Hydrogeochemical Considerations related to Disposal of Thickened
Tailings, including Paste
Rens VerburgGolder Associates, Redmond, USA
15th ANNUAL BC/MEND ML/ARD WORKSHOPDecember 3rd and 4th, 2008
![Page 2: Hydrogeochemical Considerations related to Disposal of …bc-mlard.ca/files/presentations/2008-5-VERBURG-hydro... · 2017-03-28 · Comparison of Characteristics Slurry Thickened](https://reader031.vdocuments.net/reader031/viewer/2022011818/5e8e143ca684107123582f27/html5/thumbnails/2.jpg)
Presentation Overview
IntroductionThickened Tailings
CharacteristicsPotential Benefits
Environmental BenefitsCase Study ACase Study B
Conclusions
![Page 3: Hydrogeochemical Considerations related to Disposal of …bc-mlard.ca/files/presentations/2008-5-VERBURG-hydro... · 2017-03-28 · Comparison of Characteristics Slurry Thickened](https://reader031.vdocuments.net/reader031/viewer/2022011818/5e8e143ca684107123582f27/html5/thumbnails/3.jpg)
Introduction
Increased pressure for development of innovative mine waste disposal practicesPrompted by
Regulatory pressureSustainability principlesRisk aversionCost
Tailings: dry disposal
![Page 4: Hydrogeochemical Considerations related to Disposal of …bc-mlard.ca/files/presentations/2008-5-VERBURG-hydro... · 2017-03-28 · Comparison of Characteristics Slurry Thickened](https://reader031.vdocuments.net/reader031/viewer/2022011818/5e8e143ca684107123582f27/html5/thumbnails/4.jpg)
Comparison of CharacteristicsSlurry Thickened Paste Filter Cake
Segregation High Slight None NoneSolids Content 30-50% 60-65% 70-75% 75-80%Supernatant Considerable Some None NonePost-Placement Shrinkage
High Some Insignificant None
Seepage High Some Insignificant NoneRehab Timing Delayed, often
considerableAlmost
ImmediatelyAlmost
ImmediatelyImmediately
Angle of Repose Up to 1o 1o to 3o 3o to 10o Up to Erosion Angle
Potential Water Recovery
Up to 53% Up to 67% Up to 82% Generally above 82%
Adopted from J. Johnson, Golder - Denver
![Page 5: Hydrogeochemical Considerations related to Disposal of …bc-mlard.ca/files/presentations/2008-5-VERBURG-hydro... · 2017-03-28 · Comparison of Characteristics Slurry Thickened](https://reader031.vdocuments.net/reader031/viewer/2022011818/5e8e143ca684107123582f27/html5/thumbnails/5.jpg)
Potential Benefits of Dry Disposal
Siting flexibilityMinimal liquid/solid segregationMinimal particle segregationDenser/lower permeabilitySmaller footprintReduced need for damsExtend life of facilityReduced care and maintenance
Less water to manageLess seepage/ contaminant migrationWater conservationEngineered materialLess reactive (sulfide oxidation)Concurrent/progressive closureImproved aestheticsPotential for co-disposalEnhanced sustainability
![Page 6: Hydrogeochemical Considerations related to Disposal of …bc-mlard.ca/files/presentations/2008-5-VERBURG-hydro... · 2017-03-28 · Comparison of Characteristics Slurry Thickened](https://reader031.vdocuments.net/reader031/viewer/2022011818/5e8e143ca684107123582f27/html5/thumbnails/6.jpg)
Fact or Fiction?
Assumed environmental benefit:Sulfide oxidation/ARD generation retarded due to high degree of saturation
However:Lack of operational verificationLack of systematic studies
![Page 7: Hydrogeochemical Considerations related to Disposal of …bc-mlard.ca/files/presentations/2008-5-VERBURG-hydro... · 2017-03-28 · Comparison of Characteristics Slurry Thickened](https://reader031.vdocuments.net/reader031/viewer/2022011818/5e8e143ca684107123582f27/html5/thumbnails/7.jpg)
Case Study A
Arid region20-week HCT program
Three thickened tailings samplesFilter cakePasteThickened tailings
![Page 8: Hydrogeochemical Considerations related to Disposal of …bc-mlard.ca/files/presentations/2008-5-VERBURG-hydro... · 2017-03-28 · Comparison of Characteristics Slurry Thickened](https://reader031.vdocuments.net/reader031/viewer/2022011818/5e8e143ca684107123582f27/html5/thumbnails/8.jpg)
Case Study A – Tailings Properties
Moisture content:Filter cake: 16%Paste: 22%Thickened tailings: 29%
Sulfide Sulfur: 31%NNP: -957 kg CaCO3/tonNPR: < 0.1
![Page 9: Hydrogeochemical Considerations related to Disposal of …bc-mlard.ca/files/presentations/2008-5-VERBURG-hydro... · 2017-03-28 · Comparison of Characteristics Slurry Thickened](https://reader031.vdocuments.net/reader031/viewer/2022011818/5e8e143ca684107123582f27/html5/thumbnails/9.jpg)
HCT Results - pH
![Page 10: Hydrogeochemical Considerations related to Disposal of …bc-mlard.ca/files/presentations/2008-5-VERBURG-hydro... · 2017-03-28 · Comparison of Characteristics Slurry Thickened](https://reader031.vdocuments.net/reader031/viewer/2022011818/5e8e143ca684107123582f27/html5/thumbnails/10.jpg)
HCT Results - Sulfate
![Page 11: Hydrogeochemical Considerations related to Disposal of …bc-mlard.ca/files/presentations/2008-5-VERBURG-hydro... · 2017-03-28 · Comparison of Characteristics Slurry Thickened](https://reader031.vdocuments.net/reader031/viewer/2022011818/5e8e143ca684107123582f27/html5/thumbnails/11.jpg)
Case Study B - Neves Corvo Mine
Underground high-grade Cu-(Sn)-Zn mine in Iberian Pyrite Belt since 1989Lundin MiningVolcanogenic Massive Sulfide (VMS)
![Page 12: Hydrogeochemical Considerations related to Disposal of …bc-mlard.ca/files/presentations/2008-5-VERBURG-hydro... · 2017-03-28 · Comparison of Characteristics Slurry Thickened](https://reader031.vdocuments.net/reader031/viewer/2022011818/5e8e143ca684107123582f27/html5/thumbnails/12.jpg)
Tailings ManagementUnderground paste backfill and in unlined tailings impoundment (135 ha, 15 Mt)Production of 42 Mt anticipated (14 Mt underground)Sustainable operational and post-closure tailings management: dry disposal vs. subaqueous deposition
No requirement for new dam raises (cost, risk)No increase in footprintNo requirement for maintaining pond in perpetuity (arid climate)Co-mixing with PAG waste rockConcurrent reclamation Regulatory pressures
![Page 13: Hydrogeochemical Considerations related to Disposal of …bc-mlard.ca/files/presentations/2008-5-VERBURG-hydro... · 2017-03-28 · Comparison of Characteristics Slurry Thickened](https://reader031.vdocuments.net/reader031/viewer/2022011818/5e8e143ca684107123582f27/html5/thumbnails/13.jpg)
Case Study B – Tailings Properties
Moisture content:Filter cake: 18%Paste: 26%Thickened tailings: 31%
Sulfide Sulfur: 29%NNP: -880 kg CaCO3/tonNPR: < 0.1
![Page 14: Hydrogeochemical Considerations related to Disposal of …bc-mlard.ca/files/presentations/2008-5-VERBURG-hydro... · 2017-03-28 · Comparison of Characteristics Slurry Thickened](https://reader031.vdocuments.net/reader031/viewer/2022011818/5e8e143ca684107123582f27/html5/thumbnails/14.jpg)
Tailings Environmental Stability
Bench-Scale (2000) Field Cell (2002 - 2005)
Paste Pilot (2005 - current)
![Page 15: Hydrogeochemical Considerations related to Disposal of …bc-mlard.ca/files/presentations/2008-5-VERBURG-hydro... · 2017-03-28 · Comparison of Characteristics Slurry Thickened](https://reader031.vdocuments.net/reader031/viewer/2022011818/5e8e143ca684107123582f27/html5/thumbnails/15.jpg)
Bench-Scale Study - pH
![Page 16: Hydrogeochemical Considerations related to Disposal of …bc-mlard.ca/files/presentations/2008-5-VERBURG-hydro... · 2017-03-28 · Comparison of Characteristics Slurry Thickened](https://reader031.vdocuments.net/reader031/viewer/2022011818/5e8e143ca684107123582f27/html5/thumbnails/16.jpg)
Bench-Scale Study - SC
![Page 17: Hydrogeochemical Considerations related to Disposal of …bc-mlard.ca/files/presentations/2008-5-VERBURG-hydro... · 2017-03-28 · Comparison of Characteristics Slurry Thickened](https://reader031.vdocuments.net/reader031/viewer/2022011818/5e8e143ca684107123582f27/html5/thumbnails/17.jpg)
Paste Trial
35,000 m3 in 1-hectare areaObjectives:
Experience with plant operation/placementEnvironmental monitoring• Suction lysimeters, piezometers,
standpipes• Runoff collection
Geotechnical monitoring• Tensiometers• Berm design (PAG waste rock)
Trials of cover designs• Low-flux cover without capillary break• Low-flux cover with capillary break• Barrier cover (sand/bentonite)
![Page 18: Hydrogeochemical Considerations related to Disposal of …bc-mlard.ca/files/presentations/2008-5-VERBURG-hydro... · 2017-03-28 · Comparison of Characteristics Slurry Thickened](https://reader031.vdocuments.net/reader031/viewer/2022011818/5e8e143ca684107123582f27/html5/thumbnails/18.jpg)
Pilot Cell Construction
![Page 19: Hydrogeochemical Considerations related to Disposal of …bc-mlard.ca/files/presentations/2008-5-VERBURG-hydro... · 2017-03-28 · Comparison of Characteristics Slurry Thickened](https://reader031.vdocuments.net/reader031/viewer/2022011818/5e8e143ca684107123582f27/html5/thumbnails/19.jpg)
Cover Placement and Instrumentation
![Page 20: Hydrogeochemical Considerations related to Disposal of …bc-mlard.ca/files/presentations/2008-5-VERBURG-hydro... · 2017-03-28 · Comparison of Characteristics Slurry Thickened](https://reader031.vdocuments.net/reader031/viewer/2022011818/5e8e143ca684107123582f27/html5/thumbnails/20.jpg)
Paste Trial
![Page 21: Hydrogeochemical Considerations related to Disposal of …bc-mlard.ca/files/presentations/2008-5-VERBURG-hydro... · 2017-03-28 · Comparison of Characteristics Slurry Thickened](https://reader031.vdocuments.net/reader031/viewer/2022011818/5e8e143ca684107123582f27/html5/thumbnails/21.jpg)
Draindown Modeling
Unsaturated flow modeling for estimation of seepage
Ward Wilson (UBC)Fernando Junqueira (Golder-Burnaby)
SVFluxTM - SoilVision30-meter paste layer
No coverLow-flux coverBarrier cover
![Page 22: Hydrogeochemical Considerations related to Disposal of …bc-mlard.ca/files/presentations/2008-5-VERBURG-hydro... · 2017-03-28 · Comparison of Characteristics Slurry Thickened](https://reader031.vdocuments.net/reader031/viewer/2022011818/5e8e143ca684107123582f27/html5/thumbnails/22.jpg)
100-Year Saturation Profile – No Cover
![Page 23: Hydrogeochemical Considerations related to Disposal of …bc-mlard.ca/files/presentations/2008-5-VERBURG-hydro... · 2017-03-28 · Comparison of Characteristics Slurry Thickened](https://reader031.vdocuments.net/reader031/viewer/2022011818/5e8e143ca684107123582f27/html5/thumbnails/23.jpg)
100-Year Saturation Profile – All Scenarios
![Page 24: Hydrogeochemical Considerations related to Disposal of …bc-mlard.ca/files/presentations/2008-5-VERBURG-hydro... · 2017-03-28 · Comparison of Characteristics Slurry Thickened](https://reader031.vdocuments.net/reader031/viewer/2022011818/5e8e143ca684107123582f27/html5/thumbnails/24.jpg)
Paste Trial - Pore Water pH TrendsControl (no cover)
250 mm 500 mm 1,000 mmWaste Rock
Barrier Cover (with bentonite)
![Page 25: Hydrogeochemical Considerations related to Disposal of …bc-mlard.ca/files/presentations/2008-5-VERBURG-hydro... · 2017-03-28 · Comparison of Characteristics Slurry Thickened](https://reader031.vdocuments.net/reader031/viewer/2022011818/5e8e143ca684107123582f27/html5/thumbnails/25.jpg)
Paste Trial - Pore Water pH Trends
250 mm 500 mm 1,000 mm 250 mm 500 mm
250 mm 500 mm250 mm 500 mm
Waste Rock
Waste Rock Waste Rock
![Page 26: Hydrogeochemical Considerations related to Disposal of …bc-mlard.ca/files/presentations/2008-5-VERBURG-hydro... · 2017-03-28 · Comparison of Characteristics Slurry Thickened](https://reader031.vdocuments.net/reader031/viewer/2022011818/5e8e143ca684107123582f27/html5/thumbnails/26.jpg)
Fact or Fiction?Fiction:
ARD not a concern when using thickened tailingsSaturation can be maintained in arid climate without engineered controls
Fact:Lag time to ARD is proportional to moisture content – “operational window”With engineered controls, saturation and prevention of ARD is feasibleCover design is critical• in arid climate, low-flux cover better than
barrier
![Page 27: Hydrogeochemical Considerations related to Disposal of …bc-mlard.ca/files/presentations/2008-5-VERBURG-hydro... · 2017-03-28 · Comparison of Characteristics Slurry Thickened](https://reader031.vdocuments.net/reader031/viewer/2022011818/5e8e143ca684107123582f27/html5/thumbnails/27.jpg)
Conceptual Paste Placement
![Page 28: Hydrogeochemical Considerations related to Disposal of …bc-mlard.ca/files/presentations/2008-5-VERBURG-hydro... · 2017-03-28 · Comparison of Characteristics Slurry Thickened](https://reader031.vdocuments.net/reader031/viewer/2022011818/5e8e143ca684107123582f27/html5/thumbnails/28.jpg)
Conceptual Paste Placement (cont’d)
![Page 29: Hydrogeochemical Considerations related to Disposal of …bc-mlard.ca/files/presentations/2008-5-VERBURG-hydro... · 2017-03-28 · Comparison of Characteristics Slurry Thickened](https://reader031.vdocuments.net/reader031/viewer/2022011818/5e8e143ca684107123582f27/html5/thumbnails/29.jpg)
Conceptual Paste Placement (cont’d)
![Page 30: Hydrogeochemical Considerations related to Disposal of …bc-mlard.ca/files/presentations/2008-5-VERBURG-hydro... · 2017-03-28 · Comparison of Characteristics Slurry Thickened](https://reader031.vdocuments.net/reader031/viewer/2022011818/5e8e143ca684107123582f27/html5/thumbnails/30.jpg)
Acknowledgments
Mafalda Oliveira (Lundin Mining)
Ward Wilson (UBC)
Fernando Junqueira (Golder – Burnaby)
Cheryl Ross (Golder – Redmond)
![Page 31: Hydrogeochemical Considerations related to Disposal of …bc-mlard.ca/files/presentations/2008-5-VERBURG-hydro... · 2017-03-28 · Comparison of Characteristics Slurry Thickened](https://reader031.vdocuments.net/reader031/viewer/2022011818/5e8e143ca684107123582f27/html5/thumbnails/31.jpg)