identification of failure modes for dam safety monitoring ... · spillway failures during flood •...

79
Identification of Failure Modes for Dam Safety Monitoring and Evaluation (Part 2) David Rees Gillette, PE, PhD

Upload: others

Post on 11-May-2020

5 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Identification of Failure Modes for Dam Safety Monitoring ... · Spillway Failures During Flood • Heaving of floor slab due to stagnation pressure – "slab jacking" • Failure

Identification of Failure Modes for Dam Safety Monitoring and Evaluation (Part 2)

David Rees Gillette, PE, PhD

Page 2: Identification of Failure Modes for Dam Safety Monitoring ... · Spillway Failures During Flood • Heaving of floor slab due to stagnation pressure – "slab jacking" • Failure

Causes of Embankment Dam Failures

Page 3: Identification of Failure Modes for Dam Safety Monitoring ... · Spillway Failures During Flood • Heaving of floor slab due to stagnation pressure – "slab jacking" • Failure

Flood-Induced PFMs for Embankment Dams

• Overtopping• Internal erosion• Slope instability• Erosion by spillway flow• (Spillway failure)

Page 4: Identification of Failure Modes for Dam Safety Monitoring ... · Spillway Failures During Flood • Heaving of floor slab due to stagnation pressure – "slab jacking" • Failure

● Flow over the top of the core

● Reservoir water acting against untested embankment or abutment areas

● Higher pressures and gradients

High Reservoir – Seepage Concerns

Page 5: Identification of Failure Modes for Dam Safety Monitoring ... · Spillway Failures During Flood • Heaving of floor slab due to stagnation pressure – "slab jacking" • Failure

Flood Overtopping

Page 6: Identification of Failure Modes for Dam Safety Monitoring ... · Spillway Failures During Flood • Heaving of floor slab due to stagnation pressure – "slab jacking" • Failure

Overtopping by Major Flood

Virginia Kendall Dam, Ohio USA, after being overtopped 35 cm deep by thunderstorm flood.

Note concrete core wall, which prevented breach.

Page 7: Identification of Failure Modes for Dam Safety Monitoring ... · Spillway Failures During Flood • Heaving of floor slab due to stagnation pressure – "slab jacking" • Failure

Considering only the design crest elevation – small depth of overtopping flow over the length of the dam – no problem

Looking at the actual crest profile – sufficient flow depth at low area to start erosion and breaching process

Concentrated overtopping flow

Page 8: Identification of Failure Modes for Dam Safety Monitoring ... · Spillway Failures During Flood • Heaving of floor slab due to stagnation pressure – "slab jacking" • Failure

Delhi Dam, Iowa, USA

Page 9: Identification of Failure Modes for Dam Safety Monitoring ... · Spillway Failures During Flood • Heaving of floor slab due to stagnation pressure – "slab jacking" • Failure

Delhi Dam, Iowa, USA• Concrete core wall effective in

controlling seepage until reservoir rose above top of core wall.

• No internal drains.• Spillway capacity reduced because one

of three gates could not open all the way, apparently because of repairs that were not completed – Maintenance does affect dam safety!

Page 10: Identification of Failure Modes for Dam Safety Monitoring ... · Spillway Failures During Flood • Heaving of floor slab due to stagnation pressure – "slab jacking" • Failure

Failure by Flood-induced Internal Erosion Leading to Slope Failure

Normal PoolLevel

Page 11: Identification of Failure Modes for Dam Safety Monitoring ... · Spillway Failures During Flood • Heaving of floor slab due to stagnation pressure – "slab jacking" • Failure

Erosion of Embankment by Flood Discharge

Horseshoe Dam USA

Page 12: Identification of Failure Modes for Dam Safety Monitoring ... · Spillway Failures During Flood • Heaving of floor slab due to stagnation pressure – "slab jacking" • Failure

Flood-Induced PFMs for Concrete Dams• Sliding• Overturning• Overtopping and foundation erosion

Page 13: Identification of Failure Modes for Dam Safety Monitoring ... · Spillway Failures During Flood • Heaving of floor slab due to stagnation pressure – "slab jacking" • Failure

Overtopping flow erodes foundation material

Page 14: Identification of Failure Modes for Dam Safety Monitoring ... · Spillway Failures During Flood • Heaving of floor slab due to stagnation pressure – "slab jacking" • Failure

Gibson Dam

Page 15: Identification of Failure Modes for Dam Safety Monitoring ... · Spillway Failures During Flood • Heaving of floor slab due to stagnation pressure – "slab jacking" • Failure
Page 16: Identification of Failure Modes for Dam Safety Monitoring ... · Spillway Failures During Flood • Heaving of floor slab due to stagnation pressure – "slab jacking" • Failure

Overtopping Erosion Protection for the Abutment

Gibson Dam - Modifications

Splitters to Introduce Air Under Overtopping Flow

Page 17: Identification of Failure Modes for Dam Safety Monitoring ... · Spillway Failures During Flood • Heaving of floor slab due to stagnation pressure – "slab jacking" • Failure

Gravity Dam Sliding or Overturning

AB C D E

Increased Uplift Pressure

on Base

Normal RWS

Flood Level

½ γW H2

Page 18: Identification of Failure Modes for Dam Safety Monitoring ... · Spillway Failures During Flood • Heaving of floor slab due to stagnation pressure – "slab jacking" • Failure

Spillway Failures During Flood

• Heaving of floor slab due to stagnation pressure –"slab jacking"

• Failure due to cavitation damage to concrete• Loss of material from foundation from internal

erosion or undercutting• Overtopping of chute walls due to inadequate

capacity

Page 19: Identification of Failure Modes for Dam Safety Monitoring ... · Spillway Failures During Flood • Heaving of floor slab due to stagnation pressure – "slab jacking" • Failure
Page 20: Identification of Failure Modes for Dam Safety Monitoring ... · Spillway Failures During Flood • Heaving of floor slab due to stagnation pressure – "slab jacking" • Failure

Uplift Pressures Under Chute Floor Slabs from Stagnation

Potentially high uplift pressure

Page 21: Identification of Failure Modes for Dam Safety Monitoring ... · Spillway Failures During Flood • Heaving of floor slab due to stagnation pressure – "slab jacking" • Failure

Big Sandy Dam Spillway Failure due toStagnation Pressure and “Slab Jacking”

Page 22: Identification of Failure Modes for Dam Safety Monitoring ... · Spillway Failures During Flood • Heaving of floor slab due to stagnation pressure – "slab jacking" • Failure

Big Sandy Dam SpillwayThe Results

Page 23: Identification of Failure Modes for Dam Safety Monitoring ... · Spillway Failures During Flood • Heaving of floor slab due to stagnation pressure – "slab jacking" • Failure

Defense: Good Details for Joints in Floor of Chute

Continuous Reinforcement

Water Stop

Under Drain with Filter

Overlapped Slabs

Concrete CutoffAnchor Bar

Page 24: Identification of Failure Modes for Dam Safety Monitoring ... · Spillway Failures During Flood • Heaving of floor slab due to stagnation pressure – "slab jacking" • Failure

CavitationBoiling of water due to localized vacuum from high-velocity flow. Collapsing bubbles cause shock waves that can erode concrete or even steel.

Page 25: Identification of Failure Modes for Dam Safety Monitoring ... · Spillway Failures During Flood • Heaving of floor slab due to stagnation pressure – "slab jacking" • Failure

MethodsWhere cavitation can occur

See references –Cavitation in Chutes and Spillways

Page 26: Identification of Failure Modes for Dam Safety Monitoring ... · Spillway Failures During Flood • Heaving of floor slab due to stagnation pressure – "slab jacking" • Failure

How bad it can getGlen Canyon Dam1983

Two years earlier

Page 27: Identification of Failure Modes for Dam Safety Monitoring ... · Spillway Failures During Flood • Heaving of floor slab due to stagnation pressure – "slab jacking" • Failure

Erosion of Material From Beneath the Spillway

Voids beneath the spillway floor could lead to structural collapse of the spillway floor slabs

Page 28: Identification of Failure Modes for Dam Safety Monitoring ... · Spillway Failures During Flood • Heaving of floor slab due to stagnation pressure – "slab jacking" • Failure
Page 29: Identification of Failure Modes for Dam Safety Monitoring ... · Spillway Failures During Flood • Heaving of floor slab due to stagnation pressure – "slab jacking" • Failure

Erosion of Material From Beneath the Spillway

Voids beneath the spillway floor could lead to structural collapse of the spillway floor slabs

Damaged flow surface could result in flow erosion failure

Page 30: Identification of Failure Modes for Dam Safety Monitoring ... · Spillway Failures During Flood • Heaving of floor slab due to stagnation pressure – "slab jacking" • Failure

FUENTE: HIDROVEN

Chute Overtopping - El Guapo Dam

Page 31: Identification of Failure Modes for Dam Safety Monitoring ... · Spillway Failures During Flood • Heaving of floor slab due to stagnation pressure – "slab jacking" • Failure

FUENTE: HIDROVEN

Page 32: Identification of Failure Modes for Dam Safety Monitoring ... · Spillway Failures During Flood • Heaving of floor slab due to stagnation pressure – "slab jacking" • Failure

FUENTE: HIDROVEN

Page 33: Identification of Failure Modes for Dam Safety Monitoring ... · Spillway Failures During Flood • Heaving of floor slab due to stagnation pressure – "slab jacking" • Failure

FUENTE: HIDROVEN

Page 34: Identification of Failure Modes for Dam Safety Monitoring ... · Spillway Failures During Flood • Heaving of floor slab due to stagnation pressure – "slab jacking" • Failure
Page 35: Identification of Failure Modes for Dam Safety Monitoring ... · Spillway Failures During Flood • Heaving of floor slab due to stagnation pressure – "slab jacking" • Failure

Monitoring – Flood-Related PFMsPre-Flood Baseline• Photographs (embankment, spillway, etc.)• Aerial topographic survey• Measurement point survey

Flood Response• Visual observation (flow conditions, seepage, etc.)• Photographs/video• Monitor for other failure modes also

Post-Flood• Inspection• Measurement point survey• Aerial survey

Page 36: Identification of Failure Modes for Dam Safety Monitoring ... · Spillway Failures During Flood • Heaving of floor slab due to stagnation pressure – "slab jacking" • Failure

Seismic PFMs for Embankment Dams• Liquefaction and instability• Crack erosion• Movement of fault in foundation

Page 37: Identification of Failure Modes for Dam Safety Monitoring ... · Spillway Failures During Flood • Heaving of floor slab due to stagnation pressure – "slab jacking" • Failure

Liquefaction and Instability

Sheffield Dam, 1925 Santa Barbara Earthquake

Page 38: Identification of Failure Modes for Dam Safety Monitoring ... · Spillway Failures During Flood • Heaving of floor slab due to stagnation pressure – "slab jacking" • Failure

Liquefaction of Foundations or Embankments

Page 39: Identification of Failure Modes for Dam Safety Monitoring ... · Spillway Failures During Flood • Heaving of floor slab due to stagnation pressure – "slab jacking" • Failure

Liquefaction of EmbankmentLower San Fernando Dam, California1971 San Fernando Earthquake

Page 40: Identification of Failure Modes for Dam Safety Monitoring ... · Spillway Failures During Flood • Heaving of floor slab due to stagnation pressure – "slab jacking" • Failure

Lower San Fernando Dam

Page 41: Identification of Failure Modes for Dam Safety Monitoring ... · Spillway Failures During Flood • Heaving of floor slab due to stagnation pressure – "slab jacking" • Failure

La Marquesa Dam, 1985 Central Chile EQ, M 8.0, PHA≈ 0.6 g

Crest settlement 2.3 m (23%). Remnant freeboard < 1 m.

De Alba et al. (1988)

Page 42: Identification of Failure Modes for Dam Safety Monitoring ... · Spillway Failures During Flood • Heaving of floor slab due to stagnation pressure – "slab jacking" • Failure

Failure of Fujinuma Dam, 2011 Tohoku Offshore Earthquake, Japan, 0.3-0.4 g

Photos: Geotechnical Extreme Events Reconnaissance Association, 2011

Caused by weak/sensitive silt/clay in foundation?

Page 43: Identification of Failure Modes for Dam Safety Monitoring ... · Spillway Failures During Flood • Heaving of floor slab due to stagnation pressure – "slab jacking" • Failure

Flow appears to be on a level surface with some erosion resistance, consistent with clayey fill in field reports. Picture taken 25 minutes after earthquake.

Construction Shutdown and

Material Change?

From Matsumoto, Sasaki, and Ohmachi (2011)

Page 44: Identification of Failure Modes for Dam Safety Monitoring ... · Spillway Failures During Flood • Heaving of floor slab due to stagnation pressure – "slab jacking" • Failure

Crack Erosion? Rogers Dam, Fallon Nevada Earthquake 1952

After rebuilding embankment. Note very small freeboard above stoplogs.

Page 45: Identification of Failure Modes for Dam Safety Monitoring ... · Spillway Failures During Flood • Heaving of floor slab due to stagnation pressure – "slab jacking" • Failure

Zipingpu Dam, 10 km from Wenchuan Earthquake (7.9)

• 150 m high CFRD• Reservoir low at

time of EQ

www.connect.in.com

Page 46: Identification of Failure Modes for Dam Safety Monitoring ... · Spillway Failures During Flood • Heaving of floor slab due to stagnation pressure – "slab jacking" • Failure

Settlement ~1/2 % of height; cracks 20 mm by "several m" at joints in upper part of face

www.internationalrivers.org

www.connect.in.com

Page 47: Identification of Failure Modes for Dam Safety Monitoring ... · Spillway Failures During Flood • Heaving of floor slab due to stagnation pressure – "slab jacking" • Failure

Looking up u/s slope

Looking across u/s slope

www.bbc.co.uk

waterpowermagazine.com

Page 48: Identification of Failure Modes for Dam Safety Monitoring ... · Spillway Failures During Flood • Heaving of floor slab due to stagnation pressure – "slab jacking" • Failure

But what if Zipingpu Reservoir had been full at the time of the earthquake?

What potential failure modes are there?

What governs their likelihood?

Page 49: Identification of Failure Modes for Dam Safety Monitoring ... · Spillway Failures During Flood • Heaving of floor slab due to stagnation pressure – "slab jacking" • Failure

Movement of Foundation Faults

1906 San Francisco Earthquake: four embankment dams on San Andreas Fault, few details available.

Lower Howell – FailedUpper Howell – Didn’t

Why the difference? MAYBE because Lower Howell had a steel conduit through it at the site of the fault rupture. Most of the evidence was washed away, of course.

Langalda Dam, Iceland – Aseismic opening of "tectonic fractures" in foundation – no breach.

Page 50: Identification of Failure Modes for Dam Safety Monitoring ... · Spillway Failures During Flood • Heaving of floor slab due to stagnation pressure – "slab jacking" • Failure

Failure by Foundation Fault Movement

Baldwin Hills Dam, California

Page 51: Identification of Failure Modes for Dam Safety Monitoring ... · Spillway Failures During Flood • Heaving of floor slab due to stagnation pressure – "slab jacking" • Failure

Underdrain System

Page 52: Identification of Failure Modes for Dam Safety Monitoring ... · Spillway Failures During Flood • Heaving of floor slab due to stagnation pressure – "slab jacking" • Failure

Foundation Faulting due to Oil Well Pumping – No Earthquake

Page 53: Identification of Failure Modes for Dam Safety Monitoring ... · Spillway Failures During Flood • Heaving of floor slab due to stagnation pressure – "slab jacking" • Failure

Attempted Intervention

Page 54: Identification of Failure Modes for Dam Safety Monitoring ... · Spillway Failures During Flood • Heaving of floor slab due to stagnation pressure – "slab jacking" • Failure

Baldwin Hills Dam, CA.Aseismicmovement of fault

Page 55: Identification of Failure Modes for Dam Safety Monitoring ... · Spillway Failures During Flood • Heaving of floor slab due to stagnation pressure – "slab jacking" • Failure

Seismic PFMs for Concrete Dams• Sliding on foundation or lift lines• Overturning• Structural failure of arch dam

Page 56: Identification of Failure Modes for Dam Safety Monitoring ... · Spillway Failures During Flood • Heaving of floor slab due to stagnation pressure – "slab jacking" • Failure

Sliding along disbonded or weak lift lines in earthquake (or flood)Could also occur under normal operations if there is plugging

of drains in the dam

Keyed Lift Line

Page 57: Identification of Failure Modes for Dam Safety Monitoring ... · Spillway Failures During Flood • Heaving of floor slab due to stagnation pressure – "slab jacking" • Failure

Tensile Stresses Induced by Seismic Shaking

Crack

Page 58: Identification of Failure Modes for Dam Safety Monitoring ... · Spillway Failures During Flood • Heaving of floor slab due to stagnation pressure – "slab jacking" • Failure

58

Pacoima Dam, CA (earthquake)• 113m high flood

control arch dam• 1971 M 6.6 San

Fernando and 1994 M 6.8 Northridge EQs

• Opening of joint between dam and ltthrust block, cracking of thrust block, left abut rock movements

• Reservoir was low, or dam might have failed.

Page 59: Identification of Failure Modes for Dam Safety Monitoring ... · Spillway Failures During Flood • Heaving of floor slab due to stagnation pressure – "slab jacking" • Failure

Pacoima Dam

California

Left abutment thrust block

Pacoima Dam

Page 60: Identification of Failure Modes for Dam Safety Monitoring ... · Spillway Failures During Flood • Heaving of floor slab due to stagnation pressure – "slab jacking" • Failure

Pacoima Dam• Opening of joint between dam and lt. thrust

block, cracking of thrust block, lt. abut. rock movements

• Reservoir was low, or dam might have failed

Page 61: Identification of Failure Modes for Dam Safety Monitoring ... · Spillway Failures During Flood • Heaving of floor slab due to stagnation pressure – "slab jacking" • Failure

Sefid-Rud Dam, Iran

Concrete buttress dam subjected to coseismic movement of abutments, 1990 Manjil Earthquake

Page 62: Identification of Failure Modes for Dam Safety Monitoring ... · Spillway Failures During Flood • Heaving of floor slab due to stagnation pressure – "slab jacking" • Failure

Sefid-Rud Dam

1990 Manjil EQ

Page 63: Identification of Failure Modes for Dam Safety Monitoring ... · Spillway Failures During Flood • Heaving of floor slab due to stagnation pressure – "slab jacking" • Failure

Failure of Gateor Walls Under Earthquake Loading

Page 64: Identification of Failure Modes for Dam Safety Monitoring ... · Spillway Failures During Flood • Heaving of floor slab due to stagnation pressure – "slab jacking" • Failure

Monitoring – Seismic PFMsPre-Earthquake Baseline• Seepage conditions (flow rate, piezometers)• Water pressures• Survey measurement points• Inclinometers• Visual

Earthquake Response• Visual inspection• Instrument readings (measurement points,

inclimometers, piezometers, flow rate)

Post-Earthquake Monitoring• Potential hidden damage

Page 65: Identification of Failure Modes for Dam Safety Monitoring ... · Spillway Failures During Flood • Heaving of floor slab due to stagnation pressure – "slab jacking" • Failure

New seepage, or just relief of excess pore water pressure?

Page 66: Identification of Failure Modes for Dam Safety Monitoring ... · Spillway Failures During Flood • Heaving of floor slab due to stagnation pressure – "slab jacking" • Failure

Monitoring During Extreme Loading Conditions (Floods and Earthquakes)Little can be done during event

- the key recognition and action in advance

Learn from lesser magnitude events- focused monitoring effort during the

event

Routine monitoring- baseline of pre-event condition- compare to post-event condition

Page 67: Identification of Failure Modes for Dam Safety Monitoring ... · Spillway Failures During Flood • Heaving of floor slab due to stagnation pressure – "slab jacking" • Failure

“Things Happen...”• Gates do not operate or fail.• Stoplogs cannot be removed.• Power for operating the gates is lost.

– Storm outage or electrical line to gates lost.– Auxiliary power eitherDoes not exist.Does not function as planned.

• Access to site is lost.• Procedures break down.• Operational errors.

Page 68: Identification of Failure Modes for Dam Safety Monitoring ... · Spillway Failures During Flood • Heaving of floor slab due to stagnation pressure – "slab jacking" • Failure

Operational ErrorsTaum Sauk Pumped Storage Facility, Missouri, USA

• 25 m high concrete-face rockfill dam on hilltop

• No spillway, small freeboard

• Water-level gauges were out of correct position, and pumps did not turn off.

• Failure of dam from overtopping leading to erosion and slope instability.

Page 69: Identification of Failure Modes for Dam Safety Monitoring ... · Spillway Failures During Flood • Heaving of floor slab due to stagnation pressure – "slab jacking" • Failure
Page 70: Identification of Failure Modes for Dam Safety Monitoring ... · Spillway Failures During Flood • Heaving of floor slab due to stagnation pressure – "slab jacking" • Failure

“You won’t findwhat you aren’t looking for.”

Random, unfocused activity is neither effective nor efficient.

Focused attention on key performance indicators is the best way to assure that a failure mode has not initiated or is not developing.

Page 71: Identification of Failure Modes for Dam Safety Monitoring ... · Spillway Failures During Flood • Heaving of floor slab due to stagnation pressure – "slab jacking" • Failure

Potential Failure Mode Descriptions

Initiating Condition Flood or earthquake Unusually high reservoir level Deterioration/aging of structure Operator error or malfunction

Failure Mechanism Piping of core material through the foundation Erosion of the downstream slope and crest Sliding of a block of abutment rock

How Dam Failure Actually Occurs Seepage erosion eventually leads to breach Overtopping leads to breach Abutment slide leads to cracking and failure of

concrete structure

Page 72: Identification of Failure Modes for Dam Safety Monitoring ... · Spillway Failures During Flood • Heaving of floor slab due to stagnation pressure – "slab jacking" • Failure

Potential Failure Modes Analysis

1. Assemble a team with the necessary expertise and knowledge:

EngineersGeologistsSeismologistsFlood HydrologistsDam OperatorsPFMAFacilitator

2. Study the dam, geology, and loadings, and develop "brainstorm" list of potential failure modes (PFMs).

Page 73: Identification of Failure Modes for Dam Safety Monitoring ... · Spillway Failures During Flood • Heaving of floor slab due to stagnation pressure – "slab jacking" • Failure

Component Events

• What loading makes failure start?

• How and where does it start?

• And then what happens?

• And then what?

Page 74: Identification of Failure Modes for Dam Safety Monitoring ... · Spillway Failures During Flood • Heaving of floor slab due to stagnation pressure – "slab jacking" • Failure

3. Decompose each PFM into its component conditions and events.

[0.3 to 0.4 g∩ High Res.]

WidespreadLiq’n?

SlopeInstability?

Crest Mvmt > Freeboard?

Cracks ->ErosionFailure?

NoFailure

NoFailure

OT Failure?

Failure

NoFailure

NoFailure

Failure

YY

Y

Y

Y

N

N

NN

N

Example event tree for seismic failure

Page 75: Identification of Failure Modes for Dam Safety Monitoring ... · Spillway Failures During Flood • Heaving of floor slab due to stagnation pressure – "slab jacking" • Failure

Performance Monitoring Program

1. Routine visual monitoring2. Routine instrumented monitoring3. Periodic exam and review by specialists4. Earthquake response5. Flood response

Page 76: Identification of Failure Modes for Dam Safety Monitoring ... · Spillway Failures During Flood • Heaving of floor slab due to stagnation pressure – "slab jacking" • Failure

Visual InspectionsExpected Performance

• Not easy to define

• Knowledge and experience are vital

• Understanding the potential failure modes, and how observations relate to them, helps greatly

Page 77: Identification of Failure Modes for Dam Safety Monitoring ... · Spillway Failures During Flood • Heaving of floor slab due to stagnation pressure – "slab jacking" • Failure

Failure Mode Identification andPerformance Parameters

Dam safety concerns definedUnified, focused monitoring programReasons for monitoring are clearExpected performance definedCosts low - benefits high

Page 78: Identification of Failure Modes for Dam Safety Monitoring ... · Spillway Failures During Flood • Heaving of floor slab due to stagnation pressure – "slab jacking" • Failure

Schedule for Periodic

Monitoring(L-23)

Page 79: Identification of Failure Modes for Dam Safety Monitoring ... · Spillway Failures During Flood • Heaving of floor slab due to stagnation pressure – "slab jacking" • Failure

Discussion?

Shi Kang Dam,

Taiwan

The one that did not fail!