iter cryostat main chamber and vacuum vessel pressure
TRANSCRIPT
JAERI-Tech99-026
JP9950289
wm
ITER CRYOSTAT MAIN CHAMBER AND VACUUM VESSELPRESSURE SUPPRESSION SYSTEM DESIGN
March 1999
Akira ITO, Masataka NAKAHIRA,
Hiroyuki TAKAHASHI, Eisuke TADA,
Yoshitane NAKASfflMA* and Osamu UENO*
Japan Atomic Energy Research Institute
°- Mi,
t>-£\$, H ^j&^jw^ffi^ts ^ a w ^ t t s i s (T319-H95 %.hx, fc^LiL<fc*^v\ ft is, ^
9- (T319-H95
This report is issued irregularly.Inquiries about availability of the reports should be addressed to Research
Information Division, Department of Intellectual Resources, Japan Atomic EnergyResearch Institute, Tokai-mura, Naka-gun, Ibaraki-ken 7319-1195, Japan.
©Japan Atomic Energy Research Institute, 1999
SMW-Wn a * IS =? ti fiff % PJT
JAERI-Tech 99-026
ITER Cryostat Main Chamberand Vacuum Vessel Pressure Suppression System Design
Akira ITO, Masataka NAKAHIRA, Hiroyuki TAKAHASHI,Eisuke TADA, Yoshitane NAKASHIMA* and Osamu UENO * *
Department of Fusion Engineering Research(Tokai Site)
Naka Fusion Research EstablishmentJapan Atomic Energy Research Institute
Tokai-mura, Naka-gun, Ibaraki-ken
(Received February 10, 1999)
Design of Cryostat Main Chamber and Vacuum Vessel Pressure SuppressionSystem (WPS) of International Thermonuclear Experimental Reactor (ITER) hasbeen conducted.
The cryostat is a cylindrical vessel that includes in-vessel component such asvacuum vessel, superconducting toroidal coils and poloidal coils. This cryostatprovides the adiabatic vacuum about 10"4 Pa for the superconducting coils operatingat 4 K and forms the second confinement barrier to tritium. The adiabatic vacuumis to reduce thermal loads applied to the superconducting coils and their supports soas to keep their temperature 4 K.
The WPS consists of a suppression tank located under the lower bio-shield and 4relief pipes to connect the vacuum vessel and the suppression tank The WPS is tokeep the maximum pressure rise of the vacuum vessel below the design value of 0.5MPa in case of the in-vessel LOCA (water spillage from in-vessel component). Thespilled water and steam are led to the suppression tank through the relief pipeswhen the internal pressure of vacuum vessel is over 0.2 MPa, and then the internalpressure is kept below 0,5 MPa.
This work is conducted as an ITER design study and this report corresponds to 1996 ITER Design
Task Agreement on Cryostat Main Chamber and W P S Design' (N24TD04FJ (D312)).
* ITER Joint Central Team (JCT) (Naka Site)
* * Ishikawajima Harima Heavy Industries Co.
JAERI-Tech 99-026
This report summarizes the structural design of the cryostat main chamber and
pressure suppression system, together with their fabrication and installation.
Keywords : ITER, Cryostat, Vacuum Vessel, Super conducting Coil, WPS,
Suppression Tank, Relief Pipe
JAERI-Tech 99-026
10
, 4K
(0.5MPa)
o.2MPa
0.5MPa «
N24TD04FJ(D312)CD TiTER ^ y4 ^^ 9 y
IWW^if (MfflBfe) : T 3 1 9 - 1 1 9 5* ITERJCT* *
1996 ¥ ITER
2 - 4
111
This is a blank page.
JAERI-Tech 99-026
Contents
1. Introduction 1
2. Cryostat Design Description 5
2.1 Introduction 5
2.2 Design Conditions 5
2.3 Cryostat and Penetration Design 9
2.4 Upper/Lower Cover Remote Cutting and Rewelding Equipment 28
2.5 Study of Fabrication/Construction Plan and Schedule 57
2.6 Future Works and R&D Activities 68
3. Suppression Tank Detail Design 69
3.1 Introduction 69
3.2 Design Conditions 69
3.3 Detailed Design of Suppression Tank 70
3.4 Rupture Disk/Bellows Detailed Design 76
3.5 Study of Disassembly and Assembly at Maintenance 79
3.6 Study of Rupture Disk Exchange Plan 93
3.7 Study of Fabrication/Construction Plan and Schedule 103
3.8 Future Works and R&D Activities 109
4. Conclusions- 110
4.1 Cryostat 1 io
4.2 Suppression Tank 110
Acknowledgement 110
Attachment Cryostat and Suppression Tank Drawings 111
JAERI-Tech 99-026
@
VI
JAERI-Tech 99-026
1. Introduction
1.1 Background and Objectives
The purpose of this design study is to perform the design of the following
elements of WBS 2.4 (Cryostat):
2.4.A Cryostat Main Chamber
2.4.B Cryostat Penetrations (those elements which are integral with the cryostat main
chamber).
2.4.E Vacuum Vessel Pressure Suppression System
The current ITER schedule foresees that the items which are the subject of this design
study are on the Critical Construction Path since they either have to be installed early in the
Machine Assembly Schedule, or components which are required on-site at an early stage
for other reasons (for example the cryostat upper, which may be required for use as part of
the coils cold test facility, and which may have to be available on-site ready for the delivery
of the first coils to be tested). Thus for all the items described herein, the design study must
develop the design (and all the associated documents) to the point where a call for tender
can be implemented at the end of EDA. As the overall design of the machine evolves,
crucial space requirements are emerging as. for example, remote handling access and
working envelopes are firmed up. For this reason it must be anticipated that clearances
between components may change in the light of these emerging requirements.
1.2 Technical Objectives
The major purpose of this design study is to develop the design of each
required component of WBS 2.4 to the completeness necessary to ensure adequate time
for an orderly process of call for tender, tender evaluation, contract placement and
procurement in accordance with the ITER schedule. The pressure boundaries of the
cryostat main chamber, penetrations, and vacuum vessel pressure suppression system
constitute radiological second barriers and thus have an important safety role which will
require to be assessed by failure modes and effects analysis. JCT shall be responsible for
performing such analysis.
Designs have to be developed in a way that meets all the requirements of the
GDRD and the DDD. In compliance with Section 3.6 of the GDRD, the Task performer
- 1
JAERI-Tech 99-026
shall institute a quality assurance program that shall ensure that all activities of the design
study are conducted in accordance with the ITER project management plan.
13 Outline of the Design Study
13.1 Cryostat Main Chamber (WBS 2.4.A)
The design study includes the following items :
1) An appraisal of the grade of stainless steel proposed for the cryostat (304L) in view of
the requirement for withstanding contact by low temperature helium under accident
conditions, and a recommendation for material to be used.
2) An initial review of the reference design to confirm strength and buckling stability
margin. This should include the following load case combinations (l)atmospheric
pressure load with internal vacuum (with PF coil quench EM loads superimposed),
(2)design basis accidental internal pressure and thermal traction stresses resulting from
the design basis loss of magnet cooling helium into cryostat vacuum.
3) A design of lower head segmentation compatible with the solution adopted for the
maintenance of the lower PF coils.
4) A design for partitioning the inter wall region of the cryostat cylinder and heads into 10
volumes each (30 volumes in total) to assist in leak location.
5) A fabrication method study to confirm the cost-effectiveness of the reference design.
This should aim to maximize the amount of prefabrication and vacuum leak testing
performed at the vendor's shop, within the constraints of transportation and receipt at
the ITER site (as defined in the GDRD document reference S 10 GDRD 2 95-02-10
F1.0). Additionally the facilities required for the final on-site prefabrication and
vacuum leak testing of the cryostat upper and lower heads and cylinder (before
installation in the pit, for the lower head or use as part of the coils cold tests facility for
the upper head) should be defined, including the size of building and crane capacity,
and transportation means from the facility to within the reach zone of the Tokamak hall
crane.
6) Industrial cost estimates shall be obtained for inclusion in both the detailed design
report (December 1996) and the Final ITER Design Report (January 1998). An
outline fabrication procedure is to be complied for use in the Detailed Design Report,
including all sketches necessary to illustrate the methods involved, for both shop and
- 2 -
JAERI-Tech 99-026
on-site fabrication, together with an associated time plan which will be used to ensure
that adequate lead times are allowed in the ITER overall planning schedule. The
fabrication procedure will also be used in the final ITER design report, updated to
reflect any evolution from the detailed design report.
7) Design of any reinforcement needed to the Cryostat walls to allow the attachment of
Tokamak lateral supports if it is decided that is to be a requirement.
8) Design of the upper head with the necessary degree of segmentation and to
accommodate the cryocondensation pump used to establish ultra high vacuum
conditions in the cryostat before coils cool-down.
9) A stress analysis of the Cryostat main chamber in its final configuration, including
buckling stability, as comprehensive as required by the adopted Design Code.
10) An adequate set of drawings and all associated documentation to enable a timely
implementation of a call for tender exercise at the end of EDA (the major elements of
this system have to be installed in the Pit at an early phase of the Tokamak installation).
13.2 Cryostat Penetration (WBS 2.4.B)
The cryostat penetrations comprise all apertures in the cylinder and the upper and
lower heads. The design study for penetrations includes the following items:
1) Design of reinforcements required for strengthening all apertures.
2) Design of all bolted and welded connections for penetrations.
3) An adequate set of drawings and all associated documentation to enable a timely
implementation of a call for tender exercise at the end of EDA (the major elements of
this system have to be installed in the Pit at an early phase of the Tokamak
installation).
1 3 3 Vacuum vessel Pressure Suppression System (WBS 2.4.E)
Together with associated thermo-hydraulic analysis, the conceptual design of the
Vacuum Vessel Pressure Suppression System is being performed under Task Number N 24
TD 03 95-05-02 FJ. When this conceptual design is delivered, the following activities will
be performed in the task according to the technical specification provided by the JCT
1) Detail design of the complete system including: Suppression Tank and internalpiping
and flow distribution system; associated vacuum roughing system and connection to
- 3 -
JAERI-Tech 99-026
the Tritium Plant; relief pipes connecting the Suppression Tank to the Vacuum
Vessel, including all expansion bellows necessary; rupture discs and I&C as identified
during the Conceptual Design Task N 24 TD 03 95-05-02 FJ.
2) Stress analysis of the Pressure Suppression System in its final configuration
including the worst scenario load case combinations of pressure and fluid inertia
loading that will be specified during Conceptual Design Task N 24 TD 03 95-05-02
FJ.
3) An adequate set of drawings and all associated documentation to enable a timely
implementation of a Call for Tender exercise at the end of EDA (the major elements
of this system have to be installed in the Pit at an early phase of the Tokamak
installation).
However, in 1997, the basic design concept of cryostat main chamber and
cryostat penetration was changed from double-wall configuration to the single wall
type. For this reason, the activities on cryostat main chamber and cryostat
penetration were focused on the structural assessment from a viewpoint of fabrication
and assembly according to the agreement with the JCT.
- 4 -
JAERI-Tech 99-026
2. Cryostat Design Description
2.1 Introduction
The cryostat is a cylindrical vessel that includes in-vessel components such as
vacuum vessel, toroidal and poroidal coil, divertor and blanket. And it provides
adiabatic vacuum for the superconducting coil, and forms parts of second
confinement barrier for tritium containment. The pressure inside the cryostat is
kept below 10 Pa with respect to adiabatic vacuum for the superconducting coil,
and the cryostat prevents thermal invasion applied to the superconducting coil and
their support structures that operated at cryogenic temperature, 4 K.
This report describes the major results obtained by the study on the following
design items. Since the basic structure of the cryostat has been changed by the
JCT from double-walled structure to a single-wall type in 1997, the design
activities were focused on the study of single-walled cylinder vessel
-Cryostat detail design
-Fabrication and construction plan
-Remote cutting and rewelding plan
-Vacuum pumping plan
2.2 Design Conditions
According to following conditions, we performed the detail design, the
investigation of fabrication/ construction plan and remote cutting/rewelding
plan of the cryostat.
2.2.1 Design Pressure and Design Temperature
Operating conditions concerned with the cryostat among several ITER
operating conditions are shown in Table 2.2-1. In the cryostat design,
following two condition are selected as significant operating conditions:
Operating Condition Case 3: Normal Condition/Operation
Operating Condition Case 6: LOCA/LHe Leakage
Since the electromagnetic load that is applied to the cryostat during PF coil
quench and plasma disruption is much smaller than external pressure,
electromagnetic load was neglected.
- 5 -
Table 2.2-1 Design Pressure and Design Temperature
I
I
Operating Conditions
Normal
Condition
s
LOCA
Start
Shutdown
Operation
Operation
(PF coil quench)
Operation
(Disruption)
LHe Leakage
Water Leakage
Case
No.
1
2
3
4
5
6
7
Pressure
Inside Cryostat
From 1 atm to
vacuum
From vacuum to
1 atm
1 atm
1 atm
1 atm
0.2 MPa
0.2 MPa
Outside Cryostat
1 atm
1 atm
1 atm
1 atm
1 atm
1 atm
1 atm
Temperature
300 K
300 K
300 K
300 K
300 K
(125 K)
(340 K)
Remarks
73
o3"toI
o
note : ( ) is temporary value
JAERI-Tech 99-026
2.2.2 Seismic Load
For the normal operation, we considered the following design seismic
intensity.
Horizontal Direction : 2.828 x 0.2G
Vertical Direction : 2.2 x 0.2G
(Peaking Factor x SL-2)
The combination of the seismic load and load applied during LOCA or PF
coil quench is not considered in the study because of its low probability.
2.2.3 Material and Allowable Stress
(1) Material: SUS304L
(2) Allowable Stress
The allowable stress based on the ASME BOILER AND PRESSURE
VESSEL CODE Section VIII is shown in Table 2.2-2.
Table 2.2-2 Allowable Stress
Unit (MPa)
Material
SUS304L
Operating
Condition
Normal
Operation
LOCA*1
Allowable Stress Intensity
Primary Stress
Pm
115
138
PL + Pb
172
207
Primary + Secondary
Stress
PL + Pb +Q
345
345
Remarks
including at
Earthquake
Note : Considering Stress Intensity Premium Factor (k=l .2)
Explanation of Symbols:
P m ; General Primary Membrane Stress
PL ; Local Primary Membrane Stress
Pb; Primary Bending Stress
Q; Secondary Stress
- 7 -
JAERI-Tech 99-026
2.2.4 Other Design Requirements
(l)During exchanging in-vessel equipment, the structure of upper and lower
cover shall be able to be cut and rewelded remotely.
(2)Gas pressure in the cryostat shall be less than 10 Pa.
(3)Cryopump shall be installed outside of the cryostat.
(4)Site conditions
Construction conditions are listed below:.
-Capacity of Tokamak building crane shall be 750 ton x 2.
-Distance between the cryostat and the bioshield shall be 500 mm.
-After construction, the structure shall be subjected to a pressure and
leakage testing.
(5)Considering the site conditions, dimensions of shop blocks of the cryostat
shall be the following dimensions.
-Width less than 14m
-Height less than 6m
-Length less than 19m
-Weight less than 11.77 MN( 1200 ton)/l component
Q
JAERI-Tech 99-026
2.3 Cryostat and Penetration Design
2.3.1 Structure and Dimensions of Cryostat and Penetrations
a. Cryostat
Basic structure of the cryostat and other components, and their dimensions
are shown in ATTACH. 1-1
The detail structure and dimensions of the cryostat are shown in the figures
listed below:
-Cylinder ATTACH. 1-4
-Lower Cover ATTACH. 1-5,1-6
-Upper Cover ATTACH. 1-7
b. Penetrations
The specifications of each penetrations and ports are summarized in
ATTACH. 1-2.
The arrangement of penetrations and ports is shown in ATTACH. 1-3,
General development drawing.
The detail structure and dimensions of penetrations are shown in the
attachments listed below:
-Equatorial Port Detail ATTACH. 1-17
-Divertor Port Detail ATTACH. 1-18
-Upper Port Detail ATTACH. 1-19
-Feedthrough for Coil Detail ATTACH. 1 -20
-Others ATTACH. 1-21 ~ 1-23
- 9 -
JAERI-Tech 99-026
c. Openings
In the cryostat, their openings are arranged for inspection and
maintenance of the equipment installed in the cryostat. Opening/closing
shall be connected with flanges. The airtightness shall be ensured with seal
welding (lip seal).
The arrangement of the openings is shown in above table of penetrations
and ports, and general development drawing.
The detail structure and dimensions of the openings are shown in the
attachments listed below:
-Upper Cover Central Port Detail ATTACH. 1-14
-Upper Cover RH Port Detail ATTACH. 1-15
-Lower Cylinder RH Port Detail ATTACH. 1-13
-Lower Cover RH Port Detail ATTACH. 1-12
d. Ring Pedestal and CS Support
The major function of the ring support is to support the gravity load of
the vacuum vessel and the lower cover.
The CS support is used for the assembly of the central solenoid coil.
The detail structure and dimensions of the ring pedestal and the CS support
are shown in ATTACH. 1-24.
- 10 -
JAERI-Tech 99-026
2.3.2 Mechanical Study of Cryostat and Penetrations
We confirmed the analytical results described in the JCT analysis report of
mechanical reliability of cryostat and port penetrations based on the ASME
Code Sec.VIII (Div. 2, Appendix 4), which is called " design by analysis".
In this code, the evaluation of compression stress has limitation and strength
against outernal pressure is requested to be evaluated by rule.
2.3.2.1 Summary of FE analysis results
Followings are the summary of FE analysis of cryostat described in the report
"DDD 2.4 Appendix G Cryostat atructural analysis".
(1) Design Code and targets of the analysis
a. Design Code
• ASME Sec. VIII Div. 2
b. Targets of the analysis
• Cylindrical section
• Inner section of the lower lid
• Outer section of the lower lid and main skirt
• Main section of the top lid
• Inner top small lid
• Main port expansion joint (bellows)
(2) Conditions of the analysis
a. Analysis code
• ANSYS Version 5.3
b. Analysis model
3D FE model (Fig. 2.3-1 ~ 2.3-6)
c. Loading conditions
• Dead weight
• Test pressure (internal pressure)
• External pressure
• Seismic load
The combinations of the loading conditions are shown in Table 2.3-1
d. Allowable stress
ASME Sec. VIII Div. 2 is referred
For the loading condition of category IV which is shown in the Table
- 11 -
JAERI-Tech 99-026
2.3-1, ASME Sec. Ill Subsection NE (Class MC components) is referredbecause of no description in the ASME Sec. VIII Div.2.Table 2.3-2 summarizes allowable stress for each loading condition.Table 2.3-3 shows allowable stress for each material,
e. Analysis cases
• Static stress analysis
• Buckling analysis (linear, non-linear)
• Seismic analysis
(3) ResultsThe results are summarized in Table 2.3-4. It is concluded that stressesincluding buckling are below the allowance.
(4) Comments to the FE analysis resultsa. It is necessary to evaluate the effect of initial error of assembly in detail
as a further discussion.
b. We would propose that the buckling should be evaluated with ASMECODE CASE (N-284) "Metal containment shell buckling designmethods, Class MC, Section III, Division 1".
c. The ASME CODE CASE has limitations to apply, as follows.•Di /R i<0 .1• Openings are fully reinforced according to code rules•R i / t<1000Where,Di: inner diameter of opening
Ri: diameter of main vessel
t : thickness of the vessel shell
In the case of the cryostat,
Di / Ri = 4202 mm / 36480 mm = 0.123 > 0.1 NGAr = 9.0 x 104 mm2 < A= 7.1 x 104 mm2 NGRi/1 = 36480 mm/50 mm = 730 < 1000 OK
Where,Ar : Reinforcement area required for opening
A : Area available for reinforcement
The present design does not satisfy all limitation to apply the CODE
- 12 -
JAERI-Tech 99-026
CASE.
d. It is designed to use expensive low carbon steel for frame structure on
the top lid. It would be proposed to use general carbon steel.
- 13 -
JAERI-Tech 99-026
Fig. 2.3-1 Finite element model for cylindrical section of cryostat
Fig. 2.3-2 FE model of the inner section of the lower cryostat lid
- 14
JAERI-Tech 99-026
Lra. O.XMP« tan 1 id l o . J a*1
•;1tr'..:-.-4l-Jl-/:-V.-..-:-V-:^^y.-VVv:
• . " • S w i m ' . .•-•••-'".•.•'.•>•••,'^>';;X'
.-•orr**:1.'.
Fig. 2.3-3 FE model of the inner section of the lower cryostat lid and main skirt
Fig. 2.3-4 FE model of the main section of the top lid
- 15 -
JAERI-Tech 99-026
Fig. 2.3-5 Inner top small lid, FE mesh
Fig. 2.3-6 Shell model for divertor port expansion joint
- 16 -
JAERI-Tech 99-026
Table 2.3-1 Load combination
Weight+Test pressureWeight+External pressureWeight+External pressure+Earthquake SL-1Weight+External pressure+Earthquake SL-2Weight+Helium and Water Ingress (internal pressure)
TestIII
IVIV
Table 2.3-2 Allowable stress for each loading condition
.y Category "PmPLPm +PbPL+PbPL+Pb+QPL +Pb +Q +F
0.8 Sy
Note 1
Sm1.5 Sm1.5 Sm1.5 Sm3 Sm
Sa
' :r-U: %1.2 Sm1.8 Sm1.8 Sm1.8 Sm3 S m
Sa
' **1V (Nomyr~$~Sf
1.5 Sf1.5 Sf1.5 Sf
1.5Sy1.5Sy1.5Sy
Note 2Note 2
1. Note 1: not to exceed 1.35Sy when Pm<.67Sy, or, 2.15Sy-1.2Pm when Pm>.67Sy2. Note 2: no evaluation required3. Note 3: Values in the left are for regions which are continuous and integral.
Values on the right for regions which are not continuous and integral.
Where:
Pm is the calculated primary general membrane stress intensityPL is the calculated primary local membrane stress intensityPb is the calculated primary bending component of stress intensityQ is the self-limiting secondary component of stress intensityF is the increment to all types of stress due to a notch concentrationSy is the yield strength tabulated in ASME, section II, part DSm is the design stress intensity value tabulated in ASME, section II, part DSf is defined as 85% of the general primary stress limit defined in Appendix F.
This is defined in F-1331.1 where it amounts to the lesser of 2.4Sm and 0.7Su foraustenitic steel, or 0.7Su for ferritic materials.
Su is the tensile strength tabulated in ASME, section II, part DSa is the allowable alternating stress obtained by the fatigue curves in article 5-100,
Section VIII, division 2.
- 17 -
JAERI-Tech 99-026
Table 2.3-3 Allowable stress for each material
Material S& -&FormNom.CompositionSy[MPa]Su [MPa]Sm [MPa]Sf[MPa]
' Type 304 »'^ *Plate18Cr-8Ni206517137279
Type 3041 - -Plate18Cr-8Ni172482115234
^~SA-533'~ -PlateMn-.5Mo-.25Ni572690229410
- 18 -
ID
I
Table 2.3-4 Summary of Cryostat Structural Analysis(DDD 2.4 APPENDIX G CRYOSTAT STRUCTURAL ANALYSIS )
Evaluation Parta
1. Introduction
2. Analytit of Cryottat2. 1 Loading Conditionl2. 2 Crit«rii2. 3 Matariali and
Allowable Strait L .v . l .2. 4 Static Analytia of
Cylindrical Saction
2. 5 Static analylia ofirmar Bottom Lid
2.4.1.
2.42
O Z L Z
2.4.2.3
1.43
iiSZ.
2.4.4
2.4.4.1
2A*J_
2.4.4.3
2.4.4.4
2.5J.
2.5.3
2.5.4
Analy.la
FE Modal Da»cription
.§5i?.Gll!l.?I.?.f.!yf?._tS.^
,Wil?ail.!n!!l.'.ltS?..Jff ithoutiniii"«l"diformaljontEffacta of initial dittortiona
Looal modal of aguatoritl and divartoportt ragjonTaat Prattura Loading Condition
Local analytic of aqualoriaf andd.ivJ.SK-E?.!t!.KJBS!!Local modal of RH lowar port
Bucklinjr Analyait
Ei^anvalua anal^tia on 2 aaotor mod*
Eifanvalua analyw* on 5 taotor modi
Non linaar alastie larfa daftaotionbucklinj analyaiaNon linoar inalaatio larga daflactionbueklini analysit
FE Modal Daacription
Ejittmil Prauura Load
Taat Prrnwuf Loading Condition
Bucklinj Analytit
Analyals modal
3D 9* modal
30 9 ' modal
3 0 30* mo'dai
3D partial modal
3 0 partial modal
3 0 partial modai
3D 36" modaK2>aotorJ_
30 90" moSjlfSiactorl
3D 36" modaiifitaotor)
3D 9'" modal
3D partial modal
3D partial modal
36TartiaJ m,^
3D partial modal
Analyaia Condition
Boundary Condition.Bottom; raatraint without rotationaround toroidal direction radial direction.
Toj;'r^ai"dTtDl<icamant U •ama'a. flatTd.Vortical bad: 4.ISMN
Extamal praaaura: 0.1 MPaSalfWalght
Iniliafdl«form.tion±l5mm with '72*~Equatorial maridional initial daformation ±2.Smm
faat praaaura tint.mal pra»«ur«) 0.1MP.
nitial daformation± ISmm
Initial daformation± 15mm
Extamal prataure
Intamal praiiura (taat praaaurai
R.«ult.
All strata lavalt ara within ailowabla.
Initial dafotmation doaa not affact on tlrata lavalt.
ATtiir«rra^tlirt"wii5^^^^
All ttratt lavalt ara within allowabla.
P.u.sk!!!?.i..m.*r«i!i.y§
9ucklin| mar^n 7.6
Buoklin| margin 9~8.5
3ucklin| margin 3~3.5
All strati lavalt aro within allowablo.
All ttratt lavtlt ara within allowabla.
3uckling marfin 65
Ramarkt
Mo considcrinc of waldinf d*foarvttJon
>
o
Oto
JAERI-Tech 99-026
VI
13 p
l l
u 5?S Z
c2 fi
- 20 -
Table 2.3-4 Summary of Cryostat Structural Analysis (3/3)(DDD 2.4 APPENDIX G CRYOSTAT STRUCTURAL ANALYSIS)
Evaluation Parta
2. 10 Other Loading Condition
3. Analysis of Main Pert* Bellov
4. Analysis of Vacuum V O I M IPressure Suppression Tank
5. Anajviitof Rn tP.(* . . ta l
2...2.B
2.10.1
s3.13.23.3
343.4.1342 ~3.43
4.14.2
i.3
4.4
5.1 "5.2
5.3
5.4
Analyala
Top lid sholle 5L-I.SI-2
Alternative study : Analysis of oylindswith the addition of toroidal M s
EM Load.
Individual Loadinf ConditionsCombination of LoadsCumulative Fatigue Evaluation
finite Element EvaluationsLJnsar Elaatio AnalysisLinsar Element EvaluationLarge Daflsetion Contaot Analysis
.oadim Conditions and CombinationsSriteria and Stress Allowabla
Static Strass Analysis
Suckling Analysis
.oading Conditiona and CombinationsCriteria and Stress Allowabla
Static Stress Analysis
Buckling Anslysis
Analyala modal
r
1/2modsl
3D modsll 1 full sector)
30 model(1 full saetar)
30 mod.K l/2modal)
3Dmodol(1/2model)
Analysis Condition
S.ifwoiBhtPrassuradntomat, external, hydrostatio)EarthquakeLoo*
Normal operitinj loadEarthqualia
RssuHs
SL-1 peek stress Isvals 20% hlfhsr than normalSL-? peak stress lavals 50% hitler than normalAll etrsu lavals are within allowable from statioanalysis.
Tha peak pressure by EM load is 20 timaa lasa than thanormal axtamal pressure (0.1 MPa). EM loads acting onCryostat can be considered naiHv'bla.
Total u . a » factor is below 1.
Tha divartor j w t axpansiorjolnts has snou rh bucklingm»r«in.
All stress lavals are within allowabla.
Buckling martin (.Of
Tha allowabla stress is axoaadad In tha uppar part oftha ring padastal durina^saismio events.Local reinforcements ia naoetsary.
Bucknnf. margin l9(normal oparatinf)Buoklim mariin 3.85(normai oper.um + SL- I )
Remarks
Tha distribution and direction ofeleotromaanetio loads do not consider.
i—ii
o
O
JAERI-Tech 99-026
2.3.2.2 Evaluation by Formula
The mechanical strength of cryostat for the external and internal pressure are
evaluated according to the ASME Boiler and Pressure Vessel Code Section-VDI
Division-2 Article-D3.
(l)Study of required thickness of cryostat shell
a. Mechanical strength for internal pressure
The minimum required thickness of the cryostat shell is
PRt = S-0.5P
Where,
t; minimum required thickness of the shell
P; internal pressure (considering LOCA) =0.1 MPa
R; inside radius of the shell = 18195mm
S; membrane stress intensity limit = 115MPa (SUS 304L, at room temp.)
So the minimum required thickness is0.1x18195
t = = 15.9mm115-0.5x0.1
This result is thinner than the present shell thickness of 40mm. Therefore, the
mechanical strength of the cylinder for the internal pressure satisfies with the
ASME Section-VHI Division-2.
b. Mechanical strength for external pressure
The maximum allowable external pressure is evaluated as follows.
Case 1: thickness of shell is assumed to be 40mm
L 1500 nnAt= = 0.041
D o 36470
Do _, 36470 _0]2
t 40
Where,
Do; outer diameter of shell = 36470mm
L ; distance between stiffening rings = 1500mm
- 22 -
JAERI-Tech 99-026
According to the FIG. G shown in the Subpart 3, "Charts and Table for
Determining Shell Thickness of Components under External Pressure" of
ASME B&PV Code, Sec. II Part D, the factor "A" is as follows;
A = 0.0013
Then, from the FIG. HA-3, "Chart for the determining shell thickness of
components under external pressure when constructed of austenitic
steel(18Cr-8Ni-0.0035 maximum carbon, type 304L)" of ASME B&PV
Code, Sec. II Part D, the factor "B" is determined.
B = 9200
Therefore, the maximum allowable external pressure Pa is calculated as
follows;
4B 4 x 9200a ~ 3 ( D 0 / t ) ~ 3x912
= 13.45psi= 0.09MPa < O.lMPa
The maximum allowable external pressure, Pa, is smaller than the design
external pressure of O.lMPa.
If the distance of stiffening rings is assumed to be shorter, the maximum
allowable external pressure is same as the above result due to that L/Do is
under 0.05.
Case 2: thickness of shell is assumed to be 50mm
= o.O41D o 36480
t 50
Where,
Do; outer diameter of shell = 36480mm
L ; distance between stiffening rings =1500mm
According to the FIG. G shown in the Subpart 3 of ASME B&PV Code Sec.
II Part D, the factor "A" is estimated as follows;
A = 0.002
From the FIG. HA-3 of ASME B&PV Code Sec. H Part D, the factor "B" is
determined.
B =10000
- 23 -
JAERI-Tech 99-026
Therefore, the maximum allowable external pressure Pa is calculated as
follows;
4B 4x1000Pa = —. r- =
3(D0 /1) 3 x 730
= 1826psi
= 0.125MPa>0.1MPa
The maximum allowable external pressure Pa is larger than the design
external pressure of 0.1 MPa. The moment of inertia of the stiffening ring
will be studied based on the shell thickness of 50mm.
(2)Mechanical strength of the stiffening ring
The moment of inertia of the ring is evaluated under the condition of shell
thickness of 50mm.
Case 1: the size of the stiffening ring is assumed to be T section of
T350»300*60/20.
The required moment of inertia on the combined ring-shell section Is is as follows;
D0*L.(t + A. /L, )A10.9
364802 x 1500 x (50 + 238 x 104 /1500) x 42 x 10""= i ' = 5.07 x 109mm"
10.9
Where,
As; cross-section area of the stiffening ring = 2.38 X 104mm2
Lj; length between stiffening rings = 1500mm
According to the FIG. HA-3 in the Sub chart 3 of the ASME B&PV Code
Section II, the factor "A" is
A = 4.2X10'*
Here, the factor "B" is calculated as follows,
p _ 3 [ P P ° 1 - 3 x f 0-'*36480 I4[_t + A , / L , J 4 [_50 +238xl0 4 /1500J
= 4134MPa = 6025psi
- 24 -
JAERI-Tech 99-026
If the dimensions of the cross section
are shown in the figure on the right,
the available moment of inertia is
calculated as the following procedure.
The effective width of the shell W isW = i.ioJD0T,
= U0V36480 x 50 = 1486mm
Where, Ts is the shell thickness of
50mm in the current design.
Moment of inertia is summarized as follows,
®
total
A(X104mm2)
7.43
2.38
9.81
y(mra)
25
327—
I(X108mm4)
0.1548
1.7985
1.9533
A A ^ X I O 8 ! ™ 4 )
3.9594
12.4810
16.4404
The available moment of inertia is= 1-9533 x 10* + 1 6 4 4 0 4 xy ) 108mm4
Where,
A y; distance between the center of the components
e; the gravity center of shell-ring section7.43xl04x25 + 238xl04x327 „„
e = ; = 98mm9.81x10*
The available moment of inertia I is smaller than the required moment of inertia Is.
Therefore, the distance of stiffening rings are re-arranged and calculated.
Case 2: length between stiffening rings. Ls =1000mm.
(other size of the stiffening ring is same as the case 1)
Is = 3.33xl09mm4
I=1.66Xl0 9 mm 4
The available moment of inertia I is smaller than that of the case 1 due to that the
effective width of the shell is smaller.
Case 3: the shape of the stiffening ring is flat and the distance of stiffening rings L is
1100mm
Is = 3.65X109mm4
- 25 -
JAERI-Tech 99-026
= 3.76X109mm4
The available moment of inertia I is larger than the required moment of inertia Is
These dimensions and the pitch of stiffening ring are summarized as follows,
Dimensions : Flat plate thickness 40mm
width 700mm
Pitch: 1100mm
(FB40*700)
The calculation results are shown in Table 2.3-5.
Table 2.3-5 Summary of Calculation
CaseNo.
1
2
1
4567
g
Thicknessof theshell
5050505060
6070
70
Stiffening ring(mm)
Dimensions
CT350*300CT350*300
FB40*700'FB40*680FB40*700FB40*670
FB40*700
FB40*650
Pitch
15001000
Z HOOP1000120010001250
1000
Moment of inertia(mm4)
Is
5.07 X109
3.33 XI09
3.30 X109
4.03 XI09
3.39 X109
4.24 X109
3.29 X109
I
1.84X109
1.66X109
3.411 XO9
4.08X109
3.491 XO9
4.32X109
3.401 XO9
Evaluation
X
X
Ooooo
CT: Cut Tee
FB: Flat Bar
- 26 -
JAERI-Tech 99-026
Considering the balance between the shell thickness and dimensions of the stiffening
ring, the following dimensions of each part are determined.
• Thickness of the shell : 50mm
• Dimensions of the stiffening ring : Flat plate Thickness 40mm
Width 700mm
• Pitch of the stiffening ring : 1100mm
(3) Conclusions
The cryostat structure is assessed by the formula specified in the ASME B&PV
Code Sec.VDI Div.2. The conclusions are summarized below.
(l)The thickness of the shell requires 50mm as the external pressure vessel.
(2)The increase of the shell thickness does not affect the size-down of the
stiffening ring.
(3)According to the present cryostat design which are proposed by JCT, the
thickness of upper and lower flexible joints are 20 mm. Some parts of upper and
lower flexible joints will require the thickness of over 20mm.
(4)The stiffening ring needs to change the shape from the T section of 350mm to
the flat plate with the width of 700mm. In this case, the interference between the
stiffening ring and some internal components may be a problem.
(5)The number of the stiffening rings should be increased from 13 to 21.
(6)The design code for evaluation for the external pressure utilized in this design
is the code for the general cylindrical shell vessel whose opening is sufficiently
reinforced. Therefore the parts with many openings (near the equatorial and
divertor port) will require detailed stress analysis.
- 27 -
JAERI-Tech 99-026
2.4 Upper/Lower Cover Remote Cutting and Rewelding Equipment
2.4.1 Upper Cover Remote Cutting and Re-welding Equipment
The cutting and re-welding location of the upper cover are considered as
follows:
(1)CS coil opening for CS coil maintenance
(2)Upper openings of cryostat for vacuum vessel and poroidal coil 2, 3 (PF2.
PF3) maintenance
In the case of exchanging the CS and PF coils, the openings are cut at each
flexible joint of the upper cover.
We studied the remote cutting and rewelding procedure considering the
following conditions.
-Bioshield over the upper cover shall be removed
-Upper cover (truss portions) shall be accessible to person.
-Opening guides, supports and guide rails shall be pre-installed
during construction.
-The covers shall be removed by using Tokamak building crane and
special lifting devices and be transferred to appropriate places.
a. Remote Cutting and Re-welding Procedure
The conceptual procedure of the upper cover cutting and re-welding is
summarized below;
Cutting/Removal procedure;
Step 1 : Set the remote handling devices unit
Step 2 : Cut the upper cover and dimension measurement
Step 3 : Remove the upper cover
(Repair of CS coil)
- 28 -
JAERI-Tech 99-026
Repair procedure;
Step 4 : Install the upper cover blocks and set the remote device units
Step 5 : Weld the upper cover blocks, and perform the welding nondestructive
examination
Step 6 : Bolt the test cover and perform the local leakage test.
The maintenance equipment for the upper cover is shown in Table 2.4.1.
The outline of test cover for the local leak test is shown in Figure 2.4.1.
- 29 -
toO
TRUSS TRUSS
f HANDLING LUQ
LOCAL TEST COVER [1 _ | \ / j ~ "
—1INNER COVER 11
CS OPENING <
~1 1 V 11 REMOTE DEVICE
• ROUTE
UNIT
)F UNIT FOR INNER >PEN1NC
i
OUTER COVER
TFOR CENTRAL SOLENOID COIL GUIDE PLATE
FOR CRYOSTA.T CYLINDER SHELL
1 T
IK)OU
UTE OK UNIT l*)U
LOCAL TEST COfl
UVER
REMOTEDEVICE UNIT
X1 ''' T l
GUIDE RAILSUPPORT
BIO-SHIELD
Notes ; Attachments to be welded at construction.• CS OPENING
<D HANDLING LUG© BRAKET OF TRUSS BEAM(3) GUIDE RAIL
• CYLINDER SHELL(D GUIDE RAIL SUPPORT AND RAIL@ GUIDE PLATE(UPPER AND LOWER)
•LOCAL TEST COVER<D O-RING COVER SHEET
NAME OF EQUIPMENT
LOCATION
DESIGN CONDITION
OPERATING CONDITION
TYPE OF EQUIPMENT
MAIN MATERIAL
WEIGHT
ACCESSORY
NOTES
REMOTE HANDLING DEVICE UNIT
CS OPENING AND UPPER COVER
EQUIP. CLASS
TEMPERATURE
TEMPERATURE
-
EQUIP. NO.
QUANTITY
CORROSION
MARGIN
—
-
ROOM TEMPERATURE
ROOM TEMPERATURE
CARBON STEEL
MONITORING
LIGHTING
MEASURING
CLEANING
ITV, CCD camera
1 DRTVTNfi SYSTEM
Driving Gear ; Rack & PinionSpeed ; Max. 1200 m/min.
2. CUTTING DEVICE UNIT
Type ; Laser Cutting
Speed; 10 m/sec.
3. REWELDING DEVICE UNIT
Method : Narrow Gap TIG or Laser Welding
Speed; 20~100 na/min.
4. WELDING NONDESTRUCTIVE EXAMINATION DEVICE UNIT
Method; UT5. BOLTING DEVICE UNIT
Type; Power RenchTorqu; 5O~80 N-m
>
—i
o3-
oto
Table 2.4-1 Maintenance Equipment for Upper Cover
JAERI-Tech 99-026
<Upper Cover Remote Cutting and Rewelding Procedure
and Equipment for Maintenance>
Step 1 : Install the remote handling device units
(l)Transport the remote bolting device units
(2)Lift down the remote bolting device units through the space between the cryostat
and the biological shield
(3)Set the bolting device unit at the guide rail pre-installed on cylinder in order to
loosen the bolts of test cover for leak test
(4)Remove the test cover
(5)Remove the bolting device unit
(6)Set the cutting device unit on guide rail
Step 2 : Cut the upper cover and dimension measurement
(l)Cut the upper cover
(2)Measure dimensions of the cutting edges
Step 3 : Remove the upper cover
(l)Lift up the upper cover with special devices and the Tokamak building crane
(2)Transfer the upper cover to appropriate place.
Step 4 : Upper cover and welding device units installation
(l)Install the upper cover
(2)Set the test cover
(3)Set the welding device unit and examination device unit
2.-25Step 5 : Weld the upper cover and perform welaing nondestructive examination.
(1) Weld the flexible joints
(2)Perform the welding non-destructive examination
(3)Remove the welding and examination device units
Step 6 : Bolt the test cover and perform the local leakage test
(l)Bolt the test cover.
(2)Perform the local leakage test
(3)Remove the bolting device unit
- 31 -
JAERI-Tech 99-026
TIGHTENING BOLT
O RING
O RING
TEST COVER
TIGHTENING BOLT
FLEXIBLE PLATE
> TEST COVER
SLIT GUIDE
A VIEW A
SEAT OF COVER
OUTLINE OF TEST COVER
• BOLTTING AND O RING SEAL TYPE.
• SEATS OF COVER ARE WELDED ON FLEXIBLE PLATE
AND PROVIDED WITH GUIDE FOR REMOTE
HANDLING UNITS.
• TEST COVER IS BELLOW TYPE.
SEQUENCE OF MAINTENANCE
(D SET ON O RING
® UP/DAWN AND POSITIONING OF COVER
(E> TIGHTEN BOLTS
® LEAK TEST
FIG. 2.4-1 TEST COVERFOR LOCAL LEACKAGE TEST
- 32 -
JAERI-Tech 99-026
2.4.2 Design of Lower Cover Remote Cutting and Re-welding Equipment
The cutting and rewelding location of the lower cover are considered as
follows.
(1) Outer opening for PF5,6 maintenance
(2) Inner opening for PF7 maintenance
In the case of the manintenance of these coils, the openings are cut at each
flexible joint of the lower cover.
We studied the remote cutting and rewelding procedure considering the
following conditions.
-Equipment under the lower cover shall be removed.
-Suppression tank shall be removed.
-Shield blocks and the lower covers shall be transferred with a special
lifter.
-Bio-shield shall be removed by being separated to blocks.
-The cover shall be contained in mid basement floor.
-The guide rail shall be pre-installed during initial assembly.
a. Remote Cutting and Rewelding Procedure
The conceptual procedure of cutting and rewelding of the lower cover is
summarized below:
Cutting/Repair Procedure:
Step 1 : Remove the bio-shield.
Step 2 : Set the remote handling device unit.
Step 3 : Cut the lower cover and perform dimension
measurement
Step 4 : Remove the lower cover
(Repair of PF coil)
- 33 -
JAERI-Tech 99-026
Repair Procedure;
Step 5: Install the lower cover and set the remote welding device unit
Step 6 : Weld the lower cover and perform nondestructive examination
Step 7 : Bolt the test cover and perform the local leakage test
Step 9 : Install the bio-shield
The maintenance equipment for the lower cover are shown in Table 2.4-2 and
2.4-3.
- 34 -
LOWER COVER RING PEDESTAL
SHIELD BLOCK
SHIELD BLOCK
GOO 1
MID. BESEMENT FLOOR
RAIL FOR LIFTER
TOROIDAL MOVER
i— LOWER COVER
SHIELD BLOCK
GU1DE(SHIELD) PLATE
REMOVABLSHIELD BLOCK -,
=3SETTINGBRACKETET -J 1
SECTION. A SECTION B
NAME OF EQUIPMENT
LOCATION
DESIGN CONDITION
OPERATING CONDITION
TYPE OF EQUIPMENT
MAIN MATERIAL
WEIGHT
ACCESSORY
NOTES
BIO-SHIELD BLOCK carrier
under the cryostat
EQUIP. CLASS
TEMPERATURE
TEMPERATURE
EQUIP. NO.
QUANTITY
CORROSION
MARGIN
TBD
ROOM TEMPERATURE
ROOM TEMPERATURE
Movable lifter
SUS316L / SS400
20 ton
MONITORING
LIGHTING
RAIL
ITV, CCD Camera
Main function
1.Lifter
(1) Driving system
Maximum Speed
(2) Lifting device
Lifting stroke
2.Troidal mover
(1) Driving system
maximum Speed
(2)BSW holding system
:Rail
:0.5 m / s
:Mechanical Lifter
:Up to 6,000 mm
:Rail*I
:0.2 m / 8
:Docking pin
totooto
M : Rail is ipre-installed during initial assembly
Table 2.4-2 Equipment for Maintenance of Lower Cover Shield Block
LOWER COVER
COVER ADJUSTABLE DEVICE(HORIZONTAL FREE) V
INSTALLED GUIDE RAIL
RING PEDESTAL
I
MID. BESEMENT FLOOR
NAME OF EQUIPMENT
LOCATION
DESIGN CONDITION
OPERATING CONDITION
TYPE OF EQUIPMENT
MAIN MATERIAL
WEIGHT
ACCESSORY
NOTES
LOWER COVER LIFTER
under the cryostat bottom
EQUIP. CLASS
TEMPERATURE
TEMPERATURE
EQUIP. NO.
QUANTITY TBD
CORROSION
MARGIN
ROOM TEMPERATURE
ROOM TEMPERATURE
Mechanical lifter
SUS316L
20 ton
MONITORING
LIGHTING
ITV, CCD Camera
o3-<£><£>
IO
to
Table 2.4-3 Equipment for Maintenance of Lower Cover Shield Block
JAERI-Tech 99-026
<Lower Cover Remote Cutting and Rewelding Procedure
and Equipment for maintenance>
Step 1 :Remove the bio-shield (See Figure 2.4-2(1/10) ~ (5/10))
(1) Preparation
-Install the rail for lower cover lifter
-Set the lower cover lifter beneath the building floor
-Set the remote handling device unit on the lifter
-Remove the rail for lower cover lifter
(2) Install the rail for bio-shield lifter
(3) Set the bio-shield lifter
(4) Fix the bio-shield with the bio-shield lifter
(5) Lift down the bio-shield block
(6) Transfer the bio-shield block to the outside of tokamak pit
(7) Drive the lifter with the toroidal mover of bio-shield blocks
(8) Remove the bio-shield blocks toroidally
(9) Remove the bio-shield lifter and the rail
Step 2 : Install the remote handling device units (Figure 2.4-2(6,7/10))
(1) Lift up the lower cover lifter with the bolting and cutting device units
(2) Position the lifter using guide pins pre-installed on the lower cover
(3) Set the bolting device unit at the guide rail on the lower cover
(4) Lift down the lifter for the prevention of interfere with the cutting device unit
(5) Loosen the bolts of the test cover for local leak test
(6) Lift up the lifter and remove the test cover
(7) Install the cutting device unit on the guide rail
Step 3 : Cut the lower cover and dimension measurement (Figure 2.4-2(8/10))
(1) Cut the lower cover
(2) Measure the dimensions of cutting edges
(3) Remove the cutting device unit
- 37 -
JAERI-Tech 99-026
Step 4 : Remove the lower cover (Figure 2.4-2(9/10))
(1) Lift down the lifter
(2) Remove the lower cover in building floor
Step 5 : Install the bio-shield (Figure 2.4-2(10/10))
(1) Install the rail for bio-shield lifter
(2) Install the lifter with the bio-shield block
(3) Install the shield blocks by using toroidal mover of the bio-shield blocks
(4) Tighten the bolts of the shield blocks
(5) Remove the lifter and rail
Step 6 : Install the lower cover blocks and the welding device unit.
(1) Machining of the lower cover
(2) Attach the test cover to the lower cover
(3) Set the welding device unit on the lifter
(4)Lift up the lifter
(5)Positioning of the lifter with guide pins.
(6)Install the welding device unit on the guide rail.
Step 7 : Weld the lower cover blocks and perform welding nondestructive examination
(1) Weld flexible joints
(2) Install the welding nondestructive examination device unit on the guide rail
and perform the welding nondestructive examination.
(3) Remove the welding and welding nondestructive examination device units
(4) Lift down the lifter
Step 8 : Tighten the bolts of the test cover and perform the local leakage test
(1) Tighten the bolts of the test cover
(2) Perform the local leakage test
(3) Remove the bolting device unit
Step 9 : Install the bioshield
- 38 -
t o
RING PEDESTAL
BIO-SHIELD BLOCK
i • , ! • r I i !
•.!::!• : i ; : ' : " - : -.• i , ! • s • : I • " : = ""• , ; ' i ;i • ! : ' : : • ! • : ' . . • ' ! . '
LOWER COVER LIFTER
o
O(S3
Fig. 2.4-2(1/10) Maintenance Procedure of Lower Cover
o
I
STEP1
SHIELD BLOCK LIFTER
MI" 1
. • : ' , • I . I
• ! n ]'•'•• :; , • • J | l l | i i •• • i .
•'•••••'•• " " : • " i : ; ' : ! !
LOWER COVER LIFTER ty j• IL|.^ - I i i - i . t . • r n* I • i .1 ! Ui. H. I !• - WM ' J <ijij !• I L ' . 1 . ! ' I
LI ' , :
! ' : • • I ; , , , ! ! * - ! , [ , ' i ' i ^ ' . f 1 ' ':,;'•'-'
i;U
. is." ' - • l \ . ••1 i . ••y-.\::\-. \ - ~ ^ , . . • • . •
I-HI
O
CO
oto
Fig. 2.4-2(2/10) Maintenance Procedure of Lower Cover
SHIELD BLOCK LIFTER
;- i l l 1 - . : ! i , ! : ; ! ^ : • i ; ' 1 ' 1 ^ • • • i ; 1 >• i• • ' . . . i , ' i J J • ! ' ! • : -• • ' . ' h i ' , M . i i ,
! •'! ''!• i 1 ' ' ' ' ' ' • l l 1 1
'{!kK:]jj|< LOWER COVER LIF FER : : HJr .:!-;•• : « ?
• • j ' i i . ' , : ' V : , : i ,. ' . i J • • • • " . i - ! i . I r
soi—i
i—3O
oto
oto
Fig. 2.4-2(3/10) Maintenance Procedure of Lower Cover
STEP 1
t o
SHIELD BLOCK LIFTER
. • L I . ' ! 1
- , , ! • • ;
i l l . • ' : ! * : : •1. : '1 : •
" • ' . . • . • • • • . - l
- . 'I',, i ' \ , ; - ' - I - 1 1 ! ! ' •::•
>
m
I
CDO
toIDI
OtoO5
• . i . h . > • • • • • • V ! ' : • : ! i ! ' , , , ; • ! ! ! ' • : - '
Fig. 2.4-2(4/10) Maintenance Procedure of Lower Cover
T0P0IDALMOVER
SHIELD BLOCK LIFTER
i i j l i : !LOWER COVER LIFTER
paI
o
o
Fig. 2.4-2(5/10) Maintenance Procedure of Lower Cover
STEP 1 (9) &STEP 2
rt SHIELD BLOCK LIFTER
: ii1 l ; ! i LOWER COVER LIFTER
I
o3 -
<£)t£)I
oto01
Fig. 2.4-2(6/10) Maintenance Procedure of Lower Cover
4
SHIELD BLOCK LIFTER
?|&
LOWER COVER LIFTER
33
o
totoIo
to
Fig. 2.4-2(7/10) Maintenance Procedure of Lower Cover
O5
I SHIELD BLOCK LIFTER
LOWER COVER LIFTER
1 • M • | ! i ! , | T V i - f ! I '"'I i • 1, •" F 7 r rpp j1] f'| a B | 1 |y w i
i-rtriMHil - H1T+BilJl:T(;il'1Ul^:H:Mi+l^|lt • r -sr^r-HfiEEiJ
33
i
o
tooto
Fig. 2.4-2(8/10) Maintenance Procedure of Lower Cover
STEP 3 (D,STEP 4 (D &(
SHIELD BLOCK LIFTER
, ' I " ' !• 'f !'IT p 1 ""TVPPfnnnj?« r r T ' >L r; i * •. • , ' j , i " I •' I ' r M I f » r ' • '
! I V ' : : : ^ ^ M i l l , Wa!P4ii1*iiteilfi--ri
LOWER COVER LIFTER
. • r , i i | n - i ni|,i1;H11P d i-VH 1.1'MTH |;
33I—I
Itoo
O
r r • a I
Fig. 2.4-2(9/10) Maintenance Procedure of Lower Cover
STEP 5
00
I SHIELD BLOCK LIFTER
LOWER COVER LIFTER
fn
I—3(I)o
otoI
oto
Fig. 2.4-2(10/10) Maintenance Procedure of Lower Cover
JAERI-Tech 99-026
2.4.3 Design of Equipment for Remote Cutting and Re-welding of RH Port
The following RH ports are considered to be cut and welded.
(1) Upper Cover CS Opening for cryostat vacuum pump maintenance
(2) Upper Cover RH Port for in-vessel component maintenance
(3) Lower Cylinder RH Port for in-vessel component maintenance
(4) Lower Cover RH Port for in-vessel component maintenance
We studied the remote handling procedure considering the following conditions.
-The RH port cover shall be fixed by bolts.
-Air tightness shall be kept with lip seal welding.
-The RH port cover shall be handled with Tokamak building crane and
lifting devices
a. Remote Handling Procedure
The conceptual procedure of removal/attachment of the RH ports is
summarized below.
Removal Procedure:
Step 1 : Remove the flange bolts
Step 2 : Remove the spacers
Step 3 : Cut the lip seal
Step 4 : Remove the port covers
Repair Procedure:
Step 5 : Install the port covers
Step 6 : Weld the lip seal and perform liquid penetrant
examination(PT)
Step 7 : Insert the spacers
Step 8 : Tighten the flange bolts
Step 9 : Perform the local leakage test
The maintenance equipment for RH port are shown in Table 2.4-4(1,2/2).
- 49 -
G U I D E HAIL
REMOTE CONTROL U N I T
HANDLING JIG
FLANGE BOLT
SPACES
(FOR CYLINDER & LOWER COVER)G U I D E PLATE
OUTLINE OF GUIDE PIN
C71O
S U P P O R T FOR H A N D U N G JIG
FLANGE
DRIVING GEAR(RACK)
OUTLINE OF GUIDE PLATE
NAME OF EQUIPMENT
LOCATION
DESIGN CONDITION
OPERATING CONDITION
TYPE OF EQUIPMENT
MAIN MATERIAL
WEIGHT
ACCESSORY
NOTESDRIVING QEAR(PINION)
REMOTE DEVICE UNIT
REMOTE HANDUNG DEVICE UNIT
RH PORT OF UPPER COVER
EQUIP. CLASS
TEMPERATURE
TEMPERATURE
EQUIP. NO.
QUANTITY
CORROSION
MARGIN
ROOM TEMPERATURE
ROOM TEMPERATURE
CARBON STEEL
MONITORING
LIGHTING
CLEANING
CCD Camera
1. DRIVING SYSTEM
Driving Gear; Rack & Pinion
Speed ; Max. 1200 n/min.
2. BOLTING DEVICE UNIT
Type; Power Rench
Torqu; 350~400 N-m
3. CUTTING DEVICE UNIT
Type ; Grinding
4. REWELDING DEVICE UNIT
Method : TIG Welding or YAG Laser Welding
Speed; 20—100 n/min.
5. NONDESTRUCTIVE EXAMINATION DEVICE UNIT
Method ; PT
tXJ
*-}CDO
srtoto
oto
Table 2.4-4(1/2) Equipment for Maintenance of RH Port
REMOTE DEVICE UNIT
RH PORT OF LOWER CYLINDER
GUIDE PLATE
POSITIONER
TURN AFTER FIT FLANGE
GUIDE PLATEOUTLINE OF HI TIDE PLATE
SHIELD BLOCK
TURN TABLEfTURN AFTER FIT FLANGE)
REMOTE CONTROL UNIT
OPENING FOR MAINTENANCE
LIFTER FOR RH PORT OF LOWER COVER
RH PORT OF LOWER COVER
NAME OF EQUIPMENT
LOCATION
DESIGN CONDITION
OPERATING CONDITION
TYPE OF EQUIPMENT
MAIN MATERIAL
WEIGHT
ACCESSORY
NOTES
REMOTE HANDLING DEVICE UNIT
RH PORT OF CYLINDER&LOW COVER
EQUIP. CLASS
TEMPERATURE
TEMPERATURE
EQUIP. NO.
QUANTITY
CORROSION
MARGIN
ROOM TEMPERATURE
ROOM TEMPERATURE
CARBON STEEL
MONITORING
LIGHTING
CLEANING
CCD Camera
1. DRIVING SYSTEM
Driving Gear : Rack & PinionSpeed ; Max. 1200 iWmin.
2. BOLTING DEVICE UNIT
Type ; Power Rench
Torqu; 350~400 N-m
3. CUTTING DEVICE UNIT
Type; Grinding
4. REWELDING DEVICE UNIT
Method: TIG Welding or YAG Laser Welding
Speed; 2 0 ~ 100 m/min.
5. WELDING NONDESTRUCTIVE EXAMINATION DEVICE UNIT
Method; PT
i—i
}
O
OtoO5
Table 2.4-4(2/2) Equipment for Maintenance of RH Port
JAERI-Tech 99-026
<RH Port Remote Handling Procedure
and Equipment for Maintenance>
Figure 2.4-3 shows the RH port handling procedures.
Step 1 : Loosen the flange bolts
(l)Install the bolting device unit on the guide rail
(2)Loosen the flange bolt
(3)Drive the bolting device unit around the flange
(4)Loosen the all flange bolts
Step 2 :Remove the spacers
(l)Remove the spacers by the bolting device unit
(2)Remove the bolting device unit
Step 3 : Cut the lip seal
(l)Set the welding device unit
(2)Cut the lip seal
(3)Remove the welding device unit
Step 4 : Remove the port covers
(l)Turo the lifting device in order to release the mechanical locking by guide plate
(2)Lift up the port cover
(3)Remove the port cover
(4)Inspection the surface of lip seal
Step 5 : Install the port covers on the flange
(l)Lift down the port cover
(2)Install the port cover along the guide plate
(3)Turn the lifting device for the mechanical locking by guide plate
- 52 -
JAERI-Tech 99-026
Step 6 : Weld the lip seal and perform the liquid penetrant examination (PT).
(1 )Set the welding and examination device units
(2)Weld the lip seal
(3)Perform the liquid penetrant examination (PT)
(4)Remove the welding and examination device units
Step 7 : Insert the spacers
(l)Set the bolting device unit
(2)Insert the spacers
Step 8 : Tighten the flange bolts
(l)Tighten the flange bolts
(2)Remove the bolting device unit
Step 9 : Perform the local leakage test
(l)Set the local leakage test device unit
(2)Connect the compressing piping to the joint
(3)Pressurize the lip seal part
(4)Perform the local leakage test
(5)Remove the local leakage test device unit
- 53 -
JAERI-Tech 99-026
STEP1; LOOSEN THE FLANGE BOLTS
STEP2 ; REMOVE THE SPACERS
STEP3 ; CUT THE LIP SEAL
FIG.2.4-3 MAINTENANCE PROCEDURE OF RH PORT (1/3)
54 -
JAERI-Tech 99-026
STEP4 ; REMOVE THE PORT COVERS
STEP5 ; INSTALL THE PORT COVERS ON THE FLANGE
STEP6 ; WELD THE LIP SEAL AND PERFORM THE PT
FIG.2.4-3 MAINTENANCE PROCEDURE OF RH PORT (2/3)
55 -
JAERI-Tech 99-026
STEP7 ; INSERT THE SPACERS
STEP8 ; TIGHTEN THE FLANGE BOLTS
STEP9 ; PERFORM THE LOCAL LEAKAGE TEST
FIG.2.4-3 MAINTENANCE PROCEDURE OF RH PORT (3/3)
- 56
JAERI-Tech 99-026
2.5 Study of Fabrication/Construction Plan and Schedule
Regarding with the shop fabrication, transportation and field construction plan /
schedule for the cryostat, the following items were investigated.
(l)Block Subdivision
(2)Shop Fabrication Sequence
(3)Nondestructive Examination
(4)Transportation and Field Installation Sequence
(5)Pressure Proof Test Method
(6)Field Installation Schedule
2.5.1 Block Separation
For the block separation, the following issues were considered.
(l)Arrangement of Welding Line
(2)Arrangement of Ports
(3)Maintenance after Operation
(4)Fabrication Ability of Mill Maker
(5)Fabrication Ability of Shop
(6)Transportation Limitation (Size Limitation)
(7)Ability of Crane for Field Carrying
(8)Installation Procedure
The block separation are shown in ATTACH.1-8 ~ ATTACHl-11.
2.5.2 Shop Fabrication Procedure
The fabrication procedure is studied, considering following design issues.
(l)Assembling Work (Fitting and Welding)
(2)Machine Processing
(3)Minimizing work for Turning and Transfer
(4)Minimizing Welding Distortion
(5)Unitizing
The shop fabrication procedure is shown in ATTACH. 1-37 ~ ATTACH1-40.
- 57 -
JAERI-Tech 99-026
2.5.3 Nondestructive Test
The nondestructive Test required for each welding line are studied based on the
ASME Section VIII (Div. 2).
Each weld joint located in the pressure boundary is classified into the following
categories:
Category A : Longitudinal Welding Joints within the Cylindrical Shell
and Welding Joints within the Flat Plate
Category B : Circumferential Welding Joints within the Cylindrical Shell
Category C : Welding Joints between the Flat Plate and the Cylindrical Shell
Category D : Welding Joints between the Sleeve(Port) and the Cylindrical
Shell or the Flat Plate
The welding joints between the shell/flat plate and stiffeners or ribs are
classified into "others".
The tests required to each welding category are as follows:
Category A : Radiographical Test(RT)
Category B : Radiographical Test (RT), where if one side welding joints
with backing metal, Ultrasonic Test (UT) is defined.
Category C : Liquid Penetrant Test (PT)
Category D : Liquid Penetrant Test (PT)
Others : Liquid Penetrant Test (PT)
The nondestructive tests categories are shown in ATTACH. 1-42 ~
ATTACH. 1-44.
- 58 -
JAERI-Tech 99-026
2.5.4 Transportation and Field Installation Procedure
The procedure from the shop shipping to field installation is studied by
considering the following items.
(l)Each block is transported over sea after shop shipping.
(2)A large trailer for the field transportation
(3)In field installation, available crane capacity in field, shop blocks and pre-
assembly space are considered.
The block separation and conceptual procedure field assembly / installation is
summarized in Table 2.5-1. The operation flow from shop shipment to field
assembly is shown in Figure 2.5-1.
The Installation procedure in Tokamak pit is shown in ATTACH. 1-3 5.
- 59 -
Table 2.5-1 Block Separation and Conceptual Procedure of Field Assembly/Installation
eno
Object
Anchorage
Suppression
Tank
Lower Cover
Cylinder
Upper Cover
CS Support
Ring Pedestal
Suppression Tank
General Part
Relief Pipe
Central Block
Ring Pedestal
Middle Block
Outer Block
Lower Cylinder
Middle Cylinder
Upper Cylinder
Central Block
Outer Block
Outline of Shop Blocks
Dimensions
—
15.7m X 6.9m X 6.4m
12.0m X 6.3m X 6.8m
6.1mX6.1mX2.5m
14.3mX3.6mX2.5m
14.9m X 8.5m X 0.6m
17.6m X 7.0m X 0.9m
11.3m X 9.2m X 1.7m
11.3mXl3.5mXl.8m
lt.3mX 9.9m X 1.4m
14.0mX 14.0mX l.5m
19.3m X 12.7m X 6.5m
units
—
4
4
1
6
4
8
10
10
10
1
5
Field Assembly/Installation
(Assembly into Ring is in Shop)
After installation of each anchorage(anchor bolts, etc.), installation concrete mat
of Tokamak
After assembly on ring, transfer into the pit and installation
After assembly of lower block of CS support, transfer / installation into the
Tokamak pit
Transfer into the pit and installation
The lower block of ring pedestal is installed by same procedure
After assembly on ring, transfer into the pit and installation
After assembly on ring, transfer into the pit and installation
After assembly on ring, transfer into the pit and installation
After assembly on ring, transfer into the pit and installation
After assembly on ring, transfer into the pit and installation
After assembly on ring, transfer into the pit and installation
Installation
Schedule
See
ATTACH.
1-35
STEP1
STEP 2
STEP 3
STEP 4
STEP 3
STEP 5
STEP 6
STEP 7
so
—3CDO3 "
CDto
O
FIG. 2.5-1(1/3) < PROCEDURE OF CRYOSTAT TRANSPORTATION (1/3) >
LIMITATION;
• MAX. OVER LENGTH
W14mXL19mXH6m
• MAX. WEIGHT
11.77 MN (1200TON)
ICT>
SHIPPING AT SHOP
LIFTTING CRANE
>CDPC
CDo
totoI
o(S3Oi
(FOB)
7
OCEAN
UN1X>ADING
FIG. 2.5-1(2/3) <PROCEDURE OF CRYOSTAT TRANSPORTATION ( 2 / 3) >
OCEAN
TRAILER
TRANSPORTATION AT SITE
ASSEMBLY FIXTURE
-*- WITH COVER
FIELD ASSEMBLY
pa
o
Io
FIG. 2.5-1(3/3) < PROCEDURE OF CRYOSTAT TRANSPORTATION (3/3) >
GO
TOKAMAK BUILD. CRANE
CAPACITY: 11.77 MN
(1200TON)
(ASSEMBLY HALL)
P<3
•nooTRANSPORTATION INTO
TOKAMAK BUILDING
t t X
-9
Io
PIT INSTALLATION
JAERI-Tech 99-026
2.5.5 Pressure Test Method
After the installation of cryostat, the inside of the cryostat will be pressurized up
to test pressure in order to confirm the structural integrity.
The pressure test is performed as follows;
(l)Test System
Figure 2.5-2 "Outline of Cryostat Pressure Test"
(2)Test Pressure: PtP, = 0.1 x 125*' = O.l25MPa (gage pressure)
note) *1 : according to the ASME B&PV Code Section Vffl (Div.2)
AT-320(Vessels Designed for Vacuum)
(3)Test Medium
N2gas
(4)Time Schedule
0)u3
be<sO
2
Pressure proof tes
0.125
t
y \/ 0.0625
/ TIME
Leakage Test
0.1
\
\
2.5.6 Field Installation Schedule
The schedule from shop fabrication to field installation of the cryostat is
shown in Table 2.5-2.
- 64 -
FIG. 2.5-2 < CRYOSTAT PRESSURE TEST >
PURGE VALVE
PRESS.
>RESSURE TEST
JOUNDARY
Sl^l^^S^S^te^t Jl i-BiiilHi1^: l i J^ j'p l 'iif.fe 1 s H.i^?
TANK TRUCK
'ALVE-f LN2 j
G.L
(Pc ) PRESSURE GAUGE
o
oC31
Table 2.5-2(1/2) SHOP FABRICATION & TRANSPORTATION SCHEDULE OF CRYOSTAT
ITEM
1 SHOP MANUFACTURING
1) ANCHOR BOLTS
REQUIRED PERIOD (MONTH)1
i
(
—i—2) RING PEDESTAL & CS SUPPORT
3) LOWER COVER
4) LOWER CYLINDER
5) MIDDLE CYLINDER
6) UPPER CYLINDER
7) UPPER COVER
8) PORTS
t
!!
!
!
!
1i
i
= - •
-—i—--
3!
s!
—• =
j~' r—
|
9) INSPECT1ON(V1SUAL & DIMENSIONAL CHECK)i
i
i1!
2 TRANSPORT ATION(BARGE) !;||j
!
1
»
i
4
I
= = —
j
\—-
i
jr—
t>
r
i
1
i
|
V
i
5
i
1
j
!
r
—=i=1
—
j
1
iI
i
6
—
• = .
7!
Ij
11|
i !
!
ji
,
V
V i
8!
!
1iij
i
=
—i—-i-
i!i1!
i}
91
=
—
j
i
i
i
10:
= t =
!
!I
1
i
•
y
1
1
!{
jV
12
!
j
—1—
i
i
i
I
j1
13
ii
|
— 1
14
!
-,
V
1
!
V
15
!
••
1•
i
ii
i
i
16i
1
1
;
I
i
17i
1
!
f
j
V
i
i
!
!
j
•
V
!
is
1
ii
i
j
19}
I!
1
:
i
1
i
TO
!
ii
i
!
V i
j
V
i!
REMARKS
PO
IDI
o(S3
Table 2.5-2(2/2) SITE INSTALLATION SCHEDULE OF CRYOSTAT
ITEM
1 PREPARATION
1) SITE OFFICE
2) ASSEMBLY FIELD
2 SITE CONSTRUCTION
1) ANCHOR BOLTS
REQUIRED PERIOD (MONTH)1
•=( )
i
2) RING PEDESTAL & CS SUPPORT
II
2
>
(GUARD)i— 1 —
3) LOWER COVER & LOWER CYLINDER
4) MIDDLE CYLINDER
S) UPPER CYLINDER
6) UPPER COVER
7) PORTS
8) PNUMATICTEST
i— —i
4
)
9) D1S-ASSEMBLY OF CONSTRUCTION JIG(SUPPORT ETC.)
3 CLEARING
5 6 7 8
i
1
9
1
10
•
I
11
—>
12!!
ij
131
ii
!
i
i
14
!
i
I
; 1
i
15
ii
i
< =
161
1
j
1! I
1)
17
i}
[1
!
181
i
I
ii
!
1jI
REMARKS
>
ft)o
oto
JAERI-Tech 99-026
2.6 Future works and R&D Activities
The structural design and the investigation on fabrication / installation of the
single-walled cryostat proposed by the JCT are performed.
Items that should be studied more are shown as follows.
2.6.1 Design of Cryostat
• Evaluation by detailed analysis for dynamic load
•Evaluation of reliability of the flexible joints
•Study of decreasing plate thickness (250mm) of the upper plate of ring pedestal
which are the field welding joints
• Study of possibility of the mid-basement-floor in the tokamak building for
lower cover maintenance• Study of the cryostat cylinder by flat plate
• Study of the vibration proof structure
2.6.2 Fabrication and Installation
• Study of cutting, welding and nondestructive test method of thick stainless
steels• Study of the equipment for field assembly
2.6.3 R&D
•Availability clarification of ASME Section-VDIDivision-2 for large vessel
structure with many penetrations
•Reliability clarification of the flexible joints
•Cutting, welding and nondestructive test method of thick stainless steels
• Remote handling devices for bolting, cutting, rewelding and welding
nondestructive test
- 68 -
JAERI-Tech 99-026
3. Suppression Tank Detail Design
3.1 Introduction
The vacuum vessel pressure suppression tank is the vessel which is located under
the lower bio-shield in order to keep the vacuum vessel pressure below the design
value of 0.5 MPa during the water spillage from in-vessel component. The
suppression tank with the water of half volume of tank is connected to the 4
divertor handling ports. The spilled water and steam inside vacuum vessel are led
to the suppression tank through the divertor handling ports and the pressure inside
vacuum vessel is kept below the design value.
The following design items are studied.
- Detail design of the suppression tank and pipes
- Tank removal/installation procedure for the lower PF coil maintenance
3.2 Design Conditions
3.2.1 Suppression Tank
l)Design Pressure : 0.5 MPa
2)Normal Pressure : 0.01 MPa
3)Design Temperature Normal Temperature : 20°C
LOCA Temperature : 8 0 ^
4)Seismic Load Horizontal Direction : 2.828 X0.2G
Vertical Direction : 2.2X-0.2G
(Peaking Factor XSL-2)
3.2.2 Rupture Disk
l)Opening Pressure : 0.2 MPa
2)Normal Pressure : 0.01 MPa
3)Leakage : 10"10Pa-m3/sec
3.2.3 Bellows Expansion
1 )Axial Direction Displacement/Cycle : 50mm X103cycle
2)Lateral Direction Displacement/Cycle : 80mmX103cycle
3.2.4 Material
1 Suppression Tank : SUS304L
2)Rupture Disk : SUS304L
3)Bellows Expansion : SUS304L
- 69 -
JAERI-Tech 99-026
3.3 Detailed Design of Suppression Tank
3.3.1 Structure of Suppression Tank
The structure of suppression tank is shown in the following drawings.
Attach. 2-25 VV Suppression Tank General Arrangement
Attach. 1-26 W Suppression Tank Sectional View
Attach. 1 -27 VV Suppression Tank Front View (Relief Pipe Portion)
Attach. 1-28 VV Suppression Tank Front View (Distributor Portion)
Attach. 1 -29 VV Suppression Tank Front View (Connection Portion)
Attach. 1-30 W Suppression Tank Support Detail
3.3.2 Study of mechanical strength of the suppression tank
The mechanical strength of the shell and heads of the suppression tank are
evaluated in accordance with the ASME Boiler and Pressure Vessel Code
Section-VIII division-2.
(1) Shell
a. Mechanical strength for internal pressure
The required thickness of the shell is obtained by the following formula.
t P R
S-03P
Where,
t; minimum required thickness of the shell
P; internal design pressure of 0.5MPa and static head of the fluid of 0.03MPa
=O.53MPa
R; inside radius of the shell =281 Omm
S; membrane stress intensity limit =115MPa (SUS304L, at room temp.)
The minimum required thickness is as follows;
0.53x2810t = = 13.0mm
115-0.5x0.53
The present shell thickness (14mm) is thicker than the result. Therefore, the
mechanical strength of shell for the design internal pressure satisfies with the
ASME Section-VIII division-2.
- 70 -
JAERI-Tech 99-026
b. Mechanical strength for external pressure
The maximum allowable external pressure can be evaluated by the following
procedure. The thickness of shell is assumed to be 14mm in this analysis.
- ^ = ^ = 0 . 4 0Do 5648
^ = 5 6 4 8 = 4 0 3t 14
Where,
Do; outer diameter of the shell' =5648mm
L; distance between stiffening rings =2250mm
According to the FIG. G shown in the Subpart 3 "Charts and Table for
Determining Shell Thickness of Components under External Pressure" of ASME
B&PV Code, Sec. II, Part D, the factor "A" is as follows;
A=0.00043
Then, by the FIG. HA-3 "Chart for the determining shell thickness of components
under external pressure when constructed of austenitic steel (18Cr-8Ni-0.0035
maximum carbon, type 304L)" of ASME B&PV Code Sec. II Part D, the factor
"B" is determined as follows,
B=6000
Therefore, the maximum allowable external pressure Pa is
_ 4B _ 4 x 60003(3D0/t) 3x403
= 19.85psi
= 0.136MPa>0.1MPa
The maximum allowable external pressure is larger then the design external
pressure of 0.1 MPa. The mechanical strength of shell for the design external
pressure satisfies with the ASME Section-VIII division-2.
- 71 -
JAERI-Tech 99-026
c. Mechanical strength of the stiffening ring
The moment of inertia of the stiffening ring is evaluated. The required moment of
inertia of the combined ring-shell section Is is calculated as follows;
_D02L5(
10.9
56482x2250x(l4 + 6100/2250)x2.7xl0-4 , t
= - '- = 2.971 xlO7 mm4
10.9Where,
As; cross-section area of the stiffening ring =6100mm2
Ls; length between stiffening rings =2250mm
According to the FIG. HA-3 in the Subpart 3 of the ASME B&PV Code Section
II, the factor "A" is as follows;
A=2.7xlO"4.
Here, the factor "B" is calculated as follows:
_ 2 [ 0.1 x 5648 I~4XLl4 + 6100/2250j= 253MPa = 3669psi
If the dimensions of the cross section are shown in the following figure, the
available moment of inertia is calculated as the following procedure.
The effective width of the shell W isW=U0>/DoT,
= I.I 0 x V5648xl4 = 309mm
Where, Ts is the thickness
of the shell of 14mm.
- 72 -
JAERI-Tech 99-026
The each moment of inertia is summarized as follows:
(D(D(3)
total
A (mm2)
4326
3600
2500—
y (mm)
7
126.5
251.5—
i (mm4)
7.066 X104
1.519X107
1.302 XI05
1.539 X107
AAy2 (mm4)
4.317X107
1.383 XI06
5.227 X107
9.682 XIO7 ;
The available moment of inertia is
y) l ° 7 + 9 - 6 8 2 x l ° 7 =1-122x10* mm4.
Where,
Ay; distance between the center of the component, y, and e
e; the center of gravity of the combined shell-ring section
6 =4326x7 + 3600x126.5 + 2500x251.5
4326 + 3600 + 2500
The available moment of inertia / is larger than the required moment of inertia
Is. Therefore the supposed cross-section of the stiffening ring is sufficient to
the design external pressure of 0.1 MPa.
(2) Head of the tank
a. Mechanical strength for internal pressure
The required minimum thickness is evaluated in accordance with "Article D-2,
Shells of revolution under internal pressure" AD-204"Formed Heads" of
ASME B&PV Code Section-VIII division-2. The fundamental dimensions
of the head are as follows:
• Inside crown radius of the head; L=8000mm
• Inside knuckle radius of the head; r=5 62mm
• Inside diameter of the head; D=5620mm
• r/D = 562/5620 = 0.10
- 73 -
JAERI-Tech 99-026
Several calculation trials are performed by changing the thickness of the head th.
The typical calculation examples are as follows,
(a) Case-1 th =14mm, the same thickness as the shell
In this case, the t/L is 0.00175 and is out of the applicable range specified
in the FIG. AD204.1 "Design curves for torispherical heads and 2:1 ellipsoidal
heads for use with AD204.2 and AD204.3".
(b)Case-2 th=16mm
The parameter P/S is 0.0015 from the design standard. Here, S is the
membrane stress intensity limit of 115MPa. The allowable internal pressure P
is P=0.0015xll5=0.172MPa. As the design internal pressure is 0.53MPa,
integrity of the head cannot be maintained.
(c) Case-3 th =50mm
From the design standard, the parameter P/S is 0.0063 under the condition
of th/L=50/8000=0.00625. Therefore, the allowable internal pressure is
P=0.724MPa. This result satisfies with the internal design pressure of 0.5
MPa.
(d) Case-4 th -40mm
From the design standard, the parameter P/S is 0.0047 under the condition
of th/L=40/8000=0.005. Therefore, the allowable internal pressure is estimated
as P=0.541MPa. This result also satisfies the internal design pressure of 0.5
MPa.
The thickness of the head th is concluded to be minimum 40mm by these
calculation trials. For this, the connection between head and shell with a
thickness of 14 mm is required to prevent large stress concentration due to the
geometrical discontinuity. According to the AD-420 "Transition joints
between sections of unequal thickness", a tapered transition with length of
3x(th-ts)=3x(40-14)«80mm is needed.
b. Mechanical strength for external pressure
According to the AD-360 "Formed Heads" in "Article D-3, Shells of
revolution under external pressure", the mechanical strength of the head with a
thickness of 40mm is assessed as follows:
(a) Estimation of the factor "A"
A=0.125/(Ro/th)=0.125/(8040/40)=0.000622
Here, Ro is the outside radius of the head-crown of 8040mm.
- 74 -
JAERI-Tech 99-026
(b) Estimation of the factor "B"
According to the FIG. HA-3 of the Subpart-3 in ASME B&PV Code
Section-II, the factor B is 7800psi for the factor "A".
(c) Estimation of the maximum allowable external pressure
The maximum allowable external pressure Pa is
Pa=B/(Ro/t)=7800/(8040/40)=39psi=0.268MPa.
(d) Evaluation of the mechanical strength
The maximum allowable external pressure is larger than the design
external pressure of 0.1 MPa. Therefore the thickness of the head of 40 mm
satisfies with the required mechanical strength.
c. Conclusions
The conclusions are summarized below,
(a)The thickness of shell and head are determined based on the ASME B&PV
Code, Section-VIII division-2.
The shell thickness : 14 mm
The head thickness :40 mm
(b)The configuration of stiffening ring is determined.
(c)In the future, the detailed stress assessment by FEA is needed, because the
head is not satisfied with the structural limitation specified in the AD-204.4
"Crown and Knuckle Radii".
- 75 -
JAERI-Tech 99-026
3.4 Rupture Disk / Bellows Detailed Design
3.4.1 Structure of Rupture Disk / Bellows
-The outline of the relief piping connecting the divertor handling port is shown in
ATTACH. 1-31.
-The detail structure of the rupture disk is shown in ATTACH. 1-32.
-The detail structure of the jimbal-bellows which accommodates the relative
displacement between the divertor port and the cryostat lower cover is shown in
ATTACH. 1-33.
- The detail structure of the lower cover penetration bellows that accommodates
the relative displacement between the cryostat lower cover and the suppression
tank is shown in ATTACH. 1-34.
3.4.2 Mechanical Strength of the Rupture Disk and Expansion Joint
(1) Diaphragm thickness of the rupture disk
In general, the structure of diaphragm is determined based on the results obtained
by the tests using prototype disks. Therefore, in this study, the diaphragm thickness
is determined under the assumptions listed below:
Longitudinal elastic modulus of the diaphragm material; E=195GPa
Curvature of the radius of the diaphragm; a= 130cm
Factor K=0.5 ~ 0.7 (to be confirmed by the tests)
The thickness of the diaphragm is,
02 x2xl30x(0.5~0.7)U6.7xl.95xlO5
= 0.17~0.24(cm)
Here, the rupture (burst) pressure P is 0.2MPa.
- 76 -
JAERI-Tech 99-026
The thickness of the diaphragm is concluded 2mm. As mentioned above, however,
the thickness and the height of the diaphragm should be confirmed by the tests. The
factor K should be also reassessed by the tests using prototype disks. This is one of
the R&D activity to improve the structural and safety design.
(2) Mechanical strength of the bellows
Based on the EJMA standard**!), the integrity of the bellows between the divertor port
and the suppression tank( is assessed. The loading conditions are listed below,
Internal pressure; 0.5MPa
Deflection range and number of the cycle
Axial direction; 50mm x lOOOcycles
Transverse direction; 80mm x lOOOcycles
The detailed design results are shown in Table 3.4-1.
The circumferential membrane stress due to the internal pressure;
S2=33MPa<l 15MPa=allowable membrane stress limit
Cumulated usage factor,
NE/NC=0.51 15<0.1=allowable usage factor limit
The membrane stress due to the internal pressure and the cumulated fatigue damage
due to the cyclic deflection are lower than the allowable limits. Therefore, the
mechanical strength of the bellows is sufficient under the lording condition.
[NOTE]
(*1); EJMA standard means "Standard of the Expansion Joint Manufactures
Association, INC".
(*2); The configuration and dimension of the bellows expansion are shown in the
Attachment 1-33, "Jimbal Bellows Detail".
- 77 -
JAERI-Tech 99-026
Table 3. 4-1 Stress calculation results Ifor the expnsion joint
Stress calculation sheet for double type expansion joint
Plant/Equipment ITER / Vacuum vessel pressure suppression tank
Identification of the expansion joint
geometrical specification
Bellows pitchConvolution depthPitch diameter of bellowsNominal material thickness of the one plyNumber of bellowsNumber of convolutions in one bellowsDistance between outermost ends of the convolutionLength of straight portionCurvature of convolutionOutside diameter of cylindrical tangentLength of intermediate ringLength of end pipeBellows material thickness factor of one plyShape factorShape factorRatio of maximum moment/pressureRatio of deflection/loadRatio of deflection/maximum moment
Bellows material
Symbol
qWdptcNL1ardL2L3
tpC24XC24CpCfCd
—
Unit
mmmmmmmm——mmmmmmmmmmmmmm—————
—
Design condition symbol unit**'
Maximum design pressureDesign temperatureApplied axial movementApplied lateral deflectionApplied radial deflectionApplied angular rotationNumber of cyclesLongitudinal elastic modulus
Calculation of the deflection
Equivalent radial deflection of angular componentEquivalent axial deflection of lateral componentEquivalent axial deflection of radial componentTotal axial deflection
Stress calculation
Circumferential membrane stress due to internal pressureJudgement for the stress aboveMeridian membrane stress due to internal pressureMeridian membrane stress due to internal pressureMeridian membrane stress due to deflectionMeridian bending stress due to deflectionMeridian membrane stress due to radial bulgeTotal meridian stress
PT
AXY1Y28
NDE
kq/cm2q• cmmmmmm
degreecycles
ka/mm2
Relief pipe expansion joint
Dimension
6080
12601.5
210
7845015
1180184
01.4520.380.640.681.4
1.65
type 304L SS
value
520508000
100019900
Remarks
q/4
ffd/dD)10
q/(2*W)q/(2.2*(dD • to)05)Figured 8Figured 9Figure C20
remarks
EJMA (UNREINFORCED BELLOWS)
A 0AL1AL2A
mmmmmmmm
0299.06
0.00349.06
EJMA (UNREINFORCED BELLOWS)
S2—S3S4S5S6S7St
kq/mm2
kq/mm2
kq/mm2
kq/mm2
kq/mm2
kq/mm2
kq/mm2
kq/mm2
3.35< 11.7
0.6925.80
1.02159.19
0.00178.75
good
Fatigue damage calculation EJMA (UNREINFORCED BELLOWS)
Temperature correction factorFatigue lifeFatigue damage
Cumulated usage factor
TfNc
ND/Nc
U
—
cycles—
—
1.001955
0.5115
< 1.0
(SuC + SuH)/(2*SuC)Figure C21
good
(•); The unit "kg" means a gravity force by the unit mass in the conventional engineemng unit.
- 78 -
JAERI-Tech 99-026
3.5 Study of Disassembly and Assembly at Maintenance
The disassembly/assembly procedure and the equipment which are required during
disassembly/assembly are studied.
a. Pre-conditions
In the design study of assembly / disassembly procedure, the following
pre-conditions are considered.
-The bio-shield under the lower cover should be pre-installed.
-Two openings of 4.2m height X 6m wide should be arranged in the pit to enter and
remove the suppression tank.
-The mid-basement-floor should be pre-assembled.
-There should be sufficient space to turn the suppression tank for the transportation.
b. The equipment for the suppression tank assembly / disassembly is shown in Table
3.5-1.
c. Removal and Installation procedure
The conceptual procedure of removal/installation of suppression tank is as
follows.
Removal Procedure;
STEP 1 : Remove the suppression tank water
STEP 2 : Cut the relief pipes
STEP 3 : Cut the tank
STEP 4 : Lift up the tank and set the transfer table
STEP 5 : Remove the tank by the transfer table
STEP 6 : Turn the tank
STEP 7 : Transfer the tank
(Transfer the bio-shield and remove the lower cover)
(Install the lower cover and the bio-shield)
- 79 -
JAERI-Tech 99-026
Installation Procedure
STEP 8 : Install the tank.
STEP 9 : Weld the tank and perform the welding nondestructive examination
STEP 10: Weld the relief pipes and perform the welding nondestructive
examination
STEP11: Perform the pressure test and the leakage test
- 80 -
• CUT RELIEF PIPE & PORT• SET REMOVABLE TABLE• CUT OF an SHELL
TRAVELING TABLETURN TABLE
00
REMOVE S/T TO PIT OPENING• SET S/T ON TURN TABLE
•OVER TURN S/T• HORIZONTAL TURN S/T• REMOVE TURN TABLE
• TRANSFER S/T ON TRAVEUNG TABLE• CARRY OUT SAT
NAME OF EQUIPMENT
LOCATION
DESIGN CONDITION
OPERATING CONDITION
TYPE OF EQUIPMENT
MAIN MATERIAL
WEIGHT
ACCESSORY
NOTES
TURNTABLE
SUPPRESSION TANK
EQUIP. CLASS
TEMPERATURE
TEMPERATURE
EQUIP. NO.QUANTITYCORROSIONMARGIN
ROOM TEMPERATURE
ROOM TEMPERATURE
CARBON STEEL
REMOVABLE TABLETRAVELING TABLE
FOR HORIZONTAL MOVEMENTFOR CARRY OUT
1. FUNCTION;
(DOVER TURN
© HORIZONTAL TURN
2. ALLOWABLE LOAD ; 30 tons
3.APPROX.DIMENSION; * 6 m X i-6m X H S m
4. DRIVING SYSTEM ; ELECTRICAL
>
i
o
otoOi
Table 3.5-1 Maintenance Equipment for Suppression Tank
JAERI-Tech 99-026
Suppression Tank Assembly/Disassembly Procedure>
The procedure of the assembly/disassembly of suppression tank is shown in Figure 3.5-
1.
STEP 1 : Remove the suppression tank water
(l)Prepare the storage tank
(2)Connect the piping for removal
(3)Transfer the water to the storage tank
(4) Wash out the inside of suppression tank by clean water
(5)Remove the pipes
STEP 2 : Cut the relief pipes
(l)Measure the contact dose and surface contamination of suppression tank
(2)Cut the guard pipes
(3)Cut the relief pipes
(4)Cut the distributer in the tank
STEP 3 : Set the transfer table
(l)Set the transfer table for tank transfer
(2)Fix the suppression tank by the support
STEP 4 : Disassemble the suppression tank
(1 Considering the size of the opening, disassemble the tank
STEP 5 : Transfer the tank
(l)Liftupthetank
(2)Transfer the disassembled suppression tank to the pit opening.
(3)Stop the transfer table on the turn table.
(4)Remove the removable table
STEP 6 : Turn the tank.
(l)Turn the tank with the turn table.
(2)Lift down the disassembled tank on the transfer table
STEP 7 : Transfer the tank.
(l)Transfer the tank.
- 82 -
JAERI-Tech 99-026
STEP 8 : Install the tank
(1/Transfer the tank into the pit.
(2)Turn the tank
(3)Transfer the tank from the pit opening to the installation position
STEP 9 : Weld the tank and perform the welding nondestructive examination
(l)Weld the tank and perform the welding nondestructive examination
(2)Weld the distributer and perform the welding nondestructive examination
(3)Assemble and weld the opening for human access and perform the welding
nondestructive examination
STEP 10: Weld the relief pipes and perform the welding nondestructive examination
(l)Weld the relief pipe and perform the welding nondestructive examination
(2)Weld the guard pipe and perform the welding nondestructive examination
STEP11: Perform the pressure test and the leakage test
- 83 -
STEP1; REMOVE THE SUPPRESSION TANK WATER
00
I
TRANSFER PIPING LINE
VALVE
- 3CO
o
otoO5
PUMP STORAGE TANK
FIG.3.5-1 MAINTENANCE PROCEDURE OF SUPPRESSION TANK (1/9)
STEP2 ; CUT THE RELIEF PIPES STEP3 ; SET THE TRANSFER TABLE
oo
(
ro n
«• " i> ""• • '
>
ft'
f
———
j1
^ ' •" • ' • •
r. ..r , . . ,M^T r - ,
SETTINGSUPPORT
>ml-H
ICDO
cr
oO5
TRANSFER TABLE
FIG.3.5-1 MAINTENANCE PROCEDURE OF SUPPRESSION TANK (2/9)
STEP4 ; CUT THE TANK
I00
TANKS ARE REMOVED, MAINTAINED AND
RE-INSTALLED EXCEPT THE BLOCKS IN
FRONT OF THE OPENING
CUTTING LINE
TRANSFER TABLE
OPENING OF THE PIT
THE BLOCKS IN FRONT OF THE OPENING ARE
CUT, REMOVED AND RE-ASSEMBLED.
CDO
toI
O
FIG.3.5-1 MAINTENANCE PROCEDURE OF SUPPRESSION TANK (3/9)
STEP5 ; TRANSFER THE TANK
00
I
LIFT UP
OVERTURN —
TRANSFER TO THE
PIT OPENING
TO
eno
COI
o(S3
TURN TABLE
HORIZONTAL TURN
FIG.3.5-1 MAINTENANCE PROCEDURE OF SUPPRESSION TANK (4/9)
STEP6 ; TURN THE TANK
OVER TURN
00CXI
T
HORIZONTAL TURN
V . . •_•
>
—jCDO
oto
FIG.3.5-1 MAINTENANCE PROCEDURE OF SUPPRESSION TANK (5/9)
STEP7 ; REMOVE THE TANK
ooCO
so
i
CDO
oID
O
FIG.3.5-1 MAINTENANCE PROCEDURE OF SUPPRESSION TANK (6/9)
STEP8 ; INSTALLTHE TANK
SO
o
HORIZONTAL TURNOVER
TURN->UPSET-^TRANSFER
>
mh-<
I
•H
O
ID
Oto
FIG.3.5-1 MAINTENANCE PROCEDURE OF SUPPRESSION TANK (7/9)
STEP9 ; WELD THE TANK AND PERFORM THE NDE
WELD LINE
PO
CDO
to<£>
ION3
THE BLOCKS IN FRONT OF THE OPENING
ARE RE-ASSEMBLED INTO THE PIT.
FIG.3.5-1 MAINTENANCE PROCEDURE OF SUPPRESSION TANK (8/9)
STEP10 ; WELD THE RELIEF PIPE
WELE
CO
GUARD PIPE RELIEF PIPE
WELDING PROCEDURE:
(DWELD RELIEF PIPE
©LIFT UP SPLICE PLATE
®WELD(UPPER SIDE)
<DWELD(LOWER SIDE)
SPLICE PLATE
>CDSO
I
oIS3
WELD DETAIL
FIG.3.5-1 MAINTENANCE PROCEDURE OF SUPPRESSION TANK (9/9)
JAERI-Tech 99-026
3.6 Study of Rupture Disk Exchange Plan
The exchanging procedure of rapture disk is investigated.
a. Precondition
The rapture disk remote exchange procedure is investigated with considering the
following conditions:
-The rapture disk is exchanged with remote handling equipment from the
divertor port.
b. The equipment for the rapture disk exchange is shown in Table 3.6-1.
c. Exchange Procedure
The exchanging procedure of the rapture disk is as follows.
Disassemble Procedure;
STEP 1 : Set the equipment for maintenance
STEP 2 : Disassemble and remove the cover flange
STEP 3 : Disassemble and remove the upper rapture disk
STEP 4 : Disassemble and remove the lower rapture disk
STEP 5 : Inspect the relief pipe's side-lip-seal
(Exchange new rapture disks)
Assemble Procedure;
STEP 6 : Transport and weld the lower rapture disk
STEP 7 : Transport and weld the upper rapture disk
STEP 8: Transport and weld the cover flange
STEP 9: Remove the maintenance equipment
STEP10:Perform the local leakage test
93 -
<o
I
ATTACHMENTl'OH FIXATION
REMOTE DEVICE UNIT
LIP SEAL WELD
TEST HOLE
NAME OF EQUIPMENT
LOCATION
DESIGN CONDITION
OPERATING CONDITION
TYPE OF EQUIPMENT
MAIN MATERIAL
WEIGHT
ACCESSORY
NOTES
REMOTE HANDLING DEVICE UNIT EQUIP. NO
DIVERTOR PORT
EQUIP. CLASS
TEMPERATURE
TEMPERATURE
QUANTITY
CORROSION
MARGIN
ROOM TEMPERATURE
ROOM TEMPERATURE
CARBON STEEL
MONITORING
LIGHTING
CENTERING
CLEANING
POSITIONER
ITV. CCD Camera
GUIDE RAIL
1. DRIVING SYSTEM
Driving Gear: Rack & Pinion
Speed; Max. 1200 m/min.
2. BOLTING DEVICE UNIT
Type ; Power Rench
Torqu ; 100~ 150 N-m
3. CUTTING DEVICE UNIT
Type; Grinding
4. REWELDING DEVICE UNIT
Method : TIG Welding or YAG Laser Welding
Speed; 20~ 100 na/min.
5. WELDING NONDESTRUCTIVE EXAMINATION DEVICE UNIT
Method; PT
(The transporter of each tool is a Remote Control Unit(vehicle) moving along a
guide rail)
>t-fl•pa
—3
o
IO
Table 3.6-1 Equipment for Maintenance of Rupture Disk
JAERI-Tech 99-026
<Rupture Disk Exchange ProcedurO
The rupture disk exchange procedure is shown in Figure 3.6-1.
STEP 1 : Positioning the maintenance equipment
(l)Drive the maintenance equipment to location of the relief pipe
(2)Positioning the equipment
STEP 2 : Remove the cover flange
(l)Loosen the bolts for the cover flange
(2)Remove the cover flange.
(3)Transfer the cover flange.
-Transfer the removed cover flange to the cask
STEP 3 : Remove the upper rupture disk
(l)Cut the lip seal
(2) Loosen the bolts
(3)Remove the upper rupture disk
(4) Transfer the upper rupture disk
STEP 4 : Remove the lower rupture disk
Same procedure as STEP 3
STEP 5 :Machining the relief pipe's side-lip-seal
STEP 6 : Transfer and weld the lower rupture disk
(l)Set the lower rupture disk on the maintenance equipment
(2)Set the welding device unit on the maintenance equipment
(3)Install the lower rupture disk.
(4)Weld the lip seal.
(5)Tighten the bolts
STEP 7 : Transport and weld the upper rupture disk
Same procedure as STEP 6
STEP 8 : Transfer and bolt the cover flange
(l)Set the cover flange on the maintenance equipment
(2)Set the bolting device unit on the maintenance equipment
- 95 -
JAERI-Tech 99-026
(3)Tighten the flange bolts with the bolting device unit
STEP 9 : Remove the maintenance equipment
STEP 10: Perform the local leakage test
The space between the rapture disks is pressurized with the compression line
pre-installed for the local leakage test.
- 96 -
STEP1; SET THE EQUIPMENT FOR MAINTENANCE
Divertor handling port
Relief pipe
FIG.3.6-1 MAINTENANCE PROCEDURE OF RUPTURE DISC (1/6)
>m
CDO
IOto
STEP2 ; REMOVE THE COVER FLANGE
ID
Bolting device
unit
Rapture disk handling
unit
i—i
—JCDonrto
ioto
FIG.3.6-1 MAINTENANCE PROCEDURE OF SUPPRESSION TANK (2/6)
STEP3 ; REMOVE THE UPPER RUPTURE DISC
Lip seal
FIG.3.6-1 MAINTENANCE PROCEDURE OF SUPPRESSION TANK (3/6)
STEP4;REMOVE THE LOW RUPTURE DISC STEP5;MACHINING THE RELIEF PIPE'S SIDE LIP SEALSTEP6;TRANSPORT&WELD THE LO W RUPTURE DISC
oo
i—ii
—iCDO
<£>CD
FIG.3.6-1 MAINTENANCE PROCEDURE OF SUPPRESSION TANK (4/6)
STEP7;TRANSPORT&WELD THE UPPER RUPTURE DISC STEP 8 ;TRANSPORT&WELD THE COVER FLANGE
I
O
qD
FIG.3.6-1 MAINTENANCE PROCEDURE OF SUPPRESSION TANK (5/6)
I—3(t)O
STEP9.REM0VE THE EQUIPMENT FOR MAINTENANCE STEP10;PERFORM THE LOCAL LEAKAGE TEST
©CO
emote handling
quipment
>tDpoi—i
i
CDO
<£>
Pipe for local leakage
FIG.3.6-1 MAINTENANCE PROCEDURE OF SUPPRESSION TANK (6/6)
JAERI-Tech 99-026
3.7 Study of Fabrication/Construction Plan and Schedule
Regarding with the shop fabrication, transportation and field construction plan /
schedule for the suppression tank, the following issues are investigated.
(l)Block Separation
(2)Shop Fabrication Procedure
(3 Nondestructive Examination
(4)Transportation and Field Installation Procedure
(5)Pressure Test Method
(6)Field Installation Schedule
3.7.1 Block Separation
By considering the following items, the separation method of suppression tank
are investigated.
(1 fabrication Ability of Mill Maker
(2)Fabrication Ability of Shop
(3transportation Limitation (Size Limitation)
(4)Ability of Crane in Site
(5)Installation Procedure
The block separation of suppression tank is shown in ATTACH. 1-25.
3.7.2 Shop Fabrication Procedure
The shop fabrication procedure are studied considering the cutting/bending
processing, welding procedure, required to examination/inspection and ability
of equipment in shop.
The shop fabrication sequence is shown in ATTACH. 1-41.
3.7.3 Nondestructive Examination
Based on the ASME Code Section VIII (Div. 2), the nondestructive
examination method of each welding line are studied.
The category of nondestructive examination is shown in ATTACH. 1-45.
- 103 -
JAERI-Tech 99-026
3.7.4 Transportation and Field Installation Procedure
The transportation procedure from shop to site (including the marine
transportation) is the same as that of the cryostat shown in section 2.5.4.
Since the full assembly of suppression tank is performed on the ground in site,
the required assembly procedure on the ground is studied.
The procedure of installation are shown in ATTACH. 1-35 and 1-36.
3.7.5 Pressure Test Method
After the installation, the integrity of the assembly should be clarified by the
pressure test.
Because the tank is connected to the divertor ports through relief pipes, the upper
part of the relief pipe is to be isolated from the port by the plugs during the
pressure test.
The planned test method is the pneumatic test because the tank can not fill up
with water considering the tank structure.
The procedure of the pressure test is as follows:
(l)Test System
Figure 3.7-1 " Outline of Suppression Pressure Test"
(2)Test Pressure : PtP, =0^x1.15*' =0J75MPa
note) *1 : according to ASME Sec.Vffl Div.2 AT-410 (pneumatic tests)
(3)Test Medium
N2gas
- 104 -
JAERI-Tech 99-026
(4)Time Schedule
%mCO
<x>bocti
O
83asCO
2OH-uCO
a>H
Pressure proof test Leakage Test
0.575
OF,
TIME
3.7.6 Field Installation Schedule
The shop fabrication and field installation schedule of the suppression tank is
shown in Table 3.7-1.
- 105 -
©
I
PURGE VALVE
PRESS.
TEST PLUG
DIVERTOR PORT
CRYOSTAT
^ 7A TANK TRUCK
'ALVE
-f LN2 J
G.L
PRESSURE GAUGEf—>
P
ia>osr
CD
tooto
PRESSURE TEST BOUNDARY
FIG. 3.7-1 SUPPRESSION TANK PRESSURE TEST
Table 3.7-1(1/2) SHOP FABRICATION & TRANSPORTATION SCHEDULE OF SUPPRESSION TANK
ITEM
1 SHOP MANUFACTURING
1) ANCHOR BOLTS
REOUIRED PERIOD (MONTH)1 2
—
3!
!
2) SUPPRESSION TANK(RELIEF PIPE PORTION)
I1 —3) SUPPRESSION TANK(GENERAL PORTION)
4) RUPTURE DISC
5) BELLOWS
6) RELIEF PIPE
7) PENETRATION BELLOWS
— j —1
k—
c =
-4-|
. 1
=--
- j -
1
.
8) 1NSPECT1ON(V1SUAL & DIMENSIONAL CHECK)
2 TRANSPORTATION(BARGE)
i!
I
I
]
|
j
4
\
V
ji
I
—
—
V i
1i
j
!
5
^=7-:
— • •
—
1i
6!
1
—
-_—
—,
I
71
:.—i-—
t-
V
j1
v i
8
i
|
i
i
9!
j
10
{
I I !
i-=.-4--.=
1-
i
i
12
. = —
...
j!11t
11i!i
j
i
13!
i!•;i
— i —
i
j
.iij
I
S•
i
!
si!
14
._ i •
]
I
15!
i
V
j
I
j
j
1
V
j
16;
i1
i
iiI
\
I
ii
ii!1
171
i
i
i
1
j
i
iI•
18;
I
ii|1i
1
i
i
1f!!
!1
j!
REMARKS
<£>
O
Table 3.7-1(2/2) SITE INSTALLATION SCHEDULE OF SUPPRESSION TANK
o00
ITEM
I PREPARATION
1) SITE OFFICE
2) ASSEMBLY FIELD
1 SITE CONSTRUCTION
1) ANCHOR BOLTS
REQUIRED PERIOD (MONTH)
•iIi
• i ^
f ,
21
!
I
. j :i
3j 4i
(GUARD)—
2) SUPPRESSION TANK(RELIEF PIPE PORTION)
II i3) SUPPRESSION TANK(GENERAL PORTION)
4) RUPTURE DISC
5) BELLOWS
6) RELIEF PIPE
7) PENETRATION BELLOWS
8) PNUMATICTEST
9) DIS-ASSEMBLY OF CONSTRUC
1 CLEARING
i
|
I
n —
!
TION JIG(SUPPORT ETC.)
1 :
!
1
5]
!
—
1
6
i
>
71
1
1
8
I
ji
i
9
) :1
(
,,
<
10 Hii
12!
|
]
131 14! 151
After initial assembly of divertor handling port
—2
i
!
•
!
it
j!
i
i
11|ii
!
1
;
i
f
|ii
ii
i
1ii
11 - 7
!
j
si1!
|
I!
!
161
i
i
17!
i
|
1ii!
iIi
!I
i
i
1i
1
18!
i
|
REMARKS
iCDO
IO
JAERI-Tech 99-026
3.8 Future works and R&D Activities
The detail design of tank structure and the fabrication / installation schedule is
performed.
The following items are considered for the further design study and R&D activities.
3.8.1 Suppression Tank
• Study of mechanical strength for the hydrodynamic load
•Detailed analysis of the tank head and penetrations
•Detail design of the penetrations such as manholes and drain pipes
• Study of possibility of the mid-basement-floor in the pit for tank
assembly/disassembly
3.8.2 Fabrication and Installation
• Study of the relief pipe gag retaining pressure in the divertor port
• Study of the field assembly equipment
•Study of detailed procedure of tank installation
• Study of temporary storage space of the tank after suppression tank disassembly
3.8.3 R&D•Development of rapture disk using prototype
• Development of remote handling equipment and device units for rapture disk
exchange
- 109 -
JAERI-Tech 99-026
4. Conclusions
4.1 Cryostat
(l)The detailed structural design considering the fabrication and the installation
was performed.
(2)The structural integrity has been assessed with the structural analysis by JCT.
However, when the mechanical strength was calculated by the formula of the
ASME B&PV Code Sec.VDI Div.2, the present cryostat design was not satisfied
with the required mechanical strength for external pressure. Therefore, in order to
satisfied the mechanical strength by design formula of ASME B&PV Code Sec.Vffl
Div.2, the altered stiffening ring has been proposed.
(3)The conceptual design of remote cutting and re-welding device units for the
upper cover, lower cover and RH port removal/attachment were performed. In
addition, the procedure of cutting and re-welding of each cover has been clarified.
(4)The procedure and schedule of shop fabrication, installation and testing of
cryostat are clarified.
(5)The future study and development items are listed.
4.2 Suppression Tank
(l)The detail structural design was performed considering the fabrication and the
site installation schedule.
(2)The mechanical strength for the internal and the external pressure were
assessed. The integrity of the suppression tank is verified. In addition, the
structure of bellows and rapture disk are determined.
(3)The procedure of tank assemble/disassemble are verified
(4)The procedure and schedule of shop fabrication, installation and testing were
studied.
(5)The future study and development items are listed.
Acknowledgement
The authors would like to express their sincere appreciation to Drs. M. Ohta, T.
Nagashima, S. Matsuda and Y. Seki for their continuous guidance and encouragement.
They also would like to acknowledge all of members who supported this work.
- no -
JAERI-Tech 99-026
Attachment
Cryostat and Suppression Tank Drawings
in -
This is a blank page.
o o
O
vert* covtn u^pri rott
OUTSIDE VIEW SECTIONAL VIEW
NOTE
ATTACH.1-1
m5=0i—ii
o
oto
CRYOSTAT PENETRATION LIST
art i«*r, «M *
{CASE I (MA/HAlt>
ATTACH. 1 - 2iffi CirOfTAT
TAIL1
P I
a>o3"
IO
JAERI-Tech 99-026
" \ %..1 <
\ . -
[| «> {"r r h {__
\ • [ • - - • - - • -
\ \ \ : :
_. ? . L . . J - .
3 ..... v:
[ ^sL. . | ! 1...1..
: ;it \: ' V.L..I::
"^ I' I '.1 • > ; { "
, , i , > ; ( "
"r I' I...1..-,.-..!.,
v s \ I..• ! . ! ' [ 1
i ' 1--
" f- • ' i i• ' J j T
L js ; i' • I J
w . . . . . . . . .
V «
- - l<*
H • ") - • u f
/'. S
- L ' f L
/"\ i tts. ' 8 *
S ' ' ~ * • i
' i >
s ' ' " s i
/ ^ - _ '
s J ' i •
- \ y I-,
' -I ':j . \ 3 f I
' ' " ) I, >. - 1
' 4
"• / " " " • •
' 4
j —
•
- 8
H i
o<
- 115 -
JAERI-Tech 99-026
Is
l •
- 116 -
JAERI-Tech 99-026
T
Oil f»»/ /
\ u
7
7.
i Z3 »
s-
- 117 -
JAERI-Tech 99-026
3 S
- 118 -
JAERI-Tech 99-026
» t 0 0 * ™ / 0 8 9
2 ;
111 1
— r ~ - - j — ;
0 0 0
i!
so
119 -
O
° Q ° Q ° Q ° Q O Q O Q ° Q O Q ° . L ) ° Qu-iB «• u*.u GVn w-ua u»Cu. w - u . u#?u> t*-.« *=fii VMB (X* ! * - . • 0»CDT IIP-B* tkcva uft-n* u^oa ina W*
A T T A C H . 1 - 8
KIV-FLAII
JAER1
trr)pa
IDO
toI
O
JAERI-Tech 99-026
- 121 -
o
Ioto
>CDP0
COo
totoIoto
JAERI-Tech 99-026
=i ?
• 2
so
124 -
JAERI-Tech 99-026
a
- 125 -
JAERI-Tech 99-026
>;
81Hll5
zo
- 126 -
JAERI-Tech 99-026
u
- 127 -
JAERI-Tech 99-026
X
f-
- 128 -
JAERI-Tech 99-026
1*9 "11 00 I »#
%
1 /i1 i
0 9 1
<
0 0 1
• 'OiC
"ot
?
0
"51
11 1
t 0 0 1
9 - g o t
lilt
"si
/
5 : ,
o a» M
<
- 129 -
JAERI-Tech 99-026
m
3
/
ml
©
\
' \
-
^ '
=
*
m
•
0 0 1
£ « 9 ' I ! 0 0 1 > *
171
: a
Ul
- 130 -
JAERI-Tech 99-026
: •
- 131 -
JAERI-Tech 99-026
o
I
X
- 132 -
JAERI-Tech 99-026
1*11 OCItl
09
ua
m.
- 133 -
JAERI-Tech 99-026
A
y
j
ET
AI
Q
O
1,3
, ^
Z*» 'I V k '9CE»
• ;
lUJi
- 134 -
JAERI-Tech 99-026
1x9 11 0»I»
- 135 -
JAERI-Tech 99-026
o
i'>
m
o >
e (Ia«••
>
•
: •
te
- 136 -
JAERI-Tech 99-026
II'
I! !!
<
- 137 -
K K L [ K F P I P !
0000
>m
- 3CDO
trID1X5
I
D E T A I L A D E T A I L B
A T T A C H . 1 - 2 31UU.
JAERI-Tech 99-026
,\
my
Xof-
- 139 -
JAERI-Tech 99-026
•Elsu
- 140 -
JAERI-Tech 99-026
o-H
coI
oott
ooc
'
I
-1—' •
1^ :
_t 1
V4SI
oooc
-
__-—-
= ^
±
^
99t
99SC
- 141 -
JAERI-Tech 99-026
a
-j
a
- 142 -
A T T A C H . 1 - 3 1ITEM.
i
O
JAERL•I - I
JAERI-Tech 99-026
0
3 =3 *
- 144 -
JAERI-Tech 99-026
'.. lUUWU"I l l
0 1 1 0 5 0 tC
i
HI
so
- 145 -
X
5 is
rnnJlillflflr! unfifififtL
i p; j o e I M _ aoo ei1
920-66
JAERI-Tech 99-026
\ «' \ ll
inn
if
IIIi
JJ L
lnnm
1383
3 1Si
LJLJL II J L U
nnnnn
: i
MI 3i «3 2i i
: 5
. t2 « it •> -
ILJUL II JUL
-Innnnn
D - l
innnnnm
|s nnnnnnn
- 147
00
I
BENCH HARK
TOR rORTION)
>
o
o
QROUND CONDITION BEFOR ASSEMBLY FIELD ASSEMBLY
A T T A C H . 1 - 3 6
JM-it
I LI
JAERI-Tech 99-026
ii
i
;
s
I
i
•ft
t
j
•
3
h
;
j
i
•
J
X1 I ft)
J
!
J
I
i
1
<>
i
* i I
•i
ISt
- 149 -
JAERI-Tech 99-026
- 150 -
JAERI-Tech 99-026
- 151 -
JAERI-Tech 99-026
19
is
\
i!
J
1
•
i
1
>11
i
t
Ja
i
s
•i}•
•it4
» '
«
3
ii
3ja
«
!1:#
i
t
s
c
1 <
i
i
•
i
!
1;ii
i
!
1;
2
1
3
11
j
i
1
1
i<•3;i
:s!3ti
i
t
»
i
It
1i1i
I
s
!j1
>
I
ii
i
ii•:Ss*tm
t
1 i2 i
- 9S %i
is6
9I
<li: 9
I
« •SI
s:i
- 152 -
'*• ©—0—O—0(TANK fc Bit. I I * PTPI T>
SUPPORT) Q y V
—
»
w
D f M « PTtOM
» « _ Ar. . - . . . - .
DtMstl** !*•*••>•••
r* i «»
M.r .1 . ,
" • • » • " * • • « — * — «* —
U1to
>CO
I
o
COtoI
o[S3
CO©
O
)—)OSfcrj
mitnanna jjtwnicu aue
nu \MWMOI
i n w n
XdId
IXXdIdU11
o.a
XIXdXIXdXIXIXI
HouwmvnJo <nuw
II DUII DU
CI DU01 DU6 DU1 DUI DUG DU
S DUS DUC DU» DUE OUI DUI DU(niMMJU
L "° t *!S B r l n ,
itntma
1 HJC U S +
"™*7f»Lnt
""* M*™"
-ivnum
ailMOLXCa + TBHS(Ni l JUIIS + THHS
win IVIJ + a\aais aaismUVId 'X3NKK) + 2\3TIS VIixvid 'ismto + »\aais in>
SMUS aaisxm + THISiwimiDNOi J\ans laism
ivnariLiwcn arasTs HISLTD
I V W V l D N l l d<&
D i l l dOL + 1T31B
iviavi DMawoucaDNia KU-DO + JH1)E * THIE
HT3H13 T 'IIN01 1*016
memo* "loioi TBIBiviiNajajMrauio THUS•WN i W I DdtCTIK
(DIE
<DIE
DIB<DIE
<DltS
d}IE
d»E.DIE
(naU/d3IB
<D1E
cna u / t D i B
<CIE
<nau/cDiE
<nau/j)iE
au (rnumimm
18
8dSd»dCdZiId
IS»SSS• S
CS!S15
TOWJU
a
n
oo
itHaincaa ONV SCTEM nvoidAi JO
(TIW (77IH J
(TOM dOW :
1H11 CTOM jfD HJf JV3 1J1A KKt 1
©
Q o l o n
t M KI dNIOr 41 H i
X
U HI IHIM TI1IJ
taaAOD iaddn aoi)
Ul
TYPES OF TYPICAL WELDS W D RH3UIREP EXAMINATION
MIDLE 1 OUHR COVEB RADIAL
CS SUffOHT WSffLATE RADIAL
FLEC RlNOB>SEPLATE»g)TT RINO
FLEX. RINQ LOMITUD1NM.
H.EL RINa-SUT COWECT. BIN]
SIDE H A l E + a . I T CdtlFCT. BMQ
BIB + MIHILE & OUUR COVER
PI^UODID mBlAHTUI»U.TMfOHC
(OUTSIDE VIEW (INSIDE VIEW nag rent, M U K W I
A T T A C H . 1 - 4 3
DET. BOTTOM RINO
HHI
CDO3 "
<£>( O
Ioto
1
HELD WELD
•YPES
SIS2S3S4SSS6S7S8S»SWSllSBSUSHSISSHSI7SURlR2
OF TYPIC
SKF/TIELDSKF/HEIDSICPEHCP
aicpaicpaicp310?aicpaicp/nEU)FIELD
3ICP/FIEU)
FIELD
SICP
3ICP/FI ELD
31CP
31CP/FIEU>
FIELD PIT)
ato?310?
A L WELDS <«ND REQUIRED
K 1 0 U T . ODVER KADlALaMBCUM
OUTER COVER RADIAL
CENTEH OPEN, 1NSEKT t IN PLATE
N C R COVER •> SIDE PLATE
INSIDE PLATE LCNaiTUDINA.
OUTSIDE PLATE LONOITLDINU,
CUTSIDUa.ITtFLEXRINO CIRCLIV
FLEXIBLE RIN) LONOITLDINU,
OUTER COVER + INSIDE PLATE
INSIDE PLATE LOXamiDINAL
INSIDE PLATE + FLEXIBLE RIN3
FLEXIBLE Rira LONOITIDINU,
SLTT CONNECT RINO+ FLEXRDW
OUTER COVER + OUTER SHELL
CUTER SHELL LONGITUDINAL
OUTER SHELL CIHCLKFEIGNT1AL
OUTER SHELL L0N3I1UDINAL
OUTER SHELL^CYUNDER TOP RINQ
INNER COVER + RIB
CUTER COVER + RIB
EXMlltiA
-mtm
suaautLf |ufl 3D4 1* SUS 304 1
V SU1 304 1SUS3 04L
^ SUfl 304 L
* SUt 304 I
* S M 3 0 4 1
* m» 304 1
""I'jni 3041* Alt 304 1.
*"J"jjn 3041
+ 9111 304 1
. Jj»304L
* HJS304I
TION
na Ina 2na 3na 4na sna 2na ana <na 7na ana Ina Ina ana 10na 2na nna lina 12na isn a 14
RTRTPTPTRTRTRTRTPTRTRTRTUTPTRTRTRTPTPTPT
INNER COVCB
INNER COVER
INNER COVER
INNER COVER
CUTER COVER
OUTER COVER
'MOMvajtruu:wru op UWIHATKH
rp-uou» mtEnuMr nuNuuriai
3
I
CD
n
lots5
BELIEF PIPE PORTION) (DISTRIBUTOR PORTION)
TYPES OF TYPICAL WELDS Mill REQUIRED EXAMINATION
SYkSOL
SI
saS3
s<
sss«
S7S8
PI
P2
P3
Al
A2
A3
A4
U> CATION
3ltP
SIQVTIEU
SKP
ai<p
ai<p
aitp
aiavnEioSOP
3IIP
aiip
aicp
aicp
aicp
a<a>
WUUNO rMET WM
1 M IDNOlTtDimL
V N ( aBOMFEBBTTIAL
TAW aROftOERB^TIAL EDCE)
7ANC + PSVETEAHON I^BERr
DISTRffiUXR LONJ11UDINAL
REUEF PIPE LONJ11UD1NAL
DISTRBinOR + RELIEr PIFK
DISTRBUTOH CUCUFEIEN'nAL
FEfeTMTlON IXW3IHJDJNHL
PENETRATION + INSBtT
CH»N PIPE + DISTRIBUTOR
STIFFMIKl UNO + TANI
HEUEF PIPE SUffORT BUI t TANKaJIPOBT PAD + TANK
WSTRBUTOR SUPPORT + STIKFENINO RINQ
MTBU AL
• auiaflij
t snutL
* ma4>L
. sinioti
t SVSlfiiL
•tuK"""'t MUiL
Tyrt
HO 1
na 1na tno Ina 2na ina 3na :na ina 4na sna sna T
na 7na 8
Mum or•XAMIUnOII
KT
' HT
BT
BT
BT
BT
PT
BT
BT
PT
PT
PT
PT
PT
PT
n o MM cur (Ml: wr KD or vuI R1>-UIDI0(MAniV StAMHAI
L ILLIQUID miiMn nu
UMMKI
f'l
1171 . K
6ECTICNAL V i a *
s0 .1
50I-HI
fDO3 *
O
to
ATTACH. 1 - 4 6ITEJS
lurr»lllio< Tin
JAERI-Tech 99-026
s
V.
I
— I
- T - LE
B
LO
CK
•o
«
o
Uy
b l
- 158 -
IB lift m (SI) t
MS
m.
tr.
ft
»fin
mK m
IS
ifi ft
(* ft
*
7
y
7
-
P ^
y
y
XT 7
I-
' 7
t*
X
7
? T
A
Ty
7
y
y
Id %
m
kgs
A
K
mol
cd
rad
s r
* 3
i±
i
w.
a$
ti , It-
. ^ + ' - <±^, *% , » W
a » , «SI*
ttA-b
T£88
»
'€ SSI ffi
y 9" 9 9 y
y ¥ 9 9 yIV •> V 7. S
WiR ^
i; S
a^i
•*•
nn.tn.X
$
ISX
IS
m
7?
*'
7
-b
/ I /
; i /
-s:
f
* *
X Jl
j -
-j
— D
-
— ^ y
i -
X
v U
^ i"> X
- -<IV
•y
y
y
^
KA
X
/ <
7
-
ISy
X
-(
tmHz
N
Pa
J
W
C
V
F
ns
Wb
T
H
°Clm
lx
Bq
GySv
a-
m-kg/s2
N/m2
N-m
J / s
A-s
W/A
C/V
V/A
A/V
V-s
Wb/m2
Wb/A
cd-sr
lm/m2
s "
J/kg
J/kg
'J
n
•j h
i1 * i
H
IV
y
v b
i a <?;
min, h, d
1, L
t
eV
u
eV = 1.60218xl0-|9J
u=1.66054x 10-27kg
^- y ?"x t- p - A
>•< - y
/N' ^ IV
t' iv
u- y h y y
7 K
U- A
ia *tA
b
bar
Gal
Ci
R
rad
r e m
1 b=100fm2=10-2!m2
1 bar=0.1MPa=10sPa
lGal=lcm/s2 = 10-2rn/s2
lCi=3.7xlO"'Bq
1 R=2.58xlO-'C/kg
1 rad = lcGy=102Gy
1 rem=lcSv=10 2Sv
3R5
10"
10"
1012
10'
10'
103
102
10'
10"'
io-2
io-3
10"'
io-9
io- ' !
io -"
10—
X
- :
7~
4:
/
+
X
•f'
-7
T
t°
7
T
sMtS
s>7
ii'
aa
9 Yi]
•y
y -f
ni 9 •
/
1 A (-
ia ^Ep
T
G
M
k
h
da
d
c
m
/i
n
Pf
a
(a)
uO«l± CODATA O1986^t|
3. barli,
r, barnfcj;
N(=10sdyn)
1
9.80665
4.44822
kgf
0.101972
1
0.453592
Ibf
0.224809
2.20462
1
1 Pa - s (N-s /m 2 )=10P(*TX)(g / ( cm-s ) )
It
tl
MPa( = 10bar)
1
0.0980665
0.101325
1.33322 x 10' '
6.89476 x 10"3
kgf/cm2
10.1972
1
1.03323
1.35951 x 10"3
7.03070 x 10'2
a tm
9.86923
0.967841
1
1.31579x10"'
6.80460 x 10- '<
mmHg(Torr)
7.50062 x 103
735.559
760
1
51.7149
Ibf/in2(psi)
145.038
14.2233
14.6959
1.93368 x 10'2
1
+'1
tt
7
J ( = 10'erg)
1
9.80665
3.6x10'
4.18605
1055.06
1.35582
1.60218 x 10""
kgf*m
0.101972
1
3.67098 x 10 s
0.426858
107.586
0.138255
1.63377 x 10-™
kW- h
2.77778x10-'
2.72407 x 1 0 '
1
1.16279 x 10-'
2.93072x10'
3.76616 x 10-'
4.45050 xlO-2 s
calClt«*fc)
0.238889
2.34270
8.59999x10'
1
252.042
0.323890
3.82743 x 10"M
Btu
9 . 4 7 8 1 3 x 1 0 '
9.29487 x 1 0 3
3412.13
3.96759x10- '
1
1.28506 x lO" 1
1 . 5 1 8 5 7 x 1 0 "
ft • lbf
0.737562
7.23301
2.65522 x 10'
3.08747
778.172
1
1.18171 x 1 0 ' "
eV
6.24150 x lO 1 8
6.12082x10"
2 .24694x10"
2 .61272x10"
6.58515 x ! O n
8.46233 x 1 0 "
1
1 cal = 4.18605 JCft
= 4.184J
= 4.1855 J (15 °C)
* I P S
= 75 kgf-m/s
= 735.499 W
ft Bq
1
3.7 x 10'°
Ci
2.70270 x 10-"
1
Gy
1
0.01
rad
100
1
C/kg
2.58 x 10-
3876
1
1
0.01
100
1
(86 ip 12/3 26
ITER CRYOSTAT MAIN CHAMBER AND VACUUM VESSEL PRESSURE SUPPRESSION SYSTEM DESIGNa I'