in the united states district court haines & …issue, it discovered that balfour had failed to...
TRANSCRIPT
-
1 Defendant originally moved to dismiss the complaint onDecember 2, 2008 when the case was pending before our latecolleague, Judge Thomas M. Golden. See Memorandum of Law inSupport of Balfour’s Motion to Dismiss (“MTD1"). H&K respondedon January 1, 2009. See H&K’s response (“Pl. MTD1 Resp."). Balfour replied a month later. (“Def. MTD1 Repl.”). Almost twoyears elapsed before the Chief Judge reassigned this case to us,following Judge Golden's death. We denied the motion to dismisswithout prejudice and ordered the defendant to file a renewed andupdated motion to dismiss. Relying in large part on theiroriginal motion to dismiss, defendant filed a renewed motion. See Brief in Support of the Amended Motion to Dismiss and/or StayLitigation (“MTD2"). H&K responded relying in large part on itsoriginal response (“Pl. MTD2 Resp."). Defendant thereafterreplied (Def. MTD2 Repl.”). Because the parties both rely ontheir previous motions and responses, this Memorandum addressesthe arguments presented in both sets of motions to dismiss, theresponses thereto, and the replies.
IN THE UNITED STATES DISTRICT COURT FOR THE EASTERN DISTRICT OF PENNSYLVANIA
HAINES & KIBBLEHOUSE, INC. : CIVIL ACTION:
v. ::
BALFOUR BEATTY CONSTRUCTION, :INC. : NO. 08-5505
MEMORANDUM
Dalzell, J. June 1, 2011
Plaintiff Haines & Kibblehouse, Inc. (a Pennsylvania
corporation) (“H&K”) seeks declaratory relief and judgment in
this diversity action against Balfour Beatty Construction, Inc.
(a Delaware corporation with its principal place of business in
Atlanta, Georgia) (“Balfour”) in an amount in excess of $1
million. Compl. ¶ 143, 150, 158, 165, 178. Balfour moves to
dismiss the case for failure to state a claim and/or to stay
litigation pursuant to Fed. R. Civ. P. 12(b)(6) and Fed. R. Civ.
P. 12(b)(7).1
-
2
As will be seen, given the unusual procedural posture,
we must embark on an extended analysis of relatively arcane areas
of law in order to decide this motion.
I. Factual Background
Balfour was the general contractor for the Commonwealth
of Pennsylvania's Department of Transportation (“PennDOT”) for
the construction of the Route 222 Bypass project (the “Project”).
Compl. ¶ 13. On March 15, 2004, Balfour entered into a contract
with PennDot to furnish work, labor, materials and services for
the construction of the Project. Id. ¶ 15. Balfour’s contract
with PennDot involved about $57.7 million (the "Prime Contract").
Id. ¶ 16. On April 21, 2004, Balfour entered into a subcontract
with H&K in the initial amount of $13,399,897.20 (the
“Subcontract”). Id. ¶ 17. The Prime Contract included a special
provision for project milestones. Id. ¶ 18.
The special provision required that all Project
construction would be completed on or before July 7, 2006 or
Balfour would be subject to PennDot's assessment of road user
liquidated damages. Id. ¶ 19. Because PennDot did not issue the
“Notice to Proceed” on the Project by the date the Prime Contract
anticipated, PennDot granted a seventy-three-day extension to the
Project milestone date. Id. ¶ 21. This extension revised the
Project milestone date from July 7, 2006 to September 19, 2006.
Id. ¶ 22.
H&K avers that Balfour knew that if Balfour failed to
-
3
complete the predecessor work and did not provide H&K with
unrestricted access to the worksite, H&K could not complete the
work it was contracted to do and this would result in H&K's
increased costs and expenses for which Balfour would be held
accountable. Id. ¶ 36. H&K also avers that at no time prior to
entering into the Subcontract did Balfour inform H&K that Balfour
would be making unilateral changes to the sequence or durations
of predecessor work that would directly affect H&K’s work, but,
instead, expressly and impliedly agreed "to efficiently progress
the work." Id. ¶ 43 [sic].
H&K claims that Balfour "failed to commence, prosecute
and complete the predecessor activities" in the prescribed
sequences and within the specific timeframe agreed to with H&K
and upon which H&K based its pricing. Id. ¶ 63. When Balfour
notified H&K to proceed with its subcontract work, Balfour had
not completed the predecessor work and had not yet procured the
materials to complete the work H&K agreed to do. Id. ¶ 65. H&K
claims that Balfour’s failure to complete the predecessor work
with diligence and with sufficient manpower and equipment, as
well as its denial of full access to the site to H&K interfered
with the planned sequence of operations by H&K and caused H&K to
incur additional costs. Id. ¶ 68.
As of November of 2005, the Project was significantly
behind schedule, the necessary predecessor work needed for H&K’s
placement of subbase and paving remained incomplete, and Balfour
allegedly had made many unilateral changes to the schedule and
-
2 Balfour disputes this contention. This dispute will becanvassed at length below.
3 As noted, the case was originally assigned to the lateJudge Golden.
4
sequence for the remaining work. Id. ¶ 92. Although the Project
was supposed to be completed in late 2006, it was not completed
until late 2007. Id. ¶ 96. Balfour has not yet fully paid H&K
for the impacts of its poor scheduling on H&K’s work. Id. ¶ 98.
H&K claims that Balfour has also failed to make a claim to
PennDot for the increased costs of H&K completing its work,
including, but not limited to, the increase in the unit prices
for the work H&K performed.2 Id. ¶ 99.
H&K believes that as of September 19, 2006 PennDot
began assessing liquidated damages against Balfour. Id. ¶ 111.
PennDot never assessed damages against H&K. Id. ¶ 113. H&K
estimates that the minimum impact of Balfour's failings on H&K’s
work exceeded ten million dollars. Id. ¶ 117.
II. Procedural History
The crux of this motion to dismiss will be found in the
relationship between H&K and the courts rather than the
relationship between the parties. On September 18, 2006, H&K
filed a complaint against Balfour in the Montgomery County Court
of Common Pleas. Balfour removed that case to federal court at
C.A. No. 06-48073 and filed a motion to dismiss. Judge Golden
dismissed without prejudice all of H&K’s claims except H&K’s
claim for declaratory relief. Judge Golden remanded that claim
-
5
back to state court on June 7, 2007. In doing so, Judge Golden
relied upon Balfour’s Subcontract-based defenses to the action,
holding that:
The plain meaning of Article 2.2.20 is thatany claim that the subcontractor (Plaintiff)has for performing extra work or arising outof a delay or any other claim, whether it beagainst PennDot or the Contractor (Defendant)must first be compensated by the Owner(PennDot) to the Contractor (Defendant)before Plaintiff can bring suit against theDefendant.
Haines & Kibblehouse, Inc. v. Balfour Beatty Constr., Inc. , No.
06-4807, slip. op. at 4 (E.D. Pa. Jun. 7, 2007) (we shall refer
to this case hereinafter as "Haines I") (emphasis in original).
H&K filed a motion for reconsideration of that Order, which Judge
Golden denied on July 27, 2007. Haines I, slip. op. at 1 (Jul.
27, 2007). Judge Golden also in that Order denied H&K’s request
to certify the Court’s Memorandum Opinion for interlocutory
appeal. Id.
H&K nevertheless on August 22, 2007 filed a Notice of
Appeal from Judge Golden's July 27, 2007 Order in the hope of
standing on its complaint and securing appellate review of the
four counts that Judge Golden dismissed without prejudice. MTD1,
Ex. 5 (Letter brief of Sept. 5, 2007 in C.A. No. 07-3520 (3d
Cir.)). H&K declared that "there is no way for H&K to cure the
'defect' that the District Court found in the Complaint" because
the condition precedent, as Judge Golden defined it, "will never
be achieved." Id. at 3. Thus, H&K contended to the Court of
Appeals that “H&K must stand on the allegations in the Complaint
-
4 28 U.S.C. § 1447(d) reads, “An order remanding a case tothe State court from which it was removed is not reviewable onappeal or otherwise, except that an order remanding a case to theState court from which it was removed pursuant to section 1443 ofthis title shall be reviewable by appeal or otherwise.”
6
and the order denying the Motion for Reconsideration of the June
5, 2007 Order must be considered a final order.” Id. at 5. On
January 30, 2008, our Court of Appeals issued an order providing
that although it was not appropriate at that time to dismiss the
case based on a jurisdictional defect, that view did " not
represent a finding that the Court has jurisdiction to hear the
appeal in this case." Pl. MTD1 Resp., Ex. H (Order dtd. Jan. 30,
2008 in C.A. No. 07-3520 (3d Cir.)). The parties instead were
ordered to address the effect of 28 U.S.C. § 1447(d) 4 on the
Court’s appellate jurisdiction. Id.
Thereafter -- but before our Court of Appeals set a
briefing schedule -- the parties were obliged to participate in
the Third Circuit’s mandatory mediation program. Pl. MTD2 Resp.
at 6 n.6. The mediation did not succeed. Id. The Mediation
Program Director, however, did not inform the Case Manager that
the mediation had failed, id., and so a briefing schedule did not
promptly issue. Pl. MTD2 Resp., Ex. K (September 25, 2008
correspondence from Paul A. Logan, Esq., to Joseph A.
Torregrossa, Esq.). H&K pressed our Court of Appeals to issue a
scheduling order, which it ultimately did on September 29, 2008.
Id., Ex. K; MTD1, Ex. 10.
H&K claims that before the briefing schedule could
-
5 H&K merely sent a two-sentence letter to the "Office ofthe Clerk". See MTD2 Resp., Ex. O.
7
issue, it discovered that Balfour had failed to include H&K’s
claim in its Board of Claims complaint, despite Balfour’s
representations that it would include H&K’s claims in that
complaint. Pl. MTD2 Resp. at 6 n.7. Balfour indeed filed an
amended complaint in the Board of Claims on November 9, 2007.
Id., Ex. N. H&K asserts that, as with the original complaint,
Balfour’s amended complaint to the Board of Claims also failed to
mention H&K by name or include any of its claims. Id. at 7. On
April 29, 2008, PennDot’s litigation counsel, Jeffrey W. Davis,
Esq., confirmed to H&K's counsel that the pleadings failed to
identify any affirmative subcontractor claims, and PennDot
invited Balfour to provide clear and specific evidence that
Balfour presented any of H&K’s claims to PennDot. Id., Ex. M.
H&K avers that once it learned from PennDot's counsel
that Balfour had indeed not included its claims in Balfour's
amended complaint to the Board of Claims, it informally sought to
“withdraw” its appeal.5 MTD1, Ex. 8, 10; Pl. MTD2 Resp., Ex. O.
H&K did not do this until November 5, 2008, one day after it had
filed a new complaint in the Court of Common Pleas of Montgomery
County. See generally plaintiff’s complaint. As Balfour would
not consent to such a “withdrawal” of H&K’s appeal, it instead
moved to dismiss H&K’s appeal on December 3, 2008. Pl. MTD2
Resp., Ex. P. In response, on December 17, 2008 H&K moved to
voluntarily dismiss its appeal. Id., Ex. Q. On January 22,
-
8
2009, our Court of Appeals granted H&K’s motion to voluntarily
dismiss its appeal. Id., Ex. R (Ord. of Jan. 22, 2009 in C.A.
No. 07-3520 (3d Cir.)).
Meanwhile, Balfour removed H&K’s second state court
action to this court on November 24, 2008 ("Haines II"). This
second complaint had the same parties, the same claims, and
involved exactly the same set of alleged facts as the first
action. Balfour promptly filed a motion to dismiss the complaint
based, in part, on claim preclusion. Judge Golden heard oral
argument on the motion to dismiss but did not rule on it before
he died. Haines II was then transferred to our docket. As
noted, given the long delay and the tortured history in the Court
of Appeals, we denied the motion to dismiss without prejudice and
afforded Balfour the right to file an amended motion to dismiss.
Balfour thereafter filed an amended motion to dismiss and/or stay
the litigation, which we now address.
III. Analysis
Balfour moves to dismiss this action pursuant to Fed.
R. Civ. P. 12(b)(6) for failure to state a claim. It also moves
under Rule 12(b)(7) for failure to join an indispensable party.
In the alternative, Balfour moves to stay this action pending
resolution of the dispute between it and PennDot. H&K responds
that its discovery that Balfour had not included its claims in
its amended complaint to the Board of Claims was a “watershed
development” in the context of H&K's Third Circuit appeal and its
-
6 To survive a Rule 12(b)(6) motion, a party's factualallegations must raise a right to relief above the speculativelevel, and a complaint must allege facts suggestive of illegalconduct. Bell Atlantic v. Twombly, 550 U.S. 544, 563 n.8 (2007);Phillips v. County of Allegheny, 515 F.3d 224, 232 (3d Cir. 2008)(citing Twombly). The Supreme Court recently clarified theTwombly standard in Ashcroft v. Iqbal, 129 S.Ct. 1937 (2009),where it held that a complaint must contain sufficient factualmatter to state a claim for relief that is “plausible on itsface.” Iqbal, 129 S.Ct. at 1949 (internal quotations omitted).
A claim has facial plausibility when the plaintiffpleads facts sufficient to allow the court to “draw thereasonable inference that the defendant is liable for themisconduct alleged.” Id. The plausibility standard is not asdemanding as a “probability requirement,” but it does oblige aplaintiff to allege facts sufficient to show that there is morethan the mere possibility that a defendant has acted unlawfully.Id. (internal quotations omitted).
Iqbal established two principles that now underlie theRule 12(b)(6) inquiry. First, although a court must accept astrue the factual allegations in a complaint, this does not extendto legal conclusions. Id. “Threadbare recitals of the elementsof a cause of action, supported by mere conclusory statements, donot suffice.” Id. Second, a complaint must state a plausibleclaim for relief to survive a motion to dismiss. Id. at 1950. Determining whether a complaint states a plausible claim forrelief is “a context-specific task that requires the reviewingcourt to draw on its judicial experience and common sense.” Id.If the well-pleaded facts allege, but do not “show” more than themere possibility of misconduct, then the pleader is not entitledto relief within the meaning of Rule 8(a)(2). Id.
In deciding a motion to dismiss, “courts generallyconsider only the allegations in the complaint, exhibits attachedto the complaint, matters of public record, and documents thatform the basis of a claim. A document forms the basis of a claimif the document is ‘integral to or explicitly relied upon in thecomplaint.’” Lum v. Bank of America, 361 F.3d 217, 222 n.3 (3dCir. 2004) (internal citations omitted).
9
Montgomery County remanded matter because it showed that the
condition precedent Judge Golden articulated had not been met and
this “eviscerated the factual underpinnings of the June 2007
Order,” thereby rendering that Order moot. Pl. MTD2 Resp. at 7.
A. Defendant’s Rule 12(b)(6) Motion to Dismiss 6
-
10
Balfour argues that H&K has failed to state a claim
upon which relief can be granted because Haines II is barred by
claim preclusion. Should we not find that the entire action is
barred by claim preclusion, Balfour further argues that H&K is
barred by judicial estoppel from claiming that Judge Golden’s
July 27, 2007 Order was not final. Finally, Balfour argues that
if we do not find that the action is thus barred, there are
alternative, independent reasons why H&K’s complaint must be
dismissed.
1. Claim Preclusion
Balfour contends that H&K’s second action is barred by
the principle of claim preclusion because it is duplicative of
the first action. There is no doubt that this action is between
the same two parties, on the same Subcontract, for the same
Project. Haines II requests the same damages through the same
factual allegations and most of the same legal theories, and
includes five counts that are largely indistinguishable from the
five counts alleged in Haines I. MTD1 at 13.
Balfour argues that by standing on its complaint in the
first action, H&K intentionally converted the July 27, 2007 Order
into a final judgment in order to obtain immediate appellate
review. Id. Thus, even though the Court of Appeals ultimately
allowed H&K to voluntarily dismiss the first appeal, Balfour
argues that H&K cannot now claim that there was never a final
order in Haines I. Id. H&K responds that Judge Golden’s Order
was never made final because our Court of Appeals granted its
-
11
motion to voluntarily dismiss the appeal before definitively
holding that it had jurisdiction to hear the appeal.
Although our Court of Appeals has not determined
whether state or federal preclusion analysis applies in
successive-diversity proceedings, it has suggested that it need
not decide this issue because the holding would be the same under
either state or federal law. Lubrizol Corp. v. Exxon Corp., 929
F.2d 960, 962-63 (3d Cir. 1991). “The doctrine of res judicata
protects litigants from the burden of relitigating an identical
issue with the same party or his privy and promotes judicial
economy by preventing needless litigation.” Lewis v. Smith, 361
F. App’x 421, 423 (3d Cir. 2010) (internal quotation marks
omitted).
The doctrine of claim preclusion has three elements:
(1) a final judgment on the merits must have been rendered in a
prior suit; (2) the same parties or their privies must have been
involved in both suits; and (3) the subsequent suit must have
been based on the same cause of action as the original.
Lubrizol, 929 F.2d at 963. Claim preclusion bars not only
subsequent litigation of issues decided in the first proceeding,
but also bars issues that could or should have been litigated in
the first proceeding. Selkridge v. United of Omaha Life Ins.
Co., 360 F.3d 155, 172 (3d Cir. 2004) (holding that if the three
factors of claim preclusion are present, a claim that was or
could have been raised previously must be dismissed as
precluded).
-
12
In considering whether to dismiss a complaint on the
basis of claim preclusion, “[w]e [do] not apply this conceptual
test mechanically, but focus on the central purpose of the
doctrine, to require a plaintiff to present all claims arising
out [of] the same occurrence in a single suit.” Sheridan v. NGK
Metals Corp., 609 F.3d 239, 260 (3d Cir. 2010) (internal
quotation marks omitted). “In so doing, we avoid piecemeal
litigation and conserve judicial resources.” Id.
Here, there is no question that the same parties were
involved in both suits. In addition, this suit is based on the
same cause of action upon which the first suit was based. H&K
and Balfour agree on these points. The only question remaining
is whether the events that followed Judge Golden’s July 27, 2007
Order rendered that Order "final" for the purposes of claim
preclusion.
Generally, a dismissal without prejudice does not
represent a final judgment on the merits and is not appealable.
Bethel v. McAllister Brothers, Inc., 81 F.3d 376, 381 (3d Cir.
1996). “Where, however, the plaintiff cannot cure the defect in
the complaint or elects to stand on the complaint without
amendment, the order becomes final and appealable.” Id.
When H&K filed its notice of appeal, our Court of
Appeals ordered the parties to address the effect of 28 U.S.C. §
1447(d) on its appellate jurisdiction. Pl. MTD2 Resp., Ex. H.
It also cautioned that “[t]his order does not represent a finding
that the Court has jurisdiction to hear the appeal in this case.”
-
13
Id. (emphasis in original).
Balfour argues that H&K “converted” the July 27, 2007
Order from an otherwise non-final judgment to a “final and
appealable” decision in order to invoke the jurisdiction of our
Court of Appeals. MTD1 at 17. Balfour cites Bethel v.
McAllister Brothers, Inc., 81 F.3d 376, 381 (3d Cir. 1996),
Garber v. Lego, 11 F.3d 1197, 1198 n.1 (3d Cir. 1993), and
Borelli v. City of Reading, 532 F.2d 950 (3d Cir. 1976), in
support of its contention. But those cases are distinguishable.
In Bethel and Garber, our Court of Appeals contemplated
its jurisdiction before either reaching the merits or dismissing
the appeal. If Balfour’s argument were correct, then in Bethel
and Garber our Court of Appeals would have simply noted that the
appellant had invoked appellate jurisdiction and moved on from
there. But that is not what happened. In each case, our Court
of Appeals carefully considered whether it had jurisdiction
before determining that it did and then decided the appeal on the
merits. Borelli is distinguishable because there the plaintiff
did not elect to stand on her complaint.
In Hagan v. Rogers, 570 F.3d 146, 151 (3d Cir. 2009),
our Court of Appeals considered earlier cases where it had held
that a plaintiff had elected to stand on its complaint. The
Court noted that in Frederico v. Home Depot, 507 F.3d 188, 192
(3d Cir. 2007), it had decided that the plaintiff had elected to
stand on her complaint “where at no time during the proceedings
did she seek to correct the purported pleading deficiencies, but
-
14
instead repeatedly asserted that her complaint was sufficient as
filed.” Hagan, 570 F.3d at 151. Hagan also noted that it had
jurisdiction “when a plaintiff did not amend his dismissed
complaint within the 30 days allotted by the district court.”
Id. (in reference to Batoff v. State Farm Ins. Co., 977 F.2d
848, 851 n.5 (3d Cir. 1992)). The Court also considered that it
had held that certain plaintiffs “elected to stand on their
dismissed claims after they renounced, by letter briefs filed
with this Court, any intention to reinstitute proceedings against
the defendants at issue.” Id. (referring to in Tiernan v. Devoe,
923 F.2d 1024, 1031 (3d Cir. 1991)).
In Hagan itself, the Court found that none of the
plaintiffs amended their complaints within the thirty days the
District Court afforded. In addition, all of the plaintiffs
joined in the appeal and there was “no evidence that any ever
wavered from their argument that they should be permitted to join
under Rule 20.” Id. Thus, the Court found that the
circumstances confirmed that the appellants stood on their
initial complaint. Id. Indeed, just last week the Court in
Boretsky v. Governor of N.J., No. 2011 WL 2036440, *2 (3d Cir.
May 25, 2011), held that it was “satisfied that the plaintiffs’
actions demonstrated that they elected to stand upon their
original complaint” (emphasis added).
We must therefore examine H&K's actions to determine
whether our Court of Appeals’s jurisdiction had attached. Here,
H&K told our Court of Appeals that it was electing to stand on
-
15
its complaint. But then, before our Court of Appeals had decided
whether it indeed had jurisdiction to hear the appeal, H&K
attempted to withdraw its appeal. When H&K learned that it could
not informally “withdraw” its appeal, a month and a half later it
moved voluntarily to dismiss its appeal. Our Court of Appeals
granted that motion before it decided whether it indeed had
jurisdiction over H&K’s appeal.
Thus, based on H&K’s actions, for purposes of our claim
preclusion analysis we hold that H&K did not ultimately “elect to
stand on its complaint,” and Judge Golden’s July 27, 2007 Order
was never transmuted into a "final" order. All elements of claim
preclusion are thus not satisfied here.
2. Judicial Estoppel
But Balfour also argues that H&K is judicially estopped
from asserting that the July 27, 2007 Order was not a final
judgment. Balfour reports that it has incurred significant costs
to defend the actions that H&K elected to pursue in our Court of
Appeals, in state court, and in Haines I and II, where the
parties have exchanged multiple briefs on the legal merits of
H&K’s declaratory judgment action. MTD1 at 18.
H&K contends that it argued that our Court of Appeals
should deem Judge Golden’s July 27, 2007 Order final because it
believed that the Subcontract did not contain a condition
precedent that would bar H&K from proceeding against Balfour on
claims in which Balfour, and not PennDot, is responsible for the
-
7 Balfour raised judicial estoppel by motion before JudgeGolden in Haines II and Judge Golden entertained oral argument onthat motion before he died. See, e.g., Pl. MTD2 Resp., Ex. L,transcript of May 7, 2009 argument at 12 ("THE COURT: Becauseplaintiffs can come in in state court, unlike federal court, canwithdraw cases with impunity. In federal court you can run intoa problem." H&K's counsel responded, "I understand, Your Honor,yes.").
16
damages sought. Pl. MTD1 Resp. at 21. H&K argues that when it
allegedly discovered that the condition precedent had been waived
(because Balfour did not represent H&K’s claims in its filing
with PennDot), this altered the legal landscape and rendered its
appeal moot. Id.
While we have just decided that this action is not
claim precluded, we now address the issue of whether the entire
action is judicially estopped, which is within our discretion to
do.7 Krystal Cadillac-Oldsmobile GMC Truck, Inc. v. General
Motors Corp., 337 F.3d 314, 319 (3d Cir. 2003). Our Court of
Appeals has held that “a plaintiff, who has obtained relief from
an adversary by asserting and offering proof to support one
position, may not be heard later in the same court to contradict
himself in an effort to establish against the same adversary a
second claim inconsistent with his earlier contention.” Id.
(internal quotation marks omitted). The Court also recognized
“the intrinsic ability of courts to dismiss an offending
litigant's complaint without considering the merits of the
underlying claims when such dismissal is necessary to prevent a
litigant from ‘playing fast and loose with the courts.’” Id.
(quoting Scarano v. Central R. Co. of N.J., 203 F.2d 510, 513 (3d
-
17
Cir. 1953)).
To be sure, the doctrine of judicial estoppel should
only be applied to avoid a miscarriage of justice. Id. Judicial
estoppel focuses on the relationship between the litigant and the
judicial system, and seeks to preserve the integrity of that
system. Id. at n.7. In the absence of “any good explanation, a
party should not be allowed to gain an advantage by litigation on
one theory, and then seek an inconsistent advantage by pursuing
an incompatible theory.” Id. (internal quotation marks omitted).
But the estopped party need not have actually gained an advantage
because “the application of judicial estoppel does not turn on
whether the estopped party actually benefitted from its attempt
to play fast and loose with the court.” Id. at 324.
A party is judicially estopped if (1) it has taken two
positions that are irreconcilably inconsistent, (2) it changed
his or her position in bad faith (i.e., with intent to play “fast
and loose” with the courts), and (3) there is no lesser sanction
that will adequately remedy the damage done by the litigant’s
misconduct. Id. Equity requires that the presiding court give
the party to be estopped a meaningful opportunity to provide an
explanation for its changed position. Id. at 320.
-
18
a. Irreconcilably Inconsistent Positions
Here, H&K took two irreconcilably inconsistent
positions. It argued before our Court of Appeals that “[t]he
condition precedent that the District Court inserted into Article
2.2.20 of the Subcontract will never be achieved. And,
accordingly, H&K will never be able to re-file its Complaint.”
MTD1, Ex. 5 at 3. H&K argued to our Court of Appeals that the
Order should be deemed "final" because the District Court
interpreted the Subcontract to require that H&K’s claims should
first be submitted to PennDot through Balfour before H&K could be
permitted to bring a suit against Balfour. Id. H&K justified
its appeal of the District Court’s interpretation of the
Subcontract because, as it without qualification put it to the
Court of Appeals on September 5, 2007,
Stated in the most succinct terms, PaDOT willnever -- nor should it -- compensate BBCI (orH&K) for BBCI’s breaches of its Subcontractwith H&K. Accordingly, the conditionprecedent as interpreted by the DistrictCourt can never be met, H&K will never bepermitted to pursue its claims against BBCIand BBCI will be able to freely breach theSubcontractor Agreement and damage H&Kwithout accountability.
Id. at 4.
H&K argued that at least some of the damages that it
sustained were due to Balfour’s behavior, not PennDot’s. Id.
Because H&K believes it has claims against Balfour, and because
Balfour had no legal avenue through which to seek compensation
for those claims from PennDot (because PennDot was not a party to
-
19
the Subcontract), H&K concluded that the condition precedent as
Judge Golden defined it could "never be achieved" and PennDot
would "never" compensate Balfour for H&K’s breach of contract
claims against Balfour. Id. at 3, 4. Thus, H&K argued, this
"eliminates the possibility of a second lawsuit." Id. at 5 n.3
(emphasis added).
If we accept H&K’s understanding of Judge Golden’s
interpretation of the condition precedent at face value, this was
sound logic. H&K then argues that it changed its position when
it allegedly learned that Balfour had filed a claim for
compensation from PennDot without preserving H&K’s claims. But
this later-acquired knowledge was of no significance because all
that Balfour had done was precisely what H&K argued to the Court
of Appeals Balfour would do -- seek compensation for its own
claims against PennDot without including H&K’s claims. But H&K
now argues that when Balfour filed a complaint with the Board of
Claims without seeking such specific compensation for H&K’s
claims, Balfour (somehow) did something radically new. This
purportedly paved the way for H&K to file "a second lawsuit" that
H&K flat-footedly on September 5, 2007 told the Court of Appeals
was an impossibility.
These positions are irreconcilably inconsistent. H&K
argued before our Court of Appeals that it should be permitted to
appeal because Balfour would "never" legally be able to seek
compensation for H&K’s claims against it from PennDot. H&K now
argues before us that, precisely as it predicted to the Court of
-
20
Appeals, Balfour failed to seek compensation from PennDot for
H&K’s claims against it. H&K contends that it relied on
Balfour's representations to Judge Golden that it would present
its claims before PennDot, but H&K also then knew -- and indeed
on September 5, 2007 stressed to the Court of Appeals -- that
Balfour would "never" be able to assert those claims when H&K
argued that its appeal should be accepted. H&K cannot have it
both ways.
H&K also took two irreconcilably inconsistent positions
when it argued to our Court of Appeals that it would “never be
able to refile its complaint” but then -- after the case had
reposed on our Court of Appeals’s docket for well over a year and
the parties had been through the mandatory mediation process --
it on November 4, 2008 filed "a second complaint" in the Court of
Common Pleas of Montgomery County before bothering to voluntarily
dismiss its appeal. H&K's thrice-used “never” to the Court of
Appeals meant that there were no circumstances under which it
could refile "a second complaint." Filing such a complaint while
the appeal was still pending is far from “never”.
H&K also represented to the state court in its second
complaint -- almost a year to the day after Balfour filed its
amended complaint in the Board of Claims -- that its appeal to
our Court of Appeals had been dismissed, but it did not make any
attempt -- formal or informal -- to withdraw its appeal until
after it filed the second complaint. Compl. ¶ 32 (“H&K has
voluntarily dismissed both the Remanded Montgomery County Action
-
21
and the Third Circuit Appeal without prejudice”); Pl. MTD2 Resp.,
Ex. O. H&K has offered no explanation for why it took these
irreconcilably inconsistent positions, nor why it represented to
the Montgomery County Court of Common Pleas the untruth that its
appeal had been dismissed when it had not then even tried to
withdraw that appeal. Thus, we find that H&K took two
irreconcilably inconsistent positions, and H&K has not provided
an explanation to square them.
-
22
b. Bad Faith
Our Court of Appeals held that a rebuttable inference
of bad faith arises when averments in the pleadings demonstrate
both knowledge of a claim and a motive to conceal that claim in
the face of an affirmative duty to disclose. Oneida Motor
Freight, Inc. v. United Jersey Bank, 848 F.2d 414, 416-18 (3d
Cir. 1998). To determine whether H&K had knowledge of its claim
and a motive to conceal that claim, we must examine the timing of
H&K’s actions. In its September 5, 2007 letter to our Court of
Appeals, H&K argued that it would "never" be able to refile its
complaint because H&K would "never" be able to meet the condition
precedent as the District Court defined it. MTD1, Ex. 5 at 5
n.3. H&K did not include the caveat that it would be able to
refile if Balfour waived the condition precedent because it
doubtless knew that our Court of Appeals would likely not accept
jurisdiction if H&K had included such a disclaimer.
H&K represents that it was PennDot’s April 29, 2008
letter explaining that because Balfour had not presented H&K’s
claims to PennDot -- that is, the very reality H&K on September
5, 2007 predicted to the Court of Appeals that was the keystone
of its assertion of finality -- that led H&K to decide that its
appeal of Haines I was moot. Compl. ¶ 127. And yet it was not
until over six months later that H&K first informally attempted
to “withdraw” its appeal -- after it had availed itself of the
benefits of pressure on Balfour of a pending appeal, the Third
Circuit's mandatory mediation program and the obtaining of a
-
23
briefing schedule.
H&K argues that it did not burden the judicial system
because it moved to voluntarily dismiss its appeal before our
Court of Appeals’s jurisdiction ever attached. But after H&K
elected to stand on its complaint, our Court of Appeals (1)
elected not to summarily dismiss the appeal, (2) assigned a
court-appointed mediator who attempted to broker a settlement
between the parties, (3) entertained and ruled on motions, and
(4) at H&K’s September 25, 2008 request, issued a briefing
schedule directing the parties to brief the merits of H&K’s
appeal. MTD1, Ex. 6; Ex. 10; Pl. MTD2 Resp. at 6 n.6; Ex. K.
Notably, Our Court of Appeals issued a briefing
schedule on September 29, 2008 after receiving H&K's request four
days earlier to set that schedule. Pl. MTD2 Resp., Ex. K. H&K
filed its second complaint on November 4, 2008 in the Montgomery
County Court of Common Pleas and did not move to voluntarily
dismiss its appeal until December 17, 2008 -- two weeks after
Balfour had filed a motion to dismiss H&K’s appeal, and more than
a month after it had filed its second complaint with the Court of
Common Pleas.
Thus, we can only conclude that H&K was aware of its
“new” claim well before it requested the briefing schedule. But
it had the motive to conceal this claim in the hope of keeping
the appellate pressure on Balfour while taking advantage of the
Third Circuit's mandatory mediation program -- all well before it
formally moved to have its appeal voluntarily dismissed.
-
24
In addition, in the complaint that H&K filed on
November 4, 2008 in the Montgomery County Court of Common Pleas,
H&K represented to that court that “H&K has voluntarily dismissed
both the Remanded Montgomery County Action and the Third Circuit
Appeal without prejudice.” Compl. ¶ 32. But that simply was not
true. To the contrary, H&K's representation was “tantamount to a
knowing misrepresentation to or even fraud on the court”.
Krystal Cadillac, 337 F.3d at 324 (internal quotation marks
omitted).
H&K represented to the Montgomery County Court of
Common Pleas that it had dismissed its Third Circuit appeal when
in fact it had not even filed its motion to voluntarily dismiss
its claim, let alone given Balfour the chance to respond or our
Court of Appeals the chance to rule on it. As a result, Balfour
removed this second action to this Court, where Haines II has
reposed since November 24, 2008, and where H&K had the benefit of
Judge Golden’s judicial resources, including oral argument on
Balfour’s motion to dismiss. H&K filed its second complaint
while its appeal was still pending in our Court of Appeals,
sought the jurisdiction of the Court of Common Pleas of
Montgomery County before it was proper to do so, and thereby
forced Balfour to defend itself simultaneously in three courts --
Judge Golden's, the Court of Appeals, and the Common Pleas Court
-- for the same action.
In our view, once Judge Golden dismissed H&K's claims
without prejudice, H&K had three options. First, it could have
-
25
appealed, as it originally attempted to do, making the argument
that Balfour was by then time-barred from bringing H&K’s claims
to PennDot and that Balfour could not assert claims on its behalf
to the Board of Claims anyway. Second, H&K could have decided
that Balfour was not time-barred from asserting H&K's claims (and
had standing to bring them) and waited to refile its complaint
once Balfour had collected, or failed to collect, on H&K’s claims
from PennDot. Or, third, H&K could have decided that Balfour was
not time-barred from asserting its claims, but when it realized
that Balfour had “waived the condition precedent” by failing to
represent H&K’s claims (a new legal theory that H&K raises for
the first time in this action), it could have refiled its
complaint based on that alleged waiver.
For reasons known only to H&K’s counsel, H&K did not
view these options as mutually exclusive. Instead, H&K tried to
play all the legal notes at once. In doing so, H&K affirmatively
misrepresented its procedural position and its claims to the
Court of Common Pleas of Montgomery County, to our Court of
Appeals, and to Judge Golden.
H&K’s ill-conceived strategy cost both sides money,
wasted scarce judicial resources in both the federal and state
court systems, and abused the Third Circuit's mandatory mediation
process and that Court itself. Regrettably, we can only conclude
that this was and is an “affront to the court’s authority or
integrity.” Henderson v. Chartiers Valley School, 136 F. App’x
-
8 Our Court of Appeals has noted that “a party has notdisplayed bad faith for judicial estoppel purposes if the initialclaim was never accepted or adopted by a court or agency.” DamThings from Denmark v. Russ Berrie & Co., Inc. , 290 F.3d 548, 559n.16 (3d Cir. 2002) (quoting Montrose Med. Group ParticipatingSav. Plan v. Bulger, 243 F.3d 773, 778 (3d Cir. 2001)). Here,although our Court of Appeals had not yet adopted H&K’s claimthat Judge Golden’s July 27, 2007 Order was a final judgment, theThird Circuit’s mandatory mediation program certainly had toaccept H&K’s claim to conduct the mediation. And although H&Kknew about the “changed facts” -- such as they were -- ever sincePennDot’s April 29, 2008 letter, it still pushed the Court ofAppeals for a scheduling order on September 25, 2008 after themediation failed. This was tantamount to affirmativemisrepresentation because H&K had all the information it neededto seek to voluntarily dismiss its appeal, and yet instead itcontinued to engage our Court of Appeals’s resources for severalmore months. H&K correctly notes that our Court of Appeals hasheld that there is an exception to the general concept ofjudicial estoppel regarding jurisdictional facts or positions;courts generally refuse to resort to the principles of judicialestoppel to prevent a party from “switching sides on the issue ofjurisdiction.” Whiting v. Krassner, 391 F.3d 540, 544 (3d Cir.2004) (internal quotation marks omitted). But here H&K did notjust “switch sides” on the jurisdictional issue. H&K alsodetermined that it had a new claim that it believed rendered itsappeal moot, but it concealed this from our Court of Appeals formonths until it had availed itself of the Third Circuit mandatorymediation program and sought and obtained a briefing schedule.
26
456, 460 n.4 (3d Cir. 2005) (internal quotation marks omitted). 8
Thus, we find that H&K played fast and loose with the courts --
with as many tribunals as it could, in fact -- and acted in bad
faith.
c. No Lesser Sanction
As our Court of Appeals has noted, “[t]he fact that a
sanction is to be used sparingly does not mean that it is not to
be used when appropriate.” Krystal Cadillac, 337 F.3d at 325.
To employ judicial estoppel, we must find that it is tailored to
address the harm identified and that no lesser sanction would
-
9 Indeed, H&K devoted five pages of its response to thatmotion to judicial estoppel, see Pl. MTD1 Resp. at 18-23.
27
adequately remedy the damage done by H&K’s misconduct. Here, any
lesser sanction -- such as, for example, ordering H&K to pay all
of Balfour's legal fees and costs associated with its multi-forum
folly -- would still reward H&K for duplicitous conduct in the
course of its appeals process. More seriously, it would not
compensate the three courts for their waste of scarce judicial
resources. To allow H&K to continue to press its claims in
Haines II would perpetuate an injustice and would compromise the
integrity of the state and federal judicial systems. Thus, we
find that judicial estoppel is the only adequate sanction under
these extreme circumstances.
d. Opportunity to Explain
Finally, equity requires that we give the party to be
estopped a meaningful opportunity to provide an explanation for
its changed positions. Id. at 320. But here, H&K has had not
one, but two opportunities to address the issue of judicial
estoppel, once before Judge Golden -- when Balfour raised the
issue in its original motion to dismiss 9 and Judge Golden
afforded oral argument on that motion -- and once before us. In
addition, most of the pertinent facts are taken from court
records, and H&K itself supplied the rest. Thus, we find that
H&K has had fair opportunities to argue that the doctrine does
not apply, and has failed to present persuasive arguments on that
-
subject.
Conclusion
We therefore hold that H&K is judicially estopped from
retreating from its unqualified representation to the Court of
Appeals that Judge Golden's July 27, 2007 Order "eliminates the
possibility of a second lawsuit" and therefore grant Balfour's
motion to dismiss the second lawsuit H&K filed. Because we have
granted Balfour’s motion to dismiss Haines II pursuant to Fed. R.
Civ. P. 12(b)(6), we need not address Balfour’s Fed. R. Civ. P.
12(b)(7) contentions.
BY THE COURT:
__\s\Stewart Dalzell
IN THE UNITED STATES DISTRICT COURT FOR THE EASTERN DISTRICT OF PENNSYLVANIA
HAINES & KIBBLEHOUSE, INC. : CIVIL ACTION:
v. ::
BALFOUR BEATTY CONSTRUCTION, :INC. : NO. 08-5505
ORDER
-
29
AND NOW, this 1st day of June, 2011, upon consideration of
defendant’s amended motion to dismiss (docket entry # 29),
plaintiff’s response thereto (docket entry # 32), and
defendant’s reply (docket entry # 35), and each brief’s
exhibits, and in accordance with the accompanying Memorandum, it
is hereby ORDERED that:
1. Defendant’s motion to dismiss (docket entry # 29) is
GRANTED;
2. Plaintiff’s complaint is DISMISSED WITH PREJUDICE; and
3. The Clerk of Court shall CLOSE this case
statistically.
BY THE COURT:
__\s\Stewart Dalzell