investigation of the ways to improve the performance …205382/fulltext01.pdfschool of technology...

52
School of Technology and Design, TD Investigation of the ways to improve the performance of a plant Undersökning av metoder för förbättring av anläggningskapacitet Växjö June 2007 Report ID: TD 039/2007 Muhammad Shahid Tufail Hamid Mehovic Department of Mechanical Engineering

Upload: lamtuyen

Post on 20-Mar-2018

215 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Investigation of the ways to improve the performance …205382/FULLTEXT01.pdfSchool of Technology and Design, TD Investigation of the ways to improve the performance of a plant Undersökning

School of Technology and Design, TD

Investigation of the ways to improve the performance of a plant Undersökning av metoder för förbättring av anläggningskapacitet

Växjö June 2007 Report ID: TD 039/2007

Muhammad Shahid Tufail Hamid Mehovic

Department of Mechanical Engineering

Page 2: Investigation of the ways to improve the performance …205382/FULLTEXT01.pdfSchool of Technology and Design, TD Investigation of the ways to improve the performance of a plant Undersökning

Organisation/ Organization Författare/Author(s) VÄXJÖ UNIVERSITET Institutionen för teknik och design Muhammad Shahid Tufail Växjö University Hamid Mehovic School of Technology and Design Dokumenttyp/Type of document Handledare/tutor Examinator/examiner Examensarbete/ Diplomawork Om Prakash Basim Al-Najjar Titel och undertitel/Title and subtitle Investigation of the ways to improve the performance of a plant Undersökning av metoder för förbättring av anläggningskapacitet Sammanfattning (på svenska) Nuförtiden är många företag intresserade av att förbättra sina produktionssystem. Det har blivit viktigt i den globala och konkurrensutsatta marknaden för överlevnad. Företagen undersöker sina produktionssystem ur olika aspekter för att nå konkurrensfördelar. Men viktigast är att finna problemet i produktionssystemet för att möjliggöra förbättringar. I denna uppsats studeras en del av produktionssystemet på ett företag för att finna problem i produktionssystemet för att kunna göra förbättringarna, och för att kunna rekommendera lösningar som leder till att företaget når sina strategiska mål. För att uppnå detta har beräkningar av anläggningseffektiviteten använts för att kartlägga nuläget. Dessa beräkningar av O.E.E. på olika arbetsstationer ger en klar bild av problemen. Det beräknar tillgängligheten av produktionssystemet som visar på underhållssystemets effektivitet. Kvalitetsutbytesberäkningarna visar på tillståndet hos maskiner och arbetares kompetens, medan anläggningseffektiviteten i arbetsstationerna visar på maskinutnyttjandet. Resultatet av uppsatsen efter beräkningarna av O.E.E. är att det finns problem med utnyttjandet av maskinerna. Ofta står maskinerna stilla eller väntar på underhåll om de går sönder. Nyckelord: Underhåll, O.E.E., Konkurrensfördelar, arbetskraftsledning. Abstract (in English) Nowadays many companies are interested to improve their production system. It has become important in globalize and competitive market for the survival. The companies are looking to their production systems in the different direction to get the competitive advantages. But the most important is to find out the problem of the production system to make improvements. In this thesis, a part of the production system of a company is studied to find the problems of the production system to make the improvements and to recommend some points to the company for the achievements of its goals. For this purpose, the overall equipment effectiveness calculations have been used to see the current situation of the production system of the company. These calculations of the O.E.E. of the different production work stations make the clear picture of the problems. It calculates the availability of the production system which shows that maintenance system’s effectiveness. The quality rate calculations of the work stations show the conditions of the machines and the worker’s skill and the calculations of the performance efficiency of the work stations show the utilization of the machines. The result of this thesis after all the calculations of O.E.E. is that there is a problem in the utilization of the machines. Most of the time the machines remain idle or wait for the maintenance if it fails. Key Words: Maintenance, O.E.E., Competitive advantages, manpower management. Utgivningsår/Year of issue Språk/Language Antal sidor/Number of pages 2007 English 52 Internet/WWW http://www.vxu.se/td

II

Page 3: Investigation of the ways to improve the performance …205382/FULLTEXT01.pdfSchool of Technology and Design, TD Investigation of the ways to improve the performance of a plant Undersökning

Acknowledgement A special thanks to the production chief Lars Kinnby for his co-operation and make it possible for us to complete our degree thesis. The authors also thank to the production team of the company which make possible to get the required information and data. We would like to specially thank the machine operators for their help to make the calculations. The authors would like to thank the supervisor associate professor Om Prakash for his help to complete our thesis and the rest of the personnel at the department of the tero technology at Växjö University for the help and support. Authors would like to specially thank for Mirka Kans and Anders Ingwald for their support through out the course. Authors would like to thank to the class fellows and friends for the discussions on the different topics which are helpful to clear the ideas of the programme. Muhammad Shahid Tufail Hamid Mehovic

III

Page 4: Investigation of the ways to improve the performance …205382/FULLTEXT01.pdfSchool of Technology and Design, TD Investigation of the ways to improve the performance of a plant Undersökning

Table of contents 1. Introduction ……………………………………………………………………. 1

1.1 Background………………………………………………………………..1 1.2 Problem discussion……………………………………………………….. 2 1.3 Presentation of problem…………………………………………………. 2 1.4 Problem formulation………………………………………………………3

1.5 Purpose…………………………………………………………………….. 3 1.6 Relevance…………………………………………………………………... 3 1.7 Limitations…………………………………………………………………. 3 1.8 Timeframe…………………………………………………………………. 4 2. Research methodology………………………………………………………… 2.1 Positivism and Hermeneutics………………………………………… 2.2 Qualitative and Quantitative methods…………………………………. 2.3 Data collection technique…………………………………………….. 2.4 Induction and deduction……………………………………………….. 2.5 Research strategies …………………………………………………… 2.5.1 Experiment…………………………………………………… 2.5.2 Survey………………………………………………………… 2.5.3 Interview……………………………………………………… 2.5.4 Observation…………………………………………………… 2.5.5 Case study……………………………………………………. 2.6 Validity and Reliability ……………………………………………… 2.7 Research method selection…………………………………………… 3. Theory…………………………………………………………………………. 3.1 Maintenance…………………………………………………………… 3.2 Maintenance Objectives……………………………………………… 3.3 Maintenance management……………………………………………. 3.4 Maintenance strategies……………………………………………….. 3.4.1 Preventive maintenance………………………………………. 3.4.2 Predictive maintenance………………………………………. 3.4.3 Breakdown maintenance……………………………………… 3.4.4 Design out maintenance………………………………………. 3.5 Maintenance techniques………………………………………… 3.6 Maintenance and production relationship……………………………. 3.7 Competitive advantages through efficient maintenance………………

3.8 Introduction and history of Total productive maintenance…………… 3.9 Definition of TPM……………………………………………………..

3.9.1 Down time losses……………………………………………… 3.9.2 Speed losses…………………………………………………… 3.9.3 Defect or Quality losses……………………………………….. 3.10 Overall equipment effectiveness (OEE)…………………………….

4. Empirical findings…………………………………………………………….. 4.1 Henjo Plåtteknik AB Ljungby……………………………………….. 4.2 Introduction ………………………………………………………….. 4.3Organizational plan of the company……………………………………. 4.4 Company working style and different processes…………………….. 4.5 Products of Henjo Plåtteknik AB…………………………………….. 4.6 Description of the production section activities ……………………… 4.7 Production process……………………………………………………

1 1 2 2 3 3 3 3 4 5 5 5 6 6 6 6 7 7 7 7 7 8 9 9 9 10 10 10 10 11 11 12 12 13 14 14 14 15 15 16 18 18 18 19 19 20 21 23

IV

Page 5: Investigation of the ways to improve the performance …205382/FULLTEXT01.pdfSchool of Technology and Design, TD Investigation of the ways to improve the performance of a plant Undersökning

4.8. Quality ……………………………………………………………….. 4.9. Maintenance…………………………………………………………..

4.10. Goals of the company……………………………………………….. 5. Analysis…………………………………………………………………………

5.1. O.E.E. calculation of Laser cutting work station……………………… 5.2. O.E.E. calculation of Bending work station…………………………

5.3. O.E.E. calculation of Punching work station………………………… 5.4. O.E.E. calculation of Robot Welding work station…………………… 5.5. Production line 1 & 2…………………………………………………. 5.5.1 O.E.E. calculation of Line 1 …………………………………. 5.5.2 O.E.E. calculation of Line 2………………………………….. 6 Results and Discussion………………………………………………………….. 7 Conclusions…………………………………………………………………….. 8 Recommendations………………………………………………………………. References………………………………………………………………………… APPENDIX #1……………………………………………………………………. APPENDIX #2…………………………………………………………………….

25 25 26 27 27 29 30 32 33 33 33 39 42 43 44 46 46

V

Page 6: Investigation of the ways to improve the performance …205382/FULLTEXT01.pdfSchool of Technology and Design, TD Investigation of the ways to improve the performance of a plant Undersökning

1. Introduction In this chapter the background and problem formulation with discussion for the case study will be presented. Further on the limitations and purpose of the case study will be stated. 1.1. Background

With the start of the new century, the competition and pressure to perform competitively have increased on the companies. This new age will be challenge for the companies to provide new, exciting, innovative and cost effective products in the market. (Bean R. & Radford R., 2000). Now the business has become globalize and competitive. To survive, a company has to offer best prices to its customers with high quality, service and operate with lowest cost. It is only possible for a company if all of its departments are well managed (Andersson D., 2005). In today’s competitive environment, companies want to get the benefits of the different techniques which are being used in the product processes. They have implemented total quality management (TQM), just in time (JIT) manufacturing and total employee involvement (TEI). Now many companies have shifted their focus to optimization of their assets. One of the main parts of the company which has a strong influence on the assets is the maintenance department or the employees responsible for maintenance (Wireman T.1998).the different concepts to meet the requirements of the manufacturing plant are not successful without the support of the quality and maintenance strategy. For example, JIT manufacturing concept demands for an effective and efficient maintenance which can ensure smooth flow of production and ideally, cent percent quality cost effectively. The maintenance adds to customer value in terms of profit, quality, time and service. Therefore, the maintenance function has become important for a manufacturing company’s ability to maintain its competitiveness. Without well maintained equipment; it will not be advantage in the market that requires low cost products at a high quality to be delivered quickly. (Alsyouf I.2004) There is no doubt that the maintenance has a vital role in the companies. Now a days most of the companies are giving attention to this important function which is considered as the necessary evil for the companies, i.e. an expense to the companies and a non value addition function. The companies can not survive for long time without considering the maintenance as an important function because they will be put out of the business by the companies that are considering the maintenance as a competitive weapon. Now the companies are looking it as a way to reduce the cost of producing their products. There is no doubt that it is another main area of cost. The cost reduction of this area is not meaning the decrease in service or the quality of the service. It means that the good control of the maintenance organization. The companies have used different organisational structures, change reporting structures, upsizing, downsizing, contracting out, and empowered teams for the purpose to control the maintenance. It has been realised that a typical developed system consists not only of mechanical components but also other elements such as electronic, hydraulic, electromechanical elements, software and human beings are involved in the system. This means that the disturbance in the production process may occur due to different factors such as the failures of the important components of equipments, the quality of the purchase materials and spare parts, design, manufacturing process

1

Page 7: Investigation of the ways to improve the performance …205382/FULLTEXT01.pdfSchool of Technology and Design, TD Investigation of the ways to improve the performance of a plant Undersökning

control, management systems and human error. (Tajiri M., Gotoh F.,1992 ; Wireman T.1998) The effectiveness of the manufacturing companies remains at the certain level. This is due to improper maintenance and unavailability of the equipments. In most of the manufacturing plants, the equipment is susceptible to failure through breakdown maintenance, deterioration in performance through age and use and obsolescence due to improvements in the technology. Maintenance has a strong effect on above mentioned areas. Also it can reduce the cost of the manufacturing process, improve the quality and capability of the production process. These internal improvements of the manufacturing system can be more profitable, improve the environment and safety. The unforeseen stops, speed losses, and quality defects in the operating equipments reduce the working potential of the manufacturing plant from twenty to seventy percent. These factors become the reason for the production losses and other indirect hidden costs. Ultimately, it affects the overall performance of the company. The interruptions are not only due to the maintenance but bad maintenance can be important part of the causes of disturbances (Jonsson P., 1999). The importance of maintenance has been increased than before, due to its role in maintaining and improving availability, performance efficiency, and quality products, on time deliveries, the environment, safety requirements and overall plant productivity at a high level.

1.2. Problem discussion Nowadays many companies are interested to improve their maintenance system. Because, they have come to know that this is the system through which companies can reduce the cost of their products and can develop a reliable production process. A well designed maintenance structure can be helpful for the companies to get the competitive advantages. But majority of companies are not able to manage a maintenance system. The two main reasons for that are the lack of proper measurement and the lack of control systems for maintenance. (Wireman T., 1998) The main goal of the maintenance is to reduce the failures of the industrial plant, machinery and equipments. This goal can be achieved by using different maintenance approaches such as corrective maintenance and preventive maintenance e.t.c. A good maintenance approach and schedule can not be 100 percent effective at all the time. Unforeseen equipment breakdowns and requests reduce the efficiency of the plan. Even now a good maintenance schedule can get 70 to 90 percent efficiency (Wireman T., 1994).The detection and implementation of a suitable maintenance approach makes the companies able to prevent the premature maintenance cost, maintain the stable manufacturing capabilities and control the deterioration of the system. In other words, the company can improve its performance if it implements a suitable maintenance approach for eliminating the causes of production disturbances.

1.3 Presentation of problem The idea with this project is to see the current situation of the company. Is the company using its manufacturing equipments in a proper way to get the competitive advantages? If not, then find out the main reason for that. Which kind of

2

Page 8: Investigation of the ways to improve the performance …205382/FULLTEXT01.pdfSchool of Technology and Design, TD Investigation of the ways to improve the performance of a plant Undersökning

problem is there i.e. availability, quality or performance efficiency? And what is the influence of these problems to achieve the goals of the company. The company can not compete in the competitive market unless it uses it resource and capabilities to the maximum level. The company must have to work to get rid of the problems to get the competitive advantages with respect to cost, service, quality and on time delivery. These issues do not allow the company to achieve its set goals.

1.4 Problem formulation • To investigate the current situation of the production of the case company. • To pick up the weakening in the production system those do not allow the

company to achieve its full capacity and meet the set goals. • To suggest the ways to improve the situation.

1.5 Purpose The purpose of this case study is to take a systematic and scientific way to analyse the current situation and suggest the ways to improve it to achieve the set goals. 1.6 Relevance Now a days companies are realising the importance of the maintenance in the competitive environment. They are looking to get the benefits of the maintenance. They want to make a reliable manufacturing system with minimum failures and to improve the production capacity of their plants. This is the main focus of the maintenance. The overall equipment effectiveness of the production process is the way of understanding the current situation and it gives the direction to put forward an initiative to improve the situation. Because it makes the problems clear and the effect of these problems on the company’s business can be seen easily. The value of this can be increased with the help of the full participation of the employees from management to workers and a maintenance system in the company. This study future will show the way the company’s profitability can be improved and the set goals can be meet. 1.7 Limitations The limitations of this case study are to study one manufacturing company and two production processes because these are the main production lines of the case company and of the time limitations. We are not able to study all the machines individually in selected work stations. We use the average value of all the machines at a work station. All the calculations are based on one year’s data (2006).

3

Page 9: Investigation of the ways to improve the performance …205382/FULLTEXT01.pdfSchool of Technology and Design, TD Investigation of the ways to improve the performance of a plant Undersökning

1.8 Timeframe

The time frame for the project is as follows. Introduction Methodology Theory Analysis Conclusions Collecting data Week 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23

4

Page 10: Investigation of the ways to improve the performance …205382/FULLTEXT01.pdfSchool of Technology and Design, TD Investigation of the ways to improve the performance of a plant Undersökning

2 Research methodology Many definitions of Research have been given, as a systematic method of gaining new knowledge or a way to answer the questions. (Gliner, Jeffrey A., Morgan, George A., 2000) Research methodology is considered as a supporting subject. It is used to develop a variety of research paradigms. These paradigms are varying in their contents and substance but their broader approach to inquiry is the same. ’Although the basic logic of scientific methodology is the same in all fields, its specific techniques and approaches will vary, depending on the subject matter’. There are two basic steps in the research process. The first step is to decide the goal or research questions. The second step is to find out the way to get the answers of the questions. The path to get the answers of the questions is composed of the research methodology. The selection of suitable methods, procedures and models are played an important role in each operational step of the research process to get the objectives of the research. (Kumar R., 2005). 2.1 Positivism and Hermeneutics Positivism has the roots in empirical scientific tradition. The positivist considers the complete knowledge while the hermeneutic is more understandable for the practical mind. Positivism has the belief that human being can get the knowledge in only two ways i.e. what we can sense (empirical knowledge) and what we can workout with our logical aptitude. Any one can find the fact with the help of empirical knowledge. According to the positivism the logical truths have nothing to do with observations from the reality, it has only to do with our intelligence and our way to use the language. A person should be critical to study a statement or an observation and the study should be based on the facts i.e. they can be used with out any hesitation. To be capable to make the result from these facts, a logical analysis must be preferred. Positivistic community have normally a critical view on the world around themselves. (Gliner, Jeffrey A., Morgan, George A., 2000) Hermeneutic is a science of interpretation. It uses the interpretation of pre-understanding type and learning of interpretation. Hermeneutic is about interpretation of meanings. It can be used to interpret the context in words, symbols and experience e.t.c. the interpretation explain the sense and relation which lie at the back of everything and can appear or which can be observed in the text, conversation or an act. It is must for the person that makes the interpretation to choose a starting point for the questions because the material will be based on it. The starting point consists of the basic vision, assessments and interpretation. The hermeneutic research is subjective as compare to the positivistic research. The hermeneutic researcher uses own assessments when doing the research. The pre-understanding is represented by the researchers experience and knowledge. Hermeneutic can also be observed as a common knowledge about communication and understanding. (Järvinen.P., 2001) 2.2 Qualitative and Quantitative methods The two main ways are used in the research called as quantitative or qualitative, which will be used is based on the available information. The qualitative analysis is theoretical and less nearer to the raw data as compare to the quantitative analysis. Word or sentences are used in the qualitative method but mathematical figures

5

Page 11: Investigation of the ways to improve the performance …205382/FULLTEXT01.pdfSchool of Technology and Design, TD Investigation of the ways to improve the performance of a plant Undersökning

are used in quantitative method. Like as the terms “less than” or “bigger than” can be used in qualitative method but the exact figures are used in the case of quantitative method. In the quantitative method, the researcher gathers the data and carefully examines it. The attempt is made to find the relations between different sets of facts. The researchers calculate and use the scientific technique to get the result. In the qualitative method, the researcher is more interested in the knowledge of people. (Ingwald A., 2004) 2.3 Data collection technique There are two types of data which are collected for the research purpose, primary data and secondary data. Primary data mean new data. While secondary data mean the data which already exist. The methods used to collect the new data are observations, interviews and experiments. There are some problems to the use of the data. One problem is the compatibility and the other trustworthiness. (Ingwald A., 2004) 2.4 Induction and Deduction Induction and deduction are two different ways of making the decisions. Empirical facts are the base for the conclusions in Induction approach. It is vital to understand that inductive conclusion can not be hundred percent accurate. This is only because of the empirical material is the base of the conclusion. It means that there is a probability of different results from different persons. (Järvinen P., 2001) Logic is used to make the conclusions in the deduction approach. The conclusions must be reflected as valid, logically. On the opposite this conclusion need not be true according to the reality. The conclusion can be ruled out due to the experience in the induction and this is the main dissimilarity in the induction and deduction way of making conclusion. (Järvinen P., 2001) 2.5 Research strategies There are different research methods which can be useful when performing a project. (Alsyouf I., 2001)

2.5.1 Experiment

The experiment method is divided into laboratory experiment, quasi experiment and field experiment researches. The laboratory experiment is performed in the same environment conditions for each object that takes part in the research. The basic parameters and variables are control in this type of research. The quasi experiment research is almost the same as laboratory research. But the difference is that the research is done in the reality with out control on the variables.

6

Page 12: Investigation of the ways to improve the performance …205382/FULLTEXT01.pdfSchool of Technology and Design, TD Investigation of the ways to improve the performance of a plant Undersökning

In the field experiment research, the researcher has good chance to control the variables as compare to the quasi experiment research. This method of research is also done in the reality. (Dyer C., 1995)

2.5.2 Survey The survey research uses the many basic research methods to get the data from participants in their natural environments. The basic way to get information in this method is survey. This survey is consisting of a set of one or more questions that ask the people about different issues. Opposite to the experiment research, the survey researcher does not control the variables but does inflict some constraints on the participants by using the survey tool. It is used to test the relationship between different variables. (Graziano A. and Raulin M., 2000) 2.5.3 Interview Researcher and interviewed persons are the requirement of this method. The researcher must be talented to place one self in the current situation. The researcher must take the record on the problem area that is discussed and the interviewed person must be capable to argument for the researcher’s opinion. (Järvinen P., 2001) 2.5.4 Observations This method is divided into two parts. These are named as participant and non-participant observations. In the participant observation research method, the participators are alert that they are under study. Non-participant observation research method is opposite to the open research method. The participators do not have an idea that they are under observation. (Järvinen P., 2001) 2.5.5 Case study It consists of different kind of researches. It can be based on combinations of quantitative and qualitative proof .it does not require always consisting of direct, detailed observations as a proof. The researcher chooses the most suitable method for the specific case i.e. interview or survey e.t.c. (Sekaran U., 2000). The main advantage of the case study is that the researcher can focus on one exact thing or fact and then try to discover the affect of different factors on it. 2.6 Validity and Reliability Validity views the degree to which an observation measures what it claims to measure. Validity is a theory, model, or concept which describes the reality exactly. Internal validity and external validity are the main types of the validity. The external validity is about the theoretical part of the research. While the internal validity deals with the project. It also deals with the connection between the theoretical part and the empirical parts of the research. If the different portions of the project are not able to get the required validity, it will also lead to unachieved validity for the whole project. (Järvinen P., 2001)

7

Page 13: Investigation of the ways to improve the performance …205382/FULLTEXT01.pdfSchool of Technology and Design, TD Investigation of the ways to improve the performance of a plant Undersökning

Reliability views the degree to which observations by different researchers studying the fact with same reason will get nearly the same results. (Gummeson E., 1988) There are three kinds of reliability: quixotic, synchronic and diachronic. The quixotic reliability is the extent to which a specific technique of observation generates an even measurement. The Synchronic reliability is the extent to which observations within the same time interval are similar. The Diachronic reliability is the extent to which a specific technique of observation generates the same measurements when exposed to specific observable fact at different points in time. (Järvinen P., 2001) 2.7 Research Method Selection The research strategy that is going to use in project is the case study. The case study consists of the interviews and the observations. That is the reason that the both qualitative and quantitative methods will be use in the project. The qualitative method is used when interviews are conducted and the quantitative method is used when the data is collected and analysed. The writer will collect data by themselves and will receive from the company employees. In other words, the primary and secondary data will be used. The deduction approach will be used in this case study project. This approach is helpful when comparing the collected data with the theory. The purpose of the data collection will be explained to the persons involved in the information so that a valid and reliable data can be used in the project.

8

Page 14: Investigation of the ways to improve the performance …205382/FULLTEXT01.pdfSchool of Technology and Design, TD Investigation of the ways to improve the performance of a plant Undersökning

3. Theory Nowadays the costumer’s demand is increasing. They want quality products at low cost with high service level. This attitude of the market compels the companies to make research on their production systems. Therefore every company wants to utilise their machines and equipments at the highest possible extent. This is possible only if they have a good maintenance system which makes the companies manufacturing equipments a best possible working condition. In this chapter, the theory about the maintenance concept will be presented.

3.1 Maintenance: Maintenance is a multidisciplinary area and it is hard to explain its different function. It has been defined in Macmillan’s dictionary of production management and technology as “The care and repair of equipment. There are several approaches to maintenance in manufacturing but in each case, a more strategic view is generally taken today than previously. Many of new techniques (e.g. JUST IN TIME) depend upon totally reliable equipment, and the term ‘TOTAL PLANNED MAINTENANCE’ has coined to cover this …maintenance may be PLANNED or PREVENTIVE, but some production plant is best maintained on a REACTIVE basis-having the ability to respond very quickly to plant failure.” Maintenance management in the European standard is defined as:” All activities of the management that determine the maintenance strategy, objectives and responsibilities and implement them by means such as maintenance planning, maintenance control and supervision, improvement of methods in the organisation including economical aspects”. The above definitions stress on the complicated role of maintenance. Various maintenance methods concentrate on different aspects of maintenance. The strategic and integrated maintenance is the demand for the Lean organisations. But reactive maintenance policies are reliable for some other environments. The maintenance area covers equipment and technical systems as well as organisational, human and economical aspects (Josson P., 1999) 3.2 Maintenance Objectives Maintenance is vital for the process industry .this fact was recognised and raised with the development of the Japanese’s industry. The strengthening, year by year, of maintenance management in the process industry occurred for different reasons. In the industry, production relies heavily on the plant itself, so that the most of the factors like productivity, quality, safety, pollution, and production costs depend on the condition of the plant. Also most of the industry production is of the continuous, integrated type, so plant and equipment problems generate enormous financial losses. The primary objectives of maintenance are:

• To extend equipment life. • To keep the plant and equipment in the optimal condition for production or

service and secure maximum return on the investment. • To constantly maintain the ability to cope with emergencies. • To assure safety.

(Suzuki T., 1992)

9

Page 15: Investigation of the ways to improve the performance …205382/FULLTEXT01.pdfSchool of Technology and Design, TD Investigation of the ways to improve the performance of a plant Undersökning

3.3 Maintenance management: The aim of the maintenance management was kept maintenance program operating efficiently toward the objectives of the maintenance. Once the equipment is assembled and fitted, test operations are completed and the equipment is handed over to the company and started up. At this point, the maintenance management step begins, covering the life cycle of the equipment. Maintenance management deals with the maintenance of equipment in various technical ways by using the different maintenance approaches. (Suzuki T., 1992) 3.4 Maintenance strategies: In maintenance different strategies are used. But it depends on the failure modes and their behaviour in time. The different maintenance strategies to meet the failures are as follow.

• Preventive maintenance • Predictive maintenance • Breakdown maintenance • Bad actor management

3.4.1 Preventive maintenance: The term “Preventive maintenance” means “Periodic maintenance” and is known as all over the world. Preventive maintenance in this sense is a periodic or scheduled activity, which has as its objective the direct prevention of failure modes or defects. In its simplest form this activity consists of the periodic lubrication, coating, or cleaning of the machinery components to increase the useful life duration. Periodic preventive maintenance is very useful in case of some failure modes but it is not effective for all kind of failure modes. Moreover, quite often deterioration cannot be completely abolished even in those failure modes that do respond to preventive maintenance. For example, by periodically renewing the lube oil in a pump bearing, it does not mean that the deterioration of the bearings will be finished by this activity. Because there are so many other factors which are involved in the deterioration. The quality of the oil itself may be the reason of the deterioration. So the wear of the bearings can be reduced but can not be finished. (Bloch Heinz P., Geitner Fred K., 1999) 3.4.2 Predictive maintenance: Predictive maintenance is periodic inspection activity. If any defect is deducted during inspection, it may be the replacement or overhauling of the machine parts, this maintenance activity performs its role to remove the problem of the machine. These actions of predictive maintenance do not directly reduce the deterioration rate but indirectly control the chance and cost of the accidents, breakdowns, malfunctions, and general trouble. This maintenance activity is referred as the predictive maintenance. The preventive maintenance looks mainly the time-dependent failure modes and predictive maintenance deals with the randomly and suddenly happening failure modes as far as possible by searching for them and by effecting timely repairs. With the implementation of this maintenance technique, the expectations to prevent the failures are

10

Page 16: Investigation of the ways to improve the performance …205382/FULLTEXT01.pdfSchool of Technology and Design, TD Investigation of the ways to improve the performance of a plant Undersökning

not high and are not possible to control the failures completely. But the influence on the consequences of the unexpectedly occurring defects can be reduced with this technique. Predictive maintenance strategy point out a continuous search for defects is required and in other words a continuous monitoring of the machinery condition and performance is necessary with the continuous feedback. This type of maintenance highly depends on the vigilant operators and the maintenance people as well as the type of the plant under consideration. In reality, the majority of the activities in the predictive maintenance are some how periodic and depend on the observer’s sense of seeing, hearing, feeling and smell. (Bloch Heinz P., Geitner Fred K., 1999) 3.4.3 Breakdown maintenance: Some people are optimistic about the possibilities of machinery preventive maintenance. This ability of some people can not be the parameter for the breakdown maintenance. But there are several limitations to machinery preventive maintenance concepts.

• The limitations set by random failure events. But random machinery failures are not happened after equal time intervals and form this reason, predictive maintenance is preferred in industry over breakdown maintenance. Continues inspections are the only solution of this kind of problems.

• The life dispersion of the machinery components. The time-dependent failures are not predictable at all yet. They are not occurring after the same time intervals. There can be different reasons for that. For example, the life dispersion of the mechanical gear couplings on process compressors. There is no doubt that they are components going to wear with time. If it can be assume that mean time between failures or the mean time between reaching of defect is 7.5 years. But it can be happened that the failure become after 3 years or after 15 years. This can be happened due to the misalignment, lubrication losses e.t.c.

• The third limitation of preventive maintenance in machinery is that in order to inspect we have to shut down and open up. It is a risky procedure.

We conclude from this that certain breakdown maintenance of our machinery will always be necessary. This maintenance activity brings back the machinery equipment to service after failure modes developed that were: Preventable but not prevented. Predictable but not predicted. Predicted but not acted open. Not preventable or predictable. (Bloch Heinz P., Geitner Fred K., 1999) 3.4.4 Design out maintenance This type of maintenance is different from the other types of maintenance. The aim of this maintenance type is also to minimise the failures with to minimisations of the reasons of the maintenance. Obviously, this is an engineering problem but its responsibility is also on the maintenance department. This maintenance is considered for the items of high maintenance cost which is may be due to poor maintenance, poor design or operation outside the design specifications. Some times, the design out maintenance

11

Page 17: Investigation of the ways to improve the performance …205382/FULLTEXT01.pdfSchool of Technology and Design, TD Investigation of the ways to improve the performance of a plant Undersökning

has the purpose to work on an item which does not require maintenance. Therefore, this kind of policy can be apply effectively if an information system exists which gives the service in the identification of such items. The decision is made in between to bear the cost of the redesign of the item or the cost of the repeated maintenance. (Kelly A., 1984) 3.5 Maintenance techniques: Maintenance methods and diagnostic techniques are different according to the technical category of the equipment dealt with, whether it consist of fixed vessels such as towers, tanks, heat exchanger, or rotating machines such as compressors, motors, pumps, speed reducers or furnaces, instrumentation, piping and so on. It depends on the management of each company to which method they use in maintenance. (Suzuki T., 1992) 3.6 Maintenance and Production relationship Maintenance has an important place in any organisation and it is to be positioned as a sub process or integrated part of the overall production process. The relation between maintenance and production can be shown in the figure 3.1 below. The primary inputs to production process are material, energy and manpower .These primary inputs are then transformed into primary output i.e. the final product. This transformation of primary inputs to primary output leads to a secondary production output that is the maintenance demand. Maintenance affects the potential production capacity of the plant and is necessary to keep the potential production capacity of the plant on the maximum level. In other words, it is the secondary input of the production process. (Josson P., 1999).

Production process Primary input Primary output

Secondary input

Secondary output

Maintenance

Figure 3.1 Production-maintenance processes

12

Page 18: Investigation of the ways to improve the performance …205382/FULLTEXT01.pdfSchool of Technology and Design, TD Investigation of the ways to improve the performance of a plant Undersökning

3.7 Competitive advantages through efficient maintenance The efficient maintenance influences the productivity, competitiveness and profitability of the manufacturing process because it has the direct impact on the quality, efficiency and effectiveness of the production process. In an organisation, the operations function has the responsibility to produce the goods or provide the service to the costumers of the company. In any manufacturing company, the company consists of many departments like engineering, planning, purchasing, manufacturing, quality, maintenance, despatch, e.t.c. but the operations function has relatively high budget as compared to the all other departments and consists of the largest part of the company’s budget. The main reason for that is to manage the manufacturing activities effectively, efficiently, and with high quality. The most cost effective maintenance approach has the influence on the performance of the business and on the performance of the maintenance itself. The maintenance has directly influence on the quality of the operations. On there hand, the operation quality and maintenance efficiency has the influence on the effectiveness and efficiency of the operations processes. There is no doubt that the result of a good quality, efficiency, and effectiveness of the operations processes comes in the form of productivity advantages i.e. lower cost, and value advantages(in terms of good image and reputation in the market).This leads a company towards the competitive advantages (Figure 3.2).(Alsyouf I., 2001)

3.8 Introducti

Competitive advantages

Productivity advantages

Value advantages

Profitability

Operation effectiveness

Operations quality

Operations efficiency

Efficient maintenance

Figure 3.2 How does the maintenance influence the company’s competitive advantages?

13

Page 19: Investigation of the ways to improve the performance …205382/FULLTEXT01.pdfSchool of Technology and Design, TD Investigation of the ways to improve the performance of a plant Undersökning

3.8 Introduction and history of Total productive maintenance TPM methodology was started in Japan in 1971.The concept of this methodology was come from USA. (Nakajima S., 1988).In those days the Japanese’s industry was in critical economic situation due to the oil crises and was searching the effective measures to survive in the worldwide market. They took the basic idea of the productive maintenance (PM) from united state and modified it by the Japan institute of plant maintenance to TPM system. This system was develop step by step in small group activities (Tajiri M.,Gotoh F.,1992).Therefore, TPM is an American style of productive maintenance which has been modified and improved to fit it in the Japanese industrial environment. Now it is normal in Japanese industry and becoming popular in other western countries (Nakajima S., 1988). The development of TPM is usually divided into four main development stages and these are as:

• Breakdown maintenance • Preventive maintenance • Productive maintenance • Total productive maintenance(TPM)

(Nakajima S., 1988). 3.9 Definition of TPM Total productive maintenance is also known as the productive maintenance with everyone’s participation. It can be defined as including the following goals:

1. The TPM is concentrate to maximize the overall equipment effectiveness. 2. The TPM has the aim to establish a comprehensive preventive maintenance system

for the whole life span of the equipment. 3. The TPM involve all departments which make planes, use and maintain the

equipment. 4. TPM makes the participation of all employees from top management to workers. 5. TPM promotes the preventive maintenance through motivation management i.e

through autonomous small group activities. (Suzuki T., 1992)

TPM has the main goal to maximize the overall equipment effectiveness. So to achieve its goal, TPM try to reduce the six big losses that are the main problems to get the high equipment effectiveness. The link of the losses and the effectiveness in TPM is defined in terms of both the quality of the product and the equipment availability. On the base of the detail study of the factors involve in the reduction of the equipment effectiveness are divided into six main types. 3.9.1 Down time losses

• Breakdown losses These kinds of losses are due to the defects of the equipment which need any kind of repair or maintenance. These kinds of losses consist of downtime along with the

14

Page 20: Investigation of the ways to improve the performance …205382/FULLTEXT01.pdfSchool of Technology and Design, TD Investigation of the ways to improve the performance of a plant Undersökning

labour and the spare parts required fixing the problem. The amount of these losses is calculated in the form of downtime.

• Setup and adjustment losses These losses are due to the changes in the operating conditions, like the start of the production or the start of the different shifts, changes in products and condition of the operation. The main examples of this kind of losses are equipments changeovers, exchange of dies, jigs and tools. These losses consist of setup, start-up and adjustment down times. The amount of these losses is calculated in the form of downtime. 3.9.2 Speed losses

• Minor stoppage losses These losses are due to the reason of machine halting, jamming, and idling. Many companies are considering these minor stoppages as the breakdowns in order to give importance to this problem.

• Speed losses These losses are due to the reduction in speed of the equipment. In other words the machine is not working at the original or theoretical speed. If the quality defect and minor stoppages occurs regularly then the machine is run at low speed to cover the problems. These losses are measured in the term of theoretical to the actual operating speed ratio. 3.9.3 Defect or Quality losses

• Quality defect and rework losses These losses are due to the defective products during the routine production. These products are not according to the specifications. So that rework is done to remove the defects or make a scrap of these products. Labour is required to make a rework which is the cost for the company and material become a scrap is also another loss for the company. The amount of these losses is calculated by the ratio of the quality products to the total production.

• Yield losses These losses are due to wasted raw materials .The yield losses are split into two groups. The first one is the raw materials losses which are due to the product design, manufacturing method e.t.c. The other group is the adjustment losses due to the quality defects of the products which are produced at the start of the production process, changeovers e.t.c. These six big losses indicate the three main topics which are the availability, performance rate and total yield rate (quality rate). These three topics are the base for the overall equipment effectiveness calculations.

15

Page 21: Investigation of the ways to improve the performance …205382/FULLTEXT01.pdfSchool of Technology and Design, TD Investigation of the ways to improve the performance of a plant Undersökning

O.E.E = Availability * Performance rate * Quality rate

• Breakdown losses • Setup and

adjustment losses

• Minor stoppage losses • Setup and adjustment

losses

• Breakdown losses • Setup and

adjustment losses

(Tajiri M., Gotoh F., 1992) 3.10 Overall equipment effectiveness (O.E.E) The overall equipment effectiveness is the main goal of the TPM system. It is the benchmark of the any TPM process and is used to measure the equipment effectiveness. The formula for equipment effectiveness measures the availability, the rate of performance, and the quality rate. It can be done with the involvement of all departments to measure the equipment effectiveness .The formula of the overall equipment effectiveness is as follows O.E.E = Availability * Performance rate * Quality rate (Mobley R.K., 2002)

1. Availability The availability is calculated as the required availability minus the downtime and then divided by the required availability. This can be written in the form of formula as Availability = Required availability – Downtime * 100 Required availability The required availability can be defined as the time of production to operate the equipment minus the other planned downtime like breaks, meetings e.t.c. The down time can be defined as the actual time for which the equipment is down for repairs or changeovers. This time is also some times known as the breakdown time. The out put of this formula gives the true availability of the equipment. Then further this figure is used in the overall equipment effectiveness formula to measure the effectiveness of the equipment.

2. Performance rate The performance rate can be defined as the ideal or design cycle time to produce the item multiplied by the output of the equipment and then divided by the operating time. This will give the performance rate of the equipment. The formula to calculate the performance rate can be expressed as Performance rate = design cycle time * output * 100 Operating time

16

Page 22: Investigation of the ways to improve the performance …205382/FULLTEXT01.pdfSchool of Technology and Design, TD Investigation of the ways to improve the performance of a plant Undersökning

The design cycle time or the production output will be in the unit of production, like parts per hour and the output will be the total output in the given time period interval. The operating time will be the availability value of the availability formula. The result of this formula will be in the percentage of the performance of the equipment.

3. Quality rate The quality rate can be expressed as the production input into the process or equipment minus the volume or number of quality defects then divided by the production input. The quality rate can be expressed in a formula as Quality rate = production input – quality defects * 100 Production input The production input mean that the unit of product being feed into the production process. The quality defects mean the amount of products which are below the quality standards i.e. the rejected items after the production process. This formula is very helpful to calculate the quality problems in the production process. (Mobley R.K., 2002)

17

Page 23: Investigation of the ways to improve the performance …205382/FULLTEXT01.pdfSchool of Technology and Design, TD Investigation of the ways to improve the performance of a plant Undersökning

4. Empirical findings This chapter is on the empirical findings of the case company situated in Ljungby. Lars Kinnby is the chief of production and we got the all data and information about the company through him. We also collected some information during our visit to the production lines of the company. All calculations of this project are based on one year data of 2006. 4.1 Henjo Plåtteknik AB Ljungby Henjo Plåtteknik AB is the name of the case company. 4.2 Introduction Henjo Plåtteknik AB was established in 1945 in ljungby. The founder of this company was Henry Johansson. The Company is not a large one, has only one unite which is in Ljungby with 8000m2 areas. The company has only 74 employees with 13 officers. This company is ISO 9001 and ISO 14001 certified. It is fabricating company which is producing different sheet metal products according to the orders of its customers. It is working as subcontractor because it has no its own product. It is producing different parts as the requirement of its customers. The company has 150 customers and 10 of them are the main customers of the company which give 80% of the total business of the company. The turn over of the company is increasing almost every year, this shows that the business of the company is increasing continuously. The turn over of the company is 92 Swedish MKr in 2006 (Figure 4.1). The most important customers of the company are Kalmar industries, Electrolux, Wascator, Burtech, Dynapac, Svetruck, Ljungby Maskin, SMV Konecranes, and Rapid Granulator. The order average per month of the company in 2006 is 1510. The company on time delivery average percentage is 82 and 25 percent of this 82 percent on time deliver of the orders is for those orders which are delivered on the same day (see Appendix#1).

company turnover per year

0

20

40

60

80

100

No. of years

MK

r

MKr 31 33 44 48 42 50 55 59 61 74 84 921995 1996 1997 1998 1999 2000 2001 2002 2003 2004 2005 2006

Figure 4.1 Turnover of the company from 1995 to 2006

18

Page 24: Investigation of the ways to improve the performance …205382/FULLTEXT01.pdfSchool of Technology and Design, TD Investigation of the ways to improve the performance of a plant Undersökning

4.3Organizational plan of the company The organizational plane is showing that all the working areas are working directly under the C.E.O. (Figure 4.2). All working areas are responsible of their works according to their duties and are answerable to the C.E.O. of the company.

C.E.O Sven Bodevind Hans Bodevind

I.T. Hans Bodevind Magnus Enfors

Personnel Mia Asplund

Quality & Environment

Berit Johansson Ma

Administration Lena Johansson

gnus Berg

Production Lars Kinnby

Purchase Johan Hovelius

Sale Hans Andersson

Maintenance Magnus Enfors

Production support

Assembly & Delivery

Bending Welding Painting Punching Rolling

Figure 4.2 Organizational plan of the company 4.4 Company working style and different processes The following layout is showing the company’s working style (Figure 4.3). When company receive an order from the customer, it first comes in the production planning section. This section makes the plane for the order i.e. when and how much to produce these products according to the customer requirement and according to the resources. The next section is of construction. This section makes the plane about the production method should be used in the manufacturing of the required items. It selects the line and the production machines for the particular items. The purchase section is the responsible to purchase the required items for the production and to provide on time to the production section. The production section is the responsible to produce the products according the planes and specifications receives from the planning section and construction section. These are the four main working processes which are directly involved in the production of the required items. At the end, products are delivered to the customers. There are two supporting processes that are IT and maintenance. These two processes help to make the smooth production. There is another process which makes the measurements and analysis after getting feed back from different sections and from the

19

Page 25: Investigation of the ways to improve the performance …205382/FULLTEXT01.pdfSchool of Technology and Design, TD Investigation of the ways to improve the performance of a plant Undersökning

customers. It is the management process. The management is the responsible to provide the sources for the production.

Management process Measurement & analysis

Resources

Production planning

Construction Purchase Production

Figure 4.5 Figure 4.6

Figure 4.7

4.5 Products of Henjo Plåtteknik AB Henjo Plåtteknik AB is producing 5000 different types of products. But these entire products are fabricating from the sheet metals of different sizes as per specifications of the customers. There are some pictures of the products to understand the company’s business (Figures 4.4, 4.5, 4.6, 4.7, 4.8).

Supporting processes The need of

customer Maintenance

Customers

IT

Figure 4.3 Different processes of the company

Figure 4.4

Figure 4.8

20

Page 26: Investigation of the ways to improve the performance …205382/FULLTEXT01.pdfSchool of Technology and Design, TD Investigation of the ways to improve the performance of a plant Undersökning

4.6 Description of the production section activities The company is working to produce different kinds of products as the demand of its customers. This demand varies a lot .That is the main reason that company has a flexible production system. The different activities of the production section have the capacity to work with the different requirements. The most important activities are laser cutting, bending, welding, punching, rolling, painting and assembling. There are many machines are involve in these activities. Laser cutting Three machines are involved in this activity. These machines are computerized and working according to the cutting programme. Different cutting programmes can be feed in these machines as the requirement of the products. These machines can cut the metal sheets up to 20 mm thickness. The average set up time of each machine per day is 8.57 min. and the number of failures per month of each machine are two. The time to restart the machine is 34 (10hr fault fixing + 24hr technician arriving time) hours after each failure of these machines. The short stoppages of the each Figure4.9 leaser cutting machine

machine are 975 per year. Each short stoppage takes 20 min. Eight employees are working in this activity. This working station works 24 hours a day and 7 days a week. It means this is much busy. There are total three working shifts in a day. One shift is consisting of eight hours. Forty minute break is there in each working shift. Two workers are working in each shift every day. The eight workers are mobilised in each shift of the whole week. In other worlds, two workers are remain on standby and can be used in case of emergency. The out put of this work station is 491 products per week. The machine cuts the 1 metre metal sheet in 2.8 minutes. But the machine is cutting 1 metre of the metal sheet in 3.2 minutes. There is no time wastage between the replacement of the metal sheets for the continue work. The rejected products of this work station were 1334 in year 2006. Bending There are five machines which are involved in this activity. The capacity of these machines is different. They have the capacity from 85 tones to 230 tones. The average set up time of each machine is 25 minutes per day. Each machine stops once a month due to failure. The time to restart the machine is one day and four hours. The short stoppages of each machine per year are twenty. The time for each short stoppage is 20 minutes. Ten employees are working in this work station. These employees work in one working shifts each day. There is a break for coffee of 40 minutes. Only five day per week work is done in this work station. The production capacity of this work station is to produce 266 products per week. The machine ideal cycle time is 6.6 sec (0.11 minutes) i.e. it can make a bend in this time. But the average time between two strokes of the machine is 0.65 minutes. The total 2035 products of this work station were rejected due to the quality problems in year 2006.

Figure4.10 Bending machine

21

Page 27: Investigation of the ways to improve the performance …205382/FULLTEXT01.pdfSchool of Technology and Design, TD Investigation of the ways to improve the performance of a plant Undersökning

Punching For this activity, there is only one machine. This machine is also computerized and working according to the punching programme which is feed to it for the particular job. This machine can hold ten different punching tools at a time and can use them one by one as the requirement of the item. The set up time of this machine is 30 minutes per day. This machine fails three times in a month. The time require to restart the machine is twenty four plus eight hours (i.e. one day production time 8hr + next day 8 hr will be lost ) after each failure. The short stoppages of this machine per year are 90 and each short stoppage consumes 20 minutes. The working specification of the machine is 2000*1000*6 mm. one employee is working and handles the whole work of this work station. The only one working shift is there for this activity per day and it works five days a week. The 40 minutes coffee break is included in the shift time. This work station produces 24 products per week. The machine ideal capacity is to punch a metal sheet of size 600 mm*280mm in 7 minutes. But the average time to punch this size of sheet is taking 12.21 minutes. Only 9 products of this work station were rejected due to the quality problem in whole year. Welding

Figure4.11 welding machine

Robot welding machines are used in this activity. There are two robot welding machines. A welding programme is feed to these machines and then they work as the instructions of the programme. This work station works in one shift per day and 45 minutes coffee break is also included in the working shift time. This work station work five days a week. The set up time for each machine is 30 minutes per day. Once a month each machine fails. Time to recover the fault and restart the machine is twenty four plus two hours (i.e. one day production time 8hr + next day 2 hr will be lost ). The short stoppages of each machine per year are 20 and each short stoppage take 20 minutes. Four employees are involved in this welding work. Fourteen Hands welding employees are also involve in this activity. They make the semi welded object. This work station produces 77 products per week. The robot welding machine can weld a metal product with the ideal speed of 300 mm in 10 sec. but average time which machine is taking to weld 300 mm is 39.68 sec. the rejected products of this work station in whole year were 486 products. Rolling There are two rolling machines to perform the rolling work on the metal sheets. The roll’s length of one of the machines is 1000mm and other machine has the roll length of 2000mm.the speed of these machines is controlled through the control panels of the machines. The set up time of each machine per day is 15 minutes. These machines fail once in two months and this failure takes twenty four plus four hours to restart the machine again. The number of short stoppages of each machine per year is 20 and time which is consumed in each short stoppage is 15 minutes. This data is of these machines of early years when the machines were working with full capacity. Now a day, these machines are working one or two times in a week. There is only one person to handle the entire load of this work station. This work station is available for one shift to work. The break time of this work station is 40 minutes in the working shift. This work station is producing 31 products per week.

22

Page 28: Investigation of the ways to improve the performance …205382/FULLTEXT01.pdfSchool of Technology and Design, TD Investigation of the ways to improve the performance of a plant Undersökning

Painting The company has a system for the paint of its products. For this purpose, the company has a good automatic paint plant. There are many steps are involved in this plant. The set up time of this plant is two hours. The plant fails once a month. The time to finish the problem and to start the plant once again is twenty four plus four hours. The short stoppages of this plant per year are 18 and each stoppage takes the 30 minutes. The six employees are working in paint shop. This work station has only one working shift with 45 minutes coffee break. This working shift also depends on the products available for the paints. The paint shop is painting 128 products per week. In the whole year, 126 products were rejected of this work station. Assembling The last activity of the production process is the assembling of the different parts of the products. The three employees are involved in this activity in one working shift of the production. The employees has 45 minutes coffee break during the working shift. Different tools (hammer, screw drivers e.t.c.) are used to assemble the parts and to give them the final product shape. The assembling area’s employees assemble 24 products per week. But some times, the employees do mistake in assembling the different parts. So due the assembling problem, the 28 products were rejected in the whole year. 4.7 Production process The production process of the company is complicated and consists of different production lines (see Figure 4.12). This is only due to the big variation of the product’s demand of its customers. Production process starts from the main store. The metal sheets are issued for the work as the requirement of the order to the work stations i.e. Laser cutting or punching. These two work station are at the start of all the production lines. When metal sheets reach in the laser cutting work station with job plan and specification then operator takes the metal sheet and put it on the plate form of the mention machine for the laser cutting. After fixing the metal sheet on the plate form of the machine, operator starts the machine and machine starts its work according to the cutting programme which is already feed in its operating device. Before starting, operator sets the laser intensity of the laser beam. When machine starts, the plat form of the machine with metal sheet moves in side of the machine and reaches at a fixed point (zero position). After cutting the whole cut metal sheet comes out from the machine and at the other metal sheet moves inside of the machine for the cutting. There are two plate forms of the machine which work alternatively i.e. one goes inside of the machine and other is ready for the loading of the next metal sheet. Operator takes the cut metal pieces and checks the quality of them and goes to the next work station with these metal pieces to hand over them for the next operation. What will be the next operation it depends on the specification. The next station can be bending, welding, painting or assembling after the laser cutting work station. Let’s consider the next work station is bending. It works according to the instructions as the laser cutting work station works. Operator sets the plate form of the machine according to the specification of the job before starting the machine. After adjustment of the machine, two operators put the metal piece or metal sheet on the plate form of the machine between the edges, which they have fixed on the plate form to get the require result. Then one of the operators starts the machine for the stroke to make a bend.

23

Page 29: Investigation of the ways to improve the performance …205382/FULLTEXT01.pdfSchool of Technology and Design, TD Investigation of the ways to improve the performance of a plant Undersökning

After stroke the machine head goes back and operator pick up the piece with bend. They check the bend according to the requirement if they find some problem in the bend then they put this piece once again in the machine for the same operation or some times they use hammer to get the require results. They make many bends on the piece according to the specifications or drawing. They hand over the bended pieces to the next work station for its operation after bending some pieces. If the metal pieces or metal sheet comes in the welding work station, there are robot welding machines. But before robot welding of the different pieces, the manual welding is done to make a semi welded object. The Operators see the job instructions and put the semi welded metal object on the machine plate form. These welding machines are computerized and works according to the operating programme which is already feed in it. The operator set the plate form of the machine before putting the object on it according to the welding operation programme of the machine. They use the electric hoist to put and to remove the object from the plate form of the machine. The operators have the responsibility to check the quality of the weld. After inspection, they keep the object one side and put another semi welded object on the plate form of the welding machine. They hand over their welded objects to the next work station for its operation after welding some objects. There is a work station which is for paints. When the metal pieces or objects comes in the paint shop for painting, the operator of this paint shop checks the instructions and hang the objects on the moving belt of the plant which is used to carry the objects in and out purpose through the plant. Before the painting process, the operator checks the right quantity of the paint powder and other chemicals which are used in the painting. Operator checks the quality of the paint on the objects after painting and hands over to the next station which is of the assembling of different parts or just for store as the finish product. In the assembling, the employees of this station read the instructions and see the drawing and assemble the different parts to make the final product. If we see the right side of figure 4.12, there is a punching work station. When pieces reach in this work station, the operator sees the instructions and drawing and then fixes the different punching tools in the machine. This machine use the require tool according to the punching programme, which is feed in the machine memory. Operator initializes and fixes the space for metal piece on the plate form of the machine before starting it for the punching operation. After punching, operator checks the quality of the punches and then puts other metal piece on the plate form of the machine for the punching operation. After punching some pieces, he gives them to other work station for the other operation. Other work station is for the rolling purpose. The operator of these machines fellow the instructions and drawing to roll the object. He just takes the object and put it in the rolls of the machine. Before putting the object in the machine, he sets the speed of the rolls and the gap between them. Operator checks the rolling quality as per drawing. He has the responsibility to give the rolling object according to the drawing. He gives the rolled object to the next work station for its operation on the object. All production lines end at the assembly and final product store area. The final products to the customers are delivered from this area.

24

Page 30: Investigation of the ways to improve the performance …205382/FULLTEXT01.pdfSchool of Technology and Design, TD Investigation of the ways to improve the performance of a plant Undersökning

Production process flow diagram

Main Store

Laser cutting work station Punching work station

Bending work station Welding work station

Painting work station

Assembly & Store

Customer

Rolling work station

Figure 4.12 Different production lines of the company

4.8 Quality The company is facing the quality problems. The company paid 818182 SEK due to the quality problems in 2006 (see Appendix#2). This amount is 0.89% of the turnover of the company. The operators has the responsibility of good quality and they are themselves checks the quality of the products. There are no special quality checkers in the production area. The company has a section for checking the quality of the products. But this section just checks the quality of the first piece of the production daily. The other all production quality depends on the operators. 4.9 Maintenance The company has the preventive maintenance strategy for the all machines in the company. They have the contract with the machines manufacturing companies for preventive maintenance. This maintenance plan is different for different machines. One week per year is

25

Page 31: Investigation of the ways to improve the performance …205382/FULLTEXT01.pdfSchool of Technology and Design, TD Investigation of the ways to improve the performance of a plant Undersökning

the plane preventive maintenance for each Laser cutting machine. For the other each machine like punching, a robot welding, bending machine has one day plane preventive maintenance per year. Each Rolling machine has half day and paint plant has two days plane preventive maintenance per year. The operators have the duty to keep their machines clean and lubricate the different parts of the machines when ever they feel the need for lubrication. Company has a computer technician who is also involve in the maintenance process. When ever a failure is occur, he tries to recover the fault. If he could not fix the problem then he asks to the management for calling the machine manufacturing company’s technician. The machine manufacturing company technician arrives after the company management call but he takes twenty four hours. The company does not have any spare part of the machines in its store. The company buys the spare parts from the machine manufacturing companies when ever the need the spare parts. 4.10 Goals of the company The company has set its goals for the year 2007.these goals are as 1. An increase in profit of min. 10% 2. Increase in delivery of orders on time to min. 95% to the customers (average 82% for 2006). 3. Decrease in Cost due to lack of quality to 0.3% of the turnover (0.89% in 2006).

26

Page 32: Investigation of the ways to improve the performance …205382/FULLTEXT01.pdfSchool of Technology and Design, TD Investigation of the ways to improve the performance of a plant Undersökning

5. Analysis In this chapter data and information obtained from the case company are analysed. It will lay the foundation for the recommendations to the case company for improvements. For this purpose, the authors selected two production lines (Figures 5.1A&5.1B). Line 1 Figure 5.1A: the Line 1

Main Store Laser cutting work station Bending work station Welding work station

Store

Line 2

Welding work station Punching work station Assembly & Store Main Store

Figure 5.1B: the Line 2 These production lines are the main production lines of the company’s production because most of the products of the company go through these two lines and the work stations of these two lines participate in whole production of the company alone or with the other work stations. Line 1 consists of laser cutting, bending and welding work stations. The line 2 consists of punching and welding work stations. So the current situation of the production lines will be clear with the individual situation of the work stations. The authors use the overall equipment effectiveness method to see the current situation of the production lines as well as the work stations. For this purpose, the average values of the data are used in the calculation of the O.E.E.

5.1. O.E.E calculation of Laser cutting work station

The Laser cutting machine is working 24 hour a day and 7 days a week. Setup time per day 8.57min Break time per day 120min Preventive maintenance per year 1 week No. of failure per month 2 Time to cover failure (10+24)hours short stoppages per years 975 Time for one short stoppage 20 min Planned down time = Setup time for machine + Break time (coffee) + preventive maintenance = 8.57+120+27.6= 156.17min/day Unplanned down time, due to failures /day= Failures per month

Working days / month = 2*(10+24)*60/30 =136 min/day

27

Page 33: Investigation of the ways to improve the performance …205382/FULLTEXT01.pdfSchool of Technology and Design, TD Investigation of the ways to improve the performance of a plant Undersökning

Unplanned down time, due to short stoppages = 975*20 =53.4min/day 365 Loading time = total time – planned down time = 1440 –156.17= 1283.83 min /day Operation time = loading time – unplanned down time = 1283.83–(136+53.4) = 1094.43min/day Availability Availability = Operation time = 1094.43/1283.83 = 0.8524 = 85.24% Loading time Quality rate No. of products per day=491/7=70.14 Rejection per day of products =3.65 Quality rate = Processed amount – Defective amount Processed amount = 70.14-3.65 = 0.9516 = 95.16% 70.14 Performance efficiency Machine cutting capacity 1 m= 2.8 min Machine actual speed 1 m= 3.2 min Process amount = (1m/3.2min)*1094min = 341.875 m Performance efficiency = Processed amount * Ideal cycle time Operation time = 341.875*2.8 = 0.875 = 87.5% 1094.43 O. E. E = Availability* Quality rate* Performance efficiency O. E. E = 0.8524*0.9516*0.875 = 0.7097= 70.97%

28

Page 34: Investigation of the ways to improve the performance …205382/FULLTEXT01.pdfSchool of Technology and Design, TD Investigation of the ways to improve the performance of a plant Undersökning

5.2. O.E.E. calculation of Bending work station The Bending machines are working 8 hours a day and 5 days in a week. Setup time per day 25 min Break time per day 40min Preventive maintenance per year 1 day No. of failure per month 1 Time to cover failure (4+8)hours short stoppages per years 20 Time for one short stoppage 20 min Let 1 year = 12 months * 4weeks * 5days =240 days Preventive maintenance time per day= (1*8*60)/ (12*4*5) =2min/day Planned down time = Setup time for machine + Break time (coffee) + Preventive maintenance = 25+40+2= 67 min/day Unplanned down time, due to failures /day= Failures per month

Working days / month = 1*(4+8)*60/4*5 =36 min/day

Unplanned down time, due to short stoppages = 20*20 =1.67 min/day 12*4*5 Loading time = total time – planned down time = 480 –67 = 413 min /day Operation time = loading time – unplanned down time =413 – (36+1.67) = 375.33min/day Availability Availability = Operation time = 375.33/413 = 0.9087 = 90.87% Loading time Quality rate No. of products per day= 266/5= 53.2 Rejection per day of product = 2035/240= 8.5 Quality rate = Processed amount – Defective amount Processed amount

29

Page 35: Investigation of the ways to improve the performance …205382/FULLTEXT01.pdfSchool of Technology and Design, TD Investigation of the ways to improve the performance of a plant Undersökning

= 53.2-8.5= 0.8402 = 84.02% 53.2 Performance efficiency Machine cutting capacity Ideal time for one stroke = 6.6 sec=0.11 min Actual time for one cycle stroke = 39ec =0.65 min Process amount = (1stroke/0.65min)*375.33min = 577.43 stroke/day Performance efficiency = Processed amount * Ideal cycle time Operation time = 577.43*0.11 = 0.1692 =16.92% 375.33 O. E. E = Availability* Quality rate* Performance efficiency

O.E.E = 0.9087*0.8402*0.1692 = 12.91% 5.3. O.E.E. calculation of Punching work station The Punching machine is working 8 hours a day and 5 days in a week. Setup time per day 30 min Break time per day(coffee) 40min Preventive maintenance per year 1 day No. of failure per month 3 Time to cover failure (8+8)hours No. of short stoppages per years 90 Time for one short stoppage 20 min Let 1 year = 12 months * 4weeks * 5days =240 days Preventive maintenance time per day= (1*8*60)/ (12*4*5) =2min/day Planned down time = Setup time for machine + Break time (coffee) + preventive maintenance = 30+40+2= 72 min/day Unplanned down time, due to failures /day= Failures per month

Working days / month = 3*(8+8)*60/ (4*5) =144 min/day

Unplanned down time, due to short stoppages = 90*20 =7.5 min/day 240

30

Page 36: Investigation of the ways to improve the performance …205382/FULLTEXT01.pdfSchool of Technology and Design, TD Investigation of the ways to improve the performance of a plant Undersökning

Loading time = total time – planned down time = 480 –72= 408 min /day Operation time = loading time – unplanned down time =408–(144+7.5) = 256.5min/day Availability Availability = Operation time = 256.5/408= 0.6286 = 62.86% Loading time Quality rate No. of products per day= 24/5= 4.8 Rejection per day of product = 9/240=0.0375 Quality rate = Processed amount – Defective amount Processed amount = 4.8-0.0375 = 0.9922 = 99.22% 4.8 Performance efficiency Machine punching capacity Size of the sheet punching time 600 mm*280mm = 7min Machine actual time per sheet = 12.21 min Process amount = (1 sheet/12.21min)* 256.5min = 21 sheets Performance efficiency = Processed amount * Ideal cycle time Operation time = 21*7 = 0.5731 =57.30% 256.5 O. E. E = Availability* Quality rate* Performance efficiency O. E. E = 0.6286*0.9922*0.5730 = 0.3574= 35.74%

31

Page 37: Investigation of the ways to improve the performance …205382/FULLTEXT01.pdfSchool of Technology and Design, TD Investigation of the ways to improve the performance of a plant Undersökning

5.4. O.E.E. calculation of Robot Welding work station The Robot welding machines are working 8 hours a day and 5 days in a week. Setup time per day 30 min Break time per day 45min Preventive maintenance per year 1 day No. of failure per month 1 Time to cover failure (2+8)hours No. of short stoppages per years 20 Time for one short stoppage 20 min Let 1 year = 12 months * 4weeks * 5days =240 days Preventive maintenance time per day= (1*8*60)/ (12*4*5) =2min/day Planned down time = Setup time for machine + Break time (coffee) + preventive maintenance = 30+45+2= 77 min/day Unplanned down time, due to failures /day= Failures per month

Working days / month = 1*(2+8)*60/ (4*5) =30 min/day

Unplanned down time, due to short stoppages = 20*20 =1.67 min/day 240 Loading time = total time – planned down time = 480 –77= 403 min /day Operation time = loading time – unplanned down time =403–(30+1.67) = 371.33min/day Availability Availability = Operation time = 371.33/403= 0.9214 = 92.14% Loading time Quality rate No. of products per day= 77/5= 15.4 Rejection per day of product = 486/240= 2 Quality rate = Processed amount – Defective amount Processed amount = 15.4-2 = 0.8701 = 87.01% 15.4

32

Page 38: Investigation of the ways to improve the performance …205382/FULLTEXT01.pdfSchool of Technology and Design, TD Investigation of the ways to improve the performance of a plant Undersökning

Performance efficiency Machine welding capacity 10 sec = 0.1667min = 300 mm 1 m = 0.556min Machine actual time for 300 mm = 39.68sec = 0.661 min Process amount = (300mm/0.661min)*371.33min =168531mm/day = 168.53 m/day Performance efficiency = Processed amount * Ideal cycle time Operation time = 168.53*0.556 = 0.2523 =25.23% 371.33 O. E. E = Availability* Quality rate* Performance efficiency O. E. E = 0.9214*0.8701*0.2523 = 0.2023= 20.23%

5.5 Production line 1 & 2 The overall equipment effectiveness of the production line 1 and production line 2 are calculated as from the above data. The O.E.E. of the four work stations i.e.laser cutting, bending, punching and robot welding are 70.97%, 12.91%, 35.74%, 20.23% respectively (Figure 5.2A). However, in the absence of data of each production line’s share of using welding work station; it has been assume that this work station is fully used by one production line at a time 5.5.1 O.E.E. calculation of Line 1

O.E.E. OF LINE 1 = O.E.E. of Laser cutting work station*O.E.E. of bending work station*O.E.E. of welding work station O.E.E. OF LINE 1 = 70.97%*12.91%*20.23% = 1.85%

5.5.2 O.E.E. calculation of Line 2

O.E.E. OF LINE 2 =O.E.E. of punching work station*O.E.E. of welding work station

O.E.E. OF LINE 2 = 35.74%* 20.23% = 7.23%

The value of O.E.E. of the production lines 1 and 2 are 1.85%and 7.23% respectively after multiplying the O.E.E. values of work stations of these production lines (Figure 5.2B).

33

Page 39: Investigation of the ways to improve the performance …205382/FULLTEXT01.pdfSchool of Technology and Design, TD Investigation of the ways to improve the performance of a plant Undersökning

Overall effectiveness of equipment L.C.= Laser cutting B=Bending P=Punching R.W.= Robot welding

Figure 5.2A: O.E.E. of work stations Figure 5.2 B: O.E.E. of line 1&line2

Figure 5.3

0102030405060708090

100

L.C. B P R.W.0

102030405060708090

100

Line 1 Line 2

Bending machine The bending work station’s O.E.E. is the lowest as compare to the other work stations (see Figure 5.2A). The bending machine work station is the big work station. There are ten employees are involved in the work with five bending machines. But when we see the availability, quality rate, and performance efficiency of the machines are 90.87%, 84.02% and 16.92% respectively (See Figure5.3). The performance efficiency of the machine is very low which is 16.92%. A= Availability Q.R. = Quality rate P.E. = Performance efficiency

0

20

40

60

80

100

A Q.R. P.E.

This factor has the heavy impact on the overall equipment effectiveness of this work station. In the calculation of this factor the ideal cycle time for one output result is 6.6 sec. this speed is the actual capacity of the machines as mentioned by the manufacturer of these machines. But according to calculations which are made on the machine the average cycle time for one stroke of the machine is 39 sec in the current situation. The calculation of the number of strokes per day from this time of one cycle stroke is become easy. The numbers of stroke per day are obtained by dividing the operation time for one day with the average cycle time for one stroke. This gives us the 577.43 stroke per day for one machine. So the operation time which is available for one machine every day is important to calculate the number of strokes per day and the availability of the machines too. To calculate the operation time the plan down time and unplanned down time are considered first. The plane down time for each machine of this work station is consisting of setup

34

Page 40: Investigation of the ways to improve the performance …205382/FULLTEXT01.pdfSchool of Technology and Design, TD Investigation of the ways to improve the performance of a plant Undersökning

time, coffee break and preventive maintenance time. One year has been considered as it is consist of 12 months and in each month there are 4 weeks. Because this work station works five days in a week, so to convert the one day preventive maintenance per year to the time of the preventive maintenance per day the per week maintenance time is divided with the number 5. So the plane down time of this work station is 67 minutes per day. The unplanned down time for this work station is consisting of the number of failures and the short stoppages of the machines. The failure time of the month is divided with the numbers of the working days per month to calculate the time for failures from per month in terms of per day. The time for the short stoppages of the year is converted into per day by dividing the total days of the year i.e. 12 months, 4 week and 5 days. The total number of short stoppages is multiplied with the time for each short stoppage to calculate the total time for short stoppages per year. So at the end we found unplanned down time for each machine is 37.67 minutes per day. Then the loading time has been calculated. The subtraction of the plan down time from the total time for one day gives the loading time for the machine. The loading time for the bending machine comes out as 413 minutes per day. This loading time is then future used to calculate the operation time for the machine. The subtraction of the unplanned down time from the loading time give the operation time of the machine. The operation time of the bending machine in the bending work station is 375.33 minutes per day. The second important factor in the O.E.E. calculations is the availability of the machine. The availability of the bending machines is 90.87% in the current situation. This is obtained by dividing the operation time of the machine with the loading time of the machine. The quality rate is the third important part of the O.E.E. the total number of products produce in a certain period of time and the number of rejected products in that certain period of time are used to calculate the quality rate of the machine. The rejected products are subtracted from the total produced products then the answer is divided with the produced products and this gives the quality rate of the machine. There were 266 products are produced per day but to get the production of the machines per day then the 266 is divided with the number of days per week. This gives the 53.2 products per day. The rejection of these machines is 2035 products per year but to get the rejection to per day the total amount of the rejected products are divided in to 240 working day of the year. The amount of the rejected products comes out 8.5 products per day. The quality rate of the bending work station is which is appeared at the end is 84.02%. So at the end, the different factors i.e. availability, quality rate and performance efficiency of the machine is multiplied with each other to get the O.E.E. of the machines of the work station and this value become 12.91%. Welding machine The O.E.E. value of welding work station is better than bending work station (see the Figure 5.2A). Welding machine work station is consisting of two robot welding machines. This is also a big work station with eighteen employees. Four of them are working on the robot welding machines. The O.E.E. of this work station is 20.23%. The performance efficiency is also low which is calculated as 25.23%. The figure5.4 shows the availability, quality rate, and performance efficiency of the welding machines.

35

Page 41: Investigation of the ways to improve the performance …205382/FULLTEXT01.pdfSchool of Technology and Design, TD Investigation of the ways to improve the performance of a plant Undersökning

Figure 5.4

0102030405060708090

100

A Q.R. P.E.

This machine can weld a metal of 300mm in 10 sec. This is the ideal capacity of the machine as given by the manufacturer of this machine. So in other words, this machine takes 0.556 minutes to weld a 1 meter metal. The actual output of the machine is 39.68 sec to weld a 300mm metal. i.e. 0.661 minutes are used to weld the metal of 300 mm length in the current situation. From this time calculation the output of the machine in the operating time is calculate by multiplying the 300mm with the operating time in minutes and then dividing with the 0.661 minutes and which is 168.53 meter/day. But for the operating time is calculate by considering the plan down time and unplanned down time. The plane down time is 77 minutes per day which is consisting of the coffee break time, setup time and the preventive maintenance time. The preventive maintenance is calculated with the same procedure as calculate for the bending machine preventive maintenance. Then the unplanned down time is 31.67 minutes per day for each welding machine. This is calculated by adding the failures per day and the short stoppages per day. To calculate the failure time per day, first the total time of the failure in a month is converted into the minutes by multiplying with the 60. Then this time is divided with the number of days per month. This unplanned down time is 30 minutes per day of each machine. The unplanned down time due to short stoppages of the one machine per year is calculated by multiplying the total short stoppages with the time of the each stop and then dividing with the working day of the year are 240. The unplanned down time due to short stoppages is 1.67 minutes per day comes out after calculations. The loading time for each machine is calculated by subtracting the plane down time from the total time for one day production. The loading time from this calculation becomes 403 minutes per day. Now the operating time is calculated by subtracting the unplanned down time from the loading time. So the operating time for one welding machine is 371.33 per day. The availability of the welding machines is 92.14% which is the second factor in the calculation of the O.E.E. This is calculated by dividing the operation time with the loading time. The month of calculation of these two times has been described in above paragraph. The third important part of the O.E.E. is the quality rate. The quality rate of the welding machines is 87.01%. The total products of the week are divided with the number of the working days of the week to get the per day production. The per day production after is calculation is 15.4 products of the welding work station. The rejection of this work station is 486 products per year. But to calculate this rejection per day is divided with the total working days of the year of 240. This calculation gives the rejection of the welding work station which is 2 products. The same is used, which is described in

36

Page 42: Investigation of the ways to improve the performance …205382/FULLTEXT01.pdfSchool of Technology and Design, TD Investigation of the ways to improve the performance of a plant Undersökning

the calculation of the quality rate of the bending machine, to find out the quality rate of the welding work station. Punching machine In the case of the punching work station, there is only one machine with one employee. The O.E.E. value of this work station is higher then robot welding work station’s value of O.E.E. (see Figure 5.2A). The O.E.E. of this work station is 35.74%. The O.E.E. consists of availability, performance efficency and the quality rate of the machine. The figure5.5 shows the availability, quality rate, and performance efficiency of the punching machine.

0102030405060708090

100110

A Q.R. P.E.

Figure 5.5 The performance efficiency is calculated with the help of the ideal time to punch a metal sheet and the actual time which is being used to punch the same the size of the metal sheet. The ideal time to punch a metal sheet of 600mm * 280mm is 7 minutes which is mentioned by the manufacturer of the machine. But it is taking 12.21 minutes to punch the same size of the metal sheet. This time helps to calculate the total number of the sheets which are punched in one day by dividing the operating time with the time spend on one sheet to punch. This calculation shows that this machine is punching 21 sheets a day. Now these 21 sheets are multiplied with the ideal cycle time to punch the one sheet which is 7 and then is divided with the operation time of the machine in one day to calculate the performance efficiency of the machine. The performance efficiency of the punching mach is equal to 57.30%. The operation time of this machine is also consisting of coffee break time, set time and preventive maintenance. The method to calculate is the same as described above in the case of bending machine. The operation time for the punching machine is calculated as 256.5 minutes per day. The availability of the machine is 62.86% which is getting by dividing the operation time with the loading time i.e. 408 minutes per day of the machine. The quality rate of the punching machine is obtained by the same formula which is used in the calculation of the quality rate of the bending machines as well as the welding machines. The total products of the week are divided by the number of the working days to get the products per day which are 4.8. The rejection products of this work station per day are calculated by dividing the total rejected products in the year with the working days of the year which is 0.0375. By applying the formula as described above, the quality rate of the punching machine is 99.22%.

37

Page 43: Investigation of the ways to improve the performance …205382/FULLTEXT01.pdfSchool of Technology and Design, TD Investigation of the ways to improve the performance of a plant Undersökning

Laser cutting machine The O.E.E. value of this work station is the highest as compare to the others (see Figure 5.2A). The laser cutting work station’s O.E.E. is also calculated with the same procedure as above. The difference between this work station and the other work stations is that it is working 24 hours in a day. So the working days of this work station are 365 instead of 240. The figure5.6 shows the availability, quality rate, and performance efficiency of the laser cutting machines.

0102030405060708090

100

A Q.R. P.E.

Figure 5.6 The performance efficiency of the laser cutting machines is calculated with the same procedure as described above. The machine can cut 1 meter metal sheet in 2.8 minutes and this is ideal speed of the machine to cut the metal sheet as given by the supplier of the machine. The average time which the machine is used to cut the 1 meter metal sheet is 3.2 minutes. Then the out put of the machine in one day is calculated by dividing the operation time with the 3.2 minutes of the time of one meter cutting. This out put is 341.875 meter per day i.e. the machine is cutting 341.875 meters of the metal sheet in one day. To get the performance efficiency, 342.875 meter is multiplied with the ideal cutting time of one meter which is 2.8 minutes and then divided with the operation time 1094.43minutes. The performance efficiency of the laser cutting work station is get 87.5%. The operation time is consisting of the same factors as the other machines. But there are three working shifts in this station. So the total time is consisting of 24 hours i.e. 1440 minutes per day. The loading time is found to be 1283.83 minutes per day and the operation time is found to be 1094.43 minutes per day for each machine by applying the same formula as mentioned above. The availability of the laser machines is calculated by dividing the operation time of the machine with the loading time of the machine and this is found to be 85.24%. The total products per day of the laser cutting are obtained by dividing the one week production which is 491products with the number of working days which are 7. The one day production of the laser cutting machine is become 70.14 products after calculations. The total rejection of the whole one year is 1334 of one machine is divided with the number of the working days 365 to get the rejection of the day. This becomes 3.65 products per day. So after applying the formula as described above, the quality rate of the laser cutting machines is 95.16%. the O.E.E. of the laser cutting work station is get after multiplying the availability, quality rate and the performance efficiency of the machines and is become 70.97% of the laser cutting machines.

38

Page 44: Investigation of the ways to improve the performance …205382/FULLTEXT01.pdfSchool of Technology and Design, TD Investigation of the ways to improve the performance of a plant Undersökning

6 Results and discussion We can see from the analysis the overall equipment effectiveness of the production line 1 is 1.85% and is smaller than the O.E.E. 7.23 % of the production line 2. The basic reason of this difference is due to the bending work station’s O.E.E. which is 12.91%. Then the welding work station comes with 20.23% O.E.E. But the bending work station is the main reason of the lower O.E.E. of the production line 1. This work station is needed to be focused on the first priority to increase the overall equipment effectiveness of the production line 1. When the overall equipment effectiveness of this work station becomes equal to the overall equipment effectiveness of the welding work station, then the second priority will start and that will be the welding work station along with the bending work station. The welding work station is the common work station of the selected production lines 1 and 2. It means that it has the impact on both the selected production lines. Then third and final priority will be considered. The bending work station has low O.E.E. mainly due to the low performance efficiency of the machine which is 16.92%. The reason of this low performance efficiency is the huge difference in the ideal cycle time and the actual cycle time of one stroke of the machine. The 6.6 sec ideal cycle time for one stroke is working as 39 sec in the actual working conditions. This difference in the stroke’s time is due to the losses in the working speed of the machine and the loading and unloading of the object on the plate form of the machine. The material handing also is the part of this low efficiency because the operator has the responsibility to handed over the finished work piece to the next work station. He also has the responsibility to check the quality of each piece and to make each piece according to the requirement of the job. Lot of time is wasted in theses activities. This time wastage of the operator appears in the form of low performance efficiency of the machine as during this time machine is waiting for the new work. So this area is needed to be the main focus to improve the O.E.E. of the bending machines. The performance efficiency of other work station’s machines like robot welding, punching and laser cutting are 25.23%, 57.30% and 87.5% respectively with the same problems as for the bending machine work station to achieve the high performance efficiency i.e. the difference between the ideal cycle time and the actual cycle time and more than one responsibilities of the operator are the same problems of all work stations. The other factor in the O.E.E. calculations is the quality rate which is 84.02% i.e. there are 15.98% products that are rejected due to quality problems from this work station. This problem is due to the operator and the condition of the machine. The operator makes the adjustments in the machine to get the products according to the specifications and with good quality. Because the operator is the responsible for the quality and he checks the quality of the products himself, so the skill of the operator is most important. There is no department of maintenance for checking the conditions of the machines. So this responsibility is also on the shoulders of the operators. This is the second important factor which requires attention to increase the O.E.E. of the bending machines. The robot welding, punching and laser cutting work stations are also facing the quality problems. The 12.99% of the products of the robot welding work station are rejected in the last year 2006 due to the quality problems. As the punching and laser cutting work stations rejection of products are 0.78% and 4.84% respectively in the previous year. The reasons of the quality problem are the same of the bending work station i.e.the whole responsibility of the quality depends on the skill of operator to adjust the machine and to check the quality of the products as well as the machine’s condition plays an important role. The third important factor of O.E.E. calculations is the availability of the machine for production. The availability of the bending machines is 90.87% and the availability for production of the robot welding, punching and

39

Page 45: Investigation of the ways to improve the performance …205382/FULLTEXT01.pdfSchool of Technology and Design, TD Investigation of the ways to improve the performance of a plant Undersökning

laser cutting work stations are 92.14%, 62.86% and 85.24% respectively. But there are still chances to improve the availability of the machines by minimizing the unplanned down time of the machines. This is possible with a good maintenance policy for the machine’s maintenance. Once a machine fails, lot of time is consumed to restart it because of the maintenance system of the company. First the operator himself checks and then calls the computer technician who is participating in the maintenance work. Then he decides to fix the problem by himself or call the machine’s manufacturer technician for the maintenance of the machine. Manufacturer technician takes at least one day to come in the company to fix the problem. During this time machine is not available for the production and is only waiting for maintenance. Next day he fixes the problem of the machine or waits for the spare parts if the company does not have the required spare parts it also takes time. In case of bending machine the twelve hours of the working time per month are wasted due to this maintenance procedure. In other words the company is not able to produce its products on this machine during this time which is the loss of the company. Ten working hours are wasted due to the maintenance procedure in the case of robot welding when the machine stops due to problem. For the sixteen working hours the punching machine is not able to produce the products in the case of a failure. The laser cutting machine is not available for production for thirty four working hours when it stops due to the problem. These machines are much busy machines. This can be seen that these machines are working twenty four hours a day through out the year. All these time losses can be improve with the good maintenance system. There are different views to see the satisfactory level of the O.E.E. but the target of the best satisfactory level of the value of O.E.E. is 85% with the availability more than 90%, performance efficiency more than 95% and quality rate more than 99% (Nakajima S., 1988). In the case company the O.E.E. of bending, robot welding, punching and laser cutting work stations are 12.91%, 20.23%, 35.74% and 70.97% respectively and are not at the satisfactory level. It means lot of work is required to achieve the satisfactory level of the O.E.E. The individual conditions of the factors of O.E.E. are like as the quality rate of the punching is at the satisfactory level which is 99.22%. But the other work stations are not at the satisfactory level according to the current situation of the production work stations. The performance efficiency of all the work stations is under the satisfactory level. The availability of the bending and robot welding work stations are on the satisfactory level but the laser cutting and punching work station’s machines availability is under the satisfactory level. So a priority to focus on a particular work station can be set on the basis of the lower O.E.E. and ways for the improvement can be considered and implemented. The company was not able to deliver some of its orders on the delivery dates in the last year 2006. Eighteen percent of the orders were late due to the current situation. This low value of O.E.E. makes the picture clear. It shows the problem and gives the direction to work to solve it. The good maintenance system has the ability to improve the O.E.E. of the machines to the certain level. This year in 2007, the company wants to increase the delivery to 95%. This is the reason that the company wants to take some steps to reach this goal. The O.E.E. value and the availability of the machines and quality rate of the work stations show that the current maintenance is not enough for the machines for achieving the goals of the company. The company has the preventive maintenance plan for the all machines. Each machine is shut down every year for the preventive maintenance. The number of failures and short stoppages make it clear that the preventive maintenance plan needs some improvements to make the machines on the optimal conditions. In the case of break down, the maintenance task is time taking and lengthy. Much is consumed in to clear the problem and to

40

Page 46: Investigation of the ways to improve the performance …205382/FULLTEXT01.pdfSchool of Technology and Design, TD Investigation of the ways to improve the performance of a plant Undersökning

make a decision to call the technician from the machine supplier. Because the company do not have any spare parts in its store, some times the spare parts become the problem and much time is wasted to buy and receiving them. The machine operators check and clean their machines daily before they start work. But they do not have any plan to lubricate the different parts of the machines. They do this job when ever they feel to lubricate the parts. So in general, an updated maintenance plan is the need of the system which can help to increase the overall equipment effectiveness of the equipments. The quality system of the company is also not working in an effective way. This is clear from costumer’s complaints and the transportation cost which the company bears (see appendix#2). The company bears the product’s cost as well as the transportation cost of the products due to the quality problems. The total quality problem cost is 818182 SEK in last year. This cost is the 0.89% of the total cost. The company has the goal to reduce this cost to 0.3% this year. The company third goal is to increase the profit to 10% from the previous year. This goal can be achieved by increasing the productivity of the product or by increasing the sales of its products and by minimizing the cost. The value of O.E.E. of the current situation gives the clear map to the management to take steps to improve the current situation and to achieve the goals of the company.

41

Page 47: Investigation of the ways to improve the performance …205382/FULLTEXT01.pdfSchool of Technology and Design, TD Investigation of the ways to improve the performance of a plant Undersökning

7 Conclusions The value of O.E.E. shows that the company has the production system to produce the products in more quantity in the same production time by improving the current situation i.e by improving the availability, quality rate and performance efficiency. These three factors indicate all flaws in the production system. The O.E.E. of the bending work station is the lowest as compared to the others. So to increase the production, the O.E.E. values of all work stations indicate the bending work station is the key point to start the improvements. Future, the performance efficiency value of this work station is the lowest as compare to the other factors i.e. availability and quality rate. This indicates the exact point to start the improvements in the current production system of the company. The improvement of the performance efficiency of the bending machine will increase the value of the O.E.E. of the bending work station. This increase of the value of the O.E.E. of the bending work station will increase the O.E.E. value of the production line 1. Then the robot welding work station’s value of O.E.E. will become important for the both selected production lines. This way of improvements in the current system will lead the company’s production system towards the satisfactory level slowly and slowly and to develop a good production systems. The role of the maintenance to develop a good production system and to improve the O.E.E. value of the production machines can not be ignored but it is not the main problem of the case company. The lower performance efficiency of the work stations shows that there is a problem of the man power management. The machines are waiting for the work in the production time. This is because of the more than one responsibility of the operators. Most of their time is wasted in quality checking and material handling. During this time machines are available for the production but remain idle as the operator is busy doing something else. The maintenance is the parts of the production system. Every system needs maintenance for attaining its best position for the production otherwise the problems of quality, short stops and failures become more and more which lead the company towards the losses. The maintenance has the direct contact with the production system to keep the production machines as much as possible to the best conditions to minimize the disturbance in the production and as a result the production will be more with high quality. The other advantage of the maintenance will be appearing in the form to establish a more reliable and stable production system. Then the production of the orders and delivery to customers will be on time which will increase the satisfaction level of the customer. This more production and the satisfaction of the customers are the benefits for the company to increase the sales of the products and to make the more profits for the company. Thus the O.E.E. is the tool for the company to asses the current situation and to start to make the improvements from particular point. The maintenance is the sporting activity which helps to make the improvements in the current condition and to improve the value of O.E.E. The start of the improvement in the value of O.E.E. and the development of the preventive maintenance plan for the machines will be the first step for the company towards the implementation of the TPM. Because these factors are the main objectives of the TPM.

42

Page 48: Investigation of the ways to improve the performance …205382/FULLTEXT01.pdfSchool of Technology and Design, TD Investigation of the ways to improve the performance of a plant Undersökning

8 Recommendations We would like to give the some recommendations to our case company which will be helpful for the company to develop a good and reliable production system for to get the competitive advantages. Our recommendations for the case company as fellow

• The company should use the O.E.E. as the tool to asses the current situation and to find out the starting point for the improvement process.

• The company should have to modify the current preventive maintenance plane for

the all machines which will be able to decrease the failures and short stoppages and keeping the machines in the best conditions for production.

• Some times, the time is wasted due to the spare parts .i.e. the time is consumed in

the waiting of the spare parts. So the company should keep the frequently problem creative parts in the store so that they can be used in the case of need.

• The company has the quality problems in the last year and much of money wasted

due to the quality problems. So the company should activate its quality system to reduce these problems i.e. only operator is checking the quality of the products and wasted the time which gives its impact in form of lower performance efficiency. The company has the quality system and the department for to insure the quality. The need is to make it active and make a plane for that system.

• The operators are the key persons in the production system. So to get the

maximum out put with high quality products, it is necessary that they have the good skills as according to their job. So our suggestion is that the company should arrange some training for them time to time to keep them updated and motivated.

43

Page 49: Investigation of the ways to improve the performance …205382/FULLTEXT01.pdfSchool of Technology and Design, TD Investigation of the ways to improve the performance of a plant Undersökning

References Alsyouf I. (2004), cost effective maintenance for competitive advantages, Växjö University, Sweden. Alsyouf I. (2001), the role of maintenance in company’s competitiveness and profitability improvements, Växjö University, Sweden. Andersson D. Hagser M. Alsyouf I. (2005), A model to assess and improve the cost effectiveness of inventory management decisions: A case study, International Conference on Operations and Supply Chain Management, Bali Bean R., Radford R. (2000), Powerful products. Amacom, New York. Bloch Heinz P., Geitner fred K. (1999), Machinery failure analysis and troubleshooting.2nd vol., 3rd ed.,Texas. Dyer C. (1995), Beginning research in psychology, Blackwell Gliner, Jeffrey A., Morgan, George A. (2000), Research Methods in applied setting,London. Graziano A. and Raulin M.(2000), Research Methods a process of inquiry, fourth edition,Allyn and Bacon,USA. Gummeson E. (1988), Qualitative methods in management research, student literature, Lund. Ingwald A. (2004), On the impact of using relevant information and information systems in maintenance on company profitability, Växjö University, Sweden. Jonsson P. (1999), The impact of maintenance on the production process – achieving high performance, Lund, Sweden Järvinen.P. (2001), On Research Methods, Finland. Kelly A. (1984), Maintenance planning and control, UK Kumar R. ( 2005), Research Methodology.2nd ed, London. Mobley R. K. (2002), An introduction to maintenance,2nd ed,USA. Nakajima S. (1988), Introduction to TPM, productivity press, Portland Sekaran U. (2000), Research methods in business.3rd ed,USA. Suzuki T. (1992), New direction for TPM, Massachusetts Tajiri M., Gotoh F. (1992), TPM Implementation, McGraw-hill, inc, USA.

44

Page 50: Investigation of the ways to improve the performance …205382/FULLTEXT01.pdfSchool of Technology and Design, TD Investigation of the ways to improve the performance of a plant Undersökning

Wireman T. (1994), computerized maintenance management systems,2nd ed, New York,USA. Wireman T. (1998), Developing performance indicators for managing maintenance,1st ed, new york, NY

45

Page 51: Investigation of the ways to improve the performance …205382/FULLTEXT01.pdfSchool of Technology and Design, TD Investigation of the ways to improve the performance of a plant Undersökning

APPENDIX #1 STATUS OF ORDERS IN YEAR 2006

MONTH NO.OF ORDERS

ON TIME DELIVERY

NO. OFORDER DELAY

SAME DAY DELIVERY

JAN 1563 75% 25% 31% FEB 1797 71% 29% 25% MAR 1848 80% 20% 28% APL 1627 77% 23% 27% MAY 1710 77% 23% 27% JUNE 1504 84% 16% 25% JULY 335 92% 8% 24% AUG 1251 76% 24% 19% SEPT 1789 72% 28% 19% OCT 1863 90% 10% 20% NOV 1784 96% 4% 27% DEC 1054 98% 2% 29%

AVG./MONTH 1510 82% 18% 25%

APPENDIX #2 COST DUE TO QUALITY IN YEAR 2006

MONTH INTERNAL DETECTION

EXTERNAL DETECTION TRANSPORTATION TOTAL TURNOVER

PERCENTAGE OF TURENOVER

JAN 26679 49523 4740 80942 7881264 1.03 FEB 36792 9590 2777 49159 8803801 0.56 MAR 30581 20026 5146 55753 9386031 0.59 APL 44393 38675 238 83306 7997832 1.04 MAY 62088 28244 1398 91730 8009134 1.15 JUNE 46434 29262 4122 79818 7593337 1.05 JULY 5473 3555 873 9901 1515544 0.65 AUG 22191 10505 1793 34489 6563060 0.53 SEPT 22263 9333 1707 33303 9686153 0.34 OCT 48515 25976 5083 79574 9474716 0.84 NOV 75217 81832 1750 158799 9366727 1.70 DEC 22213 35486 3709 61408 5817729 1.05

SUM 442839 342007 33336 818182 92095328 0.89

46

Page 52: Investigation of the ways to improve the performance …205382/FULLTEXT01.pdfSchool of Technology and Design, TD Investigation of the ways to improve the performance of a plant Undersökning

Institutionen för teknik och design

351 95 Växjö tel 0470-70 80 00, fax 0470-76 85 40

www.vxu.se/td

47