handling of concrete

89
KAS-2012 1 CONCRETE HANDLING IN THE FIELD By K.Shah B.E.(Civil Engg) NIT Rourkela,India M.Sc. (Environment), University of Leeds, UK Ex-GM(Civil & Environment) – MNC Currently Guest faculty-College of Technology & Engineering

Upload: kezar-ali-shah

Post on 23-Jan-2018

9.773 views

Category:

Engineering


0 download

TRANSCRIPT

Page 1: Handling of Concrete

KAS-2012 1

CONCRETE HANDLING IN THE

FIELD

By K.Shah B.E.(Civil Engg) NIT Rourkela,India

M.Sc. (Environment), University of Leeds, UK

Ex-GM(Civil & Environment) – MNC

Currently Guest faculty-College of Technology &

Engineering

Page 2: Handling of Concrete

KAS-2012 2

Stages of producing concrete.

(1) Batching

(2) Mixing

(3) Transportation

(4) Placing

(5) Compacting

(6) Curing

(7) Finishing

Page 3: Handling of Concrete

KAS-2012 3

(1) Batching

(a) Volume batching

(b) weight Baching

Page 4: Handling of Concrete

KAS-2012 4

Volume batching

Volume batching is not good method

Moist sand in loose condition weights less

than the same volume of dry sand.

Practiced for small work.

For quality work ,weigh batching is

practiced.

Page 5: Handling of Concrete

KAS-2012 5

VOLUME BATCH

Gauge box

Various gauge boxes of different volumes are

used.

Length Width Depth Volume

33.3 cm 30 cm 20 cm 20 liters

33.3 cm 30 cm 25 cm 25 liters

Grade Cement- kg Sand -lts Coarse

Aggregate

lts

1:11/2:3 (M

200)

50 35 70

1:2:4 (M

150)

50 70 140

1:3:6 (M100) 50 105 210

Page 6: Handling of Concrete

KAS-2012 6

Weigh Batch Machine

Page 7: Handling of Concrete

KAS-2012 7

Weigh batching

Weigh batching is correct method

Facilitates accuracy, flexibility & simplicity

Different batching machine are available :

(a) manual machines & (b) Automatic machines

Manual machine :

Has two buckets

Buckets mounted on common spindle about which they rotate.

One is loaded while other is discharged in mixer.

Spring loaded dials indicate the weight.

Page 8: Handling of Concrete

KAS-2012 8

Automatic weigh batch

For large works

Over head hopper and discharges into

mixer.

Useful in ready mix concrete plant

Recorders for weight

Calibration is required from time to time.

Page 9: Handling of Concrete

KAS-2012 9

(2) MIXING

Mixing of cement,sand aggregates should

ensure that:

The mass is homogeneous

Uniform in color

consistent

Page 10: Handling of Concrete

KAS-2012 10

MIXING METHODS :

(1) Hand mixing

(2) Machine mixing

Page 11: Handling of Concrete

KAS-2012 11

Hand mixing

Practiced for small scale work (small house, repairing of house etc)

10 % extra cement is added to compensate inferior concrete produced by this method.

Spread fine & coarse aggregate in alternate layer

Spread cement over it

Mix with shovel till uniform color is achieved

Water is sprinkled over it

Page 12: Handling of Concrete

KAS-2012 12

Machine mixing

Medium & large scale work use machine mixing

Mixing is efficient, economical & produce quality concrete.

Type of mixer:

(a) Batch mixer : batch by batch with time interval

(b) Continuous mixer: continuously mixed & discharged (in dam construction)

Page 13: Handling of Concrete

KAS-2012 13

CONCRETE MIXER

(1) Pan type

(2) drum Type:

(a) tilting

(b) Non –tilting

(c) Reversing

Page 14: Handling of Concrete

KAS-2012 14

PAN MIXER

Page 15: Handling of Concrete

KAS-2012 15

PAN MIXER

A forced movement pan mixer has blades

that are fixed to an assembly that agitates

the concrete throughout the pan as the

vertical shaft rotates.

Page 16: Handling of Concrete

KAS-2012 16

DRUM MIXER

As per IS: 1791-1985 mixers are

designated by number which shows

capacity (liters) of batch:

a) Tilting : 85 T, 100T, 140 T, 200T

b) Non tilting : 200 NT,280 NT, 375 NT, 500

NT, 1000 R

c) Reversing : 200 R, 280 R, 375 R,500 R,

1000 R

T= Tilting, NT =non tilting, R=Reversing

Page 17: Handling of Concrete

KAS-2012 17

TILTING MIXER

Page 18: Handling of Concrete

KAS-2012 18

TILTING MIXER

Internal blades lift and tumble the

ingredients onto itself.

Two primary types exist:

horizontal (one end has and opening for

charging and a different end for

discharging)

single drum (materials are charged and

discharged through a single opening).

Page 19: Handling of Concrete

KAS-2012 19

NON TILTING MIXER

Page 20: Handling of Concrete

KAS-2012 20

NON TILTING MIXER

Single drum rotating about a horizontal

axis.

Fixed blades work the concrete towards

the discharge end of the mixer, in order to

provide a rapid rate of discharge.

Page 21: Handling of Concrete

KAS-2012 21

REVERSING MIXER

Page 22: Handling of Concrete

KAS-2012 22

REVERSING MIXER

The entire drum rotates around its axis as materials are loaded through a charge chute at one end of the drum and exit through a discharge chute at the opposite end of the drum.

Mixing blades are mounted on the inside surface of the drum and as the drum rotates the blades mix by lifting and dropping the materials during each rotation.

Once the materials are sufficiently mixed the rotation of the drum is reversed and the blade arrangement pushes the concrete through to the discharge end of the mixer.

Page 23: Handling of Concrete

KAS-2012 23

Sequence of charging drum

First half quantity of coarse aggregate is

placed in skip

Over it half quantity of sand

On that full quantity of cement

Over it balance quantity of coarse & fine

aggregates is place.

This prevents spillage of cement in air

while discharging in drum

Page 24: Handling of Concrete

KAS-2012 24

25 % Water is placed in drum and then

mix from skip is discharged in the drum

This prevents sticking of cement on blades

75 water is immediately poured after

placing mix material (cement sand etc) in

drum.

Page 25: Handling of Concrete

KAS-2012 25

Mixing time

In small machine, mixing time varies

between 1-2 minutes

In Ready Mix Cement mixer – 15-30

seconds

RPM of drum : 15-20

Compressive strength of concrete

increases with increase in mixing time but

after 2 minutes increase in compressive

strength is not significant.

Page 26: Handling of Concrete

KAS-2012 26

If concrete is not used after mixing it may

set

But when concrete is agitated on time to

time in drum setting time rule does not

follow.

Page 27: Handling of Concrete

KAS-2012 27

Retempering of concrete :

Some time concrete from RMC plant is not delivered to site due to traffic congestion

Concrete becomes stiff and becomes unworkable

Site engineers can reject the concrete if delay is more

If it can be of used then small volume of water is added and again agitated in the drum. This is called RETEMPERING OF CONCRETE.

Page 28: Handling of Concrete

KAS-2012 28

MANUFACTURING OF

CONCRETE

With same material if care is not taken,

resulting concrete will be bad concrete

What are good rules to make good quality

concrete.

Page 29: Handling of Concrete

KAS-2012 29

TRANSPORTATION OF CONCRETE

Precaution in concrete transportation:

Homogeneity of conc. Mass is maintained

Movement of hand trolly or truck on rough

road surface makes vibrations

This results in deposition of heavy

aggregates at bottom of truck

Water & cement slurry comes on top.

Page 30: Handling of Concrete

KAS-2012 30

METHODS OF TRANSPORTATION

1. Mortar Pan

2. Wheel barrow

3. Truck Mixer & dumpers

4. Crane, Bucket & rope way

5. Belt conveyors

6. Chutes

7. Skip & hoist

8. Transit Mixer

9. Pump & pipeline

10. Helicopter

Page 31: Handling of Concrete

KAS-2012 31

MORTAR PAN

Common method in India

More labour required

Segregation of concrete is less

Greater surface area of concrete is

exposed to sun, concrete dries.

Page 32: Handling of Concrete

KAS-2012 32

WHEEL BARROW

When transportation of concrete is at

ground level.

Movement of wheel on rough road

surface, segregates concrete.

Some wheel barrows have pneumatic

wheel to reduce vibration

Page 33: Handling of Concrete

KAS-2012 33

CRANE

Used for transporting concrete above

ground level.

For high rise buildings.

Cranes are fast

Can move horizontally & vertically

Concrete in skip discharge from bottom

In bucket concrete is discharged by tilting.

Page 34: Handling of Concrete

KAS-2012 34

BUCKET & ROPEWAY

Use for construction in:

Valley

Bridge pier in river

Dam

Advantage:

Concrete is not exposed to sun or air & no

loss of water.

Page 35: Handling of Concrete

KAS-2012 35

Truck Mixer & dumpers

Used for large concrete works.

Can travel any part of site.

Dumpers - 2-3 M3 Capacity

Trucks – 4 M3 Capacity

Bottom surface of truck is kept wet

Top of truck is covered to prevent

evaporation

Page 36: Handling of Concrete

KAS-2012 36

BELT CONVEYORS

Limited use in construction

Advantages:

Can transport large volume

Very quick

Can go where access is limited

Disadvantages :

On steep slope concrete segregates.

Exposed to sun for long time.

Page 37: Handling of Concrete

KAS-2012 37

CHUTE

For transporting from ground level to lower

level. (basement etc).

Used where labour can not reach due to

less space in trench etc.

Made of metal

Slope should not be < 1 vertical : 2.5

horizontal.

Page 38: Handling of Concrete

KAS-2012 38

SKIP & HOIST

Labour can go upto 3rd or 4th floors.

So skip is used for transport vertically up

(in multistory building).

Skip travels on vertical rail.

Skip can discharge manually or

automatically.

Page 39: Handling of Concrete

KAS-2012 39

TRANSIT MIXER

Page 40: Handling of Concrete

KAS-2012 40

TRANSIT MIXER

Used for long distance travel in RMC plant.

Concrete is continuously agitated in truck drum

(2 – 6 rpm).

Also transported mix in dry condition and water

is added on reaching the destination.

Wet Mix in truck must reach site in 1- 1.5 hours.

Pumps are also fitted on truck mixer to

discharge concrete.

Page 41: Handling of Concrete

KAS-2012 41

PUMPS & PIPELINE

Most popular method

Reliable & good quality pumps are used.

Mostly operated by diesel.

Concrete is placed in collecting hopper.

Rotating blades in hopper pushes concrete towards pipe.

Vacume in hose pipe (600 mm Hg)

Rotating rollers in pump chambers squeeze the concrete in pipe and flow of concrete is started.

Concrete is discharged from other end of hose pipe.

Concrete can be pumped upto 400 m height and 2000 m distance.

Page 42: Handling of Concrete

KAS-2012 42

SECTION OF PUMP

Page 43: Handling of Concrete

KAS-2012 43

PIPELINE

Pipeline should :

Have correct diameter as per pump

pressure. (generally 125 mm)

Have sufficient thickness

Good couplings

Poor pipeline can cause blockage.

Page 44: Handling of Concrete

KAS-2012 44

PIPELINE

Thumb rule : For 30 M3 /hr concrete and

200 m length, dia should be 100 mm.

Length > 500 m then dia = 150 mm.

Dia = 3 to 4 times the size of aggregate

Leaky pipe & coupling result in escape of

water /air & finally block the concrete.

Vertical pipe should good otherwise

difficult to change at height.

Pump is kept at distance from building

about 15 % of vertical length.

Page 45: Handling of Concrete

KAS-2012 45

PUMPABLE CONCRETE

Concrete which can be pushed through a pipeline is

called pumpable concrete.

Friction between pipe wall and concrete is less.

Concrete flows in the form of plug which is separated

from pipe wall by a thin layer of lubricating cement paste.

Flow resistant must be < pump pressure.

If the concrete is more wet then water comes out of mix

which makes more resistance to flow.

Stiff and also very wet concrete is not pumpable.

Page 46: Handling of Concrete

KAS-2012 46

Design of pumpable concrete

Concrete Mix is so designed that all material remain

together.

Mix must make redial movement of grout to maintain

lubricating paste.

Mix should be deformed at bends

Cement & fine particles (0.25 mm size) are important for

good flow.

350 to 400 Kg/ M3 of fine particles are necessary for

flow.

Slump of pumpable concrete is above 75 mm.

Page 47: Handling of Concrete

KAS-2012 47

PROBLEMS IN PUMPING

Blockage in pipe

Pipe should be cleaned after each day

operation

Blockage can be cleaned by forward-

backward pumping.

Tapping pipe with hammer

Clean pipe with rod or sponge ball pushed

by compressed air.

Page 48: Handling of Concrete

KAS-2012 48

PLACING CONCRETE

Must be placed in systematic manner.

Can be placed with following methods:

Within earth mould : Foundation

In timber plank formwork : Road, airport

slab.

Steel shuttering : Dam

Under water

Page 49: Handling of Concrete

KAS-2012 49

Concrete in Foundation

In foundation, ground is made wet.

Plastic sheet are laid between ground & slab

Concrete is dumped not poured.

No heap and dragging

Placed in layers of 35 – 40 cm in mass concrete

Avoid cold joints between 2 layers

Surface of previous layer is cleaned with wire brush

Sometime, cement slurry is placed on old surface

Top of previous layer kept rough for good bond.

Page 50: Handling of Concrete

KAS-2012 50

Concrete on Road, airport, floor slabs

Placed in alternate bays (allow shrinkage)

with contraction joints :

contraction joints

Bays

Page 51: Handling of Concrete

KAS-2012 51

Concrete in Beams & Column

Reinforcement correctly placed.

Correct cover required

Joints of shuttering to be plugged.

Mould releasing agent inside formwork

Page 52: Handling of Concrete

KAS-2012 52

STRIPPING TIME Form work should not removed until good

strength has come.

Type of form work Time

Vertical wall, columns 16-24 hrs

Soffit of slab (Prop should be refixed immediately) 3 days

Soffit of beam (Prop should be refixed immediately) 7 days

Props to slab Span < 4.5 m 7 days

Props to slab Span > 4.5 m 14 days

Props of beam (Span < 6 m) 14 days

Props of beam (Span > 6 m) 21 days

Page 53: Handling of Concrete

KAS-2012 53

UNDER WATER CONCRETE

Page 54: Handling of Concrete

KAS-2012 54

UNDER WATER CONCRETE

Tremie (means hopper) is used.

Funnel on top

Pipe of 200 mm size

Pipe bottom is plugged

Fill pipe with concrete

Lift pipe or jerk to release the plug

Keep bottom of pipe inside concrete

Page 55: Handling of Concrete

KAS-2012 55

Underwater Concrete

No compaction required as hydrostatic pr

of water compacts concrete.

Concrete of 0.3 W/C ratio can be placed

with Tremie.

Used for Pile or well foundation

Page 56: Handling of Concrete

KAS-2012 56

SLIP FORM TECHNIQUE

In this method, concrete is continuously placed, compacted & form work is pulled up for next layer of concrete.

Vertical slip form for Tall structure like silo, chimney

Horizontal slip form paver machine (HSFP) for road construction.

Concrete is dumped in front of HSFP machine by dumpers.

Compaction by vibrator installed inside HSFP machines.

Finishing of surface by HSF paver.

Operation of road alignment, gradient, curve are controlled by Computerized Laser Control system.

Speed of construction is 1 mt /min.

1 km of concrete road of 3.75 mt width is built in one day (16 hrs work).

Mumbai-Pune Expressway was constructed by this machine.

Page 57: Handling of Concrete

KAS-2012 57

VERTICAL SLIP FORM

Page 58: Handling of Concrete

KAS-2012 58

HORIZONTAL SLIP FORM ROAD PAVER

Page 59: Handling of Concrete

KAS-2012 59

COMPACTION OF CONCRETE

Compaction is a process of expelling the entrapped air inside concrete mass.

During mixing, transporting & placing the concrete, air gets trapped in concrete mass.

If this air is not removed, concrete will not get strength.

5 % of air voids reduces strength by 30 %

10 % of air voids reduces strength by 50 %

Durability of concrete is also reduces with air voids.

Insufficient compaction increases permeability of concrete.

Results in entry of aggressive chemicals in solution.

Chemicals attack concrete & reinforcement and life of concrete is reduced.

Page 60: Handling of Concrete

KAS-2012 60

METHODS OF COMPACTION

1. Hand compaction

2. Compaction by vibration

3. Compaction by pressure &

jolting

4. Compaction by spinning

Page 61: Handling of Concrete

KAS-2012 61

(2) COMPACTION BY VIBRATION

a) Internal Vibrator

b) Formwork Vibrator

c) Table Vibrator

d) Platform Vibrator

e) Surface Vibrator

Page 62: Handling of Concrete

KAS-2012 62

(1) HAND COMPACTION

Hand Rodding

Poking inside concrete with 1-2 mt long steel rod

Ramming

Unreinforced foundation & ground floor work

Tamping

Wooden beam is used to beat concrete (low thickness slab, road slab)

Page 63: Handling of Concrete

KAS-2012 63

COMPACTION BY VIBRATION

In hand compaction w/c ratio is more so

we get less strength in concrete.

In mechanical vibrator w/c can be kept low

so we get good strength.

Page 64: Handling of Concrete

KAS-2012 64

INTERNAL VIBRATOR

Page 65: Handling of Concrete

KAS-2012 65

(a) INTERNAL VIBRATOR

Most common in use

Called, Needle Vibrator or Immersion vibrator or Poker vibrator.

Consists : electrical/diesel power supply, Needle and shaft.

Frequency of vibrations can be 12000 cycles vibration per minute.

Needle diameter 20 to 75 mm

Length 25 to 90 cm.

Portable.

Page 66: Handling of Concrete

KAS-2012 66

FORMWORK VIBRATOR

Used for columns, walls, precast slab

Vibrator is clamped to formwork

Vibration is given to formwork

Vibration is transferred from formwork to

concrete

Useful in thin wall where reinforcement

obstruct the needle type vibrator.

Efficiency is lower then needle vibrator

Page 67: Handling of Concrete

KAS-2012 67

TABLE VIBRATOR

Vibrator is clamped to table

Used for concrete test cubes

Cubes are kept on table to get vibrations

Also used for small prefabricated slab

Page 68: Handling of Concrete

KAS-2012 68

TABLE VIBRATOR

Page 69: Handling of Concrete

KAS-2012 69

PLATFORM VIBRATOR

Similar to table vibrator but of large size

Used for long concrete electrical pole,

railway sleeper,prefabricated roofing

element

Page 70: Handling of Concrete

KAS-2012 70

PLATEFORM VIBRATOR

Page 71: Handling of Concrete

KAS-2012 71

SURFACE VIBRATOR

Known as Screed Board Vibrator

Used for thin roof slab where needle

vibrator can not be used

Not effective if slab thickness is more then

15 cm.

Page 72: Handling of Concrete

KAS-2012 72

SURFACE VIBRATOR

Page 73: Handling of Concrete

KAS-2012 73

COMPACTION BY PRESSURE & JOLTING

Used for hollow blocks, solid concrete

blocks

Stiff concrete is vibrated, pressed & given

jolts

Stiff concrete is compacted to get dense

form & good strength is achived.

Page 74: Handling of Concrete

KAS-2012 74

VIBRATION BY SPINNING

New method

Used for concrete pipes

Concrete when spun at high speed gets

compaction by centrifugal force

Page 75: Handling of Concrete

KAS-2012 75

VIBRATORY ROLLER

Road rollers has vibrating system

Roller while moving on raod slab gives

vibrations

Used for Lean concrete (M10) for road

base

Page 76: Handling of Concrete

KAS-2012 76

ROLLER VIBRATOR

Page 77: Handling of Concrete

KAS-2012 77

PRECAUTIONS IN VIBRATING CONCRETE

Vibrator gets damaged if comes in contact with hard object (Formwork, hard concrete)

Switch on when needle is inside fresh concrete mass

Should conform to IS 2505-1963

Degree of compaction can be recognized from rising air bubbles & formation of thin film on top

Page 78: Handling of Concrete

KAS-2012 78

HYDRATION OF CEMENT

Cement is made by Cao, SiO2, Al2O3, Fe2O3, MgO, K2O,

SO3

After burning in Kiln following products are made:

3Cao. SiO2 (C3S) - Tri calcium silicate

2Cao. SiO2(C2S) – Di cacium silicate

3Cao. Al2O3 (C3A) – Tri cacium aluminate

4Cao. Al2O3. Fe2O3(C3AF) -Tricalcium alumino ferrite.

On addition of water in cement reaction of C3S, C2S, C3A

& C3AF liberate heat. Heat is suside by addition of water.

Page 79: Handling of Concrete

KAS-2012 79

CURING OF CONCRETE

Curing is defined as “ making satisfactory moisture

content & favourable temperature” in concrete after

placing the concrete. So that hydration may continue

until the strength is developed.

Curing is required immediately after placing concrete.

During hydration, heat of hydration is released.

Page 80: Handling of Concrete

KAS-2012 80

CURING OF CONCRETE

Concrete delivers its strength by the hydration of cement particles.

Hydration is continuous & long time process.

Rate of hydration is fast immediately after making the concrete

Theoretically 0.23 w/c ratio required for hydration

0.15 w/c ratio required for filling the voids in gel.

Total 0.38 w/c ratio is optimum

In field condition, water evaporates & available water quantity reduced for hydration

Extra water is given by curing

Page 81: Handling of Concrete

KAS-2012 81

METHODS OF CURING

a) Water curing

b) Membrane curing

c) Application of heat

d) Other methods

Page 82: Handling of Concrete

KAS-2012 82

WATER CURING

a) Immersion : Slab is kept in water tank

b) Ponding: Roof slab is filled with water

c) Spraying : water spary on concrete wall is

d) Wet covering : Wet gunny bags on wall

Page 83: Handling of Concrete

KAS-2012 83

MEMBRANE CURING

Concrete surface is covered by plastic membrane

It is used where water availability is less.

Plastic sheet reduces evaporation in concrete

Membrane is applied after 2 days of water curing

Page 84: Handling of Concrete

KAS-2012 84

APPLICATION OF HEAT

Spraying of steam on concrete provides heat & moisture.

Higher temperature accelerates hydration rate & strength

of concrete is attended

Early strength of structure is obtained

Steam application possible at precast factory only.

Precast prestressed concrete girders of bridge are cured

with steam

Fast construction of bridge

Page 85: Handling of Concrete

KAS-2012 85

HIGH PRESSURE STEAM CURING

Superheated steam at high pressure (8.5 kg/cm2) & high

temperature(175 deg C) is applied on concrete.

This process is called “Autoclaving”

28 days strength of concrete is achieved in one day

Concrete becomes sulphate resistant

Low shrinkage in concrete

Used in production of Cellular concrete products(

Siporex, Celcrete)

Page 86: Handling of Concrete

FINISHING OF CONCRETE

Finishing is last operation of concrete making.

Finishing of top surface is required in roads, airport

strip, home floor

Methods of Finishing:

a) Form work Finish

b) Surface Treatment

c) Applied Finishes

SHAH K.A. 86

Page 87: Handling of Concrete

FORMWORK FINISH

Concrete obeys the shape of formwork

Grooves & lining on formwork plate gives

makes grooves & lining on concrete

Prefabricated tiles can be made of any

design

Page 88: Handling of Concrete

SURFACE TREATMENT

Domestic floor should be smooth, wear resistant, crack

free.

Mix should have good proportion without excess “Matrix”

Exposed aggregate finish : Colored pebbles on top layer

of wall

Bush Hammering : Electrically operated Brush with teeth

when applied on concrete removes top cement layer,

exposes aggregates and makes shining aggregates.

KAS-2012 88

Page 89: Handling of Concrete

APPLIED FINISH

Rough cast finish : mixture of cement, sand, round

gravel is applied on wall

Non slip finish: Railway platform & walkway around

pool are given non slippery finish by mixing large size

sand particles in floor concrete.