herschel/planck january 13, 2005pacs iqr - sci-pt/332021 ggonzale: herschel pacs instrument...

11
January 13, 2005 PACS IQR - SCI-PT/33202 1 Herschel/Planck ggonzale: ggonzale: Herschel PACS Instrument Qualification Review Review Objectives and Organisation G.Crone/G.Pilbratt Herschel/Planck Project

Upload: darren-farmer

Post on 04-Jan-2016

216 views

Category:

Documents


2 download

TRANSCRIPT

Page 1: Herschel/Planck January 13, 2005PACS IQR - SCI-PT/332021 ggonzale: Herschel PACS Instrument Qualification Review Review Objectives and Organisation G.Crone/G.Pilbratt

January 13, 2005 PACS IQR - SCI-PT/33202 1

Herschel/Planckggonzale:ggonzale:

ggonzale:ggonzale:

Herschel PACS

Instrument Qualification Review

Review Objectives

and

Organisation

G.Crone/G.Pilbratt Herschel/Planck Project

Page 2: Herschel/Planck January 13, 2005PACS IQR - SCI-PT/332021 ggonzale: Herschel PACS Instrument Qualification Review Review Objectives and Organisation G.Crone/G.Pilbratt

January 13, 2005 PACS IQR - SCI-PT/33202 2

Herschel/Planck

Instruments Review Cycles in Perspective

1999 2000 2001 2002 2003 2004 2005 2006 2007

Instruments: ISVR IIDR IBDR IHDR IQR … IFAR

Spacecraft ITT SRR PDR CDR …

Phase B Phase C/D Launch

Page 3: Herschel/Planck January 13, 2005PACS IQR - SCI-PT/332021 ggonzale: Herschel PACS Instrument Qualification Review Review Objectives and Organisation G.Crone/G.Pilbratt

January 13, 2005 PACS IQR - SCI-PT/33202 3

Herschel/Planck

From Qualification to Flight Acceptance

• CQM at module (EQM) level : Delivery (DRB) Test readiness (TRR) Test review (PTR) 2005

After CQM System Campaign hold a Instrument Status Review

• FM at instrument level:ILT TRR ILTs ILT Test review prior to warm-up (PTR) 2005

To decide on need for further tests or to terminate & deliver

• FM at module (PLM) and system level:Delivery (DRB) Test readiness (TRR) Test review (PTR) 2006

In preparation of FAR Instrument Status Review

Page 4: Herschel/Planck January 13, 2005PACS IQR - SCI-PT/332021 ggonzale: Herschel PACS Instrument Qualification Review Review Objectives and Organisation G.Crone/G.Pilbratt

January 13, 2005 PACS IQR - SCI-PT/33202 4

Herschel/Planck

Herschel Status• Herschel Payload Module CDR completed in July and Space Segment

CDR completed in October with official close-out end 2004

• Herschel EQM - Ready for Herschel CQM Focal Plane Units.

• All Herschel Instruments: HIFI, PACS and SPIRE have successfully completed CQM Instrument Level Tests.

• All instruments delivered and in ASED OTN. (N.B. SPIRE to be returned 17th January)

• Instrument testing to commence April 2005

• Instrument FM program underway – Baseline delivery Nov 2005

Page 5: Herschel/Planck January 13, 2005PACS IQR - SCI-PT/332021 ggonzale: Herschel PACS Instrument Qualification Review Review Objectives and Organisation G.Crone/G.Pilbratt

January 13, 2005 PACS IQR - SCI-PT/33202 5

Herschel/Planck

Herschel EQM

Page 6: Herschel/Planck January 13, 2005PACS IQR - SCI-PT/332021 ggonzale: Herschel PACS Instrument Qualification Review Review Objectives and Organisation G.Crone/G.Pilbratt

January 13, 2005 PACS IQR - SCI-PT/33202 6

Herschel/Planck

Herschel PFM status• All units passed CDR, manufacturing well

underway

• Optical bench delivered

• HTT delivered, most cryo-components, instrumentation, MLI integrated

• HOT delivered instrumentation, cryo-

components and MLI mounted. Tank integrated on framework. Both fully integrated

• Cylinder thermal shields delivered-Others completed

• CVV cylinder delivered-Upper and lower bulk head imminent.

• Integration to be completed by May 2005; first cool-down with MTD instrument prior to shipment to ESTEC for STM campaign

Page 7: Herschel/Planck January 13, 2005PACS IQR - SCI-PT/332021 ggonzale: Herschel PACS Instrument Qualification Review Review Objectives and Organisation G.Crone/G.Pilbratt

January 13, 2005 PACS IQR - SCI-PT/33202 7

Herschel/Planck

Instrument Qualification Review - Objectives

Ref: IQR Proceedings - v2 Aug 26, 2004 - SCI-PT/27108

Confirmation of instrument CQM hardware/software qualification

Completion of instrument design verification

Assessment of performance and compliance with sci. reqs

Identification and confirmation of improvements for FM

Completion of OBSW design and demonstration of functionality

Confirmation of EGSE design and demonstration of functionality

Confirmation of instrument operability - User Manual

Page 8: Herschel/Planck January 13, 2005PACS IQR - SCI-PT/332021 ggonzale: Herschel PACS Instrument Qualification Review Review Objectives and Organisation G.Crone/G.Pilbratt

January 13, 2005 PACS IQR - SCI-PT/33202 8

Herschel/Planck

IQR - Proceedings

Data Package – complete delivery at K.O. [PACS] Documents as identified in SCI-PT/27108 Presentations as given during the K.O. meeting

Review of Data Package [Board] Discrepancies and open issues raised as RIDs RIDs issued up to one week before co-location

Answers to RIDs [PACS] Provided, discussed and resolved at co-location

Board Report = Result of the three items above [Board]

Page 9: Herschel/Planck January 13, 2005PACS IQR - SCI-PT/332021 ggonzale: Herschel PACS Instrument Qualification Review Review Objectives and Organisation G.Crone/G.Pilbratt

January 13, 2005 PACS IQR - SCI-PT/33202 9

Herschel/Planck

IQR Timeline

K.O. Meeting and Data Pack today

Preliminary feedback 18 Jan 2005

Issue of RIDs 02 Feb 2005

Co-location 10-11 Feb 2005

Issue of Board Report 25 Feb 2005

Page 10: Herschel/Planck January 13, 2005PACS IQR - SCI-PT/332021 ggonzale: Herschel PACS Instrument Qualification Review Review Objectives and Organisation G.Crone/G.Pilbratt

January 13, 2005 PACS IQR - SCI-PT/33202 10

Herschel/Planck

Review Board / Representatives of third parties

Herschel/Planck Project (ESTEC)

G. Crone (chair)

G. Pilbratt (co-chair)

A. Heske (secretary)

P. Estaria

J. Rautakoski

F. Pedersen

T. van der Laan

Industry Representative

G. Doubrovik (Alcatel)

SPIRE RepresentativeB. Swinyard (RAL)

Funding Agency RepresentativesM. Falvella (ASI)K. Mercier (CNES)K. Proetel (DLR)H. Schroeven-Deceuninck (Prodex)

Experts

D. Schink (Astrium)B. Collaudin (Alcatel)G. Coe (ESTEC)F. Marliani (ESTEC)

Page 11: Herschel/Planck January 13, 2005PACS IQR - SCI-PT/332021 ggonzale: Herschel PACS Instrument Qualification Review Review Objectives and Organisation G.Crone/G.Pilbratt

January 13, 2005 PACS IQR - SCI-PT/33202 11

Herschel/Planck

PACS IQR K.O. - Agenda09:00 Welcome MPE09:05 Review Organization and Objectives ESA09:15 Introduction – IHDR close-out and docs MPE09:45 Instrument Qualification Status and plans for PFM MPE

Mechanical, Thermal, Electrical I/Fs and EMC, Optical11:45 PhFPU Qualification and plans for PFM CEA12:15 Ge:Ga detector arrays Qualification MPE

with Coffee Break at 11:00

12:45 Lunch

13:45 On-Board Software and UM MPE14:15 EGSE, I-EGSE and MIB MPE14:25 CQM/AVM ILT Results MPE15:30 PA/QA Status MPE15:40 Management and Schedule MPE15:55 Critical Items and next steps MPE16:15 Lessons learnt from CQM Integration in Industry MPE16:30 Questions and Clarifications All17:00 First Impressions and Feedback ESA

with Coffee Break at 15:15