installation issues steve virostek lawrence berkeley national lab mice cm23 at icst, harbin january...
Post on 19-Dec-2015
218 views
TRANSCRIPT
Installation Issues
Steve VirostekLawrence Berkeley National Lab
MICE CM23 at ICST, Harbin
January 13, 2009
MICE Installation Issues – MICE CM23 at ICST, Harbin, China
Page 2Steve Virostek - Lawrence Berkeley National Lab - January 13, 2009
Topic Summary
•Packaging and delivery to RAL
•Moving of modules into MICE hall
•Assembly work in MICE hall
•Installation interfaces•End flanges and seals•Base mounting•Other connections
•Utility requirements
•Instrumentation
MICE Installation Issues – MICE CM23 at ICST, Harbin, China
Page 3Steve Virostek - Lawrence Berkeley National Lab - January 13, 2009
Progress Update
•Shipping skid for RFCC module developed
–Module axis is vertical during shipping–Skid provides for rotation to horizontal in MICE hall
•RAL developing spectrometer solenoid lift beam
–Four lifting points are included on the magnets
–Load testing and certification is required
•Two module bellows spools received at RAL
–Bellows assemblies purchased from Hyspan–Spools connect spectrometer solenoid to AFC module
–Apparent tolerance error being discussed w/vendor
MICE Installation Issues – MICE CM23 at ICST, Harbin, China
Page 4Steve Virostek - Lawrence Berkeley National Lab - January 13, 2009
Progress Update (cont’d)
•Still need a helium-to-vacuum window design
–Window separates vacuum space from tracker volume in spectrometer solenoid bore
–Preliminary plan is to use AFC style window–Good opportunity to add mounting holes now
•Several instrumentation readouts purchased
–Thermocouple and helium level readouts for the spectrometer solenoid have been received by LBNL
–Similar readouts will be needed for RFCC module
–Most instrumentation only needed during initial tests
MICE Installation Issues – MICE CM23 at ICST, Harbin, China
Page 5Steve Virostek - Lawrence Berkeley National Lab - January 13, 2009
Shipping Logistics
•All modules to be forklifted on/off truck•All magnet coils are shipped warm
•RFCC cavities, couplers, coolers & pumps removed•Coupling coil integral with vacuum vessel
•RFCC axis vertical during shipping•Concerns about shipping loads on coupling coil•Special shipping skid has been developed
•Cavities, couplers packaged to prevent damage•RF, Be windows left in place w/appropriate protection•Vac vessel, cavities and couplers backfilled with N2
MICE Installation Issues – MICE CM23 at ICST, Harbin, China
Page 6Steve Virostek - Lawrence Berkeley National Lab - January 13, 2009
RFCC Shipping Configuration
Skid holds module in vertical orientation
Cavities removed
Cryocoolers removed
Couplers removed
Vacuum pumpsremoved
MICE Installation Issues – MICE CM23 at ICST, Harbin, China
Page 7Steve Virostek - Lawrence Berkeley National Lab - January 13, 2009
MICE Hall Access
•Forklift to be used for unloading and moving through hall door
•Door is tall and wide enough for spectrometer solenoids and RFCC modules
•No special equipment or hardware is required
MICE Installation Issues – MICE CM23 at ICST, Harbin, China
Page 8Steve Virostek - Lawrence Berkeley National Lab - January 13, 2009
RFCC Rotation and Support InstallTilting runners installed on shipping skid
MICE Installation Issues – MICE CM23 at ICST, Harbin, China
Page 9Steve Virostek - Lawrence Berkeley National Lab - January 13, 2009
RFCC Rotation and Support Install
Permanent support stand structure installed on RFCC vacuum vessel
MICE Installation Issues – MICE CM23 at ICST, Harbin, China
Page 10Steve Virostek - Lawrence Berkeley National Lab - January 13, 2009
RFCC Rotation and Support InstallModule is tilted into horizontal orientation using crane
MICE Installation Issues – MICE CM23 at ICST, Harbin, China
Page 11Steve Virostek - Lawrence Berkeley National Lab - January 13, 2009
RFCC Rotation and Support InstallModule is tilted into horizontal orientation using crane
MICE Installation Issues – MICE CM23 at ICST, Harbin, China
Page 12Steve Virostek - Lawrence Berkeley National Lab - January 13, 2009
RFCC Rotation and Support Install
Finished tilting onto permanent support stand
MICE Installation Issues – MICE CM23 at ICST, Harbin, China
Page 13Steve Virostek - Lawrence Berkeley National Lab - January 13, 2009
RFCC Rotation and Support Install
Finished tilting onto permanent support stand
MICE Installation Issues – MICE CM23 at ICST, Harbin, China
Page 14Steve Virostek - Lawrence Berkeley National Lab - January 13, 2009
•Locate vacuum vessel/coupling coil on lateral tracks
•Erect portable clean room around module•Unpack cavities, couplers, coolers, pumps•Install six tuner assemblies on each cavity•Insert cavities in vacuum vessel using special fixture
•Install couplers and tuner actuators after cavity is aligned and supported by struts
•Install vacuum pumps to complete module•Perform final alignment before translation
Re-assembly of RFCC Module at RAL
MICE Installation Issues – MICE CM23 at ICST, Harbin, China
Page 15Steve Virostek - Lawrence Berkeley National Lab - January 13, 2009
Re-assembly of Module at RAL
Module ready for assembly
MICE Installation Issues – MICE CM23 at ICST, Harbin, China
Page 16Steve Virostek - Lawrence Berkeley National Lab - January 13, 2009
Re-assembly of Module at RAL
Cryocooler(s) installed
MICE Installation Issues – MICE CM23 at ICST, Harbin, China
Page 17Steve Virostek - Lawrence Berkeley National Lab - January 13, 2009
Re-assembly of Module at RAL
RF cavities installed from either end
MICE Installation Issues – MICE CM23 at ICST, Harbin, China
Page 18Steve Virostek - Lawrence Berkeley National Lab - January 13, 2009
Re-assembly of Module at RAL
Cavity tuner actuators added
MICE Installation Issues – MICE CM23 at ICST, Harbin, China
Page 19Steve Virostek - Lawrence Berkeley National Lab - January 13, 2009
Re-assembly of Module at RAL
Module vacuum pumps installed
MICE Installation Issues – MICE CM23 at ICST, Harbin, China
Page 20Steve Virostek - Lawrence Berkeley National Lab - January 13, 2009
Re-assembly of Module at RAL
RF couplers installed
MICE Installation Issues – MICE CM23 at ICST, Harbin, China
Page 21Steve Virostek - Lawrence Berkeley National Lab - January 13, 2009
Module Base Mounting
•RFCC module and Spectrometer Solenoid base connections to rails are similar
•Six mounting plates are welded to the base of the module support stands
•Location of the mounting plates will be included in an interface document (and later measured)
•Magnetic loads are carried to the floor through the vacuum vessel/support stand/base mounts
MICE Installation Issues – MICE CM23 at ICST, Harbin, China
Page 22Steve Virostek - Lawrence Berkeley National Lab - January 13, 2009
Translating Platform
MICE Installation Issues – MICE CM23 at ICST, Harbin, China
Page 23Steve Virostek - Lawrence Berkeley National Lab - January 13, 2009
Spectrometer Solenoid Mounting
Six mounting plates on the support stand base for installation on rails
MICE Installation Issues – MICE CM23 at ICST, Harbin, China
Page 24Steve Virostek - Lawrence Berkeley National Lab - January 13, 2009
RFCC Module Mounting
•Six mounting plates to be welded to the support stand base for installation on rails
•Similar to spectrometer solenoid mounting scheme
MICE Installation Issues – MICE CM23 at ICST, Harbin, China
Page 25Steve Virostek - Lawrence Berkeley National Lab - January 13, 2009
Insertion into MICE Beamline
•Locate module on lateral tracks
•Align and shim module to correct height
•Pull back bellows on both module ends with O-rings in place
•Translate module into position using rails
•Release bellows and connect flanges
•Lock out bellows using bridging bolts
•Connect utilities and instrumentation
MICE Installation Issues – MICE CM23 at ICST, Harbin, China
Page 26Steve Virostek - Lawrence Berkeley National Lab - January 13, 2009
B
MICE Bellows Joints
Bellows Joint
Bellows Joint
Bellows Joint
Bellows Joint
Bellows Joint
Bellows Joint
MICE Installation Issues – MICE CM23 at ICST, Harbin, China
Page 27Steve Virostek - Lawrence Berkeley National Lab - January 13, 2009
End Flanges and Seals
•RFCC flanges mate with AFC module flanges
•AFC flanges have no O-ring grooves or bellows
•RFCC module flanges have bellows and O-ring grooves at both ends
•Bellows are spec’d for >1 cm of total travel
•Module relative alignment is driven by clearance in flange holes
•Bellows are locked out after installation to allow transmission of forces between modules
MICE Installation Issues – MICE CM23 at ICST, Harbin, China
Page 28Steve Virostek - Lawrence Berkeley National Lab - January 13, 2009
Bellows Joint Detail
MICE RF and Coupling Coil Module – Summary of the Design and Fabrication Plan
Elastomer or Helicoflex all-metal O-ring
Clamping bolts Bellows
MICE Installation Issues – MICE CM23 at ICST, Harbin, China
Page 29Steve Virostek - Lawrence Berkeley National Lab - January 13, 2009
Bellows Joint Detail
Joint pullback for installation
MICE Installation Issues – MICE CM23 at ICST, Harbin, China
Page 30Steve Virostek - Lawrence Berkeley National Lab - January 13, 2009
Bellows Joint Detail
Clamping of spectrometer solenoid joint
MICE Installation Issues – MICE CM23 at ICST, Harbin, China
Page 31Steve Virostek - Lawrence Berkeley National Lab - January 13, 2009
Bellows Joint Detail
Clamping of AFC module joint
MICE Installation Issues – MICE CM23 at ICST, Harbin, China
Page 32Steve Virostek - Lawrence Berkeley National Lab - January 13, 2009
Bellows Joint Detail
Fully clamped joints
MICE Installation Issues – MICE CM23 at ICST, Harbin, China
Page 33Steve Virostek - Lawrence Berkeley National Lab - January 13, 2009
Bellows Joint Detail
Bridging bolts for force transmission
MICE Installation Issues – MICE CM23 at ICST, Harbin, China
Page 34Steve Virostek - Lawrence Berkeley National Lab - January 13, 2009
Module Utility Requirements•Cryomech Model PT-415 cryocoolers
•3 per spectrometer solenoid, 2 per coupling coil (12 total)•50 Hz AC: 10.5 kW @ 380/420 V, 3 phase•Cooling: minimum 3 gpm of water @ 80ºF max
•300 A Power Supplies – American Magnetics (5 ea total)
•50-60 Hz AC: 3.5 kW @ 208 V, 3, forced air cooled, rack mnt.
•60 A Power Supplies – Lake Shore Cryotronics (4 ea tot.)
•50-60 Hz AC: 0.3 kW @ 208 V, 3, forced air cooled, rack mnt.
•Vacuum: 10-3 torr @ startup thru 25 mm flanged ports
•Cavity cooling water: ~8 lpm/per cavity
•Getter pump regeneration power (100-210 VAC, 100 W)
•Pressurized N2: up to 200 psi for tuner actuators
MICE Installation Issues – MICE CM23 at ICST, Harbin, China
Page 35Steve Virostek - Lawrence Berkeley National Lab - January 13, 2009
Instrumentation
•Coupling coil and spectrometer solenoid•Coil voltage taps•Thermocouples•LHe level•Vacuum pressure
•RF cavities•RF pickup loop•N2 pressure control for tuners (1 per cavity)•Cooling water temperature/flow
•RFCC module vacuum•Getter pump power supply and controller•Pump thermocouple•Vacuum pressure