howtocreates-curvebymspproject
TRANSCRIPT
8/12/2019 howtocreates-curvebymspproject
http://slidepdf.com/reader/full/howtocreates-curvebymspproject 1/50
Author: Ong-Art S. Factory AVP
UEC-MSP-001
Rev.: 00 / 05-09-2013
8/12/2019 howtocreates-curvebymspproject
http://slidepdf.com/reader/full/howtocreates-curvebymspproject 2/50
2Author: Ong-Art S. Factory AVP
Sample of Visual in excel
8/12/2019 howtocreates-curvebymspproject
http://slidepdf.com/reader/full/howtocreates-curvebymspproject 3/50
3Author: Ong-Art S. Factory AVP
This article is to explain Project Management
Concept as a quick reference through step by step
guidance using MS Project 2013
The targeted audience is a beginner to the project
management and experienced with MS Project inearly version, such 2007 or 2010
Guide line
8/12/2019 howtocreates-curvebymspproject
http://slidepdf.com/reader/full/howtocreates-curvebymspproject 4/50
4Author: Ong-Art S. Factory AVP
1. Start Project
2. Plan the Tasks
3. Assign resources
4. Project Baseline set up
5. Update progress6. Forecast Information
7. Step by Step to S-Curve
8. Step by Step Export Data to Excel (Visual Report)
9. Close Project
Table of Contents
8/12/2019 howtocreates-curvebymspproject
http://slidepdf.com/reader/full/howtocreates-curvebymspproject 5/50 5Author: Ong-Art S. Factory AVP
Prior to start the project planning, Project manager
should be identified, who can set up a project plan
in MS project 2013
Step-1: Start Project
1. Create a new
Project File
To create a new blank project in Project,
click the file tab. Click new
8/12/2019 howtocreates-curvebymspproject
http://slidepdf.com/reader/full/howtocreates-curvebymspproject 6/506Author: Ong-Art S. Factory AVP
2. Set project
start date
Go to Project tab. Click Project information
Step-1: Start Project
8/12/2019 howtocreates-curvebymspproject
http://slidepdf.com/reader/full/howtocreates-curvebymspproject 7/507Author: Ong-Art S. Factory AVP
Step-1: Start Project
3. Define Project
Calendar
Go to Project tab. Click Change Working
time
8/12/2019 howtocreates-curvebymspproject
http://slidepdf.com/reader/full/howtocreates-curvebymspproject 8/508Author: Ong-Art S. Factory AVP
Step-1: Start Project
4. Save the
Project file
Go to Tab file, select save as with Project
Name or Job Order running number
8/12/2019 howtocreates-curvebymspproject
http://slidepdf.com/reader/full/howtocreates-curvebymspproject 9/50
9Author: Ong-Art S. Factory AVP
In the planning stage, we need to achieved project’s
goals. To do this, we have to identify the project’s
milestone, deliverables and tasks.
This plan can be use work breakdown structure
(WBS).
Step-2: Plan the Tasks
8/12/2019 howtocreates-curvebymspproject
http://slidepdf.com/reader/full/howtocreates-curvebymspproject 10/50
10Author: Ong-Art S. Factory AVP
Step-2: Plan the Tasks
1. Enter Task Click View tab. In the Task View groups,
click Gantt Chart. In the Task Name fields,enter tasks.
8/12/2019 howtocreates-curvebymspproject
http://slidepdf.com/reader/full/howtocreates-curvebymspproject 11/50
1Author: Ong-Art S. Factory AVP
Step-2: Plan the Tasks
2. Decide how
you want toSchedule Task
In Project 2013, we can schedule tasks
manually or automatically. Select schedulemethod after enter a new tasks by clicking
in the Task Mode column:-
Note: New Tasks manually set by default in
Option Tab
8/12/2019 howtocreates-curvebymspproject
http://slidepdf.com/reader/full/howtocreates-curvebymspproject 12/50
12Author: Ong-Art S. Factory AVP
Step-2: Plan the Tasks
3. Outline Tasks Create task hierarchy including tasks and
milestones under summary task, which canbe represent phase or other work divisions.
Click the Task tab. In the Schedule group
select Indent or Outdent button
•
Tip: if you created a summary task withduration, start or finish date, then the
tasks that fall under the summary task
will not be rolled up to this summary
tasks.
8/12/2019 howtocreates-curvebymspproject
http://slidepdf.com/reader/full/howtocreates-curvebymspproject 13/50
13Author: Ong-Art S. Factory AVP
4. Enter Durations Click the Duration field for a task and enter
a Duration. Two way to entering aduration:-
Mutually Schedule task
A number or text like
“Tomorrow” or “Next after rollshell” etc.
Auto Schedule task
Number only, 3d=3 Days,
0d=milestone, 6? is an estimate
duration.
Note: Both can selected in the Task Mode
Step-2: Plan the Tasks
8/12/2019 howtocreates-curvebymspproject
http://slidepdf.com/reader/full/howtocreates-curvebymspproject 14/50
14Author: Ong-Art S. Factory AVP
Step-2: Plan the Tasks
5. Link Tasks to
showrelationships
Click the Task tab, in the View Group click
Gantt Chart. Select the tasks that you wantto link then click the Link Tasks button in
the Schedule group, or move a mouse to
bar chart press and drack down to tasks
that you want to link.To change the default Finish-to-Start (FS),
double click the link line and change.
8/12/2019 howtocreates-curvebymspproject
http://slidepdf.com/reader/full/howtocreates-curvebymspproject 15/50
15Author: Ong-Art S. Factory AVP
Assignments are the associations between specific
tasks and the resources needed to completed them.We can assign more than one resources to a tasks.
We can assign work resources (People), material
(pipe/shell etc.) and cost (THB) to tasks.
Step-3: Assign Resources
8/12/2019 howtocreates-curvebymspproject
http://slidepdf.com/reader/full/howtocreates-curvebymspproject 16/50
16Author: Ong-Art S. Factory AVP
Step-3: Assign Resources
1. Add Resources
to Project
Click the Task Tab, in the Views dropdown
list select Resources Sheet. In theResources Name filed, type the name of
resources that we’ll use in this project.
8/12/2019 howtocreates-curvebymspproject
http://slidepdf.com/reader/full/howtocreates-curvebymspproject 17/50
17Author: Ong-Art S. Factory AVP
2. Assign
Resources toTasks
In the Resources Tab, Click Assign
Resources the click resources name thenclick assign
Step-3: Assign Resources
8/12/2019 howtocreates-curvebymspproject
http://slidepdf.com/reader/full/howtocreates-curvebymspproject 18/50
18Author: Ong-Art S. Factory AVP
Step-3: Assign Resources
3. Enter the Work
Hours spendingon Tasks
After assign a resources to the Tasks, work
hours automatically show in a Work. If PMprefer control a Working hours, it can be
change in in Work Field. Entering Work
reflects real world scheduling.
Go to Gantt Chart, right click on columnthen click Insert Columns type "WORK” to
select the Work Columns
8/12/2019 howtocreates-curvebymspproject
http://slidepdf.com/reader/full/howtocreates-curvebymspproject 19/50
19Author: Ong-Art S. Factory AVP
Step-3: Assign Resources
4. Know the Work
Tasks Type
After Assign a resources to Tasks, MS
Project determine how to schedule thetasks based on the tasks type.(Manually
tasks don’t use task type) durations may
change as we assign resources to tasks.
How tasks types workWork, duration and unit are determined by
formula:-
Work =Duration x Units
8/12/2019 howtocreates-curvebymspproject
http://slidepdf.com/reader/full/howtocreates-curvebymspproject 20/50
20Author: Ong-Art S. Factory AVP
Step-3: Assign Resources
In a… If we revised
Work
If we revised
Duration
If we revised
unitsFixed units tasks Duration changes Work changes Duration changes
Fixed work tasks Duration changes Units change Duration changes
Fixed duration tasks Units change Work changes Work changes
To set a default task type for the entire project, click theoptions. Go to Schedule group, in the default task type box
shown fixed units as a default, we can change to Fixed
Duration or Fixed Work
To change the task type for an individual, go to tasks tab inproperties group click information or to tasks name double
click it will appear.
8/12/2019 howtocreates-curvebymspproject
http://slidepdf.com/reader/full/howtocreates-curvebymspproject 21/50
2Author: Ong-Art S. Factory AVP
Step-3: Assign Resources
5. Identify factors
effecting taskschedules
We can use MS Project 2013 to help for
understanding how changes one task caneffect the rest of the project.
Click the task tab then in the Schedule
group click Inspect Task. A pane opens on
the left showing the factors that affect thescheduling of selected task.
Or double click in tasks name.
8/12/2019 howtocreates-curvebymspproject
http://slidepdf.com/reader/full/howtocreates-curvebymspproject 22/50
22Author: Ong-Art S. Factory AVP
Create a baseline or interim plan is to compare
between plan and actual.
Saving baseline plan enables to identify and solve
discrepancy and plan more accurately for similar
future projects.
Step-4: Set the Project Baseline
8/12/2019 howtocreates-curvebymspproject
http://slidepdf.com/reader/full/howtocreates-curvebymspproject 23/50
23Author: Ong-Art S. Factory AVP
Step-4: Set the Project Base Line
1. Save the
baseline plan
After the plan is solidly in place for the
finish date, budget and scope, we cansubmit a plan for approval.
Once it has been approved, save the
baseline plan.
Click the Project tab, in Schedule groupclick Set Baseline
8/12/2019 howtocreates-curvebymspproject
http://slidepdf.com/reader/full/howtocreates-curvebymspproject 24/50
24Author: Ong-Art S. Factory AVP
Step-4: Set the Project Base Line
2.View baseline
data in GanttChart views
In Gantt chart view, move a mouse to gantt
area, right click and select Bar Style.
Name Appearance Show for
Task
Row From To
Base Plan
(Custom)
Select bar
shave and
color
Select Normal 2 or 3 Baseline Start Baseline finish
8/12/2019 howtocreates-curvebymspproject
http://slidepdf.com/reader/full/howtocreates-curvebymspproject 25/50
25Author: Ong-Art S. Factory AVP
Step-4: Set the Project Base Line
3. View Baseline
in a Table
Go to View tab, in Data group click to Table
and select Variance or insert columns withcustom field.
8/12/2019 howtocreates-curvebymspproject
http://slidepdf.com/reader/full/howtocreates-curvebymspproject 26/50
26Author: Ong-Art S. Factory AVP
Updating the progress is the only way to ensure it
stays on tracks as work is performed. The focus atthis point is on managing changes, updating the
schedule, tracking progress and communicating
project information.
MS Project 2013 tracks 3 sets of date: Current,
Baseline and Actual. When we set the baseline,
current = baseline. when a task is 100% complete,
current=actual.
Step-5: Update Progress
8/12/2019 howtocreates-curvebymspproject
http://slidepdf.com/reader/full/howtocreates-curvebymspproject 27/50
8/12/2019 howtocreates-curvebymspproject
http://slidepdf.com/reader/full/howtocreates-curvebymspproject 28/50
28Author: Ong-Art S. Factory AVP
Step-5: Update Progress
2. Track actual
date and duration
It’s the best to decide on a single method
for tracking progress. We can enterpercentage complete, actual start and
finish dates, actual remaining durations or
actual and remaining work.
Click the Task tab, select the task that wewant to enter actual progress. In the
Schedule group select the amount of
progress done on the tasks.
Default: 0%, 25%, 50%, 75%, 100%
Note: we can put a number direct to
%Complete field
8/12/2019 howtocreates-curvebymspproject
http://slidepdf.com/reader/full/howtocreates-curvebymspproject 29/50
29Author: Ong-Art S. Factory AVP
Step-5: Update Progress
3. Track Actual
Hours and Cost
If we want to enter actual and remaining
work hours or costs, use tracking table.Click View tab, in Data group point Table
and select Tracking.
Enter progress data in the Act. Work or Act.
Cost field for the task. Program isdetermine if we put the actual start and
actual finish or % Complete.
f
8/12/2019 howtocreates-curvebymspproject
http://slidepdf.com/reader/full/howtocreates-curvebymspproject 30/50
30Author: Ong-Art S. Factory AVP
MS Project 2013 provide many ways of built in
report, but for us we have to create a customizereport by using S-Curve Reports.
Step-6: View Report Information
S 6 Vi I f i
8/12/2019 howtocreates-curvebymspproject
http://slidepdf.com/reader/full/howtocreates-curvebymspproject 31/50
3Author: Ong-Art S. Factory AVP
Step-6: View Report Information
1. Select a View MS Project 2013 has old and new views to
help you to see project information andreport it to others. Click the View Tab, in
either the Task Views group or Resources
Views group, select the view you want to
use. There’re many view but most usfulones include:-
• Team planner View
• Timeline View
• Gantt Chart View
• Calendar View
S 6 Vi R I f i
8/12/2019 howtocreates-curvebymspproject
http://slidepdf.com/reader/full/howtocreates-curvebymspproject 32/50
32Author: Ong-Art S. Factory AVP
Step-6: View Report Information
2. Customize a
View
Select the view you want to customize and
then on the Format tab click the type ofview element you want to change, such as
the bar style on the Gantt Chart or
gridlines and time scales of any views.
Tips & Tricks, if you want to filter, sort orgroup tasks prior to printing, click the View
tab and then in the Data group, click sort,
Filter or Group options.
St 6 Vi R t I f ti
8/12/2019 howtocreates-curvebymspproject
http://slidepdf.com/reader/full/howtocreates-curvebymspproject 33/50
33Author: Ong-Art S. Factory AVP
Step-6: View Report Information
3. Print a View or
Report
Set up the current view that we want it to
look when printed. Click the File Tab andthen click Print. A preview part of the view
to see the actual size of the view as it will
be printed.
St 6 Vi R t I f ti
8/12/2019 howtocreates-curvebymspproject
http://slidepdf.com/reader/full/howtocreates-curvebymspproject 34/50
34Author: Ong-Art S. Factory AVP
Step-6: View Report Information
4. Generate a
Report
In Report tab has many report to view
information of project but we’re intent tocreate the S-Curve by using MS Project as a
tools, we’ll focus on how to do it.
Click the Report tab, go to View reports
group, select Customer
St 7 St b St t S C
8/12/2019 howtocreates-curvebymspproject
http://slidepdf.com/reader/full/howtocreates-curvebymspproject 35/50
35Author: Ong-Art S. Factory AVP
Step-7: Step by Step to S-Curve
In the field list (right hand) Select Category to Time.
St 7 St b St t S C
8/12/2019 howtocreates-curvebymspproject
http://slidepdf.com/reader/full/howtocreates-curvebymspproject 36/50
36Author: Ong-Art S. Factory AVP
Step-7: Step by Step to S-Curve
Then Select Field go to Work, click Actual Work and
Cumulative Actual Work only.
Step 7: Step by Step to S Curve
8/12/2019 howtocreates-curvebymspproject
http://slidepdf.com/reader/full/howtocreates-curvebymspproject 37/50
37Author: Ong-Art S. Factory AVP
Step-7: Step by Step to S-Curve
The Click on Baseline, click Baseline Cumulative
Work, just only one.
Step 7: Step by Step to S Curve
8/12/2019 howtocreates-curvebymspproject
http://slidepdf.com/reader/full/howtocreates-curvebymspproject 38/50
38Author: Ong-Art S. Factory AVP
Step-7: Step by Step to S-Curve
In chart area Right click to change chart type.
Select Chart type to Combo.
Step 7: Step by Step to S Curve
8/12/2019 howtocreates-curvebymspproject
http://slidepdf.com/reader/full/howtocreates-curvebymspproject 39/50
39Author: Ong-Art S. Factory AVP
Step-7: Step by Step to S-Curve
In the Change Chart Type dialog in Series Name
choose All Cumulative (Actual & Baseline) Chart typeto Line Type.
Actual Work chart type to Clustered Column and
Click Secondary Axis
Step 7: Step by Step to S Curve
8/12/2019 howtocreates-curvebymspproject
http://slidepdf.com/reader/full/howtocreates-curvebymspproject 40/50
40Author: Ong-Art S. Factory AVP
Step-7: Step by Step to S-Curve
In Field List, in Tasks Tab look at Select Category, click
Edit customize time from Days to Weeks and changeformat as you like.
Step 7: Step by Step to S Curve
8/12/2019 howtocreates-curvebymspproject
http://slidepdf.com/reader/full/howtocreates-curvebymspproject 41/50
4Author: Ong-Art S. Factory AVP
Step-7: Step by Step to S-Curve
In design Tab, choose format color as you like.
In Chart Layout select Layout No 5 to show Data
Step 7: Step by Step to S Curve
8/12/2019 howtocreates-curvebymspproject
http://slidepdf.com/reader/full/howtocreates-curvebymspproject 42/50
42Author: Ong-Art S. Factory AVP
Step-7: Step by Step to S-Curve
Final as just Fonts size and others
Step-8: Export Data to Excel
8/12/2019 howtocreates-curvebymspproject
http://slidepdf.com/reader/full/howtocreates-curvebymspproject 43/50
43Author: Ong-Art S. Factory AVP
Step-8: Export Data to Excel
1. Visual Report Go to Report tab, select on Visual reports
Export.Select template dialog show, go to Task
Usage tab, move a mouse on Cash Flow
Report template, then click Edit Template.
In Visual Report-Field Picker is pop up, in
Available Field, select Base line Cumulative
Work and Cumulative Actual Work add to
selected Fields.
Step-8: Export Data to Excel
8/12/2019 howtocreates-curvebymspproject
http://slidepdf.com/reader/full/howtocreates-curvebymspproject 44/50
44Author: Ong-Art S. Factory AVP
Step-8: Export Data to Excel
2. Analyze Data in
Pivot Table
In PivotTable Fields, select only Actual
Work, Baseline Cumulative work andCumulative Actual Work.
Step-8: Export Data to Excel
8/12/2019 howtocreates-curvebymspproject
http://slidepdf.com/reader/full/howtocreates-curvebymspproject 45/50
45Author: Ong-Art S. Factory AVP
Step 8: Export Data to Excel
3. Custom Charts
in Excel
In Pivot Tab Fields, select only Baseline
Cumulative Work, Cumulative Actual Workand Actual Work.
In Chart Area Right Click mouse select
Combo chart, then All cumulative change
type to Line only Actual Work to Clustter
Column.
Step-8: Export Data to Excel
8/12/2019 howtocreates-curvebymspproject
http://slidepdf.com/reader/full/howtocreates-curvebymspproject 46/50
46Author: Ong-Art S. Factory AVP
Step 8: Export Data to Excel
Step-9: Close the Project
8/12/2019 howtocreates-curvebymspproject
http://slidepdf.com/reader/full/howtocreates-curvebymspproject 47/50
47Author: Ong-Art S. Factory AVP
Just because your project is almost finished doesn’t
mean that your work is done. We still need to solve any final project detail and
customer acceptance for final deliverables.
Conduct a “Lessons Learned” session, recording
information abount areas for improvement and bestpractices.
Make any final update to project plan.
Finally archive the project plan according to ourorganization’s guideline.
Step 9: Close the Project
Step-9: Close the Project
8/12/2019 howtocreates-curvebymspproject
http://slidepdf.com/reader/full/howtocreates-curvebymspproject 48/50
48Author: Ong-Art S. Factory AVP
Step 9: Close the Project
1. Create a Final
Report
Click the Report tab, click Visual Reports to
see project data as a Pivot Table report inExcel 2013 or Pivot Diagram view in Visio
professional 2013
We can also view basic reports that don’t
require Excel or Visio. Click Report Tab
many report category available to view
depend on how we want to views.
Step-9: Close the Project
8/12/2019 howtocreates-curvebymspproject
http://slidepdf.com/reader/full/howtocreates-curvebymspproject 49/50
49Author: Ong-Art S. Factory AVP
Step 9: Close the Project
2. Save a Project
as a Template
After completing a project, we have to
leverage what we’ve learned in the projectby making it as a template for future
projects.
Click the File tab and Save As and then in
the Save As Type box click Template.
Thanks you
8/12/2019 howtocreates-curvebymspproject
http://slidepdf.com/reader/full/howtocreates-curvebymspproject 50/50
50Author: Ong-Art S. Factory AVP
Thanks you
End