PRESENTATION

Istanbul Strait Road Tunnel Crossing

Development of a highway model for the Istanbul metropolitan area

2 European Transport Conference 2011Istanbul Strait Road Tunnel CrossingJC

I646

Outline

Project procurement Forecasting issues Forecasting approach Istanbul Traffic Model Project status and forward programme

3 European Transport Conference 2011Istanbul Strait Road Tunnel CrossingJC

I646

Istanbul strategic highway network

4 European Transport Conference 2011Istanbul Strait Road Tunnel CrossingJC

I646

Cross-Bosporus traffic growth

Current cross-Bosporus traffic = 400,000 AADT Bosporus Bridge at capacity late 1990’s. FSM Bridge approaching capacity.

0

50,000

100,000

150,000

200,000

250,000

300,000

350,000

400,000

450,00019

73

1975

1977

1979

1981

1983

1985

1987

1989

1991

1993

1995

1997

1999

2001

2003

2005

2007

Fatih Sultan Mehmet

Bogazici

5 European Transport Conference 2011Istanbul Strait Road Tunnel CrossingJC

I646

The Project

6 European Transport Conference 2011Istanbul Strait Road Tunnel CrossingJC

I646

The Project

14.6-km. motorway, including 5.4-km. twin-deck tunnel under the Bosporus in central Istanbul. Approach motorways widened to 4 lanes/direction. Bored tunnel restricted to cars and minibuses. Revenue guarantee = 25m. vehicles p.a.. Capital cost – c. $1.1bn..

7 European Transport Conference 2011Istanbul Strait Road Tunnel CrossingJC

I646

Project Procurement

The first Turkish transportation PPP project. BOT (Build, Operate, Transfer) tender:

– Issued by Turkish government - December 2006. – Bids submission - June 2008– Awarded - January 2009– Contract signed - February 2011.

Awarded to ATAS consortium on the basis of shortest concession period required. Concession period - 30 years, 6 months, 9 days, including 4 years, 7

months construction period.

8 European Transport Conference 2011Istanbul Strait Road Tunnel CrossingJC

I646

Traffic and revenue forecasting issues

Toll sensitivity Maximum toll permitted = $4.72

Land use development and economic growth– Population = c.12m., growing at 3% p.a.– Incomes 60% above national average, – Projected GDP growth = c.4%+ p.a.

Induced/suppressed demand– Suppressed demand from high congestion levels, especially on

Bosporus crossings Highway developments

– North Marmara motorway / 3rd Bosporus Bridge– Post-privatisation tolling on bridges

Modal competition– Marmaray rail link

9 European Transport Conference 2011Istanbul Strait Road Tunnel CrossingJC

I646

Forecasting approach

Existing modeling resources:– No available traffic model– ATC data and some O-D data– Limited journey time data.

Data collection programme Highway traffic model Mode choice model for public transport diversion

10 European Transport Conference 2011Istanbul Strait Road Tunnel CrossingJC

I646

Data collection

Traffic count survey Bosporus and FSM bridges 40+ other count locations across Istanbul.

Origin-Destination survey All cross-Bosporus flows covered by 18 sites 26,000 interviews.

Journey time survey 3 cross-Bosporus routes surveyed 74 survey runs.

11 European Transport Conference 2011Istanbul Strait Road Tunnel CrossingJC

I646

Istanbul Traffic Model

Zone system 424 zones Market segmentation

– 4 Car segments (commuter, education, business, other)– Minibus– Goods vehicles

Time periods Weekday A.M. peak & inter-peak hour Base year 2009 Forecast horizons 2015 and 2023 Modeling software CUBE Network 66,000 links, based upon satnav data.

12 European Transport Conference 2011Istanbul Strait Road Tunnel CrossingJC

I646

Istanbul Traffic Model - Example

13 European Transport Conference 2011Istanbul Strait Road Tunnel CrossingJC

I646

Project status

Forecasts are confidential Financial Close: Expected December 2011 Funding: Mix of commercial banks and multi-lateral institutions

14 European Transport Conference 2011Istanbul Strait Road Tunnel CrossingJC

I646

Turkish PPP programme

Gebze-Izmir motorway, inc. Izmit Bay Bridge– 420-km. BOT concession– Awarded to bidder offering the shortest concession period– Preferred Bidder: Otoyol S.A.– Capital cost: c.$11bn.– Financial Close: Expected before end-2012.

North Marmara Highway, inc. 3rd Bosporus Bridge– 361-km. BOT concession– Tender expected early 2012– Capital cost: c.$6bn.

15 European Transport Conference 2011Istanbul Strait Road Tunnel CrossingJC

I646