installation issues steve virostek lawrence berkeley national lab mice cm23 at icst, harbin january...

35
Installation Issues Steve Virostek Lawrence Berkeley National Lab MICE CM23 at ICST, Harbin January 13, 2009

Post on 19-Dec-2015

218 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Installation Issues Steve Virostek Lawrence Berkeley National Lab MICE CM23 at ICST, Harbin January 13, 2009

Installation Issues

Steve VirostekLawrence Berkeley National Lab

MICE CM23 at ICST, Harbin

January 13, 2009

Page 2: Installation Issues Steve Virostek Lawrence Berkeley National Lab MICE CM23 at ICST, Harbin January 13, 2009

MICE Installation Issues – MICE CM23 at ICST, Harbin, China

Page 2Steve Virostek - Lawrence Berkeley National Lab - January 13, 2009

Topic Summary

•Packaging and delivery to RAL

•Moving of modules into MICE hall

•Assembly work in MICE hall

•Installation interfaces•End flanges and seals•Base mounting•Other connections

•Utility requirements

•Instrumentation

Page 3: Installation Issues Steve Virostek Lawrence Berkeley National Lab MICE CM23 at ICST, Harbin January 13, 2009

MICE Installation Issues – MICE CM23 at ICST, Harbin, China

Page 3Steve Virostek - Lawrence Berkeley National Lab - January 13, 2009

Progress Update

•Shipping skid for RFCC module developed

–Module axis is vertical during shipping–Skid provides for rotation to horizontal in MICE hall

•RAL developing spectrometer solenoid lift beam

–Four lifting points are included on the magnets

–Load testing and certification is required

•Two module bellows spools received at RAL

–Bellows assemblies purchased from Hyspan–Spools connect spectrometer solenoid to AFC module

–Apparent tolerance error being discussed w/vendor

Page 4: Installation Issues Steve Virostek Lawrence Berkeley National Lab MICE CM23 at ICST, Harbin January 13, 2009

MICE Installation Issues – MICE CM23 at ICST, Harbin, China

Page 4Steve Virostek - Lawrence Berkeley National Lab - January 13, 2009

Progress Update (cont’d)

•Still need a helium-to-vacuum window design

–Window separates vacuum space from tracker volume in spectrometer solenoid bore

–Preliminary plan is to use AFC style window–Good opportunity to add mounting holes now

•Several instrumentation readouts purchased

–Thermocouple and helium level readouts for the spectrometer solenoid have been received by LBNL

–Similar readouts will be needed for RFCC module

–Most instrumentation only needed during initial tests

Page 5: Installation Issues Steve Virostek Lawrence Berkeley National Lab MICE CM23 at ICST, Harbin January 13, 2009

MICE Installation Issues – MICE CM23 at ICST, Harbin, China

Page 5Steve Virostek - Lawrence Berkeley National Lab - January 13, 2009

Shipping Logistics

•All modules to be forklifted on/off truck•All magnet coils are shipped warm

•RFCC cavities, couplers, coolers & pumps removed•Coupling coil integral with vacuum vessel

•RFCC axis vertical during shipping•Concerns about shipping loads on coupling coil•Special shipping skid has been developed

•Cavities, couplers packaged to prevent damage•RF, Be windows left in place w/appropriate protection•Vac vessel, cavities and couplers backfilled with N2

Page 6: Installation Issues Steve Virostek Lawrence Berkeley National Lab MICE CM23 at ICST, Harbin January 13, 2009

MICE Installation Issues – MICE CM23 at ICST, Harbin, China

Page 6Steve Virostek - Lawrence Berkeley National Lab - January 13, 2009

RFCC Shipping Configuration

Skid holds module in vertical orientation

Cavities removed

Cryocoolers removed

Couplers removed

Vacuum pumpsremoved

Page 7: Installation Issues Steve Virostek Lawrence Berkeley National Lab MICE CM23 at ICST, Harbin January 13, 2009

MICE Installation Issues – MICE CM23 at ICST, Harbin, China

Page 7Steve Virostek - Lawrence Berkeley National Lab - January 13, 2009

MICE Hall Access

•Forklift to be used for unloading and moving through hall door

•Door is tall and wide enough for spectrometer solenoids and RFCC modules

•No special equipment or hardware is required

Page 8: Installation Issues Steve Virostek Lawrence Berkeley National Lab MICE CM23 at ICST, Harbin January 13, 2009

MICE Installation Issues – MICE CM23 at ICST, Harbin, China

Page 8Steve Virostek - Lawrence Berkeley National Lab - January 13, 2009

RFCC Rotation and Support InstallTilting runners installed on shipping skid

Page 9: Installation Issues Steve Virostek Lawrence Berkeley National Lab MICE CM23 at ICST, Harbin January 13, 2009

MICE Installation Issues – MICE CM23 at ICST, Harbin, China

Page 9Steve Virostek - Lawrence Berkeley National Lab - January 13, 2009

RFCC Rotation and Support Install

Permanent support stand structure installed on RFCC vacuum vessel

Page 10: Installation Issues Steve Virostek Lawrence Berkeley National Lab MICE CM23 at ICST, Harbin January 13, 2009

MICE Installation Issues – MICE CM23 at ICST, Harbin, China

Page 10Steve Virostek - Lawrence Berkeley National Lab - January 13, 2009

RFCC Rotation and Support InstallModule is tilted into horizontal orientation using crane

Page 11: Installation Issues Steve Virostek Lawrence Berkeley National Lab MICE CM23 at ICST, Harbin January 13, 2009

MICE Installation Issues – MICE CM23 at ICST, Harbin, China

Page 11Steve Virostek - Lawrence Berkeley National Lab - January 13, 2009

RFCC Rotation and Support InstallModule is tilted into horizontal orientation using crane

Page 12: Installation Issues Steve Virostek Lawrence Berkeley National Lab MICE CM23 at ICST, Harbin January 13, 2009

MICE Installation Issues – MICE CM23 at ICST, Harbin, China

Page 12Steve Virostek - Lawrence Berkeley National Lab - January 13, 2009

RFCC Rotation and Support Install

Finished tilting onto permanent support stand

Page 13: Installation Issues Steve Virostek Lawrence Berkeley National Lab MICE CM23 at ICST, Harbin January 13, 2009

MICE Installation Issues – MICE CM23 at ICST, Harbin, China

Page 13Steve Virostek - Lawrence Berkeley National Lab - January 13, 2009

RFCC Rotation and Support Install

Finished tilting onto permanent support stand

Page 14: Installation Issues Steve Virostek Lawrence Berkeley National Lab MICE CM23 at ICST, Harbin January 13, 2009

MICE Installation Issues – MICE CM23 at ICST, Harbin, China

Page 14Steve Virostek - Lawrence Berkeley National Lab - January 13, 2009

•Locate vacuum vessel/coupling coil on lateral tracks

•Erect portable clean room around module•Unpack cavities, couplers, coolers, pumps•Install six tuner assemblies on each cavity•Insert cavities in vacuum vessel using special fixture

•Install couplers and tuner actuators after cavity is aligned and supported by struts

•Install vacuum pumps to complete module•Perform final alignment before translation

Re-assembly of RFCC Module at RAL

Page 15: Installation Issues Steve Virostek Lawrence Berkeley National Lab MICE CM23 at ICST, Harbin January 13, 2009

MICE Installation Issues – MICE CM23 at ICST, Harbin, China

Page 15Steve Virostek - Lawrence Berkeley National Lab - January 13, 2009

Re-assembly of Module at RAL

Module ready for assembly

Page 16: Installation Issues Steve Virostek Lawrence Berkeley National Lab MICE CM23 at ICST, Harbin January 13, 2009

MICE Installation Issues – MICE CM23 at ICST, Harbin, China

Page 16Steve Virostek - Lawrence Berkeley National Lab - January 13, 2009

Re-assembly of Module at RAL

Cryocooler(s) installed

Page 17: Installation Issues Steve Virostek Lawrence Berkeley National Lab MICE CM23 at ICST, Harbin January 13, 2009

MICE Installation Issues – MICE CM23 at ICST, Harbin, China

Page 17Steve Virostek - Lawrence Berkeley National Lab - January 13, 2009

Re-assembly of Module at RAL

RF cavities installed from either end

Page 18: Installation Issues Steve Virostek Lawrence Berkeley National Lab MICE CM23 at ICST, Harbin January 13, 2009

MICE Installation Issues – MICE CM23 at ICST, Harbin, China

Page 18Steve Virostek - Lawrence Berkeley National Lab - January 13, 2009

Re-assembly of Module at RAL

Cavity tuner actuators added

Page 19: Installation Issues Steve Virostek Lawrence Berkeley National Lab MICE CM23 at ICST, Harbin January 13, 2009

MICE Installation Issues – MICE CM23 at ICST, Harbin, China

Page 19Steve Virostek - Lawrence Berkeley National Lab - January 13, 2009

Re-assembly of Module at RAL

Module vacuum pumps installed

Page 20: Installation Issues Steve Virostek Lawrence Berkeley National Lab MICE CM23 at ICST, Harbin January 13, 2009

MICE Installation Issues – MICE CM23 at ICST, Harbin, China

Page 20Steve Virostek - Lawrence Berkeley National Lab - January 13, 2009

Re-assembly of Module at RAL

RF couplers installed

Page 21: Installation Issues Steve Virostek Lawrence Berkeley National Lab MICE CM23 at ICST, Harbin January 13, 2009

MICE Installation Issues – MICE CM23 at ICST, Harbin, China

Page 21Steve Virostek - Lawrence Berkeley National Lab - January 13, 2009

Module Base Mounting

•RFCC module and Spectrometer Solenoid base connections to rails are similar

•Six mounting plates are welded to the base of the module support stands

•Location of the mounting plates will be included in an interface document (and later measured)

•Magnetic loads are carried to the floor through the vacuum vessel/support stand/base mounts

Page 22: Installation Issues Steve Virostek Lawrence Berkeley National Lab MICE CM23 at ICST, Harbin January 13, 2009

MICE Installation Issues – MICE CM23 at ICST, Harbin, China

Page 22Steve Virostek - Lawrence Berkeley National Lab - January 13, 2009

Translating Platform

Page 23: Installation Issues Steve Virostek Lawrence Berkeley National Lab MICE CM23 at ICST, Harbin January 13, 2009

MICE Installation Issues – MICE CM23 at ICST, Harbin, China

Page 23Steve Virostek - Lawrence Berkeley National Lab - January 13, 2009

Spectrometer Solenoid Mounting

Six mounting plates on the support stand base for installation on rails

Page 24: Installation Issues Steve Virostek Lawrence Berkeley National Lab MICE CM23 at ICST, Harbin January 13, 2009

MICE Installation Issues – MICE CM23 at ICST, Harbin, China

Page 24Steve Virostek - Lawrence Berkeley National Lab - January 13, 2009

RFCC Module Mounting

•Six mounting plates to be welded to the support stand base for installation on rails

•Similar to spectrometer solenoid mounting scheme

Page 25: Installation Issues Steve Virostek Lawrence Berkeley National Lab MICE CM23 at ICST, Harbin January 13, 2009

MICE Installation Issues – MICE CM23 at ICST, Harbin, China

Page 25Steve Virostek - Lawrence Berkeley National Lab - January 13, 2009

Insertion into MICE Beamline

•Locate module on lateral tracks

•Align and shim module to correct height

•Pull back bellows on both module ends with O-rings in place

•Translate module into position using rails

•Release bellows and connect flanges

•Lock out bellows using bridging bolts

•Connect utilities and instrumentation

Page 26: Installation Issues Steve Virostek Lawrence Berkeley National Lab MICE CM23 at ICST, Harbin January 13, 2009

MICE Installation Issues – MICE CM23 at ICST, Harbin, China

Page 26Steve Virostek - Lawrence Berkeley National Lab - January 13, 2009

B

MICE Bellows Joints

Bellows Joint

Bellows Joint

Bellows Joint

Bellows Joint

Bellows Joint

Bellows Joint

Page 27: Installation Issues Steve Virostek Lawrence Berkeley National Lab MICE CM23 at ICST, Harbin January 13, 2009

MICE Installation Issues – MICE CM23 at ICST, Harbin, China

Page 27Steve Virostek - Lawrence Berkeley National Lab - January 13, 2009

End Flanges and Seals

•RFCC flanges mate with AFC module flanges

•AFC flanges have no O-ring grooves or bellows

•RFCC module flanges have bellows and O-ring grooves at both ends

•Bellows are spec’d for >1 cm of total travel

•Module relative alignment is driven by clearance in flange holes

•Bellows are locked out after installation to allow transmission of forces between modules

Page 28: Installation Issues Steve Virostek Lawrence Berkeley National Lab MICE CM23 at ICST, Harbin January 13, 2009

MICE Installation Issues – MICE CM23 at ICST, Harbin, China

Page 28Steve Virostek - Lawrence Berkeley National Lab - January 13, 2009

Bellows Joint Detail

MICE RF and Coupling Coil Module – Summary of the Design and Fabrication Plan

Elastomer or Helicoflex all-metal O-ring

Clamping bolts Bellows

Page 29: Installation Issues Steve Virostek Lawrence Berkeley National Lab MICE CM23 at ICST, Harbin January 13, 2009

MICE Installation Issues – MICE CM23 at ICST, Harbin, China

Page 29Steve Virostek - Lawrence Berkeley National Lab - January 13, 2009

Bellows Joint Detail

Joint pullback for installation

Page 30: Installation Issues Steve Virostek Lawrence Berkeley National Lab MICE CM23 at ICST, Harbin January 13, 2009

MICE Installation Issues – MICE CM23 at ICST, Harbin, China

Page 30Steve Virostek - Lawrence Berkeley National Lab - January 13, 2009

Bellows Joint Detail

Clamping of spectrometer solenoid joint

Page 31: Installation Issues Steve Virostek Lawrence Berkeley National Lab MICE CM23 at ICST, Harbin January 13, 2009

MICE Installation Issues – MICE CM23 at ICST, Harbin, China

Page 31Steve Virostek - Lawrence Berkeley National Lab - January 13, 2009

Bellows Joint Detail

Clamping of AFC module joint

Page 32: Installation Issues Steve Virostek Lawrence Berkeley National Lab MICE CM23 at ICST, Harbin January 13, 2009

MICE Installation Issues – MICE CM23 at ICST, Harbin, China

Page 32Steve Virostek - Lawrence Berkeley National Lab - January 13, 2009

Bellows Joint Detail

Fully clamped joints

Page 33: Installation Issues Steve Virostek Lawrence Berkeley National Lab MICE CM23 at ICST, Harbin January 13, 2009

MICE Installation Issues – MICE CM23 at ICST, Harbin, China

Page 33Steve Virostek - Lawrence Berkeley National Lab - January 13, 2009

Bellows Joint Detail

Bridging bolts for force transmission

Page 34: Installation Issues Steve Virostek Lawrence Berkeley National Lab MICE CM23 at ICST, Harbin January 13, 2009

MICE Installation Issues – MICE CM23 at ICST, Harbin, China

Page 34Steve Virostek - Lawrence Berkeley National Lab - January 13, 2009

Module Utility Requirements•Cryomech Model PT-415 cryocoolers

•3 per spectrometer solenoid, 2 per coupling coil (12 total)•50 Hz AC: 10.5 kW @ 380/420 V, 3 phase•Cooling: minimum 3 gpm of water @ 80ºF max

•300 A Power Supplies – American Magnetics (5 ea total)

•50-60 Hz AC: 3.5 kW @ 208 V, 3, forced air cooled, rack mnt.

•60 A Power Supplies – Lake Shore Cryotronics (4 ea tot.)

•50-60 Hz AC: 0.3 kW @ 208 V, 3, forced air cooled, rack mnt.

•Vacuum: 10-3 torr @ startup thru 25 mm flanged ports

•Cavity cooling water: ~8 lpm/per cavity

•Getter pump regeneration power (100-210 VAC, 100 W)

•Pressurized N2: up to 200 psi for tuner actuators

Page 35: Installation Issues Steve Virostek Lawrence Berkeley National Lab MICE CM23 at ICST, Harbin January 13, 2009

MICE Installation Issues – MICE CM23 at ICST, Harbin, China

Page 35Steve Virostek - Lawrence Berkeley National Lab - January 13, 2009

Instrumentation

•Coupling coil and spectrometer solenoid•Coil voltage taps•Thermocouples•LHe level•Vacuum pressure

•RF cavities•RF pickup loop•N2 pressure control for tuners (1 per cavity)•Cooling water temperature/flow

•RFCC module vacuum•Getter pump power supply and controller•Pump thermocouple•Vacuum pressure