HR SYSTEM IMPLEMENTATION WORKDAY HUMAN CAPITAL MANAGEMENT, PAYROLL, AND BENEFITS SYSTEM (HCM)

Tuesday, April 15th, 2014

Douglas County School District

Why a Human Resources, Payroll and Benefits Software Change?

2

WE KNOW:

•  Current System Replacement Required –  Obsolete –  Maintenance support soon to be discontinued –  Multiple data sources –  System streamlining needed –  Manual, time-intensive processes

•  Strategic Plan Alignment –  Autonomy and accountability –  Operational efficiencies –  Helping to maximize dollars to the classroom

3

•  Confirmed highly manual, paper-based processes

•  Identified key integration & capability gaps

•  Confirmed lack of “real-time” visibility/access to operational & financial data

•  Recommended system upgrade, numerous additional modules and self service to drive improvement and realize ongoing overhead savings

4

FROM ORACLE INSIGHT, JULY 2011

Request for Proposal (RFP)

Process

5

STARTED WITH ORACLE INSIGHT PROCESS

6

From  Oracle  Insight  Report  

Improved  Time  Keeper  Produc:vity  

($2.8M  -­‐  $3.8M)     Increased  Strategic  Sourcing  

($2.7M  -­‐  $6.3M)  

Reduced  P-­‐Card  Spend  ($0.6M  -­‐  $1.4M)  

Increased  HR  Produc:vity  

($0.6M  -­‐  $1.3M)  

Improved  Payroll  ProducEvity  

($0.05M  -­‐  $1.1M)    

Improved  Procurement  ProducEvity  

($0.13M  -­‐  $0.26M)  

Improved  Planning  &  Budge:ng  Produc:vity  

($0.2M  -­‐  $0.4M)  

Improved  AP  Produc:vity  ($0.1M  -­‐  $0.2M)  

Improved  Core  Acc  Produc:vity  

($0.05M  -­‐  $0.1M)  

Insight  analysis  es:mates  District  could  realize  a  5  year  benefit  of  $7.4M  to  $13.9M  in  labor  produc:vity  improvement1                                            

&  expense  reduc:ons  

PROJECTED COSTS, ORACLE REPORT

7

5 YR INVESTMENT BREAKDOWNBASED ON AN INITIAL ‘BUDGETARY’ LICENSE AND IMPLEMENTATION ESTIMATE

Total Initial Investment,  $6.8  M  

Oracle  Insight  -­‐Review  of  Current  District  Processes    February,  2011  Launch  

Oracle  Insight    Recommenda:ons  Delivered,  July,  2011  

SoNware  Demos    February-­‐April:    Demos  of  Top  Four  Finalists  

NegoEaEons  Workday  and  CedarCrestone  Contract    Nego:a:ons    December  -­‐  April  2014  

AdopEon  of  Internal  System  Changes  AESOP  Subfinder    Budget  Repor:ng  Tool  Spring,    2012  

Financial  &  Human  Resources  SoNware  (ERP)      RFP  Posted,  November  2012  

SoNware  Demos    July  -­‐  November:    Oracle  &  Workday  Deep  Dive  Demos    

FY  2014  FY  2013  FY  2012  FY  2011  

Financial  &  Human  Resources  SoNware  

Taleo  Recruitment  and  Onboarding      Implementa:on,    December  2012  thru  September  2013  

PROCUREMENT TIMELINE

8

Negotiations

9

NEGOTIATION RESULTS

•  Final annual cost reduced

•  Implementation cost reduced

•  Contract length extended

•  Service level agreement extended

•  Consumer price index removed

10

ANNUALIZED COST COMPARISON

11

Workday Oracle

638,715.00$                                                                 218,545.40$                                                                93,000.00$                                                                    350,000.00$                                                                4,500.00$                                                                        14,000.00$                                                                    20,783.00$                                                                    40,000.00$                                                                    94,256.00$                                                                    27,000.00$                                                                    

Annualized  Cost  Comparison 638,715.00$                         862,084.40$                        

Annualized  Cost  ComparisonOn-­‐Going  Cost  -­‐  Based  on  Year  3

HR/Payroll  Core  SoftwareEvaluationsAdministrative  EfficienciesOnboardingATSOrganizational  Development  /  Succession  PlanningCompensation  ModuleReporting  and  DashboardingAdvanced  Benefits  Admin  /  Self-­‐Service  HR

Yearly  Savings  of  $223,369.40  

IMPLEMENTATION COST COMPARISON

12

Workday Oracle

759,209.07$                                                                Included 1,799,505.00$                                                        Included 928,038.00$                                                                

2,200,000.00$                                                        600,000.00$                                                                 600,000.00$                                                                

2,800,000.00$                                                       4,086,752.07$                                                      Future  Upgrade  Costs  $                                                                                                  0   759,209.07$                                                              

Total  Implementation  Costs 2,800,000.00$                 4,845,961.15$                

New  Module  Implementation  (OAB,  SSHR,  Grants,  Perf  Mgt)OBIEE  (Business  Intelligence)  ImplementationWorkday  Implementation  (Prof  Srvcs,  Training,  Delivery  Assur)

Implementation  Cost

DCSD  Internal  Implementation  Costs

Total  Initial  Implementation  Cost

R12  Upgrade  (in  place  upgrade)

One-­‐Time  Implementa:on  Savings  of  $2,045,961  

Simplifying System Integration

& Architecture

13

UPDATING SYSTEM ARCHITECTURE

14

Badges  

All  Internal    ApplicaEons  

RecruiEng  

Content  Management  

&  Onboarding  

eBenefits  IdenEty  Management  

Edulog  

T.O.M.  

REDUCING NUMBER OF SYSTEMS

15

FUTURE ARCHITECTURE

16

Benefits For DCSD

& Our Employees

17

WORKDAY BENEFITS

OrganizaEons  § Real-­‐:me  Reorganiza:ons    § Ac:onable  Organiza:on  Charts  § Employee  Data  Trending  

Benefits  § Open  Enrollment  § PTO  and  LOA  Requests  

Performance  §  Development  Plans  §  Talent  Matrix  (9  Block)  §  Succession  Planning  

CompensaEon  § Pay  for  Performance  § Bi-­‐Weekly  Pay  

Self-­‐Service  §  Employee  Self-­‐Service  §  Manager  Self-­‐Service  

§  Employee  Details  §  Automated  Processes  

Ease  of    Use  §  Intui:ve  §  Streamlined,  documented  processes  

§  Mobile  Access  §  Innova:ve  §  Automated,  Documented,  Centrally  Managed  Processed  

Reduced  Cost  of  Ownership  §  No  Upgrade  Fees  §  Reduced  Maintenance  and  Support  Cost  

§  No  Infrastructure  Overhead  §  Replacement  for  a  Number  of  Exis:ng  Systems  

§  Reduced  Development  Need  

§  Configurable  

ReporEng  Capability  §  Data  available  directly  to  principals,  directors,  and  managers  

§  Analy:cs  §  Ac:onable  Insight  §  Dashboards  §  Real  Time  Data  

Secure  § SOC  Compliant  § ISO  27001  Cer:fied  § Safe  Harbor  Framework  § Fully  Redundant  System    § Physically  Secure  Data  Center  

18

123123  Smith,  Joe  

123123-­‐2  

123123-­‐2  

123123-­‐2  

123123-­‐2  

ABC  School  

ABC  School  

ABC  School  

ABC  School  

987  Wilcox  Street  

MOVING FROM…

19

TO A MORE INTUITIVE SYSTEM

20

•  Stakeholder input –  Only those requiring approval

•  One source of data –  Departments pull data as needed

•  Best practices (shortest cycle time) –  Bust bureaucracy

•  Autonomy –  Ensure ability to control changes in your domain

•  Accountability –  Ensure the ability to track, audit and report

PHILOSOPHY – PROCESS IMPROVEMENT

21

THANK YOU!