A Practical Approach to Asset Reliability Improvement focused on Turbo Machinery
• Poovan Naidoo
• Senior Manager: Turbo Equipment Maintenance
• Secunda Synfuels Operations
• South Africa
Place your company logo here NB: Your
company’s logo is only permitted on the
first slide!
Background Key Performance Metrics Asset Lifecycle Operate Within Agreed Parameters Methodology
Asset Management Philosophy Uptime Analysis Influence Diagrams Gap Closure Plan
Continuous Improvement and Tracking Process Flow for Specific Problems Management accountabilities
Copyright ©, 2016, Rota-Eng Consulting
Turbo Equipment Maintenance (TEM) Structure:
TEM (147)
Turbo 4 (22)
Turbo 2 (38)
Turbo 3 (30)
Turbo Monitoring
and Balancing
(27)
Asset Health
(25)
Copyright ©, 2016, Rota-Eng Consulting
Baseline Performance (2009):
3.17% Unintended Downtime on critical equipment (Compressors and Turbines)
19 months MTBF on pumps
7 Recordable Case Injuries
9% overspend on annual budget
Copyright ©, 2016, Rota-Eng Consulting
Results Achieved:
Performance Measure 2009 Actual 2015 Actual
Equipment Unavailability 3.17%
Process Pump MTBF 19 months
Recordable Case Injuries 7
Budget Comparison 1
Cost Performance 9% over budget
Still pushing the boundaries…we are not done yet!
0.09%
34 months
0 injuries for 3 years
0.93
1% under budget
Copyright ©, 2016, Rota-Eng Consulting
Acquire
Operate and Maintain
Dispose
Strategy Plan Execute Review
Copyright ©, 2016, Rota-Eng Consulting
Design Limit
Time
Parameter Value
Normal Operation
Are either of these
deviations a concern?
Copyright ©, 2016, Rota-Eng Consulting
IDEF0 Notation
Activity Input Output
Constraint
Resource FIPS Publication 183 released of IDEFØ December 1993 by the Computer Systems Laboratory of the National Institute of Standards and Technology (NIST). Copyright ©, 2016, Rota-Eng Consulting
Establish Asset Management
Standards
New and Existing Plant
Design Standards
Operate and Maintain to
standard
Evaluate and Improve Asset Performance
Raw Materials, Parts and Services
Products
Breakdowns
Plan
Do
Review
Copyright ©, 2016, Rota-Eng Consulting
6.6 6.5
7.1
6.6
7.2
6.8
6.6
7.1 6.6 6.5
6.2
4.7
4.7
6.7
7.3
6.4
0.0
2.0
4.0
6.0
8.0
10.0I) Characteristics of the Business
II) Maintenance Strategy
III) Organizational Arrangements
IV) Human Resource Management
V) Maintenance Administration
VI) Planning
VII) Scheduling
VIII) Work Orders
IX) Use of Tactics
X) Equipment Records
XI) Purchasing
XII) Stores
XIII) Inventory Control
XIV) Performance Measures
XV) Customer Satisfaction
XVI) Computerized MaintenanceManagement Systems
Diagnostic Overview
Methodology from: Uptime, John Dixon Campbell, 1995 Copyright ©, 2016, Rota-Eng Consulting
5.2 6.4
5.8
5.2
5.6
5.0
5.4
5.4
5.2
7.2
0.0
1.0
2.0
3.0
4.0
5.0
6.0
7.0
8.0
9.0
10.0
Layout, locations, access, space, racking,security
Equipment, mobile equipment
Degree of automation, bar coding
Substores, shop-floor stores, free accessitems
Receiving, issuing, stocking schedules, labor,procedures
Direct charge item storage
Quality assurance, accuracy
Telephone orders, delivery, kitting/pick lists
Consignment stock locations, vendor access
Requisitioning procedures
Stores
Methodology from: Uptime, John Dixon Campbell, 1995 Copyright ©, 2016, Rota-Eng Consulting
6.2
5.4
6.0
5.6
5.0 5.2
5.4
6.4
5.8
0.0
1.0
2.0
3.0
4.0
5.0
6.0
7.0
8.0
9.0
10.0
Catalogs, referencing, on-line information
Inventory reconciliation and absolute value ofdeviation
Use of statistical analysis by inventorycategory, stock history
Measures of investment efficiency, turnover,value, number of SKUs
Obsolescence review, no usage analysisStock control techniques, max-min, EOQ,
EOP
Control of repairable, rotables
Service level/stockout measures, back orders
Stock counting policies, schedules
Inventory Control
Methodology from: Uptime, John Dixon Campbell, 1995
Copyright ©, 2016, Rota-Eng Consulting
Competency as per
training matrix
>80%
Adherance to
training plan >80%
Improve
Employee
Engagement
Survey results
Unintended
downtime <1.45%
Zero overdue stat
>60 days without
delays approved
2.5 - 5% reduction
in GO times on
identified
equipment
Reduction of Urgent
and Emergency work
Maintenance and
Operational Schedule
Compliance >85%
Complete all
shutdown
equipment within
schedule End the year on or
below budget
Reduce satellite
stock by 50%
Zero harm to
people
Sustainable BBS
participation
above 80%
No C and D audit
findings (adhere to
governance) Complete
competition
training and
certification
Stable,
Satisfied and
performing
Employees
Planned work allows
adequate thinking
time to incorporate
safety considerations
Less breakdowns -
can execute
planned work
Allows identification
of risks and removal
of safety barriers
Adhere to
legal
compliance
Ensure stock is
managed and
controlled by
Procurement
Create a compliance
culture and
environment
(understanding of the
rules)
Perform Asset Management
Process (standardise GO
procedures, QCP's,
specifications,
SU/SD/operating parameters
and procedures, maintenance
strategies, RCA's, Renewal
projects)
Adhere to the
rules of the
company
Idenitify
competency
defficiencies
Plan and attend
training to
address
defficiencies
Create
understanding of
asset management
Copyright ©, 2016, Rota-Eng Consulting
Concern Raised By
Date Raised
Action Responsible Person
Due Date
Comment
Incorrect stock levels at Stores
Poovan 12-May-11
Evaluate required stock levels and create business case to increase inventory for deficiencies
Poovan 30-Nov-11
Prioritise compressors and turbines with high unreliability.
Copyright ©, 2016, Rota-Eng Consulting
Establish Asset Management
Standards
New and Existing Plant
Design Standards
Operate and Maintain to
standard
Evaluate and Improve Asset Performance
Raw Materials, Parts and Services
Products
Breakdowns
Manage/ Govern the
change
Update standards
Copyright ©, 2016, Rota-Eng Consulting
Determine Key Performance Indicators
Related to improvement activities and influence diagram
Regular review of performance indicators and gap closure plan status
Maintain focus on actions and due dates Give recognition where improvement is
noted Manage change with the team
Copyright ©, 2016, Rota-Eng Consulting
Define
Operating
Parameters
Assess
requirements/
capability
Design
Asset
Define
Maintenance
Strategy
Acquire
Asset
Modify
Asset
Update
maintenance
strategy/
operating
philosophy
Operate
Asset
Operate
within
agreed
parameters
Change
operating
parameters
(outside of
agreed
operating
parameters
No change
to asset
Execute
Maintenance
Strategy
Root Cause
Analysis and
Identification
Engineer
Out
Problem
Asset failure
outside of
strategy
Inspection Maintenance Renewal
Work
Management
Process
Spares
strategy
Quality
Control
Update
production
budget
Identify
need
Codes, Standards, Policies, Procedures, Practices
Dispose
Basis of maintenance budget
and strategy work in work
management process
People
Money
Facilities
Utilities
Raw
Materials
Information
Equipment
Stable
Plant/
Process
Copyright ©, 2016, Rota-Eng Consulting
Believe in your team Set the expectation on standards – aim for
achievable, incremental improvements Actively support gap closure activities Instill discipline to follow standards Encourage and reward proactive
maintenance and improvement actions
Copyright ©, 2016, Rota-Eng Consulting
Make the difficult decisions to do the right thing
Empower the team to make decisions and implement improvement actions
Focus the team on the next critical item Be involved and remove obstacles