Memorandum CITY OF DALLAS DATE October 4, 2013 TO Housing Committee Members: Carolyn R. Davis, Chair, Scott Griggs, Vice- Chair, Monica Alonzo, Rick Callahan, Dwaine Caraway, and Philip Kingston Housing Projects Update On Monday October 7, 2013, you will be briefed on Housing Projects Update. A copy of the briefing is attached. Please let me know if you have any questions. Theresa O’Donnell Interim Assistant City Manager C: The Honorable Mayor and Members of the City Council A. C. Gonzalez, Interim City Manager Rosa A. Rios, City Secretary Warren M.S. Ernst, Interim City Attorney Craig Kinton, City Auditor Judge Daniel Solis, Administrative Judge Ryan S. Evans, Interim First Assistant City Manager Forest E. Turner, Assistant City Manager Jill A. Jordan, P.E., Assistant City Manager Joey Zapata, Assistant City Manager Charles M. Cato, Interim Assistant City Manager Jeanne Chipperfield, Chief Financial Officer Frank Librio, Public Information Officer Bernadette Mitchell, Housing/Community Services, Interim Director Elsa Cantu, Assistant to the City Manager Mayor and Council “Dallas, The City That Works: Diverse, Vibrant and Progressive.’

Upload: others

Post on 25-Jul-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Housing Projects Update - Dallas · 5 Housing Projects With Anticipated Completions Over The Next 18 Months Nonprofit Development yBuilders of Hope: West Dallas s – 10 single family

Memorandum

CITY OF DALLAS

DATE October 4, 2013

TO Housing Committee Members: Carolyn R. Davis, Chair, Scott Griggs, Vice-Chair, Monica Alonzo, Rick Callahan, Dwaine Caraway, and Philip Kingston

Housing Projects Update

On Monday October 7, 2013, you will be briefed on Housing Projects Update. Acopy of the briefing is attached.

Please let me know if you have any questions.

Theresa O’DonnellInterim Assistant City Manager

C: The Honorable Mayor and Members of the City CouncilA. C. Gonzalez, Interim City ManagerRosa A. Rios, City SecretaryWarren M.S. Ernst, Interim City AttorneyCraig Kinton, City AuditorJudge Daniel Solis, Administrative JudgeRyan S. Evans, Interim First Assistant City ManagerForest E. Turner, Assistant City ManagerJill A. Jordan, P.E., Assistant City ManagerJoey Zapata, Assistant City ManagerCharles M. Cato, Interim Assistant City ManagerJeanne Chipperfield, Chief Financial OfficerFrank Librio, Public Information OfficerBernadette Mitchell, Housing/Community Services, Interim DirectorElsa Cantu, Assistant to the City Manager — Mayor and Council

“Dallas, The City That Works: Diverse, Vibrant and Progressive.’

Page 2: Housing Projects Update - Dallas · 5 Housing Projects With Anticipated Completions Over The Next 18 Months Nonprofit Development yBuilders of Hope: West Dallas s – 10 single family

1

Housing Projects UpdateA Briefing to the Housing Committee

Housing/Community Services DepartmentOctober 7, 2013

Page 3: Housing Projects Update - Dallas · 5 Housing Projects With Anticipated Completions Over The Next 18 Months Nonprofit Development yBuilders of Hope: West Dallas s – 10 single family

2

Purpose

To provide a “Snapshot” of projects completed within the past 18 months and current projects under contract with anticipated production within the next 18 months

Page 4: Housing Projects Update - Dallas · 5 Housing Projects With Anticipated Completions Over The Next 18 Months Nonprofit Development yBuilders of Hope: West Dallas s – 10 single family

3

Housing Projects Completed Within The Last 18 Months

Nonprofit Development

Builders of Hope: Prairie Creek-k 14 single family homes Builders of Hoppppe Prairie Cree: pppp(CD4); West Dallas Scattered Sites

ee -

4 single familyy hom4kk-1es-18 homes (CD6)

Catholic Housing Initiativeve: Notre Dame Place Seniors Catholic Housingggggggggg InitHousing 8 units (CD1)

City Wide CDCC: Runyon Springsgs-s- 13 single family homes Cityyyyyyyyyy W(CD8)

Defenders of Freedomm: Veteran housing 2 single family Defenders of homes (CD9)

East Dallas Community Organization: Bexar Street-East Dallas Community Organizatioy g20 townhomes (CD7); Thornton Heights

iot -

Bexar Stree ett-:oon: t 17 single family (((20 townhomes (CD7)(((

homes (CD8); NSPCD7)SP-

g Thornton Heighttss- gggg7 single 771)); )D7)P- 4 Single family homes (CD7)

Jubilee Seniors Project: 24 apartment for Seniors on JJJJubilee Seniors ProjeGurley Avenue (CD2)

South Dallas/Fair Park ICDC: Frazier Courtyardsd -11 South Dallas/Fair Park ICDC: single family homes; Pittman Place

C: -

razier Courtyardr ds- 1 11Fr F y9 single family homes g yy ;single family homes; Pittmg yy

completed (CD7); NSPPittSP-

an Placceee- g yyyyyyyyyy9 single familyy ho9 omme99mattmP- 4 single family homes (CD7)

Southfair CDCC: Fair Park Estates 22 homes (CD7)

SCB:: NSPSP-- 2 single family homes (CD4)

Page 5: Housing Projects Update - Dallas · 5 Housing Projects With Anticipated Completions Over The Next 18 Months Nonprofit Development yBuilders of Hope: West Dallas s – 10 single family

4

Housing Projects Completed Within The Last 18 Months

For Profit Development

Pleasant Oaks: 14 single family homes Pleasan(CD4)

Altura Homes: Scattered Sites- 7 single Altura Homees Scattered Site: ess- sin le 7 7family homes (CD4); Cedar Creek Ranch

nggle chggggggggggggg

-ggle hgggggg

-76 y ( )family homes (CCD4); Cedar CCD4single family homes (CD8)

Atmos Phase II: 107 Multifamily units for Atmos Phasee I 107 Multifa: families completed (CD14)

Continentalal: Ground floor commercial Continentaal Ground floor commercial: and 203 apartments downtown (CD14)

Kaminiski Building: : 7 apartment units Kaminiski Building:: apartment units 7 on Bexar and 6,700 sq. ft. of retail (CD7)

Hai Tak Building: : 9 apartment units on Hai Tak Building:: apartment units o9 Bexar and 6,000 sq. ft. of retail (CD7)

Page 6: Housing Projects Update - Dallas · 5 Housing Projects With Anticipated Completions Over The Next 18 Months Nonprofit Development yBuilders of Hope: West Dallas s – 10 single family

5

Housing Projects With Anticipated Completions Over The Next 18 MonthsNonprofit Development

Builders of Hope: West Dallas s –– 10 single family homes (CD6)

City Wide CDC: Lancaster Urban Villagege-e 14,131 square feet of commercial/retail office space City Wide CDC: ancaster Urban VillagLa gee- 4,131 square fe41and 193 apartment units (CD5); Rudy’s Commercial (CD4)

East Dallas Community Organization: Bexar Streete -et 11 townhomes (CD7); Thornton East DalHeights

Daltsts-

as Community Organization: exar StreeBe elal- 2 single family homes (CD8); NSP: Bexar Street

eetetett -

townhomes (CD7); T11tt-1t t -3 units to build(CD7)

Frazier Revitalization Inc.: 6 single family homes (CD7)

Habitat for Humanity: Greenleaf Village IIII-- 10 single family homes (CD6)

South Dallas/Fair Park ICDC: Spring Street Medical Building; Pittman Place: 10 single family South Dallas/Fair units (CD7); NSP

air SPSP-

Park ICDC: Pir PP- 3 units (CD7)

Jubilee Park CCC: 9 single family homes (CD2)

Central Dallas CDC: 50 permanent supportive housing units (CD2)

2000 Roses: 2 single family homes (CD7)

Southfair CDC: Park Row Estatese -es-8 single family homes (CD7)

Page 7: Housing Projects Update - Dallas · 5 Housing Projects With Anticipated Completions Over The Next 18 Months Nonprofit Development yBuilders of Hope: West Dallas s – 10 single family

6

Housing Projects With Anticipated Completions Over The Next 18 Months

For Profit Development

Heroes House: 32 apartment units (CD7)Hall Family: 38 apartment units (CD7)Pleasant Oaks: 6 single family homes (CD4)Altura Homes: 4 single family homes (CD4); 36 single family homes (CD8)Hatcher Gardens: 10 apartment units & 2 retail spaces (CD7)Wynnewood Seniors: 140 apartments (CD3)1400 Belleview: 164 apartments (CD2)Lake Highlands Town Center: 165,000 sq. ft. commercial space (CD10)Atmos Phase II: Ground floor commercial and 123 apartment units (CD14)

Other EntitiesDHA: Buckeye Trail Commons- 323 apartment units (CD4)

Page 8: Housing Projects Update - Dallas · 5 Housing Projects With Anticipated Completions Over The Next 18 Months Nonprofit Development yBuilders of Hope: West Dallas s – 10 single family

7

Current NIP Projects & Schedule of Work

South Dallasas-s- Greater Fair Park NIPSSoouutthh DDaallllaaass GGrreeaatteerr FFaaiirr PPaarrkk NNIIPPGG

Spring Avenue Redevelopment: : Construction start Spring Avenue Redevelopment: onstruction start Coon Spring Avenue streetscape and public improvements on Spring Avenue streetscape and public improvements on Spring Avenue streetscape and ppublic improvementspubliccommenced April 2013 with completion by May 2014. commenced April 2013 with completion by May 2014. commencedApril 2013 with completion by May 2014.Construction on first new mixed use building underway.

West Dallas NIPWWeesstt DDaallllaass NNIIPP

Neighborhood Infrastructure Improvements: Neighborhood Infrastructure Improvements: Neighborhood sidewalk improvements within the La Neighborhood sidewalk improvements within the La Neighborhood sidewalk improvements within the LaBajada and Los Altos communities to commence March Bajada and Los Altos communities to commence Bajada and Los Altos communities to commence2014 with estimated completion by May 2014.

Lancaster Corridor / Cigarette HillLLaannccaasstteerr CCoorrrriiddoorr // CCiiggggaarreettttee HHiillll

Miller Family Park Improvements: : Installation of Miller Family Park Improvements: stallation oInLED Security lighting, picnic tables, BBQ grills and LED Security lighting, picnic tables, BBQ grills and LED Security lighting picnic tables BBQQ grills andQ grcreation of small plaza on track completed July 2013.p

Neighborhood Lighting: p J y

g: Additional street lighting Neighborhood Lightingg: dditional street lightAdinstalled spring 2013 at the request of residents.

Herbert Street (West Dallas) Traffic CalmingStreet (West Dallas) Traffic CCompleted Winter 2012

Page 9: Housing Projects Update - Dallas · 5 Housing Projects With Anticipated Completions Over The Next 18 Months Nonprofit Development yBuilders of Hope: West Dallas s – 10 single family

South Dallasas-s- Ideal/Rochester ParkSSoouutth DaallaaSS aassss ddeeaal//Rooccheesstteer PaarkIddI

Bexar Street Redevelopment Investment Bexar Street RedCenter (DPD):

evelopment Investment Red:: Construction underway with Center (DPD): onstrucCo

completion by May 2014.

Bexar Street Public Improvements: Bexar Street Public Improvements: Construction of Phase II, Phase III street and Construction of Phase II, Phase III street and Construction of Phase II Phase III street andstreetscape improvements in progress, with streetscape improvements in completion by winter 2014.

Ideal/Rochester Park Neighborhood:: Public Ideal/Rochester Park Neighborhood: Public Pimprovements within the Ideal and Rochester Park improvements within the Ideal and Rochesteimprovements within the Ideal and Rochestesteneighborhood underway. Projects include neighborhood underway. Projects include neighborhood street and green space improvements, neighborhood street and green space improvementsneighborhood street and green space improgateway enhancements, landscaping, neighborhood gateway enhancements, landscaping, neighborhood gateway enhancements landscaping neighborhoodbanners, security measures, monthly stakeholder banners, securiengagement.

North Oak Cliff / Marsalis NIPNNoorrtthh OOaakk CClliiffff // MMaarrssaalliiss NNIIPPNN

Median Improvements: : Acquisition of 138 W. Median Improvements: cquisition of 138 W. AcDavis for median improvements authorized by City Davis for median impDavis for median impCouncil May 2013.

South DallaS ass- deal/Rochester ParkIdI

Current NIP Projects & Schedule of Work

8

Page 10: Housing Projects Update - Dallas · 5 Housing Projects With Anticipated Completions Over The Next 18 Months Nonprofit Development yBuilders of Hope: West Dallas s – 10 single family

9

SummaryCompleted Over Last 18 Monthso 213 single family unitso 378 multifamily unitso 12,700 sq. ft. retail/commercial space

Anticipated Production Over Next 18 Monthso 113 single family unitso 1,040 multifamily unitso 50 permanent supportive housing unitso 180,731 sq. ft. Retail/Commercial/Office Space