hughes risk management 2017/18 projects...

25
1 | Page Uncontrolled Document Hughes Risk Management 2017/18 Projects Update

Upload: others

Post on 12-Sep-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Hughes Risk Management 2017/18 Projects Updatehughesriskmanagement.com/.../07/...to-date-newest.pdf · West Courageous West Defender West Oberon The project scope of work included:

1 | P a g e

Uncontrolled Document

Hughes Risk Management

2017/18 Projects Update

Page 2: Hughes Risk Management 2017/18 Projects Updatehughesriskmanagement.com/.../07/...to-date-newest.pdf · West Courageous West Defender West Oberon The project scope of work included:

2 | P a g e

Uncontrolled Document

Project 1

Updating of HSE Cases, Major Accident Hazard Risk Assessments (MAHRA), Performance Standards and Verification Schemes for the following Jack-Up Units working in the Americas and Mexico for Seadrill.

The following Jack-Ups where included in the work programme:

West Castor

West Intrepid

West Titania

West Freedom

West Courageous

West Defender

West Oberon

The project scope of work included:

Full HSE Case update to include IADC Guidance and the Seadrill HSE Case Directives

MAHRA updates, MAH BowTie ratification and QRA and Sensitivity studies ratification

Performance Standards and Verification Scheme of SECE’s

This work has been undertaken with direct consultation and input from both the Crews, Management and Regional HSEQ inputs.

Project completion is due in October 2017 in line with the established and agreed work programme with Seadrill Americas and Mexico Region.

Page 3: Hughes Risk Management 2017/18 Projects Updatehughesriskmanagement.com/.../07/...to-date-newest.pdf · West Courageous West Defender West Oberon The project scope of work included:

3 | P a g e

Uncontrolled Document

Project 2

Development of a suite of SECE Performance Standards and Verification Scheme for Edrill ED1 and ED2 Tender Assist Barges in China.

Review of existing risk assessment and CMMS for listed Safety Critical Equipment.

Listing of SECE’s from the process linked to MAH (Major Accident Hazard), MEI (Major Environmental Incident) and MPI’s (Major Pollution Incident) and their respective BowTie barriers.

Development of the SECE Performance Standards for verification.

Development of Verification Scheme for Performance Standard assurance linked with CMMS and the HSE Case. Reports on all deliverables.

This work has been undertaken with direct consultation and input from both the ED1 and ED2 Crew, Management and Regional HSEQ inputs.

Project completed in April 2017 in line with the established and agreed work programme with Edrill Singapore and ED1 and 2 Rig

Management Team.

Page 4: Hughes Risk Management 2017/18 Projects Updatehughesriskmanagement.com/.../07/...to-date-newest.pdf · West Courageous West Defender West Oberon The project scope of work included:

4 | P a g e

Uncontrolled Document

Project 3

Management of Change Independent Audit for the TaqTaq facilities in Kurdistan

Development of Terms of Reference to cover all aspects of the current MOC process use in TTOPCO. Setting up target of acceptance criteria Previous audit reviews to establish current status of carry over actions

Site visit, interviews and assessment of the MOC process with the objective of:

Determine the adequacy of the Taq Taq documentation in supporting the overall MOC process with findings and recommendations

Assess the correct use of the documentation to ensure that what is being undertaken does comply with all aspects of the current MOC procedure

Further assess progression from previous internal MOC audits

Reporting on findings, conclusions and recommendations for TTOPCO consideration against the Terms of Reference and target criteria set.

The audit took place at TaqTaq between 13th and 16th March 2017 with prework and reporting at the HRM offices in the UK with

project completion in March 2017.

Page 5: Hughes Risk Management 2017/18 Projects Updatehughesriskmanagement.com/.../07/...to-date-newest.pdf · West Courageous West Defender West Oberon The project scope of work included:

5 | P a g e

Uncontrolled Document

Project 4

Updating of HSE Cases, Major Accident Hazard Risk Assessments (MAHRA), Performance Standards and Verification Schemes for the following Tender Assist Barges working in Thailand for Seadrill.

The following Tender Assist Barges where included in the work programme

T15

T16

The project scope of work included:

Full HSE Case update to include IADC Guidance and the Seadrill HSE Case Directives

MAHRA updates including BowTies and SECE listing

Performance Standards and Verification Scheme of SECE’s

Compliance with Chevron Safeguard Verification Programme

This work has been undertaken with direct consultation and input from both the Crews, Management and Regional HSEQ inputs.

Project completion is due in September 2017 in line with the established and agreed work programme with Seadrill Singapore and Thailand.

Page 6: Hughes Risk Management 2017/18 Projects Updatehughesriskmanagement.com/.../07/...to-date-newest.pdf · West Courageous West Defender West Oberon The project scope of work included:

6 | P a g e

Uncontrolled Document

Project 5

OPHIR Energy engaged HRM to provide Learship and scribe for a Hazard Identification and Risk Assessment for a Deepwater Drill Campaign of the coast of Cote d’Ivoire. This included the use a Seadrill Deepwater 6th Generation Drillship West Saturn to drill the well and have three supply vessels out of Abidjan and a helicopter out of San Pedro to support the project, along with a security vessel on location during the drilling campaign.

Workshop to conduct a Hazard Identification (HazId) of Major Accident Hazards (MAH) using BowTie analysis to determine barrier management and consequence outcomes.

From the HazId develop a set of MAH Bowties with supporting hazard register

Report on the process.

The key deliverable was to:

Consolidated Hazards using the Ophir Risk matrix and record the results on the hazard identification sheets

Major Accident Hazard Bowties and associated hazard management barriers (Safety Critical Equipment/Safety Critical Activities)

Control measures and interactions of Safety Critical Equipment/Safety Critical Activities

Ranking of barriers (with selected verification checks)

Bowtie profiles and Major Accident Hazard list

This work has been undertaken with direct consultation and input from West Saturn representatives and OPHIR with HRM

providing Facilitation, Scribe and reporting functions. Project completion was April 2017.

Page 7: Hughes Risk Management 2017/18 Projects Updatehughesriskmanagement.com/.../07/...to-date-newest.pdf · West Courageous West Defender West Oberon The project scope of work included:

7 | P a g e

Uncontrolled Document

Project 6

HRM conducted on behalf of TTOPCO a Quantitative Risk Assessment (QRA) for their CPF1, TPF1, TPF2 and TLS

facilities at the TaqTaq field. Based on the outputs of this QRA study, a Risk Reduction Workshop was held to provide TTOPCO with a listing of potential risk reduction measures for consideration, in order to improve the ALARP status of the facilities and to provide a structured way forward for continuous improvement. HRM where requested by TTOPCO to

conduct a review of the risk reduction measures and re – run of QRA sensitivities associated with these supported by CBA.

Review of recommended risk reduction measures against production criteria that encompassed part shutdown of facilities.

Using PHAST and Jeopardy software conduct a re-run of sensitivities based upon the review criteria to produce risk contours and PLL, IRPA and FAR rates associated with risk reduction enhancement or otherwise.

Cost Benefit Analysis to support judgment and approvals and ALARP demonstration of selected or discounted measures against the review criteria.

Reporting and overall Management presentation of findings, conclusions and recommendations at TaqTaq facilities in Kurdistan.

The work was completed in June 2017.

Page 8: Hughes Risk Management 2017/18 Projects Updatehughesriskmanagement.com/.../07/...to-date-newest.pdf · West Courageous West Defender West Oberon The project scope of work included:

8 | P a g e

Uncontrolled Document

Project 7

SECE Performance Standard development and integration with Seadrill CMMS (IFS) and new MAXIMO project (RAMP) for 37 assets including UDW, Drillships, Semi Submersibles and Jack-Up Assets worldwide. Project executed over two work phases.

Phase 1 Development of SECE lists for a Drillship (West Neptune), Jack-Up (West Castor) and Semi-Submersible (West Capricorn) from BowTie barrier analysis into a suite of Performance Standards to be placed in MAXIMO for all assurance and verification requirements. This further included updating:

MAH Bowties with SFI links and MEI/MPI considerations

Development of MAHRA connecting the barriers, SECE and Performance Standards

Suite of Performance Standards by asset

Verification Scheme by Assets

Performance Standard Assurance Sheets to be placed in MAXIMO for assurance activities relating to each Performance Standard requirement (Function Testing, etc).

Use of the deliverables as a template to roll out over the remaining 37 Seadrill assests in Phase 2.

Phase 2 Using the templates from Phase 1 development by asset type of deliverables to support the intergration (RAMP Project).

MAHRA update or development as required.

SECE and Performance Standards development based on the templates taking account of design or operation differences.

Verification Scheme by Assets.

Performance Standard Assurance Sheets for MAXIMO.

Actions listing as required from verification findings from overall process.

Updates as required. Phase 1 was completed in July 2017

Phase 2 commenced August 2017 and will run until June 2018.

Page 9: Hughes Risk Management 2017/18 Projects Updatehughesriskmanagement.com/.../07/...to-date-newest.pdf · West Courageous West Defender West Oberon The project scope of work included:

9 | P a g e

Uncontrolled Document

Project 8

CE Marking and Technical file support for can conveying systems in Bulgaria for ECi Engineering.

Review of design basis and integration with existing canning conveying systems.

Development of the Technical File and conformity statements/attachments to meet all relevant and applicable EU Directives.

Deliverables include:

Technical file and report

Machinery Directive 2006/42/EU/EC Checklist and attachments

Safety of Machinery Preliminary Hazard Identification

Machinery Directive 2006/42/EC Essential Health and Safety Requirements (Annex 1)

Declaration of Incorporation/Conformity Machinery Directive

Technical Data Sheets

Work to complete in October 2017

The work programme has commenced in January 2016 with a delivery date of February 2016. Project complete to ECi and their Client satisfaction.

Page 10: Hughes Risk Management 2017/18 Projects Updatehughesriskmanagement.com/.../07/...to-date-newest.pdf · West Courageous West Defender West Oberon The project scope of work included:

10 | P a g e

Uncontrolled Document

Project 9

Updating of the West Capella HSE Cases, Major Accident Hazard Risk Assessments (MAHRA), Performance Standards and Verification Schemes for work in Cypriot waters under EU Directive for Seadrill.

The following Drill Ship was included in the work programme:

West Capella

The project scope of work included:

Full HSE Case update to include IADC Guidance, EU Directive EU/2013/34/EU , SCR 2015 and the Seadrill HSE Case Directives

MAHRA updates, MAH Bowtie ratification and QRA and Sensitivity studies ratification

Performance Standards and Verification Scheme of SECE’s

HazId and MAH BowTie Workshop with West Capella crew

Workshop on compliance with Total In Cyprus

This work has been undertaken with direct consultation and input from both the Crews, Management and Regional HSEQ inputs.

Project completed in June 2017.

Page 11: Hughes Risk Management 2017/18 Projects Updatehughesriskmanagement.com/.../07/...to-date-newest.pdf · West Courageous West Defender West Oberon The project scope of work included:

11 | P a g e

Uncontrolled Document

Project 10

Updating of HSE Cases, Major Accident Hazard Risk Assessments (MAHRA), Performance Standards and Verification Schemes for the following Jack-Up Units working in the Arabian Gulf for Advanced Energy Systems.

The following Jack ups where included in the work programme:

Rig 261 Rig 262 Rig 266

The project scope of work included: Full HSE Case update to include IADC Guidance and the ADES HSE

Case Directives Compliance with ARAMCO SWIM and Drilling Directives MAHRA updates, MAH Bowtie ratification and QRA and Sensitivity

studies ratification SECE listing HazId and MAH Bowtie workshop in Bahrain

This work has been undertaken with direct input and consultation and input from both the Crews, Management and Regional HSEQ inputs.

Project completed in June 2017 in line with the established and agreed work programme.

Page 12: Hughes Risk Management 2017/18 Projects Updatehughesriskmanagement.com/.../07/...to-date-newest.pdf · West Courageous West Defender West Oberon The project scope of work included:

12 | P a g e

Uncontrolled Document

Project 11

Updating of HSE Cases, Major Accident Hazard Risk Assessments (MAHRA), Performance Standards and Verification Schemes for the following Units working in the Americas for Seadrill

The following where included in the work programme:

West Auriga - Drillship

West Capricorn – Semi Submersible

The project scope of work included:

Full HSE Case update to include IADC Guidance and the Seadrill HSE Case Directives

MAHRA updates, MAH Bowtie ratification and QRA and Sensitivity studies ratification

Performance Standards and Verification Scheme of SECE’s

MAH BowTie work shop in Houston with West Auriga and West Capricorn crews

HSE Case Training packages

This work has been undertaken with direct consultation and input from both the Crews, Management and Regional HSEQ inputs.

Project completed in June 2017 in line with the established and agreed work programme with Seadrill Americas,

Page 13: Hughes Risk Management 2017/18 Projects Updatehughesriskmanagement.com/.../07/...to-date-newest.pdf · West Courageous West Defender West Oberon The project scope of work included:

13 | P a g e

Uncontrolled Document

Project 12

Detailed Design Technical Safety support for NMWG under an established 3 year call off services agreement.

FEED and Detailed Design HazOp and HazId Chair and reporting.

Development of Project Technical Safety Plan, EER and Layout studies.

Qualitative risk assessment linked to the HAZID and HazOp processes. Gas dispersion review.

Input to modification change process and design change registers.

The work programme commenced in 2017.

Page 14: Hughes Risk Management 2017/18 Projects Updatehughesriskmanagement.com/.../07/...to-date-newest.pdf · West Courageous West Defender West Oberon The project scope of work included:

14 | P a g e

Uncontrolled Document

Project 13

Development of a CDM Compliance Document and Guidance with Vessel HSE Case for non-Oil and Gas production working (non regulatory).

Development of CDM 2015 Guidance document relating to Offshore Wind Farm Installation for Jan De Nul’s Vol Au Vent Vessel which included a breakdown of requirements, compliance matrices and description of roles and duties under Principal Contractor or Contractor activities.

Development of Major Accident Hazard Risk Assessment report using BowTie analysis for all operations and vessel associated risk. Listing of SECE’s and their performance standards and assurance requirements.

Development of a HSE Case document (non regulatory) to demonstrate ALARP across the vessel and its operations for prospective clients and for worker education.

The work programme completed in April 2017.

Page 15: Hughes Risk Management 2017/18 Projects Updatehughesriskmanagement.com/.../07/...to-date-newest.pdf · West Courageous West Defender West Oberon The project scope of work included:

15 | P a g e

Uncontrolled Document

Project 14

Workshop for SECE and Integrity system integration workshop to be held at Seadrill in London.

Work Task 1 Develop review sheets and overall outline of SECE and Maintenance systems acceptance/criteria matrix for work shop discussion.

Work Task 2 Attendance at a workshop to develop:

Strategies for incorporating SECE and Performance Standards into the Seadrill maintenance and integrity system.

Application of barrier management with the context of BowTies and integrity systems tagging, etc.

Directive and guidance for application with template examples.

Use of “mind mapping” to determine the points above and assist in the development of logic for the computerised systems.

Deliverables Reporting Directive/guidance document with worked examples

The work programme completed in February 2017.

Page 16: Hughes Risk Management 2017/18 Projects Updatehughesriskmanagement.com/.../07/...to-date-newest.pdf · West Courageous West Defender West Oberon The project scope of work included:

16 | P a g e

Uncontrolled Document

Project 15

Development of Major Accident Hazard Risk Assessments (MAHRA), for the following Jack-Up Units working in the Arabian Gulf and Nigeria for Shelf Drilling.

The following Jack ups where included in the work programme:

SD Mentor SD Tenacious SD Resourceful

The project scope of work included: Hazard Identification and risk ranking (SHIDAC) Compartment studies and verification activities BOWTIE Workshop, barrier assessment and ranking of MAH events SECE listing SOOB Development

This work has been undertaken with direct input and consultation and input from both the Crews, Management and Regional HSEQ inputs.

Project completed in November 2017 in line with the established and agreed work programme.

Page 17: Hughes Risk Management 2017/18 Projects Updatehughesriskmanagement.com/.../07/...to-date-newest.pdf · West Courageous West Defender West Oberon The project scope of work included:

17 | P a g e

Uncontrolled Document

Project 16

Updating of the West Saturn HSE Cases, Major Accident Hazard Risk Assessments (MAHRA), Performance Standards and Verification Schemes for work in Brazilian waters under ANP Regulations for Seadrill.

The following Drill Ship was included in the work programme:

West Saturn

The project scope of work included:

Full HSE Case update to include IADC Guidance, Seadrill Directives and ANP Regulations

MAHRA study, MAH Bowtie ratification and QRA and Sensitivity studies ratification

Performance Standards and Verification Scheme of SECE’s

HazId and MAH BowTie Workshop with West Saturn crew

ANP HSE Case compliance matrix

Red Zone HazId

This work has been undertaken with direct consultation and input from both the Crews, Management and Regional HSEQ inputs.

Project commenced in November 2017 for completion in February 2018.

Page 18: Hughes Risk Management 2017/18 Projects Updatehughesriskmanagement.com/.../07/...to-date-newest.pdf · West Courageous West Defender West Oberon The project scope of work included:

18 | P a g e

Uncontrolled Document

Project 17

HRM provided support to Full Spectrum Property Management Services in Carlisle to establish the following systems and processes

With Client, developed full HSEM system based on HSG65 and ISO14001 and 18001

Risk assessment programme covering the companies activities and roles

COSHH support programme

CDM inter-actions and specific Legislatory and Code of Practice compliance based on the services provided Consulting support programme

The work programme commenced in November 2017 and completed December 2017.

Page 19: Hughes Risk Management 2017/18 Projects Updatehughesriskmanagement.com/.../07/...to-date-newest.pdf · West Courageous West Defender West Oberon The project scope of work included:

19 | P a g e

Uncontrolled Document

Project 18

HSE Case operational tools development and implementation

Work Task 1 Develop Task Criticality roles based on SECE and Bowtie barrier outputs linked to job descriptions of responsible and accountable personnel

Work Task 2 Development of Presentations:

General crew based HSE Case and MAHRA training packages Development of specific role and responsibility training packages for

barrier management Bowtie packages Overall examination and checking tools for learning and feedback CARE Card development and T Card system

Deliverables Reporting Composite deliverables for training and education learning tools

The work programme completed in March 2018 and roll out programme in 2018. / 19.

Page 20: Hughes Risk Management 2017/18 Projects Updatehughesriskmanagement.com/.../07/...to-date-newest.pdf · West Courageous West Defender West Oberon The project scope of work included:

20 | P a g e

Uncontrolled Document

Project 19

Updating of the West Capella HSE Cases, Major Accident Hazard Risk Assessments (MAHRA), Performance Standards and Verification Schemes to meet internal RAMP and MAXIMO inputs.

The following Drill Ship was included in the work programme:

West Capella

The project scope of work included:

Full HSE Case update

MAHRA updates, MAH Bowtie ratification and QRA and Sensitivity studies ratification

Performance Standards and Verification Scheme of SECE’s to meet RAMP an MAXIMO integration with verification target values

This work is ongoing for completion May 2018.

Page 21: Hughes Risk Management 2017/18 Projects Updatehughesriskmanagement.com/.../07/...to-date-newest.pdf · West Courageous West Defender West Oberon The project scope of work included:

21 | P a g e

Uncontrolled Document

Project 20

Updating of HSE Cases, Major Accident Hazard Risk Assessments (MAHRA), Performance Standards and Verification Schemes for the following Jack-Up Units working in the KSA for Seadrill

The following where included in the work programme:

AOD 1

AOD2

AOD3

The project scope of work included:

Full HSE Case update to include IADC Guidance and the Seadrill HSE Case Directives

MAHRA updates, MAH Bowtie ratification and QRA and Sensitivity studies ratification

Performance Standards and Verification Scheme of SECE’s

MAH BowTie workshops on board the rigs with the crew and Human factors/compartment survey

HSE Case Training packages

This work is undertaken with direct consultation and input from both the Crews, Management and Regional HSEQ inputs.

Project completes in June 2018 in line with the established and agreed work programme with Seadrill KSA.

Page 22: Hughes Risk Management 2017/18 Projects Updatehughesriskmanagement.com/.../07/...to-date-newest.pdf · West Courageous West Defender West Oberon The project scope of work included:

22 | P a g e

Uncontrolled Document

Project 21

Updating HSEQ Management System, Risk Assessments, CDM and COSHH systems

Review and update of existing HSEQ systems to meet regulatory and ECi scope changes for manufacturing and installation

Deliverables include:

HSEQ Policy update and Corporate Statements

HSEQ Standards, procedures and instruction updates

Hazid register and BowTie risk assessment updating for design, manufacture, construction and installation activities

CDM 2015 updates

COSHH system review and updates

Technical Data Sheets

Work to complete in June 2018

The work programme has commenced in January 2016 with a delivery date of February 2016. Project complete to ECi and their Client satisfaction.

Page 23: Hughes Risk Management 2017/18 Projects Updatehughesriskmanagement.com/.../07/...to-date-newest.pdf · West Courageous West Defender West Oberon The project scope of work included:

23 | P a g e

Uncontrolled Document

Project 22

Development of HSE Case and supporting studies to meet EU Directive for Admarine 1V located in Egypt for ADES.

The following where included in the work programme:

AdMarine 1V and ADES Corporate

The project scope of work included:

Full HSE Case update to include IADC Guidance and the EU Directive 2013/30/EU Safety of offshore oil and gas operations

MAHRA updates, MAH Bowtie ,QRA and Sensitivity studies , EERA and ESSA studies

Performance Standards and Verification Scheme of SECE’s

ADES Corporate CMAPP

HSE Case Training packages

This work is undertaken with direct consultation and input from both the Crews, Management and Regional HSEQ inputs.

Project completes in September 2018 in line with the established and agreed work programme with ADES

Page 24: Hughes Risk Management 2017/18 Projects Updatehughesriskmanagement.com/.../07/...to-date-newest.pdf · West Courageous West Defender West Oberon The project scope of work included:

24 | P a g e

Uncontrolled Document

For further information on services or projects please contact us at

Page 25: Hughes Risk Management 2017/18 Projects Updatehughesriskmanagement.com/.../07/...to-date-newest.pdf · West Courageous West Defender West Oberon The project scope of work included:

25 | P a g e

Uncontrolled Document

[email protected]

Our location is

Or visit our website at www.hughesriskmanagement.com