integrated project delivery: built to last cmaa water summit july 20, 2010 james a. parrott...

32
Integrated Project Delivery: Built to Last CMAA Water Summit July 20, 2010 James A. Parrott Executive Director

Upload: bria-thompson

Post on 01-Apr-2015

219 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Integrated Project Delivery: Built to Last CMAA Water Summit July 20, 2010 James A. Parrott Executive Director

Integrated Project Delivery:Built to Last

CMAA Water Summit

July 20, 2010

James A. Parrott

Executive Director

Page 2: Integrated Project Delivery: Built to Last CMAA Water Summit July 20, 2010 James A. Parrott Executive Director

MSDGC Background

• Population Served– 850,000 in Hamilton

County, Ohio– 220,000

connections

• Double Governance– Hamilton County

Sewer District– Operated by City of

Cincinnati

Page 3: Integrated Project Delivery: Built to Last CMAA Water Summit July 20, 2010 James A. Parrott Executive Director

MSDGC Challenges• Aging Infrastructure

– About 50% combined sewers– Some 150 years old

• Multi-Billion $Consent Order – Plan submitted in 2006– Conditional approval in 2009

• Phase 1 = $1.2B by 2019• Stagnant/Failing Local and National

economy– Unprecedented local layoffs

(especially in government)– Affordability issues with residents

Page 4: Integrated Project Delivery: Built to Last CMAA Water Summit July 20, 2010 James A. Parrott Executive Director

Key Facts

• MSD is among the top 5 CSO dischargers in the US

• MSD must submit a plan to USEPA by December 2012 for the Lower Mill Creek Remedy (location of our largest CSO)

• MSD has until 2017 to submit Phase II Schedule

Page 5: Integrated Project Delivery: Built to Last CMAA Water Summit July 20, 2010 James A. Parrott Executive Director

MSD’s Environmental Challenge

Must control by 85%

Page 6: Integrated Project Delivery: Built to Last CMAA Water Summit July 20, 2010 James A. Parrott Executive Director

Wet Weather StrategySource ControlConveyance & StorageProduct Control

Phased ApproachPhase 1: 2009 – 2019Phase 2: Schedule to be submitted by 2017

Controlled SpendingPhase 1: $1.145BCredit for $300M of projects already builtPhase 2: To Be Determined

Strategy

Affordability

Flexibility

How to Build a Consent Order

Page 7: Integrated Project Delivery: Built to Last CMAA Water Summit July 20, 2010 James A. Parrott Executive Director

2009 2010 2011 2012 2017 2018

Submit Plan for Phase 2 including schedule and costs

2009

MSD received conditional approval of the Wet Weather

Plan after three years of negotiations

2011

Evaluate alternatives to achieve overflow reductions of 2BG

2017

2018

MSD must achieve 2 BG overflow

reduction in Lower Mill Creek

2012

MSD will integrate results to arrive at a recommended plan to submit to USEPA

2010

Final legal action anticipated

Clock is Ticking

Page 8: Integrated Project Delivery: Built to Last CMAA Water Summit July 20, 2010 James A. Parrott Executive Director

Phase 1 Costs (2006$)

$-

$20.0

$40.0

$60.0

$80.0

$100.0

$120.0

$140.0

$160.0

$180.0

$200.0

2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019

Years

Ann

ual C

ost (

M$)

$-

$200.0

$400.0

$600.0

$800.0

$1,000.0

$1,200.0

$1,400.0

$1,600.0

$1,800.0

Tota

l Cos

t (M

$)

Annual

Total

Page 9: Integrated Project Delivery: Built to Last CMAA Water Summit July 20, 2010 James A. Parrott Executive Director

WWIP Phases & Workload

250

200

150

100

50

0

Nu

mb

er o

f P

roje

cts

Year

2007 2008 20 9 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 20290

Developm ent Phase Peak Production Phase Ram p Down Phase

Construction Design PlanningMobilization

Period

WWIP Phase I70 Completed45 New Projects8 Annual Allowances

WWIP Phase IITotal167 ProjectsSchedule will be negotiated

Page 10: Integrated Project Delivery: Built to Last CMAA Water Summit July 20, 2010 James A. Parrott Executive Director

Conveyance & Storage

60%

Product Con-trol

35%Other5%

WWIP as Currently Approved

Wet Weather Strategy Determines Capital Portfolio

Page 11: Integrated Project Delivery: Built to Last CMAA Water Summit July 20, 2010 James A. Parrott Executive Director

MSD Wet Weather Strategy Determines the Project Portfolio

• Source Control– Removal of natural drainage from

entering the system– Regional BMPs, Separate storm

sewer installation• Conveyance & Storage

– Tunnels, parallel interceptors, storage facilities

– Real-Time control• Product Control

– EHRT and peak flow enhancements to existing WWTP’s

Page 12: Integrated Project Delivery: Built to Last CMAA Water Summit July 20, 2010 James A. Parrott Executive Director

MSD Wet Weather StrategyImplementation

Hydraulic Grade Line

Page 13: Integrated Project Delivery: Built to Last CMAA Water Summit July 20, 2010 James A. Parrott Executive Director

How We Got Started

• Three phased PMC– GAP Analysis

• Highlighted project risks, resource and process needs

– Developing Process to Bridge the GAP • Master Program Management Plan

– Implementation Plan and Monitor Progress

Page 14: Integrated Project Delivery: Built to Last CMAA Water Summit July 20, 2010 James A. Parrott Executive Director

MSD Organization in 2006

Director

Deputy Director

Administration Treatment Engineering CollectionsLaboratory &

Industrial Program

IT

Chief Engineer Wet Weather

Strategy

CityProgram MgtCounty

Page 15: Integrated Project Delivery: Built to Last CMAA Water Summit July 20, 2010 James A. Parrott Executive Director

Engineering Division

Superintendent

Administration PlanningProject

Management: Design

Project Management: Construction

Public Services

Program Mgt

Conventional “Cradle to Grave” Project ManagementProgram Management and Monitoring operates in own silo

Page 16: Integrated Project Delivery: Built to Last CMAA Water Summit July 20, 2010 James A. Parrott Executive Director

What We Know NowThat We Didn’t Know Then…

• Organizational structure change inevitable– What we did…. Tried to make

incremental change– What we should have done…. Slash

and Burn– Staff must:

oHave sense of urgencyo Be open to changeoObtain new skill setsoOr GET OUT OF THE WAY!

Page 17: Integrated Project Delivery: Built to Last CMAA Water Summit July 20, 2010 James A. Parrott Executive Director

How We Needed to Change

• MSD Manages Integrated Program– External Monitoring– Incentive based embedded staff

• Business Case Evaluations– Project selection by Triple Bottom Line

analysis

• Separated Planning from Design/Construction– Where the rubber hits the road– Allows priority focus for Project Delivery

Page 18: Integrated Project Delivery: Built to Last CMAA Water Summit July 20, 2010 James A. Parrott Executive Director

MSD Organization in 2010

Director

Deputy

Director

Admin TreatmentEngineering:

Project Delivery

Engineering: Planning &

DevelopmentCollections

Laboratory & Industrial Program

IT

Chief Engineer

Stormwater Management

Wet Weather Strategy

Page 19: Integrated Project Delivery: Built to Last CMAA Water Summit July 20, 2010 James A. Parrott Executive Director

Capital Programs Management

MSD Executive Leadership

Financial Planning &

Analysis

Engineering:

Project Delivery

Engineering:

Planning & Development

Enterprise Management

Project Controls

Design & Construction Management

Quality Assurance

Environmental Programs

Wet Weather Strategy

Cross-Functional Responsibility and Imbedded Program Management Support with External Monitors

Page 20: Integrated Project Delivery: Built to Last CMAA Water Summit July 20, 2010 James A. Parrott Executive Director

Environmental Programs

EP Manager

SustainableProject

Construction Delivery

Sustainable Watershed

Planner

Demonstration Programs

Concentration on Sustainable Watershed Management

Page 21: Integrated Project Delivery: Built to Last CMAA Water Summit July 20, 2010 James A. Parrott Executive Director

Conveyance & Storage

60%

Product Control

35%Other

5%

Current WWIP Profile

Source Control

35%

Conveyance & Storage

35%

Product Control

25%

Other5%

Potential Sustainable Approach

Page 22: Integrated Project Delivery: Built to Last CMAA Water Summit July 20, 2010 James A. Parrott Executive Director

Other Lessons Learned

• Financial System Inadequate – Multiple systems needed to be integrated– Need analysis and decision support tools

• Let Risk Management Drive Decisions– Justify projects and alternative selection

inside a risk framework– Strengthen Asset Management principles

• Communication– Internal and external tools necessary

Page 23: Integrated Project Delivery: Built to Last CMAA Water Summit July 20, 2010 James A. Parrott Executive Director

• Comprehensive process integrating all enterprise risks– Corporate– Asset– Operational– Project

Implementation

• Process driven by MSD Financial Policies– Owned by

Finance Manager

MSD Risk Management

Page 24: Integrated Project Delivery: Built to Last CMAA Water Summit July 20, 2010 James A. Parrott Executive Director

Other Lessons Learned

• Let Risk Management Drive Decisions– Justify projects and alternative selection

inside a risk framework– Strengthen Asset Management principles

• Financial System Inadequate – Multiple systems needed to be integrated– Need analysis and decision support tools

• Communication– Internal and external tools necessary

Page 25: Integrated Project Delivery: Built to Last CMAA Water Summit July 20, 2010 James A. Parrott Executive Director
Page 26: Integrated Project Delivery: Built to Last CMAA Water Summit July 20, 2010 James A. Parrott Executive Director
Page 27: Integrated Project Delivery: Built to Last CMAA Water Summit July 20, 2010 James A. Parrott Executive Director

Sharing the Vision

Page 28: Integrated Project Delivery: Built to Last CMAA Water Summit July 20, 2010 James A. Parrott Executive Director

Technology Drivers

Where We AreTactical

• Activity-Based• Document

Management• Construction

Coordination

Where We Are GoingStrategic

• Integrated Management• Workflow Integration

through Document Control• Watershed Management

Required Systems• Fully functional DMZ• Scheduling tool • Integrated financial management system• Forecasting and Earned Value tools• Asset management system

Page 29: Integrated Project Delivery: Built to Last CMAA Water Summit July 20, 2010 James A. Parrott Executive Director

Built to Last Formula

1. Consent Order with Flexibility

2. Wet Weather Strategy that leverages infrastructure investments to create factor conditions that support community development/urban infill

3. Organization Structure that support integrated project management

4. Renewed focus on environmental programs that support the wet weather strategy

5. Financial and Risk Practices linked with strategic organizational performance

Sustainable Organization – Financially and operationally stable

Sustainable Infrastructure – Does not create future liabilities

Sustainable Community – Maximizes benefits for all residents

Page 30: Integrated Project Delivery: Built to Last CMAA Water Summit July 20, 2010 James A. Parrott Executive Director

Value CreationLeveraging MSD Investments

Page 31: Integrated Project Delivery: Built to Last CMAA Water Summit July 20, 2010 James A. Parrott Executive Director
Page 32: Integrated Project Delivery: Built to Last CMAA Water Summit July 20, 2010 James A. Parrott Executive Director

Questions?

James A. “Tony” Parrott513-244-1212

[email protected]