inspection and validation activities on severe accident
TRANSCRIPT
Inspection and Validation Activities on
Severe Accident Management in Korea
after the Fukushima Accident
Han-Chul Kim*, Jung-Jae Lee, Sung-Han Lee
Korea Institute of Nuclear Safety (*E-mail: [email protected])
IAEA IEM on Severe Accident Management in the Light
of the Accident at the Fukushima Daiichi N.P.P.
17-21 March 2014, Vienna, Austria
2
Outline
1. Introduction
2. Special Safety Inspection for Operating Plants in Korea
3. External Cooling Water Injection
4. Confirmatory Analysis of External Cooling Water
Injection
5. Conclusions
Korea Institute of Nuclear Safety
3
Introduction
Injection flow paths for emergency cooling water is being installed
at the Korean NPPs following the Government order.
It was recommended through the Special Safety Inspection
The objective is to provide cooling water from external
sources to the primary and secondary loops during a
prolonged station blackout accident.
The effectiveness of this strategy needs to be confirmed through
evaluation of the installed system and on-site verification.
This presentation shows the background of this installation and the
relevant confirmatory analysis results for APR1400.
Korea Institute of Nuclear Safety
4
Operation
Construction
Planning
23 Units
5 Units
6 Units
20,716MW
6,600MW
8,400MW
Operation :
6 units
Operation : 6 units
Construction : 2 units
Planning : 2 units
Operation : 5 units
Construction : 1 units
Operation : 6 units
Construction : 2 units
Planning : 4 units
Seoul
Hanbit NPPs
(PWR)
Kori/Shin-Kori NPPs
(PWR)
Wolsong/Shin-Wolsong NPPs
(PHWR/PWR)
Hanul/Shin-Hanul NPP
(PWR)
Introduction Status of Nuclear Power Plants in Korea
Korea Institute of Nuclear Safety
5
Special Safety Inspection for Operating Plants in
Korea
A Special Safety Inspection (SSI) was conducted by the Government.
Seventy-three inspectors from the regulatory organizations,
research institutes, universities, etc. undertook the mission.
The assumed scenario mirrored the Fukushima accident:
earthquake tsunami power loss extreme severe accident
They inspected 21 operating NPPs, a research reactor, and fuel
cycle facilities for 5 weeks.
• Site inspection: Mar.21 ~ Apr.15, 2011
• Review of findings: Apr.16 ~ Apr.30, 2011
Hearings for the residents of the nearby towns of NPPs were held
before and after the inspection.
Korea Institute of Nuclear Safety
6
Special Safety Inspection for Operating Plants in
Korea
Major Inspection Points of SSI
Korea Institute of Nuclear Safety
Defense-In-Depth
Functions Major Inspection Points
Extreme Natural
Hazards
Adequacy of the plant design and facilities against natural hazards
- Design against earthquake and seismic capacity
- Design against coastal flooding and inundation protection capability
Prevention of
Severe Accidents
Adequacy of power supply and cooling functions
- Power system and emergency power supply
- Cooling capability in case of station blackout and inundation
Mitigation of
Severe Accidents
Adequacy of countermeasures against severe accidents
- Facilities, guidelines, and strategies against severe accidents
Emergency
Response
Adequacy of emergency response
- Emergency response to multi-units accidents
- Facilities, systems, and infrastructure for the protection of local
residents and workers
7
Special Safety Inspection for Operating Plants in
Korea
Inspection Results
Korean NPPs in operation have no imminent risk for the expected
maximum potential earthquake and coastal flooding, based on the
up-to-date investigation/research.
However, there are needs to implement the long and short-term
improvements in order to secure safety for beyond-design-basis
natural events
Korea Institute of Nuclear Safety
8
Special Safety Inspection for Operating Plants in
Korea
Major Safety Improvements for Korean NPPs
Korea Institute of Nuclear Safety
4
3
7
Containment
원자로용기
2
10m
Sea
이동형 발전차량
5 Drain Pump
6 Contro
l rod PZR
SG
Rx
Battery
EDG
Portable EDG
1
Securing the safety of emergency battery
power from flooding
Installing passive H2 removal systems
which operate without electricity [PAR]
1
2
3
4
5
6
Installing containment filtered vent or an
alternative depressurizing system
7
1 billion USD investment over 5 years
Improvements
Making the coastal barrier higher (Kori site)
Preparing a vehicle with a portable
emergency diesel generator at each site
Installing watertight doors at major buildings
Water-proofing drain pumps
9
Special Safety Inspection for Operating Plants in
Korea
On-going safety improvements concerning a severe accident
Korea Institute of Nuclear Safety
Category Improvements
Severe
Accident
Management
Guidelines Strengthening severe accident education and training
Revising severe accident management guidelines (SAMGs)
to enhance their effectiveness
Developing low-power and shutdown SAMGs
Equipment
and Facilities
Installation of injection flow paths for emergency cooling
water from external sources
Installation of passive hydrogen removal equipment (PAR)
Installation of filtered venting system (CFVS) or
depressurizing facilities in the containment building
10
External cooling water injection stratgegy
Korea Institute of Nuclear Safety
An additional line to provide emergency cooling water from
outside the reactor containment building to the reactor (A),
auxiliary feed tank (B), and steam generator (C) (KHNP plan)
Requirement:
Some alternative,
direct lineups to
inject emergency
water source to the
primary and
secondary loops
should be provided
as soon as possible.
External Cooling Water Injection
11 Korea Institute of Nuclear Safety
External cooling water for the primary system is injected into the
core through the shutdown cooling line.
Secondary system injection adopts two different ways:
Make up the exhausted auxiliary feedwater (AFW) storage tank
through a fire engine
Inject cooling water directly into the AFW discharge pipe through
a branch line using a fire engine
Injection is possible when RCS or steam generator secondary
pressure decreases below 15 kg/cm2 (1.47 MPa).
Minimum required injection flow rates were estimated by the utility.
Analysis of various accident scenarios including station blackout
using MAAP 4.06 showed that they could be achieved.
External Cooling Water Injection
12
Confirmatory Analysis of Ext. Cooling Water
Injection
Accident sequence considered: a SBO with external water injection
Korea Institute of Nuclear Safety
Time (sec) Event Remark
0.0
- Reactor Trip
- Stop to Supply MFW
- Start to Supply TDAFW
900.0 - RCP Seal Leakage Failure time
assumed
28800.0 - Stop to Supply TDAFW
30600.0 - ADV Manual Open 30 min. after AFWP
trip
Set point :
1st Pressure < 15 kg/cm2
- Injection into the primary
system
Pump performance
curve used
Set point :
2nd Pressure < 15 kg/cm2
- Injection into the secondary
system
Pump performance
curve used
13
Reactor core, primary and secondary system model
KINS has been developing a MELCOR model with the assistance of a contractor.
Korea Institute of Nuclear Safety
130 180
150
260
386 385 384 383
396 395 394 393
508
507 506 505 504 503
502
501
130
361
362363364
365
509
371
372373374
375
659
660
661
665
666
667
670
669
668
664
663
662
672
671
652 654 656
651 653 655
658
657
510
511
512
513
IRWST
S/G Compart.
673674
675675 676
Steam generator
secondary side Reactor coolant system
Core
Active Region
Lower Plenum
Reactor core
Confirmatory Analysis of Ext. Cooling Water
Injection
14
0 10 20 30 40 50
0
2
4
6
8
10
12
14
16
18
Pre
ssu
re (
MP
a)
Time (hrs)
Primary
Secondary
RCP Seal Leakage
ADV Manual Open
Secondary injection
Primary injection
P/p discharge pressure:
15kg/cm2
Preliminary result: Primary and secondary system pressure change
Korea Institute of Nuclear Safety
Confirmatory Analysis of Ext. Cooling Water
Injection
15
0 10 20 30 40 50
0.0
0.5
1.0
1.5
2.0
2.5
Ma
ss F
low
Ra
te (
kg
/s)
Time (hrs)
External-1st
0 10 20 30 40 50
0
2
4
6
8
10
12
14
16
Ma
ss F
low
Ra
te (
kg
/s)
Time (hrs)
External-2nd
Primary system injection at 19.2 hr Secondary system injection at 9.1 hr
Level control
Preliminary result: Primary and secondary injection flow rates
Korea Institute of Nuclear Safety
Confirmatory Analysis of Ext. Cooling Water
Injection
16
0 10 20 30 40 50
0
100
200
300
400
500
600
Te
mp
era
ture
(oC
)
Time (hrs)
CETSAMG entry condition
Preliminary result: Core exit temperature
Reactor core can be sufficiently cooled with an ADV open.
Further consideration will be given to the cooling rate, which is
higher than the operation limit, 55.6 ℃/h (100℉/h).
8.5 8.6 8.7 8.8 8.9 9.0 9.1 9.2 9.3 9.4 9.5
160
180
200
220
240
260
280
300
320
340
Te
mp
era
ture
(oC
)
Time (hrs)
Core Exit Temperature
Cooling Limit
Korea Institute of Nuclear Safety
Confirmatory Analysis of Ext. Cooling Water
Injection
17
Conclusions
Injection flow paths for external cooling water are being installed at
the Korean NPPs following a special safety inspection.
A best-estimate MELCOR analysis to check the effectiveness of
this strategy is being carried out.
The preliminary analysis results show that this strategy could
successfully cool the reactor core for a station blackout accident
through its effective implementation.
Korea Institute of Nuclear Safety
18
Acknowledgments
This work is based on the results from
the Nuclear Safety Research and Development program
of Nuclear Safety and Safeguard Commission.
Korea Institute of Nuclear Safety