improved field management - neftemer · petronas results –well#3s test 2 test 3 test 4 test 5 0...
TRANSCRIPT
2020 ALRDC Artificial Lift
WorkshopCox Convention Center, Oklahoma City, OK
February 17 – 20, 2020
Improved Field Management and
Production Optimisationby
Continuous Monitoring of Wells
Presented by
Andrew Jamieson
Technical Director, Neftemer Ltd
2020 ALRDC
Artificial Lift Workshop
Presentation points
⚫ Conventional well test methods
➔ do not give accurate estimates of well production
⚫ Continuous well monitoring
➔ is a recognised better alternative
⚫ Demonstrable benefits are:
➔ Optimised Production, Predictive Well Maintenance,
Increased Revenue
⚫ However, there is little apparent interest
➔ from the industry worldwide
⚫ Why is there this evident inconsistency?
Neftemer Ltd
2020 ALRDC
Artificial Lift Workshop
Why consider continuous
well monitoring?
⚫ Serious challenges to oil industry
➔ In monitoring and measuring oil well production
• More difficult fluid properties and locations
⚫ Reasonable estimates are essential
➔ Updating reserves
➔ Planning field extensions
➔ Deciding when to apply enhanced recovery
processes
⚫ Better assessment and optimisation of wells
➔ Increased revenue
➔ Less chance of breakdowns
2020 ALRDC
Artificial Lift Workshop
Why NOT continuous
monitoring?
⚫ Conventional approach (for > 100 years!)
➔ Intermittent testing for a few hours per month
• Using fixed or moveable test separators
• Or more recently multiphase meters
⚫ Strong resistance to doing anything else
➔ If it was good enough in the past, it’s still good!
• Continuous monitoring dismissed as “far too expensive”
➔ Changing oil industry mind set is DIFFICULT!
⚫ However
➔ More and more there is open acknowledgement
• Intermittent measurement CANNOT estimate production from
many wells reasonably
2020 ALRDC
Artificial Lift Workshop
NEL and OGA view?
2020 ALRDC
Artificial Lift Workshop
Issues with intermittent
measurements
⚫ Wide range of fluid mixtures and flowrates
➔ Over field lifetimes
⚫ Proper design, operation and maintenance?
➔ In current cost cutting environment?
⚫ In many parts of world
➔ Assets split up among several new operators
⚫ Allocation of oil among new operators
➔ Relatively high accuracy required
➔ Often dependent on unreliable well information
• Former operator did not install high quality systems!
2020 ALRDC
Artificial Lift Workshop
Does current practice
control assets adequately?
⚫ Current well monitoring practice
➔ Well testing only several hours per month
• Fixed or mobile test separators
• Mobile multiphase meter assemblies
• More attention to problem wells?
2020 ALRDC
Artificial Lift Workshop
Answer almost always “No!”
⚫ Key assumptions
➔ Wells produce in a stable manner
➔ Production unchanged when on test
➔ ASSUMPTIONS SELDOM VALID
➔ Later slides will demonstrate this
⚫ Continuous monitoring
➔ Key to optimising production
• Needs cost effective well measurements
2020 ALRDC
Artificial Lift Workshop
Downhole centrifugal pump
0
20
40
60
80
100
120
140
03.июн 03.июн 04.июн 04.июн 05.июн 05.июн 06.июн
Де
би
т п
о ж
ид
ко
сти
, О
бв
од
не
нн
ос
ть
0
50
100
150
200
250
300
350
400
Ра
сх
од
га
за
Дебит по жидкости (т/сут) Обводненность (%) Расход газа (м3/сут)Liquid flowrate (T/day) Watercut (%) Gas flowrate (m3/day)
Liq
uid
flo
wra
te,
Wate
rcut
Gas flo
wra
te(m
3/d
ay)
3 June 3 June 4 June 4 June 5 June 5 June 6 June
Скважина 3026 (ЭЦН 80-1400)
0
20
40
60
80
100
120
140
03.июн 03.июн 04.июн 04.июн 05.июн 05.июн 06.июн
Де
би
т п
о ж
ид
ко
сти
, О
бв
од
не
нн
ос
ть
0
50
100
150
200
250
300
350
400
Ра
сх
од
га
за
Дебит по жидкости (т/сут) Обводненность (%) Расход газа (м3/сут)Liquid flowrate (T/day) Watercut (%) Gas flowrate (m3/day)
Liq
uid
flo
wra
te,
Wate
rcut
Gas flo
wra
te(m
3/d
ay)
3 June 3 June 4 June 4 June 5 June 5 June 6 June
Скважина 3026 (ЭЦН 80-1400)
2020 ALRDC
Artificial Lift Workshop
0
10
20
30
40
50
60
70
80
90
100
04.июн 05.июн 06.июн 07.июн 08.июн 09.июн 10.июн 11.июн
Дебит по жидкости (т/сут) Обводненность (%) Расход газа (м3/сут)
Скважина 8331 (НН2Б 44-30)
Liquid flowrate (T/day) Watercut (%) Gas flowrate (m3/day)
JuneJuneJuneJuneJune JuneJuneJune
0
10
20
30
40
50
60
70
80
90
100
04.июн 05.июн 06.июн 07.июн 08.июн 09.июн 10.июн 11.июн
Дебит по жидкости (т/сут) Обводненность (%) Расход газа (м3/сут)
Скважина 8331 (НН2Б 44-30)
0
10
20
30
40
50
60
70
80
90
100
04.июн 05.июн 06.июн 07.июн 08.июн 09.июн 10.июн 11.июн
Дебит по жидкости (т/сут) Обводненность (%) Расход газа (м3/сут)
Скважина 8331 (НН2Б 44-30)
Liquid flowrate (T/day) Watercut (%) Gas flowrate (m3/day)
JuneJuneJuneJuneJune JuneJuneJune
Beam Pumped Well
2020 ALRDC
Artificial Lift Workshop
Well production fluctuates!
y = 1,0978x + 84,949
R2 = 0,2833
0
20
40
60
80
100
120
140
160
180
200
0 5 10 15 20 25 30
Время (дни)
Де
би
т ж
ид
ко
сти
0
20
40
60
80
100
120
Об
во
дн
ен
но
сть
, Р
ас
хо
д
га
за
, В
ре
мя
вы
хо
да
на
за
ме
р
Дебит жидкости (т/сут) Обводненность (%) Расход газа (м3/сут) Время выхода на замер, мин Тренд (Дебит жидкости)
Translation
Top heading: - Liquid Flow rate (t/day): Water cut (%): Gas Flow Rate (m3/day):
Measurement update time (min): Trend (Liquid Flow Rate).
X-axis: Time in days Left Y-axis: Liquid Flow Rate
Right Y-axis: Water cut, Gas Flow Rate, Measurement update time
2020 ALRDC
Artificial Lift Workshop
Typical Nigerian 24 hr
production example
0
100
200
300
400
500
600
700
0 5 10 15 20 25
Liquidrateinbarrels/day
Timeinhours
LiquidrateVersusTime
2020 ALRDC
Artificial Lift Workshop
Petrobras Campos Basin Well data 1:
Density vs. time (5 hours)
2020 ALRDC
Artificial Lift Workshop
Petrobras Campos Basin Well data 4:
Density vs. Time (8 hours)
2020 ALRDC
Artificial Lift Workshop
Petrobras Campos Basin Well data 5:
Density vs. Time (3 hours)
2020 ALRDC
Artificial Lift Workshop
Petrobras Campos Basin
well profile
PETRONAS RESULTS – Well#3S
Plot shows 24 hours data
• Large density variation – from 100 kg/m3 to 650 kg/m3• Liquid variation from 1250 to 2000 bpd (~23% variation)• Discontinuous Readings – though trend was visible
Liq Flow Rate; Gas Flow Rate; Density; Water Cut
Avg Liq Rate: 1600 bpd
Avg Liq Rate: 1300 bpd
2020 ALRDC
Artificial Lift Workshop
Production optimisation
⚫ Is this an important aim?
➔ If “No”, what are we here for?
➔ If “Yes”, continue!
⚫ Measure all phases (oil, water, gas)
➔ Into and out of ground
⚫ Many (most?) wells do NOT produce steadily
➔ Continuous measurement gives obvious benefits
➔ Major upset to a 150 year tradition
2020 ALRDC
Artificial Lift Workshop
0
20
40
60
80
100
120
140
0
200
400
600
800
1000
1200
1400
1600
1800
Ch
ok
e S
ize /6
4"
Wate
r Cu
t (%)
Oil
/ L
iqu
id r
ate
(B
PD
)P
ressu
re (
Psi)
Well Test History
THP
Oil
ChokeSize
Example well test history - 1
2020 ALRDC
Artificial Lift Workshop
Example well test history - 2
⚫ From June ‘09 – Nov ’11 about 900 days
➔ Well could have flowed at 1000 bbl./day
➔ At $50/bbl., value of production $45 million
• (900 x 1000 x 50)
⚫ Actual production from well over 900 days
➔ about ½ x 1000 bbl./day (estimate area under graph)
➔ Serious lack of optimisation!
⚫ Well could have produced twice what it did
➔ The operator lost $22.5 million in production
PETRONAS RESULTS – Well#3S
Test 2 Test 3 Test 4 Test 5
0
50
100
150
200
250
0 0.5 1 1.5 2
Liq
uid
Rate
(b
bl/d
ay)
Injected Gas Rate (mmscfd)
Gas Lift Optimization - Verification
• A Gas Lift optimization
exercise was conducted
to test the sensitivity of
meter and prove the
future usage
• (Red Dot) was the
actual Gas Injection
Rate which Field P field
was injecting
• The exercise verified
with actual relative
values that the current
Gas lift injection was an
optimum injection
Findings for A4
• For low gas injection (less than 20 Ksm3/d)- significant risk of flow shut down
• Increasing gas injection rate leads to gradualreduction of liquid production
• average density of multiphase flow goes downwith more gas injected- increasing liquid velocity does not compensate
Recommendation for A4
• We recommend to keep gas injection rate as lowas reasonably possible keeping in mind the riskof flow shut down at the gas injection rates lessthan 20 Ksm3/d
20 30 40 50 60 70 80220
230
240
250
260
270
280
Gas injection, Ksm3/d
Liq
uid
flo
w r
ate
, t/
d
A4 Multi rate test
Lift gas rate used
2020 ALRDC
Artificial Lift Workshop
Increased production from
injection of light oil into wellСкважина, оснащенная установкой НН2Б-70-30
Реакция прибора Нефтемер (оперативные значения массового расхода жидкости) на промывку (прокачку) скважины легкой
нефтью агрегатом АДП.
Liq
uid
flo
w r
ate
(m
3/d
ay)
Time (Hours)
2020 ALRDC
Artificial Lift Workshop
Russia - Recent well
optimisation by about 40%
2020 ALRDC
Artificial Lift Workshop
Stages in Field Life
2020 ALRDC
Artificial Lift Workshop
Field Management
⚫ Field life stages and departments in charge• Exploration (Drilling)
• Development (Project)
• Production (Operations)
• Improvement (another project?)
• Rundown and decommissioning (????)
⚫ Measuring and monitoring• Require reasons, information and equipment
• All change for different stages
• Not usual to keep track of these
• Installed equipment only works for part of field life
⚫ Flexible measurement equipment important
Production Reporting Requirements
Allocation and Sales Agreements
Safety, Environmental and Operational Requirements
Local
Processing
Secure
Data link
Office
Processing
Secure
Data link
Further
Processing,
Reporting
INFORMATION
Packaging:
e.g. land,
offshore,
subsea
Comms link
e.g. wire,
radio,
microwave
Packaging
Comms link
e.g. wire,
radio,
microwave
PackagingMECHANICAL
Data Integrity checks
Process simulation models
Calibration information
CONTRACTUAL
LEGISLATIVE
BUSINESS NEEDS
Sensors
Sensor
packaging
and
installation
FUNCTIONAL ASPECTS OF MODERN METERING,
MEASUREMENT AND MONITORING SYSTEMS
2020 ALRDC
Artificial Lift Workshop
6. TEST OF MULTIPHASE METER ON PPM-1
The multiphase meter Neftemer was tested in
the month of May on wells PM-50 and PM-11
and showed satisfactory results. The meter
was capable of measuring simultaneously
the flow of gas, oil and BS&W. After analysis
in the Test Centre of Petrobras (NUEX) in
Aracaju a report will be issued with the
results achieved and the final conclusions.
The meter had a lot of attention in ATP-C
department of Petrobras, as it was the first
top-side meter with a nucleonic source, but
after intervention of the measuring teams
(Cenpes, ATP-C/EE, ENGP/EE) and SMS with
a presentation of conscientiousness, all the
work force was in agreement with the
planned tests. The operations team showed
confidence in the performance of the meter
in the task of monitoring the wells and have
great expectations that multiphase meters
will assist them, in the near future, to adjust
the essential parameters to maintain and
even increase production in the wells of the
unit.
Petrobras
Newsletter
2020 ALRDC
Artificial Lift Workshop
Expense and manpower
⚫ Take oil well + completion cost at $12 million
➔ Produces for, say, 10 years at 1000 bbl/day
• 3.6 million bbl, at $50/bbl results in $180 million
⚫ Cost of monitoring over 10 years
➔ Say equipment $1 million, manpower $100,000/yr
• Total cost easily less than $2 million; 40 days production.
⚫ Cost of poor or non-existent monitoring
➔ Example showed this as easily half of the production
➔ In 2004 Shell overestimated reserves by 20%
• Huge costs and litigation lasting years
⚫ Continuous monitoring is CHEAP; a no-brainer
2020 ALRDC
Artificial Lift Workshop
Recent comments
⚫ Major North Sea company
➔ We install multiphase meters on all our wells
• gives 1 – 2% improvement in the reserves
• It improves our competitive position – we don’t shout about it!
⚫ Director of ANP Brazil, Décio Oddone
➔ Improving reserves recovery factor is top priority
• 1% improvement means 2 billion barrels of oil
Note: at $50 per barrel, this equates to $100 Billion
⚫ Several operators
➔ Process or petroleum engineers in metering positions
• Much more interested in optimising wells and fields
2020 ALRDC
Artificial Lift Workshop
A way forward?
⚫ New mind set of continuous well monitoring
➔ Dramatically assists well production optimisation
• Better Field Management a direct consequence
⚫ Large scale field deployment practical
➔ Starts with two meters on one facility
• Extend to more facilities and so the whole field
⚫ Training of oil and service companies’ staff
➔ Gradual deployment allows excellent training
• Requires close collaboration between departments
⚫ Timescale
➔ Not so long, once benefits are recognised!
Copyright
Rights to this presentation are owned by the company(ies) and/or author(s) listed on the title page. By submitting this presentation to the Artificial Lift Strategies for Unconventional Wells Workshop, they grant to the Workshop, the Artificial Lift Research and Development Council (ALRDC), and the Southwestern Petroleum Short Course (SWPSC), rights to:
▪ Display the presentation at the Workshop.
▪ Place it on the www.alrdc.com web site, with access to the site to be as directed by the Workshop Steering Committee.
▪ Place it on a CD for distribution and/or sale as directed by the Workshop Steering Committee.
Other use of this presentation is prohibited without the expressed written permission of the author(s). The owner company(ies) and/or author(s) may publish this material in other journals or magazines if they refer to the Artificial Lift Strategies for Unconventional Wells Workshop where it was first presented.
322020 ALRDC Artificial Lift Workshop
Oklahoma City, OKFeb. 17 - 20, 2020
Disclaimer
332020 ALRDC Artificial Lift Workshop
Oklahoma City, OKFeb. 17 - 20, 2020
The following disclaimer shall be included as the last page of a Technical Presentation or Continuing Education Course. A similar disclaimer is included on the front page of the Artificial Lift Strategies for Unconventional Wells Web Site.
The Artificial Lift Research and Development Council and its officers and trustees, and the Artificial Lift Strategies for Unconventional Wells Steering Committee members, and their supporting organizations and companies (here-in-after referred to as the Sponsoring Organizations), and the author(s) of this Technical Presentation or Continuing Education Training Course and their company(ies), provide this presentation and/or training material at the Artificial Lift Strategies for Unconventional Wells Workshop "as is" without any warranty of any kind, express or implied, as to the accuracy of the information or the products or services referred to by any presenter (in so far as such warranties may be excluded under any relevant law) and these members and their companies will not be liable for unlawful actions and any losses or damage that may result from use of any presentation as a consequence of any inaccuracies in, or any omission from, the information which therein may be contained.
The views, opinions, and conclusions expressed in these presentations and/or training materials are those of the author and not necessarily those of the Sponsoring Organizations. The author is solely responsible for the content of the materials.
The Sponsoring Organizations cannot and do not warrant the accuracy of these documents beyond the source documents, although we do make every attempt to work from authoritative sources. The Sponsoring Organizations provide these presentations and/or training materials as a service. The Sponsoring Organizations make no representations or warranties, express or implied, with respect to the presentations and/or training materials, or any part thereof, including any warrantees of title, non-infringement of copyright or patent rights of others, merchantability, or fitness or suitability for any purpose.