IBL 15 May 2012 J.Godlewski PH-DT-PO 1 Insertable B Layer Cooling System Services Jan Godlewski Bart Verlaat

Upload: elu

Post on 12-Jan-2016

30 views

Category:

Documents


0 download

DESCRIPTION

Insertable B Layer Cooling System Services. Jan Godlewski Bart Verlaat. Power supply Water cooling Compressed air Vacuum IBL flushing. Power supply. Total need of power for IBL cooling station has been estimated to 20 kW This include: Chiller compressor Heaters - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Insertable  B Layer Cooling System Services

IBL 15 May 2012 J.Godlewski PH-DT-PO 1

Insertable B Layer Cooling System

Services

Jan Godlewski

Bart Verlaat

Page 2: Insertable  B Layer Cooling System Services

Power supply Water cooling Compressed air Vacuum IBL flushing

IBL 15 May 2012 J.Godlewski PH-DT-PO 2

Page 3: Insertable  B Layer Cooling System Services

Power supply Total need of power for IBL cooling station has been estimated

to 20 kW This include:

Chiller compressor Heaters Electrical and control system components

We will ask for UPS for IBL cooling system Statement from Wieslaw Iwanski:

Atlas has enough reserve in existing UPS to feed the 20 kW pump of the IBL cooling system. However, there is no actually possibility to connect such a circuit to existing UPS distribution as all available breakers in UPS switchboards in USA15 are already in use. Atlas will therefore order and install during the LS1 a new switchboard fed from the UPS network in USA15 to address this situation.

It’s assumed that this switchboard will provide a standard monitoring of all breakers i.e. ‘on/off’  and ‘electrical fault’ sensors without possibility to turn on/off breakers by external systems

IBL 15 May 2012 J.Godlewski PH-DT-PO 3

Page 4: Insertable  B Layer Cooling System Services

Nitrogen flushing from gas room in USA15

IBL 15 May 2012 J.Godlewski PH-DT-PO 4

Page 5: Insertable  B Layer Cooling System Services

IBL nitrogen flushing

IBL will be flushed with nitrogen using existing system in USA15 gas room

PH/DT Gas group will take care about additional equipment and modification in the ID flushing rack

Goal is to reach dew point in IBL volume below -60 C ATLAS TC will install copper pipe between ID rack in USA15

gas room and IBL volume 8 mm OD copper pipe

IBL 15 May 2012 J.Godlewski PH-DT-PO 5

Page 6: Insertable  B Layer Cooling System Services

Mixed water for the chiller

Chiller for IBL cooling station will have water cooled condenser

Amount of water is around 20 l/min Close to proposed cooling unit location there exist piping for

primary, mixed and chilled water Necessary amount of water will be taken from mixed or primary

water circuit

IBL 15 May 2012 J.Godlewski PH-DT-PO 6

Chiller

Water cooled condenser

Page 7: Insertable  B Layer Cooling System Services

Vacuum and compressed air

Vacuum pump for vacuum insulated transfer lines will be installed in UX15 on HS level 7.

Compressed air for CO2 cooling units will be delivered from evaporative system air compressors situated in USA15 CV room.

IBL 15 May 2012 J.Godlewski PH-DT-PO 7