indiana university data center
TRANSCRIPT
Presented by:
Bill Ash, AIA LEED APAssociate SmithGroup
Stacy Kukelhan, PEProject ManagerEYP Mission Critical Facilities
Indiana University Data CenterCase Study
Session 2Tuesday, September 16, 2008San Jose, California
Labs21DataCenters21
Through a case study of the Indiana University Data Center, participants will gain knowledge of sustainability and energy efficiency strategies as they apply to the design of data centers.
Learning Objectives
• 1998 IT Strategic Plan, UITS• Desktop computing, networking, email• 2006 Acquired IBM e1350 Blade Center Cluster (Big Red)
Life SciencesAstronomyInformaticsComputational PhysicsHumanities
National Science FoundationNational Institutes of HealthNational Endowment for the Humanities
IU Information Technology
Location IU Bloomington
Historic Campus Core
Greenways,QuadsJordan River
Planned Technology PrecinctOld High School BldgsRecreational Fields
Location Technology Precinct
Technology Precinct Master Plan
Data Center SiteWrubel Computing Center(Existing Home, Information Technology)
• Build on disturbed land.• Increase density• Working landscape• Pedestrian circulation
Planning Right-Sizing
Fitting the building on its site
Wrubel Computing Center(Existing Home, Information Technology) Data Center Site
• Build only what you need• Site Constraints
Existing Chiller BuildingData Center Growth
NEW EXISTING
Planning Right-Sizing
Fitting the building on its site
Wrubel Computing Center(Existing Home, Information Technology) Data Center Site
Phased Master Plan, Site for data center shoe-horned between 2 buildings and an existing chiller plant. Logistics of chiller plant serving existing data ctr.
But allow for growth. Delicate balance of tier level mix, area demands and budget.
Existing Chiller BuildingData Center Growth
NEW EXISTING
• Build only what you need• Site Constraints• Other Variables
Whether equipment is located indoors or outdoorsFault tolerance (Tier 4)Concurrent maintainability (Tier 3)Sophistication of monitoring and security systemsFinal UPS design topologyFinal cooling topology Availability of long-lead equipment itemsChanging equipment and materials costs (e.g., cost of copper)Other spaces, such as administrative, storage, NOC, etc. Site workResistance to natural disasters
Building Organization A House for MachinesLess than 4% of the building normally occupied by people
Berms | Landscaping• Berm on all sides & trees protect and shade• Native & drought-resistant grasses• Recycled site waste
Building Components
Cast-in-place Concrete Shell• 9,000 cubic yards of concrete cast on site• Concrete as sustainable material
Longevity/DurabilityThermal MassResource availabilityRecycled contentRegional ProductionMinimal waste
Building Components
Precast Concrete Cladding• More economical than stone• Regional Production
Building Components
Wells Library Limestone Loose-laid limestone site walls
Day 1 Protected Membrane Future Phase – Extensive System
Phasable Green Roof• Cost $9 - $15 / sf• Benefits
City IncentivesReduce RunoffRemaining Runoff delayed, cleaned, cooledEnergy Savings Roof LifeAestheticsAcousticsImproved Air QualityReduce Heat Island EffectHabitat Preservation | Biodiversity
Building Components
Interior Environment• Flexibility of space• Bamboo wall cladding• Exposed concrete & cmu, low voc paints & stains
Building Components
Approaches to Electrical Systems Organization & Efficiencies
• Equipment proximity to load • Locate PDUs as close to RPP as possible – minimize 208 V feeder lengths• Locate medium voltage transformers in UPS room
• Consider 575V critical power distribution in lieu of 480V• Calculated savings of $75,000 energy savings per year for
1.5 MW critical power system (at 6 cents per KWH)• Evaluate UPS technologies
• Varying costs, efficiencies and backup capabilities
UPS Technologies
Technology / Manufacturer Ride Thru Time EfficiencyCost Relative toStatic On-Line Unit
Static On-Line UPS with Battery / Powerware, Liebert, MGE
As Required, Usually10-15 Minutes
92-94% 100%
Flywheel UPS /Active Power, Pentadyne, Piller 12-30 Seconds 94-97% 70%
Static Off-Line UPS with Battery /S&C 60 Seconds 98-99% 60%
UPS Technologies
Rotary Units Advantages• Supports Tier 3 Enterprise Data Center• Low Install Base• Less than 2% Distortion• Higher Operating Efficiency• No major battery maintenance• Critical Load Ride Through Time – 20 seconds for generator startup• Reduced ventilation requirements
Online Static UPS Units Disadvantages• Higher level of distortion• Requirement for battery space• Requirement for battery maintenance• Performance affected by fluctuating loads• Lower operating efficiency• No major battery maintenance
UPS Technologies Rotary UPS
Approaches to Mechanical Systems Efficiencies & ReliabilityEnergy Efficiency – governed primarily by system selection• Chilled water systems (water cooled) – 0.5-0.7kW (annualized) per kW of UPS. • Chilled water systems (air cooled) – 1.0-1.4kW per kW of UPS• Direct expansion systems (air cooled) – 1.5-2.0kW per kW of UPS
Energy Efficiency – Other Design Considerations• Water Side Economizer• Air Side Economizer • VFD’s on Mechanical Equipment• Hot Water Heating
Reliability – governed primarily by system architecture• N+1, N+2, 2N, etc• Single or dual path piping systems • Requirement for make-up water• Is there an uninterruptible cooling requirement to support high density cooling?
Water Side Economizer
• Uses cold condenser water to generate chilled water• Minimize or eliminate the requirement to operate the chillers when the ambient conditions permit• The cooling tower fans and pumps generated the cold condenser water• Energy savings dependent upon wet-bulb (moisture content of air)• Regions with lower wet-bulb are necessary• Usable Economizer Hours, Bloomington, IN – Approximately 1700 hours a year• Higher design chilled water temperature (above conventional 45F) extends use of economizer
CHILLER
PUMP
EXCHANGERHEAT
CHILLED WATER RETURN
CHILLED WATER SUPPLY
CONTROLVALVE
Water Side Economizer
Alternate Plant descriptionPlant Annualenergy cost Differential Percentage
No economizer 2200 ton load $760,000.00 Base BaseParallel economizer 2200 ton load $639,000.00 $121,000.00 84%Series economizer 2200 ton load $518,000.00 $242,000.00 68%
Note: Data based on $0.06/kWh
Indiana University Design – Parallel Economizer
Water Side Economizer
Indiana University Payback Period ~ 5 years.
Air Side Economizer
• Uses outside air to directly cool support equipment rooms• Energy savings dependent on dry-bulb (thermometer temperature) and wet-bulb (moisture
content of air) temperature – enthalpy control• Need to control supply air temperature to produce optimal dry-bulb and moisture content – don’t
want air too dry• Equipment requirement for Data Center to operate in 40 to 55% RH range significantly reduces
available hours
Questions?