Agenda

• Who is IPS?• How have we managed our Gas Wells in

the past? • What is Wellhead Management from Day

1?• How do we ensure that our wells are

delivering the most Production possible?• How can the IPS/Menex solution deliver

higher profits?

INTEGRATED PRODUCTION SERVICES

IPS Operating Units

Project Mgmt

& Engineering

Artificial LiftTools & Systems

Production Testing

SlicklineServices

Cased HoleElectric Line

Oil & Gas WellOptimization

Well Automation & Diagnostic

Instruments

ProductionManufacturing

Production&

ReservoirKnowled

ge

INTEGRATED PRODUCTION SERVICES

Basic Common Shares 24.9 million Fully Diluted 27.2 million Recent Price (Dec 10) $2.20/share Market Cap (Dec 10) $60 million 52 Week High $4.30 52 Week Low $2.20

IPS the Public Company

INTEGRATED PRODUCTION SERVICES

Majority Shareholders of IPS?

APPROXIMATELY 50% OF IPSSHARES ARE FREE TRADING

50%

4%

39%

7%

FREE TRADINGESCROWSCFHSBC

INTEGRATED PRODUCTION SERVICES

How have we managed our Gas Wells in the Past?

INTEGRATED PRODUCTION SERVICES

• Circular Charts• Daily, Weekly or Monthly Averages• Trends from various Scada outputs• Verbal reports from the well

operators• Web based access to data

What is the format of your production data?

INTEGRATED PRODUCTION SERVICES

• Flow rates, line pressures and temperatures– Everything is fine– Production is up– Production is down– On line time for the well is lower than last

month– On line time for the well is higher than last

month

What does the production data tell us?

INTEGRATED PRODUCTION SERVICES

• Casing and Tubing pressures; historically or current

• Why the well’s production is higher or lower than last month

• Why your well was the first one to be shut in and the last one to be started up following a disruption at the plant or in the flowline

What doesn’t the production data tell us?

INTEGRATED PRODUCTION SERVICES

Typical Life Cycle of a Gas Well

Primary Production Secondary Production

Production/day

Normal DeclineWhat determines when we shift from primary to secondary Production?

INTEGRATED PRODUCTION SERVICES

• What is it?– The minimum rate required which will enable

the well to lift it’s own liquids.

• Why does it change?– Lower reservoir pressure.– Higher liquid production.– Variance in line pressures.

• What does it do to your production?– Normally costs you production.

Critical Rate

INTEGRATED PRODUCTION SERVICES

Typical Life Cycle of a Gas Well

Primary Production Secondary Production

Production/day

CRITICAL RATE

Normal Decline

INTEGRATED PRODUCTION SERVICES

What do we do when the well’s rate falls below

critical? • Unload the well to a tank (on location or at the battery).• Drop Soap Sticks in the wellbore.• Shut the well in to build up wellbore and reservoir pressure.

• Install some new hardware:- Flow Intermitter- Velocity

String - Plunger Lift- Wellsite Compression

INTEGRATED PRODUCTION SERVICES

What should we do to make sure we implement the best

solution? • Gather accurate downhole information.• Gather historical and current production data.• Analyze the gathered information.

• Prepare a recommendation and source the required equipment.• Implement the recommendations.• Continually monitor the results and make adjustments when and where required.

INTEGRATED PRODUCTION SERVICES

• Changing field conditions.• The lack of field support.• The lack of engineering support.

What stops us from staying optimized?

• The industry has never had the right piece of equipment that combines technology and field tested hardware that will adjust automatically to the changes that occur in every wells life.

INTEGRATED PRODUCTION SERVICES

• The Menex Philosophy – What would you do if you were an

operator living at the well 24 hours per day 7 days a week with direct communication to all wellhead and flow line pressures, liquid and gas rates both historically and current.

What is Wellhead Management from Day 1?

INTEGRATED PRODUCTION SERVICES

Wellhead

Reservoir

Point of Sale

Where is the best place to make decisions about

optimization?

INTEGRATED PRODUCTION SERVICES

Normal Suspension

Increased Secondary and

Primary Production

Production/day

Secondary Production

Cumulative Production

Extended Production

Primary Production

CRITICAL RATE

Normal Decline

Well Management from Day 1

INTEGRATED PRODUCTION SERVICES

• Flow the casing whenever possible!!

How do we increase Primary Production?

• Eliminate dirty transitions.

INTEGRATED PRODUCTION SERVICES

• Flow the casing whenever possible!!

How do we increase Secondary Production?

• Eliminate dirty transitions.• React to downstream changes with little or no operator/engineering

intervention.

INTEGRATED PRODUCTION SERVICES

• Flow the casing whenever possible!!

How do we realize extended Production?

• Eliminate dirty transitions.• React to downstream changes with little or no operator/engineering

intervention.

• Add wellsite compression with plunger lift.

INTEGRATED PRODUCTION SERVICES

• Allows you to flow the casing whenever possible!!

Why is the Menex technology better for your

well?

• Eliminates dirty transitions.• Reacts to downstream changes with little or no operator/engineering

intervention.

• Controls plunger lift, casing flow and a wellsite compressor from the same control box.

INTEGRATED PRODUCTION SERVICES

• Utilizes variable setting control valves on the casing and tubing.

How does the Menex Box make plunger lift more

efficient?

• Calculates a new critical rate 10 times per second.

• Does not need an operator or engineer to tell it when to make changes.

• Optimizes each cycle to ensure that the plunger’s travel time is 270 meters per minute as it comes up the hole.

INTEGRATED PRODUCTION SERVICES

• Gets the liquid in the wellbore and near wellbore above the plunger prior to cycling.

Pre-staging the Plunger!

and• Keeps the liquid above the plunger prior to cycling!

INTEGRATED PRODUCTION SERVICES

PLUNGER LIFT SYSTEM FOR LIQUID LOADED GAS WELLS

GAS OPTIMIZATION

Uses reservoir pressure to expel liquids from the well and increase gas production

INTEGRATED PRODUCTION SERVICES

PLUNGER LIFT SYSTEM FOR LIQUID LOADED GAS WELLS

GAS OPTIMIZATION

Uses reservoir pressure to expel liquids from the well and increase gas production

INTEGRATED PRODUCTION SERVICES

Variable setting tubing and casing valves installed on a

wellhead

INTEGRATED PRODUCTION SERVICES

Menex control box installed on a wellsite separator

building

INTEGRATED PRODUCTION SERVICES

Menex installed with wellsite Compression

INTEGRATED PRODUCTION SERVICES

• Allows you to continuously maximize the wells production without operator intervention when the well needs it and not when the operator can get around to it.

Why is the Menex technology better for your

profits?

• Calculates and maintains a historical record of production rates that are directly transferable to the AEUB. (AGA 8)

• Combines every gas well control system that has ever been produced into one control package that will work on your well from Day 1 to Abandonment.

INTEGRATED PRODUCTION SERVICES

Extended Production– Well production beyond normal zone

suspension or abandonment– Well is currently still producing

– 2750 E3m3 (100,000 mcf) extended production as of November 30, 2001;$250,000 at $2.50 per mcf

Why is the Menex technology better for your

profits?

INTEGRATED PRODUCTION SERVICES