APPENDIX 1 Housing Delivery Test Action Plan 2019 - 2022 Bournemouth, Christchurch and Poole Council October 2019

Upload: others

Post on 19-Mar-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Housing Delivery Test Action Plan 2019 - 2022 1... · APPENDIX 1 1 1 Introduction Background 1.1 In February 2017, the Housing White Paper ‘Fixing our broken housing market’ was

APPENDIX 1

Housing Delivery Test

Action Plan 2019 - 2022

Bournemouth, Christchurch and

Poole Council

October 2019

Page 2: Housing Delivery Test Action Plan 2019 - 2022 1... · APPENDIX 1 1 1 Introduction Background 1.1 In February 2017, the Housing White Paper ‘Fixing our broken housing market’ was

APPENDIX 1

1

1 Introduction

Background

1.1 In February 2017, the Housing White Paper ‘Fixing our broken housing market’

was published. It set out the government’s plans to increase housing supply, in

acknowledgment that for decades, the pace of house building had not kept pace

with population growth. To address this issue the government set an ambitious

target to deliver at least 300,000 new homes annually ‘for the foreseeable future’.

1.2 The White Paper also introduced a new ‘housing delivery test’ (HDT) designed to

assess whether local authority housing delivery is above or below target. The HDT

measures net additional dwellings provided in a local authority area against the

homes required for the 3 preceding financial years. The methodology for

calculating the HDT is set out in the Housing Delivery Test Measurement Rule

Book1. The Ministry of Housing, Communities and Local Government (MHCLG)

will publish the HDT result for each local planning authority annually. The first

housing delivery test measurement was published in February 2019.

1.3 HDT Action Plans are required in local authority areas where housing delivery has

fallen below 95% of the housing target. The purpose of housing delivery test

action plans is to assess reasons for under delivery and to identify measures to

improve delivery to meet annual housing requirements.

Local Context

1.4 Delivering the number of new homes required across BCP needs to be considered

in the context of local environmental constraints. The South East Dorset Green

Belt and nationally and internationally designated areas of heathland to the north

are a significant constraint. Poole and Christchurch are also affected by significant

areas of high flood risk in the town centres and the Twin Sales Regeneration Area

when present day and future tidal and fluvial flood risk is taken into account.

These constraints limit the opportunities for identifying and bringing forward

suitable sites for housing development and makes delivery of the housing

numbers required challenging.

The Housing Delivery Test Action Plan for Bournemouth, Christchurch and

Poole

1.5 This Bournemouth, Christchurch and Poole (BCP) Housing Delivery Test (HDT)

Action Plan has been prepared in response to the 2018 HDT result. In the BCP

area housing delivery over the last 3 years has been less than 95% of adopted

Local Plan requirements. Therefore, in accordance with the National Planning

Policy Framework (NPPF) an HDT Action Plan is required. The 2018 HDT result

was calculated in relation to housing delivery measured against the housing

1 https://www.gov.uk/government/publications/housing-delivery-test-measurement-rule-book

Page 3: Housing Delivery Test Action Plan 2019 - 2022 1... · APPENDIX 1 1 1 Introduction Background 1.1 In February 2017, the Housing White Paper ‘Fixing our broken housing market’ was

2

requirements set out in the adopted Bournemouth Core Strategy (2012),

Christchurch and East Dorset Core Strategy (2014) and Poole Local Plan (2018).

1.6 This Action Plan sets out housing delivery performance against Local Plan targets,

analysis of housing land supply, issues affecting housing delivery and measures

to improve the delivery of new homes. The Action Plan covers the period 2019 –

2022 which reflects the delivery timescales for actions contained in the plan.

1.7 On the 1st April 2019 the Bournemouth, Christchurch and Poole (BCP) Council

was established. The new BCP Council brings together the former Bournemouth,

Poole and Christchurch borough councils. BCP is preparing a single Action Plan

as this is the most effective way of addressing issues affecting housing delivery for

the new council area.

1.8 The 2018 Housing Delivery Test measurement was published on the 19th

February 2019 and the results for the BCP areas are set out in Table 1.

Area Number of homes required

Total number

of homes

required

Number of homes delivered

Total number

of homes

delivered

Housing Delivery

Test: 2018 measurement

Housing Delivery

Test: 2018 consequence

2015-16

2016-17

2017-18

2015-16

2016-17

2017-18

Bournemouth 730 730 893 2,353 732 607 631 1,970 84%

Action Plan / 20% Buffer

Christchurch & East Dorset 488 500 540 1,528 300 436 405 1,141 75%

Action Plan / 20% Buffer

Poole 500 500 500 1,500 392 584 300 1,276 85% Action Plan

(Table 1, BCP February 2018 HDT Result).

1.9 The HDT measurement will continue to be calculated against the relevant housing

requirement for the adopted Local Plans in Bournemouth, Christchurch and East

Dorset, and Poole, or household projections where those plans are more than five

years old, until these plans are superseded by new Local Plans for the BCP and

Dorset councils.

1.10 East Dorset now forms part of the new Dorset Council unitary authority and a

separate Action Plan will be prepared by the Dorset Council for this area. BCP is

working closely with the Dorset Council in relation to cross border measures that

are appropriate to assist housing delivery in East Dorset.

1.11 This Action Plan was prepared collaboratively by BCP Council with the

involvement of the Growth and Infrastructure and Housing Departments. The

process of identifying issues affecting housing delivery and measures to address

Page 4: Housing Delivery Test Action Plan 2019 - 2022 1... · APPENDIX 1 1 1 Introduction Background 1.1 In February 2017, the Housing White Paper ‘Fixing our broken housing market’ was

3

these issues has involved consultation with the development industry. This Action

Plan received sign off through Cabinet on the 9th October 2019.

1.12 Locally across the BCP area, the issues around the need for additional homes and

an increase in housing supply across all tenures is recognised in the legacy

Housing Strategies. Housing demand is very high and housing costs are equally

high. Work has already been underway across the legacy Councils to assist in

enabling the supply of additional homes but this report sets out a move towards a

‘step change’ in enabling additional housing supply to help meet local housing

requirements.A priority for BCP council is to put in place a new housing strategy.

The purpose of a housing strategy is to inform local residents and partners about

BCPs housing needs and issues and set out key challenges where action will be

required to help meet both current and future housing need. The strategy will

contribute towards the Council’s wider strategic aims and priorities and will link

into many key policies such as local plans.

1.13 The structure and scope of this Action Plan is as follows:

1. Introduction

2. BCP Housing Market Delivery and Supply Analysis

a. BCP Housing Delivery Analysis

b. BCP Housing Supply Analysis:

i. Nature and Composition of Local Housing Market

ii. An overview of the typologies of sites/development activity

3. Strategic Approach to Housing Delivery

a. Planning Context – Adopted Plans / BCP Local Plan

b. Housing Delivery & Cross Border Working

c. Strategic Infrastructure & Delivery

4. Addressing Barriers to Housing Delivery

5. BCP SMART Housing Delivery Test Action Plan

6. Project Management & Monitoring Arrangements

Page 5: Housing Delivery Test Action Plan 2019 - 2022 1... · APPENDIX 1 1 1 Introduction Background 1.1 In February 2017, the Housing White Paper ‘Fixing our broken housing market’ was

4

2 BCP Housing Market Delivery and Supply Analysis

Housing Delivery Analysis

2.1 This section sets out an analysis of housing delivery in BCP measured against the

housing requirements of the current adopted Bournemouth, Christchurch and East

Dorset and Poole Local Plans. Separate tables are set out for Bournemouth,

Christchurch and Poole to reflect housing delivery since the adoption of the

respective local plans.

Bournemouth Housing Delivery

200

6 /

07

200

7/0

8

200

8/0

9

200

9/1

0

201

0/1

1

201

1/1

2

201

2/1

3

201

3/1

4

201

4/1

5

201

5/1

6

201

6/1

7

201

7/1

8

201

8/1

9

201

9/2

0

Core Strategy Housing Target

730 730 730 730

730

730

730

730

730

730

730

730

730

1,422

Net Completions

1089

1534

1218

622

492

555

639

394

964

730

581

635

659

N/A

(Table 2, Bournemouth Housing Delivery, Core Strategy 2012)

2.2 The Bournemouth Core Strategy was adopted in 2012 and covers a plan period of

2006 to 2026.

2.3 Over the first 5 years of the plan period a total of 4,955 dwellings were delivered.

This equates to an average of 991 dwellings per year which was in excess of the

annual local plan requirement. Since 2009 housing delivery has fluctuated but

generally fallen below the adopted plan target. However, over the first 13 years of

the plan period 10,112 dwellings have been delivered against a target of 9,490.

2.4 From 2019/20 onwards the housing requirement in Bournemouth steps up

significantly from 722 to 1,422 dwellings per annum with the transition to the

government’s standard methodology. This step change in housing requirement

presents a significant challenge for BCP in relation to housing delivery and

housing land supply.

Page 6: Housing Delivery Test Action Plan 2019 - 2022 1... · APPENDIX 1 1 1 Introduction Background 1.1 In February 2017, the Housing White Paper ‘Fixing our broken housing market’ was

5

Christchurch and East Dorset Housing Delivery

2013/14 2014/15 2015/16 2016/17 2017/18 2018/19 2019/20

Core Strategy Housing Target

566 566 566 566 566 566

791(Standard Methodology)

Christchurch Completions

149 154 117 245 100 182 N/A

East Dorset Completions

156 180 237 185 305 290 N/A

Combined 305 334 354 430 405 472 N/A

(Table 3, Christchurch Housing Delivery, Core Strategy 2014)

2.5 The Christchurch and East Dorset Core Strategy was adopted in 2014 and covers

a plan period of 2013 to 2028. The Core Strategy housing target and 5 year land

supply remains joint for the Christchurch and East Dorset plan area (until

superseded by the new BCP and Dorset Council Local Plans).

2.6 Over the first 6 years of the plan period 2,300 dwellings have been delivered

against a housing requirement of 3,396 dwellings for this period.

2.7 From 2019/20 the housing requirement for the Christchurch and East Dorset Plan

area moves to the Government’s standard methodology of 791 dwellings per

annum (Christchurch, 349 dwellings / East Dorset, 442 dwellings p.a.). The uplift

in housing requirement presents a challenge for both BCP and the Dorset Council

in relation to housing land supply, particularly in Christchurch.

Poole Housing Delivery

2013/14 2014/15 2015/16 2016/17 2017/18 2018/19 2019/20

Local Plan Housing Target

500 500 500 500 500 710 710

Net Completions

177 298 335 570 307 426 N/A

(Table 4, Poole Housing Delivery, Local Plan 2018)

2.8 The Borough of Poole Local Plan was adopted in November 2018 and covers a

plan period of 2013 to 2033. Over the first 6 years of the plan period a total of

2,113 dwellings have been delivered against a requirement of 3,210 dwellings.

2.9 The Poole Local Plan was recently adopted, therefore the adopted Local Plan

housing target will apply until superseded by the BCP Local Plan.

Page 7: Housing Delivery Test Action Plan 2019 - 2022 1... · APPENDIX 1 1 1 Introduction Background 1.1 In February 2017, the Housing White Paper ‘Fixing our broken housing market’ was

6

Bournemouth, Christchurch and Poole Housing Delivery

2013/14 2014/15 2015/16 2016/17 2017/18 2018/19 2019/20

BCP Housing Requirement

1,796 1,796 1,796 1,796 1,796 2,006 2,481

BCP Net Completions

876 1,596 1,419 1,581 1,347 1,557 N/A

(Table 5, BCP Housing Delivery based on adopted Local Plans)

2.10 Separate Local Plans are in place for Bournemouth, Christchurch and Poole but it

is useful to examine the aggregate position for the BCP Council area.

2.11 Over the period 2013 / 14 to 2018/19 an aggregate total of 10,986 dwellings have

been required based on the adopted Local Plans for Bournemouth, Poole and

Christchurch. Over this period a total of 8,376 dwellings have been delivered

which presents a shortfall of 2,610 dwellings.

2.12 From 2019/20 the Government’s standard methodology housing requirement

applies in Bournemouth and the Christchurch / East Dorset Plan area which

represents a significant step change in housing delivery required. This Action Plan

sets out a range of measures to address housing delivery including the production

of the BCP Local Plan to an accelerated timeframe.

Housing Supply Analysis

2.13 Understanding the current supply of sites available for delivering the new homes

required across the BCP Council area, is crucial to ensuring delivery targets are

met.

2.14 As a starting point, evidence bases were compiled for the former local authority

areas of Bournemouth, Christchurch and Poole, of key sites contributing to the

current supply and falling within the following categories:

Strategic sites of 40+ dwellings;

‘Major’ sites with planning permission for 10+ dwellings (net); and

Sites for 10+ dwellings (net) identified in Strategic Housing Land Availability

Assessments (SHLAA).

2.15 An analysis of the identified sites has been undertaken to establish the nature and

scale of sites currently available to meet housing needs. The following provides a

summary of this analysis for the BCP Council area.

Page 8: Housing Delivery Test Action Plan 2019 - 2022 1... · APPENDIX 1 1 1 Introduction Background 1.1 In February 2017, the Housing White Paper ‘Fixing our broken housing market’ was

7

Strategic sites of minimum 40+ new homes

2.16 Strategic housing sites are defined as those having the capacity to deliver a

minimum of 40 new homes. They predominantly consist of sites allocated through

the adopted local plans of the three former local authority areas of Bournemouth,

Christchurch and Poole. Also included are a number of major sites with planning

permission which exceed the 40 dwelling strategic site threshold. It should be

noted that site allocations normally provide an estimated figure for the number of

new homes that a site could accommodate, with this figure often exceeded at the

formal planning application stage.

2.17 A total of 81 strategic sites in the BCP area were identified and included in the

analysis. It is important to note that a further 10 strategic housing allocations

(remaining to come forward) are located in East Dorset which form part of the

Christchurch and East Dorset plan area housing supply.

2.18 A key consideration in relation to these sites was what issues, challenges and

barriers there might be to their coming forward for development. An assessment of

the sites was undertaken utilising a green, amber red ‘traffic light’ system, which

established that there were 35 ‘green’ sites where little or no delays or barriers

were identified to their development. The same number of ‘amber’ sites were

considered to have issues that needed to be overcome or resolved in the

immediate to short term before development could proceed, and a further 11 ‘red’

sites were identified as having significant challenges to their coming forward for

development. The issues and barriers identified through the evidence gathering

and assessment process, together with appropriate actions aimed at addressing

the challenges to unlocking many of these sites for development are set out in

detail in Sections 4 and 5.

2.19 The strategic sites identified across the BCP Council area currently have a total

combined capacity of 13,180 dwellings. However, monitoring indicates that 13 of

these sites are under construction, delivering 1,220 dwellings on completion,

leaving remaining capacity of approximately 11,960 dwellings. Of this remaining

capacity, a further 25 sites (31%) currently benefit from planning permission for a

total of 4,090 dwellings. The majority of strategic sites are categorised as being on

previously developed land (brownfield land), whist 8 sites fall into the category of

greenfield sites. 44 (54%) of sites have the capacity to deliver between 40 and 99

dwellings. The remaining 37 sites have the capacity to deliver a minimum of 100

new homes, with 8 (10%) of these identified as large sites delivering in excess of

400+ new homes.

2.20 Figure 1 shows the number of strategic sites categorised within number ranges by

the dwellings each site could accommodate.

Page 9: Housing Delivery Test Action Plan 2019 - 2022 1... · APPENDIX 1 1 1 Introduction Background 1.1 In February 2017, the Housing White Paper ‘Fixing our broken housing market’ was

8

(Figure 1: Strategic sites across the BCP Council area categorised by number of

dwellings)

Major sites of 10+ new homes with planning permission

2.21 In total, 84 sites were identified and classified as major sites (i.e. 10+ dwellings

(net) and above) with planning permission, having total overall capacity of 1,544

dwellings. Of these 52 (62%) were smaller scale sites delivering between 10 and

19 dwellings. The remaining sites vary in capacity of between 20 and 39

dwellings.

2.22 Annual housing development monitoring indicates that of the 84 major sites

identified, 32 (38%) are now under construction, delivering 521 new homes on

completion and leaving capacity across the remaining sites of just over 1,020

dwellings. Only 2 of the major sites are categorised as greenfield sites.

2.23 As the majority of these sites have secured planning permission (a small number

of qualifying sites are currently in the process of being determined), a ‘traffic light’

assessment has identified a limited number of issues and barriers to development.

As with the strategic sites, appropriate actions aimed at overcoming impediments

to development are set out in detail in sections 4 and 5.

2.24 Figure 2 shows the number of major sites categorised within number ranges by

the dwellings each site could accommodate.

38

18

6

58

40 - 99

100 - 199

200 - 299

300 - 399

400+

Page 10: Housing Delivery Test Action Plan 2019 - 2022 1... · APPENDIX 1 1 1 Introduction Background 1.1 In February 2017, the Housing White Paper ‘Fixing our broken housing market’ was

9

(Figure 2: Major sites across the BCP Council area categorised by number of dwellings)

SHLAA sites (non-allocated sites and sites without planning permission,

with minimum capacity of 10+ new homes (net))

2.25 The 57 sites identified in this category are included in the annual SHLAA updates

for Bournemouth, Christchurch and Poole and represent sites assumed to be

deliverable in the medium to long-term. They are identified from a number of

sources, with no clear indication of when they might become available and, as a

consequence, are included in the 6 - 15 year land supply. The sites in this

category would, if developed, deliver 1,655 new homes.

2.26 Figure 3 shows the number of sites categorised by the number of dwellings each

site could potentially accommodate.

42

18

9

10 - 19

20 - 29

30 - 39

Page 11: Housing Delivery Test Action Plan 2019 - 2022 1... · APPENDIX 1 1 1 Introduction Background 1.1 In February 2017, the Housing White Paper ‘Fixing our broken housing market’ was

10

(Figure 3: SHLAA sites (non-allocated sites and sites without planning permission for 10+

new homes(net)) categorised by number of dwellings)

2.27 As part of the early work on the BCP Local Plan, it would be appropriate to review

the identified SHLAA sites to determine their future potential for allocation, or

whether, working with the owners/developers, there are opportunities to bring

them forward sooner for development.

Summary of BCP Housing Supply Analysis

2.28 Analysis of housing sites across the BCP Council area demonstrates a healthy

supply of sites of various sizes and greenfield / brownfield locations available for

development. This mix of supply provides a sufficient range of large strategic sites

and smaller sites to not significantly affect the rate of housing delivery.

2.29 The sites identified would deliver approximately 14,700 new homes, which does

not include smaller sites of less than 10 dwellings identified through individual

SHLAA’s and which represent long term development opportunities. There is a

broadly even division between the number of ‘strategic’ scale sites (81) capable of

delivering in excess of 40 dwellings and the smaller ‘major’ sites (84) delivering

between 10 and 40 dwellings.

2.30 It is worth noting that the majority of the 165 strategic and major sites identified for

analysis, 94% are categorised as being on ‘previously developed land’, with only

6% of sites being categorised as ‘greenfield’ land development. Of these

greenfield sites, 8 are strategic in scale and would deliver approximately 3,380

dwellings. Four of these strategic greenfield sites are large, with each delivering

400 new homes or more.

2.31 Whilst many of the sites identified through this HDT Action Plan process present

little or no issues in their coming forward for development (a number being already

under construction), there are sites which have more significant issues and

46

92

10 - 39

40 - 99

100+

Page 12: Housing Delivery Test Action Plan 2019 - 2022 1... · APPENDIX 1 1 1 Introduction Background 1.1 In February 2017, the Housing White Paper ‘Fixing our broken housing market’ was

11

barriers to their development. It is the issues and barriers affecting these sites that

have been addressed in Sections 4 and 5.

The Letwin Review

2.32 In seeking to support the Government’s objective of significantly boosting the

supply of homes2, it is appropriate to consider the findings of the ‘Independent

Review of Build Out’ (October 2018), led by Sir Oliver Letwin. The review

considers the effect that the homogeneity of the types and tenures of the homes

on offer on large sites in areas of high housing demand, and the limits on the rate

at which the market will absorb such homogenous products, are fundamental

drivers of slow build out rates.

2.33 Sites currently under construction and those likely to begin construction in the

near future, within or near to the BCP Council area were identified. These sites

are shown on Map 1.

2.34 Analysis of the sites indicated that a significant proportion of the dwellings being

delivered, or proposed, were either 3, 4 or 5 bedroom homes. At present there is

no evidence that the similarity of product being delivered across these sites is

resulting in slow build out rates. With a number of strategic sites likely to begin

construction in the next year or so, it will be necessary to monitor build out and

market absorption rates and seek to address this issue through future Action

Plans, should the need arise.

(Map 1: Strategic sites currently under construction or likely to begin construction in the

near future in South-East Dorset.)

2 Housing White Paper “Fixing our broken housing market” – February 2017.

Page 13: Housing Delivery Test Action Plan 2019 - 2022 1... · APPENDIX 1 1 1 Introduction Background 1.1 In February 2017, the Housing White Paper ‘Fixing our broken housing market’ was

12

3 Strategic Approach to Housing Delivery

3.1 This section of the Action Plan sets out BCP’s strategic approach to housing

delivery. This includes a review of the current status of Local Plans and the

emerging BCP Local Plan. The review of Local Plans also sets out how the

council is working with neighbouring authorities in the context of the duty to co-

operate and a cross border approach to housing delivery. This section also sets

out measures to address strategic infrastructure requirements to deliver housing

such as transport strategies and major infrastructure bids to lever in external

sources of funding.

BCP Adopted Local Plans

3.2 The current Development Plan for the BCP Council comprises the existing Local

Plans adopted for the preceding Bournemouth, Christchurch and Poole Borough

Councils. These Local Plans set out the strategic approach to housing delivery.

Plan Period

In date Local Plan as at April 2019.

Local Plan Housing Target

Housing target p.a based on adopted Local Plan.

Standard Methodology p.a Figure.

Housing figure applied as of April 2019

Bournemouth 2006 - 2026

No 14,600 730 1422 1422 pa

Christchurch and East Dorset

2013 - 2028

No 8,490 566 Christchurch: 349 East Dorset: 442

Christchurch: 349 East Dorset: 442

Poole 2013 - 2033

Yes 14,200 710 801 710 pa

BCP TBC N/A N/A N/A 2,572 2,481

(Table 6, BCP Local Plan Status).

3.3 The Bournemouth Core Strategy was adopted in October 2012 and in conjunction

with the Bournemouth Town Centre Area Action Plan (March 2013), sets out the

housing delivery strategy for Bournemouth from 2006 to 2026. The Core Strategy

is now more than 5 years old and from April 2019 the annual housing requirement

is based on the government’s standard methodology figure of 1,422 per annum.

3.4 The Christchurch and East Dorset Core Strategy was adopted in April 2014 and

sets out the housing delivery strategy for Christchurch and East Dorset for the

period 2013 to 2028. The Core Strategy is now more than 5 years old and from

April 2019, the annual combined housing requirement for Christchurch and East

Dorset is based on the government’s standard methodology figure of 791 per

annum.

Page 14: Housing Delivery Test Action Plan 2019 - 2022 1... · APPENDIX 1 1 1 Introduction Background 1.1 In February 2017, the Housing White Paper ‘Fixing our broken housing market’ was

13

3.5 The Poole Local Plan was adopted in November 2018 and sets the housing

delivery strategy in Poole for the period 2013 – 2033. The Local Plan is less than

5 years old and as of April 2019 the adopted Local Plan housing figure is applied

until superseded by a BCP Local Plan.

Relationship to Other Plans and Strategies

BCP Corporate Plan

3.6 BCP’s emerging Corporate Plan is based around five key actions. A commitment

to investing in the homes the communities of BCP need, supported by the

development of sustainable infrastructure is key to the strategy’s ‘Dynamic

Region’ action theme.

Bournemouth, Christchurch and Poole Local Plan

3.7 BCP has made the decision to prepare a single Local Plan which, once adopted

will replace the current adopted Local Plans for Bournemouth, Christchurch and

Poole.

3.8 The BCP Local Plan is being prepared to an accelerated timetable with adoption

scheduled for December 2022. This accelerated timescale will assist with housing

delivery, ensuring that new housing allocations are in place and key infrastructure

issues addressed for development to come forward.

3.9 The Dorset Council has also recently produced a local development scheme

setting out a timeframe for the production of a single Dorset Local Plan. The

consultation stages of the Dorset Local Plan are broadly aligned to the BCP Local

Plan which ensures opportunity for effective cross border planning and housing

delivery. The Dorset Council Local Plan is currently scheduled for adoption in

spring 2023, shortly after the BCP Local Plan.

Housing Delivery and Cross Border Working

3.10 In accordance with the Duty to Co-operate BCP works closely with neighbouring

authorities regarding housing delivery including the Dorset Council, New Forest

District Council, and the New Forest National Park. BCP is working closely with

these councils as part of the preparation of the BCP Local Plan.

Strategic Planning Forum

3.11 The Dorset Strategic Planning Forum was established in 2015 to consider

strategic planning issues that affect cross border matters, and to guide strategic

planning matters at the ‘larger than local’ scale. The purpose of the forum has

Page 15: Housing Delivery Test Action Plan 2019 - 2022 1... · APPENDIX 1 1 1 Introduction Background 1.1 In February 2017, the Housing White Paper ‘Fixing our broken housing market’ was

14

been to facilitate effective policy development across administrative borders and

to help fulfil the requirements of the duty to co-operate.

3.12 Since the formation of the BCP and Dorset Councils in April 2019 there is a need

for the terms of reference of the SPF to be revisited. There is a need for a refocus

around strategic planning matters concerning the preparation and delivery of the

BCP and Dorset Local Plans including housing delivery.

Statement of Common Ground (between local planning authorities in

Dorset) (March 2019)

3.13 Prior to the formation of the BCP and Dorset Councils in April 2019, in accordance

with the NPPF a Statement of Common Ground (SCOG) was prepared between

the Bournemouth, Dorset and Poole councils. The preparation of the SOCG was

overseen by the Dorset Strategic Planning Forum.

3.14 The SOCG provides a summary of key strategic planning matters where co-

operation across administrative boundaries may be appropriate. The current

SOCG is a written record of progress made against strategic matters across local

authority boundaries. Key strategic matters addressed by the SOCG include the

delivery of housing against the relevant local housing requirements. The SOCG

recognises that new Local Plans based on the latest government standard

methodology will require a step change in housing delivery and greater emphasis

on meeting unmet housing need across administrative boundaries.

3.15 The current SOCG states that where it is the case that an authority in the area is

unable to meet their identified needs, the local planning authorities within the area

are committed to working together to assess the potential for some or all of this

unmet need to be delivered within other authorities areas.

3.16 Following the formation of the BCP and Dorset Councils in April of this year the

approach to cross border working and strategic planning is being revisited. This

will require an update to the SOCG to take into account the latest adopted Local

Plan housing requirements including where the government’s standard

methodology now applies. The SOCG will also examine the emerging housing

requirements from the draft BCP and Dorset Local Plans and the actions required

to address delivery.

BCP Housing Strategy

3.17 A priority for BCP council is to put in place a new housing strategy. The purpose of a housing strategy is to inform local residents and partners about BCPs housing needs and issues and set out key challenges where action will be required to help meet both current and future housing need. The strategy will contribute towards

Page 16: Housing Delivery Test Action Plan 2019 - 2022 1... · APPENDIX 1 1 1 Introduction Background 1.1 In February 2017, the Housing White Paper ‘Fixing our broken housing market’ was

15

the Council’s wider strategic aims and priorities and will link into many key policies such as local plans.

3.18 The supply and enabling of new homes has been a priority in all of the legacy

housing strategies for Bournemouth, Christchurch and Poole and will most likely feature highly in the new BCP Housing Strategy setting out a number of actions to aid the supply of new homes. The Housing strategy is currently being prepared ideally with planned adoption in autumn 2020.

Local Transport Plan

3.19 BCP is examining options to progress an update to Local Transport Plan 3 which

applied to the previous Bournemouth, Dorset and Poole local authority areas. BCP

is liaising with the Dorset Council to examine options for progressing LTP 4 which

it is envisaged would be produced alongside preparation of the BCP and Dorset

Council Local Plans. A new LTP would identify a transport strategy for the BCP

area and strategic transport improvements that will help to facilitate housing

delivery.

Strategic Infrastructure and Housing Delivery

3.20 BCP Council is actively engaged in a number of strategic projects to deliver key

infrastructure to help facilitate the delivery of new housing development in the

area. BCP is working closely with the Dorset Council and the Dorset LEP in

pursuing cross border initiatives. Key strategic projects are set out below.

Western Gateway Transport Body

3.21 BCP is engaged with the Western Gateway Transport Body in the preparation of a

regional transport strategy to be produced by 2021. The regional strategy will

identify strategic improvements to improve regional connectivity which will also

help to assist the delivery of new housing development. Progress to date includes:

1. Completed regional Economic Connectivity Study considering growth

across the region and productivity gaps;

2. Submitted MRN schemes to Government, which relate to the Bournemouth

International Growth Programme;

3. Work to commence on preparation of a regional rail strategy;

4. Delivery of a Western Gateway Regional Transport Strategy by 2021.

South East Dorset Urban Mobility Study

3.22 BCP, Dorset Council and the Dorset LEP are working jointly in the preparation of a

South East Dorset Urban Mobility Study (SEDUMS). The 2019 SEDUMS is a

refresh of the South East Dorset Multi Modal Transport Study (SEDMMTS)

Page 17: Housing Delivery Test Action Plan 2019 - 2022 1... · APPENDIX 1 1 1 Introduction Background 1.1 In February 2017, the Housing White Paper ‘Fixing our broken housing market’ was

16

published in 2012, which informed the joint Local Transport Plan 3 for

Bournemouth, Dorset and Poole. The SEDUMS study will provide an updated

transport evidence base to inform strategic planning and transport strategy for

South East Dorset by the end of 2019 that will facilitate growth and development

aspirations in line with local, regional and national policies. This study is a key

element of the evidence base for the BCP and Dorset Council Local Plans in

terms of identifying strategic transport improvements necessary to support new

development proposals emerging through the new Local Plans.

Dorset LEP Growth Deal

3.23 The Dorset LEP Growth Deal has funded a number of key infrastructure projects

across the BCP Council area in recent years to help enable strategic housing and

employment development.

3.24 A total of £45,200,000 was awarded to Bournemouth Borough Council and Dorset

County Council through the Government’s Growth Deal. This funding has been

match funded with £14,200,000 to provide a total of £59.4M. This funding will

deliver a series of strategic transport improvements along the A338 and B3073 by

2021. These improvements will help facilitate the delivery of strategic housing and

employment development in the BCP and Dorset Council areas.

3.25 Current Progress with the BIG programme is as follows:

o A338 Reconstruction (PROJECT COMPLETED)

o A338 Package: Blackwater Junction, Wessex Fields, Widening

o A348 Corridor

o Chapel Gate Roundabout (PROJECT COMPLETED)

o Hurn Roundabout (PROJECT COMPLETED)

o Parley Cross, Parley West, Parley East

3.26 A total of £25,560,000 was awarded to Borough of Poole to improve access to the

Port of Poole and help unlock key brownfield housing sites around Twin Sails

Bridge. The last phase, Townside Access, will be completed in during 2019/2020.

Transforming Cities Bid

3.27 BCP Council in partnership with local transport providers have submitted a draft

Transforming Cities Fund (TCF) bid to the Department of Transport (DfT).

3.28 The bidfocuses on linking residential areas to employment and education sites

which could most benefit from significant improvements to encourage walking,

cycling and increased use of public transport. The aim is to reduce the number of

local journeys made by car thereby reducing congestion and bringing about a wide

range of benefits associated with sustainable travel, such as improved health and

wellbeing.

Page 18: Housing Delivery Test Action Plan 2019 - 2022 1... · APPENDIX 1 1 1 Introduction Background 1.1 In February 2017, the Housing White Paper ‘Fixing our broken housing market’ was

17

3.29 The main areas the draft bid focuses on are:

Improving and creating new walking and cycling routes

developing sustainable work places

enhancing the bike share scheme offer

bus and rail improvements

improved network management, and

a dedicated Travel App incorporating all modes of transport

3.30 If successful the TCF will deliver key sustainable transport improvements along

some BCP Priority Transport Corridors in close proximity to strategic housing and

employment allocations. The delivery of sustainable transport measures through

TCF alongside other planned infrastructure improvements will help to facilitate

new housing development.

Local Industrial Strategy

3.31 The Dorset Local Enterprise Partnership are preparing a local industrial strategy

for Dorset to help deliver the Government’s national strategy. The Dorset LIS is

being prepared in close collaboration with local businesses, organisations, BCP

Council and Dorset Council. Once published Dorset’s LIS will be a twenty-year

plan to increase productivity, innovation, earnings and well-being across the

county, delivering on an ambition to create a local economy that is sustainable,

innovative, resilient and inclusive.

Page 19: Housing Delivery Test Action Plan 2019 - 2022 1... · APPENDIX 1 1 1 Introduction Background 1.1 In February 2017, the Housing White Paper ‘Fixing our broken housing market’ was

18

4 Addressing Barriers to Housing Delivery

4.1 In the preparation of this Action Plan and associated evidence gathering, a range

of key issues have been identified for the BCP area that are affecting housing

delivery. These issues have been identified through engagement with the

development industry, analysis of Local Plan monitoring and consultation with

BCP planning policy, development management, housing and property officers. A

summary of the key issues and actions are set out in a SMART Action plan in

Section 5. This section sets out more detailed background to the key issues and

planned actions.

4.2 It is important to note that this Action Plan will evolve over time as the strategy for

increasing Housing Supply is developed and with oversight from a Steering

Group. This Action Plan effectively forms a much-needed consolidated

programme of activity which will gain momentum and profile over the next few

years as resources are focused on increased housing delivery.

4.3 The actions are focused around 5 strategic issues:

1. BCP Housing land Supply

2. Infrastructure

3. Viability

4. Economic Factors / Housing Market

5. Commercial Market Communications

Strategic Issue: BCP Housing Land Supply

4.4 The first strategic issue affecting housing delivery across the BCP area concerns

housing land supply. Sub issues related to this issue include:

1) Strategic site delays

2) Government standard housing methodology & Increased Targets

3) Progress with Duty to Co-operate and cross border strategic planning

4) Unimplemented planning consents

5) Environmental and other constraints

Sub Issue 1: Strategic Site Delays

4.5 Across the BCP area there are 81 strategic sites (40+ dwellings) which are

planned to deliver 13,180 dwellings and form a very significant element of the

BCP housing land supply. BCP local plan monitoring and evidence gathering for

the HDT Action Plan has identified there are key issues affecting site delivery that

need specific actions to address them. Some of these key issues are set out as

follows in respect of housing allocations across Bournemouth, Christchurch and

Poole:

Page 20: Housing Delivery Test Action Plan 2019 - 2022 1... · APPENDIX 1 1 1 Introduction Background 1.1 In February 2017, the Housing White Paper ‘Fixing our broken housing market’ was

19

Bournemouth Housing Allocations

4.6 The Bournemouth Town Centre Area Action Plan containing the majority of

Bournemouth allocations was adopted in March 2013 by Bournemouth Council.

Through monitoring of the AAP it has been identified that some housing sites

allocated in the plan may not come forward. These sites include Commercial Road

/ Avenue Road, Asda (Holdenhurst Road), and Holdenhurst Road Retail Park.

Christchurch and East Dorset Strategic Housing Allocations

4.7 The Christchurch and East Dorset Core Strategy adopted in April 2014 identifies a

housing requirement of 8,490 dwellings. Of this requirement, approximately 3,500

dwellings are located on strategic sites in Christchurch, Burton, Corfe Mullen,

Wimborne / Colehill, Ferndown / West Parley and Verwood. Through preparation

of the Core Strategy developers and land owners were closely engaged in

establishing strategic site delivery trajectories for the Core Strategy allocations. A

number of key strategic sites allocated in the Core Strategy have not come

forward as expected due to the following reasons:

Delays to delivery of strategic transport infrastructure

Delays to the delivery of Strategic Alternative Natural Green Space (SANG)

Delays to developer and land owner private land transactions

Delays to allocations in multiple land ownerships due to site access and

shared infrastructure delivery issue.

Addressing abnormal site infrastructure requirements e.g. under grounding

overhead pylons

Securing alternative allotments site for replacement of statutory allotments

Delays to issuing planning consents linked to viability and affordable

housing negotiations and securing planning obligations such as education

contributions

Market Factors including absorption rates and developers not bringing sites

forward due to economic / market conditions

4.8 Housing supply and strategic site delivery is still currently considered together as

part of the Christchurch and East Dorset Core Strategy joint plan area. This will

change following the adoption of the BCP and Dorset Council Local Plans which

are anticipated for adoption in 2022 and 2023 respectively. Dorset Council are

preparing an HDT Action Plan and will identify detailed actions to deal with

strategic site delivery in East Dorset. However, the BCP Council, where

appropriate will work closely with the Dorset Council to assist delivery. For

Page 21: Housing Delivery Test Action Plan 2019 - 2022 1... · APPENDIX 1 1 1 Introduction Background 1.1 In February 2017, the Housing White Paper ‘Fixing our broken housing market’ was

20

example, cross border working on strategic transport planning can assist in site

delivery.

Poole

4.9 Poole adopted its Local Plan in 2018, which included a number of new allocations

including urban extensions at North Poole. The key focus of the plan was,

however, Poole town centre regeneration and delivery of a number of major

brownfield sites that collectively can deliver around 5,000 homes. Progress has

stalled on many of these brownfield sites due to long standing viability issues

associated with remediation and delivery of critical infrastructure such as flood

defences.

Actions

4.10 As part of the BCP Local Plan preparation all allocations in the adopted Local

Plans will be reviewed and the deliverability of new allocations confirmed.

4.11 BCP will adequately resource the planning officer teams to facilitate the timely

determination of major housing allocations applications. .

4.12 In terms of Roeshot Hill in Christchurch, BCP will also be working closely with the

Christchurch Town Council to bring forward the Roeshot Hill Allotments site so

that the entire Core Strategy allocation can be delivered.

4.13 BCP Council is also working closely with the landowner to progress a planning

application for the Core Strategy allocation on Land South of Burton. This will also

link to the consideration of a possible larger allocation to be considered through

the preparation of the BCP Local Plan.

4.14 BCP Council will continue to focus efforts on helping to unlock Poole Town Centre

regeneration through working with partners, reviewing funding options and

considering other interventions required to hell kick start delivery.

4.15 BCP Council will also co-ordinate cross border working, where appropriate to help

facilitate delivery of strategic allocations in the East Dorset area. Co-ordinated

actions include the preparation of the SEDUMS study, Local Transport Plan,

Bournemouth International Growth Programme, Western Gateway Transport

Strategy and Transforming Cities.

Page 22: Housing Delivery Test Action Plan 2019 - 2022 1... · APPENDIX 1 1 1 Introduction Background 1.1 In February 2017, the Housing White Paper ‘Fixing our broken housing market’ was

21

Sites with Existing Uses

4.16 Across the BCP area there are sites in existing use where residential development

is planned but cannot come forward until the existing use ceases, thereby

delaying delivery. Examples of these sites include the Poole Civic Centre and St.

Mary’s Maternity Hospital.

Action

4.17 As part of the BCP accommodation plan timescales will be confirmed in the short

term for the Poole Civic Centre redevelopment. Timescales will also be confirmed

for bringing forward the hospital site through direct discussions with the NHS. in

BCP Car Parking Requirements

4.18 Across the BCP area there is a need to provide an updated strategic approach to

car parking provision, to ensure that car parking needs are met alongside the

delivery of key housing sites.

4.19 Sites in Bournemouth Town Centre, which are being developed by the

Bournemouth Development Company, are subject to delay due to the issue of

securing the re-provision of parking in accordance with policy requirements.

Action

4.20 A new BCP Car Parking Strategy will be prepared in step with the preparation of

the BCP Local Plan.

BCP Officer Resources

4.21 BCP Council was recently formed in April 2019 and a staff restructuring process is

currently underway. The restructuring process will need to ensure that appropriate

resources are dedicated to planning policy, development management, transport

planning and housing enabling. This is necessary to ensure that all departments

associated with housing delivery are sufficiently resourced to increase the supply

of homes.

Action

4.22 In the short term BCP will ensure the most efficient and effective use of the

existing staff resource across BCP and improve this resource where possible. As

part of the BCP restructuring process the Council will need to ensure that

departments associated with housing delivery are sufficiently resourced to

address the key priority of increasing housing supply across all tenures.

Page 23: Housing Delivery Test Action Plan 2019 - 2022 1... · APPENDIX 1 1 1 Introduction Background 1.1 In February 2017, the Housing White Paper ‘Fixing our broken housing market’ was

22

The Housing Service Unit will be increasing the staff resources focused on the

housing supply agenda to help ensure a proactive and sustained approach to

enable a ‘step-change’ in overall housing delivery.

Sub Issue 2: Government Housing Methodology & Housing Land Supply

4.23 Across the BCP area there are separate adopted Local Plans in place for the

Bournemouth, Christchurch and Poole areas.

4.24 Sufficient housing land supply has been identified through the BCP Strategic

Housing Land Availability Assessments (SHLAAs) to meet adopted Local Plan

housing targets.

4.25 The issue facing BCP is that the Bournemouth and Christchurch and East Dorset

Core Strategies are now more than 5 years old and the relevant housing targets

for these plan areas is now based on the Government’s standard methodology

from 2019/20 onwards. In Bournemouth, this means there is a substantial uplift in

the annual housing requirement from 730 to 1,422 dwellings per annum. In

Christchurch and East Dorset the annual housing delivery requirement, also

based on the Government’s standard methodology, increases from 566 per

annum to 791 dwellings per annum. Christchurch’s proportion of this target, which

the BCP Local Plan will be responsible for is 349 dwellings per annum.

4.26 BCP Council faces a challenge in identifying sufficient land for housing to meet the

uplift in housing requirement from 2019/20 onwards.

Actions

BCP Local Plan

4.27 A BCP Local Plan is being prepared which will supersede current adopted Local

Plans in the Bournemouth, Christchurch and Poole areas. The Local Plan is being

prepared to an accelerated timeframe with adoption scheduled for 2022. The new

Local Plan will seek to identify a range of new allocations to improve the supply of

new housing. BCP will also be working closely with the Dorset Council, Hampshire

County Council and New Forest District Council regarding the delivery of any

unmet housing need which cannot be met in the BCP area.

Strategic Housing Land Availability Assessments & Employment Land Reviews

4.28 Strategic Housing Land Availability Assessments and Employment Land Reviews

will be reviewed and updated to inform the BCP Local Plan and to identify further

housing potential. SHLAA updates provide the opportunity for further sites to be

identified and to review approaches to housing densities on existing SHLAA sites.

Page 24: Housing Delivery Test Action Plan 2019 - 2022 1... · APPENDIX 1 1 1 Introduction Background 1.1 In February 2017, the Housing White Paper ‘Fixing our broken housing market’ was

23

This also provides the opportunity to contact landowners regarding specific sites

where there may be uncertainty concerning whether a site will come forward.

4.29 As part of the SHLAA process, the Council is also undertaking a detailed urban

capacity study to consider what additional potential for housing there is across the

most sustainable parts of the BCP area.

4.30 Updating employment land reviews and employment land projections will inform

the potential release of employment land for housing where not required to meet

future market requirements over the BCP plan period.

Strategic Green Belt Review

4.31 To inform the preparation of the BCP and Dorset Council Local Plans, a strategic

review of the South East Dorset Green Belt will be considered . The preparation of

this evidence will inform possible strategic council decisions regarding amendment

to Green Belt boundaries that may need to be made to accommodate new

housing. BCP will seek to engage the Dorset Council, New Forest District Council

and National Park authorities in undertaking a comprehensive study for the South

East Dorset Green Belt as a whole.

BCP Property Strategy

4.32 The BCP Property Strategy is currently being prepared and this will aim to

maximise the use of Council owned land, where appropriate for residential

development. This builds on lots of work over the last few years within the legacy

Councils, working across teams to bring forward surplus Council owned land and

building for residential development. We need to further maximise this

identification of surplus land where possible and encourage the use as housing

sites. Many housing developments have already come forward on surplus Council

owned sites over the last few years.

Land Acquisitions / Land Assembly

4.33 In order to improve the supply of land for housing, the Council will consider the

acquisition of land where appropriate. Land acquisition may also be achieved

through joint ventures in terms of potential joint bids for acquiring land.

4.34 BCP will review opportunities to work with other public sector bodies to deliver

sites for housing through land assembly. An example of where this has been

achieved is the Magistrates Court Site, Barrack Road as well as Gravel Hill.

Developing strong links with other public sector agencies will be key to identifying

surplus sites and engaging in land assembly discussions. This will include

discussions with Health colleagues.

Page 25: Housing Delivery Test Action Plan 2019 - 2022 1... · APPENDIX 1 1 1 Introduction Background 1.1 In February 2017, the Housing White Paper ‘Fixing our broken housing market’ was

24

Joint Ventures / Registered Providers

4.35 There is an opportunity to develop structured partnerships such as joint ventures

developing shared approaches with Registered Providers (RPs) to improve the

supply of housing. Registered Providers are key in the development of new

homes including affordable housing provision locally. The Council will be working

proactively with RPs to ensure their investment in new housing locally.

Compulsory Purchase Orders (CPOs)

4.36 It is important that BCP considers a wide range of measures that may be required

to improve housing land supply. CPOs have not been widely used across the BCP

area. The Council will explore the potential use of CPO where necessary and seek

funding for expert advice to guide the use of CPO in the BCP area.

National Housing and Finance Institute (HFi) / Local Government Association

4.37 BCP will work closely with the HFi and the LGA to help to identify further

opportunities to increase housing land supply. This will help ensure that

national good practice is identified in this emerging agenda.

Sub Issue 3: Progress with Duty to Co-operate and cross border strategic

planning

4.38 BCP Council faces a significant challenge in future housing delivery through a

step change in housing requirements based on the Government’s standard

methodology.

4.39 BCP has commenced work on a BCP Local plan that will supersede the current

adopted local plans currently in place for Bournemouth, Christchurch and Poole.

The Council will need to work effectively with neighbouring authorities to ensure

housing needs can be addressed. In accordance with the Duty to Co-operate BCP

works closely with neighbouring authorities regarding housing delivery including

the Dorset Council, Hampshire County Council, New Forest District Council, and

the New Forest National Park.

4.40 This process of Local Plan preparation may need to examine how any unmet

housing needs could be met in an adjoining authority area. Prior to the formation

of the BCP and Dorset Council there has been positive cross border working

between the former Bournemouth, Dorset and Poole councils and with the New

Forest District Council and National Park Authority.

Page 26: Housing Delivery Test Action Plan 2019 - 2022 1... · APPENDIX 1 1 1 Introduction Background 1.1 In February 2017, the Housing White Paper ‘Fixing our broken housing market’ was

25

4.41 Section 3 of this Action Plan has reviewed cross border approaches including:

The effectiveness of the Strategic Planning Forum

Statement of Common Ground between former Bournemouth, Dorset and

Poole local authorities

Possible cross border approaches for housing distribution

Actions

4.42 BCP will review the terms of reference of the Strategic Planning Forum in the

context of the new BCP and Dorset Council to improve its effectiveness.

The existing Statement of Common Ground previously prepared by the

Bournemouth, Dorset and Poole authorities will be reviewed in order to more

effectively deal with cross border strategic planning issues including housing

delivery.

4.43 BCP will work with the Dorset Council and Hampshire authorities to consider a

range of options to address cross border strategic planning issues including

housing delivery which will explore the following possible options:

Statements of Common Ground

Informal Strategies

Explore potential for Strategic joint statutory Plans

Sub Issue 4: Unimplemented Planning Consents

4.44 BCP local plan monitoring has identified a number of unimplemented planning

consents which affect housing land supply. There are also many cases of the

unimplemented consents being superseded by new applications for revised

schemes. This introduces a delay in housing delivery which was envisaged to

come forward in line with original planning consents.

Action

4.45 This is not a straightforward issue for the Council to influence. One approach

could be to limit the time from the issue of planning consent to implementation. In

terms of revised schemes the council can apply sufficient development

management resources to deal with applications expediently.

Sub Issue 5: Environmental and other Constraints

4.46 The BCP Council area is subject to a significant level of environmental constraints

including areas liable to flood, Green Belt, Special Protected Areas, Sites of

Page 27: Housing Delivery Test Action Plan 2019 - 2022 1... · APPENDIX 1 1 1 Introduction Background 1.1 In February 2017, the Housing White Paper ‘Fixing our broken housing market’ was

26

Special Scientific Interest and Conservation Areas that affects the amount of land

available for housing. It is also important to recognise that these constraints

contribute to BCP’s rich and diverse natural and built environment meaning

therefore that they need to be balanced with the requirements to deliver housing.

Actions

4.47 The Council will need to undertake detailed assessment of the area’s constraints

when preparing the Local Plan alongside the urban capacity work. These

workstreams will inform the amount of housing the area can reasonably plan for

as well as establish the extent of any shortfall that would need to be addressed

through the Duty to Cooperate and discussions with adjoining authorities.

Strategic Issue: Infrastructure

4.48 The second strategic issue affecting housing delivery in BCP concerns delivery of

strategic infrastructure required to facilitate development. Sub issues relating to

this issue include:

1. Overall Strategic infrastructure required to support development

2. Suitable Alternative Green Space (SANG) delivery

3. Transport Strategy and delivery of Strategic transport infrastructure

4. Flood Risk Strategy & Infrastructure

Sub Issue 1: Overall Strategic infrastructure required to support

development

4.49 The BCP Local Plan will need to plan effectively for the full range of infrastructure

requirements required to support new development across the plan period.

Actions

BCP Local Plan Infrastructure Delivery Plan

4.50 The BCP Local Plan will be underpinned by an Infrastructure Delivery Plan which

will identify the range of infrastructure required to support delivery of the Local

Plan. This will be required to be published alongside the Pre Submission stage of

the Local Plan scheduled for autumn 2021.

External Funding

4.51 BCP will continue to develop and strengthen our working relationship with Homes

England and take advantage of funding opportunities as they arise to support the

Page 28: Housing Delivery Test Action Plan 2019 - 2022 1... · APPENDIX 1 1 1 Introduction Background 1.1 In February 2017, the Housing White Paper ‘Fixing our broken housing market’ was

27

delivery of housing. A strategic relationship with Homes England will be further

developed at a senior level to encourage thinking around enabling sites to come

forward and help access funding for specific schemes

4.52 BCP will also actively continue to lever in external sources of funding such as

Growth Deal and the Transforming Cities Fund to deliver key strategic

infrastructure to support housing delivery.

Sub Issue 2: Suitable Alternative Green Space (SANG delivery)

4.53 The adopted Local Plans for Bournemouth, Christchurch and Poole require

housing development within 5km of the heathland to mitigate its impact from

increased recreational pressure on the Dorset Heaths. Housing development

within BCP is required by national and local policy to contribute to heathland

mitigation or SANG provision.

4.54 In Bournemouth and Christchurch in particular, the delivery of some strategic sites

have been held up through timescales to secure and deliver necessary SANG

provision. A more effective approach towards SANG provision and delivery is

required across the BCP area to avoid delays to development.

Actions

BCP Local Plan

4.55 Preparation of the new BCP Local Plan will identify and allocate new SANGs,

where required to support new housing development.

BCP SANG Strategy

4.56 The development of a strategic SANG strategy for the BCP area will examine a

range of options including:

Stour Valley Strategic SANG

Two Riversmeet / Stanpit Recreation Ground

Upton Country Park SANG

Hicks Farm

4.57 BCP will need to consider progressing this strategy in advance of the adoption of

the BCP Local Plan to ensure that heathland mitigation requirements to support

new development are met.

Page 29: Housing Delivery Test Action Plan 2019 - 2022 1... · APPENDIX 1 1 1 Introduction Background 1.1 In February 2017, the Housing White Paper ‘Fixing our broken housing market’ was

28

South East Dorset Heathland SPD

4.58 The review of the current Heathland SPD will be undertaken by BCP and the

Dorset Council. This will identify a range of new SANG and heathland

infrastructure projects to support new development. The forthcoming update of the

SPD will cover the period of 2020 – 2025. The revised Heathland SPD will be in

place by April 2020.

Sub Issue 3: Transport Strategy and delivery of Strategic transport

infrastructure

4.59 The preparation of the BCP Local Plan will need to be underpinned by the

appropriate evidence base and transport strategy to enable new residential

development to come forward sustainably.

4.60 In order to avoid delay in preparation and adoption of the BCP Local Plan the

South East Dorset Urban Mobility Study is required to test the deliverability of new

housing options and to identify strategic transport mitigation measures.

4.61 In terms of strategy and effective cross border planning there is also a need to

consider how Local Transport Plan 3 will be updated for the BCP and Dorset

Council area.

4.62 BCP will also need to lever in sources of external funding to secure the delivery of

strategic transport improvements.

Actions

South East Dorset Urban Mobility Study

4.63 Completion of the South East Dorset Urban Mobility Study will be required to

inform the options stage of the BCP Local Plan which is scheduled for autumn

2020.

Local Transport Plan

4.64 Local Transport Plan 3 provided the transport strategy for the Bournemouth,

Dorset and Poole Area. BCP is currently considering options for the preparation of

LTP4 which include determining the administrative area of coverage. It is

envisaged that LTP4 will be prepared in step in with the preparation of the BCP

Local Plan.

Western Gateway Transport Body

Page 30: Housing Delivery Test Action Plan 2019 - 2022 1... · APPENDIX 1 1 1 Introduction Background 1.1 In February 2017, the Housing White Paper ‘Fixing our broken housing market’ was

29

4.65 BCP will continue to work closely with the Western Gateway Transport Body to

deliver strategic transport infrastructure on a regional planning level that helps to

facilitate new residential development in the BCP area. The preparation of the

regional transport strategy by 2021 will be important alongside the preparation of

local transport strategies to facilitate new development.

Sub Issue 4: Flood Risk Strategy & Infrastructure

4.66 Significant areas of central Christchurch and Poole are affected by tidal and fluvial

flood risk where appropriate flood risk strategies and mitigation is required to

enable residential development to come forward.

4.67 In Poole a strategic approach is being developed to deliver strategic flood defence

infrastructure to support new residential development in the Twin Sails

Regeneration area. This will look at funding arrangements including how

developer contributions could be used.

Actions

Christchurch Town Centre Floodrisk SPD

4.68 A supplementary planning document is currently being prepared for the town

centre study area. The SPD will provide a planning framework and identify a

package of floodrisk mitigation measures to enable residential development to

come forward within the study area.

Christchurch Strategic Flood Risk Assessment

4.69 The SFRA Level 2 for Christchurch has been updated with guidance for

developers to provide an up to date position and clarity on future floodrisk and

where residential development is appropriate.

Poole Flood Defence Grant

4.70 Funds have been secured to prepare an outline business case for funds from

Flood Defence Grant Aid for flood defences along the West Quay Road and

southern part of Holes Bay Road. Funding will also be required from developers to

secure implementation.

Strategic Issue: Viability

4.71 The third overarching issue affecting housing delivery in BCP concerns

development viability. Sub issues relating to this issue include:

Page 31: Housing Delivery Test Action Plan 2019 - 2022 1... · APPENDIX 1 1 1 Introduction Background 1.1 In February 2017, the Housing White Paper ‘Fixing our broken housing market’ was

30

1. Sites not coming forward due to viability issues.

2. Delays linked to S106 negotiations including affordable housing

Sub Issue 1: Sites not coming forward due to viability issues

4.72 Adopted local plans prepared across the BCP area have been prepared with plan

wide viability appraisals that also informed current adopted CIL charging

schedules. Therefore, for BCP generally viability has not been a significant area

wide issue affecting housing delivery.

4.73 However, there are significant sites in Poole Town Centre and the Twin Sails

Regeneration Area which have not come forward due to viability issues. Some

schemes within these areas have not come forward as they have not achieved a

sufficient uplift in land value following grant of planning permission. This is linked

to the price paid for land pre-recession and in conjunction with policy requirements

for the area (Including flood risk infrastructure).

4.74 Although not currently a barrier to residential development there are separate CIL

charging schedules for the Bournemouth, Christchurch and Poole areas that were

produced at separate times. Through the preparation of the BCP Local Plan CIL

charging schedules will need to be reviewed to ensure CIL charging regimes

remain viable with updated policy requirements.

4.75 As part of the preparation of the BCP Local Plan and revised CIL charging

schedules a Local Plan viability study will be required to test the impact of all

policy requirements in accordance with national policy.

Actions

4.76 BCP CIL Charging schedules will be reviewed in step with the preparation of the

BCP Local Plan and associated plan wide viability study.

Sub Issue 2: Planning Permission Delays linked to S106 negotiations

including affordable housing

4.77 Across the BCP area and East Dorset there have been delays to the

determination of planning applications due to the time involved in the negotiation

of planning obligations including affordable housing, education and transport

contributions. Delays are linked to the processes for appraising planning

application viability assessments and BCP access to appropriate viability

expertise.

Page 32: Housing Delivery Test Action Plan 2019 - 2022 1... · APPENDIX 1 1 1 Introduction Background 1.1 In February 2017, the Housing White Paper ‘Fixing our broken housing market’ was

31

4.78 Significant delays have also been experienced in the Christchurch area in terms of

the time taken to establish robust justification for education contributions whilst

part of a two tier authority.

Actions

Viability Appraisal Review

4.79 BCP will review its processes for planning application viability appraisals which will

examine the following options:

a) Potential for developing a framework of viability experts or internal expertise for

BCP

b) BCP to put in place more robust quality control measures regarding viability

advice received.

c) Training for planning officers regarding scheme design / layout / density issues

that affect viability.

d) Review validation checklist guidance of viability.

Strategic Issue: Economic Factors / Housing Market

4.80 The fourth strategic issue affecting housing delivery across the BCP area

concerns Economic Factors / Housing Market. Sub issues related to this issue

include:

1) Market Absorption Rates / Impact on Housing Delivery /

2) Economic Conditions / Impact of Brexit.

4.81 Housing supply across the BCP area includes 81 strategic sites (40+ dwellings)

which are planned to deliver 13,180 dwellings. The adopted Core Strategy for

Christchurch also includes the East Dorset area where there are 10 remaining

allocated strategic sites to come forward. These sites form a key part of the

housing land supply for the Christchurch and East Dorset plan area.

4.82 It is anticipated that as further strategic housing allocations begin to come forward

across BCP and East Dorset there may be issues associated with market

absorption rates. There are a number of sites that will offer a similar market

product and developers may slow the rate of housing delivery to reflect local

market absorption rates.

4.83 Further work is required to establish a clearer picture regarding market absorption

rates, the BCP housing trajectory and the impact of multiple strategic sites which

are anticipated to come forward concurrently.

Page 33: Housing Delivery Test Action Plan 2019 - 2022 1... · APPENDIX 1 1 1 Introduction Background 1.1 In February 2017, the Housing White Paper ‘Fixing our broken housing market’ was

32

4.84 The overall economic climate and impact of Brexit is also affecting the local

housing market, however further evidence is required to better understand the

impact this will have over time in BCP and Dorset.

Actions

4.85 The issue of market absorption rates and strategic site delivery will be explored

further through a developers’ forum and also through the Strategic Planning

Forum and Dorset wide Strategic Housing Group.

4.86 BCP will consider engaging a consultant to review economic factors influencing

the delivery of housing in the BCP area. BCP will seek to engage the Dorset

Council in this area of work in order to understand the implications for the cross

border delivery of housing.

4.87 The BCP SHLAAs will be reviewed in step with the preparation of the BCP Local

Plan to further assess the range of housing sites to provide the best mix to suit

market absorption rates and the needs of the local housing market.

4.88 The BCP Local Plan preparation will also consider new housing allocations and

the appropriate mix of sites and housing products to provide a suitable range of

housing to meet market requirements. This will also include reviewing the potential

to promote use of modular construction as part of the Government’s drive to use

this to help with increasing supply.

Strategic Issue: Commercial Market Communications

4.89 The fifth strategic issue affecting housing delivery across the BCP area concerns

Commercial Market Communications. The following sub issue relates to this

strategic issue:

1. Effective Engagement with the Development Industry

4.90 BCP engages with the development industry and has done so in the preparation

of this action plan. However, further engagement is required on a more regular

basis to fully capture and address all the key issues affecting housing delivery in

the BCP area.

Page 34: Housing Delivery Test Action Plan 2019 - 2022 1... · APPENDIX 1 1 1 Introduction Background 1.1 In February 2017, the Housing White Paper ‘Fixing our broken housing market’ was

33

Actions

4.91 BCP has written to planning agents regarding progress with existing planning

permissions to review progress and to provide the opportunity for issues affecting

housing delivery to be raised.

4.92 A BCP developers’ forum will be established to meet regularly to assess the

issues affecting housing delivery in BCP and how these will be addressed.

4.93 In addition to this, Housing will assist in the proactive face to face engagement

with developers, land owners and funders to help bring forward housing sites

through to completion. Links with Economic Development colleagues will be a key

part of this to encourage the wider promotion of the BCP as an area for people to

invest in. An engagement strategy will be developed to ensure engagement on

both a local and national scale to bring forward opportunities wherever possible.

This outward facing industry wide engagement will identify additional interventions

and help shape the overall strategy going forward.

4.94 A communications strategy will be developed with multiple audiences to ensure

that there are high profile communications around this work programme to help

encourage a shared vision and ultimately a ‘step change’ in deliver

Summary

4.95 This section has reviewed in detail the five key strategic issues that affect housing

delivery across the BCP area including setting out a series of actions to address

them.

4.96 Section 5 brings these actions together into a set of SMART Action Plan with

associated timescales for implementation.

Page 35: Housing Delivery Test Action Plan 2019 - 2022 1... · APPENDIX 1 1 1 Introduction Background 1.1 In February 2017, the Housing White Paper ‘Fixing our broken housing market’ was

APPENDIX 1

34

5 BCP HDT SMART Action Plan

Root Cause Evidence Action Who / When Action Achieved?

Strategic Issue: Housing Land Supply

1) Strategic Site Delays

Bournemouth Housing Allocations:

Some sites allocated in Bournemouth Town Centre Area Action Plan (AAP) may not come forward as planned affecting housing supply e.g. Commercial Road/ Avenue Road, Asda (Holdenhurst Road), and Holdenhurst Retail Park.

Allocations to be reviewed through BCP Local Plan.

Planning Policy / December 2022.

Policy CN1 - Christchurch Urban Extension: Delays in relation to Local Plan site trajectory. Delays linked to SANG application, time taken to sign S106, Developer and land owner land transaction, abnormal on site infrastructure i.e. pylons.

BCP Planning Co-ordination of Reserved Matters for Roeshot Hill with applicant.

Planning Policy and Development Management / 2019 / 2020.

BCP work with Christchurch Town Council to bring forward Roeshot Hill Allotments (as part of allocation site) including identification of alternative allotments site.

Policy CN2 - Land South of Burton:

Landowner wishes to pursue larger allocation as part of BCP Local Plan preparation. .

Working with landowner towards submitting application for existing allocation that would not prejudice possible larger allocation considered as part of BCP Local Plan.

East Dorset Housing Allocations: Delays in strategic sites coming forward in East Dorset (as part of Christchurch and East Dorset adopted Core Strategy 2014). Delays linked to road infrastructure, viability and affordable housing negotiation, site access, SANG delivery, market and absorption rates.

Co-ordination between BCP and DC HDT Action Plans BCP and DC Planning Policy / August 2019 / Ongoing

Sites with existing uses:

Sites reliant on current use ceasing before allocated use comes forward i.e. Poole Civic Centre and Maternity Hospital.

As part of BCP accommodation plan to confirm timescales for Poole Civic Centre redevelopment.

Confirm timescales for hospital site in conjunction with Wessex Fields development in Bournemouth.

BCP Property Services / Development Management / Planning Policy / 2019 / 2020.

BCP Car Parking Requirements:

Strategic sites in Bmth Town Centre include car parks being developed by Bournemouth Development Company. Delays associated with re-providing car parking in accordance with policy requirements and viability impacts. Car parking requirements and wider town centre provision have also been raised regarding the Magistrates Court site in Christchurch.

A new BCP wide car parking strategy will be prepared. Planning Policy / Development Management / Property Services / 2019/20.

Viability:

Delays in Poole Town Centre Regeneration Area sites linked to viability (addressed in viability section of AP).

Addressed in viability section of Action Plan.

Addressed in viability section of Action Plan.

BCP Officer Resources:

BCP Development Management / Planning Policy / Housing and Transport Planning teams resource limitations affecting timing for delivery of strategic sites.

Delays in time taken to sign S106 agreements and issue planning permissions. (Not possible to influence delays caused by private landowner / developer negotiations).

Improvement in the resourcing of Development Management, Planning Policy, Housing and Transport Planning teams as part of BCP reorganisation process.

Growth and Infrastructure Director and Head of Planning / 2019/20.

Increase proactive housing enabling resources within the BCP Housing Team to encourage sites to come forward that are of mixed tenure.

Growth and Infrastructure Director / Director of Housing (2019/20)

Page 36: Housing Delivery Test Action Plan 2019 - 2022 1... · APPENDIX 1 1 1 Introduction Background 1.1 In February 2017, the Housing White Paper ‘Fixing our broken housing market’ was

35

Root Cause Evidence Action Who / When Action Achieved?

2) Government Housing Methodology & Housing Land Supply.

Adopted BCP Local Plans and Strategic Housing Land Availability Assessments (SHLAAs) do not identify sufficient land to meet future requirements based on government methodology.

Strategic Housing Land Availability Assessments:

Some SHLAA sites submitted to the Councils have not come forward for development.

Uncertain whether some sites in BCP SHLAAs included in the 6 – 15 year land supply will come forward (identified from officer survey). These include following site types:

Existing viable commercial uses (office, car dealers, builders merchants); Caravan Parks (Xch); and

Residential for redevelopment i.e. outworn flats, existing residential plots.

Sufficient land to meet adopted Local Plan housing targets but future Bournemouth and Christchurch requirements now based on Government standard methodology which creates a major uplift and step change in housing delivery requirements.

BCP SHLAA and Employment Land Review updates including update of BCP / DC employment land projections.

BCP SHLAA and ELR Update reviewing assumptions and contacting landowners regarding uncertain sites.

Review Sovereign Housing stock and redevelopment opportunities.

Further potential SHLAA sites to be identified in BCP area.

Planning Policy / SHLAA annual updates / ELR 2019 - 2021.

SHLAA annual updates complete summer 2019.

Maximise use of Council owned land for residential development linked to the BCP Property Strategy.

Planning Policy / Property Services– October 2019 onwards.

BCP Strategic Green Belt Review / Potential Co-ordination with Dorset Council.

Planning Policy / 2019 / 20

Prepare BCP Local Plan and identify new housing allocations.

Planning Policy / December 2022.

BCP to explore use of Compulsory Purchase Orders (CPO) to increase land available for housing development.

To seek appropriate funding for expertise to guide the use of CPO in BCP.

Planning Policy / Development Management / Housing / 2019 / 20

Council to consider land acquisitions to increase land supply for housing e.g. Canford Heath Road, Gravel Hill, Police Station. Consider joint ventures to make joint bids for acquiring land.

Planning Policy / Housing / Development Management / Property / 2019 - 2022

Work with public sector agencies to encourage land assembly options and use of surplus sites / building for residential e.g. Barrack Road, Magistrates Court Site, Xch.

Property Services, Housing / Planning Policy / Development Management (2019 ongoing)

Develop structured partnerships such as joint ventures / development share approach with developing Registered Providers to increase supply. BCP working with RPs through joint ventures to bring sites forward.

Director of Housing (October 2019 onwards)

Work with the national Housing and Finance Institute (HFI) and Local Government Agency to help identify further opportunities to increase housing land supply.

Director of Housing and Director of Growth and Infrastructure 2019 - Ongoing

Cross boundary strategic planning with Dorset Council and Hampshire local authorities (as set out below).

As set out below.

3) Unimplemented Planning Consents BCP wide monitoring has identified a number of unimplemented planning consents which are superseded by revised schemes resulting in delays to site / housing delivery.

Also issue of landowners not willing to bring forward sites for consented use (e.g. town centre / regeneration area, Poole).

Review time limit from the issue of consent to implementation.

Sufficient development management resource applied to revised applications.

BCP Planning / 2019 / 2020.

4) Duty to Co-operate and Cross BCP / Dorset Council (DC) Strategic Planning Forum (SPF) lacking effectiveness. BCP and DC to review terms of reference of SPF. BCP and DC Planning Policy / 2019.

Page 37: Housing Delivery Test Action Plan 2019 - 2022 1... · APPENDIX 1 1 1 Introduction Background 1.1 In February 2017, the Housing White Paper ‘Fixing our broken housing market’ was

36

Root Cause Evidence Action Who / When Action Achieved?

Border Working

Current SOCG for BCP / DC only identifies cross boundary strategic issues. There is a need to revise to deal effectively with housing distribution and un met housing need.

Review current BCP / DC SOCG BCP and DC Planning Policy / 2019.

Lack of cross boundary agreed strategy / approach between BCP, Dorset Council and Hampshire to address housing need across these administrative areas.

BCP and DC to review options and agree approach to address future housing requirement.

Options:

1. SOCG

2. Informal Strategy

3. Strategic BCP / DC Plan (potentially with Hampshire).

BCP and DC Planning Policy / 2019/2020.

Strategic Issue: Infrastructure

1) Strategic infrastructure required to support housing development.

In particular Local Plan evidence identifies deficiencies in strategic infrastructure across the BCP / Dorset Council area which holds up housing development. This is particularly in relation to transport infrastructure and SANGs.

Develop and strengthen our working partnership with Homes England to take advantage of funding opportunities.

BCP Housing, Planning Policy 2019 onwards

BCP to work actively with the Homes England, Dorset LEP and the Western Gateway Transport body to lever in relevant funding sources to deliver key infrastructure to support housing investment and delivery.

BCP, Growth and Infrastructure 2019 onwards.

Prepare BCP Local Plan Infrastructure Delivery Plan, confirm funding sources and delivery mechanism for key infrastructure.

Planning Policy / Autumn 2021.

2) SANG provision holding up sites in Christchurch and Bournemouth.

Strategic urban area sites in Christchurch and Bournemouth held up by the timing for securing and delivering SANG policy requirements.

Strategic SANG delivery:

1. Stour Valley (including production of masterplan).

2. Two Riversmeet / Stanpit Rec SANG.

3. Meyrick Estate options

4. Hicks Farm

BCP Planning Policy / Parks and Countryside / 2019/2020.

South East Dorset Heathland SPD update – (including new SANG and HIPs projects).

BCP / DC Planning Policy / Countryside teams / (March 2020)

BCP Local Plan allocating strategic SANGs. BCP Planning Policy / Dec 2022.

3) Transport Strategy and delivery of strategic transport infrastructure.

For BCP Local Plan to progress SEDUMs study is needed to test deliverability of new housing options and to identify mitigation options required. Following this the BCP LP Infrastructure Delivery Plan can be prepared. Sources of government funding will be required to deliver strategic transport infrastructure.

There is a need to consider the preparation of an updated Local Transport Plan for BCP and Dorset to co-ordinate the delivery of a cross border transport strategy.

Completion of South East Dorset Urban Mobility Study (SEDUMs).

BCP and DC Transport Planning / Autumn 2019.

BCP Local Plan Infrastructure Delivery Plan. Planning Policy / Autumn 2020.

BCP Transforming Cities Bid / pursuing other government sources of funding.

BCP / 2019/20 and ongoing

BCP Local Plan preparation.

Planning Policy / December 2022.

Consider options for preparation of Local Transport Plan 4.

Prepare Local Transport Plan BCP / DC 2019 / 20.

BCP / DC 2022.

4) Flood risk strategy & Infrastructure

Housing prevented from coming forward on brownfield land in Christchurch Town Centre due to floodrisk.

Prepare Christchurch Town Centre Floodrisk SPD to provide framework for development to come forward.

Planning Policy / Spring 2020.

Page 38: Housing Delivery Test Action Plan 2019 - 2022 1... · APPENDIX 1 1 1 Introduction Background 1.1 In February 2017, the Housing White Paper ‘Fixing our broken housing market’ was

37

Root Cause Evidence Action Who / When Action Achieved?

Update and publish revised Christchurch Level 2 SFRA and guidance for developers.

Planning Policy / September 2019.

Complete

Impact of strategic flood infrastructure costs in Poole i.e. flood defences on West Quay Road. Need to reduce cost for flood risk infrastructure delivery.

Secured funding to prepare outline business case for funds from Flood Defence Grant in Aid for flood defence scheme along West Quay Road and southern part of Holes Bay Road (Funding earmarked for EA MTP funding 2021/22. Will also require developer contributions for implementation.

BCP Planning / 2021/22

Strategic Issue: Viability

1) Sites not coming forward due to viability issues.

Sites in Poole, including specific sites with planning permission not coming forward due to viability issues. Schemes do not have a sufficient up lift in value to bring forward linked to price paid for land pre-recession and with policy requirements addressed e.g. 27-31 West Quay Road, and Salterns Marina.

New Poole CIL charging schedule including zero rating for development in Poole town centre and Twin Sails Regeneration Area.

Zero rating of specific sites for CIL (Complete, Feb 19).

Complete

BCP forward funding of strategic flood risk infrastructure in Poole Regeneration Area.

Forward funding of floodrisk infrastructure (Complete).

10% affordable housing requirement in Poole Regeneration Area.

Planning Policy / Completed as part of Poole LPR.

Complete

More flexible approach in Poole TC / regeneration area to mix of uses.

Planning Policy / Completed as part of Poole LPR.

Complete

A less restrictive approach to building heights, particularly in Poole Town Centre North and Twin Sails Regeneration Area.

Planning Policy / Completed as part of Poole LPR.

Complete

Separate charging schedules in Bournemouth, Christchurch and Poole adopted at different times. Need to be reviewed to check viability and in step with BCP Local Plan Review.

Review BCP CIL Charging Schedules. Planning Policy / 2020 / 21

Lack of BCP wide evidence to inform preparation of BCP Local Plan.

Rise in build costs affecting viability in the BCP area e.g. Belvedere Hotel, Bournemouth.

Prepare BCP Local Plan Viability Study to inform Local Plan review process.

Planning Policy / September 2020.

2) Delays linked to S106 negotiations including affordable housing.

Delays to determining applications including strategic sites due to negotiations on planning obligations including affordable housing, education and transport.

Planning Applications Viability Appraisal Review:

Develop framework of viability experts to draw on relevant to type of application e.g. small scale or strategic site.

BCP to put in place more robust quality measures for viability advice received.

Training for DM officers to pick up on scheme design / layout / density issues prior to viability appraisals.

Review validation checklist guidance of viability.

Growth and Infrastructure Director and Head of Planning / 2019/20.

Strategic Issue: Economic Factors / Housing Market

1) Market absorption rates & impact on housing delivery

Multiple allocations not coming forward across BCP / East Dorset at same time due to similar market product. Need further evidence to examine in detail.

To be explored through developers forum and Dorset wide strategic housing group.

Planning Policy, Economic Development Team / 2019 / 2020

BCP to engage consultant to review relevant economic factors for BCP area.

Review of BCP SHLAAs to identify greater range of sites. Planning Policy / Annual reviews 2019 onwards

2019 SHLAA reviews complete.

BCP Local Plan to review allocations and ensure appropriate balance of larger and smaller sites

Planning Policy / December 2022.

Page 39: Housing Delivery Test Action Plan 2019 - 2022 1... · APPENDIX 1 1 1 Introduction Background 1.1 In February 2017, the Housing White Paper ‘Fixing our broken housing market’ was

38

Root Cause Evidence Action Who / When Action Achieved?

2) Economic Conditions / Impact of Brexit.

Economic conditions and the impact of Brexit are affecting the housing market but further evidence is required.

To be explored through developers forum and Dorset wide strategic housing group.

Planning Policy, Economic Development Team / 2019 / 20.

BCP to engage consultant to review relevant economic factors for BCP area.

Strategic Issue: Commercial Market Communications

1) Effective Engagement with Development Industry.

Engagement with development industry is undertaken but needs to be improved to fully capture and address all issues affecting housing delivery in BCP area.

Write to agents with existing planning permissions to confirm site progress and any issues affecting delivery.

Planning Policy / June 2019 Complete

Set up Developers forum to meet regularly to discuss issues affecting site / housing delivery.

Planning Policy to set up meetings from 2019 onwards.

Page 40: Housing Delivery Test Action Plan 2019 - 2022 1... · APPENDIX 1 1 1 Introduction Background 1.1 In February 2017, the Housing White Paper ‘Fixing our broken housing market’ was

APPENDIX 1

39

6 Project Management and Governance Arrangements

6.1 The Table in Section 5 of this document sets out a range of short and medium

term actions which aim to increase the delivery of new homes in the BCP

Council area. It also identifies timescales and responsibilities for delivery of

the actions, where appropriate. Monitoring of the actions will be undertaken

annually following receipt of the annual HDT measurement (anticipated to be

November each year), and the annual review of the Action Plan will draw on

information from a range of sources including the annual housing completions

surveys (which provides figures for the number of new homes completed each

year) and other relevant documents.

6.2 Where necessary actions will be updated, or new actions added in response

to currently unforeseen issues or barriers to development, or as a result of

changes in government policy, legislation or planning practice guidance.

6.3 Progress on the actions will be robustly jointly monitored by Planning Policy

and Housing and will be subject to review by a Steering Group consisting of

BCP officers from planning policy, development management, housing,

transport planning and property. The work of the steering group will be

overseen by the Portfolio Holders of Strategic Planning and Housing.

6.4 The need for robust governance is recognised as key to ensuring a step

change in increasing housing supply locally.