item 7 - greased anchor wires
TRANSCRIPT
-
8/13/2019 Item 7 - Greased Anchor Wires
1/9
-
8/13/2019 Item 7 - Greased Anchor Wires
2/9
-
8/13/2019 Item 7 - Greased Anchor Wires
3/9
-
8/13/2019 Item 7 - Greased Anchor Wires
4/9
-
8/13/2019 Item 7 - Greased Anchor Wires
5/9
-
8/13/2019 Item 7 - Greased Anchor Wires
6/9
Gorgon ProjectBarrow Island LNG Plant
For Contracto r Name Signature Date
Completed by:
Authorised by:
For Company Name Signature Date
Approved by:
Copy to: Contract AdministratorResident Construction Manager
Confidential Property of Chevron Australia Pty Ltd. May be reproduced and used only in accordance with theexpress written permission of Chevron Australia Pty Ltd.
Template # G1-PP-DWN-FRM-KH200029 Rev 4 Page 1 of 4
WORK METHOD STATEMENT HHEESSOOFFFFIICCEEUUSSEE
Contractor Solstad Offshore Asia and Pacific/Norce Offshore/SLCWWMMSSNNOO::
Contract No. IISSSSUUEEDDAATTEE::
Contract TitleRREEVVIISSIIOONNSSTTAATTUUSS::
Document No. Rev 1 Date 18-9-2013DDAATTEE::
Task Greasing of winch wires Bow and SternRRIISSKKAASSSSEESSSSMMEENNTTNNOO::
Location Norce Endeavour Winch RoomsJJHHAANNOO::
1. INTRODUCTION
Norce Endeavour has 8 Winches installed on the vessel which are designed for anchoring of the vessel on anyspecific project. The Norce Endeavour is a non propelled vessel and relies solely on its anchoring system formaintaining position and movement when not the under control of a tug.
The maintenance of the Winches and Wires is critical to the vessels safety and wellbeing. Prior to coming to thisproject the maintenance and periodical inspections have been undertaken in a safe and efficient manner.
This WMS will cover:
1. Training and competency of work team.2. Maintaining Star IPS maintenance requirements3. Safe work practices
4. Correct PPE5. Clear Communication
This WMS will not cover the running and maintenance of Winches in detail, as that is considered covered by themakers instruction manual and the vessels Planned Maintenance System (Star IPS).
-
8/13/2019 Item 7 - Greased Anchor Wires
7/9
-
8/13/2019 Item 7 - Greased Anchor Wires
8/9
Gorgon ProjectBarrow Island LNG Plant
WORK METHOD STATEMENT
Template # G1-PP-DWN-FRM-KH200029 Rev 4 Page 3 of 4
Risk:
Low if manufacturers inspection and service guidelines along with this WMS are followed.
7. EMERGENCY RESPONSE REQUIREMENTS
Radio Contact With Control Tower
8. ENVIRONMENTAL MANAGEMENT REQUIREMENTS.
IMO rules and guidelines applicable for Norce Endeavour.
9. APPLICABLE HESQ DOCUMENTS AND PLAN
JHA, WMS
10. HAZARDOUS MATERIALS INVENTORY INVOLVED IN WORK ACTIVITY
Fluid Wire Rope Grease RD205 Chemwatch25770 version no: 3 Rocol
11. PERSONAL PROTECTIVE EQUIPMENT
1. Arrangement in conjunction with general PPE as required by SLC/KJV and Solstad for this project.2. Specific Gloves
12. CHANGE MANAGEMENT
None
13. SIMULTANEOUS OPERATION MANAGEMENT AND PLANNING
In contact with Control Tower before start of operation and when operation completed.
14. APPLICABLE REFERENCE DOCUMENTS & DRAWINGS
None.
-
8/13/2019 Item 7 - Greased Anchor Wires
9/9
Gorgon ProjectBarrow Island LNG Plant
WORK METHOD STATEMENT
Template # G1-PP-DWN-FRM-KH200029 Rev 4 Page 4 of 4