impacts and actions resulting from the august 14, 2003 ... 14 2003 blackout investigati… ·...

59
Impacts and Actions Resulting from the August 14, 2003 Blackout David W. Hilt P.E. July 29, 2006 Illinois Society of Professional Engineers

Upload: others

Post on 03-Aug-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Impacts and Actions Resulting from the August 14, 2003 ... 14 2003 Blackout Investigati… · August 14, 2003 Generatino Net Output MWe 32 36 40 44 48 52 56 60 64 System Frequenc

Impacts and ActionsResulting from the August 14, 2003 Blackout

David W. Hilt P.E.July 29, 2006

Illinois Society of Professional Engineers

Page 2: Impacts and Actions Resulting from the August 14, 2003 ... 14 2003 Blackout Investigati… · August 14, 2003 Generatino Net Output MWe 32 36 40 44 48 52 56 60 64 System Frequenc

1:31:34 p.m.1:31:34 p.m.

August 14, 2003What Happened?

765kVDC

Voltage

MontrealOttawa

Toronto

DetroitCleveland

AkronCanton

Buffalo

New YorkPittsburg

Toledo

2:02 p.m.3:05:41 to 3:41:33 p.m.3:45:33 to 4:08:58 p.m.4:08:58 to 4:10:27 p.m.4:10:00 to 4:10:38 p.m.4:10:40 to 4:10:44 p.m.4:10:44 to 4:13:00 p.m.

Page 3: Impacts and Actions Resulting from the August 14, 2003 ... 14 2003 Blackout Investigati… · August 14, 2003 Generatino Net Output MWe 32 36 40 44 48 52 56 60 64 System Frequenc

Summary of August 14 Blackout● Impacts

8 states/2 provincesOver 50 million people 60-65,000 MW30 hours to restoreManufacturing disrupted531 generators tripped− 19 nuclear generators

at 10 plants

● StatisticsLine trips began at 3:05 PMCascading began at 4:06 PM− Lasted approximately 12 seconds

Thousands of discrete events

Page 4: Impacts and Actions Resulting from the August 14, 2003 ... 14 2003 Blackout Investigati… · August 14, 2003 Generatino Net Output MWe 32 36 40 44 48 52 56 60 64 System Frequenc

Every Blackout has Impacts● November 9, 1965 – NY Blackout

30,000,000 people and over 20,000 MW of demand –up to 13 hours

● July 13, 1977 - New York City9,000,000 people and 6,000 MW of demand – up to 26 hours

● July 2, 1996 – Western US2,000,000 customers (10 % of the Western Interconnection) and 11,850 MW of demand for up to several hours

● August 10, 1996 – Western US7,500,000 customers; 28,000 MW of demand for up to 9 hours

Page 5: Impacts and Actions Resulting from the August 14, 2003 ... 14 2003 Blackout Investigati… · August 14, 2003 Generatino Net Output MWe 32 36 40 44 48 52 56 60 64 System Frequenc

August 14, 2003

Warm But Not Unusual for August

Page 6: Impacts and Actions Resulting from the August 14, 2003 ... 14 2003 Blackout Investigati… · August 14, 2003 Generatino Net Output MWe 32 36 40 44 48 52 56 60 64 System Frequenc

Situational Awareness● 2:14 PM – First Energy Alarm logger fails and

operators are not aware of any line outagesS. Canton - Star 345 kV line trip and reclose at 2:27 PM

● FirstEnergy IT staff reboots system when paged –did not communicate with operators

● No contingency analysis by FirstEnergy of events during the day

● Midwest ISO – Failure of part of monitoring system due to data error

Page 7: Impacts and Actions Resulting from the August 14, 2003 ... 14 2003 Blackout Investigati… · August 14, 2003 Generatino Net Output MWe 32 36 40 44 48 52 56 60 64 System Frequenc

What happened on August 14At 1:31 pm, FirstEnergy

lost the Eastlake 5 power plant, an important source of reactive power for the Cleveland-Akron area

Starting at 3:05 pm EDT, three 345 kV lines in FE’s system failed –within normal operating load limits -- due to contacts with overgrown trees

Page 8: Impacts and Actions Resulting from the August 14, 2003 ... 14 2003 Blackout Investigati… · August 14, 2003 Generatino Net Output MWe 32 36 40 44 48 52 56 60 64 System Frequenc

East Lake 5 Exciter Failure Causes Trip

Page 9: Impacts and Actions Resulting from the August 14, 2003 ... 14 2003 Blackout Investigati… · August 14, 2003 Generatino Net Output MWe 32 36 40 44 48 52 56 60 64 System Frequenc

Hanna - Juniper Tree Contactpoor ground clearance = premature failures

Page 10: Impacts and Actions Resulting from the August 14, 2003 ... 14 2003 Blackout Investigati… · August 14, 2003 Generatino Net Output MWe 32 36 40 44 48 52 56 60 64 System Frequenc

15:05:41 EDT

15:32:03 EDT

15:41:35 EDT

15:51:41 EDT

16:05:55 EDT

0

20

40

60

80

100

120

140

% o

f Nor

mal

Rat

ings

Canton C

entral Transformer

Babb-W

.Akron 138 kV H

arding-C

hamberlin

Hanna-

Juniper

Star-S.Canton

Cloverdale-Torrey 138 kV

E.Lima-N

ew Liberty 138 kV

W.A

kron-Pleasant Valley 138 kV

E.Lima-N

.Finlay 138 kV

Cham

berlin-W.A

kron 138 kV

W.A

kron 138 kV Breaker

Dale-W

.Canton 138 kV

Sammis-Star

What Happened - Ohio

138 kV Cascade Contributes to the ultimate overload of the Sammis-Star 345 kV line.

This line begins the spread of the cascade beyond Ohio

Page 11: Impacts and Actions Resulting from the August 14, 2003 ... 14 2003 Blackout Investigati… · August 14, 2003 Generatino Net Output MWe 32 36 40 44 48 52 56 60 64 System Frequenc

What Happened -- Ohio

After the 345 kV lines were lost, at 3:39 pm FE’s 138 kV lines around Akron began to overload and fail; 16 overloaded and tripped out of service

0

20

40

60

80

100

120

140

160

180

200

% o

f Nor

mal

Rat

ings

Dale-W

.Canton

W.A

kron Breaker

E.Lima-N

.Finlay

Canton

CentralTransform

er

WA

kron-PleasantValley

Babb-W

Akron

ELim

a-New

Liberty

Cloverdale-Torrey

Star-S.Canton

345 kVH

anna-Juniper345

kVH

arding-Cham

berlin345 kV C

hamberlin-W

.Akron

15:05:41ED

T

15:32:03ED

T

15:41:35ED

T

15:51:41ED

T

16:05:55ED

T

Page 12: Impacts and Actions Resulting from the August 14, 2003 ... 14 2003 Blackout Investigati… · August 14, 2003 Generatino Net Output MWe 32 36 40 44 48 52 56 60 64 System Frequenc

CommunicationsPhone Calls to Control Area (FE)

● CA receives calls from MISO, AEP, and PJM but did not recognize evolving emergency

2:32 AEP calls regarding trip & reclose of Star-S. Canton

3:19 AEP calls confirming Star-S. Canton trip & reclose

3:36 MISO calls regarding contingency overload on Star-Juniper for loss of Hanna-Juniper

3:45 tree trimming crew calls in regarding Hanna-Juniper flashover to a tree

PJM calls MISO at 3:48 and FE at 3:56 regarding overloads on FE system

Page 13: Impacts and Actions Resulting from the August 14, 2003 ... 14 2003 Blackout Investigati… · August 14, 2003 Generatino Net Output MWe 32 36 40 44 48 52 56 60 64 System Frequenc

What Happened -- OhioAt 4:05 pm,

FirstEnergy’s Sammis-Star 345 kV line failed due to overload.

40 20 0 20 40 60

20

40

60

80

100

Sammis-Star 345kV @ Sammis 1606:03110

10−

Im ZBCx( )Im Z1l( )

7040− Re ZBCx( ) Re Z1l( ),

Page 14: Impacts and Actions Resulting from the August 14, 2003 ... 14 2003 Blackout Investigati… · August 14, 2003 Generatino Net Output MWe 32 36 40 44 48 52 56 60 64 System Frequenc

Actual Loading on Critical Lines

0

400

800

1200

1600

12:00 13:00 14:00 15:00 16:00

Time - EDT

Flow

s (M

W)

Harding - ChamberlinHanna - JuniperStar - South CantonSammis - Star

East Lake 5 Trip

Harding - Chamberlin Line Trip

Hanna - Juniper Line Trip

Sammis - Star Line Trip

Star - South Canton Line Trip

Page 15: Impacts and Actions Resulting from the August 14, 2003 ... 14 2003 Blackout Investigati… · August 14, 2003 Generatino Net Output MWe 32 36 40 44 48 52 56 60 64 System Frequenc

Actual Voltages Leading to Sammis-Star

250

270

290

310

330

350

370

15:00 16:00Time - EDT

Vol

tage

(kV)

Star

Hanna

Beaver

Perry

100% Voltage

95% Voltage

90% Voltage

Sammis - Star 345 kVLine Trip

Star - South Canton345 kV Line Trip

Hanna - Juniper345 kV line Trip

Harding - Chamberlain345 kV Line Trip

Page 16: Impacts and Actions Resulting from the August 14, 2003 ... 14 2003 Blackout Investigati… · August 14, 2003 Generatino Net Output MWe 32 36 40 44 48 52 56 60 64 System Frequenc

What Happened -- Cascade

1) 4:06 2) 4:08:57

3) 4:10:37 4) 4:10:38.6

Page 17: Impacts and Actions Resulting from the August 14, 2003 ... 14 2003 Blackout Investigati… · August 14, 2003 Generatino Net Output MWe 32 36 40 44 48 52 56 60 64 System Frequenc

NY to Ontario 345kV Line Flows at NiagaraProgressively Worsening Stability Conditions

New York to Ontario 345 kV Line Flow at Niagara(does not include 230 kV line flow)

0.00

200.00

400.00

600.00

800.00

1000.00

1200.00

1400.00

1600.00

1800.00

2000.00

16:0

5:43

16:0

5:49

16:0

5:54

16:0

6:00

16:0

6:05

16:0

6:11

16:0

6:16

16:0

6:22

16:0

6:27

16:0

6:33

16:0

6:38

16:0

6:44

16:0

6:49

16:0

6:55

16:0

8:55

16:0

9:00

16:0

9:06

16:0

9:11

16:0

9:17

16:0

9:23

16:0

9:28

16:0

9:33

16:0

9:39

16:0

9:45

16:0

9:50

16:0

9:56

16:1

0:01

16:1

0:20

16:1

0:26

16:1

0:31

16:1

0:37

16:1

0:42

16:1

0:48

MW

200.0

220.0

240.0

260.0

280.0

300.0

320.0

340.0

360.0

380.0

KV

Niagara KV

PA301&2 MW

Sammis-Star 345 trip

East Lima - Fostoria Central 345 trip

Thetford-Jewel, Hampton Pontiac,& Perry - Ashtabula 345kV lines trip

Argenta - Battle Creekdouble circuit 345 trip

ONTARIO

Transmission Lines

765 kV500 kV345 kV230 kV

Transmission Lines

765 kV500 kV345 kV230 kV

Page 18: Impacts and Actions Resulting from the August 14, 2003 ... 14 2003 Blackout Investigati… · August 14, 2003 Generatino Net Output MWe 32 36 40 44 48 52 56 60 64 System Frequenc

What Happened -- Cascade

5) 4:10:39 6) 4:10:44

7) 4:10:45 8) 4:13

Page 19: Impacts and Actions Resulting from the August 14, 2003 ... 14 2003 Blackout Investigati… · August 14, 2003 Generatino Net Output MWe 32 36 40 44 48 52 56 60 64 System Frequenc

Detroit Units Slip Poles Keith-Waterman (J5D) 230 kV - Tie Line

-800

-600

-400

-200

0

200

400

600

800

37 38 39 40 41 42 43 44

Seconds from 16:10

VPQ

ClassicalStability

Severe Voltage Depressionin Downtown and Southern

Detroit Region

Toledo/Cleveland IslandSeparates from Detoit Detroit Area Generation Pulls

Out of Synch and Slips 2 Polesas Frequency Increases to ~62 hz

Significant Generation Loss and/orTransmission Seperation in Detroit Remaining Detroit Generation

Slips 2 Poles as Frequency Fallsat

Keith-Waterman Tripsat 16:10:43.2

#1 #2 #3

#4

Page 20: Impacts and Actions Resulting from the August 14, 2003 ... 14 2003 Blackout Investigati… · August 14, 2003 Generatino Net Output MWe 32 36 40 44 48 52 56 60 64 System Frequenc

Severe Under Frequency Condition

Page 21: Impacts and Actions Resulting from the August 14, 2003 ... 14 2003 Blackout Investigati… · August 14, 2003 Generatino Net Output MWe 32 36 40 44 48 52 56 60 64 System Frequenc

View Into Detroit from Lambton

Page 22: Impacts and Actions Resulting from the August 14, 2003 ... 14 2003 Blackout Investigati… · August 14, 2003 Generatino Net Output MWe 32 36 40 44 48 52 56 60 64 System Frequenc

Frequency in Ontario and New York

Page 23: Impacts and Actions Resulting from the August 14, 2003 ... 14 2003 Blackout Investigati… · August 14, 2003 Generatino Net Output MWe 32 36 40 44 48 52 56 60 64 System Frequenc

GenerationThe blackout shut down 263

power plants (531 units) in the US and Canada, most from the cascade after 4:10:44 pm – but none suffered significant damage

Generation outages did not initiate this cascading blackout

On-line units in the Cleveland area were running at maximum MVAR

Page 24: Impacts and Actions Resulting from the August 14, 2003 ... 14 2003 Blackout Investigati… · August 14, 2003 Generatino Net Output MWe 32 36 40 44 48 52 56 60 64 System Frequenc

Nine Mile Point Unit 2 Trips Nine Mile Point Unit 2 Generation Data

(Reconstructed)

-200

0

200

400

600

800

1000

1200

1400

30 40 50 60 70 80 90 100 110 120Seconds from 16:10

August 14, 2003

Gen

erat

ino

Net

Out

put M

We

32

36

40

44

48

52

56

60

64

Syst

em F

requ

ency

Unit 2 AcceleratesDuring Frequency

Increase

60.3 Hz63.0 Hz 63.1 Hz

GovernorRunback

GovernorRunback

Unit 2Accelerates

Reactor Trip on Low TurbineControl Hydraulic Pressure

Excitation SystemTripped

Breakers Open

DisturbanceBegins

Page 25: Impacts and Actions Resulting from the August 14, 2003 ... 14 2003 Blackout Investigati… · August 14, 2003 Generatino Net Output MWe 32 36 40 44 48 52 56 60 64 System Frequenc

Power System High Level Sequence● Premature failure of three 345kV lines

first trip and reclose at 2:27 PM due to ground faultstarting at 3:05 PM, three permanent outages within 40 minutes due to ground faultsampere loading less than Emergency long time ratingfailure of ground clearance management (trees)

● Northeast Ohio 138kV cascade began3:39 PM

● Northern Ohio 345kV high speed cascade of three overloaded lines 4:05:57 - 4:09:07 PM

● Eastern Interconnection Separates by 4:11PM● Blackout Complete by 4:13 PM

Page 26: Impacts and Actions Resulting from the August 14, 2003 ... 14 2003 Blackout Investigati… · August 14, 2003 Generatino Net Output MWe 32 36 40 44 48 52 56 60 64 System Frequenc

When the Cascade Was Over50+ million people8 states and 2 provinces60-65,000 MW of loadinitially interrupted− Approximately 11% of

Eastern Interconnection

Sammis – Star trip at 4:06 PM – Blackout essentially complete by 4:13 PMHigh speed cascading lasted approximately 12 secondsThousands of discrete events to evaluate− Time stamping - critical

Page 27: Impacts and Actions Resulting from the August 14, 2003 ... 14 2003 Blackout Investigati… · August 14, 2003 Generatino Net Output MWe 32 36 40 44 48 52 56 60 64 System Frequenc

Investigation Organization OverviewSteering Group

MAAC/ECAR/NPCC Coordinating Group

MAAC

ECAR

NPCC

MEN Study Group

Project Planning and Support

Sequence of Events

Data Requests and Management

Investigation Team Lead – D. Hilt

System Modeling and Simulation Analysis

NERC & Regional Standards/Procedures

& Compliance

Transmission System Performance,

Protection, ControlMaintenance & Damage

Operations - Tools, SCADA/EMS

Communications Op Planning

System Planning, Design, & Studies

Root Cause AnalysisCooper Systems

Generator Performance, Protection, Controls

Maintenance & Damage

U.S – CanadaTask Force

Vegetation/ROW Management

Frequency/ACE

Restoration

Investigation Process Review

Page 28: Impacts and Actions Resulting from the August 14, 2003 ... 14 2003 Blackout Investigati… · August 14, 2003 Generatino Net Output MWe 32 36 40 44 48 52 56 60 64 System Frequenc

Causes of the August 14 Blackout● Inadequate

situational awareness

● Ineffective vegetation management

0

400

800

1200

1600

12:00 13:00 14:00 15:00 16:00

Time - EDT

Flow

s (M

W)

Harding - ChamberlinHanna - JuniperStar - South CantonSammis - Star

East Lake 5 Trip

Harding - Chamberlin Line Trip

Hanna - Juniper Line Trip

Sammis - Star Line Trip

Star - South Canton Line Trip

● Inadequate diagnostic support at MISO

● Failure to follow NERC Operating & Planning Standards

Page 29: Impacts and Actions Resulting from the August 14, 2003 ... 14 2003 Blackout Investigati… · August 14, 2003 Generatino Net Output MWe 32 36 40 44 48 52 56 60 64 System Frequenc

Key Findings● Inadequate system planning

and design studies, operations planning, facilities ratings, and modeling data accuracy

● Operating with insufficient reactive margins

● More effective system protection and controls could slow or minimize spread of cascading outage

● Problems from prior blackouts were repeated

Page 30: Impacts and Actions Resulting from the August 14, 2003 ... 14 2003 Blackout Investigati… · August 14, 2003 Generatino Net Output MWe 32 36 40 44 48 52 56 60 64 System Frequenc

The Old● The three “T’s”

Tools – for the operator to monitor and manage the system

Trees – vegetation management to prevent tree contacts

Training – operators need to provided training and drills to be prepared to respond to system emergencies

Page 31: Impacts and Actions Resulting from the August 14, 2003 ... 14 2003 Blackout Investigati… · August 14, 2003 Generatino Net Output MWe 32 36 40 44 48 52 56 60 64 System Frequenc

The New● Failure of tools

Information Technology support – communications“Game Over”

● Generation protectionConsideration of performance during dynamic and extreme low voltage eventsCoordination of plant controls with the transmission system

Page 32: Impacts and Actions Resulting from the August 14, 2003 ... 14 2003 Blackout Investigati… · August 14, 2003 Generatino Net Output MWe 32 36 40 44 48 52 56 60 64 System Frequenc

NERC Actions

● Initial Near-Term Actions● Actions Resulting from Investigation

Corrective ActionsStrategic InitiativesTechnical Initiatives

Goals:1. Correct root cause deficiencies 2. Address contributing factors3. Identify objective and

measurable actions

Page 33: Impacts and Actions Resulting from the August 14, 2003 ... 14 2003 Blackout Investigati… · August 14, 2003 Generatino Net Output MWe 32 36 40 44 48 52 56 60 64 System Frequenc

Corrective Actions: FE● Voltage criteria and

reactive resources● Operational

preparedness and action plan

● Emergency response capabilities and preparedness

● Control center and operator training

Juniper 345kV

-1000

-900

-800

-700

-600

-500

-400

-300

-200

-100

0

100

200

300

400

500

0.7 0.8 0.9 1 1.1

Voltage PU

Reac

tive

Pow

er (M

VAR)

15-05 Chamberlin-Harding

15-32 Hanna-Juniper

15-41 Star-S Canton

15-45-40 Canton Central-Tidd

15-59 West Akron 138kV Lines

Page 34: Impacts and Actions Resulting from the August 14, 2003 ... 14 2003 Blackout Investigati… · August 14, 2003 Generatino Net Output MWe 32 36 40 44 48 52 56 60 64 System Frequenc

Corrective Actions: Reliability Coordinators

● PJMCommunications protocols and procedures

● MISOReliability toolsVisualization toolsOperator trainingCommunicationsOperating agreements

Page 35: Impacts and Actions Resulting from the August 14, 2003 ... 14 2003 Blackout Investigati… · August 14, 2003 Generatino Net Output MWe 32 36 40 44 48 52 56 60 64 System Frequenc

NERC Strategic Initiatives

● Strengthen compliance● Readiness audits● Vegetation-related

outage reporting● Track implementation

of recommendations

Page 36: Impacts and Actions Resulting from the August 14, 2003 ... 14 2003 Blackout Investigati… · August 14, 2003 Generatino Net Output MWe 32 36 40 44 48 52 56 60 64 System Frequenc

Strengthen Compliance with NERC Standards

● Strengthen standards & measures

● Confidential reports to the NERC Board

Specific violationsResults of audits

● Release of confirmed violations

Identification of violators

● Legislation needed to make rules mandatory

Page 37: Impacts and Actions Resulting from the August 14, 2003 ... 14 2003 Blackout Investigati… · August 14, 2003 Generatino Net Output MWe 32 36 40 44 48 52 56 60 64 System Frequenc

Readiness Audits● Audit all control areas

and reliability coordinators

Based on preparedness to comply with NERC requirementsSeek to achieve excellence

● Complete within 3 years and repeat on a 3-year cycle

● Reports to the Board

Not a Compliance Audit

Page 38: Impacts and Actions Resulting from the August 14, 2003 ... 14 2003 Blackout Investigati… · August 14, 2003 Generatino Net Output MWe 32 36 40 44 48 52 56 60 64 System Frequenc

Vegetation-Related Outage Reports

● Report tree contacts to the Regions (230+ kV)

● Regions report to NERC● Regions to conduct and

report on annual vegetation management surveys

Page 39: Impacts and Actions Resulting from the August 14, 2003 ... 14 2003 Blackout Investigati… · August 14, 2003 Generatino Net Output MWe 32 36 40 44 48 52 56 60 64 System Frequenc

Recommendations Tracking

● NERC and Regions will track:Implementation of recommendationsCompliance auditsReadiness audit recommendationsLessons learned from system disturbances

● U.S. – Canada Power System Task Force – June 2006

Recommendations implemented

Page 40: Impacts and Actions Resulting from the August 14, 2003 ... 14 2003 Blackout Investigati… · August 14, 2003 Generatino Net Output MWe 32 36 40 44 48 52 56 60 64 System Frequenc

Technical Initiatives

● Forward looking to preventfuture blackouts

New standards, procedures, protocolsExisting technologies to be consideredNew technologies Changes in system planning, design, and assessmentChanges to operator training programs 40 20 0 20 40 60

20

40

60

80

100

Sammis-Star 345kV @ Sammis 1606:03110

10−

Im ZBCx( )Im Z1l( )

7040− Re ZBCx( ) Re Z1l( ),

Page 41: Impacts and Actions Resulting from the August 14, 2003 ... 14 2003 Blackout Investigati… · August 14, 2003 Generatino Net Output MWe 32 36 40 44 48 52 56 60 64 System Frequenc
Page 42: Impacts and Actions Resulting from the August 14, 2003 ... 14 2003 Blackout Investigati… · August 14, 2003 Generatino Net Output MWe 32 36 40 44 48 52 56 60 64 System Frequenc

Next Steps

● Continue to implement strategic initiatives and recommendations

● Readiness audits● Mandatory standards

and compliance enforcement

Page 43: Impacts and Actions Resulting from the August 14, 2003 ... 14 2003 Blackout Investigati… · August 14, 2003 Generatino Net Output MWe 32 36 40 44 48 52 56 60 64 System Frequenc

Energy Policy Act of 2005 andThe Electric Reliability Organization

NERC’s Proposal for a Strong and Effective ERO

Page 44: Impacts and Actions Resulting from the August 14, 2003 ... 14 2003 Blackout Investigati… · August 14, 2003 Generatino Net Output MWe 32 36 40 44 48 52 56 60 64 System Frequenc

CanadaAlberta, British Columbia, Manitoba, Ontario, New Brunswick, Nova Scotia,

Quebec, and Saskatchewan

Electric Reliability Organization

United StatesFederal Energy

Regulatory Commission

MexicoComision Reguladora

de Energia

Electric ReliabilityOrganization

RegionalEntities

Other ERO Members

Other ERO Members Bulk Electric System

Owners, Operators, UsersBulk Electric System

Owners, Operators, Users

ReliabilityStandards

ComplianceEnforcement

Reliability Assessment

Page 45: Impacts and Actions Resulting from the August 14, 2003 ... 14 2003 Blackout Investigati… · August 14, 2003 Generatino Net Output MWe 32 36 40 44 48 52 56 60 64 System Frequenc

Proposed Implementation Schedule● July 2006

FERC approves NERC (conditionally)

● October 2006Compliance filing addressing conditions

● First quarter 2007Standards approved for implementationEntities notified of penalty – no monies collected

● Six months laterPenalties applied

Page 46: Impacts and Actions Resulting from the August 14, 2003 ... 14 2003 Blackout Investigati… · August 14, 2003 Generatino Net Output MWe 32 36 40 44 48 52 56 60 64 System Frequenc

What’s Really, Really Important● Strong and competent ERO● Clear, consistent, enforceable, and

technically excellent reliability standards● Consistent, firm compliance enforcement● Effective relationships with regulators,

regions and stakeholders● Continuous reliability improvement● Performance monitoring

Page 47: Impacts and Actions Resulting from the August 14, 2003 ... 14 2003 Blackout Investigati… · August 14, 2003 Generatino Net Output MWe 32 36 40 44 48 52 56 60 64 System Frequenc

ERO Membership● Open and voluntary● No membership fee● ERO membership distinct from standards

ballot body● Members elect committee

2 per industry sector for 2-year staggered termsAdditional Canadian representation as needed (0 – 4)Region members elect regional representativeCommittee elects chairman and vice chairmanNon-voting observers appointed by board

Page 48: Impacts and Actions Resulting from the August 14, 2003 ... 14 2003 Blackout Investigati… · August 14, 2003 Generatino Net Output MWe 32 36 40 44 48 52 56 60 64 System Frequenc

Governance● Maintain independent board

11 trustees (2 Canadian)● Retain nominating committee of board

Chaired by trusteeStakeholder representatives

● Board approves changes to certificate, bylaws, rules of procedure, regulatory filings

● Members rightsElect board membersVote on changes to bylawsAdvise boardCall meeting of members

Page 49: Impacts and Actions Resulting from the August 14, 2003 ... 14 2003 Blackout Investigati… · August 14, 2003 Generatino Net Output MWe 32 36 40 44 48 52 56 60 64 System Frequenc

Funding● Funding for ERO and regional delegated

functions allocated to load-serving entitiesBulk power system usersBased on NEL

● Rationalize across balancing authorities, regions and countries

● ERO will fund regions for delegated functions

● Use practical collection mechanisms

Page 50: Impacts and Actions Resulting from the August 14, 2003 ... 14 2003 Blackout Investigati… · August 14, 2003 Generatino Net Output MWe 32 36 40 44 48 52 56 60 64 System Frequenc

Reliability Standards● Retain ANSI-accredited process and RBB● Retain SAC elected by segments● Revise standards manual

Pro rata segment votes and editorial changes● Filed existing 104 standards

Key issue: enforceabilityStandards roadmap

● Coordinate annual work plan with regulators

● Remands/directives through regular process

Page 51: Impacts and Actions Resulting from the August 14, 2003 ... 14 2003 Blackout Investigati… · August 14, 2003 Generatino Net Output MWe 32 36 40 44 48 52 56 60 64 System Frequenc

Regional Standards

● All reliability standards are ERO-approved standards

Regional criteria are not standards

● Regions may use ERO-approved procedure

Open, fair, inclusive, balanced and transparent

Page 52: Impacts and Actions Resulting from the August 14, 2003 ... 14 2003 Blackout Investigati… · August 14, 2003 Generatino Net Output MWe 32 36 40 44 48 52 56 60 64 System Frequenc

Compliance Enforcement

● Strong ERO oversight of regional compliance programs

● Retain existing compliance disclosure principle

● Compliance authority applies to bulk power system owners, operators, and users

Page 53: Impacts and Actions Resulting from the August 14, 2003 ... 14 2003 Blackout Investigati… · August 14, 2003 Generatino Net Output MWe 32 36 40 44 48 52 56 60 64 System Frequenc

Regional Compliance Program Essential Features ● Compliance program independence

Including independence of staff making compliance determinations

● Monitor designated standards for all entities

● Timely reporting of information and all violations

● No sub-delegation● Adequate compliance resources● ERO oversight with audits every 3 years● Single appeals procedure

Page 54: Impacts and Actions Resulting from the August 14, 2003 ... 14 2003 Blackout Investigati… · August 14, 2003 Generatino Net Output MWe 32 36 40 44 48 52 56 60 64 System Frequenc

Penalties and Sanctions● Matrix of base penalties

Risk factors: high, medium, lowLevels of non-compliance: low, moderate, high, severe

● Quantitative adjustment factors

Entity sizeRepeat infractions and prior warningsTime horizon

● Other qualitative factors for consideration, e.g.:

Self-reporting and self-correctionQuality of entity compliance program and overall performanceDeliberate violations

FERC statutory limit:$1,000,000 per day

Lower Moderate High Severe(Level 1) (Level 2) (Level 3) (Level 4)

$1,000 $3,000 $6,000 $10,000

Lower $1,000 $1,000 $1,500 $2,000 Upper $2,000 $6,000 $12,000 $20,000

$5,000 $15,000 $25,000 $40,000

Lower $2,000 $3,000 $5,000 $8,000 Upper $10,000 $30,000 $50,000 $80,000

$35,000 $50,000 $70,000 $100,000

Lower $7,000 $10,000 $14,000 $20,000 Upper $70,000 $100,000 $140,000 $200,000

Violation Severity LevelViolator Size&

Time HorizonLimits

Standard Penalty

Standard Penalty

ViolationRisk

Factor

High

Lower

Medium

Standard Penalty

Page 55: Impacts and Actions Resulting from the August 14, 2003 ... 14 2003 Blackout Investigati… · August 14, 2003 Generatino Net Output MWe 32 36 40 44 48 52 56 60 64 System Frequenc

Organization Registration & Certification

● Maintain list of responsible entities

All bulk electric system owners, operators and usersRegistration by functional model

● Certify balancing authorities, transmission operators and reliability coordinators

● ERO program with responsibilities delegated to regions

Page 56: Impacts and Actions Resulting from the August 14, 2003 ... 14 2003 Blackout Investigati… · August 14, 2003 Generatino Net Output MWe 32 36 40 44 48 52 56 60 64 System Frequenc

Additional ERO Programs● Reliability assessments and performance

Traditional reliability assessments Event analysis and benchmarking

● Reliability readiness audit and improvement

● Training and educationSystem personnel certificationContinuing education provider certification

● Situation awareness and infrastructure security

Page 57: Impacts and Actions Resulting from the August 14, 2003 ... 14 2003 Blackout Investigati… · August 14, 2003 Generatino Net Output MWe 32 36 40 44 48 52 56 60 64 System Frequenc

Business Planning and Budgets ● ERO annual budget process

Includes ERO functionsBudget filed in August and approved by regulators in October

● ERO reviews regional budgets for delegated functions

Regions may have other non-ERO functions not funded through ERO

● Flexibility on funding collection methods● Apply penalty funds first to marginal costs

by NERC and region for compliance enforcement for particular entity

Page 58: Impacts and Actions Resulting from the August 14, 2003 ... 14 2003 Blackout Investigati… · August 14, 2003 Generatino Net Output MWe 32 36 40 44 48 52 56 60 64 System Frequenc

Key Features of Transition Plan● Naming of ERO and compliance order● Form new corporation; transfer from members● Recognition in Canada● Execution of delegation agreements● Update standards manual● Update standards and roadmap● Plan for fill-in-the-blank regional standards● 2007 budget and funding allocation● Compliance enforcement program 2007

6-month trial period for financial penalties● ERO reorganization and staffing adjustments● Role of committees

Page 59: Impacts and Actions Resulting from the August 14, 2003 ... 14 2003 Blackout Investigati… · August 14, 2003 Generatino Net Output MWe 32 36 40 44 48 52 56 60 64 System Frequenc

Questions