how the supergrid really will be built

Upload: lolobidus

Post on 02-Jun-2018

222 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/10/2019 How the Supergrid Really Will Be Built

    1/68

    HOW THE SUPERGRID IS

    REALLY GOING TO BE

    BUILT INPUTS SESSION 0930HRS

    TUESDAY 17 MARCH, 2009

  • 8/10/2019 How the Supergrid Really Will Be Built

    2/68

    Chairpersons

    Mr Brendan Halligan Sustainable Energy Ireland

    and

    Mr Jost deJager State Secretary of the Ministry of Economical Affairs of

    Schleswig-Holstein / Germany

  • 8/10/2019 How the Supergrid Really Will Be Built

    3/68

    Mr Matthias Machnig

    State Secretary of the Federal Ministry forthe Environment / Germany

    - Offshore Wind Development in Germany

  • 8/10/2019 How the Supergrid Really Will Be Built

    4/68

    Mr Brian Hurley

    Wind Site Evaluation Ltd.

    - Offshore Wind Resources in Europe

  • 8/10/2019 How the Supergrid Really Will Be Built

    5/68

    Wind energy in lower 1km of atmosphere

    Smil gives a figure, 3.8 x 1022 J, for the annual flux

    for the winds in the atmosphere below a height of

    1km. He puts the maximum convertible at 3.8 x

    1022J or 1.1 x 106 TWh.

    Ref: Smil, Vaclav. Inherent Limits of Renewable Energies. 2004

  • 8/10/2019 How the Supergrid Really Will Be Built

    6/68

  • 8/10/2019 How the Supergrid Really Will Be Built

    7/68

    Potential TW

    Area considered with 5MW/Km2

    North Atlantic East of longitude 300, North to latitude800, and South to latitude 360, East to longitude 300:

    35.7TW

    Mediterranean Sea: 12.5TW

    Total 48.2TW

    or48,200,000MW

  • 8/10/2019 How the Supergrid Really Will Be Built

    8/68

    Offshore Wind Resource Estimate

    Area considered with 5MW/Km2

    North Atlantic East of longitude 300, North to

    latitude 800

    , and South to latitude 360

    , East tolongitude 300: 133,000TWh

    Mediterranean Sea: 28,000TWh

    Total 161,000TWh

  • 8/10/2019 How the Supergrid Really Will Be Built

    9/68

    Europes Electricity Demand

    EU25 Final Demand of 2500 TWh (2004)

    Total Offshore Resource: 161,000TWh

    64 times the demand is available offshore

  • 8/10/2019 How the Supergrid Really Will Be Built

    10/68

    Mr Gunnar Asplund

    ABB

    - HVDC Supergrid - Technology and Costs

  • 8/10/2019 How the Supergrid Really Will Be Built

    11/68

    To bring the power to the consumers by electric

    transmissionAC versus HVDC transmission

    0 200 400 600 800 10000

    500

    1000

    1500

    PowerinMW

    .

    Overhead lines

    Cables

    400 kV

    AC line

    320 kV

    DC line

    Three 400 kV

    AC cables

    Two 320 kVDC cables

  • 8/10/2019 How the Supergrid Really Will Be Built

    12/68

    Power and Voltage - present situation

    HVDC with OH lines

    0 1000 2000 3000 4000 5000 6000 7000

    HVDC

    with

    extruded

    cable

    HVDC

    with sea cables

    Power in MW

    Udc

    in kV

    800

    700

    600

    500

    400

    300

    200

    0

  • 8/10/2019 How the Supergrid Really Will Be Built

    13/68

    Estlink

    2006, 350 MW

    Murraylink

    2002, 220 MW

    Directlink

    2000,3X60 MW

    Gotland

    1999, 50 MW

    Tjreborg

    2000,7 MW

    Eagle Pass

    2000, 36MW

    Mosel

    2000, 38 MVAr

    Hagfors

    1999, 22 MVAr

    Polarit

    2003, 164 MVA

    Troll

    2004,2X40 MW

    Evron

    2003, 16 MVAr

    Hllsjn

    1997, 3 MW

    Legend:

    Valhall

    2009,75 MWNORD E.ON 1

    2009,400 MW

    Caprivi2009,300 MW

    Projects based on HVDC/SVC Light Technology

    HVDC Light

    SVC Ligh t

    Cross Sound

    2002, 330 MW

    Holly

    2004, 95 MVAr

  • 8/10/2019 How the Supergrid Really Will Be Built

    14/68

    HVDC in Germany - Offshore windE.ON Netz, Borkum 2, 400 MW HVDC Light

    75 km land cable

    128 km sea cable

    400 MW offshoreconverter

    400 MW converter

  • 8/10/2019 How the Supergrid Really Will Be Built

    15/68

    Europe 20XX Scenario

    Solar

    700 GW

    8000 km sq90 x 90 km

    Wind

    300 GW

    25 000 km sq

    5000 x 10 km

    Hydro

    200 GW

  • 8/10/2019 How the Supergrid Really Will Be Built

    16/68

    Cost example of a Supergrid

    Distance north-south 2000 km

    Distance east-west 1500 km

    Mesh size 300 km

    Number of sea wind stations 7

    Number of land solar stations 6

    Number of land receiving stations 13Power per station 2000 MW

    Subsea cable length 6700 km

    Overhead line length 9000 km

    Underground cable length 6800 km

    Supergrid cost 26 % 1)

    1) Reference is the cost of solar and wind generation

  • 8/10/2019 How the Supergrid Really Will Be Built

    17/68

    Mr Joe Corbett

    Mainstream Renewable Power

    - Detailed Design of the Supernode

  • 8/10/2019 How the Supergrid Really Will Be Built

    18/68

    Supernode Concept

    SUPERNODE CONCEPT

    400kV

    2 x 500MW2 x 500MW

    2 x 500MW2 x 500MW

    Converter Station

    2.4GW

    2.4GW

    2.4GW

    2.4GW

    320kV

    320kV

  • 8/10/2019 How the Supergrid Really Will Be Built

    19/68

    Mainstream Renewable Powers Plan

    Supernode 1

    Supernode 2

  • 8/10/2019 How the Supergrid Really Will Be Built

    20/68

    SUPERNODE 1

    North

    Supernode 2

    2 x 500MW2 x 500MW

    2 x 500MW2 x 500MW

    RTW 400kV

    National

    Grid400kV

  • 8/10/2019 How the Supergrid Really Will Be Built

    21/68

    SUPERNODE 2

    500MW 500MW

    GERMANY

    380kV

    Supernode 1

  • 8/10/2019 How the Supergrid Really Will Be Built

    22/68

    Cost Comparisons

    Project

    Installed Capital

    Cost (M)

    Capacity

    Offshore Wind(MW)

    Capacity Trade

    (MW)

    Average

    Capacity Factor Annual GWh

    Cost / Annual

    Energy

    Transmitted(/MWh)

    NorNed

    600 0 700 80% 4,905 122

    MRP I

    2,974 2,000 4,000 47% 24,528 121

    MRP II

    3,036 4,000 4,000 60% 31,536 96

    MRP III

    3,648 5,000 4,000 73% 38,544 95

    MRP IV3,648 6,000 4,000 80% 42,048 87

  • 8/10/2019 How the Supergrid Really Will Be Built

    23/68

    Cost Comparison Chart

    0

    20

    40

    60

    80

    100

    120

    140

    NorNed MRP I MRP II MRP III MRP IV

    Cost Comparison

    Cost / Annual MWh (/MWh)

  • 8/10/2019 How the Supergrid Really Will Be Built

    24/68

    Mr Fenno Leeuwerke

    Hochtief Construction

    - Building at Sea and 3rd Generation of Ships

  • 8/10/2019 How the Supergrid Really Will Be Built

    25/68

    First Generation of Equipment

    Civil Construction Jack-ups

    Accommodation Jack-ups inoffshore wind

    Project Load 1500

    to

    Crane Capacity

    300 to

    400 to

    nacelle

    approx. 150

    to

    85 m

    135 to

    200 to

  • 8/10/2019 How the Supergrid Really Will Be Built

    26/68

    Second Generation of Equipment

    Second Generation Jack-ups in

    offshore wind

    Crane Capacity

    500 to

    Project Load 2500

    to

    300 - 600 to

    nacelle

    approx. 150

    - 430 to

    120 m

    200 to

    200 to

  • 8/10/2019 How the Supergrid Really Will Be Built

    27/68

    Third Generation of Equipment

    Offshore wind Jack-ups100 m

    400 tons

    nacelle approx.

    100 tons

    Project Load7000 10 000 to

    Crane Capacity

    1 000 to

  • 8/10/2019 How the Supergrid Really Will Be Built

    28/68

    What Next

    - Gravity base

    - Floating

    - Robust

    - Reliable

    - Redundend

    - Optimized cycle times/logistics

  • 8/10/2019 How the Supergrid Really Will Be Built

    29/68

    Mr Herbert Peels

    2-B Energy

    - A New Design for Offshore Wind

    Power Plant

  • 8/10/2019 How the Supergrid Really Will Be Built

    30/68

    2-B Energy

    30

    Background

    2-B was founded early 2007 by M. Jakobsson and H. Peels

    2-B team has extensive experience in wind energy

    (GE/Enron/Shell/Siemens)

    Shareholders of 2-B: Mainstream Renewable Power/P.

    Mouratoglou/Truffle

    Goals

    Introduction of new, clean sheet dedicated offshore powerplant concept with lower cost of energy

    Aim for large scale projects further out to sea

    First prototype to be installed 2010

  • 8/10/2019 How the Supergrid Really Will Be Built

    31/68

    Offshore consideration in 2-B design

    31

    Cost of energy

    Consequential downtime

    No/limited noise requirements

    Project size utility scale

    No/limited visual impact

    Deep(er) waters

    Access-ability

  • 8/10/2019 How the Supergrid Really Will Be Built

    32/68

    2-B Principles and Values

    32

    Significant reduction of COE and risk through:

    Reduction of no of components

    Reduction of material consumption

    Building on HVDC functionality

    Off the shelf components

    Leading key supply chain engaged

    Simplification of installation and O&M

    Longer life on all structural components

  • 8/10/2019 How the Supergrid Really Will Be Built

    33/68

    2-B Technology

    33

    2-B design key features:

    Full jacket structure 2 bladed concept

    6 MW generator

    130 m diameter

  • 8/10/2019 How the Supergrid Really Will Be Built

    34/68

    2-B Technology

    34

    Project life cycle and operational concept:

    Power plant life cycle for structural

    components

    Planned overhaul principle

    New replacement strategies for

    gearbox and other components

    Electrical system:

    Simplified HV generation concept

    AC WTG collection grid system

    Central transformers for WTG groups

    More resilient grid configuration

  • 8/10/2019 How the Supergrid Really Will Be Built

    35/68

    2-B continued..

  • 8/10/2019 How the Supergrid Really Will Be Built

    36/68

    Q&A

  • 8/10/2019 How the Supergrid Really Will Be Built

    37/68

    HOW THE SUPERGRID IS

    REALLY GOING TO BE

    BUILT OUTPUTS SESSION 1100HRS

    TUESDAY 17 MARCH, 2009

  • 8/10/2019 How the Supergrid Really Will Be Built

    38/68

    Ms Liz McRobb

    Shepherd and Wedderburn

    - Regulatory Issues

  • 8/10/2019 How the Supergrid Really Will Be Built

    39/68

    Making Supergrid happen problems,

    barriers, hurdles?

    2020 targets a real time of opportunity

    Trans European energy networks

    2006 TEN-E Guidelines and Priority Interconnection Plan

    Appointment of European Co-ordinators a four year

    mandate to achieve change

    Connection to offshore wind power in Northern Europe

  • 8/10/2019 How the Supergrid Really Will Be Built

    40/68

    Making Supergrid happen problems,

    barriers, hurdles?

    Changes to EU legislation to shorten the

    authorisation process

    Balancing of environmental concerns with strategic

    2020 targets

    Tackling fragmentation at a practical level

    UK consenting developments what lessons will we

    learn?

    What can MS do now to support the EU initiative?

  • 8/10/2019 How the Supergrid Really Will Be Built

    41/68

    Making Supergrid happen problems,

    barriers, hurdles?

    Many success stories over time from bilateral links

    Regulatory framework has fostered investment and

    third party access

    TSOs increasingly experienced at joint venturing

    Multi-lateral success stories as well

  • 8/10/2019 How the Supergrid Really Will Be Built

    42/68

    Making Supergrid happen so where

    could we start?

    Speed of development for grid is critical to 2020

    MS have their individual headaches

    UK position for grid to support Round 3

    Prioritising multilateral collaboration is key

    Using EU enhanced co-operation

  • 8/10/2019 How the Supergrid Really Will Be Built

    43/68

    Mr Adam Bruce

    Mainstream Renewable Power

    - Regulatory Issues Part 2 and Governance

    (OTSO)

  • 8/10/2019 How the Supergrid Really Will Be Built

    44/68

    Delivering Supergrid The Regulatory Process

    A European project at scale Cross-border trade and infrastructure

    Multilateral regulation

    Not just point-to-point connection

    Enhanced Co-operation

    An existing framework

    A process that works

    Allows for fast-tracking

    EU Offshore

    TransmissionOperator

    OTSO

  • 8/10/2019 How the Supergrid Really Will Be Built

    45/68

    Supergrid Governance

    EUInstitutions

    OTSOBoard

    OTSOExecutive

    Supergrid

    Enhanced Co-

    operationEU Octet marine

    energy member states

  • 8/10/2019 How the Supergrid Really Will Be Built

    46/68

    Supergrid Governance

    The regulatory process for delivering Supergrid

  • 8/10/2019 How the Supergrid Really Will Be Built

    47/68

    Supergrid Governance

    EU Institutions

    EU Energy policy

    Supergrid Charter

    OTSO Board

    National Governments

    National TSOs andappointees

    Commission appointee

    OTSO Executive

    What to build

    Where to build

    When to build

    Supergrid Charter

    Purposes:

    Security of supply

    Eliminate GHGs

    Create free market in electricity

    Ensure competitiveness

    OTSO Board

    Purposes:

    Governance

    Sets policy

    Project approvals

    Raises finance

    Supergrid

  • 8/10/2019 How the Supergrid Really Will Be Built

    48/68

    Mr Fintan Whelan

    Mainstream Renewable Power

    - Investment Opportunities, Risks and

    Incentivisation

  • 8/10/2019 How the Supergrid Really Will Be Built

    49/68

    Incentives

    Risk

    Opportunities

  • 8/10/2019 How the Supergrid Really Will Be Built

    50/68

    Energy Consumers,Taxpayers,Voters

    Government as Proxy/Agent

    Robust Demand for

    Renewable Energy Generation

    Way of Life, Development,Competitiveness

    SUSTAINABILITY

  • 8/10/2019 How the Supergrid Really Will Be Built

    51/68

    Human & Financial Capital

    Incentives in PlaceRisks Allocated/Mitigated/Managed

    Supply Chain Capacity & Integration

    Reliable Supply of

    Renewable Energy

    Opportunities:

    Risks/Returns

    SUSTAINABILITY

  • 8/10/2019 How the Supergrid Really Will Be Built

    52/68

    Key Themes

    Risk: Mutual Reduction in Uncertainty

    Incentives : Support is not one-way, it is a Quid Pro Quo

    Opportunity : Integrate Supply Chain to Secure Capacity

    and Provide Line of Sight to End Game

  • 8/10/2019 How the Supergrid Really Will Be Built

    53/68

    Mr Andreas Wagner

    German Offshore Wind Energy Foundation

    - New Employment Opportunities with

    Offshore Wind Energy

    Stiftung OFFSHORE WINDENERGIE

  • 8/10/2019 How the Supergrid Really Will Be Built

    54/68

    Stiftung OFFSHORE-WINDENERGIE

    Voice of the German offshore wind energy sector

    Created in 2005 Acquired permits for alpha ventus in 2005 - lease to DOTI in Dec. 06

    Communication platform for politics, industry, R/D, business & finance

    PR and mediation activities to overcome obstacles

    Promoting public acceptance (e.g. POWER Cluster)

    Initiates and contributes to R/D initiatives (e.g. RAVE, WINDSPEED)

    Offshore Wind in Germany starting to take off

  • 8/10/2019 How the Supergrid Really Will Be Built

    55/68

    Offshore Wind in Germany starting to take-off

    Huge potential in the medium/longer run (by 2030)

    Can generate up to 15% of German electricity consumption

    85-100 TWh (25.000 MW) New employment opportunities, mainly along the German coast,

    20,00030,000 direct and indirectjobs,

    Total investment 75-100 billion Euro

    Strong in (environmental) R/D, turbine technology (Multi-MW),

    engineeringBUT

    Challenging external conditions (distance to shore, water depth,economics, infrastructure & logistics, technology solutions, O&M,grid connection and integration issues w ith regulator and TSOs)

    Industrial cross-border Co-operation needed emerging with UK, N, NLCo-operation on environmental R/D with Dk and S since 2007

    HR issues, Training & Qualification

    Spatial Planning/Permitting

    Finance

    Just a beginning

  • 8/10/2019 How the Supergrid Really Will Be Built

    56/68

    Just a beginning 400-500 Mio. Investments in NW-Germany2000-3000 new jobs and more to come

    Source: wab

    Emden/Bremen

    Nordenham

    Cables

    Bremerhaven

    OFFSHORE-BASISCUXHAVEN

    Bremerhaven

    250 Mio

    Offshore Wind in Europe

  • 8/10/2019 How the Supergrid Really Will Be Built

    57/68

    Offshore Wind in Europe

    BGP - Beyond Gas and Petroleum

    Starting with 20-40 GW Offshore Wind by 2020 600 new wind turbines (5 MW each) per year means new jobs in:

    - Turbine and component assembly,

    - Offshore foundations,

    - Electrical infrastructure (cables),

    - Offshore installation and logistics- O&M, Training offshore personnel, etc.

    New Offshore infrastructure is required at coastal sites across

    Europe Compensating for decline in traditional maritime sectors

    (e.g. shipyards, European O&G industry, etc.)

    Electrical Offshore Infrastructure New Opportunities for cablemanufacturers, the steel industry (transformer stations), and

    maritime logistics

    Source: Delivering Offshore Wind Power in Europe (EWEA, 2008)

    Offshore Wind in Europe the new Job Machine

  • 8/10/2019 How the Supergrid Really Will Be Built

    58/68

    Offshore Wind in Europe - the new Job Machine

    35 GW Offshore Wind can generate up to half of all employment

    in the wind sector by 2020 150,000 (!) new jobs created by Offshore Wind in 2020

    Source: Wind at Work (EWEA, 2009)

  • 8/10/2019 How the Supergrid Really Will Be Built

    59/68

    Ready for Taking-Off!?

  • 8/10/2019 How the Supergrid Really Will Be Built

    60/68

    Mr Michael McElhinney

    Scottish Government

    - Connecting Northern Europe.

    A Scottish Perspective

    The Window of Opportunity

  • 8/10/2019 How the Supergrid Really Will Be Built

    61/68

    The Window of Opportunity

    The EU policy landscape: Strategic Energy Review

    UK policy landscape: UK Climate Change Bill,

    Transmission Access Review,

    Links with Ofgem and National Grid,

    Crown Estate leasing of offshore renewable generation sites.

    Scottish policy landscape: Responsive and stable regulatory regime e.g. Marine Bill,

    Climate Change Bill,

    National Planning Framework,

    Streamlined consenting for renewables projects.

    Current financial cl imate: EU & Scottish Economic Recovery Plans:

    Renewable energy as a driver of recovery.

    Developing Offshore Grid

  • 8/10/2019 How the Supergrid Really Will Be Built

    62/68

    Developing Offshore Grid

    Existing studies North Sea and Irish Sea

    Proven capacity and capability on and offshore

    Strong on innovation R&D and the Saltire Prize

    1st class test and demonstration facilities:

    Beatrice Offshore Wind Demonstrator and EMEC.

    Working closely with industry and academia on developing technology

    2007 - 20% of electricity consumed in Scotland came from renewable sources

    5.5 GW renewables capacity installed, consented and under construction more than our 2011 target of 31% of electricity demand from renewables.

    Our National Planning Framework identifies priorities for energy, encouragesdevelopment of renewables and North Sea offshore grid.

    And keen to do more.

  • 8/10/2019 How the Supergrid Really Will Be Built

    63/68

    SK 1,2,3

    NorNed

    SK 4

    NORD.LINK / NorGer

    Ekofisk

    Windpark

    New interconnectors

    wi ll use VSC HVDC

    technology

    Cable capacity from

    Norway ~ 6000 MW

    Included transit thru

    Sweden~10000MW

    Standardisation

    Cooperation

    CoordinationHydro

    Reservoirs for

    balancing

    ?

    ?

    ?

    In operation

    Early planning

    Evaluation

    Connectionplatform

    Windpark

    Proposed European modular development

    Accommodating Increased Volume

  • 8/10/2019 How the Supergrid Really Will Be Built

    64/68

    g

    of Renewables from ScotlandUK and Scottish Government, Ofgem

    and transmission licensees work to

    identify transmission reinforcements tosupport the delivery of UK renewable

    energy targets including onshore and

    offshore reinforcement in Scotland.

    Outcomes of this work Vision 2020

    published on 4th March.

    HVDC cable from Hunterston Deeside (circ 1.8GW)

    HVDC cable from Peterhead toHumberside (circ 1.8GW)

    HVDC circuit

    Re-conductor or re-insulate

    existing OHL route

    Series compensation

    Accommodates ~11.4GW of

    renewables in the north of Scotland

    Transmission Development Overview

  • 8/10/2019 How the Supergrid Really Will Be Built

    65/68

    Transmission Development Overview

    New HVDC circuit

    Re-conductor or re-

    insulate on existing towersFull re-build or new-build

    double circuit overhead line

    New AC subsea cable

    Series compensation

    equipment in existing

    substation compounds

    Norway

    Early instance of multiple HVDCterminals will occur in Scotland

    (AND potential for HVDC link withNorway given that the shortest

    route option is to Peterhead)

    Fundamental power systemsplanning, operation and control

    issues associated with aconcentration of multiple HVDC

    terminals

    Understanding and resolution isrequired for Scotland, but will also

    be key to realisation of any wider

    vision for North Sea renewablesreliant on HVDC transmission.

    HVDC in Scotland provides an invaluable test

    case towards a wider pan-European grid

    Future thinking North Sea Grid Post 2020

  • 8/10/2019 How the Supergrid Really Will Be Built

    66/68

    Future thinking North Sea Grid Post 2020

    Needs

    Vision

    Commitment

    Commercialisation

    Investment

    Reward

    Regulation

    Collaboration

    SK 1,2,3

    NorNed

    SK 4

    NORD.LINK / NorGer

    Ekofisk

    Windpark

    Proposed European modular development

    Standardisation

    Cooperation

    Coordination

    Hydro

    Reservoirs

    for balancing

    North SeaGrid

    ~~~~~ ~~~~~

  • 8/10/2019 How the Supergrid Really Will Be Built

    67/68

    Dr Eddie OConnor

    Mainstream Renewable Power

    - Wrap Up and Q&A

  • 8/10/2019 How the Supergrid Really Will Be Built

    68/68

    Q&A