Homework AssignmentHomework AssignmentJob Shop SchedulingJob Shop Scheduling
MGMT E - 5065 MGMT E - 5065 Operations and LogisticsOperations and Logistics
Management Management
ACME TOOL & DIE , Inc.ACME TOOL & DIE , Inc.
Due December 11th
Acme ToolAcme Tool & Die , Inc.& Die , Inc.
It is the first day of the month. Your job shop operates seven ( 7 ) days a week. This new month’s work consists of six ( 6 ) jobs, with processing time estimates and deadlines as follows:
JOBJOB
ESTIMATED ESTIMATED TIMETIME
( in days )DEADLINEDEADLINE
( date )
A 5 8th
B 7 12th
C 1 5th
D 9 14th
E 4 10th
F 3 19th
Acme Tool & Die , Inc.Acme Tool & Die , Inc.
REQUIREMENT :
1. Under the STATIC SLACK ( SS ) priority sequence rule:
a. Determine the static slack for each job.
b. Compute the average job completion time.
c. Compute the average job lateness.
d. Identify the name(s) and the number of jobs that will be late this month.
NOTE: For simplicity, assume that the job shop has only one ( 1 ) work center.
Homework AssignmentHomework AssignmentJob Shop SchedulingJob Shop Scheduling
MGMT E - 5065 MGMT E - 5065 Operations and LogisticsOperations and Logistics
Management Management
ACME TOOL & DIE , Inc.ACME TOOL & DIE , Inc.