izmit bay bridge - brodag izmit.pdf · agenda 1 april 2014 2 dansk brodag izmit bay bridge ›...
TRANSCRIPT
![Page 1: IZMIT BAY BRIDGE - Brodag IZMIT.pdf · Agenda 1 APRIL 2014 2 DANSK BRODAG IZMIT BAY BRIDGE › Introduction to the project › General layout › Seismic › Substructure Design/Construction](https://reader030.vdocuments.net/reader030/viewer/2022021423/5a9d7cdd7f8b9a21688b972d/html5/thumbnails/1.jpg)
IZMIT BAY BRIDGE
BRIDGES EUROPE1
Kent J. Fuglsang
COWI
![Page 2: IZMIT BAY BRIDGE - Brodag IZMIT.pdf · Agenda 1 APRIL 2014 2 DANSK BRODAG IZMIT BAY BRIDGE › Introduction to the project › General layout › Seismic › Substructure Design/Construction](https://reader030.vdocuments.net/reader030/viewer/2022021423/5a9d7cdd7f8b9a21688b972d/html5/thumbnails/2.jpg)
Agenda
1 APRIL 2014
DANSK BRODAG2
IZMIT BAY BRIDGE
› Introduction to the project› General layout› Seismic› Substructure Design/Construction
› Tower foundations› South Anchor Block› North Anchor Block
![Page 3: IZMIT BAY BRIDGE - Brodag IZMIT.pdf · Agenda 1 APRIL 2014 2 DANSK BRODAG IZMIT BAY BRIDGE › Introduction to the project › General layout › Seismic › Substructure Design/Construction](https://reader030.vdocuments.net/reader030/viewer/2022021423/5a9d7cdd7f8b9a21688b972d/html5/thumbnails/3.jpg)
5 MARCH 2013
DANSK BRODAG3
GeneralIZMIT BAY BRIDGE
› Bridge site location approx. 50 kilometers East of Istanbul
› First phase of major infra-structure project in Turkey. New highway from Gebze to Izmir.
› BOT project, approx. $11 billion const. const
1 APRIL 2014
![Page 4: IZMIT BAY BRIDGE - Brodag IZMIT.pdf · Agenda 1 APRIL 2014 2 DANSK BRODAG IZMIT BAY BRIDGE › Introduction to the project › General layout › Seismic › Substructure Design/Construction](https://reader030.vdocuments.net/reader030/viewer/2022021423/5a9d7cdd7f8b9a21688b972d/html5/thumbnails/4.jpg)
› Invitation to Tender May 2010 – Design & Build
› Tender conditions – Suspension bridge- Main span 1550 – 1700m- Total length 3km
› Tender submission September 2010› Three bidding contractor groups –
Japan(IHI), China, Korea, › IHI announced preferred bidder Jan 2011› Contract negotiations Jan–Sep 2011› Bridge construction cost approx. $1.2 billion› Detailed design start Sep 2011› Preparatory Site Works started Sep 2012› Permanent Site Works started Jan 2013› Bridge completion early 2016
1 APRIL 2014
DANSK BRODAG4
Project dates summaryIZMIT BAY BRIDGE
![Page 5: IZMIT BAY BRIDGE - Brodag IZMIT.pdf · Agenda 1 APRIL 2014 2 DANSK BRODAG IZMIT BAY BRIDGE › Introduction to the project › General layout › Seismic › Substructure Design/Construction](https://reader030.vdocuments.net/reader030/viewer/2022021423/5a9d7cdd7f8b9a21688b972d/html5/thumbnails/5.jpg)
› Concrete Anchor Blocks and Tower Foundations› Tower Foundations at approx. 40 m water depth› Navigational clearance profile 64x1000m› South Piers supported on South Anchor Block (Integrated structure) › Steel towers 250m high
General layout
1 APRIL 2014
DANSK BETONDAG5
IZMIT BAY BRIDGE
![Page 6: IZMIT BAY BRIDGE - Brodag IZMIT.pdf · Agenda 1 APRIL 2014 2 DANSK BRODAG IZMIT BAY BRIDGE › Introduction to the project › General layout › Seismic › Substructure Design/Construction](https://reader030.vdocuments.net/reader030/viewer/2022021423/5a9d7cdd7f8b9a21688b972d/html5/thumbnails/6.jpg)
› Orthotropic steel deck – dehumidified› 3 traffic lanes each direction› 14mm deck plate and 60mm surfacing
General arrangement - Bridge deck
1 APRIL 2014
DANSK BRODAG6
IZMIT BAY BRIDGE
![Page 7: IZMIT BAY BRIDGE - Brodag IZMIT.pdf · Agenda 1 APRIL 2014 2 DANSK BRODAG IZMIT BAY BRIDGE › Introduction to the project › General layout › Seismic › Substructure Design/Construction](https://reader030.vdocuments.net/reader030/viewer/2022021423/5a9d7cdd7f8b9a21688b972d/html5/thumbnails/7.jpg)
› Steel towers / low weight / increased flexibility / fast construction
› Seismic load combinations and normal ULS combinations are more or less equal in governing the tower design
› Constructed by prefabricated elements – 22 blocks
› Horizontal joints by combined welding and bolting
General arrangement - Towers
1 APRIL 2014
DANSK BRODAG7
IZMIT BAY BRIDGE
![Page 8: IZMIT BAY BRIDGE - Brodag IZMIT.pdf · Agenda 1 APRIL 2014 2 DANSK BRODAG IZMIT BAY BRIDGE › Introduction to the project › General layout › Seismic › Substructure Design/Construction](https://reader030.vdocuments.net/reader030/viewer/2022021423/5a9d7cdd7f8b9a21688b972d/html5/thumbnails/8.jpg)
Tower erection
1 APRIL 2014
DANSK BRODAG8
IZMIT BAY BRIDGE
Panel erectionBlock no. 12-22Tower crane, 40t
Block erectionBlock no. 1-11Floating crane, 300t
Bolt friction connection in stiffeners
![Page 9: IZMIT BAY BRIDGE - Brodag IZMIT.pdf · Agenda 1 APRIL 2014 2 DANSK BRODAG IZMIT BAY BRIDGE › Introduction to the project › General layout › Seismic › Substructure Design/Construction](https://reader030.vdocuments.net/reader030/viewer/2022021423/5a9d7cdd7f8b9a21688b972d/html5/thumbnails/9.jpg)
› Sag-to-span-ratio 1:9 › Prefabricated strands› 110 strands each with 127 nos. 5.91 mm diameter wires, 1760 MPa› 781 mm diameter
General arrangement – Main Cables
1 APRIL 2014
DANSK BRODAG9
IZMIT BAY BRIDGE
![Page 10: IZMIT BAY BRIDGE - Brodag IZMIT.pdf · Agenda 1 APRIL 2014 2 DANSK BRODAG IZMIT BAY BRIDGE › Introduction to the project › General layout › Seismic › Substructure Design/Construction](https://reader030.vdocuments.net/reader030/viewer/2022021423/5a9d7cdd7f8b9a21688b972d/html5/thumbnails/10.jpg)
› Progression of 20th Century EQs along the NAF
› 1999 EQsSurface Ruptures Map
› Gölcük 1999 EQ– 7.5 magnitude
› Izmit Site
High Seismic Activity
1 APRIL 2014
DANSK BRODAG10
IZMIT BAY BRIDGE
![Page 11: IZMIT BAY BRIDGE - Brodag IZMIT.pdf · Agenda 1 APRIL 2014 2 DANSK BRODAG IZMIT BAY BRIDGE › Introduction to the project › General layout › Seismic › Substructure Design/Construction](https://reader030.vdocuments.net/reader030/viewer/2022021423/5a9d7cdd7f8b9a21688b972d/html5/thumbnails/11.jpg)
› Reinforced soil with steel inclusion piles (~200 nos. ø2m dia.)
› Gravel bed (3m thick) allowing caisson to slide during earthquake
› Pre-fabricated caisson (54x68x15m)
› Composite steel/concrete shafts (16m dia., t = 1.2m) with high robustness against ship impact
› Solid plinths with anchor bolts for fixing of the steel tower
General arrangement - Tower foundations
1 APRIL 2014
DANSK BRODAG11
IZMIT BAY BRIDGE
![Page 12: IZMIT BAY BRIDGE - Brodag IZMIT.pdf · Agenda 1 APRIL 2014 2 DANSK BRODAG IZMIT BAY BRIDGE › Introduction to the project › General layout › Seismic › Substructure Design/Construction](https://reader030.vdocuments.net/reader030/viewer/2022021423/5a9d7cdd7f8b9a21688b972d/html5/thumbnails/12.jpg)
› Dry dock stage – Part of the caisson structure is constructed in a purpose built dry dock with a limited depth of approximately 7.5 m.
Construction stages- Tower foundations – Dry dock
1 APRIL 2014
DANSK BRODAG12
IZMIT BAY BRIDGE
![Page 13: IZMIT BAY BRIDGE - Brodag IZMIT.pdf · Agenda 1 APRIL 2014 2 DANSK BRODAG IZMIT BAY BRIDGE › Introduction to the project › General layout › Seismic › Substructure Design/Construction](https://reader030.vdocuments.net/reader030/viewer/2022021423/5a9d7cdd7f8b9a21688b972d/html5/thumbnails/13.jpg)
Tower foundation construction – Dry dock
1 APRIL 2014
DANSK BRODAG13
IZMIT BAY BRIDGE
![Page 14: IZMIT BAY BRIDGE - Brodag IZMIT.pdf · Agenda 1 APRIL 2014 2 DANSK BRODAG IZMIT BAY BRIDGE › Introduction to the project › General layout › Seismic › Substructure Design/Construction](https://reader030.vdocuments.net/reader030/viewer/2022021423/5a9d7cdd7f8b9a21688b972d/html5/thumbnails/14.jpg)
Tower foundation construction – Dry dock
1 APRIL 2014
DANSK BRODAG14
IZMIT BAY BRIDGE
![Page 15: IZMIT BAY BRIDGE - Brodag IZMIT.pdf · Agenda 1 APRIL 2014 2 DANSK BRODAG IZMIT BAY BRIDGE › Introduction to the project › General layout › Seismic › Substructure Design/Construction](https://reader030.vdocuments.net/reader030/viewer/2022021423/5a9d7cdd7f8b9a21688b972d/html5/thumbnails/15.jpg)
Wet dock stage - The caisson is towed out of dry dock and the remaining part of the caisson as well as the steel shafts are completed in a wet dock in floating condition at an intermediate site with a minimum water depth of 15 m. The prefabricated steel shaft is lifted by cranes and placed on temporary support.
Construction stages- Tower foundations – Wet dock
1 APRIL 2014
DANSK BRODAG15
IZMIT BAY BRIDGE
![Page 16: IZMIT BAY BRIDGE - Brodag IZMIT.pdf · Agenda 1 APRIL 2014 2 DANSK BRODAG IZMIT BAY BRIDGE › Introduction to the project › General layout › Seismic › Substructure Design/Construction](https://reader030.vdocuments.net/reader030/viewer/2022021423/5a9d7cdd7f8b9a21688b972d/html5/thumbnails/16.jpg)
Dry Dock – Tower Foundations
1 APRIL 2014
DANSK BRODAG16
IZMIT BAY BRIDGE
![Page 17: IZMIT BAY BRIDGE - Brodag IZMIT.pdf · Agenda 1 APRIL 2014 2 DANSK BRODAG IZMIT BAY BRIDGE › Introduction to the project › General layout › Seismic › Substructure Design/Construction](https://reader030.vdocuments.net/reader030/viewer/2022021423/5a9d7cdd7f8b9a21688b972d/html5/thumbnails/17.jpg)
Tower foundation construction
1 APRIL 2014
DANSK BRODAG17
IZMIT BAY BRIDGE
![Page 18: IZMIT BAY BRIDGE - Brodag IZMIT.pdf · Agenda 1 APRIL 2014 2 DANSK BRODAG IZMIT BAY BRIDGE › Introduction to the project › General layout › Seismic › Substructure Design/Construction](https://reader030.vdocuments.net/reader030/viewer/2022021423/5a9d7cdd7f8b9a21688b972d/html5/thumbnails/18.jpg)
Tower foundation construction – End September 2013
1 APRIL 2014
DANSK BRODAG18
IZMIT BAY BRIDGE
![Page 19: IZMIT BAY BRIDGE - Brodag IZMIT.pdf · Agenda 1 APRIL 2014 2 DANSK BRODAG IZMIT BAY BRIDGE › Introduction to the project › General layout › Seismic › Substructure Design/Construction](https://reader030.vdocuments.net/reader030/viewer/2022021423/5a9d7cdd7f8b9a21688b972d/html5/thumbnails/19.jpg)
Tower foundation construction
1 APRIL 2014
DANSK BRODAG19
IZMIT BAY BRIDGE
![Page 20: IZMIT BAY BRIDGE - Brodag IZMIT.pdf · Agenda 1 APRIL 2014 2 DANSK BRODAG IZMIT BAY BRIDGE › Introduction to the project › General layout › Seismic › Substructure Design/Construction](https://reader030.vdocuments.net/reader030/viewer/2022021423/5a9d7cdd7f8b9a21688b972d/html5/thumbnails/20.jpg)
Tower foundation construction – Steel shaft installation
1 APRIL 2014
DANSK BRODAG20
IZMIT BAY BRIDGE
![Page 21: IZMIT BAY BRIDGE - Brodag IZMIT.pdf · Agenda 1 APRIL 2014 2 DANSK BRODAG IZMIT BAY BRIDGE › Introduction to the project › General layout › Seismic › Substructure Design/Construction](https://reader030.vdocuments.net/reader030/viewer/2022021423/5a9d7cdd7f8b9a21688b972d/html5/thumbnails/21.jpg)
Tower foundation construction – Pile installation
1 APRIL 2014
DANSK BRODAG21
IZMIT BAY BRIDGE
![Page 22: IZMIT BAY BRIDGE - Brodag IZMIT.pdf · Agenda 1 APRIL 2014 2 DANSK BRODAG IZMIT BAY BRIDGE › Introduction to the project › General layout › Seismic › Substructure Design/Construction](https://reader030.vdocuments.net/reader030/viewer/2022021423/5a9d7cdd7f8b9a21688b972d/html5/thumbnails/22.jpg)
Tower foundation construction – Gravel bed placing
1 APRIL 2014
DANSK BRODAG22
IZMIT BAY BRIDGE
![Page 23: IZMIT BAY BRIDGE - Brodag IZMIT.pdf · Agenda 1 APRIL 2014 2 DANSK BRODAG IZMIT BAY BRIDGE › Introduction to the project › General layout › Seismic › Substructure Design/Construction](https://reader030.vdocuments.net/reader030/viewer/2022021423/5a9d7cdd7f8b9a21688b972d/html5/thumbnails/23.jpg)
› Immersion of the tower foundation by ballasting - Tower foundation is lowered into its final position by filling the caisson cells with ballast water.
› It is noted that in order to maintain floating stability of the caisson in the stage where the main body gets immersed the caisson is tilted about 10 degrees.
› The infill concrete in the shafts from level -21 m to -1 m is cast after the structure has been immersed.
Construction stages- Tower foundations - Immersion
1 APRIL 2014
DANSK BRODAG23
IZMIT BAY BRIDGE
![Page 24: IZMIT BAY BRIDGE - Brodag IZMIT.pdf · Agenda 1 APRIL 2014 2 DANSK BRODAG IZMIT BAY BRIDGE › Introduction to the project › General layout › Seismic › Substructure Design/Construction](https://reader030.vdocuments.net/reader030/viewer/2022021423/5a9d7cdd7f8b9a21688b972d/html5/thumbnails/24.jpg)
Wet Dock – Tower Foundations
1 APRIL 2014
DANSK BRODAG24
IZMIT BAY BRIDGE
![Page 25: IZMIT BAY BRIDGE - Brodag IZMIT.pdf · Agenda 1 APRIL 2014 2 DANSK BRODAG IZMIT BAY BRIDGE › Introduction to the project › General layout › Seismic › Substructure Design/Construction](https://reader030.vdocuments.net/reader030/viewer/2022021423/5a9d7cdd7f8b9a21688b972d/html5/thumbnails/25.jpg)
Wet Dock – South Tower Foundation
1 APRIL 2014
DANSK BRODAG25
IZMIT BAY BRIDGE
![Page 26: IZMIT BAY BRIDGE - Brodag IZMIT.pdf · Agenda 1 APRIL 2014 2 DANSK BRODAG IZMIT BAY BRIDGE › Introduction to the project › General layout › Seismic › Substructure Design/Construction](https://reader030.vdocuments.net/reader030/viewer/2022021423/5a9d7cdd7f8b9a21688b972d/html5/thumbnails/26.jpg)
Tow out – North Tower Foundation
1 APRIL 2014
DANSK BRODAG26
IZMIT BAY BRIDGE
![Page 27: IZMIT BAY BRIDGE - Brodag IZMIT.pdf · Agenda 1 APRIL 2014 2 DANSK BRODAG IZMIT BAY BRIDGE › Introduction to the project › General layout › Seismic › Substructure Design/Construction](https://reader030.vdocuments.net/reader030/viewer/2022021423/5a9d7cdd7f8b9a21688b972d/html5/thumbnails/27.jpg)
Immersion – North Tower Foundation
1 APRIL 2014
DANSK BRODAG27
IZMIT BAY BRIDGE
![Page 28: IZMIT BAY BRIDGE - Brodag IZMIT.pdf · Agenda 1 APRIL 2014 2 DANSK BRODAG IZMIT BAY BRIDGE › Introduction to the project › General layout › Seismic › Substructure Design/Construction](https://reader030.vdocuments.net/reader030/viewer/2022021423/5a9d7cdd7f8b9a21688b972d/html5/thumbnails/28.jpg)
Immersion – North Tower Foundation
1 APRIL 2014
DANSK BRODAG28
IZMIT BAY BRIDGE
![Page 29: IZMIT BAY BRIDGE - Brodag IZMIT.pdf · Agenda 1 APRIL 2014 2 DANSK BRODAG IZMIT BAY BRIDGE › Introduction to the project › General layout › Seismic › Substructure Design/Construction](https://reader030.vdocuments.net/reader030/viewer/2022021423/5a9d7cdd7f8b9a21688b972d/html5/thumbnails/29.jpg)
Final position – North Tower Foundation
1 APRIL 2014
DANSK BRODAG29
IZMIT BAY BRIDGE
![Page 30: IZMIT BAY BRIDGE - Brodag IZMIT.pdf · Agenda 1 APRIL 2014 2 DANSK BRODAG IZMIT BAY BRIDGE › Introduction to the project › General layout › Seismic › Substructure Design/Construction](https://reader030.vdocuments.net/reader030/viewer/2022021423/5a9d7cdd7f8b9a21688b972d/html5/thumbnails/30.jpg)
› Gravity based solution founded on dense sand› Foundation massif 124x58x16m› Guitar shape to provide additional stability of excavation
General arrangement – South Anchor Block
1 APRIL 2014
DANSK BRODAG30
IZMIT BAY BRIDGE
![Page 31: IZMIT BAY BRIDGE - Brodag IZMIT.pdf · Agenda 1 APRIL 2014 2 DANSK BRODAG IZMIT BAY BRIDGE › Introduction to the project › General layout › Seismic › Substructure Design/Construction](https://reader030.vdocuments.net/reader030/viewer/2022021423/5a9d7cdd7f8b9a21688b972d/html5/thumbnails/31.jpg)
South Anchor Block Excavation
1 APRIL 2014
DANSK BRODAG31
IZMIT BAY BRIDGE
Design circular part- Uniform water-pressures and soil-pressures- Hoop structure, i.e. all panels in tangential compression- No vertical distribution of forces in D-wall panels- Compression transferred to junctions- Reinforcement in D-wall panels 75 kg/m3
![Page 32: IZMIT BAY BRIDGE - Brodag IZMIT.pdf · Agenda 1 APRIL 2014 2 DANSK BRODAG IZMIT BAY BRIDGE › Introduction to the project › General layout › Seismic › Substructure Design/Construction](https://reader030.vdocuments.net/reader030/viewer/2022021423/5a9d7cdd7f8b9a21688b972d/html5/thumbnails/32.jpg)
South Anchor Block – D-wall panel reinforcement
1 APRIL 2014
DANSK BRODAG32
IZMIT BAY BRIDGE
![Page 33: IZMIT BAY BRIDGE - Brodag IZMIT.pdf · Agenda 1 APRIL 2014 2 DANSK BRODAG IZMIT BAY BRIDGE › Introduction to the project › General layout › Seismic › Substructure Design/Construction](https://reader030.vdocuments.net/reader030/viewer/2022021423/5a9d7cdd7f8b9a21688b972d/html5/thumbnails/33.jpg)
Technical details for guitar shaped excavation; › Diaphragm wall (all); thickness 1.0m, top level +1.5m, toe level -32.0m, length 33.5m › Excavation level -15.0m, Platform level +1.5m, depth 16.5m› Watertightness at base of the excavation achieved by 10m thick clay layer, underlaid by
sand› Construction time for D-wall and excavation: 6month
1 APRIL 2014
DANSK BRODAG33
South Anchor Block ExcavationIZMIT BAY BRIDGE
![Page 34: IZMIT BAY BRIDGE - Brodag IZMIT.pdf · Agenda 1 APRIL 2014 2 DANSK BRODAG IZMIT BAY BRIDGE › Introduction to the project › General layout › Seismic › Substructure Design/Construction](https://reader030.vdocuments.net/reader030/viewer/2022021423/5a9d7cdd7f8b9a21688b972d/html5/thumbnails/34.jpg)
South Anchor Block Excavation
1 APRIL 2014
DANSK BRODAG34
IZMIT BAY BRIDGE
![Page 35: IZMIT BAY BRIDGE - Brodag IZMIT.pdf · Agenda 1 APRIL 2014 2 DANSK BRODAG IZMIT BAY BRIDGE › Introduction to the project › General layout › Seismic › Substructure Design/Construction](https://reader030.vdocuments.net/reader030/viewer/2022021423/5a9d7cdd7f8b9a21688b972d/html5/thumbnails/35.jpg)
South Anchor Block Construction
1 APRIL 2014
DANSK BRODAG35
IZMIT BAY BRIDGE
![Page 36: IZMIT BAY BRIDGE - Brodag IZMIT.pdf · Agenda 1 APRIL 2014 2 DANSK BRODAG IZMIT BAY BRIDGE › Introduction to the project › General layout › Seismic › Substructure Design/Construction](https://reader030.vdocuments.net/reader030/viewer/2022021423/5a9d7cdd7f8b9a21688b972d/html5/thumbnails/36.jpg)
Progress– South Anchor Block
1 APRIL 2014
DANSK BRODAG36
IZMIT BAY BRIDGE
![Page 37: IZMIT BAY BRIDGE - Brodag IZMIT.pdf · Agenda 1 APRIL 2014 2 DANSK BRODAG IZMIT BAY BRIDGE › Introduction to the project › General layout › Seismic › Substructure Design/Construction](https://reader030.vdocuments.net/reader030/viewer/2022021423/5a9d7cdd7f8b9a21688b972d/html5/thumbnails/37.jpg)
General arrangement – South Anchor Block
1 APRIL 2014
DANSK BRODAG37
IZMIT BAY BRIDGE
![Page 38: IZMIT BAY BRIDGE - Brodag IZMIT.pdf · Agenda 1 APRIL 2014 2 DANSK BRODAG IZMIT BAY BRIDGE › Introduction to the project › General layout › Seismic › Substructure Design/Construction](https://reader030.vdocuments.net/reader030/viewer/2022021423/5a9d7cdd7f8b9a21688b972d/html5/thumbnails/38.jpg)
› Typical gravity based structure deeply embedded in rock - Foundation massif 50x66x22m
General arrangement – North Anchor Block
1 APRIL 2014
DANSK BRODAG38
IZMIT BAY BRIDGE
![Page 39: IZMIT BAY BRIDGE - Brodag IZMIT.pdf · Agenda 1 APRIL 2014 2 DANSK BRODAG IZMIT BAY BRIDGE › Introduction to the project › General layout › Seismic › Substructure Design/Construction](https://reader030.vdocuments.net/reader030/viewer/2022021423/5a9d7cdd7f8b9a21688b972d/html5/thumbnails/39.jpg)
North Anchor Block construction
1 APRIL 2014
DANSK BRODAG39
IZMIT BAY BRIDGE
![Page 40: IZMIT BAY BRIDGE - Brodag IZMIT.pdf · Agenda 1 APRIL 2014 2 DANSK BRODAG IZMIT BAY BRIDGE › Introduction to the project › General layout › Seismic › Substructure Design/Construction](https://reader030.vdocuments.net/reader030/viewer/2022021423/5a9d7cdd7f8b9a21688b972d/html5/thumbnails/40.jpg)
Progress– North Anchor Block
1 APRIL 2014
DANSK BRODAG40
IZMIT BAY BRIDGE
![Page 41: IZMIT BAY BRIDGE - Brodag IZMIT.pdf · Agenda 1 APRIL 2014 2 DANSK BRODAG IZMIT BAY BRIDGE › Introduction to the project › General layout › Seismic › Substructure Design/Construction](https://reader030.vdocuments.net/reader030/viewer/2022021423/5a9d7cdd7f8b9a21688b972d/html5/thumbnails/41.jpg)
Summary of Main Quantities
1 APRIL 2014
DANSK BRODAG41
IZMIT BAY BRIDGE
Structure Material Unit Quantity
Anchor blocks Concrete m3 130000
Tower foundations Concrete m3 45000
Steel inclusions Steel ton 16000
Towers Steel ton 17000
Main cable Steel ton 18000
Bridge deck Steel ton 33000
![Page 42: IZMIT BAY BRIDGE - Brodag IZMIT.pdf · Agenda 1 APRIL 2014 2 DANSK BRODAG IZMIT BAY BRIDGE › Introduction to the project › General layout › Seismic › Substructure Design/Construction](https://reader030.vdocuments.net/reader030/viewer/2022021423/5a9d7cdd7f8b9a21688b972d/html5/thumbnails/42.jpg)
Questions?
19 SEPTEMBER 2013
DANSK BRODAG42
IZMIT BAY BRIDGE COWI