ILFOV COUNTY COUNCIL

Intermodal transport project

“BIMH: Bucharest – Ilfov Multimodal Hub”

- November 2014 -

Page 2: Intermodal transport project - NETLIPSEnetlipse.eu/media/82468/3-bucharest-ilfov-multimodal-hub-by-remus... · Intermodal transport project ... arising from the use of multimodal

CONTENTS

1. The role of Ilfov County Council in planning and implementing the “BIMH” project

2. Action plan

3. Sustainability

4. “BIMH”:

a. History & description b. Location c. National and European relevance - in the context of the Trans-European

Transport Network - TEN-T Programme

5. “BIMH” structure

6. Proposal for capacity and functionality of the “BIMH” project

Page 3: Intermodal transport project - NETLIPSEnetlipse.eu/media/82468/3-bucharest-ilfov-multimodal-hub-by-remus... · Intermodal transport project ... arising from the use of multimodal

“BIMH: Bucharest –Ilfov Multimodal Hub”: history & description

Institutional steps:

√ March 2014: Cooperation Agreement signed by Ilfov County Council, National Railways Company “NRC”-S.A., National “Bucharest Airports” Company-S.A., National Company of Motorways and National Roads in Romania-S.A., Dascălu Local Council, Moara Vlăsiei Local Council, Otopeni Local Council and Tunari Local Council for the studies necessary for the construction of the intermodal transport hub “Bucharest – Ilfov Multimodal Hub”(BIMH)

√ March 2014: Ilfov County Council applies for European funding for the studies related to “BIMH” project through the TEN-T Programme of the Innovation and Networks Executive Agency (INEA) of the European Commission

√ August 2014: Ilfov County Council obtaines European funding for carrying out the studies related to the “BIMH” project

√ September - December 2014: Ilfov County Council continues public consultations with institutional partners signatories of the Agreement, railway, road and airway transporters

Page 4: Intermodal transport project - NETLIPSEnetlipse.eu/media/82468/3-bucharest-ilfov-multimodal-hub-by-remus... · Intermodal transport project ... arising from the use of multimodal

ACTION PLAN

Activities Period of implementation

Signing the co-financing agreement with INEA

December 2014

Finalization of the feasibility study

December 2015

Identification of funding sources & partners

2016

Tenders for design, construction & operation

2017

Construction of the project 2018 - 2020

Page 5: Intermodal transport project - NETLIPSEnetlipse.eu/media/82468/3-bucharest-ilfov-multimodal-hub-by-remus... · Intermodal transport project ... arising from the use of multimodal

The role of Ilfov County Council in planning and implementing the “BIMH” project

• Main Promoter

• Project Coordinator

• Project Applicant, with the support of the following partner

institutions:

• Henri Coandă International Airport

• Romanian Railways Company (CFR)

• Romanian National Company of Motorways and National Roads (CNADNR)

• Local Councils of Otopeni, Tunari, Moara Vlăsiei and Dascălu

• Integrator of feasibility studies already developed by “BIMH” project partner institutions

• Financial contributor

• Beneficiary of the socio-economic impact of the project

Page 6: Intermodal transport project - NETLIPSEnetlipse.eu/media/82468/3-bucharest-ilfov-multimodal-hub-by-remus... · Intermodal transport project ... arising from the use of multimodal

PROJECT SUSTAINABILITY

Ilfov County Council, through public consultations, will involve institutional partners signatories of the Agreement, state and private operators and transporters in selecting the optimal technical-financial solution for the realization of the project.

Project funding will be provided by several partners, being open to private operators and transporters.

The operation of “BIMH” will be done by concession / rental by state or private operators, providing users with services at the same rates charged in Europe.

Page 7: Intermodal transport project - NETLIPSEnetlipse.eu/media/82468/3-bucharest-ilfov-multimodal-hub-by-remus... · Intermodal transport project ... arising from the use of multimodal

The proposed location for the BIMH project– 114 ha

Moara Vlăsiei commune (Ilfov County), between A2 highway (Bucharest – Constanța)

and A3 highway (Ploiești – Brașov)

and in the proximity of Henri Coandă International Airport - Bucharest

The feasibility study will determine the optimal location, stages of achievement and investment value of the “BIMH” project!

Page 8: Intermodal transport project - NETLIPSEnetlipse.eu/media/82468/3-bucharest-ilfov-multimodal-hub-by-remus... · Intermodal transport project ... arising from the use of multimodal

National relevance

National Strategic Framework

▪ Ilfov County Development Strategy – Horizon 2020:

→ existence of a pre-feasibility study

→ Zonal Urban Plan with road connections between Henri Coandă Airport, A3 highway and the new ring road of Bucharest

▪ Intermodal Transport Strategy 2020 in Romania & the General Transport Master Plan draft (The Ministry of Transport)

▪ Airport Infrastructure Development Strategic Program for the Henri Coandă International Airport:

→ ongoing prefeasibility and feasibility, including a multimodal cargo platform and connection with the rail network

▪ NRC Intermodal Strategy

→ development of an intermodal terminal Ploiești - Bucharest - Giurgiu – Oltenița (2014 - 2020)

→ feasibility study for the electrification of Bucharest North Railway Station – Otopeni railway

Objectives / Benefits:

√ Developing an innovation and knowledge-based economy

√ Improving the efficiency of underdeveloped logistics connections

√ Optimal use of transport infrastructure

√ The development of green logistics corridors in Europe

√ Optimal integration of transport modes and reducing the financial disparities affecting intermodal transport

√ Promoting a green economy, more efficient in terms of resources and jobs

√ Reducing bureaucratic issues and costs arising from the use of multimodal transport platforms

Page 9: Intermodal transport project - NETLIPSEnetlipse.eu/media/82468/3-bucharest-ilfov-multimodal-hub-by-remus... · Intermodal transport project ... arising from the use of multimodal

European relevance

√ Romania has 2 TEN-T Core Network Corridors: The Orient/East-Med Corridor and The Rhine-Danube Corridor

√ Strengthening Romania as The East Gate Hub of Europe: Romania possesses the geographical ''turntable” position for inter-continental (Asia to Europe) and interregional (Silk Route and Central & Eastern Europe hinterland) transport

√ Improving the competitive global position of Europe

√ EU new policy refocuses transport financing on a tightly defined new core network (setting up of 9 major transport corridors)

√ It will remove bottlenecks, upgrade infrastructure and streamline cross border transport operations for freight, businesses and passengers throughout the EU

√ Safer and less congested travel

√ Smoother and quicker transport (goods, persons)

See the Info Map

Page 10: Intermodal transport project - NETLIPSEnetlipse.eu/media/82468/3-bucharest-ilfov-multimodal-hub-by-remus... · Intermodal transport project ... arising from the use of multimodal

Logistic and Re-export Hub for Central and Eastern Europe - Romanian Gateway MINISTRY OF ECONOMY MINISTRY OF TRANSPORT

Page 11: Intermodal transport project - NETLIPSEnetlipse.eu/media/82468/3-bucharest-ilfov-multimodal-hub-by-remus... · Intermodal transport project ... arising from the use of multimodal

The project’s relevance in the context of the Trans-European Network for Transportation - TEN-T Programme

√ Helps connect the main national ways of transportation with TEN-T’s Priority Axis, mainly PA 7 (Igoumenitsa/Patras-Atena- Sofia -Budapest - Nădlac - Sibiu - Bucharest/Constanţa), PA 22 (NRC - Athens - Sofia - Budapest - Viena - Prague - Nürenberg/Dresda-Curtici - Braşov - Bucharest/Constanța), Pan-European Corridor IV and Pan -European Corridor IX.

√ Improves the European Market and the economical and social cohesion at European level

√ Assures a sustainable mobility for persons and goods in the best social, environmental and safety conditions integrating all modes of transport

√ Strengthens the Pan European transport network’s capacity, reducing both the transport distances and the bottlenecks created on the main transport ways, and the transport time

√ Creates an integrated European network through the interconnection of various ways of transportation into a multimodal network

Page 12: Intermodal transport project - NETLIPSEnetlipse.eu/media/82468/3-bucharest-ilfov-multimodal-hub-by-remus... · Intermodal transport project ... arising from the use of multimodal

The project’s relevance in the context of the Trans-European Network for Transportation - TEN-T Programme

Page 13: Intermodal transport project - NETLIPSEnetlipse.eu/media/82468/3-bucharest-ilfov-multimodal-hub-by-remus... · Intermodal transport project ... arising from the use of multimodal

INTERMODAL PLATFORM for railway, road and airway transport

RAILWAY CARGO

TERMINAL

THE NATIONAL RAILWAY

AND ROAD NETWORKS

LOGISTIC PARK

INTELLIGENT TRANSPORT

SYSTEM (ITS)

CARGO TERMINAL IN THE AIRPORT

AND RAILWAY STATION

FOR PASSENGERS

“BIMH: Bucharest - Ilfov Multimodal Hub”

Structure

Page 14: Intermodal transport project - NETLIPSEnetlipse.eu/media/82468/3-bucharest-ilfov-multimodal-hub-by-remus... · Intermodal transport project ... arising from the use of multimodal

Proposal for the BIMH project’s capacity and functionality

Multimodal railway platform

• A transfer cargo capacity of approx. 800.000 – 1.2 mil tons per year,

approx 90.000-100.000 TEU/year.

• Double access (in both directions) to CFR’s Balotești-Bucharest (North Station)

(a Feasibility Study for electrification already exists, commisioned by CFR).

• 5 electrified railways of 750 meters each are proposed for the interior,

in order to load / unload.

• A train – auto cargo zone will have 2 electrical cranes of 45 tons each.

• A temporary cargo handling / storing area of 12.000/50.000 square meters.

• Storage and handling for all types of cargo and containers, including reefers.

Page 15: Intermodal transport project - NETLIPSEnetlipse.eu/media/82468/3-bucharest-ilfov-multimodal-hub-by-remus... · Intermodal transport project ... arising from the use of multimodal

Proposal for the BIMH project’s capacity and functionality

Page 16: Intermodal transport project - NETLIPSEnetlipse.eu/media/82468/3-bucharest-ilfov-multimodal-hub-by-remus... · Intermodal transport project ... arising from the use of multimodal

Proposal for the BIMH project’s capacity and functionality

Multimodal Cargo Airport Platform - Located close to the A2 motorway in an area of about 80 ha, it has been the subject of the feasibility study contained in “The Airport Infrastructure Development Strategic Program” Its traffic operating capacity is for about 50 tons/hour (arrivals and departures) and a maximum storage capacity of 400 tons/day (arrivals and departures). For both flows, it will provide a storage capacity for perishable food freight of maximum 200.000 tons/year. Multimodal Cargo Airport Platform Structure: - Multi Aircraft Ramp System (MARS), allowing for simultaneous service to 10 aircraft with

large fuselages (IATA code E) or 20 middle-sized fuselage aircraft (IATA code C).

- Interim storage capacity – extensible platform, 6 modules from 35.000 tons/yearly to maximum 200.000 tons/year (planned for 10 tons/square meters) - semi-automated, efficient ULD/Cargo handling, traceability for location of shipments and containers/pallets. One electrified rail line for freight (750 m) with 2 access points – assuring the connection with the national rail network.

Page 17: Intermodal transport project - NETLIPSEnetlipse.eu/media/82468/3-bucharest-ilfov-multimodal-hub-by-remus... · Intermodal transport project ... arising from the use of multimodal

www.bucharestairports.ro

Calea Bucurestilor Nr.224 E

Otopeni-Romania

www.otp-airport.ro, www.baneasa-airport.ro

TEL: +40 21 201 33 04, FAX: +40 21 201 49 90

SITA: OTPAPXH, BBUAPXH, TELEX: ROPRAYD, LRBSRAYD,

E-MAIL: [email protected], [email protected]

Multimodal Cargo Platform

Terminal

Taxiway System

Aprons

High Tech Park

Commercial Area

Access Roads

Airport Infrastructure Development Strategic Program

at BHCIA – Stage 2

Proposal for the BIMH project’s capacity and functionality

Page 18: Intermodal transport project - NETLIPSEnetlipse.eu/media/82468/3-bucharest-ilfov-multimodal-hub-by-remus... · Intermodal transport project ... arising from the use of multimodal

Passenger Railway Terminal

Located inside the airport terminal between the two motorways, and sized with

3 platforms of 350 m for 2 tracks, electrified, and ERTMS level 1 ready. This

Passenger Terminal, together with Multimodal Cargo Airport Platform and direct

connection between the airport and the main railway station in Bucharest

(Bucharest North Railway Station) was the subject of the abovementioned feasibility

study “The Airport Infrastructure Development Strategic Program”.

Page 19: Intermodal transport project - NETLIPSEnetlipse.eu/media/82468/3-bucharest-ilfov-multimodal-hub-by-remus... · Intermodal transport project ... arising from the use of multimodal

Proposal for the BIMH project’s capacity and functionality

ILFOV LOGISTICS PARK Developed in the proximity of the CFR (Romanian Railways Company) multimodal platform, on an area of 60 – 80 ha, with direct road connections to the railway and airway multimodal platform. It has a modular design, with storage spaces for all types of goods.

Page 20: Intermodal transport project - NETLIPSEnetlipse.eu/media/82468/3-bucharest-ilfov-multimodal-hub-by-remus... · Intermodal transport project ... arising from the use of multimodal

Industrial Park

Objectives:

• Attracting investors in the county and/or keeping the ones that already exist by offering locations that have the appropriate equipment and facilities

• Creating job for the local labor force

Estimated budget: EUR 100,000,000

Potential partners: Local Councils

Potential financing sources: ERDF, local budgets, own funds, PPP

.

Page 21: Intermodal transport project - NETLIPSEnetlipse.eu/media/82468/3-bucharest-ilfov-multimodal-hub-by-remus... · Intermodal transport project ... arising from the use of multimodal

Technical and scientific park

Objectives:

• Attracting high-tech companies / activity interested in capitalizing on the R&D infrastructure created through the ELI NP project

• Creation of local jobs in knowledge-based economic areas

• Maximizing the economic impact of the ELI NP project

Estimated budget: EUR 100,000,000

Possible location: Măgurele town and its neighboring communes

Potential Partners: Măgurele Townhall, INCD IFIN Horia Hulubei

Potential financing sources: ERDF, local budgets, PPP

Page 22: Intermodal transport project - NETLIPSEnetlipse.eu/media/82468/3-bucharest-ilfov-multimodal-hub-by-remus... · Intermodal transport project ... arising from the use of multimodal

Mini - Romania Park

Objectives:

• Developing a tourism park in the north area of Ilfov County;

• Promoting the sights of Romania;

Estimated budget: EUR 25,000,000

Possible location: The north area of Ilfov County

Potential Partners: Local Councils, private partners, Ministry of Tourism

Potential financing sources: ERDF, local budgets, PPP

Page 23: Intermodal transport project - NETLIPSEnetlipse.eu/media/82468/3-bucharest-ilfov-multimodal-hub-by-remus... · Intermodal transport project ... arising from the use of multimodal

ILFOV COUNTY COUNCIL

Thank you!