injection and dump system
DESCRIPTION
Injection and Dump System . W. Bartmann, M.J. Barnes, C. Bracco , E. Carlier, B. Goddard, V. Kain, M. Meddahi, V. Mertens, J. Uythoven, L. Drosdal . Outline. LBDS: 2010/2011 performance TCDQ induced beam dumps and HW problems Injection System: 2010/2011 performance MKI problems: - PowerPoint PPT PresentationTRANSCRIPT
Injection and Dump System
W. Bartmann, M.J. Barnes, C. Bracco, E. Carlier, B. Goddard, V. Kain, M. Meddahi, V. Mertens, J. Uythoven, L. Drosdal
LHC Beam Operation Workshop
Outline LBDS:
2010/2011 performance TCDQ induced beam dumps and HW problems
Injection System: 2010/2011 performance MKI problems:
Flashover Erratic Vacuum Temperature
Other observations XPOC IQC Summary
Evian, 12/12/2011
LHC Beam Operation Workshop
2010 LBDS
Evian, 12/12/2011
Asynchronous beam dump, during energy scan without beam (due to spark on the outside of the gate turn-off GTO thyristor): 1 at 5 TeV 2 at 7 TeV
5 internal triggers: 1 due to BETS and 4 due to vacuum interlocks on the MKB for B2 (FALSE vacuum pressure reading)
1 Asynchronous beam dump with beam: Failure of a single power driver in one Trigger Fan-Out unit (TFO) LBDS self-
triggering of two generators for Beam 1: MKD C and D IPOC fault and XPOC fault
Subsequent retriggering of remaining 13 generators worked perfectly
2 beam dumps induced by TCDQ faults: timing event sent TCDQ and thresholds to 3.5 TeV setting (< 4 s at 450 GeV)
beam then was injected and dumped due to losses in point 6. beam 1 dumped due to a glitch in position readings (resolver read injection
values) at end of ramp (out of thresholds).
Evian 2010
LHC Beam Operation Workshop
2011 LBDS
Evian, 12/12/2011
No asynchronous beam dump 7 internal triggers with beam (BETS, PLC, vacuum pump off in
the dump line …) Internal triggers without beam due to:
TSU new firmware back to 2010 version PXI failures N.I. digitizer fuses replaced on all boards GTO switches
10 Beam dumps induced by TCDQ: Retraction TCSG/TCDQ SIS interlock (90 m b* ALPHA roman pots
setup, tight collimators settings) TCDQ at wrong position when injecting pilot (after previous test to check
TCDQ offset) SIS interlock on beam position at TCDQ during ramp and at flattop 2 energy interlocks at the beginning of the ramp (glitch in energy limit)
relaxed limits Position interlock at the end of the ramp (server problem)
BPMS interlock still reading wrong number of bunches, HW interlock based on another signal so we can leave with that
Mainly during ramp down, 2-3 h access required
LHC Beam Operation Workshop
Other problems with TCDQ
Evian, 12/12/2011
Problems with running TCDQ sequence, loading settings and thresholds generally solved repeating sequence and/or running ramp (in some cases the beam had to be dumped)
Mechanical offset: Measured on 10/03/2011 and compensated by adding:
B1: -0.25 mm for all settings B2: +0.5 mm at 3.5 TeV setting and +1 mm at 450 GeV
B2 TCDQ offset “Corrected” during TS previously defined settings non more valid TCDQ offset put back but in the wrong direction offset had to be re-measured (2 hours) new settings B2: -0.6 mm for all settings
10/03/2011 13/07/2011
LHC Beam Operation Workshop
2010 Injection System
Evian, 12/12/2011
Chamonix 2011
Abort Gap Keeper (AGK) prevented MKI from firing Train of 32 bunches dumped on upper TDI jaw showers to ALICE
Losses in ALICE in agreement with simulations (further benchmarking data from TDI grazing tests) ALICE ready for 288 bunches on TDI
LHCb, only grazing tests with TDI No indication of limits on
injected intensity: 288 bunches OK! BUT TDI must be correctly set up!!
LHC Beam Operation Workshop
MKI Flashover 18/04/2011
Evian, 12/12/2011
Injection of 2 × 36 bunches spaced by 2.2 ms Breakdown after ~2 ms All 36b of 2nd batch were kicked with 110-125% nominal MKI deflection
Beam was on LOWER TDI jaw and over-kicked, i.e. breakdown in second half of magnet (LHCb signals support this)
Nearly all p+ of the 36b impacted on the TDI/TCLIB (grazing) 11 magnets quenched
B1 1
2bB2
12b
B1 7
2bB2
72b
B1 7
2bB2
72b
B1 7
2bB2
72b
B1 is causing the vacuum pressure rise in the B2 kicker – this is not new
MKI HW vacuum interlock reduced from 5e-8 mbar to 2e-8 mbar
New SIS to prevent injection if MKI pressure >2e-9 mbar for 50 ns beam (temporary >2.5e-9 mbar for scrubbing with 25 ns beam)
Checked carefully TDI angular alignments in IR2 and IR8
TCLI openings TCLIB to 8.3 s New Fixed Display in CCC with MKI pressures Solenoids between MKI and Q4/A5 switched ON
ALICE Polarity
B1 left [mrad]
B1 right [mrad]
B2 left [mrad]
B2 right [mrad]
Old -70 -750 -190 -110New +86 -1035 -190 -110
LHC Beam Operation Workshop
MKI Vacuum Activity
Evian, 12/12/2011
To avoid possible vacuum/breakdown problems with the MKIs, solenoids:
ON during normal operation OFF during scrubbing provided pressure
does not become too high (respect SIS injection interlock)
In future, possible to include a interlock (under study)
Solenoid switched off
Intensity
EnergyVacuum in IR2 Energy
Intensity
Vacuum in IR8
Vacuum MKI Beam 1
Vacuum MKI Beam 2
M.J. Barnes
dtP
2E-9
2E-9
LHC Beam Operation Workshop
MKI Erratics on 28/7/2011
Evian, 12/12/2011
4.5µs
2µs
MSC erratic
Current in kicker magnet
0
5000
10000
15000
20000
25000
30000
35000
40000
45000
50000
55000
Appr
ox P
FN V
olta
ge
Sample Number
MKI2. 28 July 2011, 6:03:09 PM
7/28/2011 6:03:09 PM PFN1
7/28/2011 6:03:09 PM PFN2
7/28/2011 6:03:09 PM PFN3
7/28/2011 6:03:09 PM PFN4
Erratic turn-on of MKI2 MSC
16:30:43
18:03:09
Interlocks detected an MSC erratic and correctly triggered MS’s and DS’s of system (within 2µs), emptying PFN via both ends. Hence kicker-C pulsed for 6.5ms and 3 other kicker magnets pulsed for up to 4.5µs, emptying PFNs of energy. Circulating beam was not in IP2 and therefore not disturbed. Batch was extracted from SPS but saw no kick at MKI2 (current already back to zero in all magnets) and went straight into the TDI upper jaw.
Erratic of MKI2 MSC at 33kV during resonant charging – sending current to one of the four kicker magnets Interlocks did NOT detect erratic of MS3: hence no immediate action was taken to turn-on other thyratrons full 9 ms PFN pulse length to kicker C. Failure ~500µs into charging process: extraction from SPS correctly inhibited;Circulating beam was swept over aperture and grazed TDI (~17% of normal kick) for ~8-9µs 150-190 bunches
LHC Beam Operation Workshop
MKI Erratics on 28/7/2011
Evian, 12/12/2011
4.5µs
2µs
Current in kicker magnet
0
5000
10000
15000
20000
25000
30000
35000
40000
45000
50000
55000
Appr
ox P
FN V
olta
ge
Sample Number
MKI2. 28 July 2011, 6:03:09 PM
7/28/2011 6:03:09 PM PFN1
7/28/2011 6:03:09 PM PFN2
7/28/2011 6:03:09 PM PFN3
7/28/2011 6:03:09 PM PFN4
Erratic turn-on of MKI2 MSC
16:30:43
18:03:09
Interlocks detected an MSC erratic and correctly triggered MS’s and DS’s of system (within 2µs), emptying PFN via both ends. Hence kicker-C pulsed for 6.5ms and 3 other kicker magnets pulsed for up to 4.5µs, emptying PFNs of energy. Circulating beam was not in IP2 and therefore not disturbed. Batch was extracted from SPS but saw no kick at MKI2 (current already back to zero in all magnets) and went straight into the TDI upper jaw.
Erratic of MKI2 MSC at 33kV during resonant charging – sending current to one of the four kicker magnets Interlocks did NOT detect erratic of MS3: hence no immediate action was taken to turn-on other thyratrons full 9 ms PFN pulse length to kicker C. Failure ~500µs into charging process: extraction from SPS correctly inhibited;Circulating beam was swept over aperture and grazed TDI (~17% of normal kick) for ~8-9µs 150-190 bunches
Hardware problem faulty
components exchanged +
additional diagnostic + faster
detection electronics with
lower voltage threshold
MSC erratic
LHC Beam Operation Workshop
MKI Erratic Effects
Evian, 12/12/2011
173 bunches - 2.15e13 p+ lost (not dumped) 3 magnets quenched ALICE:
The values of BCM threshold for beam background were exceeded: 16:30 - 80 times 18:03 - 3559 times
9 /17 sub-detectors were affected during second erratic event All subsystems except Silicon Drift Detector (SDD) recovered using standard
procedures 20% of modules with good drift speed from injector on layer 3 and 60% on layer
4 (permanent effect)intensity and #bunches will still increase
(slightly) worse impact parameter possible
Up to a factor of 2-4 higher losses might occur in future years!OK for machine, but main concern is safety for ALICE/LHCb.
Detectors must be off during injection! M.Lechman
LHC Beam Operation Workshop
0
0.5
1
1.5
2
2.5
3
3.5
4
85 90 95 100 105 110 115 120 125 130 135 140 145
Indu
ctan
ce (μ
H)
Average of Magnet Input Face and Output Face Temperature During Cool down (˚C)
33 cells * 101nH/cell
106˚C
Magnet in vacuum tank; tank at atmospheric pressure; no bake-out jacket.
MKI Temperature Interlock
Evian, 12/12/2011
Ferrite Heating Measurements in Clean Room:Curie point of ferrite corresponds to 106 ˚C measured on ground plates
M.J. Barnes
y = 7.39E-10x + 2.04E-07R² = 9.98E-01
y = 3.79E-09x + 3.25E-07R² = 1.00E+00
6.00E-07
6.10E-07
6.20E-07
6.30E-07
6.40E-07
6.50E-07
6.60E-07
6.70E-07
6.80E-07
6.90E-07
7.00E-07
7.10E-07
2.580E-07
2.600E-07
2.620E-07
2.640E-07
2.660E-07
2.680E-07
2.700E-07
2.720E-07
2.740E-07
2.760E-07
2.780E-07
2.800E-0775 77.5
80 82.5
85 87.5
90 92.5
95 97.5
100
50%
Del
ay (s
)
TMR
Volta
ge R
ise T
ime
(s)
Magnet Inductance Scale Value (%)
Predicted 5% to 95% rise-time versus magnet Inductance
RISE_TIMEC(V(MagOut)*50kV/250,1.25k,23.75kV)
XVALUE_AT_YV(V(MagOut)*50k/250,12.5k)-XVALUE_AT_YV(V(MagIn)*50k/250,12.5k)
Magnet inductance decreases with reducing ferrite permeability magnet strength decrease Rise-time decreases with reducing inductance and/or capacitance Delay decreases with reducing inductance and/or capacitance
Softstart measure rise-time indirect measurement of inductance (temperature)
During Xmas stop: new diagnostic to measure delay (more sensitive)
LHC Beam Operation Workshop
MKI Temperature Interlock
Evian, 12/12/2011
y = -1.325E-05x + 7.069E-01R² = 1.501E-02
y = -7.324E-05x + 7.041E-01R² = 7.792E-01
y = -2.065E-05x + 6.970E-01R² = 3.514E-01
y = -3.563E-05x + 7.004E-01R² = 8.375E-01
y = -2.828E-04x + 7.153E-01R² = 6.809E-01
0.695
0.696
0.697
0.698
0.699
0.7
0.701
0.702
0.703
0.704
0.705
0.706
0.707
0.708
0.709
20.00 25.00 30.00 35.00 40.00 45.00 50.00 55.00 60.00 65.00 70.00Ri
se T
ime
(µs)
MKI8 Measured Temperature (˚C)
MKI.UA87.IPOC.?B2:T_RISETIME (October 2011)
MKI.UA87.IPOC.AB2:T_RISETIME
MKI.UA87.IPOC.BB2:T_RISETIME
MKI.UA87.IPOC.CB2:T_RISETIME
MKI.UA87.IPOC.DB2:T_RISETIME
SIS interlock presently 62 ˚C (originally 55 ˚C ) cannot be further increased !MKI Temperature is < 68 ˚C and lags real temperature (ferrite thermal capacity) Softstart: OK injection
not Ok wait for MKI cooling
M.J. Barnes
Capacitance Inductance
LHC Beam Operation Workshop
Other Problems Related to Injection System
Evian, 12/12/2011
UFOs at MKI several beam dumps at the beginning of the run (T. Baer’s talk) Problems with kicker delay (ions run) Beam on TDI (32 and 144 bunches) due to operational error (AGK inhibited MKI
from pulsing as it should) Vacuum pressure increase at TDI in IR2 and IR8 when at parking position (±20
mm) High background in ALICE (shielding?) new parking position ±55 mm (B. Salvant’s talk)
TDI.4L2 controls problem: required setting different from
measured motor position Noise in the measurement of jaw
positions gap opening outside limits TDI.4L2 gap interlocks changed by 100mm to avoid interlocks due to drift of the position reading triggered by electromagnetic noise
Wrong settings of injection protection collimators (TCDI, TCLI and TDI): Association with “bad” beam process (during MD) Solution: injection protection collimators on an independent beam process
S. Redaelli
LHC Beam Operation Workshop
XPOC
Evian, 12/12/2011
Encountered problems Data missing (BLM, BCT, BSRA, Vacuum) Wrong filling patterns and faults on MKB waveforms
new release and filters to reduce noise due to high bunch intensities (not completely solved)
Problems with inject and dump (late BLM data) new BIS interface card installed
Acknowledgment logic: EIC-MPS can reset errors in Context and BLM modules LBDS-EXPERT can reset all modules. No evident reason to change it in 2012!
LHC Beam Operation Workshop
IQC
Evian, 12/12/2011
New features: Injection oscillations max/rms vs bunch number; Playback: actual or of the date reference thresholds
LHC Beam Operation Workshop
IQC
Evian, 12/12/2011
New features: Injection oscillations max/rms vs bunch number; Playback: actual or of the date reference thresholds
Problems: Injection of 144 bunches not seen by the IQC and the injection
sequencer danger of overinjection (server communication problem?)
Missing MKI data and BCT from TL
Acknowledgment and Improvements: Phase error integration Limits at TL BPM (MD to define them) easier steering Clear warning level at critical BLMs depending on number of bunches
injected (i.e. MSI ≥ 5% with 12 bunches steering needed ) Injection oscillations interlock still maskable in 2012?
LHC Beam Operation Workshop
Summary 1/2
Evian, 12/12/2011
Equipment Problems in 2011 Applied Solution 2012 Operation
LBDS Internal triggers Electronics, faulty components exchanged
Ok, new power supplies. Testing time during machine checkout for new HW/SW/FW
No async. dump Ok
TCDQ Load thresholds/settings, energy limits and position interlocks
Repeat sequence Ok, b* interlock +new potentiometer electronic more precise position reading
Mechanical Offset Compensation with beam based alignment
Ok
MKI Flashover
SIS interlock to inhibit injection in case of vacuum exceeding thresholds
Ok if injection protection collimators correctly set up and detectors off during injection
Erratic Faulty components replaced + diagnostic + faster electronics with lower voltage threshold
Ok if injection protection collimators correctly set up and detectors off during injection
Temperature SIS at 62°C + softstart to measure rise-time (inductance)
Ok if T does not increase further since close to Curie limit.New diagnostic to measure delay
Vacuum HW interlock + MKI cond.+ e-cloud solenoids
Ok but waiting time between injections, conditioning (25 ns more critical)
LHC Beam Operation Workshop
Summary 2/2
Evian, 12/12/2011
Equipment Problems in 2011 Applied Solution 2012 Operation
TDI Angular offset Compensation with beam based alignment
Ok
Vacuum and ALICE background
Parking position to ±55mm
Ok
Controls (LVDT noise) Relaxed gap interlock Ok, if noise not worse
TDI/TCLI/TCDI Association to “bad” beam process wrong position
Not Ok, Separate beam process needed
XPOC Missing data, faults New release, filters, cards….
Ok, stronger filters + BI data collection improvements (directly into PM system)
IQC Missing data, injection not detected
New release Ok but needs to become clearer (closer to operation, easier steering). Risk of 144 bunches overinjeciton must be eliminated
Ready for 2012 operation but: Dedicate enough time w/wo beam to properly test components (new electronics, SW, FW....) and set up (collimators, IQC references for steering...) Respect safety instructions (Experiments off during injection, MKI vacuum and temperature interlocks)
Safe operation and reduce downtime!!!
Backup
LHC Beam Operation Workshop
TCDQ Upgrade (LS1)
Evian, 12/12/2011
Upgrades for IR6 dump protection TCDQ upgrade for robustness: graded Carbon Composite (1.4g/cc and
1.65 g/cc), absorber length 6m -> 9m (1 more module) TCDQ controls: collimation stepping motor system and low-level (to be
decided) New improved TCDQ bellows TCSG with BPM buttons Additional TCLA – to be decided after FLUKA studies Phase advance MKD-TCDQ exactly 90° to reduce # of escaping particles
rematch the optics (R. Bruce’s talk)
T. Kramer
LHC Beam Operation Workshop
Two More Erratics…….
Evian, 12/12/2011
16:30:43Two more erratics happened during softstart on 30/07/2011
Hardware problem Actions:
• Replaced MS3– damaged current regulator on bias board • Remote current monitoring added• New G1 trigger cards installed• Damaged thyratron switch replaced• Fiber optic read-back to better monitor thyratron and bias-board G1 current ??
Diagnostics added
Power supply and crate for MS3 heater/reservoir replaced.
Trigger units for MS3 replaced.