inventory guide
DESCRIPTION
Problems on InventoriesTRANSCRIPT
M96 Materials Booklet
Mgmt 120 Technique Review for Materials Management
This section contains study problems for the following topics.
Inventory Measures
Bill of Materials Concepts
Independent Demand Inventory Models
Materials Requirements Planning
Answers for all the problems are found in the back of this section.
1. Joan Pontius, the materials manager at Money Enterprises, is beginning to look for ways to reduce inventory. A recent accounting statement shows inventories at the following levels.
Raw materials: $2,345,000
Work-in-progress: $5,670,000
Finished Goods: $2,161,000
This year's cost of goods sold should be about $29.4 million. Assuming 52 business weeks per year, express total inventory as:
a. weeks of supply
b. inventory turns
2. One product line is experiencing 7 turns per year, and its annual sales volume (at cost) is $750,200. How much inventory is being held, on the average?
3. MINC, Inc. keeps 4 items in stock, three machines and a repair kit. The current inventory level and last years demand are shown below along with the value of the items. (Assume 52 weeks per year.)
Last year's demandCurrently on handValue
of item
Model 117,0002500$200
Model 215,0001500$300
Model 38,5002000$150
Repair kits450100$24.00
a. How many weeks of supply do they currently have on hand?
b. If the current inventory level is characteristic, how many turns per year does MINC Inc. have?
4. A subassembly is produced in lots of 450 units. It is assembled from two components worth $50. The value added (for labor and variable overhead) in manufacturing one unit from its two components is $40, bringing the total cost per completed unit to $90. The typical lead time for the item is 5 weeks and its annual demand is 1872 units. There are 52 business weeks per year.
a. How many units of cycle inventory are held, on average, for the subassembly? What is the dollar value of this cycle inventory?
b. How many units of pipeline inventory are held, on average, for the subassembly? What is the dollar value of this inventory? (Assume that the typical job in pipeline inventory is 50 percent completed. Thus one half the labor and overhead costs have been added, bringing the total unit cost to $70 (or $50 + $40/2).
5. The bill of materials from item A shows that it is made from two units of B. Item B, in turn is made from two units of purchased item C. The per unit purchase price of item C is $10. The table below gives additional information. No anticipation inventory is held.
a. what is the dollar value of inventory held, on average, for each item, broken down by cycle, safety stock, and pipeline inventory?
b. How many weeks of supply are held to support demand for item A?
ItemDemand (units/wk)Value added
($/unit)Lot size
(units)Safety stock
(units)Lead time
(wk)
A405080201
B802016002
C160-4001001
6. Consider the bill of materials diagram below.
a. How many immediate parents does item I have? item B item E?
b. How many unique components does item A have at all levels?
c. How many unique purchased items does item A have at all levels?
d. How many of item I are used in each item A?
e. How many unique intermediate items does product A have at all levels?
f. The items have the following lead times.
A: 2 weeksD: 2 weeksG: 5 weeks
B: 1 weekE: 4 weeksH: 3 weeks
C: 3 weeksF: 3 weeksI: 2 weeks
What is the customer response time if
i. all items are specials (made to order)
ii. only items E and I are standard (made to stock)
iii. only items E, F, G, H, and I are standard
EMBED Word.Picture.8
7. Item A is made from components B, C, and D. Item B, in turn, Is made from C. Item D is also an intermediate item, made from B. Usage quantities are all one except that two units of item C are needed to make one unit of B. Draw the bill of materials for item A.
8. Consider the BOM below, which includes lead times.
a. What would be the customer response time if every item is a special?
b. What would be the customer response time if items D and F are made standards?
c. List each item and whether it is an end item, a purchased part, or an intermediate item.
d. Are there any subassemblies in this BOM? If so, which item(s)?
EMBED Word.Picture.8
EMBED Word.Picture.8
9. A discount appliance store sells combination radio and tape cassette players for only $60 per unit. These hand held units have exceptional sound quality and are in great demand. For these units:
Demand = 80 units/wk
Order cost = $70/order
Annual holding cost rate = 25% of selling price
Desired cycle-service level = 75%
Lead time = 2 wk
standard deviation of weekly demand = 20 units
current on-hand inventory is 183 units, with no open orders or backorders.
The store operates 52 weeks per year. It has a continuous inventory review system.
a. What is the EOQ?
b. What would be the average time between orders (in weeks) using this EOQ?
c. What should R be?
d. An inventory withdrawal 0f 10 units has just occurred. Is it time to reorder?
10. Suppose that you were in charge of the inventory of an item worth $45 per unit. Every 4 weeks you place an order. To determine the order quantity, you take the current on-hand quantity and subtract it from 400. The result is the amount you order. The weekly demand for this product is 60, with a standard deviation of 8. The cost to place an order is $35, and the holding cost rate is $10 per unit per year. You desire to avoid having a stock out 92% of the time. Assume there are 52 weeks in a year. The lead time is a constant 1 week.
a. What is the current annual inventory cost (holding and ordering) for this item?
b. If you cannot change the frequency of orders, could you save money by changing your target amount from 400?
c. If you could change your frequency of orders, what would be the "optimal" ordering policy (Use periodic review system and round P to nearest week)? How much money would this save over the current strategy?
11. Given the following data, what is the EOQ(optimal Q) and R?
Annual demand is 20,800 units
Ordering cost is $40 per order
Holding cost rate is $2 per unit per year.
Lead time = 2 weeks
Safety stock level, set by company policy, is 1000 units.
Assume 52 weeks in a year.
12. Given the following data, compute the parameters for a periodic review system (P and T) for a P that would provide an average order quantity approximately equal to the EOQ.
Annual demand is 20,800 units
Ordering cost is $40 per order
Holding cost rate is $2 per unit per year.
Lead time = 2 weeks
Safety stock level, set by company policy, is 1000 units.
Assume 52 weeks in a year.
13. a. Complete the record using an FOQ of 45 units
Item:Lot sizeunits
Desc.Lead time4weeks
Parents:
12131415161718192021
Gross requirements253040252530
Scheduled receipts45
Projected on hand | 25
Planned receipts
Planned order releases
b. Complete the record using the L4L lot sizing rule.
Item:Lot sizeunits
Desc.Lead time4weeks
Parents:
12131415161718192021
Gross requirements253040252530
Scheduled receipts45
Projected on hand | 25
Planned receipts
Planned order releases
c. Complete the record using the POQ, with P=3 lot sizing rule
Item:Lot sizeunits
Desc.Lead time4weeks
Parents:
12131415161718192021
Gross requirements253040252530
Scheduled receipts45
Projected on hand | 25
Planned receipts
Planned order releases
14. The MPS for product A calls for 70 units to be completed in week 4 and 80 units in week 7 (the lead time is one week.) The MPS for product B calls for 150 units in week 7 (the lead time is 2 weeks). Develop the material requirements plan for the next six weeks for items C, D, E, and F. Identify any action notices that will be generated.
Item
Data CategoryCDEF
Lot-size ruleFOQ = 100L4LFOQ = 150POQ (P=3)
Lead time1232
Scheduled receipts100(week 1)None150(week 3)None
On-hand inventory350125400
EMBED Word.Picture.8
LeadMPSQuantities
ProductTime123456
Item:Lot sizeunits
Desc.Lead timeweeks
Parents:
123456
Gross requirements
Scheduled receipts
Projected on hand |
Planned receipts
Planned order releases
Item:Lot sizeunits
Desc.Lead timeweeks
Parents:
123456
Gross requirements
Scheduled receipts
Projected on hand |
Planned receipts
Planned order releases
Item:Lot sizeunits
Desc.Lead timeweeks
Parents:
123456
Gross requirements
Scheduled receipts
Projected on hand |
Planned receipts
Planned order releases
Item:Lot sizeunits
Desc.Lead timeweeks
Parents:
123456
Gross requirements
Scheduled receipts
Projected on hand |
Planned receipts
Planned order releases
Answers:
1. average aggregate inventory value = $10,176,000
weekly sales = EQ \F(29.4 million,52 weeks per year) = .565 mill/week
weeks of supply = EQ \F(10.176 million,.565million/week) = 17.99 18 weeks of supply
inventory turns = EQ \F(29.4 million,10.176 million) = 2.89 2.9 turns per year
2. turns = EQ \F(annual sales,ave. aggr. inventory value) 7 = EQ \F(750200,ave. aggr. inventory value) Thus ave. aggr. inventory value = EQ \F(750200,7) = 107,171 107,000
3.
Last year's demandCurrently on handValue
of itemValue on handYearly value in sales
Model 117,0002500$200$500,000$3.4 mill
Model 215,0001500$300$450,000$4.5 mill
Model 38,5002000$150$300,000$1.275 mill
Repair kits450100$24.00$2400$.0108 mill
Ave. aggr. inventory value = $1.2524 mill.
Annual sales = $9.185 mill.
weekly sales = EQ \F(9.185,52) = $.176650 mill
weeks of supply = EQ \F(1.2524,.176650) = 7.09 7 weeks of supply
turns = EQ \F(9.1858,1.2524) = 7.33 turns per year
4. cycle inventory = EQ \F(450,2) = 225 units
$ value = (225)($90) = $20,250
pipeline inventory = dL = EQ \B(\F(1872,52))(5) = 180 units
$ value = (180)($70) = $12,600
5. The inventory items are valued, per unit, as follows:
ItemUnit value upon completionUnit value as WIP
C$10$10
B2($10)+$20 = $402($10)+$20/2 = $30
A2($40)+ $50 = $1302($40)+$50/2 = $105
a. Average inventory in dollars
Itemcyclesafetypipelinetotal
A$130(80/2) = $5,200$130(20) = $2,600$105(1)(40)= $4,200$12,000
B$40(160/2)= $3,2000$30(2)(80)= $4,800$8,000
C$10(400/2)= $2,000$10(100)= $1000$10(1)(160)= $1,600$4,600
Ave. aggr. inventory value = $24,600
b. weeks of supply = EQ \F($24600,(40 units/week)($130/unit)) = 4.7 weeks
6. a. I: 1 ; B: 1 ; E: 3
b. 8
c. 4
d. 4
e. 4: E,B,C,D
f. i. 11
ii. 10
iii. 5
7.
EMBED Word.Picture.8
8. a. 10
b. 7
c. A - end, B - intermediate, C - intermediate, D - purchased, E - intermediate,
F - purchased, G - purchased
d. B is a subassembly
9. a. d = 80 ; D = (80)(52) = 4160
H = i*price = (.25)(60) = 15
EOQ = EQ \R(\F((2)(4160)(70),15)) = 197.04 => 197
b. Time between orders is = EQ \F(Q,d) = EQ \F(197,80) = 2.46 2.5 weeks
c. R = d(LT) + zL z, from normal table with cycle service level = 75%, = .67
demand is variable, leadtime is constant: L = = EQ \R(2) (20) R = (80)(2) + (.67) EQ \R(2) (20) = 179 units
d. 183 - 10 = 173. This is lower that the reorder point figured in part c, so an order should be placed.
10. a. Current approach: P = 4, T = 400
Safety stock = T - d(P+L) = 400 - (60)(4+1) = 100
C = EQ \B(\F((4)(60),2) + 100) (10) + EQ \B(\F(52,4)) (35) = $2,655
b. With a service level desired of 92%, the safety stock can be reduced. z = 1.41
The new target inventory would be:
T = d(P+L) + zd= (60)(4+1) + 1.41(8) EQ \R(4+1) = 300 + 25.2 = 325.2
Safety stock would be:
= T - d(P+L) = 325.2 - (60)(4+1) 25 units
C = EQ \B(\F((4)(60),2) + 25) (10) + EQ \B(\F(52,4)) (35) = $1,905
Savings = $2,655 - $1,905 = $750
c. D = (d)(ppy) = (60)(52) = 3120 per year (ppy = period per year)
optimal P = EQ \F(1,d)\R(\F((2)(3120)(35),(10))) = 2.46 weeks 2 weeks
new T = (60)(2+1) + 1.41(8) EQ \R(2+1) = 180 + 19.5 = 199.5 200
safety stock = 200 - (60)(2+1) = 20 units.
new C = EQ \B(\F((2)(60),2) + 20) (10) + EQ \B(\F(52,2)) (35) = $1,710 for a savings of $945.
11. EOQ = EQ \R(\F((2)(20800)(40),2)) = 912
Usually, R = d(L) + zL , but in this case safety stock is set at 1000.
That means R = d(L) + safety stock or R = EQ \B(\F(20800,52))(2) + 1000 = 1800
12. d = EQ \F(D,ppy) = EQ \F(20800,52) = 400
P = EQ \F(1,400)\R(\F((2)(20800)(40),2)) = 2.28 2.3 weeks
As in problem 11, safety stock is given, thus the revised formula for T is
T = d(OI + LT) + safety stock = (400)(2.3 + 2) + 1000 = 2720
13. a.
Item:Lot size45units
Desc.Lead time4weeks
Parents:
12131415161718192021
Gross requirements253040252530
Scheduled receipts45
Projected on hand | 2545451515204040151530
Planned receipts454545
Planned order releases4545 45
b.
Item:Lot sizeL4Lunits
Desc.Lead time4weeks
Parents:
12131415161718192021
Gross requirements253040252530
Scheduled receipts45
Projected on hand | 2545451515000000
Planned receipts25252530
Planned order releases25252530
c. Complete the record using the P=3 lot sizing rule
Item:Lot sizeP = 3units
Desc.Lead time4weeks
Parents:
12131415161718192021
Gross requirements253040252530
Scheduled receipts45
Projected on hand | 2545451515250030300
Planned receipts5055
Planned order releases5055
14.
Item:CLot size100units
Desc.Lead time1weeks
Parents: 1 per A
123456
Gross requirements7080
Scheduled receipts100
Projected on hand | 3513513565656585
Planned receipts100
Planned order releases100
Item:DLot sizeL4Lunits
Desc.Lead time2weeks
Parents:1 per A,1 per B
123456
Gross requirements7015080
Scheduled receipts
Projected on hand | 0000000
Planned receipts7015080
Planned order releases7015080
Item:ELot size150units
Desc.Lead time3weeks
Parents:1 per B, 1 per D
123456
Gross requirements7015080150
Scheduled receipts150
Projected on hand | 125555555125125125
Planned receipts150150
Planned order releases150150
Item:FLot sizeP=3units
Desc.Lead time2weeks
Parents:1 per D, 1 per E
123456
Gross requirements22015015080
Scheduled receipts
Projected on hand | 4001803080000
Planned receipts200
Planned order releases200
Action notices: Order 70 Ds now, order 150 Es now, order 200 Fs now
Delay shipment of 100 Cs until period 3, if possible.
Materials Management Problems
_1084786296.unknown
_1084786298.unknown
_1084790751.unknown
_1084790899.unknown
_1084786300.unknown
_1084786297.unknown
_1084786295.unknown