VSPP – using
environmental-friendly fuels, mainly natural gas plus
growing contribution from renewables.
In operation
Vietnam(4 projects)
Oman(1 project)
Thailand(28 projects)
Installed capacity Gross Equity
In operation 5,791 MW 2,583 MW
Preparing for or under construction/ development 6,119 MW 4,295 MW
Total 11,910 MW 6,878 MW
1994
Thailand’s 1st IPP
2007 20132010 2016 2018
Thailand’s 1st SPP
Thailand’s 2nd IPP
Thailand’s 2nd SPP
Thailand’s 3rd SPP
Thailand’s 3rd IPP
-
8
Power capacity growth – over 20% in 5 years
Gross Installed Capacity (MW):
Equity Installed Capacity (MW):
831
2,485
4,237 4,237 4,772 5,282
5,791 5,919 6,083
7,596
9,145
10,585
11,910
-
2,000
4,000
6,000
8,000
10,000
12,000
14,000
2013 2014 2015 2016 2017 2018 May-19 2019 2020 2021 2022 2023 2024
GJP GMP IPD GCG Gulf Solar Vietnam Oman Total
Note: 1/ Gulf's equity stake in GJP was 10% until August 15, 2016 when the stake was increased to 40%; equity installed capacities for 2013-2016 are based on the pro-forma 40% stake for comparison purposes
2/ Include the gas-fired power project in Oman
76%
20%
4%
320 982
1,683 1,683 1,964 2,253
2,583 2,673 2,775
3,827
4,913
5,950
6,878
-
1,000
2,000
3,000
4,000
5,000
6,000
7,000
8,000
2013 2014 2015 2016 2017 2018 May-19 2019 2020 2021 2022 2023 2024
GJP GMP IPD GCG Gulf Solar Vietnam Oman Total
76%
18%
6%
IPP2
SPP
Renewables
IPP2
SPP
Renewables
1
1
1 1
1
1
1 1
-
9
2. Project Updates
-
10
GVTP
COD 16 May 2017
GNC
COD 1 Mar 2018
GBL
COD 1 Sep 2018
GBP
COD 1 Nov 2018
GNLL2
COD 1 Jan 2019
GTS4
COD 1 Jan 2018
GNPM
COD 1 Mar 2019
GNRV1
COD 1 May 2019
GNRV2
SCOD Jul 2019
GTS1
COD 8 Jul 2017
GTS2
COD 1 Sep 2017
GTS3
COD 1 Nov 2017
Installed
capacity
Electricity: 1,563.4 MW
Steam: 225.0 TPH
Contracted
capacity
Electricity: 1,466.5 MW
Steam: 210.5 TPH
PPA: Signed with EGAT,
for 25 years
GSA: Signed with PTT
EPC:Signed with Toyo
Engineering
LTSA: Signed with SIEMENS
and GE
COD: 2017 – 2019
Project cost: 6,200 MB → 6,000 MB (managed to be under budget)
Overall status: • 11 projects in operation
• 1 project under
construction
✓ ✓ ✓ ✓
✓ ✓
COD
2017
COD
2018
COD
2019
Construction progress on track
98.3%
✓
✓
✓
✓
GMP – 12 SPPs (1,563 MW)
✓
✓
✓ ✓ ✓
As of May 2019
-
11
IPD – 2 IPPs (5,300 MW)
In operation
Under construction/
development
CHONBURI
RAYONG
Location: WHA Eastern Seaboard
Industrial Estate 1, Chonburi
Installed
capacity
2,650.0 MW
Contracted
capacity:
2,500.0 MW
Fuel type: Gas-fired
PPA Signed with EGAT
for 25 years
GSA Signed with PTT
EPC Signed with Mitsubishi,
MHPS and STEC
LTSA Signed with MHPS
SCOD: Unit 1-2: Mar and Oct 2021
Unit 3-4: Mar and Oct 2022
Project
cost:
51,000 MB → 50,000 MB (savings from FX hedging & IRS)
• Debt: 38,000 MB (D/E 3:1)
• Equity back-ended structure
Overall
status:
Under construction
26% completed
Location: Rojana Rayong 2
Industrial Park, Rayong
Installed
capacity
2,650.0 MW
Contracted
capacity:
2,500.0 MW
Fuel type: Gas-fired
PPA Signed with EGAT
for 25 years
GSA Signed with PTT
EPC Signed with Mitsubishi,
MHPS and STEC
LTSA Signed with MHPS
SCOD: Unit 1-2: 2023
Unit 3-4: 2024
Project cost: Approx. 51,000 MB
• Debt: 38,000 MB (D/E 3:1)
• Equity back-ended structure
Overall
status:
• Under development
• Financial close is
expected by Sep 2019
✓
✓
✓
✓
✓
✓
✓
✓
As of April 2019
-
12
GSRC’s project developments
Civil works progress as planned
-
13
Gulf Chana Green (25 MW)
(GCG)
SONGKHLA
Location: Songkhla, Thailand
Installed
capacity:
25.0 MW
Contracted
capacity:
20.6 MW
Fuel type Parawood
Tariff EP + Ft + Bt 1.3 adder for 7 years
after COD
PPA Signed with EGAT
EPC Signed with STEC
SCOD: Mar 2020
Project cost: Approx. 2,300 MB
Overall
status:Under construction
50% completed
✓
✓
As of April 2019
-
14
NGD projects (4,000,000 mmbtu/year)
Location: WHA Eastern Seaboard
Industrial Estate 2
Capacity: 2,000,000 mmbtu/year
Customers: 500,000 mmbtu/year
(Around 60% was secured under
10-year, long-term contracts)
GSA Signed with PTT (10 years)
COD: 1 Dec 2018
Project cost: Approx. 198 MB
Location: WHA Eastern Seaboard
Industrial Estate 4
Capacity: 2,000,000 mmbtu/year
Customers: 500,000 mmbtu/year
(Around 20% was secured under
10-year, long-term contracts)
GSA Signed with PTT (10 years)
SCOD: Jun 2019
Project cost: Approx. 234 MB
Overall
status:
Under construction
95% completed
✓
✓
✓
As of April 2019
-
15
New renewable investment in Vietnam
Project ProvinceFuel
type
Equity
interest
Gross
installed
capacity
(MW)
Equity
installed
capacity
(MW)
Approx.
project
cost
(US$m)
COD/SCOD
TTCIZ-01 Tay Ninh Solar 49% 69 34 65 6 Mar 2019
TTCIZ-02 Tay Ninh Solar 90% 50 45 50 19 Apr 2019
Mekong
Solar Farm
Ben Tre Solar 95%* 30 28 33 [2019-2020]
Mekong
Wind Farm
Ben Tre Offshore
wind
95%* 310 295 618 2021-2023
Total 460 402 766
Investment portfolio
One of the leading conglomerates in Vietnam,
operating various businesses, including energy and
industrial estates with an asset size of approx.
US$1.9 billion
Under construction/
developmentNote: *On April 25, 2019, GIH signed the Share Purchase Agreement and Shareholders Agreement to
increase its equity interest in Mekong Projects from 49% to 95% and the share transfer is expected to
be completed tentatively by the end of May 2019.
In operation
-
16
TTCIZ-01 and TTCIZ-02 (119 MW) reached COD
Location Tay Ninh, Vietnam
Installed
capacity
Approx. 69 MW
Shareholding - GULF (49%)
- TTC Group (51%)
Fuel type Solar
EPC Signed with JGC Vietnam
Offtaker Vietnam Electricity (EVN)
Tariff US9.35c./kWh
PPA Signed with EVN for 20 years
COD 6 Mar 2019
Project cost Approx. US$ 65 million
TTCIZ-01 TTCIZ-02
Location Tay Ninh, Vietnam
Installed
capacity
Approx. 50 MW
Shareholding - GULF (90%)
- TTC Group (10%)
Fuel type Solar
EPC Signed with JGC Vietnam
Offtaker Vietnam Electricity (EVN)
Tariff US9.35c./kWh
PPA Signed with EVN for 20 years
COD 19 Apr 2019
Project cost Approx. US$ 50 million
As of April 2019
In operation
-
17
Mekong Project in Vietnam (340 MW)
Location Ben Tre, Vietnam
Installed
capacity
Approx. 30 MW
Shareholding - GULF (95%)*
- TTC Group (5%)
Fuel type Solar
Offtaker Vietnam Electricity (EVN)
Tariff US[9.35c.]/kWh
SCOD [2019-2020]
Project cost Approx. US$ 33 million
Overall status Waiting for approval from
Ministry of Industry and
Trade of Vietnam
Mekong Solar Mekong Wind
Location Ben Tre, Vietnam
Installed
capacity
1st Phase: 30 MW
2nd Phase: 49 MW
3rd Phase: 231 MW
Total: 310 MW
Shareholding - GULF (95%)*
- TTC Group (5%)
Fuel type Offshore Wind
Offtaker Vietnam Electricity (EVN)
Tariff Increase from approx.
US7.8c./kWh to approx.
US9.8c./kWh
PPA 20 years
SCOD 1st Phase (30MW): 2021
2nd Phase (49 MW): 2021
3rd Phase (231 MW): 2022-2023
Project cost Approx. US$ 618 million
Overall
status
• Under EPC selection process
• Seeking for key licenses and
PPA
• Expect to sign EPC contract
by Jul 2019 and begin the
construction in Q3 2019
Note: *On April 25, 2019, Gulf entered into SHA and SPA to increase its equity interest
from 49% to 95%. The share transfer will be completed tentatively by May 2019. As of April 2019
Under construction/
development
In operation
-
18
Newly awarded gas-fired project in Oman (326 MW)
DUQM
POWER
PROJECT Desalinated
water
Electricity
55%45% 50%50%
Duqm Independent Power
& Water Project (DIPWP)
Location Duqm Special Economic Zone, Oman
Installed
capacity
Power: approx. 326 MW
Water: approx. 1,667 m3/hour
Contracted
capacity
Power: approx. 208 MW
Water: approx. 1,250 m3/hour
Shareholding - GULF (45%)
- Oman Oil (55%)
Fuel type Gas
Gas turbine SIEMENS SGT800
EPC Signed with consortium of
4 companies:
1) Alghanim International General
Trading & Contracting Co. W.L.L.
2) Cobra Instalaciones y Servicios
S.A.
3) Sojitz Corporation
4) Tecnicas De Desalinizacion De
Aguas
Offtaker Duqm Refinery
PPA Signed with Duqm refinery for
25 years (+5 years renewal)
SCOD 2020-2022
Project cost Approx. US$ 483 million
Overall status Under construction
18% completed
Oman Oil Kuwait Petroleum
Capacity: 230,000 bbl/day
Project cost: US$7,000m
(Designed to have
extra 2 units to
standby in case of
emergency (n-2).
Availability
payment will be
paid based on
installed capacity.)
Under construction/
development
As of April 2019
In operation
-
19
3. Operating performance
-
20
Projects in operation
40%Ownership
70%Ownership
4,237 MW 1,435 out of 1,563 MW
GKP1
GKP2
GTLC
GNNK
GNLL
GCRN
GNK2
GNS
GUT
100%
100%
100%
100%
100%
75%
100%
114 MW
114 MW
114 MW
114 MW
123 MW
119 MW
133 MW
100%
100%
1,653 MW
GVTP
GTS1
GTS2
GTS3
75%
75%
75%
75%
137 MW
134 MW
134 MW
130 MW
7 SPPs 2 IPPs 11 SPPs out of 12 SPPs
COD: 2013
COD: 2014-15
COD: 2017
1,752 MW
GTS4
GNC
GBL
GBP
75%
100%
75%
75%
130 MW
126 MW
127 MW
127 MW
COD: 2018
GNLL275%
127 MW
COD: 2019
GNPM100%
135 MW
GNRV1
135 MW
100%
-
21
GJP – 2 IPPs (3,406 MW)
6,989 7,061
6,963
Average
Average heat rate (BTU/kWh)
2017 2018 3M'19
2 IPPs Key customer
94.697.296.2 97.3
99.8 99.7
GNS GUT
Availability (%)
2017 2018 3M'19
COD: Unit 1 Jun 2014
Unit 2 Dec 2014
GNS GUT
COD: Unit 1 Jun 2015
Unit 2 Dec 2015
100% of contracted capacity
-
22
GJP – 7 SPPs (831 MW)
98 9799 99 99 99 9997 97 98 97 98 97 99
100 100 99 99 99 100 97
GKP1 GKP2 GTLC GNNK GNLL GCRN GNK2
Availability (%)
2017 2018 3M'19
7,700 7,685 7,677
Average heat rate (BTU/kWh)
2017 2018 3M'19
COD: Jan 2013 COD: Feb 2013 COD: Mar 2013 COD: Apr 2013
COD: May 2013 COD: Jul 2013
GKP1 GKP2 GTLC GNNK
GNLL
COD: Oct 2013
7 SPPs Key customers
GCRN GNK2
90 MW of each project is dispatched to
The rest is supplied to industrial users
-
23
GMP – 10 out of 12 SPPs (1,307 MW)
COD: May 2017 COD: Jul 2017 COD: Sep 2017 COD: Nov 2017
COD: Jan 2018
GVTP GTS1 GTS2 GTS3
COD: Mar 2018
10 out of 12 SPPs Key customers
GTS4 GNC
90 MW of each project is dispatched to
The rest is supplied to industrial users
COD: Sep 2018GBL
96
98 100 9898 97 98 97 98 98100 100100 100 99 100 100 99 100
98100 100
GVTP GTS1 GTS2 GTS3 GTS4 GNC GBL GBP GNLL2 GNPM
Availability (%)
2017 2018 3M'19
7,479
7,415 7,411
Average heat rate (BTU/kWh)
2017 2018 3M'19
COD: Nov 2018GBP
COD: Jan 2019GNLL2
COD: Mar 2019GNPM
-
24
A B C
A (3 days)
CI (10 days)
CI (1 days)
SIEMENS
MHPS
GE
B (18 days)
TI (18 days)
HGPI (18 days)
C (22 days)
MI (35 days)
MO (22 days)
Maintenance Schedule 2018 - 2019
Group Project Type COD
2018 2019
Quarter
1
Quarter
2
Quarter
3
Quarter
4
Quarter
1
Quarter
2
Quarter
3
Quarter
4
GJP
GKP1 SPP
2013
GKP2 SPP
GTLC SPP
GNNK SPP
GNLL SPP
GCRN SPP
GNK2 SPP
GNS IPP 2014
GUT IPP 2015
GMP
GVTP SPP
2017GTS1 SPP
GTS2 SPP
GTS3 SPP
GTS4 SPP 2018
A
A
A
A
A
A
A
B
A
A
A
A
C
C
C
C
A C
CA
A
A
A
A
A B
A
A
As of April 2019
-
25
SPP heat rate improvement, to be fully completed in 2019
• Heat rate will improve around 150 BTU/kWh/plant
• Gross profit will improve around 50 MB/year/SPP
• Gross profit of the total 14 plants will improve approx.
700 MB/year (Gulf’s portion 350 MB/year)
TIE-LINE CONCEPT
Plant A Plant B
Plant A Plant B
67% 67%67% 67%
100% 100%100%
Turbine Turbine Turbine Turbine
Turbine Turbine Turbine Turbine
Off Peak
GJP: 7 SPPs
Stand-alone 3 SPPs 7,750 BTU/kWh
Tie-line concept 4 SPPs 7,600 BTU/kWh
GMP: 12 SPPs
Stand-alone 2 SPPs 7,450 BTU/kWh
Tie-line concept 10 SPPs 7,300 BTU/kWh
-
26
Tie-line 14 SPPs (7 pairs) from the total 19 SPPs
2013 2014 2015 2016 2017 2018 2019
GKP1 & GKP2Nong Kae Industrial Estate
Saraburi
GTS1 & GTS2Eastern Seaboard
Industrial Estate
Rayong
GTS3 & GTS4WHA Eastern Seaboard
Industrial Estate
Rayong
GBL & GBPHi-Tech
Industrial Estate
Ayutthaya
GNLL & GNLL2WHA Rayong
Industrial Land
Rayong
GNK2 & GNPMWHA Rayong
Industrial Land
Saraburi
GNRV1 & GNRV2Suranari Industrial
Estate
Nakhon
Ratchasima
-
27
4. Financial Highlights
-
28
3,361
5,193
6,477 75
75
77
1,300
437
895
48
51
47
4,784
5,756
7,496
Q1'18 Q4'18 Q1'19
Sales revenue Management fee Share of profit
Other incomes Total revenues
Total revenues
SPPs commencing their operations in 2017–Q1’19 boosted up revenues
Total Revenues
Unit: Million Baht
Note: 1/ Consolidated sales revenue include electricity and steam sales from SPPs under GMP and electricity sales from VSPPs under Gulf Solar
2/ Consolidated other incomes include dividend income, interest income and other income
57% YoY
Total revenues in Q1’19 was 7,496 MB
• QoQ: +30% from COD of GNLL2 and GNPM in
Q1’19 and the overall increase in electricity and
steam sold.
• YoY: +57% mainly from 10 SPPs under GMP
group compared to 6 SPPs in Q1’18. Volume of
electricity and steam sold also increased.
-
29
Share of profit from GJP (40%)
Share of profit from GJP
Unit: Million Baht
GJP’s share of profit (excl. FX) in Q1’19 was 655 MB
• QoQ: +45% from lower maintenance days (2 power
plants in Q1’19 vs. 4 power plants in Q4’18)
• YoY: -6% from GNS’s lower AP rate and 19% surge
in gas price while Ft rates increased by only 4.3
satang
GJP’s share of profit (incl. FX) in Q1’19 was 895 MB
• +99% QoQ and -31% YoY mainly from the FX rates
fluctuations
695
452
655
605
-2
240
1,300
450
895
Q1'18 Q4'18 Q1'19
Share of profit (excluding FX) FX gain/loss
Share of profit from GJP (excl. FX) improved QoQ but softened YoY
Total share of profit
-31% YoY
-6% YoY
(Gas price was 237.29 baht/MMBTU, 279.00 baht/MMBTU and
282.02 baht/MMBTU in Q1’18, Q2’18 and Q1’19, respectively)
-
30
Net profit / Core profit
Net profit / Core profit
Core profit continued to increase aligned with increasing number of power projects
Unit: Million Baht
756 522
857
347
34
196
605
-2
240
1,708
553
1,293
Q1'18 Q4'18 Q1'19
Core profit GMP Gain on FX
GJP Gain on FX Net profit
13% YoY
(Baht 31.41/ USD, Baht 32.61/ USD and Baht 31.98/ USD in
Q1’18, Q4’18 and Q1’19, respectively)
Core profit in Q1’19 was 857 MB
• QoQ: +64% from greater contribution from GMP
(10 SPPs in Q1’19 vs. 8 SPPs in Q4’18) and power
plants’ lower maintenance days
• YoY: +13% due mainly to:
• Better performance from GMP (10 SPPs compared
to 6 SPPs in Q1’18). Also, profit margin improved
from increasing demand from both existing and
new IUs.
• However, share profit from GJP dropped by 6%.
Net profit in Q1’19 was 1,293 MB
• +134% QoQ and -24% YoY from the movement in
unrealized FX gain.
-24% YoY
-
31
31,556 31,556 31,556
1,935 3,924 5,217 1,074
1,057 907 4,783 8,251 9,161
39,348
44,788 46,840
31-Dec-17 31-Dec-18 31-Mar-19
Total equity
Balance sheet
Balance sheet
Unit: Million Baht
4,374 9,349 8,357
56,930 69,532
75,172
61,304
78,880 83,528
31-Dec-17 31-Dec-18 31-Mar-19
Total liabilities
9,267 15,552 15,740
50,547
67,664 73,362
20,439
21,659 22,130
20,399
18,794 19,137
100,652
123,669 130,369
31-Dec-17 31-Dec-18 31-Mar-19
Total assets
D/E ratio as of Mar 31, 2019 was at 1.78x
Total assets was 130,369 MB,
+5% from the development and
construction of SPPs under GMP
and GSRC, TTCIZ-02 and GCG
Total liabilities was 83,528 MB,
+6% mostly from long-term loan
drawdowns for the construction of
SPPs under GMP and GSRC
Total equity was 46,840 MB,
+5% from the increase in R/E
and non-controlling interests
31-Dec-17 31-Dec-18 31-Mar-19
D/E 1.56x 1.76x 1.78x
ID/E 1.45x 1.55x 1.60x
ND/E 1.04x 1.34x 1.37x
Cash, cash equivalents and deposits
used as collateral
Investments in an associate and joint
ventures
Property, plant and equipment
Other assets
Interest-bearing debts
Other liabilities
Non-controlling interests
Other components of equity attributable
to owners of the parent
Paid-up capital and share premium
Unappropriated retained earnings
5%
6%
5%
-
32
Debts outstanding
As of March 31, 2019
40% 70% 75% 100%
7,500 MB in
debentures
70%
56%
44%
74%
26%1,015 MUSD
41,162MB
447 MUSD
39,777 MB
83%
17%
63 MUSD
10,050 MB
100%22 MB
100%1,274 MB
Total
73,627 MBTotal
54,083 MB
Total
12,066 MB
• All of the power projects in Thailand have long term loans of 20 - 23 years (vs. PPA term of 25 years).
• To mitigate interest rate fluctuation, the company entered into interest rate swaps to swap interest rate from floating
rate into fixed rate for 18-20 years.
-
33
Bond issuance in January 2019
Indicative terms
Issuer Gulf Energy Development Public Company Limited
Objective • To repurchase the existing debenture valued 6,000 million baht• To fund new investments
Type of security Thai Baht unsecured and unsubordinated debentures
Issue size 7,500 million baht
Placement methodology
Private Placement to institutional and high net worth investors
Credit rating Company rating “A” and issue rating “A-” by TRIS Rating Company Limited
Issue date January 25, 2019
Joint Lead Arrangers
• Bangkok Bank Public Company Limited
• Kasikornbank Public Company Limited
• The Siam Commercial Bank Public Company Limited
Co-Manager • Standard Chartered Bank (Thai) Public Company
Details of the allotment
Debenture Term Interest rate Amount
Debenture tranche 1 3 years 2.73% 2,000 million baht
Debenture tranche 2 5 years 3.28% 2,500 million baht
Debenture tranche 3 7 years 3.61% 2,000 million baht
Debenture tranche 4 10 years 3.85% 1,000 million baht
Total 5.7 years 3.30% 7,500 million baht
-
34
Dividend payment
Shareholders approved dividend payment of Bt 1.2 per share
Note: The Company has 2,133.3 million shares outstanding.
Unit: Million baht 2017 2018
Dividend (Baht per share) 0.40 1.20
Dividend payment 853 2,560
Separate net profit for the year 1,730 3,245
Dividend payout 49.3% 78.9%
Dividend payout• Gulf has a dividend payment policy to
pay out at least 30.0% of the Company’s
separate net profit (after taxes), subject to
meeting the relevant legal reserve
requirement and contractual obligations.
• On April 24, 2019, the Company’s
shareholders approved dividend payment of
1.20 baht per share, totaling 2,560 million
baht, representing 78.9% of the separate
net profit (after tax).
Key dates
Ex-dividend date : May 2, 2019
Dividend payment date : May 21, 2019
-
Thank You