introduction narmada cement-jafrabad works ultratech...

67
1 INTRODUCTION Narmada Cement-Jafrabad Works a unit of UltraTech Cement Ltd. had setup a cement clinkerisation unit at village Babarkot, Taluka-Jafarabad in Dist. Amreli of Gujarat having capacity of 1.5 million tonnes per annum. The cement plant was commissioned in 1981. UltraTech Cement Limited, a flagship of Aditya Birla Group, is today the youngest and one of the most dynamically growing cement companies in India. UltraTech has always been proud of its part in nation-building and creating lasting relationships. It is among the leading cement manufacturer in the world. UltraTech is India's single largest producer with 69.3 MTPA capacity with market share of 18% and also the largest exporter of cement clinker spanning over to export markets in countries across the Indian Ocean, Africa, Europe and the Middle East. UltraTech and its subsidiaries have a presence in 5 countries through 12 integrated plants, 1 white cement plant, 1 clinkerisation plant, 19 grinding units,2 wall care putty plants, 7 bulk terminals and more than 100 RMC plants. The company is set for further increasing its market share with its ambitious plan of acquisition of JP Associates 21.20 MT capacity. Govt. of Gujarat issued a Letter of Intent (LOI) vide letter no. MCR-102011-ML-739-CHH.1 dt.04.02.2012 over an area of 49.8454 ha for grant of lease and advised to submit an approved Mining Plan under MCR. (Annexure - I) The State Govt has finalised guidelines for grant of mining lease of limestone and identified pending cases under sec. 6(1)(B) & 10 A (1)(C) of MMDR Amendment Act-2015. The case of Narmada Cement-Jafrabad Works of UltraTech Cement Ltd. was also included in the list and under active consideration for grant. (Annexure-II) Therefore the unit is submitting this Mining Plan for approval for grant of the lease. Submission of Mining Plan: - In compliance of LoI issued by State Govt., the Mining Plan with Progressive Mine Closure Plan is prepared and submitted under Rule 17 of Minerals (other than Atomic & Hydrocarbon Energy Minerals) Concession Rules, 2016 and 23(B)(3) of MCDR, 1988 for first five financial years i.e. from the date of lease execution.

Upload: vantuyen

Post on 21-Apr-2018

604 views

Category:

Documents


15 download

TRANSCRIPT

Page 1: INTRODUCTION Narmada Cement-Jafrabad Works UltraTech ...environmentclearance.nic.in/writereaddata/FormB/TOR/Additional... · 1 INTRODUCTION Narmada Cement-Jafrabad Works a unit of

   

  1

INTRODUCTION Narmada Cement-Jafrabad Works a unit of UltraTech Cement Ltd. had setup a cement clinkerisation unit at village Babarkot, Taluka-Jafarabad in Dist. Amreli of Gujarat having capacity of 1.5 million tonnes per annum. The cement plant was commissioned in 1981. UltraTech Cement Limited, a flagship of Aditya Birla Group, is today the youngest and one of the most dynamically growing cement companies in India. UltraTech has always been proud of its part in nation-building and creating lasting relationships. It is among the leading cement manufacturer in the world. UltraTech is India's single largest producer with 69.3 MTPA capacity with market share of 18% and also the largest exporter of cement clinker spanning over to export markets in countries across the Indian Ocean, Africa, Europe and the Middle East. UltraTech and its subsidiaries have a presence in 5 countries through 12 integrated plants, 1 white cement plant, 1 clinkerisation plant, 19 grinding units,2 wall care putty plants, 7 bulk terminals and more than 100 RMC plants. The company is set for further increasing its market share with its ambitious plan of acquisition of JP Associates 21.20 MT capacity. Govt. of Gujarat issued a Letter of Intent (LOI) vide letter no. MCR-102011-ML-739-CHH.1 dt.04.02.2012 over an area of 49.8454 ha for grant of lease and advised to submit an approved Mining Plan under MCR. (Annexure - I) The State Govt has finalised guidelines for grant of mining lease of limestone and identified pending cases under sec. 6(1)(B) & 10 A (1)(C) of MMDR Amendment Act-2015. The case of Narmada Cement-Jafrabad Works of UltraTech Cement Ltd. was also included in the list and under active consideration for grant. (Annexure-II) Therefore the unit is submitting this Mining Plan for approval for grant of the lease. Submission of Mining Plan: - In compliance of LoI issued by State Govt., the Mining Plan with Progressive Mine Closure Plan is prepared and submitted under Rule 17 of Minerals (other than Atomic & Hydrocarbon Energy Minerals) Concession Rules, 2016 and 23(B)(3) of MCDR, 1988 for first five financial years i.e. from the date of lease execution.

Page 2: INTRODUCTION Narmada Cement-Jafrabad Works UltraTech ...environmentclearance.nic.in/writereaddata/FormB/TOR/Additional... · 1 INTRODUCTION Narmada Cement-Jafrabad Works a unit of

   

 

UNIVERSAL FORMAT FOR MINING PLAN/ SCHEME OF MINING INCLUDING PROGRESSIVE MINE CLOSURE PLAN

MINING PLAN WITH PROGRESSIVE MINE CLOSURE PLAN

1.0 GENERAL a) Name of the Applicant/ lessee Narmada Cement - Jafarabad Works

(A Unit of M/s UltraTech Cement Ltd.)

Address: Regd. Office: ‘B’ Wing, 2nd Floor, Ahura Centre, Mahakali Caves Road, Andheri (E)

Works Office: Narmada Cement Jafrabad Works Village: Babarkot Taluka: Jafarabad

District: Mumbai Amreli

State: Maharashtra Gujarat

Pin Code: 400 093 365 540

Phone: 022 – 66917800 02794 245121,

Fax: 022 – 66928109 02794 245110,

e-mail: [email protected]

deepak.mahule @adityabirla.com

Rule 45 IBM Registration Number

IBM/441/2011

b) Status of applicant/ lessee:

(Private individual/ Cooperative Association/ Private Company/ Public Company/ Public Sector Undertaking/ Joint Sector Undertaking)

Public Limited Company registered under the Companies Act – 1956.

Name of partner/ Directors  with full 

address  

List of Board of Directors of M/s UltraTech Cement Limited enclosed as Annexure-III. Nominated Owner: Mr. Krishna Kishore Maheshwari, Managing Director Office Address: B Wing, Ahura Centre, 2nd Floor Mahakali Caves Road, Andheri (East), Mumbai PIN: 400 093 (Maharashtra, India) Phone - 022 – 66917800 Fax - 022 – 66928109 E-mail: [email protected] Refer Annexure-IV for Resolution passed for appointement for Nominated Owner under Mines

Page 3: INTRODUCTION Narmada Cement-Jafrabad Works UltraTech ...environmentclearance.nic.in/writereaddata/FormB/TOR/Additional... · 1 INTRODUCTION Narmada Cement-Jafrabad Works a unit of

   

 

Act, 1952 and also refer Annexure-V for photo ID and address proof of Nominated Owner.

c) Mineral(s) which is / are included in prospecting license (fresh Grant)

It is a case of fresh grant

d) Mineral(s) which is / are included in Letter of Intent/ lease deed.

Limestone

e) Mineral(s) which the lessee intends to mine

Limestone

f) Name of Person under rule 15 of MCR,2016 preparing Mining Plan OR

Rakesh Purohit (BE-Mining) & S.K.Soni (M.Sc.-Geology)

g)

Experience of the Persons prepared the mining plan

Rakesh Purohit: - Total experience of 5 year 6 months & 21 days from 09.01.1991 to 30.07.1996 in BelkaPahar Calcite &Wollastonite Mine of M/s Wolkem India Ltd. S.K. Soni: - Total experience of 5 year 18 days in Dhanappa Limestone Mine of M/s JK Cement Ltd. from 15.01.2011 to 04.04.2012 & in Clay Mine from 01.06.1988 to 31.03.1992. (Annexure-VI)

Address of person who prepared the mining plan-

Rakesh Purohit: - 17E/403, C.H.B., Jodhpur – 342 008 (Raj.) Telefax No.:- (0291) 2706098 Email: [email protected] S.K. Soni: - J3C-1, Subhash Colony, Gali No. 4 Defence Lab. Road, Jodhpur (Raj.)-342 011 Mobile No. 099282 - 92928 Email: [email protected]

Phone number /mobile number As mentioned in above cell

Fax Number As mentioned in above cell

Page 4: INTRODUCTION Narmada Cement-Jafrabad Works UltraTech ...environmentclearance.nic.in/writereaddata/FormB/TOR/Additional... · 1 INTRODUCTION Narmada Cement-Jafrabad Works a unit of

   

 

2.0 LOCATION AND ACCESSIBILITY Lease details Applied ML Area: 49.8454 ha a) Name of mine/ applied area Babarkot Limestone bearing Area b) Lease No. &Mine_code Survey Nos.: Various

(Details of village wise survey no. falling in applied ML area is enclosed as Annexure-VII and Cadastral Plan is enclosed as Pate No.-9) Mine Code: Not applicable

c) Location of mine/ area Village, Tehsil, Police station - District, PIN

Village – Babarkot Taluka – Jafarabad District – Amreli (Guj.)

d) Details of applied/ lease area with location plan-

Forest (Specify)- Protected- Notified-

No forest land involved

Non Forest a) Waste land(Govt.) b) Grazing Land c) Agriculture land d) Others (private)

a) 0.172 b) Nil c) Nil d) 49.6734 Ha

Village wise survey distribution of applied ML area has been tabulated below in Table 2.1.

Khasra no./ survey no.

Details have been enclosed as Annexure-X.

e) Whether the area falls under Coastal Regulation Zone (CRZ)? if yes, details Thereof

No part of applied ML area has been reported to fall under Coastal Regulatory Zone (CRZ).

f) Existence of public road/railway line, if any nearby and approximate distance-

The applied area is located east of Jafarabad town, in the Amreli district of Gujarat. The whole applied area falls in revenue area of Babarkot village. Jafarabad is approachable by State Highway SH-34 which branches off from National Highway 8E (NH 8E) near Rajula. Rajula Railway junction is about 30 km from the applied area and is the terminus of broad gauge railway line from Ahemedabad. The road to Babarkot branches off from SH 34 about 3 km before Jafarabad town. The area is located about 2 km down this road. The nearest airport is Diu (65 km) and Bhavnagar (160 km) is connected by daily air service to Mumbai.

e) Topo sheet No. with latitude & longitude of all corner boundary point/ pillar

The area falls in topo sheet no. 41P/5(Open Series Map No. F42X5 as per new nomenclature) which has been restricted by

Page 5: INTRODUCTION Narmada Cement-Jafrabad Works UltraTech ...environmentclearance.nic.in/writereaddata/FormB/TOR/Additional... · 1 INTRODUCTION Narmada Cement-Jafrabad Works a unit of

   

 

competent authority of the area. The extension of applied ML area is: Latitude 20°53'13.20"N to 20°53'53.3"N & Longitude 71°23'00.10"E to 71°24'32.40"E. Boundary pillars latitude & longitude has been tabulated below.

Table 2.1: Khasra No. falling in applied ML area

Survey no. Area in Ha. Survey no. Area in Ha.83 1.5580 110/1 3.6522 83 1.5479 111/2 0.7689 88 2.6710 111/1 0.172089 2.8531 112/1 1.5985 90 1.4468 114 2.478790 2.4281 119/1 6.2524 92 5.5037 126/1 0.7588 92 1.6187 101 0.030493 2.2157 102/1 1.6067 95 1.8211 102/2 1.608696 0.9309 102/1/1 1.6086 108 1.9425 105 1.5682 109 1.2039 Total 49.8454

Table 2.2: Co-ordinates of extremities applied ML Boundary

Point ID Latitude Longitude 1 N20° 53’ 15.3’’ E71° 24’ 17.7’’ 2 N20° 53’ 15.3" E71° 24’ 17.5’’ 3 N20° 53’ 13.2’’ E71° 24’ 15.7’’ 4 N20° 53’ 13.5’’ E71° 24’ 15.4’’ 5 N20° 53’ 13.9’’ E71° 24’ 15.3’’ 6 N20° 53’ 15.5’’ E71° 24’ 15.2’’ 7 N20° 53’ 17.3’’ E71° 24’ 15.0’’ 8 N20° 53’ 18.8’’ E71° 24’ 15.6’’ 9 N20° 53’ 20.1’’ E71° 24’ 16.6’’ 10 N20° 53’ 23.5’’ E71° 24’ 20.6’’ 11 N20° 53’ 26.2’’ E71° 24’ 19.1’’ 12 N20° 53’ 25.6’’ E71° 24’ 18.3’’ 13 N20° 53’ 26.1’’ E71° 24’ 17.8’’ 14 N20° 53’ 26.7’’ E71° 24’ 18.5’’ 15 N20° 53’ 28.5’’ E71° 24’ 17.8’’ 16 N20° 53’ 30.2’’ E71° 24’ 16.8’’ 17 N20° 53’ 31.8’’ E71° 24’ 19.4’’ 18 N20° 53’ 31.7’’ E71° 24’ 20.6’’ 19 N20° 53’ 31.9’’ E71° 24’ 20.9’’ 20 N20° 53’ 32.3’’ E71° 24’ 21.0’’

Page 6: INTRODUCTION Narmada Cement-Jafrabad Works UltraTech ...environmentclearance.nic.in/writereaddata/FormB/TOR/Additional... · 1 INTRODUCTION Narmada Cement-Jafrabad Works a unit of

   

 

21 N20° 53’ 33.4’’ E71° 24’ 20.3’’ 22 N20° 53’ 33.0’’ E71° 24’ 20.1’’ 23 N20° 53’ 32.0’’ E71° 24’ 18.6’’ 24 N20° 53’ 32.1’’ E71° 24’ 16.5’’ 25 N20° 53’ 32.9’’ E71° 24’ 14.5’’ 26 N20° 53’ 32.3’’ E71° 24’ 14.0’’ 27 N20° 53’ 32.2’’ E71° 24’ 12.9’’ 28 N20° 53’ 33.7’’ E71° 24’ 12.4’’ 29 N20° 53’ 35.2’’ E71° 24’ 12.0’’ 30 N20° 53’ 36.8’’ E71° 24’ 11.9’’

30A N20° 53’ 36.6’’ E71° 24’ 11.4’’ 31 N20° 53’ 35.5’’ E71° 24’ 11.0’’ 32 N20° 53’ 36.4’’ E71° 24’ 10.4’’ 33 N20° 53’ 37.0’’ E71° 24’ 09.9’’ 34 N20° 53’ 36.7’’ E71° 24’ 09.7’’ 35 N20° 53’ 35.3’’ E71 24 08.4’’ 36 N20° 53’ 34.6’’ E71° 24’ 05.6’’ 37 N20° 53’ 34.4’’ E71° 24’ 04.4’’ 38 N20° 53’ 33.8’’ E71° 24’ 02.8’’

38A N20° 53’ 32.7’’ E71° 24’ 02.6’’ 39 N20° 53’ 31.3’’ E71° 24’ 02.4’’ 40 N20° 53’ 30.0’’ E71° 24’ 02.5’’ 41 N20° 53’ 29.7’’ E71° 24’ 02.7’’ 42 N20° 53’ 29.5’’ E71° 24’ 02.3’’ 43 N20° 53’ 29.0’’ E71° 24’ 02.3’’ 44 N20° 53’ 27.3’’ E71° 24’ 00.5’’ 45 N20° 53’ 27.5’’ E71° 24’ 00.1’’ 46 N20° 53’ 27.9’’ E71 23 59.9’’ 47 N20° 53’ 27.5’’ E71 23 59.0’’

47A N20° 53’ 27.6’’ E71 23 58.7’’ 48 N20° 53’ 28.0’’ E71 23 57.0’’

48A N20° 53’ 28.2’’ E71 23 56.9’’ 49 N20° 53’ 28.8’’ E71 23 57.1’’ 50 N20° 53’ 29.1’’ E71 23 57.0’’

50A N20° 53’ 30.4’’ E71 23 57.8’’ 51 N20° 53’ 32.3’’ E71 23 59.0’’ 52 N20° 53’ 33.9’’ E71° 24’ 00.7’’ 53 N20° 53’ 35.7’’ E71° 24’ 01.7’’ 54 N20° 53’ 36.9’’ E71° 24’ 01.9’’ 55 N20° 53’ 37.4’’ E71° 24’ 02.3’’ 56 N20° 53’ 38.0’’ E71° 24’ 02.3’’ 57 N20° 53’ 38.3’’ E71° 24’ 01.8’’

Page 7: INTRODUCTION Narmada Cement-Jafrabad Works UltraTech ...environmentclearance.nic.in/writereaddata/FormB/TOR/Additional... · 1 INTRODUCTION Narmada Cement-Jafrabad Works a unit of

   

 

58 N20° 53’ 38.4’’ E71° 24’ 00.2’’ 59 N20° 53’ 37.4’’ E71° 23’ 58.5’’ 60 N20° 53’ 37.2’’ E71° 23’ 57.8’’ 61 N20° 53’ 40.0’’ E71° 23’ 57.6’’ 62 N20° 53’ 41.9’’ E71° 23’ 57.6’’ 63 N20° 53’ 42.3’’ E71° 23’ 57.9’’ 64 N20° 53’ 43.0’’ E71° 23’ 57.7’’ 65 N20° 53’ 43.8’’ E71° 23’ 58.4’’ 66 N20° 53’ 44.8’’ E71 23’ 58.8’’ 67 N20° 53’ 45.7’’ E71° 23’ 58.7’’ 68 N20° 53’ 46.4’’ E71° 23’ 59.6’’ 69 N20° 53’ 46.1’’ E71° 24’ 00.1’’ 70 N20° 53’ 47.2’’ E71° 24’ 02.0’’ 71 N20° 53’ 47.5’’ E71° 24’ 02.1’’ 72 N20° 53’ 46.9’’ E71° 24’ 03.6’’ 73 N20° 53’ 48.2’’ E71° 24’ 06.0’’ 74 N20° 53’ 50.8’’ E71° 24’ 05.6’’ 75 N20° 53’ 52.2’’ E71° 24’ 06.0’’ 76 N20° 53’ 53.5’’ E71° 24’ 07.6’’ 77 N20° 53’ 53.2’’ E71° 24’ 07.9’’ 78 N20° 53’ 53.7’’ E71° 24’ 08.5’’ 79 N20° 53’ 53.2’’ E71° 24’ 08.5’’ 80 N20° 53’ 51.8’’ E71° 24’ 10.5’’ 81 N20° 53’ 53.7’’ E71° 24’ 13.8’’ 82 N20° 53’ 54.0’’ E71° 24’ 15.6’’ 83 N20° 53’ 55.9’’ E71° 24’ 18.0’’ 84 N20° 53’ 54.9’’ E71° 24’ 18.9’’ 85 N20° 53’ 54.1’’ E71° 24’ 18.5’’ 86 N20° 53’ 53.6’’ E71° 24’ 18.4’’ 87 N20° 53’ 53.4’’ E71° 24’ 16.6’’ 88 N20° 53’ 52.4’’ E71° 24’ 15.2’’ 89 N20° 53’ 51.7’’ E71° 24’ 16.0’’

89A N20° 53’ 51.1’’ E71° 24’ 15.8’’ 89B N20° 53’ 51.0’’ E71° 24’ 16.2’’ 89C N20° 53’ 49.9’’ E71° 24’ 17.3’’ 89D N20° 53’ 49.0’’ E71° 24’ 17.2’’ 98 N20° 53’ 49.0’’ E71° 24’ 14.0’’ 99 N20° 53’ 48.6’’ E71° 24’ 13.7’’ 100 N20° 53’ 47.9’’ E71° 24’ 15.6’’ 101 N20° 53’ 47.8’’ E71° 24’ 17.2’’ 102 N20° 53’ 47.3’’ E71° 24’ 18.4’’ 103 N20° 53’ 46.9’’ E71 24’ 17.7’’

Page 8: INTRODUCTION Narmada Cement-Jafrabad Works UltraTech ...environmentclearance.nic.in/writereaddata/FormB/TOR/Additional... · 1 INTRODUCTION Narmada Cement-Jafrabad Works a unit of

   

 

104 N20° 53’ 46.9’’ E71° 24’ 16.5’’ 105 N20° 53’ 46.3’’ E71° 24’ 15.4’’ 106 N20° 53’ 45.4’’ E71° 24’ 15.1’’ 107 N20° 53’ 44.9’’ E71° 24’ 12.2’’ 108 N20° 53’ 45.6’’ E71° 24’ 12.0’’ 109 N20° 53’ 46.4’’ E71° 24’ 10.7’’ 110 N20° 53’ 45.9’’ E71° 24’ 08.9’’ 111 N20° 53’ 45.4’’ E71° 24’ 08.4’’ 112 N20° 53’ 44.4’’ E71° 24’ 08.2’’ 113 N20° 53’ 43.6’’ E71° 24’ 08.4’’ 114 N20° 53’ 43.3’’ E71° 24’ 07.6’’ 115 N20° 53’ 42.0’’ E71° 24’ 07.2’’ 116 N20° 53’ 41.0’’ E71° 24’ 06.0’’ 117 N20° 53’ 40.2’’ E71° 24’ 06.3’’ 118 N20° 53’ 42.4’’ E71° 24’ 08.4’’ 119 N20° 53’ 42.2’’ E71 24 09.7’’ 120 N20° 53’ 43.5’’ E71° 24’ 11.8’’ 121 N20° 53’ 42.5’’ E71° 24’ 12.9’’ 122 N20° 53’ 41.1’’ E71° 24’ 12.0’’ 123 N20° 53’ 40.0’’ E71° 24’ 12.2’’ 124 N20° 53’ 39.1’’ E71° 24’ 13.4’’ 125 N20° 53’ 38.5’’ E71° 24’ 15.5’’ 126 N20° 53’ 39.7’’ E71° 24’ 17.5’’ 127 N20° 53’ 36.9’’ E71° 24’ 18.2’’ 128 N20° 53’ 37.1’’ E71° 24’ 19.0’’ 129 N20° 53’ 39.4’’ E71° 24’ 22.1’’ 130 N20° 53’ 40.2’’ E71° 24’ 23.9’’ 131 N20° 53’ 38.4’’ E71° 24’ 24.7’’ 132 N20° 53’ 37.4’’ E71° 24’ 23.6’’ 133 N20° 53’ 35.4’’ E71° 24’ 24.1’’ 134 N20° 53’ 35.1’’ E71° 24’ 23.8’’ 135 N20° 53’ 35.1’’ E71° 24’ 24.6’’ 136 N20° 53’ 35.4’’ E71° 24’ 25.1’’ 137 N20° 53’ 36.0’’ E71° 24’ 25.2’’ 138 N20° 53’ 36.3’’ E71° 24’ 24.8’’ 139 N20° 53’ 37.0’’ E71° 24’ 24.8’’ 140 N20° 53’ 38.6’’ E71° 24’ 26.3’’ 141 N20° 53’ 39.4’’ E71° 24’ 28.9’’ 142 N20° 53’ 38.5’’ E71° 24’ 29.0’’ 143 N20° 53’ 38.5’’ E71° 24’ 29.4’’ 144 N20° 53’ 36.3’’ E71° 24’ 29.1’’ 145 N20° 53’ 32.6’’ E71° 24’ 28.5’’

Page 9: INTRODUCTION Narmada Cement-Jafrabad Works UltraTech ...environmentclearance.nic.in/writereaddata/FormB/TOR/Additional... · 1 INTRODUCTION Narmada Cement-Jafrabad Works a unit of

   

 

146 N20° 53’ 27.7’’ E71° 24’ 27.7’’ 147 N20° 53’ 23.7’’ E71° 24’ 27.4’’ 148 N20° 53’ 19.9’’ E71° 24’ 26.2’’ 149 N20° 53’ 19.5’’ E71° 24’ 25.7’’ 150 N20° 53’ 18.5’’ E71° 24’ 23.4’’ 151 N20° 53’ 18.0’’ E71° 24’ 22.0’’ 152 N20° 53’ 17.2’’ E71° 24’ 19.8’’ 153 N20° 53’ 16.0’’ E71° 24’ 18.7’’ 161 N20° 53’ 47.5’’ E71° 24’ 31.5’’ 162 N20° 53’ 48.0’’ E71° 24’ 31.9’’ 163 N20° 53’ 48.7’’ E71° 24’ 32.2’’ 164 N20° 53’ 49.1’’ E71° 24’ 32.3’’

164A N20° 53’ 49.2’’ E71° 24’ 32.1’’ 165 N20° 53’ 49.8’’ E71° 24’ 32.4’’ 166 N20° 53’ 50.6’’ E71° 24’ 32.3’’ 167 N20° 53’ 50.7’’ E71° 24’ 32.1’’

167A N20° 53’ 49.8’’ E71° 24’ 31.4’’ 168 N20° 53’ 49.3’’ E71° 24’ 30.7’’ 169 N20° 53’ 50.6’’ E71° 24’ 29.9’’ 170 N20° 53’ 50.9’’ E71° 24’ 29.4’’ 171 N20° 53’ 52.3’’ E71° 24’ 29.3’’ 172 N20° 53’ 52.3’’ E71° 24’ 28.8’’ 173 N20° 53’ 52.0’’ E71° 24’ 28.3’’ 174 N20° 53’ 52.5’’ E71° 24’ 28.2’’ 175 N20° 53’ 53.0’’ E71° 24’ 28.2’’ 176 N20° 53’ 53.3’’ E71° 24’ 28.1’’ 177 N20° 53’ 53.3’’ E71° 24’ 27.3’’

177A N20° 53’ 52.7’’ E71° 24’ 26.5’’ 177B N20° 53’ 52.1’’ E71° 24’ 25.4’’ 178 N20° 53’ 50.8’’ E71° 24’ 23.4’’ 179 N20° 53’ 50.8’’ E71° 24’ 23.1’’ 180 N20° 53’ 50.7’’ E71° 24’ 22.1’’ 181 N20° 53’ 49.1’’ E71° 24’ 21.5’’

181A N20° 53’ 49.0’’ E71° 24’ 20.8’’ 181B N20° 53’ 49.0’’ E71° 24’ 20.2’’ 181C N20° 53’ 49.0’’ E71° 24’ 19.7’’ 182 N20° 53’ 49.0’’ E71° 24’ 19.4’’

182A N20° 53’ 46.8’’ E71° 24’ 19.3’’ 183 N20° 53’ 46.3’’ E71° 24’ 19.2’’ 184 N20° 53’ 44.6’’ E71° 24’ 17.6’’ 185 N20° 53’ 44.8’’ E71° 24’ 17.0’’ 186 N20° 53’ 44.3’’ E71° 24’ 16.4’’

Page 10: INTRODUCTION Narmada Cement-Jafrabad Works UltraTech ...environmentclearance.nic.in/writereaddata/FormB/TOR/Additional... · 1 INTRODUCTION Narmada Cement-Jafrabad Works a unit of

   

10 

 

186A N20° 53’ 43.7’’ E71° 24’ 16.3’’ 186B N20° 53’ 43.5’’ E71° 24’ 16.2’’ 187 N20° 53’ 43.2’’ E71° 24’ 16.0’’ 188 N20° 53’ 42.5’’ E71° 24’ 16.6’’ 189 N20° 53’ 42.6’’ E71° 24’ 17.8’’ 190 N20° 53’ 42.2’’ E71° 24’ 18.4’’ 191 N20° 53’ 41.5’’ E71° 24’ 18.4’’ 192 N20° 53’ 40.6’’ E71° 24’ 19.3’’

192A N20° 53’ 41.3’’ E71° 24’ 19.8’’ 193 N20° 53’ 42.2’’ E71° 24’ 20.4’’ 194 N20° 53’ 43.2’’ E71° 24’ 22.6’’ 195 N20° 53’ 43.8’’ E71° 24’ 23.1’’ 196 N20° 53’ 43.8’’ E71° 24’ 22.5’’ 197 N20° 53’ 44.9’’ E71° 24’ 22.5’’ 198 N20° 53’ 44.8’’ E71° 24’ 23.3’’ 199 N20° 53’ 45.9’’ E71° 24’ 24.8’’ 200 N20° 53’ 45.8’’ E71° 24’ 26.5’’ 201 N20° 53’ 46.6’’ E71° 24’ 27.6’’ 202 N20° 53’ 45.9’’ E71° 24’ 30.0’’ 203 N20° 53’ 46.5’’ E71° 24’ 30.6’’ 204 N20° 53’ 46.7’’ E71° 24’ 31.2’’ 205 N20° 53’ 47.0’’ E71° 24’ 31.2’’ 206 N20° 53’ 47.9’’ E71° 24’ 23.7’’ 207 N20° 53’ 49.7’’ E71° 24’ 26.0’’ 208 N20° 53’ 50.8’’ E71° 24’ 26.2’’ 209 N20° 53’ 51.4’’ E71° 24’ 26.8’’ 210 N20° 53’ 51.7’’ E71° 24’ 26.6’’ 211 N20° 53’ 51.8’’ E71° 24’ 25.8’’ 212 N20° 53’ 51.1’’ E71° 24’ 24.6’’ 213 N20° 53’ 50.6’’ E71° 24’ 24.4’’ 214 N20° 53’ 50.4’’ E71° 24’ 23.8’’ 215 N20° 53’ 48.4’’ E71° 24’ 22.0’’ 216 N20° 53’ 48.2’’ E71° 24’ 22.2’’

Page 11: INTRODUCTION Narmada Cement-Jafrabad Works UltraTech ...environmentclearance.nic.in/writereaddata/FormB/TOR/Additional... · 1 INTRODUCTION Narmada Cement-Jafrabad Works a unit of

   

11 

 

3.0 DETAILS OF APPROVED MINING PLAN & MODIFIED MINING PLAN 3.1 Date and reference of earlier approved MP/ SOM S.N. Type of

document & rule under which prepared

Approval letter no. & date

Lease area for which approval given (ha)

Proposal from – to

Not applicable as it is a case of fresh grant. 3.2 Details of last modifications if any (for approved MP/ SOM, indicating date of

approval, reason for modification the previous approved period) of Not applicable as it is a case of fresh grant. 3.3 REVIEW OF EARLIER APPROVED PROPSAL-

(Exploration, Development & Reclamation etc.) items Proposals Actual work done Remarks Not applicable as it is a case of fresh grant.

3.4 Give status of compliance of violations pointed out by IBM Not applicable as it is a case of fresh grant. 3.5 Indicate and give details of any

suspension/ closure/ prohibitory order issued by any Government agency under any rule or Court of law.

Not applicable as it is a case of fresh grant.

3.6 In case the MP/ SOM is

submitted under rules 9 and 10 of the MCDR’88 or under rule 17 of the MCR’2016 for approval of modification, specify reason and justification for modification under these rules.

Yes, mining plan is submitted under the provision of MCR, 2016.

Page 12: INTRODUCTION Narmada Cement-Jafrabad Works UltraTech ...environmentclearance.nic.in/writereaddata/FormB/TOR/Additional... · 1 INTRODUCTION Narmada Cement-Jafrabad Works a unit of

   

12 

 

PART – A 1.0 GEOLOGY AND EXPLORATION

(a) Briefly describe the topography, drainage pattern, vegetation, climate and rainfall data of the area applied/mining lease area.

Topography & Drainage Pattern:The area has generally flat to gently undulating topography. There are limestone cliffs along the sea coast near Jafarabad and Babarkot villages. There is large mud flat forming marshy land connected by Jafarabad creek. The highest contour at 48m runs in south eastern area and lowest contour of 30m runs in southern part of the applied area. The applied area and even the surroundings are exposed as comparatively sub undulating terrain of limestone dominated by the milliolitic limestone. The applied area is surrounded by two working and captives mines of UltraTech Cement Ltd, The Narmada Cement-Jafrabad Works & Gujarat Cement works.. The surrounding mining leases are under active working feeding to its two clinkerisation units. The applied area is lying in between these mining leases and geologically no changes observed. There are three old pits viz OP-1, OP-2 & OP-3 near boundary pillar no. 14, 33 & 55 respectively which are covered by windblown sand. There is neither any perennial nor seasonal drainage system existing within the applied area. In the area drainage is developed by Raidi river which is ephermal in nature and roughly flowing north to south at a distance of 8 Kms in a NE direction from the area and eventually merges into Jafarabad creek. General slope towards south & west direction and rainwater flows along slope. Climate & Rainfall: The climate of the area is characterized by general dryness (except during the south-west monsoon season) and hot summer. The temperature ranges from 9.4oC to 42.2oC. The rainy season extends from mid June to mid September. The mean annual rainfall has been recorded as 819 mm. The relative humidity is generally high during the period from June to September and is least during the January-February period. The predominant wind direction from May to September is from West and South West while in the post monsoon and winter it is from SW to NE. In April to June the sky remains cloudless and moderately clouded during July to September. Vegetation: The applied ML area is not having any indications of good vegetation. The applied ML area is generally devoid of large trees which includes very poor vegetal cover, Acacia Nilotica Acacia ninuata, Prosopis juliflora are some of the common species. Besides common trees, natural vegetation grows mostly during monsoon and fades away with the onset of summer. The area does not have any rare and endangered species.

(b) Brief descriptions of Regional Geology with reference to location of lease/ applied area.

Regional Geology of the Area The Deccan-Trap-covered coastal region of Saurashtra had experienced a number of marine transgressions and regressions during the late Tertiary Period. The rich limestone beds of the region were deposited by the accumulation of calcium-rich forameniferal (Miliolitic) crust and chemical precipitation of carbonates from the shallow sea. Land-derived material from volcanic constituted the impurities in the limestone deposit. The regional geological set up of the Coastal Saurashtra Region is given in Table: A1.1.

Page 13: INTRODUCTION Narmada Cement-Jafrabad Works UltraTech ...environmentclearance.nic.in/writereaddata/FormB/TOR/Additional... · 1 INTRODUCTION Narmada Cement-Jafrabad Works a unit of

   

13 

 

Table A1.1: Regional Stratigraphic Sequence of Rocks Age Formation Lithology

Holocene Recent Wind-blown sand, Fluviao-marine deposits.

Sub-recent to Pleistocene Porbandar Beds Miliolitic limestone, Marl, Calcareous shale, etc.

Pleistocene to Pliocene Dwarka Beds Cherty limestone, Clay, Silt. Pliocene to Miocene Gaj Beds Variegated clay, Marl, Impure

limestone, etc. Eocene Supratrappean Impure limestone, Calcareous

sandstone, Lateritic rock. Eocene to Cretaceous Deccan Trap and

Intertrappean Basaltic rock, with minor

Intertrappean clay. Traps: Deccan Traps occupy most of the area. They include several types of volcanic rocks, which have come up through fissures in several eruptive phases. The main rock types encountered are intermediate types of basalt, trachyte, diorite, rhyolite, etc. The hilltops generally contain the hard and tough, compact massive flows, whereas the soft type occupies the valley floors and the plains. The hard flows stand out, whereas the softer ones are weathered to form low areas. The entire trap rocks show shearing and multi-directional fracturing. Gaj Beds: Gaj beds occur as isolated outcrops at the margin of traps towards coast and as small mounds in the alluvium. They are marine sediments, comprising fossiliferrous yellow marly limestone with clay. Miliolite Limestone: The limestone deposits of the area are termed as “Coastal deposits”. It is marine limestone commonly known as Miliolite Limestone which occurs as thick cross-laminated beds. The name “miliolite” has apparently been derived from the Miliolidae, belonging to the common foraminifera present in the rock. Occurrence of such distinctive type of rocks is reported only along the Saurashtra (Kathiawar) coast and Kutch in Gujarat. Recent Deposits: The youngest deposits in the district are represented by various types of soils, alluvium, windblown sand, fluvio-marine mud deposits of tidal flats and shell and shingle deposits of shore area.

(c) Detailed description of geology of the lease area such as shape and size of the mineral/ ore deposit, disposition various litho-units indicating structural features if any etc. (Applicable for Mining Plan for grant & renewal and not for Scheme of mining/ Modifications in the approved mining plan/scheme of Mining)

Stratigraphic sequence of the applied ML area is as under: 1. Wind Blown Sand 2. Miliolitic limestone intermixed with Marl construe 3. Deccan traps (basalt)

Windblown Sand The younger most geological formation in the ML is windblown sand constitutes the overburden with an average thickness varying from 0.5m to 4.0m. Occupying the flatter grounds, the thickness of overburden is comparatively more towards Kovaya and Vandh village while the thickness decreases towards village Babarkot which is on higher ground.

Page 14: INTRODUCTION Narmada Cement-Jafrabad Works UltraTech ...environmentclearance.nic.in/writereaddata/FormB/TOR/Additional... · 1 INTRODUCTION Narmada Cement-Jafrabad Works a unit of

   

14 

 

Miliolitic limestone Just below the windblown sand, miliolitic limestone occurs as compact limestone & marl of varying thickness which can be average out to 25m. With depth, there is general deterioration in the quality of limestone accompanied by soft, friable layers & lenses of marl. The limestone is buff, yellow or pinkish in colour, while the weathered surfaces show sooty to brownish appearance. The main constituent of the limestone is the calcic shell fragments of Miliola and related organisms. The limestone deposit shows enrichment in calcium content at the upper layers, due probably to leaching out of silica, calcium enrichment by capillary action and re-deposition in crevices. The limestone is generally compact, hard and bouldery in nature at many places. The average quality of limestone is varies in terms of CaO 40.0 to 48.00, SiO2 4.0 to 7.5, Al2O3 1.5 to 3.0 and Fe2O3 1.0 to 2.5. Deccan trap (basalt) Below the limestone, Deccan Traps occupy most of the area. It includes several types or volcanic rocks, which have come up through fissures in several eruptive phases. The main rock types encountered are intermediate types of basalt, trachyte, diorite, rhyolite, etc. The entire trap rocks show shearing and multi-directional fracturing. Structural Features The limestone of this area is miliolitic limestone, which follows general strike N700E- S700W and dips gently in NNW-SSE direction. Minor vertical and inclined joints are present and can be observed all along the mine face.

(d) The Directorate of Geology & Mining, Govt. of Gujarat has explored the area so far as detailed in Table A1.2 below. Besides this, the area has also been explored in the adjoining mining leases (Narmada Cement Mine of Ultratech Cement Ltd.) of the same company in the year 1975-78.

Table A1.2: Details of Exploration Agency S. No.

Name of agency Address E-mail ID Phone No.

1. Commissioner of Geology & Mining (CGM), During 1972-73

Commissionerate of Geology & Mining Government of Gujarat, 7th Floor, Udyog Bhavan, Gandhinagar 382010, Gujarat

[email protected]

+91-79-23254151

(e) Details of prospecting/exploration already carried out: i) Number of pits and trenches indicating dimensions, spacing etc along and across

the strike/ foliation with reference to geological plan. No exploration was carried out by creating pits/ trenches etc. ii) Number of boreholes indicating type (Core/ RC/ DTH), diameter, spacing,

inclination, Collar level, depth etc with standard borehole logs duly marking on geological plan/sections.

   

Page 15: INTRODUCTION Narmada Cement-Jafrabad Works UltraTech ...environmentclearance.nic.in/writereaddata/FormB/TOR/Additional... · 1 INTRODUCTION Narmada Cement-Jafrabad Works a unit of

   

15 

 

Previous Exploration: - The area was explored on regional basis by DGM, Govt. of Gujarat in two phases i.e. in the year 1972-73 in Babarkot village as details tabulated below: -

Table A1.3: Details of Exploration carried out by CGM Phase Year Village No. of

BoreholesDrilling

meterageArea

explored Reserves estimated

1. 1972-73 Babarkot 35 277.35 1.8 sq.km. 50 MT (Annexure-VIII)

Recent Exploration: - Subsequent to the regional geological work of the Directorate of Geology & Mining, Gujarat, UltraTech Cement Ltd. company had engaged private agencies and carried out detailed exploration covering Babarkot, Kovaya leaseholds etc. limestone deposit covering an area more than 3.27 sq. km. The present area is situated between the two leaseholds. The company has been carried detailed exploration in both the surrounding mining leases i.e. Narmada Cement Mines and Kovaya Limestone Mines. Narmada Cement Mine adjoins south western portion of the applied area whereas Kovaya limestone mine in east &south east. The core boreholes drilled in Narmada Cement Mine which falls within the 100m range of applied ML area is: -

Table A1.4: Details of BH carried in the nearby operative mining leases

Bore Hole No. Location

Total Depth Nearest Distance from applied

area BH31236 125 m 34 m BH31334 88 m 30 m BH31134 57 m 30 m BH30534 114 m 30 m BH30432 99 m 38 m BH30130 10 m 34.7 m BH30330 70 m 32 m BH30428 On the boundary 31.5 m BH30726 72 m 45 m BH30424 61 m 41.6 m BH30224 95 m 43.5 m

Table A1.5: Summary of few BH sunk in Narmada Cement Mine (value in %)

BH ID SiO2 Al2O3 Fe2O3 CaO MgO P2O5 K2O LOI LSF

BH30130 14.48 2.54 2.12 43.70 0.76 0.00 0.22 35.00 97.29

BH30224 14.50 3.44 2.82 42.86 0.85 0.16 0.24 34.41 92.20

BH30330 19.46 2.50 2.31 41.44 0.68 0.00 0.20 33.16 70.31

BH30424 16.31 4.09 3.13 41.28 0.96 0.14 0.30 33.25 78.60

BH30428 15.63 2.28 2.10 43.82 0.71 0.00 0.17 35.06 91.66

BH30726 17.53 2.93 2.42 42.26 0.69 0.00 0.23 33.81 78.11

Page 16: INTRODUCTION Narmada Cement-Jafrabad Works UltraTech ...environmentclearance.nic.in/writereaddata/FormB/TOR/Additional... · 1 INTRODUCTION Narmada Cement-Jafrabad Works a unit of

   

16 

 

Table A1.6: Dimensions of old pits & surface outcrops in applied area S. No. Old Pit No./

surface outcrops Length*Width*Depth (m*m*m)

Total area covered (in ha)

1. 1 42*30*2.5 0.10 2. 2 30*23*2.0 0.05 3. 3 18*12* 1.5 0.015

Table A1.7: Lithological sequence observed of old pits & surface outcrops in

applied area S. No. Old Pit No./

surface outcrops Lithogoly observed Thickness of

lighology (m) 1. 1 Sand

Limestone 1.0 1.5

2. 2 Sand Limestone

0.75 1.25

3. 3 Sand Limestone

0.50 1.00

Table A1.5: Summary analysis of surface samples picked up from the area (%)

Sample ID SiO2 Al2O3 Fe2O3 CaO MgO P2O5 K2O LSF

BKT/L-1/1 9.08 2.00 1.83 47.14 0.53 0.03 0.06 162.76

BKT/L-1/2 7.79 1.30 1.36 48.68 0.47 0.02 0.03 200.87

(Annexure-X)In such a total of 11 core bore holes, old pits and surface exposures has been considered for influence for resources and reserves. All the core bore holes sunk in the nearby operative mines is depicted on Surface Geological Plan; Plate No. 4 on scale 1000:1.

iii) Details of samples analysis indicating type of sample (surface/ sub-surface from pits/ trenches/ borehole etc.) Complete chemical analysis for entire strata for all radicals may be undertaken for selected samples from a NABL accredited Laboratory or Government laboratory or equivalent. Entire mineralized area may be analyzed meter wise with 10% of check samples. (At least for 10% of total samples may be analyzed in accordance to BIS and reports from NABL accredited/ other government laboratory). Sample analysis attached from NABL accredited Lab.

The quality of limestone exhibits distinct lateral as well as depth variation. The limestone is mostly of cement grade i.e. below 43.82% CaO. Further the lower level deposit is mostly of inferior limestone/ marl having presence of free silica as compared to the upper level limestone. Deposit Quality The average quality of the entire deposit has been estimated and is summarized below: - ROM Quality of Limestone Since there is little overburden in the form of windblown sand and also not any remarkable intercalations observed within the limestone (as can be seen in the borehole logs and pit face of nearby mining leases) the Run of Mine (RoM) quality of limestone can be considered to be the same as the overall average quality of limestone as estimated for

Page 17: INTRODUCTION Narmada Cement-Jafrabad Works UltraTech ...environmentclearance.nic.in/writereaddata/FormB/TOR/Additional... · 1 INTRODUCTION Narmada Cement-Jafrabad Works a unit of

   

17 

 

the whole of the deposit is summarized below: - Table A1.8: ROM Quality of Mineral in terms of major oxides & LOI

Constituants Assay (%) SiO2 16.42 Al2O3 2.82 Fe2O3 2.44 CaO 42.14 LOI 41.25

iv) Expenditure incurred in various prospecting operations. The area was explored by Govt. of Gujarat. No exploration was carried out in the applied

area as the area was not allotted under prospecting license.

(f) The surface plan of the lease area may be prepared on a scale of 1: 1000 or 1: 2000 with contour interval of maximum of 10 m depending upon the topography and size of the area duly marked by grid lines showing all features indicated under Rule 28(1)(a) of MCDR 1988

The Surface Plan of the lease area prepared on a scale of 1:1000 with contour interval of 2.0 m depending upon the topography of the area duly marked by grid lines showing all features indicated under Rule 28(1)(a) of MCDR 1988 and has been enclosed as Plate No. 3.

(g) For preparation of geological plan, surface plan prepared on a scale of 1: 1000 or 1: 2000 scale specified under para 1.0(f) of Part A of the format may be taken as the base plan. The details of exploration already carried out along with supporting data for existence of mineral, locations proposed exploration, various litho units along with structural features, mineralized/ore zone with grade variation if any may be marked on the geological plan along with other features indicated under Rule 28 (1)(b) of MCDR 1988.

The Surface Geological Plan of the lease area is prepared on a scale of 1:1000 with contour interval of 2.0 m depending upon the topography of the area duly marked by grid lines showing all features indicated under Rule 28(1) (b) of MCDR 1988 and has been enclosed as Plate No. 4.

(h) Geological sections may be prepared on natural scale of geological plan at suitable interval across the lease area from boundary to boundary.

A total of five Geological Sections is prepared at 200 m intervals across the Babarkot Limestone Area. Geological Sections has been enclosed as Plate No. 4A.

(i) Broadly indicate the future programme of exploration with due justification (duly marking on Geological plan year wise location in different colours) taking into consideration the future tentative excavation programme planned in next five years as in table below: -

Year No. of boreholes (Core/RC/DTH)

Grid interval

Total Meterage

No. of Pits, dimensions and volume

No. of Trenches,

dimensions - Although the limestone area is surrounded by big operative mines of limestone & marl

which proves the mineral availability. State govt. has also carried out prospecting work at widely spaced bore holes in the area. Few core boreholes sunk in the surrounding mines

Page 18: INTRODUCTION Narmada Cement-Jafrabad Works UltraTech ...environmentclearance.nic.in/writereaddata/FormB/TOR/Additional... · 1 INTRODUCTION Narmada Cement-Jafrabad Works a unit of

   

18 

 

has supported the presence of mineral. From the nature and extent of the deposit, the quantum and intensity of exploration have been programmed to prove with adequate degree of reliability under geological axis G1. The exploration is required and hence proposed the same during the very first years of mining. The future exploration is proposed in the first year of the applicability of mining plan. It has been proposed a total of 20 core bore holes in unexplored area upto a depth of 40 m vertically each. Details of proposed BH has been tabulated below: -

Proposed Bore Hole No.

Location

N E/W

PBH-1 200N 100E PBH-2 200N 150E PBH-3 400N 200E PBH-4 500N 50E PBH-5 600N 300E PBH-6 640N 100E PBH-7 800N 200E PBH-8 700N 100W PBH-9 500N 500W PBH-10 700N 300W PBH-11 950N 200W PBH-12 800N 500W PBH-13 900N 400W PBH-14 975N 500W PBH-15 1000N 300W PBH-16 1000N 100W PBH-17 1200N 300W PBH-18 1200N 100W PBH-19 1000N 100E PBH-20 1100N 300E

j) Reserves and Resources as per UNFC with respect to the threshold value notified by IBM may be furnished in a tabular form as given below: (Area explored under different level of exploration may be marked on the geological plan and UNFC code for area considered for different categories of reserve/ resources estimation may also be marked on geological cross sections). Submit a feasibility/ pre-feasibility study report along with financial analysis for economic viability of the deposit as specified under the UNFC field guidelines may be incorporated.

Assessment of the deposit has been carried out based on the followings: - 1. Core bore hole data of nearby operative mining leases, bore holes comprising of

topographical data, assay data etc. 2. Old pits available in the area 3. Exposures of mineral in the area 4. Prospecting work carried out by the state govt.

Page 19: INTRODUCTION Narmada Cement-Jafrabad Works UltraTech ...environmentclearance.nic.in/writereaddata/FormB/TOR/Additional... · 1 INTRODUCTION Narmada Cement-Jafrabad Works a unit of

   

19 

 

Estimation of Resources/ Reserves Method adopted for Resources/ Reserves estimation Estimation of resources and reserves has been carried out by cross sectional area method. i) Area and Depth Considered for Resources/ Reserves estimation For estimation of geological resources, the depth considered is based on as encountered in bore hole drilled. ii) Usable Limestone The entire limestone have been considered as usable limestone for manufacture of quality Ordinary Portland Cement (OPC). Thus the cut off limit has been set below as prescribed by CCOM Circular No. 03/2010 dated 14.07.2010 (>34% CaO and <4% of MgO) during estimation of limestone resources/reserves. iii) Ultimate Pit Limit in the Mining Area The ultimate pit limit has been marked on the basis of the extent of mineralization observed within the area of ML. Laterally the boundary barrier within the lease area forms the limit of mining while at depth the ultimate pit limit shall be restricted upto 0 mRL levels. iv) Tonnage Factor An overall tonnage factor of 1.8 has been considered for limestone for this area as the same has been taken for estimation of resources and reserves in the nearby working mines. (Annexure-IX) Resources/ Reserves Categories The resources and reserves of the area has been categorized under different geological axis as per the followings: - 1. Inferred resources (G3 Axis): The first estimate of grade and amount of limestone in a deposit calculated purely based on data available and supplemented by surface exploration. Such an estimate is based on assumed surface continuity and width of the bed on geological evidences, which included information from past nearby mining activity and comparison with similar deposit in the locality. In this case, the reserves which fall outside 100 m zone on either sides of the G2 axis are classified as G3 axis. The area under this category is measured as 30.0454ha. 2. Indicated resources (G2 Axis): This category of resources estimation carried out partly from actual exploration in the nearby area and on geological grounds. The grade and tonnage of the ore blocks shall be calculated on geological grounds based on widely spaced drill holes carried out by state govt. and pits. In this case, the resources/ reserves which are falling between 100 m to 150 m on either sides of the bore holes and upto 00 m above MSL has been classified as Inferred. The area under this category is measured as 7.20ha. 3. Measured resources (G1 Axis): The resources/ reserves estimated by details proving by sinking drill holes by state govt., exposures, old pits and nearby boreholes by the same company has been placed the deposit in this category. In this case, the resources which are falling within the command length of 100 m on either sides of the bore holes, old pits and upto depth of the bore holes has been classified as measured category of resources. The area under this category is measured as 12.60ha. Basis for awarding UNFC code 1) All the reserves falling under G1 axis are placed in the mineable proved i.e. E1, F1

& G1 category (111) based on the availability of mineral in the area and as the

Page 20: INTRODUCTION Narmada Cement-Jafrabad Works UltraTech ...environmentclearance.nic.in/writereaddata/FormB/TOR/Additional... · 1 INTRODUCTION Narmada Cement-Jafrabad Works a unit of

   

20 

 

reserves are falling in the private land and the land is owned by the applicant. This reserve is devoid of mineral resources blocked due to safety barrier, working

to be restricted upto 0 mRL, narrow spaces etc. 2) All the reserves under G2 axis are placed in the category mineable probable i.e.

E1, F2 & G2 category (122) of reserves based on the information available in the area and as the reserves falling in the private land which is owned by the company and pre feasibility study carried out for the said area.

3) The resources under G1 & G2 axis which cannot be mined at present due to working below 0mRL, making safety bench, along statutory boundary barrier etc. are placed under Feasibility Mineral Resources and are classified under code 211 & 222.

4) The resources under the Inferred G3 axis are resources category outside the indicated mineral resources upto applied area boundary is placed under 333.

Pre Feasibility Study Report is enclosed as Annexure-XI. k) Furnish detailed calculation of reserves/ resources section wise (When the mine is

fully mechanized and deposit is of complex nature with variation of size, shape of mineralized zones, grade due to intrusion within ore zone etc, an attempt may be made to estimate reserves/ resources by slice plan method). In case of deposits where underground mining is proposed, reserve/resources may be estimated by level plan method, as applicable, as per the proposed mining parameters.

The resources/ reserves estimation has been carried out by cross-sectional area method. In the estimation, the formation was identified viz. limestone. The cross-sectional area of litho unit is computed by graphic method on each cross section. The average intersectional area is calculated by averaging the cross-sectional areas on two consecutive sections. The average cross sectional area is multiplied by mean distance between two consecutive sections to arrive at the volume. The volumes so determined were converted to weight (in-situ reserves) in tonnes by applying density/ tonnage conversion factor. Finally the mineable reserves have been estimated by depletion of blocked resources. The thickness of mineral varies from place to place; using the influence of boreholes, the average thickness of the mineral bed is 30 m. The deposit is sedimentary origin. The lease area does not contain any structural disturbances. Total 5 (A-A’, B-B’, C-C’, D-D’ & E-E’) cross sections have been drawn across the entire applied lease covering G1, G2 & G3 axis. A distance of 200m has been kept each between two consecutive sections.

Table A1.11: Estimation of reserves/ resources Resources & Reserves (in million tonnes)

Resources & Reserves (in million tonnes)

UNFC Total Limestone

111 4.75 211 0.96

121 & 122 2.81 221 & 222 1.34

333 13.38 Total 23.24 (Refer Annexure-XII for detailed resources/ reserves estimation)

Page 21: INTRODUCTION Narmada Cement-Jafrabad Works UltraTech ...environmentclearance.nic.in/writereaddata/FormB/TOR/Additional... · 1 INTRODUCTION Narmada Cement-Jafrabad Works a unit of

   

21 

 

Estimation loss at 10% has been applied for arriving final figure of resources and reserves in the applied area.

Table A1.11: Estimation of reserves/ resources at 10% loss

Resources & Reserves (in million tonnes)

UNFC Total Limestone

111 4.28211 0.86

121 & 122 2.53221 & 222 1.21

333 12.04Total 20.92

Table A1.17: Resources blocked under various barriers

Particular of blocked R & R area

Mineral Resources Blocked (mill. tonnes)

UPL benching 2.07 Statutory boundary

barrier Below 0mRL 00

Total 2.07

l) Mineral Reserves/ Resources:

Mineral Reserves: (Mineral reserves are optimised at cut off 97 LSF as per plant requirement) CaO * 100 LSF (Lime Saturation Factor) = ------------------------------------------------------ 2.80 * SiO2 + 1.18 * Al2O3 + 0.65 * Fe2O3 Mineral Resources: Calculated based on area of influence and extent of ore body. Total 20.92 million tonnes of geological resources are available. (Mineral resources are being estimated purely based on level of exploration, with reference to the threshold value of minerals declared by IBM)

Level of Exploration Resources in million tonnes Grade G1 - Detailed exploration 5.14 Cement grade G2 - General Exploration 3.74 Cement grade G3 – Prospecting 12.04 Cement grade G4- Reconnaissance - - Resources and Reserves within the lease may be arrived after applying results feasibility/ prefeasibility study and economic evaluation of deposit based on various factors such as: a) Mining method, Recovery factor, mining losses, processing loss etc. b) Cut off grade, Ultimate pit depth proposed. c) Mineral/ ore blocked due to benches, barriers, pillars, road, railway, river, nalah, reservoir, electric line and other statutory barriers etc, under forest, sanctuaries etc. where necessary permissions are not available.

Page 22: INTRODUCTION Narmada Cement-Jafrabad Works UltraTech ...environmentclearance.nic.in/writereaddata/FormB/TOR/Additional... · 1 INTRODUCTION Narmada Cement-Jafrabad Works a unit of

   

22 

 

TABLE A1.18: RESOURCES/ RESERVES OF LIMESTONE UNFC

Code Quantity

(in mill. tonnes)

Grade

Total Limestone

A. Total Mineral Reserve Proved Mineral Reserve 111 4.28 Cement-gr. Probable mineral Reserve 121 & 122 2.53 Cement-gr. B. Total Remaining Resources

Feasibility mineral Resource

211 0.86 Cement-gr.

Prefeasibility mineral resource

221 & 222 1.21 Cement-gr.

Measured mineral resource 331 - Indicated mineral resource 332 - Inferred mineral resource 333 12.04 Cement-gr. Reconnaissance mineral resource

334 -

Total Reserves + Resources 20.92 Cement-gr.

MINE LIFE

At the production rate of 2.5lac TPA Total life of mine is 16 years

Life of mine may be increased subject to conversions of resources under 333 category into category of reserves 111

Page 23: INTRODUCTION Narmada Cement-Jafrabad Works UltraTech ...environmentclearance.nic.in/writereaddata/FormB/TOR/Additional... · 1 INTRODUCTION Narmada Cement-Jafrabad Works a unit of

   

23 

 

2.0 MINING

2.1 A. OPEN CAST MINING: - a) Briefly describe the existing as well as proposed method for excavation with all

design parameters indicating on plans/ sections: - Salient description of proposed mining method

Mining operations is proposed to be carried out by opencast fully mechanized method of mining by making benches of height 6 m (normally 6m) with width 15m and maintaining working bench slope of 750. Conventional method i.e. drilling and blasting is proposed. Surface Miner is also proposed for winning of mineral in case of additional option. Looking towards heterogeneity of deposit, separate mining of limestone is just impossible. Hence entire ROM material is proposed to be feed to crusher directly. The blasting zone would be fixed away from local vicinity in the lease area or may be selected in the running development block with suitable measures. The mineral being free from overburden (except sand) therefore there is no need for any mine development work during mining operation except removal of sand. The excavation, loading and transportation is proposed to be carried out by hydraulic excavator, loader, dumpers and tippers. Drilling is proposed to be done by ICM 260 drill machine with blast hole burden 4.0 m and spacing 5.0m. ANFO is proposed to be used with slurry explosive. Blasting frequency shall be 2 to 3 a week. Safe and controlled basting shall be practised by competent authority as the same is being in practice in nearby working mines of the same unit. Excavator of capacity 4.0 cum shall be used for loading of fragmented rock mass of mineral and transported to crusher situated outside the ML through dumpers and tippers. The details of the installed crusher is: - Type of crusher - Impact Crusher Capacity – 500 tonnes/hr Hourly output- 450 tonnes Output per day 8100 tonnes Besides conventional method, surface miner is proposed in a specific situation which is eco-friendly especially in blocks near habitation and boundary areas. The salient features of surface miner are safe and steady operation, minimum dust generation and low noise. It strips the strata in slices of 25-30 cm thickness and 2-2.2 m width. The Broad parameters of mining operation will be as below:

Number of working days : 300 days/year Working shift/day : 1 shift of 8 hours Working benches : 4 Height : 6.0 +/– 2.0 m Width : For running bench 15 m (min.) for closing bench 4.5 m Bench slope : 750 Ultimate Pit slope : 450

There are old pits (OP-1 to OP-3) present in the mine with maximum level upto 35.8 mRL. The grid reference of extent of all the old pits is from 432N-460N/72E-118E, 721N-745N / 212W-241W and 702N-721N / 343W-356W respectively.

Page 24: INTRODUCTION Narmada Cement-Jafrabad Works UltraTech ...environmentclearance.nic.in/writereaddata/FormB/TOR/Additional... · 1 INTRODUCTION Narmada Cement-Jafrabad Works a unit of

   

24 

 

The dimensions of old pits existing within applied area is: - Table A2.1: Dimensions of old pits exist in applied area

S. No. Old Pit No./ surface outcrops

Length*Width*Depth (m*m*m)

Total area covered (in ha)

1. 1 42*30*2.5 0.10 2. 2 30*23*2.0 0.05 3. 3 18*12* 1.5 0.015

Total 0.165

Refer Surface Plan, Plate No. 3 on scale 1000:1.

b) Indicate year-wise tentative Excavation in Cubic Meters indicating development, ROM, pit wise as in table below.

Opencast method of mining will be practised with fully mechanized means by drilling and blasting. Occasionally surface miner is proposed to be deploy as an second option. Overburden (sand) removal is envisaged from the Babarkot Limestone Area. Total mineable reserves quality stands at 43.8% CaO. To meet the plant quality requirement the ROM supply is optimized at 97 LSF. Thus lower grade mineral from area will be utilized which will eventually lead to mineral conservation. It is proposed to produce 2.5 lac TPA of limestone from the area and remaining from the existing mine and one another applied in the vicinity. ROM quantity comprise of limestone. The production target shall be proposed in line with Consent to Operate. Accordingly development blocks are being proposed. The stripping ratio of limestone to overburden for the first five years of mining operations will be 1:0.05. Details of bench-wise year-wise development and production for the first five years has been given in table below.

Table A2.2: Expected excavation during first five years plan period (in cum)

Year

Over-burden Sand*

Waste Rock

ROM Mineral

Ore:OB

(in cum) (tonnes:cum)

1st 22489 Nil 250000 1:0.09 2nd 19110 Nil 250000 1:0.08 3rd - Nil 250000 1:0.00 4th 25220 Nil 250000 1:0.10 5th - Nil 250000 1:0.00

Total 66819 Nil 1250000 1:0.05 * Overburden sand is windblown sand which is not fertile in nature.

Page 25: INTRODUCTION Narmada Cement-Jafrabad Works UltraTech ...environmentclearance.nic.in/writereaddata/FormB/TOR/Additional... · 1 INTRODUCTION Narmada Cement-Jafrabad Works a unit of

   

25 

 

Table A2.3: Expected excavation during first five years plan period (in tonnes)

Year Saleable/ usable

ROM mineral (tonne)

Sub grade mineral (tonne)

Reject (tonne)

1st 250000 Nil Nil

2nd 250000 Nil Nil

3rd 250000 Nil Nil

4th 250000 Nil Nil

5th 250000 Nil Nil

Total 1250000 Nil Nil

Conversion factor has been taken 1.8 for conversion of volume to tonnage for the purpose of mining of mineral. The development location may change at few locations due to following reasons: - 1) Land acquisition problem. 2) Depending on rainfall, surface water storage/ conservation of water in last bench. 3) Although mine planning has been proposed one location looking towards required quantity, quality and also in the conservation of mineral. A total of fresh area is also proposed under mine planning in view of the advancement of pits. Company is looking forward to have more surface rights which is a continuous process in mining industries. In view of possession of new area and also in quality matter, slight changes may taken place in proposed mine planning & development upto 10-20%.

Page 26: INTRODUCTION Narmada Cement-Jafrabad Works UltraTech ...environmentclearance.nic.in/writereaddata/FormB/TOR/Additional... · 1 INTRODUCTION Narmada Cement-Jafrabad Works a unit of

   

26 

 

Table A2.6: Proposal of Excavation of mineral with R.O.M. Quality and overburden sand to be removed during 1st year Location Bench

RL(m) Area Avg.

bench Ht.

Vol. cum

Vol. OB Soil

ROM Tonnes

Quality

LSF

From To (sq.mt) (m) (cum)

N323 to 571N and 19E to 195E.

38 37 22489 1 22489 22489 -

97 37 36 22489 1 22489 - 40480 36 30 19400 6 116400 - 209520

Total 22489 250000

Table A2.7: Proposal of Excavation of mineral with R.O.M. Quality and overburden sand to be removed during 2nd year

Location Bench RL(m)

Area Avg. bench

Ht.

Vol. cum

Vol. OB Soil

ROM Tonnes

Quality

LSF

From To (sq.mt) (m) (cum)

N 571N to 611N and E 195 to 277E

40 38 19110 1 19110 -

97 38 36 19110 2 38220 - 68796 36 30 16779 6 100674 - 181213

Total 19110 250009

Page 27: INTRODUCTION Narmada Cement-Jafrabad Works UltraTech ...environmentclearance.nic.in/writereaddata/FormB/TOR/Additional... · 1 INTRODUCTION Narmada Cement-Jafrabad Works a unit of

   

27 

 

Table A2.8: Proposal of Excavation of mineral with R.O.M. Quality and overburden sand to be removed during 3rd year Location Bench

RL(m) Area Avg.

bench Ht.

Vol. cum

Vol. OB Soil

ROM Tonnes

Quality

LSF

From To (sq.mt) (m) (cum)

N361 to 482 and E 63 to 275E

30 26 23150 6 138900 - 250020 97

Total - 250020

Table A2.9: Proposal of Excavation of mineral with R.O.M. Quality and overburden sand to be removed during 4th year

Location Bench

RL(m) Area Avg.

bench Ht.

Vol. cum

Vol. OB Soil

ROM Tonnes

Quality

LSF

From To (sq.mt) (m) (cum)

N197 to 392N and 18E 277E.

37 36 25230 1 25230 97 36 30 23150 6 138900 - 250020

Total 25230 250020

Page 28: INTRODUCTION Narmada Cement-Jafrabad Works UltraTech ...environmentclearance.nic.in/writereaddata/FormB/TOR/Additional... · 1 INTRODUCTION Narmada Cement-Jafrabad Works a unit of

   

28 

 

Table A2.10: Proposal of Excavation of mineral with R.O.M. Quality and overburden sand to be removed during 5th year

Location Bench RL(m)

Area Avg. bench

Ht.

Vol. cum

Vol. OB Soil

ROM Tonnes

Quality

LSF

From To (sq.mt) (m) (cum)

N 197 to 456 N and E 79 to 212E

30 24 14035 6 84210 - 151578

97 24 22 18230 3 54690 - 98442

- Total - 250020

Page 29: INTRODUCTION Narmada Cement-Jafrabad Works UltraTech ...environmentclearance.nic.in/writereaddata/FormB/TOR/Additional... · 1 INTRODUCTION Narmada Cement-Jafrabad Works a unit of

   

29 

 

Tentative fresh area to be broken during the proposal of first five years i.e. 1st, 2nd , 3rd , 4th & 5th is 2.15ha, 2.10ha, 0.00, 2.25ha & 0.00ha respectively. C) Dump re-handling (for the purpose of recovery of mineral): Estimated available

material (Cum)

Dump no. Year wise handling

Estimated recovery of saleable material

Rejects

No dump of waste/ OB/ reject exists within the applied area as the area is fresh grant.

c) Enclose Individual year wise development plans and sections showing pit layouts, dumps, stacks of mineral reject, if any, etc in case of 'A' category mines. Composite development plans showing pit layouts, dumps, stacks of mineral reject, if any, etc. and year wise sections in case of 'B' category mines. Year wise working plan and sections showing pit layout, stacks of sand, plantation location etc. is enclosed as Plate No. 5A to 5E & 5S. d) Describe briefly giving salient features of the proposed method of working

indicating Category of mine. sr Items Details i) Method of mining

With bench parameters It is proposed ‘A’ category mine to be worked by opencast method of mining with mechanization maintaining bench height of 6+/- 2.0m and sloping bench at about 75 degree and bench width >15m. The bench nomenclature i.e. OB sand bench is assigned as first bench of average thickness of 0.5m to 4.0m. The mine working is proposed to be worked in 1 shift of 8 hr. The average distance from proposed working pit to crusher is 3km. The quality of limestone from this area is not self sufficient to prepare required raw mix for clinkerization hence blending with lower CaO limestone is required before milling along with other ingredients.

ii) Drilling DTH drilling by 110 mm DTH drills using Atlas copco-ICM-260. The drilling is proposed keeping burden 2.75m to 4.0m and spacing 3.75m to 5.0 m.

iii) Blasting Shock tubes & detonating fuse along with electric detonators are proposed to be used for initiating the explosives. Shock tube is proposed commonly to be used to keep ground vibration and AOP in control. Charging and firing patterns shall be proposed by skilled blasting engineer and verified by blasting manager. Utmost care shall be taken to minimise AOP and ground

Page 30: INTRODUCTION Narmada Cement-Jafrabad Works UltraTech ...environmentclearance.nic.in/writereaddata/FormB/TOR/Additional... · 1 INTRODUCTION Narmada Cement-Jafrabad Works a unit of

   

30 

 

vibration while designing blast and it’s firing & charging pattern. Ground vibration and AOP is proposed to be measured by Nomis Mini Supergraph instrument for each blast. Average powder factor envisaged to 10 te/kg as being practised in nearby mines.

iv) Excavation The geological investigations suggest that the deposit is hard to semi hard.So opencast mechanized mining by forming systematic benches of 6.0+/- 2.0m height with proper width of about more than 15.0 m by conventional means is proposed.

v) Loading Loading by excavator and wheel loader. vi) Transportation ROM transportation shall be practised by

means of dumpers/tippers to the crusher located just outside the applied area.

vii)

Crushing/ screening Crushing unit has been provided outside the area.

e) Describe briefly the layout of mine workings, pit road layout, the layout of faces and sites for disposal of overburden/waste along with ground preparation prior to disposal of waste, reject etc. A reference to the plans and sections may be given. UPL or ultimate size of the pit is to be shown for identification of the suitable dumping site.

As stated in table above, production rate of 2.5 lac TPA of limestone is proposed during the first five years (refer Plate No. 5A to 5E & 5S). The proposed production has been tabulated in the table above. Four benches are proposed to be worked including first bench of overburden sand ir-respective of its thickness as it is practiced in nearby mine. The details of proposed year wise working is given below: - Development & production programme for 1st Year During this year the development will be carried out starting from the old pits in earlier formed limestone at locations between the grid lines N323 to 571N and 19E to 195E. Overburden soil removal shall be carried out from the first bench. During this year of mining operation total quantity of overburden soil to be removed is estimated around 22489 cum. This will be stacked temporarily at earmarked sites for OB During working it is also proposed to make ramps to access the various benches with proper gradient. Year wise tentative excavation for this year is shown in Proposed Yearwise Working Plan, Plate No. 5A. The proposed R.O.M. quantity & quality is tabulated in Table A2.5. Development & production programme for 2nd Year During this year the development in bench will move forward between the grid lines N 571N to 611N and E 195 to 277E. Overburden soil removal shall be carried out in separately at first bench . During this year of mining operation total quantity of overburden soil to be removed is estimated around 19110 cum. This will be stacked temporarily at earmarked sites for OB During working it is also proposed to make ramps to access the various benches with proper gradient.

Page 31: INTRODUCTION Narmada Cement-Jafrabad Works UltraTech ...environmentclearance.nic.in/writereaddata/FormB/TOR/Additional... · 1 INTRODUCTION Narmada Cement-Jafrabad Works a unit of

   

31 

 

Year wise tentative excavation for this year is shown in Proposed Yearwise Working Plan, Plate No. 5B. The proposed R.O.M. quantity & quality is tabulated in Table A2.6. Development & production programme for 3rd Year During this year the development will be carried out in earlier formed limestone benches between the grid lines N361 to 482 and E 63 to 275E. Development & production programme for 4th Year During this year the development will be carried out in earlier formed limestone benches between the grid lines N197 to 392N and 18E 277E. Overburden soil removal shall be carried out in separate bench as bench first. During this year of mining operation total quantity of overburden soil to be removed is estimated around 25220 cum. This will be stacked temporarily at earmarked sites for OB During working it is also proposed to make ramps to access the various benches with proper gradient. Development & production programme for 5th Year During this year the development will be carried out in earlier formed limestone benches between the grid lines N 197 to 456 N and E 79 to 212E. Overburden soil removal shall be carried out in separate bench as bench first. During working it is also proposed to make ramps to access the various benches with proper gradient.

ix) Extent of mechanization- Describe briefly with calculation for adequacy and type of machinery and equipment proposed to be used in different activities of drilling, material handling in development and stope, hauling, hoisting to surface, surface transportation and any other operation.

Capacities Required The designed rated capacity for limestone production during the first five years when operating at full rated capacity and with no overburden is as given below: - Mineral per annum: 2.5 lac tonnes OB sand to be removed: 0.67 lac cubic meter Waste handling Nil No. of operating days per annum: 300 No. of operating shifts per day: 1 No. of scheduled hours shift: 8 Actual utilization hours: 6

Table A2.10: Day, shift and hour wise proposed production Production In tonnes

Per day 700 Per Shift 700 Per Hour 117

The quantum and type of mining equipment proposed to be provided for various mining operations is as given below: - List of machinery proposed Drill Machines:- In order to calculate the number of drill machines required, it is essential to know the drilling capacity/ rate of drilling of one machine and the total drilling required taking into consideration burden, spacing, sub-grade drilling etc. It is

Page 32: INTRODUCTION Narmada Cement-Jafrabad Works UltraTech ...environmentclearance.nic.in/writereaddata/FormB/TOR/Additional... · 1 INTRODUCTION Narmada Cement-Jafrabad Works a unit of

   

32 

 

proposed to deploy compressed air operated down the hole Atlas-ICM 260 of 110 mm dia. holes. Drilling capacity of drill machine: Based on the performance of drill machine at Narmada Cement Mine, Atlas ICM-260 is able to drill about 20 meters/ hour. For the purpose of calculations same drilling rate has been assumed. Therefore, taking into consideration 8.0 hours a shift, 300 working days in year & 70% utilization & 85% as availability, the annual drilling capacity of one drill machine works out as follows: - 20 * 8 * 300 * 0.70 * 0.85 * 1 = 28560 say 28600 meters/ drill/ year Drilling Pattern: With 110 mm dia. drill holes, the present practice in the nearby mine is to keep burden of average 4.5m & spacing of average 3.25 m. However, for the purpose of calculating the total drilling required the above drilling pattern is being assumed. Drilling Specification for ICM-260 working in limestone works out to 4.50 x 3.25 x 1.8 =26.32 tonnes or say 26 tonnes/meter of drilling. Therefore, the total drilling required for mining 2.5 lakh tonnes per annum works out to be 9498.48 m say 9500 m. Taking into consideration 5% drilling required towards collapse of holes, misfires, abandoning of holes ect. total drilling required will be about 10000 m. No. of Blasting Drills required: Taking into consideration the drilling capacity of one drill machine and the total drilling required, the number of drill machines required works out to: 10000/57000 = 0.18 say 1.0 drill machine Assuming 85% as the availability, the number of drill machine required works out to 1 ICM-260 drills. Secondary drilling: No secondary drilling is proposed. Explosives: In medium hard rock like limestone, shale etc. ANFO along with some other high explosive as the booster/ base charge is most suitable. It is therefore proposed to use ANFO as the primary column charge and some cap sensitive high explosive like Aqua-dyne/ Super dyne etc. as the booster/ base charge for blasting. However, during the rainy season or in water holes it is proposed to use slurry or emulsion explosives. It has been estimated that consumption of ANFO & other high explosives shall be in the ratio of 80:20. In order to calculate the explosive consumption per day, powder factor of 10 tonnes/ kg for limestone. Therefore, the monthly requirement of explosive will be:

10000/ 10 = 1000 Kg. The breaking of big size boulders generating due to blasting is proposed to be done by breaker attached to L & T Backhoe wheel loader. Taking into consideration the feed size of the crusher the maximum size of the boulder which it can handle works out to 600 mm size. Explosive Magazine: As calculated above about 1000 kg of explosive will be required for blasting per month. The unit already has one explosive magazine within nearby lease area where no mining activity will be undertaken. The total capacity of storing 20,000 kg of category 2 explosive, 44,000 detonators & 40,000 m of detonating fuse. As this storage capacity is considered adequate to meet the requirement therefore, no additional explosive magazine is proposed for this applied ML. Loading of Limestone from Face: As indicated earlier, it is proposed to use hydraulic excavator of 3.8 cum. Bucket capacity & loader of 3.7 cum bucket capacity for loading of blasted/cutting material & O/B sand removal from the mine face. The production from the mine can be maintained during the first five years by working one day shift. Loading Capacity of Excavators & Loader: The loading capacity of Excavator & Loader are given by the following equation:

Page 33: INTRODUCTION Narmada Cement-Jafrabad Works UltraTech ...environmentclearance.nic.in/writereaddata/FormB/TOR/Additional... · 1 INTRODUCTION Narmada Cement-Jafrabad Works a unit of

   

33 

 

L = B x r x n x t x E/K Where L = Loading capacity per shift in cum B = Bucket capacity in cum (3.7 cum) r = Co-efficient of filling (assumed 0.8) n = Avg. number of lading cycles/hr. (taken as 90 on the basis of cycle time of 30 seconds) t = No. of effective working hours in a shift (taken as 6.0) E = Efficiency of utilization (assumed as 0.70) K = Swell factor (taken as 1.33 i.e. 33%) For Loader : a) For O/B Sand:

L = 1.6 x 0.8 x 90 x 6 x 0.70/ 1.33 = 363.79 cum /shift (say 364 cum) b) For Surface miners: L = 5.70 x 0.8 x 90 x 6 x 0.70 / 1.33 = 1296.00 cum /shift (say 1296 cum.)

For Excavator: L = 3.70 x 0.8 x 90 x 6 x 0.70 / 1.33 = 864.00 cum /shift (say 864 cum.) The handling capacity of Loader with 1.60 cum bucket capacity works out to 364 cum/ shift for sand. Taking an average density of 1.80 for limestone, loader with 5.70 bucket capacity works out to 2332.8 (say 2333 tonnes) per shift & excavator with 3.80 bucket capacity works out to 1555.2 (say 1555 tones) per shift. Number of Excavators Required: One loader & one excavator are sufficient for the proposed production capacity. Transport of Limestone in the Mine: As mentioned earlier the limestone from the face will be loaded by the hydraulic excavator & loader in to 20 tonnes tippers and transported to the crusher. Tipper requirement: Average load per cycle of the excavator/loader with 3.80/5.70 cum. bucket capacity assuming 33% as swell factor, 80% as the fill factor and 1.80 as the density for limestone works out to be: For Excavator = 3.80 x 0.8 x 1.80/ 1.33 = 4.11 tones

For Loader = 5.70 x 0.8 x 1.80 / 1.33 = 6.17 tones. Taking average carrying of a tippers as 10 & 20 tonnes, total number of cycle required to fill a truck works out to

For Excavator = 10/ 4.11 = 2.43 say 3.0 For Loader = 20 / 6.17 = 3.24 say 3.0

Taking an average cycle time of an loader as 30 seconds, assuming 70% as coefficient of utilization, the time required for an excavator & loader to fill a 10 & 20 tonnes tippers works out to: For Excavator & Loader = 3 x 0.5/ 0.7 = 2.14 or say 2 min. Cycle Time of Tippers for Limestone Spotting Time = 0.5 mins. Loading Time = 5.0 mins. Travel time loaded @ 20 km/ Hr. With avg. distance of 4 km. = 12.0 mins. Unloading Time = 0.5 mins. Travel time Unloaded @ 20 km/Hr. Avg. distance of 4 km. = 12.0 mins. TOTAL = 30 mins. With a cycle time of 30 mins. a tippers will be able to make about 12 trips to the crusher

Page 34: INTRODUCTION Narmada Cement-Jafrabad Works UltraTech ...environmentclearance.nic.in/writereaddata/FormB/TOR/Additional... · 1 INTRODUCTION Narmada Cement-Jafrabad Works a unit of

   

34 

 

i.e. about 720 tonnes per day with one shift working. Therefore, the number of tippers required for transport of limestone from the face to the crusher works out to 740/720 = 1.02 say 2. Therefore in all 2 tipper/dumpers in operation will be required per day for the mines. Taking 80% as the availability the total number of tippers required for the mine works to be 02 Tippers. DRAINAGE AND DEWATERING The applied lease area is situated nearby sea coast but beyond the 500 m limit of Coastal Regulation Zone so no danger is envisaged this regard. Observation from nearby wells & bore wells in the area reveal that depth of water table is below mean sea level. The working is proposed till 22 MRL and so will not reach mean sea level and hence there will be no interception of water table. Except for the scanty rainfall in this semiarid region, there is no source of water that is likely to be encountered in pits. Rainwater will be harvested/ accumulated in the lower most benches/ level of mined out pits. Accumulated rainwater will act as ground water recharge structure & water harvested will be used for plantation, dust suppression & plat use.

Table A2.2: List of Mining Machinery/ Equipment to be deployed

Type of Machinery/ Equipment deployed

Capacity of each unit

( Cu.M/Tonnes) No. of units

SHOVEL (HYD. EXCAVATOR ) L&T EXCAVATOR-POCLAIN-300 CK 3.7 Cu-Mtr 1 COMPRESSOR & DRILL Atlas ICM-260 Drill machine* 4" dia hole 1 DUMPERS BEML DUMPER-HAULPAK 31.72 T 2 BEML DUMPER -HAULPAK (WT) * Water Sprinkler 1 DOZER DOZER D-155 A-KOMATSU JAPAN* 65 D B P 1 WHEEL LOADERS WHEEL LOADER 2021(STD) * 1.7 Cu-Mtr 1 BACKHOE LOADER L&T BACKHOE WHEEL LOADER* 580 0.9 Cu-Mtr -B 1 PRODUCT SUPPORT EQUIPMENT LIGHTING TOWER 9 Mtrs High 2 MINE JEEP ( BOLERO) * 6 seater 1 EXPLOSIVE VAN-EXPLOSIVE VAN * 5 T 1 FUEL DISPENSING UNIT-DIESEL TANKER * 3000 Ltrs 1

Page 35: INTRODUCTION Narmada Cement-Jafrabad Works UltraTech ...environmentclearance.nic.in/writereaddata/FormB/TOR/Additional... · 1 INTRODUCTION Narmada Cement-Jafrabad Works a unit of

   

35 

 

TATA MAINTENANCE VAN * 7 T 1 Surface Miner # 275 TPH 1

* Machines are proposed to be used commonly for all the nearby mines # Surface Miner in combination with wheel loader shall be hired as and when required Remaining machines shall belong to the company.

f) Conceptual Mine planning upto the end of lease period taking into consideration the present available reserves and resources describing the excavation, recovery of ROM, Disposal of waste, backfilling of voids, reclamation and rehabilitation showing on a plan with few relevant sections.

General Every mine needs to be planned in a way that the useable mineral is extracted to the maximum extent without causing severe irreversible environmental damages. In the case of the Babarkot Limestone Area; the concept is to take necessary steps in order to keep the area under disturbance at any stage of mining operations to the minimum. And we are operating our mines on the concept of zero waste mining and maximum utilization of low grade mineral so we are in the process of planning to extract the mineral upto 0 mRL in the conceptual stage. Rehabilitation of the mined out area shall be done with least time between damage and repair. The end land use of the mine is controlled by the following factors: - No rejects/waste are generated during mining except windblown sand, hence backfilling towards restoring entire worked out area to pre-mining land use is not feasible for entire worked out area. As it is not feasible to bring the mine pits to the ground level it is not found useful to convert it into agricultural land use. As the area is facing scarcity of water hence found useful to convert the mined out area into rainwater storage. A little part of worked out area can be reclaimed and rehabilitated with sand which exists as capping of area The surrounding areas have very low vegetation discouraging fauna habitats; hence a flora and fauna habitat will be useful. A water body will be a pleasing addition. This will avoid any chance of salinity ingress into the groundwater. Additionally, the rainwater harvested in mined out area shall induce freshwater recharge, thereby improving the quality of the groundwater in the upstream areas. In view of the above, it would be appropriate to convert the mine into a mix of water bodies to stabilize the groundwater with green belt area for ecological and aesthetic restoration. The mine planning and land reclamation shall be carried out to achieve the above aim. The disturbed land will be fully reclaimed/ rehabilitated before abandoning the mine.

i) Exploration- From the nature and extent of the deposit, adequate reserves along with quality have been

proved with certain degree of reliability based on nearby mines pits, boreholes and old pits in the applied area. A handsome quantity of resources has been estimated which to be is proved under mineable reserves for which further exploration is required and hence proposed the same. In this regard, exploration is proposed during the first year of the

Page 36: INTRODUCTION Narmada Cement-Jafrabad Works UltraTech ...environmentclearance.nic.in/writereaddata/FormB/TOR/Additional... · 1 INTRODUCTION Narmada Cement-Jafrabad Works a unit of

   

36 

 

applicability of mining plan. There has been proposed a total of 20 core bore holes in unexplored area vertically. This will bring the resources within G1 category. The details of proposed bore holes have already been given in chapter – Geology & Exploration.

ii) Excavation- The mining operations during period of mining plan are proposed to be carried out at one

location. Mining shall not be carried out in the area of 7.5 m barrier along the either sides of the public road and boundary line. Permission shall be obtained from competent authority i.e. DGMS to work in statutory boundary barrier along common lease boundaries looking towards conservation of valuable minerals. No other feature is present in the ML area which is likely to affect the design of ultimate working except HT electric line. At places where mining is not feasible due to narrow spaces has also been affected ultimate pit limit. The layout of ultimate pit extension and depth has been designed to reach ultimate angle of 45 degree by keeping bench height 6m, width 4.5m depth upto 0 mRL. The schematic section of ultimate layout of mine working with bench configuration is shown in figure below: -

LEVEL IN METER W.R.T. MSL

6.0M6.0M

The broad parameters of conceptual mine design is as below:

Benches to be developed : 7 Ultimate bench height : 6.0 m Ultimate bench width : 4.5 m Ultimate face slope : 600 Ultimate pit slope : 450

Page 37: INTRODUCTION Narmada Cement-Jafrabad Works UltraTech ...environmentclearance.nic.in/writereaddata/FormB/TOR/Additional... · 1 INTRODUCTION Narmada Cement-Jafrabad Works a unit of

   

37 

 

Total four pits shall be there at the end of mine life as detailed below: - Table A2.11: Ultimate Dimensions of Pits at the end of mine life

S. No.

Pit No.

Dimensions of Pit (m*m)

Pit bottom (m AMSL)

Overall Pit slope

Area covered

(ha) 1. I 100 * 100 +0.0 450 0.70 2. II 168 * 200 +0.0 450 2.00 3. III 144 * 300 +0.0 450 3.50 4. IV 785 * 715 +0.0 450 28.50

Total 34.70 Fresh area of ML shall be taken up for development and exploitation simultaneously. After the entire exhaustion and as backfilling is not envisaged, the voids shall be used for accumulation of rainwater which will be part of rainwater harvesting scheme. Thus the excavated areas will be beneficial to human being, flora and fauna, in this water starved region of Amreli district of Gujarat State. During the entire mine life following activities are proposed to be carried out. 1. Development During this period removal of OB sand is envisaged from fresh mineable area. Other than production activities, routine developmental activities shall be taken place. Mine office and work shop and other necessary infrastructures are already established in nearby mines of same company. 2. Production In due course of time working is proposed upto 0.00mRL with due permission of MoEF. Geo-Technical Study shall be carried out to determine slope stability and accordingly ultimate pit shall be designed and changed. The area have also been identified for working in a block of 5 years upto mine life as shown in Conceptual Plan, Plate No. 7.

Table A2.12:Phase wise Working Programme for the Mine Life S. No. Phase Duration

In years Excavation Area Cumulative (ha)

1. Old pits - 0.165

2. Till 5th year (Mining Plan period)

05 6.665

3. Till 10th year 05 13.70 4. Till 15th year 05 19.90 5. Till end of mine life Remaining

period 34.70

Page 38: INTRODUCTION Narmada Cement-Jafrabad Works UltraTech ...environmentclearance.nic.in/writereaddata/FormB/TOR/Additional... · 1 INTRODUCTION Narmada Cement-Jafrabad Works a unit of

   

38 

 

Table A2.13: Stage Wise Land Use and Reclamation Area (ha) S.

No. Land Use Category Pre-

Operational (Present)

Operational (At the end of first five years)

Post-Operational(At the end of mine life)

1. Overburden Sand Dump Nil 1.10 Nil 2. Waste Dump Nil Nil Nil 3. Excavation 0.165 (old pits) 6.665 34.70

4. Road, mine road etc. Nil 0.50 0.50 5. Infrastructure (HT line) 1.8 1.8 1.8 6. Township Area Nil Nil Nil 7. Natural Water Bodies Nil Nil Nil 8. Mineral Storage (Sub-

grade/mineral) Nil Nil Nil

9. Undisturbed area 47.8804 39.7804 12.8454 10. Total 49.8454 49.8454 49.8454 11. Backfilled area Nil Nil 2.50 12. Plantation & Greenbelt Nil 2.50 7.00

iii) Waste Disposal- Since no waste/ mineral reject is available so no dumping is required. Also no sub-grade

limestone will be generated; hence no arrangement is required for stacking the same. On sand is required to be stacked temporarily which ultimately is proposed to be backfilled in worked out area.

iv) Reclamation and rehabilitation - Reclamation

The mining area covering 34.70 ha shall be gradually developed and exploited for limestone. Part of the mined out area is envisaged for backfilling with the available overburden soil. The voids below the general ground level shall be used for storage of rainwater and surface run-off water which could be used for agricultural and domestic purposes in this area. This accumulated water shall be kept suitably fenced off all around. There are plans for developing pisciculture and picnic spot. It is proposed to create four water storages during the mine life. These rainwater storages will cover an area of 34.70 ha. Rehabilitation It has already been mentioned that the area of mining lease is free from any habitation and therefore there will not be any oustees. Afforestation Program Company has a plan to plant saplings of trees and shrubs all along the statutory barrier around the HT line passing through the applied lease boundary. Plantation is proposed to be done at the rate of 1000 saplings per hectare and area 0.5ha per year. Soil, if any removed during mining is proposed to be used for plantation purposed. By the end of this mining plan period, an area of 2.50 ha area under greenbelt shall be developed. When the mine is exhausted completely, entire area of ML will have four large to small water storages and big gardens with trees and shrub, which will be beneficial of human population of the region in Jafarabad Taluka of Amreli District. The relevant help for successful reclamation/ afforestation will be taken from experienced

Page 39: INTRODUCTION Narmada Cement-Jafrabad Works UltraTech ...environmentclearance.nic.in/writereaddata/FormB/TOR/Additional... · 1 INTRODUCTION Narmada Cement-Jafrabad Works a unit of

   

39 

 

Forest Officials. The following native species are recommended: -

Table A2.14: Species of saplings planted and proposed S. No. Botanical Name Local Name

1. Acacia auriculiformis Bangalibaval

2. Acacia catechu Khair

3. Acacia nilotica Deshi babul

4. Albezialebbeck Siras

5. Azadirectaindica Neem

6. Bamboo spps. Vans

7. Cassia fistula Amaltas

8. Cassia seamea Kashod

9. Casuarinaequisetifolia Saroo

10. Cordiasebestina Cordia

11. Dalbergiasissoo Shisam

12. Delonixregia Gulmohar

13. Erythrinaindica Pangaro

14. Ficusreligiosa Pipal

15. Gmelinaarbora Shavan

16. Jetrophaspps. RatanJyot

17. Kigeliapinnata Kigelia

18. Padocarpuschinenses Teak

19. Parkinsonia spp. Rambaval

20. Peltoforumferrungium Sonmohar

21. Pithecelobiumdulse Gorasimli

22. Phyllanthusembelica Amla

23. Pongamiapinnata Karanj

24. Salvadoraspps. Pillu

25. Samaniasaman Raintree

26. Sygiumcumini Jambun

27. Tabubiaspps. Tabubia

28. Terminaliacuttappa Almond

29. Thespeciapopulanee Portia tree 30. Cocosnuciphera Coconut 31. Sapotasps Chiku 32. Others

Page 40: INTRODUCTION Narmada Cement-Jafrabad Works UltraTech ...environmentclearance.nic.in/writereaddata/FormB/TOR/Additional... · 1 INTRODUCTION Narmada Cement-Jafrabad Works a unit of

   

40 

 

The afforested area has to be protected from cattle menace, soil erosion, plant diseases etc. Plants will be protected from diseases by application of proper pesticides. Soil working, manuring etc. will be done whenever necessary. Plants will be protected from cattle menace by proper watch and ward or fencing. Damaged plants will be replaced with new one. Post mining land use pattern

Table A2.15: Land Use Pattern at end of mine life (in ha)

Particulars Forest Land

Private/ Ag.

Land

Grazing Land

Waste Land Others Total

a) Pits & Quarries - 34.70 - - - 34.70 b) Dumps of ore Waste & O.B./ Soil stack

- Nil - - - Nil

c) Infrastructure including of office

- 1.80 - - - 1.80

d) Haul roads/ roads - 1.0 - - - 1.0

e) Others (i) Govt. land (ii) Private/Ag. land

- -

- -

12.1734

- -

0.172

-

- -

- 0.172

12.1734 Total occupied Area

- 49.6734 - 0.172 - 49.8454

f) Area reclaimed/ rehabilitated by mine owner = 2.50 ha g) Area afforested by mine owner = 7.0 ha The final land use and restoration plan including conversion of the void into rainwater storage and plantation position etc are depicted on Conceptual Plan, Plate No. 7.

2.2 UNDERGROUND MINING- Not applicable

Page 41: INTRODUCTION Narmada Cement-Jafrabad Works UltraTech ...environmentclearance.nic.in/writereaddata/FormB/TOR/Additional... · 1 INTRODUCTION Narmada Cement-Jafrabad Works a unit of

   

41 

 

3.0. MINE DRAINAGE a) Minimum and maximum depth of water table based on observations from

nearby wells and water bodies The applied area is situated nearby sea coast beyond the 500 m limit of Coastal

Regulation Zone. Observation from nearby wells & bore wells in the area reveal that depth of water table is upto or below mean sea level. The water table observed in the peizometers installed in the nearby ML area is -2.0m msl.

b) Indicate maximum and minimum depth of Workings. As it is a case of fresh grant hence no working carried out. c) Quantity and quality of water likely to be encountered, the pumping

arrangements and places where the mine water is finally proposed to be discharged

No ground water intersection envisaged due to mine working upto 22.0mRL during this plan period. No seasonal drains exist in the applied ML area. The rainwater falling in the catchment area of the mine pits is proposed to be stored in the sump proposed to be created and to be used for dust suppression and watering plants. Rainwater shall be required to be pumped out from the mine sump as and when required. Rainwater collected in the mined out area shall be used for mining purposes.

d) Describe regional and local drainage pattern. Also indicate annual rain fall, catchments area, and likely quantity of rain water to flow through the lease area, arrangement for arresting solid wash off etc.

The Babarkot Limestone Area is devoid of any perennial or seasonal river through the area. The rainwater flows as per natural flow in the un-worked area down-stream to the sea. Regionally the drainage of the area is controlled by seasonal rivers Dhantarwadi and Raidi, joined by small nalahs which drain to the backwaters/ Gulf of Khambat in the Arabian Sea, with whatever little precipitation is received in this semi arid region. The recorded average rainfall in area is 819 mm per annum. During the year in which the rainfall is less and consequently precipitation is less it results in drought condition. However, as a precaution towards flash floods due to heavy rains, if any, caused due to cyclonic conditions, sump 500m*300m and 6m deep, has been proposed for storage of rain (sweet) water. Water is being conserved for dry months. Catchment area is quite big as it does not form a part of any major river system due to its proximity to the sea coast. The water is proposed to be used for consumption for dust suppression and plantation. The quality of rainwater remains intact as no effluent is proposed to be mixed with and on the other hand no contamination is envisaged as the mineral limestone is non-toxic in nature.

Page 42: INTRODUCTION Narmada Cement-Jafrabad Works UltraTech ...environmentclearance.nic.in/writereaddata/FormB/TOR/Additional... · 1 INTRODUCTION Narmada Cement-Jafrabad Works a unit of

   

42 

 

4.0 STACKING OF MINERAL REJECT/ SUB-GRADE MATERIAL AND DISPOSAL OF WASTE

a) Indicate briefly the nature and quantity of topsoil, overburden/ waste and Mineral Reject to be disposed off.

On an average about 1.0m cover of overburden sand is available in the applied ML area. The thickness of overburden sand is comparatively more towards Kovaya villages while the thickness decreases towards village Babarkot which is on higher ground. The entire deposit contains windblown sand and is about minimum 0.5 m and at places even 4m thick. OB sand available is very low in quantity and useless. The OB sand shall be removed separately and shall be used for backfilling as well as for plantation/ green belt purposes. During first five years of working, OB sand shall be removed from fresh area. This shall be disposed of by means of stacking covering an area 1.10ha (110m*140m*6m) near boundary pillars during first five years. The yearly generation/ use of overburden sand is furnished in table below: -

Table A4.1: Generation of OB Sand during first five years (in cum) Year OB sand 1st 22489 2nd 19110 3rd - 4th 25220 5th -

Total 66819

Table A4.2: Use of OB Sand during first five years (in cum) Year Opening

stock OB sand reuse

Topsoil storage

Mineral reject Backfilling

Mineral reject Storage

Mineral reject Blending

Beneficiation

1st Nil Nil - - - - - 2nd Nil Nil - - - - - 3rd Nil Nil - - - - - 4th Nil Nil - - - - - 5th Nil Nil - - - - -

Total Nil Nil - - - - -

Waste is not available as well either in the form of overburden or in inter-burden. Only OB sand is available which is non – toxic in nature.

b) The proposed dumping ground within the lease area be proved for presence or absence of mineral and be outside the UPL unless simultaneous backfilling is proposed or purely temporary dumping for a short period is proposed in mineralized area with technical constraints & justification.

As the area shall not be available for backfilling hence OB sand removed during first five years is proposed to be utilized for backfilling in future.

c) Attach a note indicating the manner of disposal of waste, configuration and sequence of year wise build up of dumps along with the proposals for protective measures.

Not applicable as no waste is available for backfilling. OB sand shall be temporarily stacked at earmarked site.

Page 43: INTRODUCTION Narmada Cement-Jafrabad Works UltraTech ...environmentclearance.nic.in/writereaddata/FormB/TOR/Additional... · 1 INTRODUCTION Narmada Cement-Jafrabad Works a unit of

   

43 

 

5.0 USE OF MINERAL AND MINERAL REJECT The following are to be furnished in the interest of mineral conservation a) Describe briefly the requirement of end-use industry specifically in terms of

physical and chemical composition. The limestone produced combinedly from this mine will be for captive use for cement

manufacturing in the existing cement plant in the vicinity. Therefore the blending of the various grades of limestone is designed in a set ratio to meet out required raw mix. NCBM (National Council for Cement and Building Materials) have in their norms recommended broad chemical specifications of cement grade limestone (ROM quality) as given below. -

Table A5.1: Broad Chemical Specifications of Cement Grade Limestone Sr.

No. Oxide Components

Acceptable range (%) for manufacture of OPC

Limiting Values taking into consideration other types of cements, scope of beneficiation & blending (%)

Remarks

01. CaO 40 - 52 <34 02. MgO Max. 3.5 Max 5.0 03. Al2O3 2.5 AM 1.20 to 2.50 04. Fe2O3 2.5 SM 2.20 to 2.80 05. SiO2 <12.5 LSF 85 to 110 06. Mn2O3 <0.5 <3

07. R2O (K2O+Na2O) <0.6 <1

08. Total S (as SO=)

<0.6 <0.8

09. P2O5 <0.6 <1 10. Cl <0.05 <0.1

The Babarkot Limestone Area shall be captive source of limestone to its own cement plant in the vicinity. The cement plant has not imposed any change in the specification except corrective materials. The different additives used for cement manufacturing is furnished below:

Aluminous Clay : 0.5 - 1.50%

Ferruginous Clay : 1.0 - 2.50%

Iron Ore : 0.25 - 0.50%

Basalt : 1.0 - 2.00%

Bauxite : 0.5 – 1.00%

Sweetener : 5.0 – 6.5%

Basalt is an igneous rock and has easy melting character. It is mainly used for replacement of un-reactive silica i.e. Quartz in limestone, which leads to high free lime in clinker. Basalt converts the un-reactive silica in to reactive and controls free lime in clinker.

Page 44: INTRODUCTION Narmada Cement-Jafrabad Works UltraTech ...environmentclearance.nic.in/writereaddata/FormB/TOR/Additional... · 1 INTRODUCTION Narmada Cement-Jafrabad Works a unit of

   

44 

 

b) Give brief requirement of intermediate industries involved in up-gradation of mineral before its end-use.

Not applicable c) Give detail requirements for other industries, captive consumption, export,

associated industrial use etc. The mineral mined out from the Babakot Limestone Area shall be used as captive purpose

at the cement plant in the vicinity. There is no proposal of export of mineral and other industrial use except cement manufacturing.

d) Indicate precise physical and chemical specification stipulated by buyers Not applicable e) Give details of processes adopted to upgrade the ROM to suit the user

requirements. Not applicable

Page 45: INTRODUCTION Narmada Cement-Jafrabad Works UltraTech ...environmentclearance.nic.in/writereaddata/FormB/TOR/Additional... · 1 INTRODUCTION Narmada Cement-Jafrabad Works a unit of

   

45 

 

6.0 PROCESSING OF ROM AND MINERAL REJECT

a) If processing/ beneficiation of the ROM or Mineral Reject is planned to be conducted, briefly describe nature of processing/ beneficiation. This may indicate size and grade of feed material and concentrate (finished marketable product), recovery etc.

The ROM are proposed to be utilized for cement manufacturing by dry process. There is no wet processing or beneficiation necessary to upgrade the limestone. The ROM material is directly fed to the crusher installed outside the ML area for further process.

b) Give a material balance chart with a flow sheet or schematic diagram of the processing procedure indicating feed, product, recovery, and its grade at each stage of processing.

Not applicable c) Explain the disposal method for tailings or reject from the processing plant. Not applicable d) Quantity and quality of tailings /reject proposed to be disposed, size and capacity

of tailing pond, toxic effect of such tailings, if any, with process adopted to neutralize any such effect before their disposal and dealing of excess water from the tailings dam.

Not applicable e) Specify quantity and type of chemicals if any to be used in the processing plant. Not applicable f) Specify quantity and type of chemicals to be stored on site / plant. Not applicable g) Indicate quantity (cum per day) of water required for mining and processing and

sources of supply of water, disposal of water and extent of recycling Water balance chart may be given.

The water for mining is required in terms of industrial use and domestic use. Domestic water (2 KLD) requirement shall be fulfilled from existing Desalination & RO plant installed within cement plant area and water for industrial use (15KL) shall be sourced from mine sump water of nearby mines. Water is sourced from the sea for overall domestic use of entire plant. Domestic waste water generated is treated in the STP and used for industrial use. Spraying of water on the haul roads will not generate any waste water as the same would evaporate or percolate to lower levels through the strata below (which are normally porous). There shall be no recycling of water on this account. No waste water is proposed to be discharged from the applied area. The water balance for the mine is as below: -

Water Requirement per day Discharge Activities Quantity (m3) Quantity (m3) Domestic Use 2 Zero Industrial Use 15 Zero Total Requirement 17 Zero

Page 46: INTRODUCTION Narmada Cement-Jafrabad Works UltraTech ...environmentclearance.nic.in/writereaddata/FormB/TOR/Additional... · 1 INTRODUCTION Narmada Cement-Jafrabad Works a unit of

   

46 

 

7.0 OTHERS Describe briefly the following: a) Site Services The following Site services have been developed at mining site of nearby mining lease area:

1. Mines Offices for Managerial Staff 2. Vocational Training Centre 3. Time Office 4. First-aid Room 5. Canteen 6. Workshop For fuel filling, we have a diesel tanker which feeds all the HEMM and other machinery as per requirement. The First-Aid Station with the necessary facilities for imparting first-aid to the injured shall be installed at the mining area. Temporary rest shelters are proposed to be installed within the applied mine site. Canteen facilities are being maintained for the benefit of field staff and workers within the adjoining mining lease.

b) Employment potential- Officer* and Staff

(Highly Skilled) 03

Skilled 07 Semi-Skilled - Un-Skilled 4 Total 14

* Man Power to be deployed under rule 42 of MCDR, 1988

Page 47: INTRODUCTION Narmada Cement-Jafrabad Works UltraTech ...environmentclearance.nic.in/writereaddata/FormB/TOR/Additional... · 1 INTRODUCTION Narmada Cement-Jafrabad Works a unit of

   

47 

 

8.0 PROGRESSIVE MINE CLOSURE PLAN UNDER RULE 23 OF MCDR’1988

8.1 Environment Base line information: Attach a note on the status of baseline information with regard to the following. a) Existing land use pattern indicating the area already degraded due to mining,

roads, processing plant, workshop, township etc in a tabular form. Table A8.1: Existing Land Use Pattern (in ha)

Particulars Forest Land

Private/ Ag. Land

Grazing Land

Waste Land Others Total

a) Pits (old pits) - 0.165 - - - 0.165 b) Dumps of ore Waste & O.B./ Soil stack

- - - - - -

c)Infrastructure including of office, haul roads

- - - - - -

d) HT line - 1.80 - - - 1.80 e) Others (i) Govt. land (ii)Private/Ag. land

- -

-

47.7084

- -

0.172

-

- -

0.172

47.7084 Total occupied Area - 49.6734 - 0.172 - 49.8454

f) Area reclaimed/ rehabilitated by applicant = Nil g) Area afforested by applicant = Nil

b) Water regime, quality of air, ambient noise level, flora, climatic conditions The applied lease area is undulating land with elevated mounds partly occupied by

limestone outcrops. The topographical elevation varies between 48m to 30 m above MSL. No seasonal/ perennial river/ nallah passed through the area. Rainwater flows as per natural slope of the area. Ground Water Observation from nearby wells & bore wells in the area reveal that depth of water table is below 0.0m mean sea level i.e. upto (-) 2m bmsl. Limestone exposed in the mine area does not have any primary porosity. The ground water occurs within the secondary porosity of limestone & other formation. The ground water occurs in unconfined state over the study area. Water Quality To evaluate the physico-chemical characteristics of the water resources existing in the surrounding area, water samples from surface and ground water sources were collected during the summer season and characterized for physico-chemical parameters. Water samples from five ground water source were characterized. The locations of water sampling stations are shown in Table below.

Table A8.2: Location of Water Sampling Stations S. No. Name of Sampling Station Source of water

1. Village Varahswarup Ground water 2. Village Kovaya Ground water 3. Village Bhakodar Ground water 4. Village Babarkot Ground water 5. Village Vandh Ground water

Page 48: INTRODUCTION Narmada Cement-Jafrabad Works UltraTech ...environmentclearance.nic.in/writereaddata/FormB/TOR/Additional... · 1 INTRODUCTION Narmada Cement-Jafrabad Works a unit of

   

48 

 

Samples from ground water sources were collected by adopting grab sampling. The sample was filled into a sampling bottle. The physico-chemical quality of water samples were characterized by adopting the relevant parts of IS. Ground Water Quality The test for ground water shows that all the parameters are well within the desirable limits, except the dissolved solids. TDS in the ground water are within the desirable limits except village Bhakodar, Varahswarup & Kovaya whereas fluoride is also within the desirable limit except village Kovaya. The water is suitable for drinking and other purposes.

Table A8.3: Results of ground water of Kovaya village

Parameter UOM Permissible

limit Jan-15 Feb-15 Mar-15

pH pH Unit

- 7.25 7.35 7.31

Total Suspended solids mg/I 30.0 12 14 17

BOD (5 days at 200 C) mg/I 20.0 14 13 15

Residual chlorine ppm Min. – 0.5 0.6 0.5 0.6

(Refer Annexure-XIII for latest environment monitoring reports)AIR ENVIRONMENT Sampling Period and Stations In order to establish the baseline status with respect to ambient air quality, few air sampling stations were established in the surrounding ML areas and in buffer zone. The ambient air quality survey was conducted during winter to spring 2015. The locations of these sampling station locations, as mentioned in Table below.

Table A8.4: Location of air sampling stations S. No. Location Inside ML/ Outside

ML 1. Manubhari Madhubhai Kotila Farm, Vandh Outside ML 2. Farm of Mohan Patel, Babarkot Outside ML 3. Primary School, Bhakodar Outside ML 4. Bhakodar Mining Block Outside ML 5. Near Temple, Varaswaroop Outside ML 6. Vandh area Outside ML 7. Near Mines Office Outside ML 8. Babarkot area Outside ML 9. Bhakodar area Outside ML

Sampling Schedule & Parameters The study was conducted by private laboratory. The survey was performed during the 24 hours period of summer season. These samples were analyzed in laboratory by adopting the methods specified in National Ambient Air Quality Standards, The following air pollution parameters were monitored during the sampling periods.

1. PM2.5 2. PM10 3. Sulphur Dioxide (SO2)

Page 49: INTRODUCTION Narmada Cement-Jafrabad Works UltraTech ...environmentclearance.nic.in/writereaddata/FormB/TOR/Additional... · 1 INTRODUCTION Narmada Cement-Jafrabad Works a unit of

   

49 

 

4. Oxides of Nitrogen (NOx) Observations A summary of the observations made during the air quality survey has been given in Table below. Table A8.6: Summary of Ambient Air Quality Monitoring Results in surrounding

area (in µg/m3) Location Para-

meter Permi-ssible limit

Dec. 14 (Mar. 14 Average

Manu Bhai Madhubhai Kotila Farm Village- Vandh

PM2.5 60.0 20.50 16.50 18.50 PM10 100.0 45.50 45.00 45.25 SO2 80.0 8.50 6.35 7.43 NOX 80.0 15.90 15.45 15.68

Farm Of Mohan Patel Village Bararkot

PM2.5 60.0 24.50 21.00 22.75 PM10 100.0 54.00 48.00 51.00 SO2 80.0 8.15 7.80 7.98 NOX 80.0 16.30 14.30 15.30

Near Primary School Village Bhakhodar

PM2.5 60.0 21.00 20.00 20.50 PM10 100.0 48.00 51.00 49.50 SO2 80.0 8.80 8.00 8.40 NOX 80.0 15.55 17.00 16.28

Bhakhodar Mining Block Village Bhakhodar

PM2.5 60.0 32.50 29.00 30.75 PM10 100.0 56.50 67.50 62.00 SO2 80.0 9.45 10.20 9.83 NOX 80.0 18.35 18.20 18.28

Near Temple Village Varahswraoop

PM2.5 60.0 20.00 14.50 17.25 PM10 100.0 47.50 41.00 44.25 SO2 80.0 8.20 7.20 7.70 NOX 80.0 15.75 16.10 15.93

(Refer Annexure-XIII for latest environment monitoring reports)On perusal of the observed results, it is concluded that the level of air pollutants is within the specified permissible limits. AMBIENT NOISE LEVEL The noise level measurements have been made at 4 locations within surrounding applied ML area. Based on the observations made during the studies, it is concluded that the noise levels observed at all the locations are within the limits specified for residential and rural area category.

Page 50: INTRODUCTION Narmada Cement-Jafrabad Works UltraTech ...environmentclearance.nic.in/writereaddata/FormB/TOR/Additional... · 1 INTRODUCTION Narmada Cement-Jafrabad Works a unit of

   

50 

 

Table A8.8: Noise level monitoring results in surrounding area (unit in dB(A))

Location

Noise Level- Leq. dB(A)

CPCB Limits Mar-15 Average

Day Time

Night

Time

Day Time

Night

Time

Day Time

Night

TimeManu Bhai Madhubhai Kotila Farm Village- Vandh

55 50 43.2 41.2 43.9 41.8

Farm Of Mohan Patel Village Bararkot 55 50 44.9 43.1 44.5 42.9

Near Primary School Village Bhakhodar

55 50 49.4 41.1 50.1 41.7

Bhakhodar Block Village Bhakhodar 55 50 53.9 48.1 54.2 46.8

Near Temple Village Varahswraoop 55 50 46.7 38.8 45.9 40.3

(Refer Annexure-XIII for latest environment monitoring reports) CLIMATE & METEOROLOGY Climate The climate of the area is characterized by general dryness (except during the south-west monsoon season) and hot summer. The temperature ranges from 9.4oC to 42.2oC. The rainy season extends from mid June to mid September. Rainfall The mean annual rainfall has been recorded as 819 mm. The relative humidity is generally high during the period from June to September and is least during the January-February period. Wind Speed & Direction The predominant wind direction from May to September is from West and South West while in the post monsoon and winter it is from North East to South East. In April to June and October the sky remains cloudless or lightly clouded and moderately clouded during July to September. Forest There is no forest in the core zone. Wildlife Sanctuary/ National Park etc There is no wildlife sanctuary, National Park etc. in the radius of 10 km. Vegetation: The applied ML area is not having any indications of good vegetation except natural vegetation. The applied ML area is generally devoid of large trees which includes very poor vegetal cover. Acacia nilotica Acacia ninuata, Prosopis juliflora are some of the common species. Besides common trees, natural vegetation grows mostly during monsoon and fades away with the onset of summer. The area does not have rare and endangered species.

c) Human settlements Six villages Kovaya, Vandh, Varahswarup, Babarkot, Bhakodar, Mitiyala, and a town

Page 51: INTRODUCTION Narmada Cement-Jafrabad Works UltraTech ...environmentclearance.nic.in/writereaddata/FormB/TOR/Additional... · 1 INTRODUCTION Narmada Cement-Jafrabad Works a unit of

   

51 

 

Jafarabad lies within the 5 km radius of applied lease area in all directions which constitutes small size human settlements. The villagers are mostly employed in agricultural work. Some people are engaged in other businesses. In the study area, i.e. the area falling within 5 km from the mine, there are 5 inhabited revenue villages. The entire buffer zone of 5km radius falls within Amreli District of Gujarat.

d) Public buildings, places of worship and monuments There are no such places within the core zone or in the surrounding area of tourist or

historical importance. There are village temples and mosques in the surrounding. e) Indicate any sanctuary is located in the vicinity of leasehold There is no wildlife sanctuary, National Park etc in the mine lease as well as in zone of 10

km radius.

Page 52: INTRODUCTION Narmada Cement-Jafrabad Works UltraTech ...environmentclearance.nic.in/writereaddata/FormB/TOR/Additional... · 1 INTRODUCTION Narmada Cement-Jafrabad Works a unit of

   

52 

 

8.2 Impact Assessment: Attach an Environmental Impact Assessment Statement describing the impact of mining and beneficiation on environment on the following:

i) Land area indicating the area likely to be degraded due to quarrying, dumping, roads, workshop, processing plant, tailing pond/dam, township etc.

Table A8.9: Land Use Pattern at the end of first five years (in ha)

Particulars Forest Land

Private/ Ag. Land

Grazing Land

Waste Land Others Total

a) Pits & Quarries - 6.50 - - - 6.50 b) Dumps of ore Waste & O.B./ Soil stack

- 1.10 - - - 1.10

c)Infrastructure including of office, haul roads

- 0.50 - - - 0.50

d) HT line - 1.80 - - - 1.80 e) Others (i) Govt. land (ii)Private/Ag. land

- -

-

39.7734

- -

0.172

-

- -

0.172

39.7734 Total occupied Area - 49.6734 - 0.172 - 49.8454

f) Area reclaimed/ rehabilitated by applicant = nil g) Area afforested by applicant = 2.50 ha

ii) Air quality- Air Quality

Air or atmosphere pollution is another significant consequence of mining operations. Basically Suspended Particulate Matter (SPM) is the only pollutant inducted into the atmosphere and the mining activities may contribute to the SPM concentration. Monitoring of Air Quality For effective control over the quality of air sampling stations has been established in the surrounding. It is proposed to be established AAQ samplings stations within the applied area. Samples will be collected periodically and analyzed. An analysis record of the samples will be maintained in a bound paged book to ensure that the quality of ambient air is within the permissible limit. a) Following standards in ambient air quality of mining area shall be achieved

Parameters Standard for Ambient Air for 24 hours average

PM10 100 ug/M3 PM2.5 60 ug/M3 SO2 80ug/M3 NOx 80ug/M3

Data on ambient air quality shall be regularly submitted to MoEF, SPCB/ CPCB once in six months. b) Vehicle emission shall be kept under control and regularly monitored. Measures shall be taken for maintenance of vehicle used in mining operation and in transport of mineral. The vehicles not to be overloaded. c) Fugitive dust emission from all sources shall be controlled regularly. Water spraying on

Page 53: INTRODUCTION Narmada Cement-Jafrabad Works UltraTech ...environmentclearance.nic.in/writereaddata/FormB/TOR/Additional... · 1 INTRODUCTION Narmada Cement-Jafrabad Works a unit of

   

53 

 

haul roads, loading & unloading and transfer points shall be provided and maintained. d) Persons working in dusty area shall wear protective respiratory devices and they shall be provided adequate training and education on safety and health aspect. e) Stabilization of backfilled area, if any by suitable plantation. g) Maximum use of surface miner h) Controlled blasting by competent persons i) Periodic monitoring of ambient air quality

iii) Water quality Water Quality

No ground water intersection is envisaged due to mining operations in the applied mining lease area. Rainwater accumulated in the mine sump, if required will be quite away from mining operations. In such no adverse impact on ground water as well as on surface water is envisaged. Monitoring of Water Quality a) Quality of water to be monitored periodically as per norms prescribed by CPCB and in compliance of MoEF & SPCB. b) Results of water to be reported to concerned authority c) Monitoring of water level through piezometers to be installed, if required in the area d) Relevant remedial action to be taken in case of abnormal results

iv) Noise levels Noise Level

The present noise levels as revealed by noise survey conducted at various points around the other applied ML area, noise levels are generally within the permissible limit. The noise levels shall be kept as detailed below: - (i) Day time - 75 dBA (ii) Night time - 65 dBA Monitoring of Noise Level a) Measures shall be taken for control of noise levels below 85 dBA in the work environment. Workers should be provided with ear plugs/ muffs. b) The operator's cabin would be safe guarded with proper enclosures to reduce the noise levels c) A thick tree belt would be provided in phased manner around the periphery of the mine to attenuate noise d) The prime movers/diesel engines would be proper designed and will be properly maintained e) Period monitoring of noise level as per norms

v) Vibration levels (due to blasting) Noise and vibrations are intimately connected to each other. One is the cause for other.

In opencast mines, blasting is resorted to loosen the material. The method of blasting in the Babarkot Limestone Area has already been described in Chapter “Mining”. Vibration study shall be carried out periodically during mining course. Mitigation Measures: 1. Controlled blasting practise will be proposed by competent persons 2. Modern technique i.e. NONEL shall be in practise to control vibration and flying

rocks 3. Secondary blasting shall be avoided by means of using rock breaker 4. Periodic monitoring to know intensity of induced vibration

Page 54: INTRODUCTION Narmada Cement-Jafrabad Works UltraTech ...environmentclearance.nic.in/writereaddata/FormB/TOR/Additional... · 1 INTRODUCTION Narmada Cement-Jafrabad Works a unit of

   

54 

 

vi) Water regime As the matter of fact the applied area of Babarkot Limestone is not part of seasonal or

perennial drains. Direct precipitation as well as water from catchment area shall be accumulates in sump to be created. There is no chance of disturbance of water course due to mining in the past and also in the future. Underground Drainage No source of groundwater was found in the core zone. The ground water table is quite below the present general ground level and proposed working during the period of this mining plan. Hence no ground water intersection is envisaged during this mining plan period. Prior permission, if required necessary shall be obtained from competent authority for working proposed below 2.0mRL. Mitigation Measures: a) Regular monitoring of ground water by establishing network of Piezometer at suitable locations in the project area in consultation with Gujarat Water Resources Development Corporation Ltd., Gandhinagar. The frequency of monitoring shall be four times a year. Data thus collected shall be sent at regular interval to competent authorities. b) Ground water table not to be punctured c) Wherever required, bund shall be provided around the working pits A full-fledged separate environmental management cell with suitable qualified personnel has been set-up under the control of a Senior Executive.

vii) Acid mine drainage Not applicable viii)

Surface subsidence

Not applicable ix) Socio-economics Details of Key Fields towards Community Development carried out by the company is

detailed below: Education Health care Sustainable lively hood Infrastructure development Social Changes

Expenses incurred towards community development by the company during last five years is tabulated below: -

Particulars Expenses incurred (in Lacs

Rs.) 1. Education 28.89

2. Health care 20.85 3. Sustainable lively hood 50.37 4. Infrastructure development 100.05 5. Social Changes 41.24

Total 241.4

Page 55: INTRODUCTION Narmada Cement-Jafrabad Works UltraTech ...environmentclearance.nic.in/writereaddata/FormB/TOR/Additional... · 1 INTRODUCTION Narmada Cement-Jafrabad Works a unit of

   

55 

 

Proposal of work to be done towards social welfare: - The expenses proposed to be incurred for social welfare development by the company will be under following heads: -

i. Drinking water facility ii. Public transportation iii. Safety & Medical Health iv. Education sector v. Religious work vi. And others

a. Like recreation activity. b. Prizes, Games, Sports, Scholarship etc.

The expenses proposed to be incurred towards social welfare development for period of mining plan period is proposed about Rs. 5 Lacs/- per year.

x) Historical monuments etc. No historic monuments etc. are within the applied ML area.

Page 56: INTRODUCTION Narmada Cement-Jafrabad Works UltraTech ...environmentclearance.nic.in/writereaddata/FormB/TOR/Additional... · 1 INTRODUCTION Narmada Cement-Jafrabad Works a unit of

   

56 

 

Page 57: INTRODUCTION Narmada Cement-Jafrabad Works UltraTech ...environmentclearance.nic.in/writereaddata/FormB/TOR/Additional... · 1 INTRODUCTION Narmada Cement-Jafrabad Works a unit of

   

57 

 

8.3 Progressive reclamation Plan: To mitigate the impacts and ameliorate the condition, describe year wise steps proposed for phased restoration, reclamation of lands already/ to be degraded in respect of following items separately for 5 years period.

Table A8.11: Proposal of phased restoration, reclamation of land etc. for 1st year Items Details Proposed Remarks

Area in Hect

Quantity (cum)

Expenditure in Rs.

1 2 3 4 5 6 (A) RECLAMATION & REHABILITATION OF MINED OUTLAND / AREA

i) Backfilling - - - - ii) Afforestation on the back filled area

- - - -

iii) Others (please specify eg. Afforestation on exhausted benches)

- - - -

iv) Pisciculture - - - - v) Converting into water reservoir

- - - -

vi) Picnic spot - - - - (B) STABILISATION & REHABILITATION OF DUMPS (WITHIN LEASE)

i) Terracing - - - - ii) Pitching - - - - iii) Construction of parapet walls/ Retaining wall at toe of dumps

- - - -

iv) Construction of check dams along slope of vallies

- - - -

v) Construction of Settling ponds (Garland drains etc)

- - - -

vi) Desiliting of settling ponds, channels

- - - -

vii) Afforestation on dumps - - - - viii) Others (Please specify) - - - -

( C) REHABILIATION OF BARREN AREA WITHIN LEASE

i) Afforestation (Green belt building)

0.50 500 1,50,000/- 300/- sapling

ii) Others (Care & Maint of existing plantation of reclaimed area)

- 500 1,50,000/- 300/- sapling

iii) Wire fence - 50 12,500/- 250/- mtr (D) ENVIRONMENTAL MONITORING (Core & Buffer zone separately)

i) Ambient Air Quality - - 3,50,000/- - ii) Water Quality - - 80,000/- - iii) Noise Level Survey - - 35,000/- - iv) Ground Vibration - - 1,50,000/- - v) Others Soil Analysis - - - -

Total 9,27,500/-

Page 58: INTRODUCTION Narmada Cement-Jafrabad Works UltraTech ...environmentclearance.nic.in/writereaddata/FormB/TOR/Additional... · 1 INTRODUCTION Narmada Cement-Jafrabad Works a unit of

   

58 

 

Table A8.12: Proposal of phased restoration, reclamation of land etc. for 2nd year Items Details Proposed Remarks

Area in Hect

Quantity

Expenditure in Rs.

1 2 3 4 5 6 (A) RECLAMATION & REHABILITATION OF MINED OUTLAND / AREA

i) Backfilling - - - - ii) Afforestation on the back filled area

- - - -

iii) Others (please specify eg. Afforestation on exhausted benches)

- - - -

iv) Pisciculture - - - - v) Converting into water reservoir

- - - -

vi) Picnic spot - - - - (B) STABILISATION & REHABILITATION OF DUMPS (WITHIN LEASE)

i) Terracing - - - - ii) Pitching - - - - iii) Construction of parapet walls/ Retaining wall at toe of dumps

- - - -

iv) Construction of check dams along slope of vallies

- - - -

v) Construction of Settling ponds (Garland drains etc)

- - - -

vi) Desiliting of settling ponds, channels

- - - -

vii) Afforestation on dumps - - - - viii) Others (Please specify) - - - -

( C) REHABILIATION OF BARREN AREA WITHIN LEASE

i) Afforestation (Green belt building)

0.50 500 1,50,000/- 300/- sapling

ii) Others (Care & Maint of existing plantation of reclaimed area)

- 500 1,50,000/- 300/- sapling

iii) Wire fence - 50 12,500/- 250/- mtr (D) ENVIRONMENTAL MONITORING (Core & Buffer zone separately)

i) Ambient Air Quality - - 3,50,000/- - ii) Water Quality - - 80,000/- - iii) Noise Level Survey - - 35,000/- - iv) Ground Vibration - - 1,50,000/- - v) Others Soil Analysis - - - -

Total 9,27,500/-

Page 59: INTRODUCTION Narmada Cement-Jafrabad Works UltraTech ...environmentclearance.nic.in/writereaddata/FormB/TOR/Additional... · 1 INTRODUCTION Narmada Cement-Jafrabad Works a unit of

   

59 

 

Table A8.13: Proposal of phased restoration, reclamation of land etc. for 3rd year Items Details Proposed Remarks

Area in Hect

Quantity

Expenditure in Rs.

1 2 3 4 5 6 (A) RECLAMATION & REHABILITATION OF MINED OUTLAND / AREA

i) Backfilling - - - - ii) Afforestation on the back filled area

- - - -

iii) Others (please specify eg. Afforestation on exhausted benches)

- - - -

iv) Pisciculture - - - - v) Converting into water reservoir

- - - -

vi) Picnic spot - - - - (B) STABILISATION & REHABILITATION OF DUMPS (WITHIN LEASE)

i) Terracing - - - - ii) Pitching - - - - iii) Construction of parapet walls/ Retaining wall at toe of dumps

- - - -

iv) Construction of check dams along slope of vallies

- - - -

v) Construction of Settling ponds (Garland drains etc)

- - - -

vi) Desiliting of settling ponds, channels

- - - -

vii) Afforestation on dumps - - - - viii) Others (Please specify) - - - -

( C) REHABILIATION OF BARREN AREA WITHIN LEASE

i) Afforestation (Green belt building)

0.50 500 1,50,000/- 300/- sapling

ii) Others (Care & Maint. of existing plantation of reclaimed area)

- 500 1,50,000/- 300/- sapling

iii) Wire fence - 50 12,500/- 250/- mtr (D) ENVIRONMENTAL MONITORING (Core & Buffer zone separately)

i) Ambient Air Quality - - 3,50,000/- - ii) Water Quality - - 80,000/- - iii) Noise Level Survey - - 35,000/- - iv) Ground Vibration - - 1,50,000/- - v) Others Soil Analysis - - - -

Total 9,27,500/-

Page 60: INTRODUCTION Narmada Cement-Jafrabad Works UltraTech ...environmentclearance.nic.in/writereaddata/FormB/TOR/Additional... · 1 INTRODUCTION Narmada Cement-Jafrabad Works a unit of

   

60 

 

Table A8.14: Proposal of phased restoration, reclamation of land etc. for 4th year Items Details Proposed Remarks

Area in Hect

Quantity

Expenditure in Rs.

1 2 3 4 5 6 (A) RECLAMATION & REHABILITATION OF MINED OUTLAND / AREA

i) Backfilling - - - - ii) Afforestation on the back filled area

- - - -

iii) Others (please specify eg. Afforestation on exhausted benches)

- - - -

iv) Pisciculture - - - - v) Converting into water reservoir

- - - -

vi) Picnic spot - - - - (B) STABILISATION & REHABILITATION OF DUMPS (WITHIN LEASE)

i) Terracing - - - - ii) Pitching - - - - iii) Construction of parapet walls/ Retaining wall at toe of dumps

- - - -

iv) Construction of check dams along slope of vallies

- - - -

v) Construction of Settling ponds (Garland drains etc)

- - - -

vi) Desiliting of settling ponds, channels

- - - -

vii) Afforestation on dumps - - - - viii) Others (Please specify) - - - -

( C) REHABILIATION OF BARREN AREA WITHIN LEASE

i) Afforestation (Green belt building)

0.50 500 1,50,000/- 300/- sapling

ii) Others (Care & Maint of existing plantation of reclaimed area)

- 500 1,50,000/- 300/- sapling

iii) Wire fence - 50 12,500/- 250/- mtr (D) ENVIRONMENTAL MONITORING (Core & Buffer zone separately)

i) Ambient Air Quality - - 3,50,000/- - ii) Water Quality - - 80,000/- - iii) Noise Level Survey - - 35,000/- - iv) Ground Vibration - - 1,50,000/- - v) Others Soil Analysis - - - -

Total 9,27,500/-

Page 61: INTRODUCTION Narmada Cement-Jafrabad Works UltraTech ...environmentclearance.nic.in/writereaddata/FormB/TOR/Additional... · 1 INTRODUCTION Narmada Cement-Jafrabad Works a unit of

   

61 

 

Table A8.15: Proposal of phased restoration, reclamation of land etc. for 5th year Items Details Proposed Remarks

Area in Hect

Quantity

Expenditure in Rs.

1 2 3 4 5 6 (A) RECLAMATION & REHABILITATION OF MINED OUTLAND / AREA

i) Backfilling - - - - ii) Afforestation on the backfilled area

- - - -

iii) Others (please specify eg. Afforestation on exhausted benches)

- - - -

iv) Pisciculture - - - - v) Converting into water reservoir

- - - -

vi) Picnic spot - - - - (B) STABILISATION & REHABILITATION OF DUMPS (WITHIN LEASE)

i) Terracing - - - - ii) Pitching - - - - iii) Construction of parapet walls/ Retaining wall at toe of dumps

- - - -

iv) Construction of check dams along slope of vallies

- - - -

v) Construction of Settling ponds (Garland drains etc)

- - - -

vi) Desiliting of settling ponds, channels

- - - -

vii) Afforestation on dumps - - - - viii) Others (Please specify) - - - -

( C) REHABILIATION OF BARREN AREA WITHIN LEASE

i) Afforestation (Green belt building)

0.50 500 1,50,000/- 300/- sapling

ii) Others (Care & Maint of existing plantation of reclaimed area)

- 500 1,50,000/- 300/- sapling

iii) Wire fence - 50 12,500/- 250/- mtr (D) ENVIRONMENTAL MONITORING (Core & Buffer zone separately)

i) Ambient Air Quality - - 3,50,000/- - ii) Water Quality - - 80,000/- - iii) Noise Level Survey - - 35,000/- - iv) Ground Vibration - - 1,50,000/- - v) Others Soil Analysis - - - -

Total 9,27,500/-

Page 62: INTRODUCTION Narmada Cement-Jafrabad Works UltraTech ...environmentclearance.nic.in/writereaddata/FormB/TOR/Additional... · 1 INTRODUCTION Narmada Cement-Jafrabad Works a unit of

   

62 

 

8.3.1. Mined-Out Land: Describe the proposals to be implemented for reclamation and rehabilitation of mined-out land including the manner in which the actual site of the pit will be restored for future use. The proposals may be supported with yearly plans and sections depicting yearly progress in the activities for land restoration/ reclamation/ rehabilitation, afforestation etc, called “Reclamation Plan”. Limestone is partly out-cropping, overburden sand is negligible. Therefore, no backfilling of excavated out area is envisaged during this plan period. Sand is proposed to be stacked temporarily at earmarked site. Proposed plantation: -

Table A8.16: Proposed Plantation on backfilled area

Year Number of

Plants Area to be covered

(ha) Location

1st 500 0.50

Statutory barrier of 7.5 m along the lease boundary

2nd 500 0.50

3rd 500 0.50

4th 500 0.50

5th 500 0.50

Total 2500 2.50

Survival rate envisaged is about 70% based on previous experience in the nearby mines. The location of proposed plantation is shown in Reclamation Plan, Plate No. 8. The proposed species of saplings easy to grown in the area as recommended by State Forest Department as furnished in table in chapter Mining under para “Conceptual Mine Plan”. The rainwater collected in the excavated area shall be used for greenbelt/ Afforestation/ plantation purposes. 8.3.2 Topsoil Management: The topsoil available at the site and its utilization may be described. Whatsoever overburden sand encountered shall be disposed of by means of stacking temporarily at earmarked site. 8.3.3 Tailings Dam Management: The steps to be taken for protection and stability of tailing dam, stabilization of tailing material and its utilization, periodic desilting measures to prevent water pollution from tailings etc, arrangement for surplus water overflow along with detail design, structural stability studies, the embankment seepage loss into the receiving environment and ground water contaminant if any may be described. Not applicable 8.3.4 Acid mine drainage, if any and its mitigative measures. Not applicable 8.3.5 Surface subsidence mitigation measures through backfilling of mine voids or by any other means and its monitoring mechanism. The information on protective measures for reclamation and rehabilitation works year wise may be provided as per the following table.

Page 63: INTRODUCTION Narmada Cement-Jafrabad Works UltraTech ...environmentclearance.nic.in/writereaddata/FormB/TOR/Additional... · 1 INTRODUCTION Narmada Cement-Jafrabad Works a unit of

   

63 

 

Items Details Existing Proposals

Dump management

Area afforested (ha) No waste dump exists

No proposal of waste is there. OB sand has been proposed to be stacked covering 1.1ha area.

No. of saplings planted - - Cumulative no. of plants - - Cost including watch and care during the year

- -

Management of worked out benches

Area available for rehabilitation (ha)

None No management of worked out benches proposed

Afforestation done (ha) - - No. of saplings planted in the year - - Cumulative no. of plants - - Any other method of rehabilitation (specify)

- -

Cost including watch and care during the year

- -

Reclamation and Rehabilitation by backfilling

Void available for Backfilling (L x B x D) pit wise/stope wise

None No backfilling is proposed.

Void filled by waste/tailings - - Afforestaion on the backfilled area

- -

Rehabilitation by making water reservoir

None No water reservoir is proposed.

Any other means (specify) - - Rehabilitation of waste land within lease

Area available (ha) - - Area rehabilitated - - Method of rehabilitation - -

Others (plantation)

- - 2.5ha within the safety barrier.

To evaluate the effectiveness of environmental management programme regular monitoring of the important environmental parameters will be taken up. A team of qualified and trained personnel is engaged to carry out the task and be responsible for the following: Collecting water and air samples, work zone monitoring for air pollutants. [1] Analyzing the water and air samples [2] Implementing the control and protective measures [3] Coordinating the environment related activities within the mine [4] Green belt development etc. [5] Monitoring the progress of implementation of environmental management programme [6] An area where employment opportunities presently are limited. With mining activities, local people will have a lot of direct and indirect employment avenues opened up due to enhancement in production. Hence, enhancement in mining activities will have a beneficial effect on socio

Page 64: INTRODUCTION Narmada Cement-Jafrabad Works UltraTech ...environmentclearance.nic.in/writereaddata/FormB/TOR/Additional... · 1 INTRODUCTION Narmada Cement-Jafrabad Works a unit of

   

64 

 

economic condition with schools, hospital and markets coming up in otherwise almost barren area. [7] Good housekeeping will improve the working conditions. [8] Regular cleaning of roads to avoid accumulation of dust/ water. [9] Regular cleaning/ washing of shop floors. [10] Maintaining nurseries and development of greenbelt around the mining site, the plantation of trees are not only for the suppression of dust and pollutant transportation but it is also for enhancing the aesthetic values. [11] Avoiding accumulation and dumping of waste and damaged equipment. [12] Maintaining hygienic condition in the canteen, drinking water sources and toilets. [13] Occupational safety and health is another important factor in the mining area and following steps are to be taken. [i] Audio visual dissemination of information on safety, embracing risks associated with their profession, safety regulation will be adopted meticulously [ii] Organization of safety weeks. [iii] Seminars/ workshops related to industrial safety. [iv] Mandatory use of personal safety equipment like helmets, goggles, gloves, masks muffs etc. wherever required. [14] Non-destructive testing of all equipment and machinery will be carried out at regular intervals. 8.4 Disaster Management and Risk Assessment: This may deal with action plan for high risk accidents like landslides, subsidence flood, inundation in underground mines, fire, seismic activities, tailing dam failure etc. and emergency plan proposed for quick evacuation, ameliorative measures to be taken etc. The capability of lessee to meet such eventualities and the assistance to be required from the local authority may also be described. As the area is close to coast there are chances of hitting of cyclone which may cause: [1] Flash floods [2] Damage of life and property [3] Disruption of road & telecommunication facilities. [4] Lightning The following points will be followed in this Progressive Mine Closure Plan for disaster management: [1] Working of mine as per approval. [2] Working as per applicable Rules & Regulations [3] Responsibilities from top to bottom line in case of high-risk accidents have been well defined. [4] Action plan has been made for quick evacuation in case of high-risk accident and natural disaster. 8.5 Care and maintenance during temporary discontinuance: An emergency plan for the situation of temporary discontinuance due to court order or due to statutory requirements or any other unforeseen circumstances may indicate measures of care, maintenance and monitoring of status of discontinued mining operations expected to re-open in near future. In case of any temporary discontinuance due to court order or due to statutory requirement or any other unforeseen circumstance following measures for care and maintenance and monitoring of status shall be taken.

Page 65: INTRODUCTION Narmada Cement-Jafrabad Works UltraTech ...environmentclearance.nic.in/writereaddata/FormB/TOR/Additional... · 1 INTRODUCTION Narmada Cement-Jafrabad Works a unit of

   

65 

 

Notice of temporary discontinuance of work in mine shall be given in case the discontinuance to the Controller General Controller of Mine and the Regional Controller, IBM and DGMS Officials. All the mining machinery shall be shifted to a safe place. Entrance to the mines or part of the mines to be discontinued shall be fenced off and security guards shall be posted for the safety and to restrict any unauthorized entry to the area. Competent persons shall inspect the area regularly. Air, water and other environmental monitoring shall be carried out. Care and upkeep of plantation done shall be carried out on regular basis. Status of the working and status monitoring for re-opening of the mines shall be discussed in weekly meeting on last working day of the week. In case of discontinuance due to any natural calamities mining operation will be restarted as early as possible after completing rescue work, restoring safety and security and repairs of roads.

Page 66: INTRODUCTION Narmada Cement-Jafrabad Works UltraTech ...environmentclearance.nic.in/writereaddata/FormB/TOR/Additional... · 1 INTRODUCTION Narmada Cement-Jafrabad Works a unit of

   

66 

 

8.6 Financial Assurance:- The financial assurance can be submitted in any en-cashable form preferably a Bank Guarantee from a Scheduled Bank as stated in Rule 23(F)(2) of Mineral conservation and DevelopmentRules,1988 for five years period expiring at the end of validity of the document. The amount calculated for the purpose of Financial Assurance is based on the CCOM’s Circular no. 04 dated 2006 as below. Table indicating the break-up of areas in the Mining Lease for Calculation of Financial Assurance

S. No.

Items Area put to use at start of scheme of mining (ha)

Additional requirement during plan period (ha)

Total area (ha)

Area considered as fully reclaimed & rehabilitated ha

Net area considered for calculation ha

1. Area under mining 0.165 6.50 6.665 - 6.665 2. Storage for

overburden soil - 1.10 1.10 - 1.10

3. Waste dump site - - - - - 4. Mineral storage - - - - - 5. Infrastructure –

workshop, administrative building etc.

- - - - -

6. Roads - 0.50 0.50 - 0.50 7. Railways - - - - - 8. Tailing pond - - - - - 9. Effluent Treatment

Plant - - - - -

10. Mineral Separation Plant

- - - - -

11. Township area - - - - - 12. Others (HT line) 1.80 - 1.80 - -

Grand Total 1.965 8.10 10.065 - 10.065

Under Rule 23F(3) of MCDR, lessee will deposit the financial assurance in terms of bank guarantee in prescribed format. Area to be used in mining & allied activities will be 10.065ha at the end of first five years of Progressive Mine Closure Plan. Since the proposed Mines belongs to ‘A’ category, so financial assurance calculated at Rs. 25,000/- per ha. Therefore total financial assurance will be Rs. 2,51,625/- (Rupees Two Lac Fifty One Thousand Six Hundred Twenty Five Only). The financial assurance shall be deposited in the form of bank guarantee to IMB, Udaipur after mining lease deed.

Page 67: INTRODUCTION Narmada Cement-Jafrabad Works UltraTech ...environmentclearance.nic.in/writereaddata/FormB/TOR/Additional... · 1 INTRODUCTION Narmada Cement-Jafrabad Works a unit of

   

67 

 

PART B

1.0 Certificates/ Undertakings/ Consents The above mentioned actions have been taken to be stated clearly in the mine closure plan. A certificate duly signed by the lessee to the effect that said closure plan complies all statutory rules, regulations, orders made by the Central or State Government, statutory organizations, court etc. have been taken into consideration and wherever any specific permission is required, the lessee will approach the concerned authorities. The lessee may also give an undertaking to the effect that all the measures proposed in this closure plan will be implemented in a time bound manner as proposed.

Certificates/ undertaking/ consents have been enclosed with this report.

(Rakesh Purohit) (S.K. Soni)

Date : (BE-Mining) (M.Sc. Geology) Place : Jodhpur