janapriya engineers syndicate pvt....

81
Janapriya Engineers Syndicate Pvt. Ltd. SURVEY NOS. 663(P), 668(P) AND 671(P), KAPRA, MEDCHAL - MALKAJGIRI DISTRICT 1. CONCEPTUAL PLAN 2. EMP report RESIDENTIAL CONSTRUCTION PROJECT Submitted By M/s Janapriya Engineers Syndicate Pvt. Ltd., D. No. 8-2-120/86/1, Keerthi & Pride Towers, Road No.2, Banjara Hills, Hyderabad-500 034 Studies & Documented By M/s Team Labs and Consultants B-115 - 117 & 509, Annapurna Block, Aditya Enclave, Ameerpet, Hyderabad- 500 038 Phone: 91-040-23748555/616 Fax : 91-040-23748666 e-mail: [email protected] SUBMITTED TO STATE LEVEL ENVIRONMENT IMPACT ASSESSMENT AUTHORITY, TELANGANA GOVERNMENT OF INDIA

Upload: lamdung

Post on 03-Apr-2018

226 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: Janapriya Engineers Syndicate Pvt. Ltd.environmentclearance.nic.in/writereaddata/FormB/EC/Risk...RAMP DOWN TO CELLAR RAMP UP TO GROUND FLOOR M.H RAMP DN TO CELLAR 33.00M M.H M.H M

Janapriya Engineers Syndicate Pvt. Ltd.SURVEY NOS. 663(P), 668(P) AND 671(P),KAPRA, MEDCHAL - MALKAJGIRI DISTRICT

1. CONCEPTUAL PLAN2. EMP report

RESIDENTIAL CONSTRUCTION PROJECT

Submitted ByM/s Janapriya Engineers Syndicate Pvt. Ltd.,D. No. 8-2-120/86/1,Keerthi & Pride Towers,Road No.2, Banjara Hills,Hyderabad-500 034

Studies & Documented ByM/s Team Labs and ConsultantsB-115 - 117 & 509,Annapurna Block, Aditya Enclave,Ameerpet, Hyderabad- 500 038Phone: 91-040-23748555/616Fax : 91-040-23748666e-mail: [email protected]

SUBMITTED TOSTATE LEVEL ENVIRONMENT IMPACT ASSESSMENT AUTHORITY,

TELANGANAGOVERNMENT OF INDIA

Page 2: Janapriya Engineers Syndicate Pvt. Ltd.environmentclearance.nic.in/writereaddata/FormB/EC/Risk...RAMP DOWN TO CELLAR RAMP UP TO GROUND FLOOR M.H RAMP DN TO CELLAR 33.00M M.H M.H M

Janapriya Engineers Syndicate Pvt. Ltd. Environmental Impact Assessment

Team Labs and Consultants2 - 1

2.0 PROJECT DESCRIPTION/CONCEPTUAL PLAN

This chapter details the need for the project, description of the proposed project andalternatives, and identifies the valued ecosystem components. The project is envisagedto provide housing to meet the growing demands for housing in the growing urban areaof Hyderabad.

2.1 THE PROJECT LOCATIONThe project is envisaged to develop 5.15 hectares of land in Survey Nos. 663(P), 668(P),671(P), Kapra, Medchal -Malkajgiri District into residential units for various socioeconomic sectors. The project would cater to various market demands and needs of thepeople. The project site is surrounded open lands in all the directions except in Northdirection. An existing 18 m wide road connecting Bank colony. The nearest railwaystation is Ammuguda railway station at a distance of 3.6 km.

2.2 PROJECT DESCRIPTION2.2.1 DESIGN STAGEThe project is envisaged as a gated community of Residential Apartments withamenities. The dwelling profile is in accordance with the defence caders. The land areaavailable for the project is 5.15 hectares and will be allocated for dwelling andamenities based on the development rules of HMDA. The land allocation and thenumber of units proposed are presented in table 2.1. The prescribed floor area andproposed area are presented in table 2.2.

It is proposed to provide 2246 units in 10 Blocks with 2 Cellar floors for parking and G+9 floors and Amenities block with C+G+6 into residential units. The land allocation willbe optimized to ensure compliance with the FAR regulations of HMDA. The waterrequirement of the project during operation will be drawn from HMWSSB. Sewagetreatment plant will be provided to treat the sewage. Water conservation measures willbe incorporated in the plumbing designs. Water recycling/reuse will be adopted by wayof using treated sewage for toilet flush systems and green belt development. Thetreated sewerage and storm water will be let-out into the municipal storm water. Therequired power will be drawn from the TSTRANSCO and the energy requirement willbe optimized by providing open space between each flat to allow sunlight.Construction material will be drawn from local sources. It is proposed to provideapproximately 1: 1 car parking spaces in the. The parking provision follows theguidelines prescribed by FAR and Building policy of Telangana. The layout of the projectsite and floor plans of individual unit and Apartments are presented in Figure. 2.1 and2.2. It is proposed to provide approximately 1:1 car parking spaces in the. The parkingprovision follows the guidelines prescribed by FAR and Building policy of Telangana.The number of parking spaces provided is presented in Table 2.2.

Page 3: Janapriya Engineers Syndicate Pvt. Ltd.environmentclearance.nic.in/writereaddata/FormB/EC/Risk...RAMP DOWN TO CELLAR RAMP UP TO GROUND FLOOR M.H RAMP DN TO CELLAR 33.00M M.H M.H M

Janapriya Engineers Syndicate Pvt. Ltd. Environmental Impact Assessment

Team Labs and Consultants2 - 2

Table 2.1 Built up Area Statement

Land Use No ofFloors

Total No ofUnits

Total SiteArea in m2

Total Built uparea (m2)

Block A1 2C+G+9 277 1948.8 19820.8Block A2 2C+G+9 277 1948.8 19820.8Block A3 2C+G+9 277 1948.8 19820.8Block A4 2C+G+9 277 1948.8 19820.8Block B 2C+G+9 218 1658.6 16999.8Block C1 2C+G+9 219 2053.0 20981.7Block C2 2C+G+9 219 2053.0 20982.0Block D 2C+G+9 176 1684.1 16921.4Block E 2C+G+9 119 1222.2 12409.9Block (LIG & EWS) 2C+G+9 187 667.6 6554.7Amenities block C+ G+6 621.7 4646.9Green Area 7424.8Road Area 15353.0Open Area 11002.8ParkingCellar 39068.4Sub cellar 38074.1Total 2246 51536.0 255922.0

Circulation Plan:Ground Floor Driveway : 7.0 mNo. of Cellar : 2No. of Ramps : 11Width of Ramp : 5.4Slope of Ramp : 1 in 8Cellar Driveway : 4.5 mNo. of Lifts : 33Capacity of each Lift: 15 pax.Connecting Road : 18 m ROW

Generated TrafficModified Los & Performance

RoadExistingvolume,PCU/hr

Existingvolume/Capacity

Additionalvolume

ModifiedVolume

ModifiedVolume/Capacity

ModifiedLos &

performance

DammaigudaRoad 456 0.169 190 646 0.239 “A”

Excellent

ECIL –TirumalagiriRoad

1139 0.316 200 1339 0.372 “B” VeryGood

Page 4: Janapriya Engineers Syndicate Pvt. Ltd.environmentclearance.nic.in/writereaddata/FormB/EC/Risk...RAMP DOWN TO CELLAR RAMP UP TO GROUND FLOOR M.H RAMP DN TO CELLAR 33.00M M.H M.H M

Janapriya Engineers Syndicate Pvt. Ltd. Environmental Impact Assessment

Team Labs and Consultants2 - 3

ParkingIt is proposed to provide 2 cellar floors for parking. The parking provision follows theguidelines prescribed by FAR and Building policy. The number of parking spacesprovided is presented in table 2.2.

Table 2.2 Parking Space Provision of the Project

Floor Parking No's provided4 - Wheeler 2 - Wheeler

Cellar 946 213Sub cellar 952 227Total 1898 440

Page 5: Janapriya Engineers Syndicate Pvt. Ltd.environmentclearance.nic.in/writereaddata/FormB/EC/Risk...RAMP DOWN TO CELLAR RAMP UP TO GROUND FLOOR M.H RAMP DN TO CELLAR 33.00M M.H M.H M

Janapriya Engineers Syndicate Pvt. Ltd. Environmental Impact Assessment

Team Labs and Consultants2 - 4

Fig 2.1 Layout of project

SECURITY 1

NEIG

HBOU

RS LA

ND

7.00

M W

IDE

DRIV

EWAY

33.00M

LIFT

OPENTO SKY

M.H

RAMP UP TO GROUND FLOOR

IN

M.H OPEN TO SKY

M.H

2.0M

WID

E GR

EENE

RY

12.20M

RAMP DOWN TO CELLAR

7.00

M W

IDE

DRIV

EWAY

18.92M

OPENTO SKY

7.05M

LIFT

7.00M

10.00

M

M.H

UP

TOT-LOT-1106.59 Sqmts

OPEN TO SKY

M.H

BORE

33.00M

OPENTO SKY

S L

O P

E - 1

:8

16.52

M

2.00M

S.LIFT

PROPOSED COMPOUND WALL

EXT . 9.0 M ROAD

M.H

14.71M

M.H

RAMP DOWN TO CELLAR

LIFT

PROPOSED

TOWARDS SHANTHI VIHAR CLY

M.H

M.H

LIFT

7.01M

M.H

2.0M

WID

E GR

EENE

RY

S L

O P

E - 1

:8

RAMP UP TO GROUND FLOOR

M.H

GARB

AGE

B

IN

23.64M

M.H

2.0M

WID

E GR

EENE

RY

PROPOSED

M.H

5.40

M

OPENTO SKY

S L

O P

E - 1

:8

7.08M

7.00

M W

IDE

DRIV

EWAY

46.03

M

10.00

M

M.H

M.H

GARB

AGE

B

IN

M.H

M.H

M.H

7.00M WIDE DRIVEWAY

85.42

M

PROPOSED

RAMP DOWN TO CELLAR

LIFT

M.H

S L

O P

E - 1

:8

OPEN TO SKY

75.60

M

M.H

UP

M.H

AREA 18.0 M WIDE MASTER PLAN ROAD

OPENTO SKY

TOT-LOT-5 544.45Sqmts

10.00

M

M.H

2.0M WIDE GREENERY

M.H

10.00M

RAMP UP TO GROUND FLOOR

LIFT

BLOCK-L.I.G /E.W.S

OUT

STORM WATER LINE

5.40

M

8.55M

7.00

M W

IDE

DRIV

EWAY

IN

PROPOSED

6.63M

S L O P E - 1:8

M.H

14.73M

GARB

AGE

B

IN

LIFT

16.52

M

2.00M

OPEN TO SKY

M.H

10.00M

M.H

21.58M

18.85M

S L O P E - 1:8 LIFT

IN

SHANTHI VIHAR CLY/GREENPARK ENCLAVE

11.18

M

23.64M

CUT-OUT-3737.30 SQ.MT

21.03

M

10.00M

LIFT

55.28M

M.H

RAM

P UP

TO

GRO

UND

FLOO

R

55.90M

S L O P E - 1:8

M.H

STP

M.H

10.00

M

M.H

BLOCK-C2

M.H

OPENTO SKY

33.73M

IN

4.48

M

M.H

M.H

OPENTO SKY

RAMP UP TO GROUND FLOOR

M.H

PROPOSED

TOT-LOT-4 2350.39Sqmts

LIFT

M.H

RAMP DOWN TO CELLAR

RAM

P UP

TO

GRO

UND

FLOO

R

M.H

RAM

P DN

TO

CELL

AR

33.00M

M.H

M.H

57.50M

UP

19.84

M

2.0M

WID

E GR

EENE

RY

15.23M

M.H

OPENTO SKY

UP

33.00M

12.0M W

IDE EXISTING ROAD

7.00M WIDE DRIVEWAY

75.60

M

M.H

LIFT

OPEN TO SKY

OUT

M.H

S L O P E - 1:8

S L

O P

E - 1

:8

M.H

S L

O P

E - 1

:8

GARB

AGE

B

IN

M.H

7.01M

M.H

M.H

OPENTO SKY

M.HGARB

AGE

B

IN

64.45

M

17.96M

OPENTO SKY

16.55

M

GARB

AGE

B

IN

7.00

M W

IDE

DRIV

EWAY

7.00

M W

IDE

DRIV

EWAY

M.H

23.64M

OPENTO SKY

M.H

S L O P E - 1:8

OUT

M.H

TRANSFORMER

M.H

21.08

M

RAM

P DO

WN

TO

CEL

LAR

53.57M

3.75M

S L O P E - 1:8

12.0M WIDE EXISTING PERIPHERAL ROAD

M.H

CIVIC AMENITIES

17.41M

EXT.ROAD

M.H

M.H

OPEN TO SKY

7.00

M W

IDE

DRIV

EWAY

M.H

M.H

33.00M

GARB

AGE

B

IN

5.40

M

249.2

2M

M.H

BLOCK-A4

M.H

IN

M.H

10.00M

M.H

CUT-OUT-3237.63 SQ.MT

SEWERAGE LINE

Sy.No.669 & 670

S L O P E - 1:8

63.87

M

16.68M

OUT

BLOCK-D

10.09M

M.H

7.45M

M.H

TOT-LOT-3720.43Sqmts

LIFT

M.H

11.35

M

5.40

M

SURV

EY.N

o : 6

66

BLOCK-E

PROPOSED

19.23M

7.00

M W

IDE

DRIV

EWAY

OPENTO SKY

LIFT

M.H

M.H

41.93

M

OPENTO SKY

RAM

P UP

TO

GRO

UND

FLOO

R

DOMESTIC WATERSUMP 4,00,000 Lts

LIFT

M.H

M.H

10.00

M

OPEN TO SKY

BLOCK-A2

69.23

M

LIFT

M.H

10.00M

CUT-OUT-3137.63 SQ.MT

10.99

M

M.H

RAM

P DO

WN

TO

CEL

LAR

12.38M

7.00

M W

IDE

DRIV

EWAY

M.H

RAMP UP TO GROUND FLOOR

BORE

7.00M WIDE DRIVEWAY

IN

STORM WATER SUMP

OUT

LIFT

75.60

M

12.0M W

IDE EXISTING ROAD

M.H

M.H

LIFT

PROPOSED

M.H

LIFT

268.8

5M

75.60

M

M.H

7.00M WIDE DRIVEWAY

SECURITY 1

M.H

73.95

M

M.H

12.11

M

OPEN TO SKY

7.00M WIDE DRIVEWAY

33.00M

OUT

BLOCK-A1

14.72

M

S L O P E - 1:8

M.H

M.H

M.H

UP

66.45

M

IN

36.99M

75.61

M

LIFT

20.76M

84.25

M

33.00M

11.05

M

S.LIFT

M.H

M.H

M.H

30.43M

OPENTO SKY

25.46M

23.64M

10.04

M

LIFT

10.00M

M.H

CUT-OUT-3821.10 SQ.MT

25.83M

M.H

BLOCK-A3RA

MP

DOW

N T

O C

ELLA

R

62.26M

LIFT

CUT-OUT-3537.30 SQ.MT

TOT-LOT-6936.06Sq.mts

CUT-OUT-3419.55 SQ.MT

LIFT

10.00M

M.H

CUT-OUT-3629.98 SQ.MT

12.11

M

M.H

PROPOSED

WATER LINE

EXISTING CLY

APPROVED BY

GHMC, KAPRA CIRCLE,

PERMIT NO.42/MP2/H/2003

114.97M

P.P

TOT-LOT-2909.75Sqmts

IN

M.H

PROPOSED

M.H

15.69

M

OPEN TO SKY

M.H

M.H

OUT

M.H

7.00

M W

IDE

DRIV

EWAY

LIFT

SY.NO. 671(P)

M.H

M.H

SECURITY 2

M.H

7.00

M W

IDE

DRIV

EWAY

OPEN TO SKY

OPENTO SKY

UP

M.H

M.H

61.80M

S.LIFT

LIFT

M.H

S L

O P

E - 1

:8

7.00M WIDE DRIVEWAY

M.H

SITE PLAN(SCALE 1:500)

S L O P E - 1:8

M.H

GARBAGE BIN

OUT

3.07M

OPEN TO SKY

OPEN TO SKY

M.H

7.00M

PROPOSEDPROPOSED

33.00M33.00M

33.00M

BLOCK- BBLOCK-C1

CUT-OUT-2537.63 SQ.MT

RAMP DOWN TO CELLAR

CUT-OUT-2829.98 SQ.MT

S L O P E - 1:8

CUT-OUT-2921.10 SQ.MT

RAMP UP TO GROUND FLOOR

CUT-OUT-3032.14 SQ.MT

S L O P E - 1:8

11.02M

S.LIFT

85.42

M

33.00M

10.00M

10.00

M

15.48M

10.00

M

2.00M

LIFT

LIFTLIFT

10.00M

31.48M

65.84M

OPENTO SKY

OPENTO SKY

OPENTO SKY

OPENTO SKY

OPENTO SKY

OPENTO SKY

OPENTO SKYOPEN

TO SKYOPEN TO SKY

OPEN TO SKY

85.42

M

6.00M

RAMP DOWN TO CELLAR

M.H

S L O P E - 1:8

Page 6: Janapriya Engineers Syndicate Pvt. Ltd.environmentclearance.nic.in/writereaddata/FormB/EC/Risk...RAMP DOWN TO CELLAR RAMP UP TO GROUND FLOOR M.H RAMP DN TO CELLAR 33.00M M.H M.H M

Janapriya Engineers Syndicate Pvt. Ltd. Environmental Impact Assessment

Team Labs and Consultants2 - 5

Fig 2.2 Floor Plans

A1'

A1

A1'

A1 A1

BALCONY PROJECTION AT 2nd FLOOR Lvl

A1

2.00M

14.30M

7.30M

R A M P U P T O G R O U N D F L O O R

R A M P D O W N T O CELLAR

7.30M

14.30M

TOILET1.20X2.13M

7.20M

3.00M

14.30M

7.30M

TOILET1.20 X2.30M

UP

7.30M

UP UP

S L O P E - 1:8V

2.00M

V

UP UP UP

S L O P E - 1:8

7.20M

W

UP UPUP

2.00M7.20M7.20M2.00M

7.30M

D2

1.22M

7.30M

BAL

CONY

3.05 x

1.22M

3.05M

A1'

2.00M

3.05M

7.20M

BEDROOM3.55X2.74M

7.20M

7.30M

3.00M

BALCONY PROJECTION AT 2nd FLOOR Lvl

7.20M

75.59

M

7.20M

BALCONY PROJECTION AT 2nd FLOOR Lvl

TOILET1.20X2.13M

TOILET2.00X1.22M

7.20M

8.46M

W

33.00M7.30M

6.63M

W

TOILET2.00X1.22M

KW

8.46M

TOILET1.20X2.13M

7.30M

BAL

CONY

PRO

JECT

ION

A

T 2n

d FLO

OR Lv

l

W

KW

W

3.05M

W

7.20M

BALCONY PROJECTION AT 2nd FLOOR Lvl

UTI

LITY

2.29X

1.0M

1.22M

2.00M

3.00M

GARBAGE LIFT 1.36X 1.83M

7.30M

BAL

/ UT

ILITY

3.0

5 x1.2

2M

TOILET2.06 X1.20M

D2

8.46M

VV

3.00M

TOILET2.53X1.20M

3.05M

TOILET2.53X1.20M

8.36M

TOILET2.53X1.20M

8.36M

8.36M

V

BEDROOM3.55X2.74M

UP

BAL

CONY

3.05 x

1.22M

8.46M

1.22M

D2

3.00M

BALCONY3.05 x1.22M

26

CUT-OUT -1FOR BASEMENTS

38.06 SQMTS

BAL

/ UT

ILITY

3.0

5 x1.2

2M

3.05M

8.36M

24

1.22M

6.63M

3.05M

1.22M

UP

3.00M

1.22M

8.36M

8.36M

1.22M

2.00M

3.00M

3.00M

UP

8.36M

8.36M

BEDROOM3.55X2.74M

8.46M

6.63M

3.05M

6.10M

6.63M

3.00M

3.00M

KW

3.00M

8.36M

8.46M

TOILET2.06 X1.20M

3.05M

1.22M

1.22M

1.22M

3.05M

1.22M

D2

1.22M

A1'

D2

1.22M

3.05M

1.22M

D1

3.00M

BALCONY3.05x1.22M

1.22M

3.05M

3.05M

2M W

IDE

CORR

IDOR

8.36M

BAL

CONY

PRO

JECT

ION

A

T 2n

d FLO

OR Lv

l

3.00M

3.05M

3.05M

BAL

CONY

PRO

JECT

ION

A

T 2n

d FLO

OR Lv

l

BAL

CONY

3.05 x

1.22M

BAL

CONY

PRO

JECT

ION

A

T 2n

d FLO

OR Lv

l

D2

TOILET1.20X2.0M

KW

TOILET1.20 X2.0M

BAL

CONY

PRO

JECT

ION

A

T 2n

d FLO

OR Lv

l

1.22M

D1

W

BAL

CONY

PRO

JECT

ION

A

T 2n

d FLO

OR Lv

l

W

BALCONY3.41x1.22M

UTI

LITY

2.29X

1.0M

BAL

CONY

PRO

JECT

ION

A

T 2n

d FLO

OR Lv

lW

KITCHEN2.54X2.02M

8.36M

BALCONY3.05x1.22M

BALCONY PROJECTION AT 2nd FLOOR Lvl

KW1 KW2D2

KW

3.05M

02

8.36M

V

3.05M

8.36M

BAL

/ UT

ILITY

3.0

5 x1.2

2M

25

3.05M

6.63M

BALCONY3.05x1.22M

3.05M

25

1.22M

3.00M

GARBAGE LIFT1.36X1.83M

3.05M

8.46M

1.22M

BALCONY3.05x1.22M

KW

3.05M

1.22M

TOILET1.20X2.25M

33.00M

KW1 KW2D2

6.10M

6.63M

KW

BALCONY3.05x1.22M

8.46M

BAL

/ UT

ILITY

3.0

5 x1.2

2M

8.36M

3.05M

BALCONY PROJECTION AT 2nd FLOOR Lvl

D2

3.00M

1.22M BALCONY

3.05x1.22M BALCONY PROJECTION AT 2nd FLOOR Lvl

7.30M

3.05M

KITCHEN2.54X2.02M

8.36M

BALCONY PROJECTION AT 2nd FLOOR Lvl

22

2M W

IDE

CORR

IDOR

6.63M

BAL

CONY

PRO

JECT

ION

A

T 2n

d FLO

OR Lv

l

02

BAL

CONY

PRO

JECT

ION

A

T 2n

d FLO

OR Lv

l

TOILET1.20X2.0M

TOILET1.20X2.0M

BAL

CONY

3.05 x

1.22M

FIRST FLOOR PLAN

2.00M

3.00M

W

D2

TOILET2.05 X1.20M

BLOCK-A1

2.00M

8.36M

W3.0

5M

8.36M D

3.05M

DIN / LIV2.86 /4.14 X 5.78M

2.00M

V

2.00M

BEDROOM3.55X2.74M

25

TOILET1.20 X2.23M

6.63M

3.00M

D1

22

TOILET1.22 X2.53M

UP

V

2.00MUP

TOILET1.22X2.53M

KW

V

W

KW

W

GARBAGE LIFT1.36X1.83M

TOILET1.20X2.0M

CUT-OUT -1FOR BASEMENTS

38.06 SQMTS

TOILET1.20 X2.30M

DIN / LIV2.86 /4.14 X 5.78M

TOILET1.20X2.25M

TOILET1.20 X2.23M

TOILET1.20X2.25M

DIN / LIV2.86 /4.14 X 5.78M

TOILET1.20 X2.24M

TOILET1.20X2.25M

TOILET1.20 X2.23M

UTI

LITY

2.41X

1.0M

W

W

WV

X X

GARBAGE LIFT 1.36X 1.83M

5.70M

23.64M

TOILET2.05 X1.20M

KW

TOILET2.05 X1.20M

BEDROOM3.55X2.74M

GARBAGE LIFT1.36X1.83M

UTI

LITY

2.29X

1.0M

BEDROOM3.55X2.74M

26

A1'

A1'

26

VW

TOILET1.20 X2.30M

CUT-OUT -1FOR BASEMENTS

38.06 SQMTS

TOILET1.20X2.13M

TOILET1.20X2.13M

TOILET1.20 X2.0M

TOILET1.22 X2.53M

TOILET1.20X2.13M

UP

UTI

LITY

2.29X

1.0M

TOILET1.20 X2.0M

8.46M

UTI

LITY

2.29X

1.0M

8.46M

UP3.0

0MUP

3.00M

TOILET1.22 X2.53M

W

3.00M

WW

2M W

IDE

CORR

IDOR

7.77M

V

GARBAGE LIFT 1.36X 1.83M

3.00M

2M W

IDE

CORR

IDOR

7.77M

D1

3.00M

UTI

LITY

1.93X

1.07M

3.00M

BEDROOM3.55X2.74M24

TOILET1.20X2.13M

UP

TOILET1.20X2.0M

TOILET1.22 X2.53M

UP

UP

UTI

LITY

2.29X

1.0M

2M W

IDE

CORR

IDOR

2M W

IDE

CORR

IDOR

D1

TOILET1.20X2.13M

TOILET1.20X2.0M

UTI

LITY

2.29X

1.0M

V

6.10M

V

D1

3.00M

3.00M

2.00M

KW KW TOILET1.20X2.0M

TOILET1.20 X2.30M

TOILET1.20X2.25M

TOILET1.20 X2.24M

UTI

LITY

2.41X

1.0M

W

TOILET1.22 X2.53M

TOILET1.22 X2.53M

D1

UTI

LITY

1.93X

1.07M

V

D1

D1

V

D1

TOILET1.22 X2.53M

V

TOILET1.22X2.53M

V

W

W

D

8.46M

8.46M

3.00M

6.10M

3.00M

7.77M

3.00M

7.77M

3.00M

3.00M

2.00M

3.00M

3.00M

8.46M

UTI

LITY

2.29X

1.0M

TOILET1.22 X2.53M

BEDROOM3.55X2.74M24

A1A1

D

KW1 KW2D2

KW1 KW2D2

KW1 KW2D2

KW

TOILET2.06 X1.20M

BEDROOM3.55X2.74M

22

KW KW TOILET1.20X2.0M

TOILET1.20 X2.30M

TOILET1.20X2.25M

TOILET1.20 X2.24M

UTI

LITY

2.41X

1.0M

W

UTI

LITY

2.29X

1.0M

VW

TOILET1.20 X2.30M

TOILET1.20X2.13M TOILET

1.22 X2.53M

TOILET1.22 X2.53M

D1

UTI

LITY

1.93X

1.07M

V

D1

TOILET1.22 X2.53M

D1

V

D1

TOILET1.22 X2.53M

V

TOILET1.22X2.53M

V

W

W

75.59

M

33.00 M

8.46M

8.46M

3.00M

6.10M

3.00M

3.00M

7.77M

3.00M

7.77M

3.00M

3.00M

2.00M

3.00M

3.00M

8.46M

3.00M

8.36M

6.63M

3.00M

8.36M

8.20M

3.15M

8.36M

6.63M

8.46M

8.46M

3.00M

8.36M

6.63M

3.00M

8.36M

8.36M

3.00M

8.36M

6.63M

3.00M

7.30M2.00M7.20M7.20M2.00M

CUT-

OUT

- 2 F

OR B

ASEM

ENTS

LIFT

DUC

T

CUT-

OUT

- 2 F

OR B

ASEM

ENTS

LIFT

DUC

T

LI

FT D

UCT

Page 7: Janapriya Engineers Syndicate Pvt. Ltd.environmentclearance.nic.in/writereaddata/FormB/EC/Risk...RAMP DOWN TO CELLAR RAMP UP TO GROUND FLOOR M.H RAMP DN TO CELLAR 33.00M M.H M.H M

Janapriya Engineers Syndicate Pvt. Ltd. Environmental Impact Assessment

Team Labs and Consultants2 - 6

Fig 2.3 Parking Floor Plans

S L O P E - 1:8

4.50

M

21.10 SQ.MT

4.50M

WID

E DR

IVE

WAY

5.40M

WID

E DR

IVE

WAY

4.50M WIDE DRIVE WAY

4.50M WIDE DRIVE WAY

RAM

P DO

WN

TO C

ELLA

R

ELECTRICAL/M&E ROOM 12.33X5.89M

3.05M

4.50

M W

IDE

DRIV

E WAY

2.50M4.50M WIDE DRIVE WAY

S ER .LIFT1.83X2.44M

21.350M

ELEC TRICALR OO M 2-D5.260x 4.580M

4.50M WIDE DRIVE WAY

CUT-OUT

CUT-OUT - 25FOR BASEMENTS

36.81 SQMTS

CAR

CUT-OUT

5.40M

WID

E DR

IVE

WAY

4.50M WIDE DRIVE WAY

4.50M WIDE DRIVE WAY

4.50

M

4.50M

WID

E DR

IVE

WAY

18.99M

4.50M WIDE DRIVE WAY

PRO.BLOCK-A2

RAM

P UP

TOc

ellar

FLO

OR

229

4.50M WIDE DRIVE WAY

2.50M

S L O P E - 1:8

S L

O P

E -

1:7

21.00

0M

5.400M

S L

O P

E -

1:8

3.64M

4.50M WIDE DRIVE WAY

Scooter Parking

5.40M WIDE DRIVE WAY

5.40M

WID

E DR

IVE

WAYS L O P E - 1:8

CAR

4.50

M

4.50M WIDE DRIVE WAY

4.50M WIDE DRIVE WAY

5.40M

WID

E DR

IVE

WAY

PRO.BLOCK-A1

Scooter Parking

Scooter Parking

4.50

M W

IDE

DRIV

E WAY

RAW

WAT

ER TA

NKRE

QUI

RED

= 40

,000

Ltrs

PRO

VIDE

D =

44,1

00 Lt

rs

UPLIFT

1.83X1.83M

4.50M WIDE DRIVE WAY

PRO.BLOCK-A4

4.50M WIDE DRIVE WAY

CAR

230

CAR

4.50M WIDE DRIVE WAY

4.50M WIDE DRIVE WAY

5.40M

WID

E DR

IVE

WAY

SWEA

T W

ATER

TANK

REQ

UIRE

D =

20,0

00 L

trsPR

OVI

DED

= 25

,200

Ltrs

LIFT1.83X1.83M

5.40M

WID

E DR

IVE

WAY

4.50M WIDE DRIVE WAY

CAR

4.50M WIDE DRIVE WAY

5.40M

WID

E DR

IVE

WAY

PRO.BLOCK-B

4.50

M

5.40M W

IDE DRIVE WAY

CAR

2.50

M

Scooter Parking

S L O P E - 1:8

4.50M WIDE DRIVE WAY

12.73 SQ.MT

CUT-OUT - 24FOR BASEMENTS

37.15 SQMTS

37.63 SQ.MT

5.40M

WID

E DR

IVE

WAY

2.50M

PRO.BLOCK-D

4.50M WIDE DRIVE WAY

4.50M WIDE DRIVE WAY

S L

O P

E -

1:8

4.50M

PRO.BLOCK-C1

PRO.BLOCK-C2

CAR

E-P L11.900x 1.900M (8 pass.)

LIFT1.83X1.83M

2.50M

5.40M

WID

E DR

IVE

WAY

PRO.BLOCK-A3

4.50M

Scooter Parking

CAR

4.50M WIDE DRIVE WAY

4.50

M W

IDE

DRI

VE W

AY

5.40M

WID

E DR

IVE

WAY

PRO.BLOCK-LIG/EWS

Scooter Parking

FLUS

H W

ATER

TAN

K ( BL

OCK-E

)RE

QUI

RED

= 28

,000

Ltrs

PRO

VIDE

D =

28,6

00 Lt

rs

4.50M WIDE DRIVE WAY

4.50M WIDE DRIVE WAY

4.50M WIDE DRIVE WAY

4.50M WIDE DRIVE WAY

4.50M WIDE DRIVE WAY

4.50M

WID

E DR

IVE

WAY

Scooter Parking

4.50M

WID

E DR

IVE

WAY

PRO.BLOCK-E

4.50M

WID

E DR

IVE

WAY

4.50M WIDE DRIVE WAY

29.98 SQ.MT

4.50M WIDE DRIVE WAY

2.50

M4.50M WIDE DRIVE WAY

4.50

M W

IDE

DRIV

E WAY

CUT-OUT

S L

O P

E -

1:7

5.40M

WID

E DR

IVE

WAY

EV.1

18.51M

4.50M WIDE DRIVE WAY

4.50M WIDE DRIVE WAY

Scooter Parking

CUT-OUT

4.50M

WID

E DR

IVE

WAY

5.40M

WID

E DR

IVE

WAY

4.50M WIDE DRIVE WAY

4.50M WIDE DRIVE WAY

Scooter Parking

4.50M

WID

E DR

IVE

WAY

5.40M

WID

E DR

IVE

WAY

5.40M

WID

E DR

IVE

WAY

5.40M

WID

E DR

IVE

WAY

EXPANSIONJOINT

EXPANSION JOINT

4.50M WIDE DRIVE WAY

4.50M WIDE DRIVE WAY

4.50M WIDE DRIVE WAY

SUB CELLAR PLAN ( SCALE 1:500 )

10.15M

4.50M WIDE DRIVE WAY

4.50M WIDE DRIVE WAY

4.50M WIDE DRIVE WAY

4.50M WIDE DRIVE WAY

5.40M

WID

E DR

IVE

WAY

8.23M

S L O P E - 1:8

TOI LET2.00X2.44M

TOI LET2.00X2.44M

4.50M WIDE DRIVE WAY

5.40M

WID

E DR

IVE

WAY

3.58M

CAR

4.50

M

2 .50M

CAR

4.50

M

2 .50M

CAR 4.50

M

2 .50M

CAR

4.50

M

2 .50M

CAR 4.50

M

2 .50M

CAR 4.50

M

2 .50M

4.50

M

CAR

S L

O P

E - 1:

7

Page 8: Janapriya Engineers Syndicate Pvt. Ltd.environmentclearance.nic.in/writereaddata/FormB/EC/Risk...RAMP DOWN TO CELLAR RAMP UP TO GROUND FLOOR M.H RAMP DN TO CELLAR 33.00M M.H M.H M

Janapriya Engineers Syndicate Pvt. Ltd. Environmental Impact Assessment

Team Labs and Consultants2 - 7

2.2.1.1 Storm water drains:Conservation of water resource is most important aspect of the project duringconstruction and occupation phases. Storm water drainage planning, domestic waterplanning and sewerage transfer and sewage treatment planning are critical aspects ofconstruction and occupation stages of housing projects.

Storm water drains will be provided all over the site to meet the expected increase inthe runoff during rainy seasons due to the impervious nature of the roads and otherpaved areas. The site is uneven and it is proposed to maintain the levels as much aspossible, hence 2 numbers of storm water let outs from the site are anticipated. Theexpected runoff is calculated for the design of the storm water runoff and presented infollowing table.

Calculation for Storm Water DrainQuantity of storm water(a) With out projectArea of Catchment, ‘A’ : 5.1536 HaRun off Coefficient, ‘C’ : 0.6Maximum intensity of rainfall, ‘I’ : 40 mm/hrTherefore Q : 0.344 m3/sec(b) With project :Area for catchment for roof and road : 3.311 HaArea of Catchment, ‘A’ : 3.311 HaRun off Coefficient, ‘C’ : 0.9Maximum intensity of rainfall, ‘I’ : 40 mm/hrTherefore Q = : 0.331 m3/sec

Area for catchment for open areas : 1.843 HaRun off Coefficient, ‘C’ : 0.6Maximum intensity of rainfall, ‘I’ : 40 mm/hrTherefore Q = : 0.123 m3/secTotal Discharge : 0.454 m3/secBut, Discharge, Q = A/V

Where,A= Area of the Drain,V= Max. Permissible Velocity : 6 m/sec for concrete drain

Area of drain, ‘A’ = Q/V : 0.076 m2

Taking depth of drain as 0.6 m at the startingpoint : 0.6Width of drain = Area/depth = : 0.126 m 126 mm

Width of the drain is to taken 126 mm and depth varies according to the slope of ground.

Page 9: Janapriya Engineers Syndicate Pvt. Ltd.environmentclearance.nic.in/writereaddata/FormB/EC/Risk...RAMP DOWN TO CELLAR RAMP UP TO GROUND FLOOR M.H RAMP DN TO CELLAR 33.00M M.H M.H M

Janapriya Engineers Syndicate Pvt. Ltd. Environmental Impact Assessment

Team Labs and Consultants2 - 8

Table 2.3 Strom Water Runoff

Land Use Area inHectares

Vol./hrafter

developmentC=0.8

Vol./hrbefore

developmentC=0.6

Differencein

DischargesRemarks

Roof Area 1.78 568.2 426.1 142.0

Harvested in sumps witha capacity of 10 X 15 m3

and used for domesticpurpose

Road Area 1.54 491.3 368.5 122.8 70 nos. of RWH pits areprovided of size 1.5m X

1.5m X 2.0 mOpen Area 1.84 221.1* 442.3 -221.1TOTAL 5.15 43.7

* C=0.3 after development of greenery

The roof waters arechanneled through stormwater drains which areconnected with waterharvesting pits. Stormwater from the roof topswill be directed tointermediate rainwaterharvesting pits to beprovided (as per HMDAnorms) at a rate of 1 eachat a distance of 50m,Typical drawings ofintermediate rainwaterharvesting pits ispresented in Figure 2.3

Fig

2.4 Rainwater Harvesting Structure

Page 10: Janapriya Engineers Syndicate Pvt. Ltd.environmentclearance.nic.in/writereaddata/FormB/EC/Risk...RAMP DOWN TO CELLAR RAMP UP TO GROUND FLOOR M.H RAMP DN TO CELLAR 33.00M M.H M.H M

Janapriya Engineers Syndicate Pvt. Ltd. Environmental Impact Assessment

Team Labs and Consultants2 - 9

2.2.1.2 Water Availability:Water is required for the construction as well as during occupation stage as the same isan important resource. The water requirement during construction is in the order of100 cum/day with a peak demand of 200 cum/day, and during occupation stage in theorder of 1601.9 KLD. The water resource available with the Municipal authorities wasstudied to identify the source and feasibility. The water resource both domestic waterand sewage is dealt by the Hyderabad Metropolitan water supply and Sewerage Board(HMWSSB) in the HMDA area. The HMWSSB has been maintaining the water supplyresources for Hyderabad along with the treatment of wastewater. The resourcesavailable with the HMWSSB are presented in table 2.4.

Table 2.4 Details of present sources of water supply to Hyderabad

Source Name River Year ImpoundmentName

Distance fromcity km

InstalledCapacity MGD

Osmansagar Musi 1920 Osmansagar 15 27Himayatsagar ESI 1927 Himayatsagar 9.6 18Manjira Phase I Manjira 1965 Manjira barrage 58 15Manjira Phase II Manjira 1981 Manjira barrage 59 30Manjira Phase III Manjira 1991 Singur Dam 80 37Manjira Phase IV Manjira 1993 Singur Dam 80 38Krishna Phase I Krishna 2005 Nagarjuna Sagar 116 90Krishna Phase II Krishna 2008 Nagarjuna Sagar 116 90Krishna Phase III Krishna 2015 Nagarjuna Sagar 116 90Godavari Phase I Godavari 2016 Yellampally 186 172

Source: Hyderabad Metropolitan Water Supply & Sewerage Board, www.hyderabadwater.gov.in

It may be noted that the following water supply projects i.e., Krishna Phase III (Part II)with 45 MGD capacity and Godavari phase – I with 172 MGD capacity is anticipated tobe operational during 2015 and 2016 respectively. It may also be noted that thedependability of Osman sagar and Himiyath sagar is reduced to approximately 60%. 45MGD supply is available.

Domestic Water: It is proposed to draw domestic water from the HyderabadMetropolitan Water Supply and Sewerage Board (HMWSSB) to mitigate the drinkingwater demand, which has been encouraging bulk consumers. The water shortage if anyduring summer season will be drawn from ground water sources. During theconstruction stage, water will be sourced primarily through tankers that would bearranged by the contractor or bulk supplies from HMWS&SB. During the projectoperational stage the water demand shall be sourced bulk supplies from HMWS&SB.The water requirement of the project during occupation stage is in the order of 1601.9KLD.

The water requirement for the project during the occupation stage is presented in table2.5. The water savings for the project is presented in table 2.5.

Page 11: Janapriya Engineers Syndicate Pvt. Ltd.environmentclearance.nic.in/writereaddata/FormB/EC/Risk...RAMP DOWN TO CELLAR RAMP UP TO GROUND FLOOR M.H RAMP DN TO CELLAR 33.00M M.H M.H M

Janapriya Engineers Syndicate Pvt. Ltd. Environmental Impact Assessment

Team Labs and Consultants2 - 10

Table 2.5 Water Requirement of the Project

Land Use No. ofUnits

No. ofPersons/

unit

Waterrequirement per

person in l *

Total WaterRequirement

in KLDBlocks 2246 5 135 1516.1Amenities 1 300 45 13.5Swimming pool 1 5.0Visitors 2 15 67.4TOTAL 1601.9*Water requirement as per NBC

Table 2.6 Water Savings of the Project

Land UseNo.of

Units

No. ofPersons/

unit

WaterRequirement

KLD

Treatedwater

reuse/day @40 klpd

EffectiveWater

Requirementin KLD

Blocks 2246 5 1516.1 505.4 1010.7Amenities 1 300 13.5 6.0 7.5Swimming pool 5.0 5.0Visitors 2 67.4 44.9 22.5TOTAL 1601.9 556.3 1045.7

Table 2.7 Water BalanceInput KLD Output KLDDomestic water from HMWSSB 1045.7 Excess treated water will be

sent to sewer lines 706.3

Recycled water 556.3 Recycled water 556.3Water requirement for greenbelt during non monsoon 19.0Losses approx 20% 320.4

Total 1601.9 Total 1601.9

The water used in the order of 1601.9 KL/day would generate 1281.5 KL/day ofwastewater, which has to be treated for reuse and or disposal. The effluentcharacteristics of wastewater are presented in table 2.8.

Sewage treatment plant based on SEQUENTIAL BATCH REACTOR (SBR) technology

Description of Sewage Treatment Plant Sequential Batch Reactors (SBR)IntroductionThe Sequential Batch Reactor (SBR) is a modification of activated sludge processdesigned to operate under non-steady state conditions also. An SBR operates in a truebatch mode with aeration and sludge settlement both occurring in the same tank. Themajor differences between SBR and conventional continuous-flow, activated sludgesystem is that the SBR tank carries out the functions of equalization, aeration and

Page 12: Janapriya Engineers Syndicate Pvt. Ltd.environmentclearance.nic.in/writereaddata/FormB/EC/Risk...RAMP DOWN TO CELLAR RAMP UP TO GROUND FLOOR M.H RAMP DN TO CELLAR 33.00M M.H M.H M

Janapriya Engineers Syndicate Pvt. Ltd. Environmental Impact Assessment

Team Labs and Consultants2 - 11

sedimentation in a time sequence rather than in the conventional space sequence ofcontinuous-flow systems. In addition, the SBR system can be designed with the abilityto treat a wide range of influent volumes whereas the continuous system is basedupon a fixed influent flow-rate. Thus, there is a degree of flexibility associated withworking in a time rather than in a space sequence.

SBR’s produce sludge’s with good settling properties, provided the influent wastewateris admitted into the aeration in a controlled manner. Controls range from a simplifiedfloat and timer based system with a PLC to a PC based SCADA system with colorgraphics using either flow proportional aeration or dissolved oxygen controlledaeration to reduce aeration to reduce energy consumption and enhance the selectivepressures for BOD, nutrient removal, and control of filaments. An appropriatelydesigned SBR process is a unique combination of equipment and software. Workingwith automated control reduces the number of operator skill and attentionrequirement.

The majority of the aeration equipment of Sequential batch reactors consists of jet, finebubble, and coarse bubble aeration systems.

The SBR process can be controlled with simple manual trained labor with out any PLC,SCADA, as the labor cost is cheap in India. Simple timer switches, can be introduced forthe Indian conditions of sustainability. This system can adopt to the changes in theinfluent quality of wastewater than any other process due to the change in the use ofthe chemicals / procedures as in case of the Hotels/ laundries etc.

Sequential Batch Reactor Process CyclesThe operating principles of a batch activated sludge process, or SBR, are characterizedin six discrete periods:

1. Anoxic Fill2. Aerated fill3. React4. Settle5. Decant6. Idle.

Anoxic FillThe influent wastewater is distributed throughout the settled sludge through theinfluent distribution manifold to provide good contact between the microorganismsand the substrate. The influent can be either pumped in or allowed to flow in bygravity. Most of this period occurs without aeration to create an environment thatfavors the procreation of microorganisms with good settling characteristics. Aerationbegins at the beginning of this period.

Aerated FillMixed liquor is drawn through the manifold, mixed with the influent flow in the motiveliquid pump, and discharged, as motive liquid, to the jet aerator. This initiates the feastperiod. Feast is when the microorganisms have been in contact with the substrate and

Page 13: Janapriya Engineers Syndicate Pvt. Ltd.environmentclearance.nic.in/writereaddata/FormB/EC/Risk...RAMP DOWN TO CELLAR RAMP UP TO GROUND FLOOR M.H RAMP DN TO CELLAR 33.00M M.H M.H M

Janapriya Engineers Syndicate Pvt. Ltd. Environmental Impact Assessment

Team Labs and Consultants2 - 12

a large amount of oxygen is provided to facilitate the substrate consumption.Nitrification and denitrification occurs at the beginning of this stage. This period endswhen the tank is either full or when a maximum time for filling is reached.

ReactDuring this period aeration continues until complete biodegradation of BOD andnitrogen is achieved. After the substrate is consumed famine stage starts. During thisstage some microorganisms will die because of the lack of food and will help reduce thevolume of the settling sludge. The length of the aeration period determines the degreeof BOD consumption.SettleAeration is discontinued at this stage and solids separation takes place leaving clear,treated effluent above the sludge blanket. During this clarifying period no liquidsshould enter or leave the tank to avoid turbulence in the supernatant.

DecantThis period is characterized by the withdrawal of treated effluent from approximatelytwo feet below the surface of the mixed liquor by the floating solids excludingdecanter. This removal must be done without disturbing the settled sludge.

IdleThe time in this stage can be used to waste sludge or perform backwashing of the jetaerator. The wasted sludge is pumped to an anaerobic digester to reduce the volume ofthe sludge to be discarded. The frequency of sludge wasting ranges between once eachcycle to once every two to three months depending upon system design.

Aeration Equipment:As usual with 'Activated sludge process'

ConclusionWastewater treatment has been a challenge throughout the years due to varyinginfluent chemical and physical characteristics and stringent effluent regulations.Treatment systems using activated sludge have been able to handle many of thesedifficulties. Given the lack of on-line computer controls, continuous flow systems havebeen mostly used for these purposes versus Sequential batch processes. The availabilityof artificial intelligence has now made the option of a SBR process more attractive thusproviding better controls and results in wastewater treatment. This is coupled by theflexibility of a SBR in the treatment of variable flows, minimum operator interactionrequired, option for anoxic or anaerobic conditions in the same tank, good oxygencontact with microorganisms and substrate, small floor space, and good removalefficiency.

Sequential batch reactors operate by a cycle of periods consisting of fill, react, settle,decant, and idle. The duration, oxygen concentration, and mixing in these periods couldbe altered according to the needs of the particular treatment plant. Appropriateaeration and decanting is essential for the correct operations of these plants. Theaerator should make the oxygen readily available to the microorganisms. The decanter

Page 14: Janapriya Engineers Syndicate Pvt. Ltd.environmentclearance.nic.in/writereaddata/FormB/EC/Risk...RAMP DOWN TO CELLAR RAMP UP TO GROUND FLOOR M.H RAMP DN TO CELLAR 33.00M M.H M.H M

Janapriya Engineers Syndicate Pvt. Ltd. Environmental Impact Assessment

Team Labs and Consultants2 - 13

should avoid the intake of floating matter from the tank. The many advantages offeredby the SBR process justify the recent increase in the implementation of this process inindustrial and municipal wastewater treatment.

Table 2.9 Characteristics of Waste waterParameter Quantity in mg/l

PH 6 – 7Total Suspended Solids 400 – 600BOD 200 – 300COD 450 – 500

Design of the unitBasic dataCapacity : 1600 m3/day or KLDFlow : 1281 m3/dayInfluent BOD : 350 mg/litInfluent Suspended Solids : 300 mg/litInfluent COD : 600 mg/litEffluent BOD : 30 mg/litEffluent COD : 200 mg/litEffluent Suspended Solids : 100 mg/lit

1. Bar Screen ChamberAverage flow : 0.0185 m3/secPeak factor : 3.5Peak flow : 0.0648 m3/secVelocity at peak flow : 0.75 m/SecEffective area of screen RequiredAt average flow : 0.0616 m2

At Peak flow : 0.0864 m2

Provide Effective area of screen : 0.0864 m2

Considering the bar of dia. 10 mm(w) and clear spacing of 20 mm (b)Overall area required : 0.129 m2

Considering screen depth as : 0.5 mNumber of clear spacing : 12.96Number of bars : 13 Consider 15 Nos.Hence Provide 5 barsProvide a screen of 0.5 m X 0.5 m at an inclination of sin 600. In a screen channel of onemeter (1 m) length.2. Oil & Grease Trap (O & G)Flow Rate : 1600.0 m3/day or KLDAverage flow/Hourly flowPeak factor : 2.50Peak flow : 166.67 m3/hr

Page 15: Janapriya Engineers Syndicate Pvt. Ltd.environmentclearance.nic.in/writereaddata/FormB/EC/Risk...RAMP DOWN TO CELLAR RAMP UP TO GROUND FLOOR M.H RAMP DN TO CELLAR 33.00M M.H M.H M

Janapriya Engineers Syndicate Pvt. Ltd. Environmental Impact Assessment

Team Labs and Consultants2 - 14

Retention Period : 6.00 min

Volume of the tank : 16.67 m3 (Say 7.5 m3)Side water depth : 1.00 mSurface Area required : 16.67 m2

length of the tank : 3.00 m (Say 3.0 m)Width of the tank : 5.56 m (Say 6.0 m)

3. Equalization tank:The flow from the bar screen chamber is let into the equalization tank of minimum2hours capacity. This tank is provided to even out the flow variation, and to provide acontinuous feed into the secondary biological treatment units.Peak flow : 166.67Hydraulic retention time : 3 hrs. at peak flowVolume of the tank : 500.0 m3

Assuming depthArea : 142.9 m2

length of the tank : 10.0 mwidth of the tank : 14.3 m (Say 6.5 m)Area required 142.86 m2Diffuser required 95.2 Nos.Diffuser adopted 40.0 Nos.Diffuser size 5" dia. disk diffuserair required 200.0 m3/h

4. SEQUENTIAL BATCH REACTOR (SBR):The polypropylene media have been provided with a specific surface area of 350 – 520m2 /m3. This allows micro-organisms to get attached and biomass concentration can beincreased to four folds as compared to Activated Sludge Process. This enables toconsider higher Organic loading rates.

The micro-organisms attached to media are kept in a fluid state thereby maintainingthe CSTR (continuous Stirrer tank reactor) regime as well as two tanks are provided inseries making the plug – flow system. This will enhance the efficiencies and have themerits of both CSTR and plug-flow regimes.Flow Rate : 1600 m3/day or KLDVolume of SBR tank : 1280 KLD (80% of STP capacity)

No. of tanks in series : 2 mCapacity of each Tank : 800 KLDNumber of Batch Per day : 5 /day/tankBatch Volume : 160.00Fill Fraction : 0.28Reactor Volume Required : 571.4Water Depth : 3.70Surface Area Required : 154.4 m²

Page 16: Janapriya Engineers Syndicate Pvt. Ltd.environmentclearance.nic.in/writereaddata/FormB/EC/Risk...RAMP DOWN TO CELLAR RAMP UP TO GROUND FLOOR M.H RAMP DN TO CELLAR 33.00M M.H M.H M

Janapriya Engineers Syndicate Pvt. Ltd. Environmental Impact Assessment

Team Labs and Consultants2 - 15

width required : 8.0 meterLength required : 19.3 meterArea Proposed : 154.44Diffuser reqd. : 57.92Diffuser proposed : 26.00Total diffuser required : 52.00Diffusers size : 2 m long tubular diffuserAir Required :Inlet BOD : 350Batch volume : 160.0BOD load Per batch : 56.0Oxygen required : 86.80Aeration Time : 2.4Oxygen Required Rate : 36.17Field correction Factor : 0.51SOTR : 70.92SOTE : 0.06Water Depth : 3.50Air Required per tank : 1223.52Air RequiredTotal Air required (Eq. Tank + SBR tank) : 750.00Add for others (10%) : 75.00Grand Total : 825.00Proposed Blower Capacity : 850

5. Sludge Holding tankNo. of Tanks : 1.00Sludge weight : 126.00Hydraulic retention time : 48.00Sludge volume : 12.60SHT Volume : 25.20Water Depth : 2.50surface Area : 10.08Length : 5.00Width reqd. : 2.02surface area adopted : 10.08diffuser required : 5.04diffuser adopted : 5.00diffuser size : 5"disk diffuserAir Required : 25.00 m3/hr

6. Multi Grade Filtersurface loading rate : 15 m³/m²/HrFiltration rate proposed : 39 m³/HrNos. of filter : 1filtration rate of each filter : 39 m³/HrArea Required : 2.6 m²

Page 17: Janapriya Engineers Syndicate Pvt. Ltd.environmentclearance.nic.in/writereaddata/FormB/EC/Risk...RAMP DOWN TO CELLAR RAMP UP TO GROUND FLOOR M.H RAMP DN TO CELLAR 33.00M M.H M.H M

Janapriya Engineers Syndicate Pvt. Ltd. Environmental Impact Assessment

Team Labs and Consultants2 - 16

Dia Required : 1819.9 mmDia Adopted : 1850 mmHOS : 1800 mm

7. Activated Carbon Filter:Vertical down flow type with graded/sand bed under drain plate with polysterenestrains.Surface loading rate : 15 m³/m²/HrFiltration rate proposed : 39.0 m³/HrNos. of filter : 1.0filtration rate of each filter : 39.0 m³/HrArea Required : 2.60 m²Dia Required : 1819.9 mmDia Adopted : 1850 mmHOS : 1800 mmProvide Activated Carbon filter of 3200 mm dia with granular Activated carbon asmedia and 3500 mm HOS with sand as media layer, under drain pipe, laterals facepiping etc for each stream.

8.Ultraviolet Disinfection:UV applied to low turbidity water is a highly effective means of disinfection. UV is notharmful to aquatic organisms in the receiving water. UV light kills viruses, Vegetative-and spore-forming bacteria, algae and yeasts. No chemicals are added to thewastewater to change the pH, conductivity, odor or taste to create possible toxiccompounds. UV treatment has a few moving parts to adjust or wear out.

9.Final Treated Water Holding TankIt is always preferred to provide one final holding tank of minimum one day holdingcapacity, so that the treated effluents can be stored and used back for gardening orother tertiary purposes.Capacity: 1600 m3

10. Sludge Filter Press:The biomass in the aeration tank stabilizes BOD in wastewater by consuming theorganic matter in the wastewater. The metabolic activity results in growth of thebiomass population in the Fluidized Aerobic Bio Reactor (FAB). Sludge holding tank hasbeen provided with filter press for dewatering sludge. The filtrate drains off throughthe media, which is again let into equalization tank. The dewatered sludge is collectedin trays, which can be used as manure in the garden.No. of plates : 24Size of plates : 600 mm X 600 mmPlate moc (material of construction) : PP (poly propline)

Page 18: Janapriya Engineers Syndicate Pvt. Ltd.environmentclearance.nic.in/writereaddata/FormB/EC/Risk...RAMP DOWN TO CELLAR RAMP UP TO GROUND FLOOR M.H RAMP DN TO CELLAR 33.00M M.H M.H M

Janapriya Engineers Syndicate Pvt. Ltd. Environmental Impact Assessment

Team Labs and Consultants2 - 17

Type of operation : HydraulicPower pack capacity : 2 HP

The biomass in the aeration tank stabilizes BOD in wastewater by consuming theorganic matter in the wastewater. The metabolic activity results in growth of thebiomass population in the Sequential Batch Reactors (SBR)

Sludge holding tank has been provided with filter press for dewatering sludge. Thefiltrate drains off through the media, which is again let into equalization tank.

The dewatered sludge is collected in trays, which can be used as manure in the garden.

Characteristics of Treated Waste waterParameter Quantity in mg/l

pH 7 – 8Total Suspended Solids < 50BOD 20COD < 50

Disposal of Treated Waste Water: It is proposed to reuse the treated wastewater forgreen belt development and for toilet flushing. Excess treated water shall be let outinto the municipal sewer line. It is proposed to release/dispose the storm water in thestorm water drains.

Page 19: Janapriya Engineers Syndicate Pvt. Ltd.environmentclearance.nic.in/writereaddata/FormB/EC/Risk...RAMP DOWN TO CELLAR RAMP UP TO GROUND FLOOR M.H RAMP DN TO CELLAR 33.00M M.H M.H M

Janapriya Engineers Syndicate Pvt. Ltd. Environmental Impact Assessment

Team Labs and Consultants2 - 18

Fig 2.5 Sewage Treatment Plant

Page 20: Janapriya Engineers Syndicate Pvt. Ltd.environmentclearance.nic.in/writereaddata/FormB/EC/Risk...RAMP DOWN TO CELLAR RAMP UP TO GROUND FLOOR M.H RAMP DN TO CELLAR 33.00M M.H M.H M

Janapriya Engineers Syndicate Pvt. Ltd. Environmental Impact Assessment

Team Labs and Consultants2 - 19

2.2.1.3 Solid WasteMunicipal Solid Waste CompositionIn India the biodegradable portion dominates the bulk of Municipal Solid Waste.Generally the biodegradable portion is mainly due to food and yard waste. The table 2.9presents Composition of Municipal Solid Waste.

Table 2.9 Composition of Municipal Solid WasteType Composition (%) Solid waste in kg

Paper 8 564Plastics 9 635Metals 1 71Glass 1 71others 4 282Biodegradable 48 3385Inerts 25 1763Rags 4 282Total 100 7053

Source: (NSWAI: National Solid Waste Association of India)

Design StageThe total number of people anticipated to stay in the housing project is in the range of16200. The anticipated solid waste/garbage is in the range of 500 g/head, and the totalgarbage will be in the order of 7053 kg/day. The present practice is to collect thegarbage from each house using the services of Maintenance department and send it tothe segregation point by cycle-rickshaws. The biodegradable garbage after segregationis composted at the segregation point and the remaining waste is sent to the landfill.The landfill site is yet to obtain clearance under Municipal solid waste rules of MoE&F,GOI. The table 2.10 presents the aniticpated garbage quantity after occupation. Theresponsibility of garbage collection and disposal lies with the Greater HyderabadMunicipal Corporation, however the project authorities propose to educate theresidents to segregate the waste at source before disposal.

Table 2.10 Solid Waste Generation

Land Use No. ofUnits

No. ofPersons/unit

Total No. ofPersons

Total Solidwaste in Kgs

Blocks 2246 5 11230 5615Amenities 1 300 300 90Visitors 2 4492 1348

TOTAL 7053

2.2.2 CONSTRUCTION STAGEThe sequence of construction operations and the approximate time requirement ispresented in the following table 2.11. The construction sequence is for the flatsconstruction. The time schedule of the entire project is approximately 48 months.

Page 21: Janapriya Engineers Syndicate Pvt. Ltd.environmentclearance.nic.in/writereaddata/FormB/EC/Risk...RAMP DOWN TO CELLAR RAMP UP TO GROUND FLOOR M.H RAMP DN TO CELLAR 33.00M M.H M.H M

Janapriya Engineers Syndicate Pvt. Ltd. Environmental Impact Assessment

Team Labs and Consultants2 - 20

Table 2.11 Construction Sequence for the HousingS.NO Description of work

1 Clearing and Grubbing2 Leveling by way of cut and fill3 Construction of Retaining wall4 Earth Work Excavation for Foundations.5 P.C.C. Bed for Foundations.6 R.C.C. for Foundations & Columns up to Plinth Beam Level7 R.C.C. Plinth Beams, Staircase First Flight & Sump8 R.C.C. Columns up to First Slab9 1st Slab Shuttering, Fabrication of Reinforcement & Concreting

10 Columns up to 2nd slab11 2nd Slab Shuttering, Fabrication of Reinforcement & Concreting12 1st Slab De-shuttering & Cleaning13 Columns up to Typical Slabs14 Earth filling for Flooring Bed & P.C.C. Bed15 Typical Slabs Shuttering, Fabrication of Reinforcement & Concreting16 2nd Slab De-shuttering & Cleaning17 Typical Slabs De-shuttering & Cleaning seimentinusly18 Water proofing for Sunken Slabs19 Brick work up to lintel height20 Electrical Concealed works

Electrical conduit junction boxes & board fixing.21 Plumbing Concealed works22 R.C.C. Lintels & Chajjas Shuttering, Reinforcing & Concreting23 Brick Work up to roof beam height24 Chajjas De-shuttering25 First Coat Ceiling Plastering26 Columns up to Staircase Head Rooms, lift machine rooms & Over head tanks27 Slab shuttering, Reinforcing & Concreting for above items28 De-shuttering for above items29 Electrical Concealed works

Electrical conduit junction boxes & board fixing for above items30 Plumbing Concealed works for above items31 First Coat Internal Plastering32 Door & Window Frame Fixing33 Masonry work in Elevation34 First Coat External Plastering35 Masonry work for Cupboards & internal finishes36 Internal & External Railings Fixing37 Second Coat Ceiling Plastering38 Second Coat Internal plastering39 Internal flooring, Skirting & Dadoing works40 Internal & External Electrification41 Internal & External Plumbing, Sanitary works

Page 22: Janapriya Engineers Syndicate Pvt. Ltd.environmentclearance.nic.in/writereaddata/FormB/EC/Risk...RAMP DOWN TO CELLAR RAMP UP TO GROUND FLOOR M.H RAMP DN TO CELLAR 33.00M M.H M.H M

Janapriya Engineers Syndicate Pvt. Ltd. Environmental Impact Assessment

Team Labs and Consultants2 - 21

S.NO Description of work42 Internal & External Flooring Finishes (incl. kitchen platforms)43 Doors & Window Shutter Fixing44 Parapet wall in terrace & Other miscellaneous works45 Terrace Water proofing works46 Finishes to Staircase Head Rooms, lift machine rooms & Over head tanks47 Second Coat External Paintings48 External Development, (Parking area flooring, Compound wall finishing)49 Internal & External Railing Paintings & Compound wall painting50 Amenities Fixing (Transformer & etc.,)

The clearing and grubbing activity involves clearing of 104 trees and shrubs mainly asthe greenery is not disturbed in the layout plan. The cut and fill operation for the entirearea is presented in table 2.13. There is excess cut material which would be used forthe purpose of aggregate for the construction purpose.

Table 2.13 Earth Work Quantities

Area Qty of fill (m3) Qty of cut (m3) SurplusFill(m3)

SurplusCut(m3)

Site area 49475 61843 --- 12369

The cut material contains mainly granite stones, which is suitable for aggregatepurpose. The excess cut material if any will be used for the purpose of aggregate forRCC and dust for flooring.

The construction of this magnitude would require huge quantities of constructionmaterials. The material requirement for the project is presented in table 2.14.

Table 2.14 Material Consumption for Total Units of Housing

UnitsBUA perunit in(m2)

Total ReadyMix

Concrete(m3)

TotalCement(bags)

TotalSand(m3)

TotalAggregate(m3)

TotalWater(m3)

TotalBricks(Nos) x1000

TotalReinforcement

Steel(MT)

Total BUA 255922 104928 238007 99810 11005 61933 29687 5886Total 255922 104928 238007 99810 11005 61933 29687 5886

Thus aggregate requirement will be met from within the Local Market. The leaddistance for various construction materials is presented in table 2.15.

2.2.2.1 Water RequirementThe water required for this project is in the order of 62000 cum for the entire projectimplementation period. The peak demand for water may be 200 m3/day, howevertypical daily consumption will be in the order of 100 m3/day. The required water will bedrawn from ground water sources/bulk suppliers/municipal tankers. The water supply

Page 23: Janapriya Engineers Syndicate Pvt. Ltd.environmentclearance.nic.in/writereaddata/FormB/EC/Risk...RAMP DOWN TO CELLAR RAMP UP TO GROUND FLOOR M.H RAMP DN TO CELLAR 33.00M M.H M.H M

Janapriya Engineers Syndicate Pvt. Ltd. Environmental Impact Assessment

Team Labs and Consultants2 - 22

and plumbing will be optimized and low water consuming faucets and flush tanks willbe used to conserve water.

Table 2.15 Lead Distance for Construction MaterialsS.No Material Source Lead Distance (Km)

1Sand ROBOSAND and or Krishna or

Godavari river bed areaspermitted by Govt.

150 – 240

2 Aggregate From quarries 20-303 Cement Manufacturing units 140 – 2004 Reinforcement Steel SAIL/TATA godowns 3.55 Bricks Local Suppliers 306 Plumbing Material Local suppliers 2 – 77 Electrical Material Local Suppliers 2 – 78 Sanitary Material Local suppliers 2 – 7

9 Flooring andPavement Tiles

Manufacturers 12 – 150

10 Paints Local Manufacturers 10 – 2511 Ready Mix Concrete Local Batch Plants 5 – 10

2.2.2.2 Construction DebrisThe construction debris consists of various types of materials. The construction debriswill be in both hazardous and non hazardous categories. The hazardous debris consistsof empty containers of adhesives, thinners, paints, petroleum products. These emptycontainers will be sold to authorized recyclers. The non hazardous wastes containrecyclable debris like iron and other metal, glass, plastics, cartons of paper, wood etc.These wastes will be sent for reuse/recycle. The waste percentage will be in the orderof 2%. Construction debris containing bricks, will be used for land grading/ in the placeof subgrade.

2.2.2.3 PaintsAll the paints used in the premises will be ensured to have an albedo of at least 0.4 toincrease the reflectivity and reduce the heat dissipation and heat island effects.

2.2.2.4 Work Force:The labor/work force requirement is approximately 3000 man days of various skilledand unskilled employees. Sufficient labor force and skilled employees are available asHyderabad is a favorite destination of skilled employees and migrating people from therural areas. The peak labor force requirement will be in the order of 400 people andsome of the labor force will be provided with temporary accommodation within thesite. The labor force will be provided with a temporary toilet facilities connected to aseptic tank followed by soak pit. The labor accommodation will provide accommodationto about 200 families. The water requirement for the labor force will be approximately30000 lt/day.

Page 24: Janapriya Engineers Syndicate Pvt. Ltd.environmentclearance.nic.in/writereaddata/FormB/EC/Risk...RAMP DOWN TO CELLAR RAMP UP TO GROUND FLOOR M.H RAMP DN TO CELLAR 33.00M M.H M.H M

Janapriya Engineers Syndicate Pvt. Ltd. Environmental Impact Assessment

Team Labs and Consultants2 - 23

2.2.2.5 Material preparation and transportMost of the construction material including aggregate will be drawn from outside. Thematerial will be transported by trucks and the approximate number of truck trips are500. The material transport within the site will be facilitated by required number oftippers. All grades of concrete will be procured from RMC suppliers. No stone crushershall be installed at site. Aggregate for Road, pavements and floorings shall be procuredthrough the metal suppliers in the required quantities.

2.2.2.6 Batching PlantThe required concrete will be prepared in a batching plant to be located temporarily inthe site so as to maintain the quality and reduce the lead distance. The capacity of thebatching plant will be 20 m3 to 30 m3/hr. The raw mix design (Cement: sand: coarseaggregates: water: admixture) is stored in electronic panel board and the quantities areweighed automatically as per the design mix. Aggregates in the sizes of 10 mm, 20 mmis stacked in separate bins and these materials are loaded into the hopper by scrapperand load cells. Cement is provided to the mix through silos (30 MT to 40 MT capacity)with the help of screw conveyor. Measured quantity of water and admixture is fed intohopper though load cells. In the hopper coarse aggregates, fine aggregates, cement,water and admixture gets mixed in required quantities by rotary motion of the mixerand after proper mixing it is unloaded into transit mixers at the rate of 0.5 m3/minute.The water consumption for this process is approximately 160 lts/m3 of concrete. Theentire operation is closed and there is no scope of fugitive dust as the operation is wetin nature.

2.2.2.7 Stone CrusherThe required aggregate will be drawn from within the site from a temporary stonecrusher. The capacity of the stone crusher is 100 tons/hour. The stone crusher will usethe rocky boulders removed during the cut operations and used for the production ofaggregates of various sizes. The main raw material is boulders obtained from within thesite during clearing operations of the land and conveyed by tippers & dumpers to theplant site. All the crushing units are mobile and electrically operated. The boulder ischarged into the hopper with help of dumper. The boulders are crushed and screenedto required size with help of screens and carried by belt conveyors to the storage yard.The dust and the aggregate of less than 8.5 mm size will be used for road constructionand as sub base for flooring purpose instead of sand. All the silos and the conveyor beltswill be covered and the transfer points will be provided with water sprinkling. Thewater requirement for this plant is approximately 5 cum/day.

2.2.3 OCCUPATION PHASEA number of facilities will be provided by M/s Janapriya Engineers Syndicate Pvt. Ltd.,for the occupants and the facilities are shown in table 2.15

Page 25: Janapriya Engineers Syndicate Pvt. Ltd.environmentclearance.nic.in/writereaddata/FormB/EC/Risk...RAMP DOWN TO CELLAR RAMP UP TO GROUND FLOOR M.H RAMP DN TO CELLAR 33.00M M.H M.H M

Janapriya Engineers Syndicate Pvt. Ltd. Environmental Impact Assessment

Team Labs and Consultants2 - 24

Table 2.16 Amenities ProposedAmenity Nos. or description

Community Center 1STP 1Green Area 7424.8 m2

DG Sets 500 Kva X 10 nos.

The owners/purchasers will form cooperatives to run the all amenities like sewagetreatment plant, DG sets. The major requirement of resource is for electricity andwater. The electricity will be drawn from TRANSCO. Transformers will be provided toreduce voltage fluctuation and to provide quality energy. The power requirementduring operation phase is presented in table 2.17

Table 2.17 Electricity Consumption Statement

S.No. DescriptionNo. ofUnits Load in KW

TotalConnected

Load(KW)

TotalConnected

Load(kVA)

Total MaxDemand

(KVA)1 Blocks 2246 6 13476.0 16845.0 16845.02 Street Lights 90 0.04 3.6 4.5 3.63 Amenities 297.9 372.3 297.94 STP 1 95 95.0 118.8 118.85 Lifts 7 15 105.0 131.3 131.3

TOTAL 13977.5 17471.8 17396.5Maximum demand in kw at 0.6 diversity factor 8386.5Consumption of power for 8 hours per day 67091.9Maximum demand in kw at 0.2 diversity factor 2795.5Consumption of power for 16 hours per day 44727.9Total consumption of power per day 111819.8 KWTotal consumption of power per year 408.1 Lakh Units

Table 2.18 Energy Saving by using Solar Water Heater

S.No Description No. ofUnits

Powerallocated inwatts / unit

Total powerrequired in

(KW)1 Blocks 890 2500 2225

TOTAL 2225Maximum demand in kw at 1 diversity factor 2225Consumption of power for 2 hours per day 4450Maximum demand in kw at 0.4 diversity factor 890Consumption of power for 2 hours per day 1780Total consumption of power per day 6230.0 KWTotal consumption of power per year 22.74 Lakh Units

Page 26: Janapriya Engineers Syndicate Pvt. Ltd.environmentclearance.nic.in/writereaddata/FormB/EC/Risk...RAMP DOWN TO CELLAR RAMP UP TO GROUND FLOOR M.H RAMP DN TO CELLAR 33.00M M.H M.H M

Janapriya Engineers Syndicate Pvt. Ltd. Environmental Impact Assessment

Team Labs and Consultants2 - 25

Table 2.19 Energy Saving by using Solar Street Lights

S.No Description No. ofUnits

Powerallocated inwatts / unit

Total powerrequired in

(KW)1 Street lights 30 40 1.2

TOTAL 1.2Maximum demand in kw at 0.6 diversity factor 0.7Consumption of power for 8 hours per day 6Maximum demand in kw at full load 1Consumption of power for 4 hours per day 5Total consumption of power per day 10.6 KWTotal consumption of power per year 0.04 Lakh Unitssaving with Solar Heater and Street Lighting 22.78 Lakh Units

Table 2.20 Electrical Power savings using CFL for lighting

S.No Description Area inm2

Powerallocated inwatts / unit

Total powerrequired in

(KW)1 Residential 178779 10 17882 Common & Utilities 77143 4 309

TOTAL 2096Maximum demand in kw at 0.9 diversity factor 1887Consumption of power for 12 hours per day 22641Total consumption of power per day 22640.7 KWTotal consumption of power per year 82.64 Lakh UnitsSavings in power using CFL 24.79 Lakh Units

Table 2.21 Savings in Electrical Power Consumption – SUMMARY

S.No Description WithCFL

With SolarHeater and

StreetLighting

TotalConsumption

lakh unitsTotal Saving

1 Savings in lakhkwh units 24.79 22.78

408.1447.57

2 Savings inpercentage (%) 6.07 5.58 11.7

2.2.3.1 Domestic WaterThe domestic water will be drawn from HMWSSB and during non availability ofmunicipal water supply, ground water will be drawn and used to augment the supplies.The waste water will be treated and reused for gardening and flush tanks. The lineproviding grey water will be colored blue and ensured that the tank is at least 1 footbelow the level of other tanks and a distance of minimum 2 feet from the other waterpipelines.

Page 27: Janapriya Engineers Syndicate Pvt. Ltd.environmentclearance.nic.in/writereaddata/FormB/EC/Risk...RAMP DOWN TO CELLAR RAMP UP TO GROUND FLOOR M.H RAMP DN TO CELLAR 33.00M M.H M.H M

Janapriya Engineers Syndicate Pvt. Ltd. Environmental Impact Assessment

Team Labs and Consultants2 - 26

2.2.3.2 Solid WasteThe solid wastes anticipated during occupation stage include garbage, sludge from STP,hazardous waste of used oils, and batteries from generators. The quantity of wastes ispresented in table 2.22.

Table 2.22 Solid Waste Generated during Occupation PhaseS.No Type of

WasteQuantity Collection/storage Disposal

1 Garbage 7053kg/day

Segregation at source intobio-degradable, non bio-degradable and DomesticHazardous wastes. Disposal ofrecyclable waste toAuthorized Waste Pickers /Authorized Recyclers.Balance segregated wastegiven to Authorized Agency ofLocal Body.

Municipal solidwaste disposal

2Sewage

TreatmentPlant Sludge

80kg/day Stored in HDPE bags. Used as manure and

or given to farmers.

3 UsedBatteries

15 nos.year

Sent to Authorizedrecyclers or returned

to seller

4 UsedLubricant

250l/year Stored in HDPE Carbouy Sold to authorized

recyclers

5 TransformerOil

300l/year Stored in HDPE Drum

Sold to TRANSCOauthorizedcontractors

Page 28: Janapriya Engineers Syndicate Pvt. Ltd.environmentclearance.nic.in/writereaddata/FormB/EC/Risk...RAMP DOWN TO CELLAR RAMP UP TO GROUND FLOOR M.H RAMP DN TO CELLAR 33.00M M.H M.H M

Janapriya Engineers Syndicate Pvt. Ltd. Environment Management Plan

Team Labs and Consultants8 - 1

8.0 ENVIRONMENT MANAGEMENT PLAN

The M/s Janapriya Engineers Syndicate Pvt. Ltd., envisaged constructing residentialunits. The project is envisaged to develop 5.15 hectares of land in Survey Nos. 663(P),668(P), 671(P), Kapra, Medchal -Malkajgiri District.

8.1 PROJECT DETAILS

The project is envisaged to develop 5.15 hectares of land in Survey Nos. 663(P), 668(P),671(P), Kapra, Medchal -Malkajgiri District into residential units for various socioeconomic sectors. The project would cater to various market demands and needs of thepeople. The project site is surrounded open lands in all the directions except in Northdirection. An existing 18 m wide road connecting Bank colony. The nearest railwaystation is Ammuguda railway station at a distance of 3.6 km.

8.2 MAJOR FINDINGS OF THE EIAAn EIS was conducted and the major findings of the EIA study are presented below

8.3 Environmental ImpactsImpact on Physical ResourcesConstruction of proposed project requires huge quantities of natural resources likesand, sub grade and aggregate, and materials produced from natural resources likebricks, cement and steel. The material shall be drawn from local sources, and the leaddistances range from 1 – 250 km. The impacts on physical resources of sand will beirreversible while bricks will be brought from kilns which use Coal ash. The materialrequirement of steel, cement etc. will be purchased from manufacturers with in state.Hence, no major impacts on physical resources as regards the availability andprocurement of construction material are anticipated due to the project.

Impacts on Air QualityImpacts on air quality during construction stage are likely to be due to operation ofconstruction yards, material transport on trucks and fugitive emissions from theconstruction sites. The model results for occupation stage show slight increase in theair quality and in worst concentrations are falling within the site, and the results arewith in the prescribed limits. Mitigation measures required for offsetting the air qualityimpacts are presented in the table 8.1 Environment Management and Action Plan.

Impacts on Noise QualityImpacts on noise quality during construction stage will be significant. Hence theconstruction near the habitation is proposed only during daytime. The impacts duringoccupation stage will be on the plots near to the main entrance. Construction workerswill be provided with protection equipment to guard against the noise impacts. Noisemitigating measures will be suggested for construction equipment and DG sets.

Impact on FloraThe project site and its surroundings do not form a habitat to any endangered flora.There are no trees within the project site due to anthropogenic pressures. The project

Page 29: Janapriya Engineers Syndicate Pvt. Ltd.environmentclearance.nic.in/writereaddata/FormB/EC/Risk...RAMP DOWN TO CELLAR RAMP UP TO GROUND FLOOR M.H RAMP DN TO CELLAR 33.00M M.H M.H M

Janapriya Engineers Syndicate Pvt. Ltd. Environment Management Plan

Team Labs and Consultants8 - 2

will enhance the aesthetics of the site due to the provision of avenue plantation andcentral greening. This would ensure minimum impact on flora.

Impact on FaunaAs there are no endangered species of wild life in and around the project site, it is likelyto have minimal impact. The avifauna will find abode on the trees proposed to beplanted. This would enhance the aesthetics of the area. Pet animal faeces should notenter the storm water drains.

Impact on Land useThere is no land acquisition for this project. The land use of the site fallow land andclassified as residential by GHMC/HMDA. However the topography of the land beingrocky plains involves cut and fill operation. Erosion and sedimentation are impactsanticipated during construction. Mitigation measures shall be adopted to avoid thesame. The area development would increase the housing activity in the surroundings,which is a positive impact, as barren lands will be used for productive usage, and thenegative impacts will be pressure on the infrastructure facilities.

Impact on Surface Water ResourcesThe degradation of water quality can occur during construction phase from increasedsediment load into watercourses near the construction site. Suitable mitigationmeasures proposed, as part of the EMP will ensure that the residual impacts areminimal. Storm water runoff would increase due to the increase in impervioussurface, and rainwater harvesting structures will be provided as mitigation measure.The design of the storm water drain will consider the additional runoff. The urbanstorm water joining the storm water drains may carry pollutants from impervioussurfaces.

Impact on Ground Water ResourcesGround water shall be drawn during construction, and will be used to augment themunicipal supply during non-monsoon season if necessary. Exploitation of groundwater will have an impact and the same shall be restricted to ensure resourceconservation. This impact will be marginal, as the ground water will not be drawncontinuously.

Impact on InfrastructureThe infrastructure of communication available at present is saturated; the proposal tolay new connectors between HMDA, GHMC will reduce the congestion. Thedevelopment in combination with this project activity will have marginal impact. Theadditional requirement of power would increase the pressure on the electricalinfrastructure and requires additional power generation in the overall context.

Impact on Human Use ValuesThe dominant land use in the area is residential, and expected commercial space willincrease the pressure on the residential localities. There is no additional requirementand or acquisition of land. The provision of public lung space in the project and othercommunity facilities will reduce the additional transport required availing the facilities.

Page 30: Janapriya Engineers Syndicate Pvt. Ltd.environmentclearance.nic.in/writereaddata/FormB/EC/Risk...RAMP DOWN TO CELLAR RAMP UP TO GROUND FLOOR M.H RAMP DN TO CELLAR 33.00M M.H M.H M

Janapriya Engineers Syndicate Pvt. Ltd. Environment Management Plan

Team Labs and Consultants8 - 3

The project authorities will provide road safety measures to reduce risk of accidents inthe internal roads. The impact on Human use values is marginal.

8.4 ENVIRONMENT MANAGEMENT MEASURES PROPOSEDA description of the various management measures during the various stages of theproject is provided in the following sections.

8.4.1 Pre-construction stageDuring the design and preconstruction stage the management proposes to comply withthe regulations of town planning, explore the availability of sufficient resources, provideplantation and sink bore wells after obtaining the necessary permission.

8.4.2 Construction stageThis will be the most crucial and active stage for the Environment Management Plan. Inaddition to the monitoring of the construction activity itself to the pollution levelswithin permissible limits, mitigation and enhancement measures for water resourceswill go on simultaneously as the construction progresses. To facilitate implementationof the enhancement and mitigation measures suggested working drawings of the samewould be prepared after completion of detailed project report. In addition, the needfor a balanced evaluation and planning for risks associated with construction activitiesrelated to housing and commercial project will be part of the Supervising Contractorsresponsibility.

The resource conservation by way of identification of materials and construction debrisrecycle/disposal will be formulated by the supervising consultants. The responsibility ofenvironment management plan lies with the project authorities that would implementthe plan in consultation with other consultants, by including appropriate provisions inthe contract/sub contract documents and providing the necessary facilities.

8.4.3 Operation stageThe environment management plan will be implemented by ownersassociations/societies, where project authorities are co-opted as members, and whilethe management plan related to the utilities like roads, street lighting and commonopen spaces lies with the Serilingampally Municipality. The management in operationstage will essentially entail maintenance of sewage treatment plant, maintenance ofutilities, and monitoring activity in the project site. Monitoring for pollutants specifiedin the Monitoring Plan will serve the two purposes. In addition to checking the efficacyof the protection/mitigation/enhancement measures implemented, this will help verifyor refute the predictions made as a part of the impact assessment. Thus, it willcomplete a very important feedback loop for the project.

The measures adopted and/or to be adopted during different stages of the project havebeen detailed in table 8.1.

Page 31: Janapriya Engineers Syndicate Pvt. Ltd.environmentclearance.nic.in/writereaddata/FormB/EC/Risk...RAMP DOWN TO CELLAR RAMP UP TO GROUND FLOOR M.H RAMP DN TO CELLAR 33.00M M.H M.H M

Janapriya Engineers Syndicate Pvt. Ltd. Environment Management Plan

Team Labs and Consultants8 - 4

Table 8.1 Environmental Management Plan and Action PlanEnvironmentalIssues/Impacts

Enhancement/ MitigationMeasures Management Action

CONSTRUCTION PHASE

Dust generation dueto construction

activities

Roads in the constructionarea will be sprinkled withwater to reduce the raisingof dust.

Plantation taken up at initialstage.

Plantation to be ensuredHorticulturists to identify thespecies.

Supervising consultants/contractor to ensure the watersprinkling

Exhaust gases fromheavy machinery and

transportation ofmaterials

Vehicle and equipmentmaintenance.

PUC for all transportvehicles.

Avoidance of idling ofequipment.

Contractors to be educated andsupervising consultant toensure the same.

Sedimentation ofstorm water during

rainy season

Avoiding stockpiles ofmaterials near naturaldrains.

Provision of filter fenceProvision of storm waterdrains wherever possiblebefore the beginning ofconstruction.

Architects, in consultation withSupervision consultants shouldidentify the measures needed.

Sewage transfer

Lead bearing piping to beavoided

Project authorities andplumbing consultant incoordination with theSupervision consultant shouldimplement the same.

Sewage Treatment

Sewage to be treated in theSTP and reused/disposed.

STP shall be provided by theproject authorities and ensuredthe design of STP is optimisedto meet the prescribedstandards with energyefficiency.

Alteration ofDrainage

Storm water drains to followthe natural course as far aspossible.

Storm water drains to have amin. water velocity of 1m/sand a max. 3 m/s.

Min. width of 0.6 meters anddepth based on the gradient.

Provision of rainwaterharvesting structures.

Architects in consultation withsanitary engineeringconsultants.

Supervision consultant toensure the same.

Page 32: Janapriya Engineers Syndicate Pvt. Ltd.environmentclearance.nic.in/writereaddata/FormB/EC/Risk...RAMP DOWN TO CELLAR RAMP UP TO GROUND FLOOR M.H RAMP DN TO CELLAR 33.00M M.H M.H M

Janapriya Engineers Syndicate Pvt. Ltd. Environment Management Plan

Team Labs and Consultants8 - 5

EnvironmentalIssues/Impacts

Enhancement/ MitigationMeasures Management Action

Water ConsumptionWater conservationmeasures duringconstruction.

Sub contractors to be educatedon water conservationmeasures.

Pollution fromconstruction workers

Provision of toiletsconnected to septic tankfollowed by soak pit.

Sludge usage for on landirrigation for plantation.

Proper availability ofdrinking water.

Proper Sanitation practices.

Sub contractors of the campsto be educated.

Project authorities shouldprovide the facility.

Supervision consultant toensure the same.

Loss of productivesoil

The site area is rocky.Topsoil to be stock piledseparately with 1:2 slopeand reused for greeningpurpose.

Supervision consultant toensure the same inconsultation with horticulturistand architect.

Soil Erosion

Cut and fill operation to bedone during non-monsoonseason.

Silt fence to ensure silt doesnot enter storm waterdrains.

Side slopes will be keptflatter wherever possible,and in case of steeper slopesit is mulched.

Supervision consultant toensure the same inconsultation with projectauthorities.

Compaction of Soil

Movement of constructionvehicles preferably in theproposed road areas.

Heavy vehicle movementrestricted in central greenarea.

Ploughing the area afterconstruction.

Architects to identify the roadareas.

Contamination of Soil

Vehicle washing andmachinery washing to beavoided in site.

Parking of vehicles andmaintenance of vehicles tobe avoided in site.

Disposal of solid wastes byconstruction workers to bemade in garbage bins only.

Subcontractors and Projectauthorities should ensure.

Designate the parking areasProvision of Garbage bin byproject authorities andarrangements to be for disposalof the same.

Page 33: Janapriya Engineers Syndicate Pvt. Ltd.environmentclearance.nic.in/writereaddata/FormB/EC/Risk...RAMP DOWN TO CELLAR RAMP UP TO GROUND FLOOR M.H RAMP DN TO CELLAR 33.00M M.H M.H M

Janapriya Engineers Syndicate Pvt. Ltd. Environment Management Plan

Team Labs and Consultants8 - 6

EnvironmentalIssues/Impacts

Enhancement/ MitigationMeasures Management Action

Septic tank provision fortoilets.

Accidental Leakage andspillage of fuels and otherconstruction materials to becontrolled by providing roadsigns and covered trucks.

Natural Resourceconsumption

Identify sand availabilityfrom government-authorisedlocations.

Identify and use bricks fromcoal ash users.

Aggregate to be made fromthe excess materials of cutoperations.

Identify and use recycledsteel wherever possible.

Proper availability ofdrinking water andsanitation facilities to theworkers.

The design team inconsultation with projectauthorities and supervisionconsultants must identify thesuppliers.

Health facilities forconstruction workers

Availability of first aid andhealth facilities

Ensure first aid boxes inadequate numbers and makeshift dispensary. The abovecondition may be put incontract document.

Fire PreventionAdopt safe work practiceand have adequate firefighting facilities

Provision of adequate firefighting equipment

Noise Pollution fromheavy machinery, and

transportation.

Noise and dust causingequipment to be locatedaway from residential areas.

Noise causing activities to beconducted during daytime.

Maintenance of equipmentand vehicles to mitigatenoise generation.

Inclusion of appropriate clausesin construction contracts;monitoring of complianceduring construction and properadministration of contracts.

Locating the constructionequipments in consultationwith project authorities andsupervision consultants.

Pressures onInfrastructure

Identification of alternativeroutes for transport ofmaterials from outside thesite.

Transport of materials

Using alternative road toreduce traffic pressure onroads.

Transporting the materialsduring nighttime.

Page 34: Janapriya Engineers Syndicate Pvt. Ltd.environmentclearance.nic.in/writereaddata/FormB/EC/Risk...RAMP DOWN TO CELLAR RAMP UP TO GROUND FLOOR M.H RAMP DN TO CELLAR 33.00M M.H M.H M

Janapriya Engineers Syndicate Pvt. Ltd. Environment Management Plan

Team Labs and Consultants8 - 7

EnvironmentalIssues/Impacts

Enhancement/ MitigationMeasures Management Action

during non-peak hours. Installing ElectricalTransformer if necessarybased on TRANSCO advice toavoid power fluctuations inthe site and also theneighbouring areas.

Consultation with TRANSCO byproject authorities.

Construction debris

Construction debris to beused for aggregate and orsub grade purpose in thecase of RCC.

Recyclable metals to becollected and sold torecyclers.

Avoidance of excessinventory of materials.

Packing materials to be sentfor reuse/recycling.

Hazardous waste containersto be returned toseller/authorised recyclers.

Provision of waste disposal sitefor waste from constructionand storage yard.

Supervision consultant inconsultation with the subcontractors.

Inclusion of appropriate clausesin construction contracts;monitoring of complianceduring construction and properadministration of contracts.

Plantation andEnvironmental

greening.

Soil reclamationUse of top soil Initiation of plantation

Horticulture consultant shallprepare the plan for soilreclamation and use of top soilsin consultation with architectsand supervision consultants.

Social Impacts Additional employment tolocals.

Qualified locals to be chosenfor employment.

Occupational Safetyand Health

Construction workers are tobe provided with personalprotective equipment (PPE)such as earplugs, helmets,safety shoes, gloves, etc.

Comply with Buildingconstruction acts.

The premises shall be fencedand no trespassing beallowed.

Ensure adequacy andavailability of Personalprotective equipments.

Project authorities to ensurecompliance with statutoryrequirements.

Project authorities to fence theboundaries to avoidunauthorised trespassing.

OCCUPATION STAGE

Urban Heat IslandEffect

Cool Roof Vegetation

Building blocks to be providedwith cool roofing material.

Vegetation to be provided byhorticulturist for the avenues,

Page 35: Janapriya Engineers Syndicate Pvt. Ltd.environmentclearance.nic.in/writereaddata/FormB/EC/Risk...RAMP DOWN TO CELLAR RAMP UP TO GROUND FLOOR M.H RAMP DN TO CELLAR 33.00M M.H M.H M

Janapriya Engineers Syndicate Pvt. Ltd. Environment Management Plan

Team Labs and Consultants8 - 8

EnvironmentalIssues/Impacts

Enhancement/ MitigationMeasures Management Action

and central green

Dust Generation fromtraffic.

Plantation. Maintenance of roads byway of sweeping.

Horticulturist should ensureavenue plantation

The managing committeesshould ensure maintenance ofavenue plantation.

Municipal authorities shouldensure the road maintenance.

Generation ofExhaust gases from

transport andutilities.

Avenue plantation. Rule to allow only vehicleswith PUC.

Proper maintenance ofvehicles.

Stack heights of the DG setsmust be provided as perCPCB guidelines and theemission levels should meetthe CPCB standards.

To be maintained by theJanapriya Engineers SyndicatePvt. Ltd..

Project authorities must ensurethat the DG sets are providedwith acoustic enclosures andproper stack heights.

Sewage Management

All Sewage will be collectedby underground drainagesystem.

The sewage will be treatedin sewage treatment plant

The treated sewage isreused for on land irrigationfor the development ofgreen belt.

Treated water line will beprovided for reuse forflushing.

Excess treated sewage willbe let out into Municipaldrain.

M/s Janapriya EngineersSyndicate Pvt. Ltd.Managementwill maintain the STP, andsewerage.

Municipal authorities will beappraised during rainy seasonwhen excess quantities arereleased into the drain.

Treated water lines will becolored blue and a distance of 2feet will be maintained fromthe other lines by the projectauthorities.

Records of influent andtreated effluent quality andquantity should be maintainedby the society, and thetreatment must be ensured tomeet the standards prescribedby GSR 422 E.

Storm waterManagement

Storm water will bedisposed into storm waterdrain provided byMunicipality.

Storm water drains will be

Storm water drain system anddisposal point to be providedby the project authorities.

Rain water harvestingstructures to be provided by

Page 36: Janapriya Engineers Syndicate Pvt. Ltd.environmentclearance.nic.in/writereaddata/FormB/EC/Risk...RAMP DOWN TO CELLAR RAMP UP TO GROUND FLOOR M.H RAMP DN TO CELLAR 33.00M M.H M.H M

Janapriya Engineers Syndicate Pvt. Ltd. Environment Management Plan

Team Labs and Consultants8 - 9

EnvironmentalIssues/Impacts

Enhancement/ MitigationMeasures Management Action

maintained periodicallybefore monsoon.

Accidental dischargesspillages will not be allowedto join storm water drains.

Roads, pavements and othersurfaces are swept regularly.

Rainwater harvestingstructures will be connectedto all the areas andmaintained periodically toremove sediment.

project authorities.Maintenance of storm waterdrains by Municipal authoritiesand the society shall overseethe same.

Management to interact withthe Municipal authorities.

Ground water usage

Ground water sources to beused during non-availabilityof sufficient supplies fromHMWSSB.

Ground water to be usedsparingly and waterconservation measures to beadopted.

Water ConservationMeasures

Water conservation measuresto be adopted to reduceresource consumption.

Management to educate theemployees and provide a book letof measures to reduce waterconsumption.

Loss of productivesoil

Individuals to be educatedabout importance greeningto avoid loss of productivesoil.

Management to educate thepeople.

Solid Wastes

Solid waste/garbage to becollected in green and bluedustbins.

The biodegradable wastes tobe removed everyday whilethe recyclable wastes to beremoved once a week.

Solid waste/garbage to bepicked by management staffor its representative NGO.

Transporting the garbage tomunicipal garbagebin/segregation pointlocated near high-techrailway station.

Municipality shall transportthe wastes to dump yards.

The sludge from the STP maybe used as manure for

The project authorities tomake arrangements with theMunicipality.

The management shall ensurethe transfer of wastes to themunicipal bin/segregationpoint.

The project authorities mustidentify the users for STPsludge and authorised recyclersfor hazardous wastes.

Page 37: Janapriya Engineers Syndicate Pvt. Ltd.environmentclearance.nic.in/writereaddata/FormB/EC/Risk...RAMP DOWN TO CELLAR RAMP UP TO GROUND FLOOR M.H RAMP DN TO CELLAR 33.00M M.H M.H M

Janapriya Engineers Syndicate Pvt. Ltd. Environment Management Plan

Team Labs and Consultants8 - 10

EnvironmentalIssues/Impacts

Enhancement/ MitigationMeasures Management Action

greening program isdisposed to farmers.

The used oils and usedbatteries, and usedtransformer oils should besent to authorised recyclers.

Consumption ofnatural resource

The major natural resourceconsumed during occupationstage is water and power.

Consumption of naturalresources shall be optimised byeducation and conservationmeasures.

Noise Levels

Noise levels due to trafficwill increase in the area andthe mitigation measures ofconstruction and Greening.

Noise levels from DG sets tobe mitigated by theprovision of acousticenclosures.

The project authorities shallensure that the material ofconstruction shall use bestsound transmission classmaterials to ensure that thesound levels with in theresidence are within theprescribed limits for residentialareas.

Plantation should becompleted before theoccupation stage to ensure thatthe noise levels are mitigated.

The project authorities mustensure the provision of acousticenclosures to the DG sets.

Traffic Volumes andparking facilities

Traffic volumes will increaseover a period of time andput pressure on theinfrastructure.

Subsequent increase in airpollution loads on theproject site and itssurroundings.

Provision of parking facilitiesTraffic and road safetysignals to be provided.

The project authorities mustensure public transport busstations in the immediatevicinity of the site.

The project authorities mustprovide the traffic and roadsafety signals in the project.Two-way mirrors must beprovided at blind corners.

Flora

The impacts on flora are dueto air pollution from exhaustof vehicles to be mitigatedby the choice of species.

The flora of the site shallincrease with the greeningprogram.

The Project authorities/ M/sPBEL Property Development(India) Pvt. Ltd., managementto ensure greening the openspace.

Horticulturists to assist theemployees in identifying the

Page 38: Janapriya Engineers Syndicate Pvt. Ltd.environmentclearance.nic.in/writereaddata/FormB/EC/Risk...RAMP DOWN TO CELLAR RAMP UP TO GROUND FLOOR M.H RAMP DN TO CELLAR 33.00M M.H M.H M

Janapriya Engineers Syndicate Pvt. Ltd. Environment Management Plan

Team Labs and Consultants8 - 11

EnvironmentalIssues/Impacts

Enhancement/ MitigationMeasures Management Action

plant species with an objectiveof reducing the energy costsand mitigating the heat islandeffect.

Energy Conservation

The energy conservationbuilding practices withrespect to building envelopfenestration and roofmaterials to be adopted.

The Architect shall ensure thecodes are implemented in thedesign drawings and workingdrawings.

Use of CFLS, Electronic Ballast,and ON/OFF sensors, etc.

Fire Safety

Provision of fire safetymeasures as per the firesafety regulations.

The project authorities mustprovide the measures andobtain the NOC from theDirector General of fire safety.

8.5 IMPLEMENTATION ARRANGEMENTSThe responsibility of implementing the mitigation measures lies with M/s JanapriyaEngineers Syndicate Pvt. Ltd.during design and construction stages while theresponsibility lies with the cooperative owner’s society and the RajendranagarMunicipality during occupation stage. All construction activities taken up by the projectauthorities will be supervised by the Supervision Consultant (SC). Implementationschedule will be worked for phase wise implementation of the mitigation measuresafter completion of detailed designs. In the pre-construction phase of the project thesupervision consultants shall review the EMP to identify environmental and social issuesand arrive at a suitable strategy for implementation. The activities to be carried out andthe target dates will be worked out after completion of detailed designs.

8.6 INSTITUTIONAL STRENGTHENINGThe management of M/s Janapriya Engineers Syndicate Pvt. Ltd.will evaluate theorganizational structure with respect to inadequacies in implementing the environmentmanagement plans. The housing project is typical as the responsibility of managementlies with the owners/residents during occupation stage. The owners form acooperative society/association to manage the utilities and common areas in a normalcase. The M/s Janapriya Engineers Syndicate Pvt. Ltd.will have little role to play inenvironment management. Hence it is suggested to explore the possibility of co-optinga member from M/s Janapriya Engineers Syndicate Pvt. Ltd.into these societies so asthe spirit of environment management plan is not lost. The common areas, electricalsupply, street lighting, open space of central green will be taken over and managed bythe Municipality and TRANSCO. The role of residents is limited to being stakeholderswith little say in the day-to-day matters; the town planning agencies and thegovernment must address this issue.

The Environment Management Plan envisages on-site monitoring of constructionactivities for environmental pollution and will involve collection of samples and theirsubsequent analysis. For this purpose two chemists would be required especially when

Page 39: Janapriya Engineers Syndicate Pvt. Ltd.environmentclearance.nic.in/writereaddata/FormB/EC/Risk...RAMP DOWN TO CELLAR RAMP UP TO GROUND FLOOR M.H RAMP DN TO CELLAR 33.00M M.H M.H M

Janapriya Engineers Syndicate Pvt. Ltd. Environment Management Plan

Team Labs and Consultants8 - 12

the implementation of the two phases goes on simultaneously. Induction of two moreassistant engineers, one each for the biophysical and social environment will also benecessary.

8.7 TRAININGThe existing supervising staff and the additional staff have to be trained to effectivelycarry out.

Co-ordinate, with supervision consultants and contractors on compliancemonitoring of mitigation measures during construction phase.

Monitoring of environmental components in the operation stage; Co-ordinate with concerned departments on environmental issues; Environmental impact studies for future housing projects; Liase with State and Government of India on fiscal policies to reduce environmental

pollution from housing activity.

8.8 ENVIRONMENTAL MONITORING8.8.1 IntroductionThe environmental monitoring programme provides such information on whichmanagement decision may be taken during construction and occupation phases. Itprovides basis for evaluating the efficiency of mitigation and enhancement measuresand suggest further actions that need to be taken to achieve the desired effect.

The monitoring includes:(i) Visual observations;(ii) Selection of environmental parameters at specific locations;(iii) Sampling and regular testing of these parameters.

8.8.2 ObjectivesThe objectives of the environmental monitoring programme are: Evaluation of the efficiency of mitigation and enhancement measures; Updating of the actions and impacts of baseline data; Adoption of additional mitigation measures if the present measures are insufficient; Generating the data, which may be incorporated in environmental management

plan in future projects.

8.8.3 MethodologyMonitoring methodology covers the following key aspects: Components to be monitored; Parameters for monitoring of the above components; Monitoring frequency; Monitoring standards; Responsibilities for monitoring; Direct responsibility, Overall responsibility; Monitoring costs.

Page 40: Janapriya Engineers Syndicate Pvt. Ltd.environmentclearance.nic.in/writereaddata/FormB/EC/Risk...RAMP DOWN TO CELLAR RAMP UP TO GROUND FLOOR M.H RAMP DN TO CELLAR 33.00M M.H M.H M

Janapriya Engineers Syndicate Pvt. Ltd. Environment Management Plan

Team Labs and Consultants8 - 13

Environmental monitoring of the parameters involved and the threshold limits specifiedare discussed below.

8.8.4 Ambient Air Quality (AAQ) MonitoringAmbient air quality parameters recommended for road transportation developmentsare Respirable Particulate Matter (RPM), Suspended Particulate Matter (SPM), Oxidesof Nitrogen (NOX), Sulphur Dioxide (SO2) and Lead (Pb). These are to be monitored atdesignated locations starting from the commencement of construction activity. Datashould be generated over three days at all identified locations in accordance to theNational Ambient Air Quality Standards (table 8.2) location, duration and the pollutionparameters to be monitored and the responsible institutional arrangements aredetailed out in the Environmental Monitoring Plan.

Table 8.2 National Ambient Air Quality StandardsS. No Pollutant Time

WeightedAverage

Concentration in Ambient Air

Industrial,Residential, Rural andOther Area

EcologicalSensitive Area

(Notified byCentral

Government)

Methods ofMeasurement

(1) (2) (3) (4) (5) (6)1 Sulphur Dioxide

(SO2), µg/m3Annual*

24Hours**

50

80

20

80

- Improved westand Gaeke

- Ultravioletfluorescence

2 Nitrogen Dioxide(NO2), µg/m3

Annual*

24Hours**

40

80

30

80

- Modified Jacob& Hochheiser(Nn-Arsenite)

- Chemiluminescence

3 ParticulateMatter (Size Lessthan 10 µm) orPM10 µg/m3

Annual*

24Hours**

60

100

60

100

- Gravimetic- TOEM- Beta

Attenuation

4 ParticulateMatter (Size Lessthan 2.5µm) orPM2.5 µg/m3

Annual*

24Hours**

40

60

40

60

- Gravimetic- TOEM- Beta

Attenuation

5 Ozone (O3)µg/m3

8hours**

1 hour**

100

180

100

180

- UV Photometric- Chemilminesce

nce- Chemical

Method6 Lead (Pb) µg/m3 Annual*

24hours**

0.50

1.0

0.50

1.0

- AAS /ICPmethod aftersampling onEPM 2000 orequivalent filterpaper

Page 41: Janapriya Engineers Syndicate Pvt. Ltd.environmentclearance.nic.in/writereaddata/FormB/EC/Risk...RAMP DOWN TO CELLAR RAMP UP TO GROUND FLOOR M.H RAMP DN TO CELLAR 33.00M M.H M.H M

Janapriya Engineers Syndicate Pvt. Ltd. Environment Management Plan

Team Labs and Consultants8 - 14

S. No Pollutant TimeWeightedAverage

Concentration in Ambient Air

Industrial,Residential, Rural andOther Area

EcologicalSensitive Area

(Notified byCentral

Government)

Methods ofMeasurement

- ED-XRF usingTeflon filter

7 CarbonMonoxide (CO)mg/m3

8hours**

1 hour**

02

04

02

04

- Non DispersiveInfra Red (NDIR)

- Spectroscopy

8 Ammonia (NH3)µg/m3

Annual*24hours**

100400

100400

- Chemilminescence

- Indophenolblue method

9 Benzene (C6H6)µg/m3 Annual* 05 05

- GasChromotography basedcontinuousanalyzer

- Absorption andDesorptionfollowed by GCanalysis

10 Benzo(o)Pyrene(BaP) –ParticulatePhase only,ng/m3

Annual* 01 01 - Solventextractionfollowed byHPLC/GCanalysis

11 Arsenic (As),ng/m3

Annual* 06 06 - AAS/ICPmethod aftersampling onEPM 2000 orequivalent filterpaper

12 Nickel (Ni),ng/m3

Annual* 20 20 - AAS/ICPmethod aftersampling onEPM 2000 orequivalent filterpaper

Source:Anon 1996-97, National Ambient Air Quality Monitoring Series NAQMS/a/1996-97, Central Pollution Control Board, Delhi.*Average Arithmetic mean of minimum 104 measurements in a year taken for a week24 hourly at uniform interval.**24 hourly/8 hourly values should meet 98 percent of the time in a year

Page 42: Janapriya Engineers Syndicate Pvt. Ltd.environmentclearance.nic.in/writereaddata/FormB/EC/Risk...RAMP DOWN TO CELLAR RAMP UP TO GROUND FLOOR M.H RAMP DN TO CELLAR 33.00M M.H M.H M

Janapriya Engineers Syndicate Pvt. Ltd. Environment Management Plan

Team Labs and Consultants8 - 15

8.8.5 Water Quality MonitoringThe physical and chemical parameters recommended for analysis of water qualityrelevant to road development projects are pH, total solids, total dissolved solids, totalsuspended solids, oil and grease, COD, chloride, lead, zinc and cadmium. The location,duration and the pollution parameters to be monitored and the responsibleinstitutional arrangements are detailed in the Environmental Monitoring Plan. Themonitoring of the water quality is to be carried out at all identified locations inaccordance to the Indian Standard Drinking Water Specification – IS 10500: 1991(stated in table 8.3).

Table 8.3 Indian Standard Drinking Water Specifications – IS: 10500:1991S. No Substance or

CharacteristicsRequire

ment(Desirable Limit)

UndesirableEffect Outsidethe Desirable

Limit Perm

issi

ble

Lim

it in

the

Abse

nce

ofAl

tern

ate

Sour

ce

Methods ofTest (Ref. To

IS)

Remarks

ESSENTIAL CHARACTERISTICS1 Colour, Hazen

units, Max.5 Above 5,

consumeracceptancedecreases

25 3025 (Part 4)1983

Extended to25 only iftoxicsubstancesare notsuspected,in absenceof alternatesources

2 Odour Unobjectionable

- - 3025 (Parts5):1984

a) Test coldand whenheatedb) Test atseveraldilutions

3 Taste Agreeable

- - 3025 (Part 7and 8)1984

Test to beconductedonly aftersafety hasbeenestablished

4 Turbidity NTU,Max.

5 Above 5,consumeracceptancedecreases

10 3025 (Part 10)1984

-

5 pH Value 6.5 to 8.5 Beyond thisrange, thewater will affectthe mucousmembrane

Norelaxati

on

3025 (Part 11)1984

-

Page 43: Janapriya Engineers Syndicate Pvt. Ltd.environmentclearance.nic.in/writereaddata/FormB/EC/Risk...RAMP DOWN TO CELLAR RAMP UP TO GROUND FLOOR M.H RAMP DN TO CELLAR 33.00M M.H M.H M

Janapriya Engineers Syndicate Pvt. Ltd. Environment Management Plan

Team Labs and Consultants8 - 16

S. No Substance orCharacteristics

Requirement

(Desirable Limit)

UndesirableEffect Outsidethe Desirable

Limit Perm

issi

ble

Lim

it in

the

Abse

nce

ofAl

tern

ate

Sour

ce

Methods ofTest (Ref. To

IS)

Remarks

and/or watersupply system

6 Total hardness(as CaCO3)mg/l, Max

300 Encrustation inwater supplystructure andadverse effectson domestic use

600 3025 (Part 21)1983

-

7 Iron (as Fe)mg/l, Max

0.3 Beyond thislimittaste/appearance are affected,has adverseeffect ondomestic usesand watersupply struc-tures, andpromotes ironbacteria

1 32 of 3025 :1964

-

8 Chlorides (as CI)mg/l, Max

250 Beyond thislimit, taste,corrosion andpalatibility areaffected

1000 3025 (Part 32)1988

-

9 Residual, freechlorine, mg/l,Min

0.2 - - 3025 (Part 26)1986

To beapplicableonly whenwater ischlorinated.Tested atconsumerend. Whenprotectionagainst viralinfection isrequired, itshould beMin 0.5mg/l

DESIRABLE CHARACTERISTICS1 Dissolved solids

mg/l, Max500 Beyond this

palatability2000 3025 (Part 16)

1984-

Page 44: Janapriya Engineers Syndicate Pvt. Ltd.environmentclearance.nic.in/writereaddata/FormB/EC/Risk...RAMP DOWN TO CELLAR RAMP UP TO GROUND FLOOR M.H RAMP DN TO CELLAR 33.00M M.H M.H M

Janapriya Engineers Syndicate Pvt. Ltd. Environment Management Plan

Team Labs and Consultants8 - 17

S. No Substance orCharacteristics

Requirement

(Desirable Limit)

UndesirableEffect Outsidethe Desirable

Limit Perm

issi

ble

Lim

it in

the

Abse

nce

ofAl

tern

ate

Sour

ce

Methods ofTest (Ref. To

IS)

Remarks

decreases andmay causegastro intestinalirritation

2 Calcium (as Ca)mg/l, Max

75 Encrustation inwater supplystructure andadverse effectson domestic use

200 3025 (Part 40)1991

-

3 Magnesium (asMg), mg/l, Max

30 Encrustation towater supplystructure andadverse effectson domestic use

100 16, 33, 34 of IS3025: 1964

-

4 Copper (as Cu)mg/l, Max

0.05 Astringenttaste,discolorationand corrosion ofpipes, fittingand utensils willbe causedbeyond this

1.5 36 of 3025:1964

-

5 Manganese (asMn) mg/l, Max

0.1 Beyond thislimittaste/appearance are affected,has adverseeffects ondomestic usesand watersupplystructures

0.3 35 of 3025:1964

-

6 Sulphate (as200 SO4) mg/l,Max

200 Beyond thiscauses gastrointestinal irrita-tion whenmagnesium orsodium arepresent

400 3025 (Part 24)1986

May beextendedup to 400provided(as Mg)does notexceed 30

7 Nitrate (as NO2)mg/l, Max

45 Beyond this,may causemethaemoglobi

100 3025 (Part 34)1988

-

Page 45: Janapriya Engineers Syndicate Pvt. Ltd.environmentclearance.nic.in/writereaddata/FormB/EC/Risk...RAMP DOWN TO CELLAR RAMP UP TO GROUND FLOOR M.H RAMP DN TO CELLAR 33.00M M.H M.H M

Janapriya Engineers Syndicate Pvt. Ltd. Environment Management Plan

Team Labs and Consultants8 - 18

S. No Substance orCharacteristics

Requirement

(Desirable Limit)

UndesirableEffect Outsidethe Desirable

Limit Perm

issi

ble

Lim

it in

the

Abse

nce

ofAl

tern

ate

Sour

ce

Methods ofTest (Ref. To

IS)

Remarks

nemia8 Fluoride (as F)

mg/l, Max1 Fluoride may be

kept as low aspossible. Highfluoride maycause fluorosis

1.5 23 of 3025:1964

-

9 Phenoliccompounds (AsC6H5OH) mg/l,Max

0.001 Beyond this, itmay causeobjectionabletaste and odour

0.002 54 of 3025:1964

-

10 Mercury (as Hg)mg/l, Max

0.001 Beyond this, thewater becomestoxic

Norelaxati

on

(see Note)Mercury ionanalyser

To betestedwhenpollution issuspected

11 Cadmium (asCd), mg/l, Max

0.01 Beyond this, thewater becomestoxic

Norelaxati

on

(See note) To betestedwhenpollution issuspected

12 Selenium (asSe), mg/l, Max

0.01 Beyond this, thewater becomestoxic

Norelaxati

on

28 of 3025:1964

To betestedwhenpollution issuspected

13 Arsenic (As As)mg/l, max

0.05 Beyond this, thewater becomestoxic

Norelaxati

on

3025 (Part 37)1988

To betestedwhenpollution issuspected

14 Cyanide (AsCN), mg/l, Max

0.05 Beyond thislimit, the waterbecomes toxic

Norelaxati

on

3025 (Part 27)1986

To betestedwhenpollution issuspected

15 Lead (as Pb),mg/l, Max

0.05 Beyond thislimit, the waterbecomes toxic

Norelaxati

on

(see note) To betestedwhenpollution issuspected

Page 46: Janapriya Engineers Syndicate Pvt. Ltd.environmentclearance.nic.in/writereaddata/FormB/EC/Risk...RAMP DOWN TO CELLAR RAMP UP TO GROUND FLOOR M.H RAMP DN TO CELLAR 33.00M M.H M.H M

Janapriya Engineers Syndicate Pvt. Ltd. Environment Management Plan

Team Labs and Consultants8 - 19

S. No Substance orCharacteristics

Requirement

(Desirable Limit)

UndesirableEffect Outsidethe Desirable

Limit Perm

issi

ble

Lim

it in

the

Abse

nce

ofAl

tern

ate

Sour

ce

Methods ofTest (Ref. To

IS)

Remarks

16 Zinc (As Zn).Mg/l, Max

5 Beyond thislimit it cancause astringenttaste and anopalescence inwater

15 39 of 3025:1964)

To betestedwhenpollution issuspected

17 Anionicdetergents (AsMBAS) mg/l,Max

0.2 Beyond thislimit it cancause a lightfroth in water

1 Methylene-blue extractionmethod

To betestedwhenpollution issuspected

18 Chromium (AsCr6+) mg/l, Max

0.05 May becarcinogenicabove this limit

Norelaxati

on

38 of 3025:1964

To betestedwhenpollution issuspected

19 Poly nucleararomatichydrocarbons(as PAH) g/1,Max

- May becarcinogenicabove this limit

- - -

20 Mineral oilmg/l, Max

0.01 Beyond thislimit un-desirable tasteand odour afterchlorinationtake place

0.03 GasChromatographic method

-

21 Pesticides mg/l,Max

Absent Toxic 0.001 - -

22 Radioactive materials: 58 of3025:01964

-

23 a) Alphaemitters Bq/l,Max

- - 0.1 - -

24 Beta emiterspci/1, Max

- - 1 - -

25 Aluminium (asAl), mg/l, Max

200 Beyond thislimit tastebecomesunpleasant

600 13 of3025:1964

-

26 Aluminium (as 0.03 Cumulative 0.2 31 of 3025: -

Page 47: Janapriya Engineers Syndicate Pvt. Ltd.environmentclearance.nic.in/writereaddata/FormB/EC/Risk...RAMP DOWN TO CELLAR RAMP UP TO GROUND FLOOR M.H RAMP DN TO CELLAR 33.00M M.H M.H M

Janapriya Engineers Syndicate Pvt. Ltd. Environment Management Plan

Team Labs and Consultants8 - 20

S. No Substance orCharacteristics

Requirement

(Desirable Limit)

UndesirableEffect Outsidethe Desirable

Limit Perm

issi

ble

Lim

it in

the

Abse

nce

ofAl

tern

ate

Sour

ce

Methods ofTest (Ref. To

IS)

Remarks

Al), mg/l, Max effect isreported tocause dementia

1964

27 Boron, mg/l,Max

1 - 5 29 of 3025:1964

-

Source: Indian Standard Drinking Water Specification-IS10500: 1991

8.8.6 Noise Level MonitoringThe measurements for monitoring noise levels would be carried out at all designatedlocations in accordance to the Ambient Noise Standards formulated by Central PollutionControl Board (CPCB) in 1989 (refer table 8.4) Sound pressure levels would bemonitored on twenty-four hour basis. Noise should be recorded at “A” weightedfrequency using a “slow time response mode” of the measuring instrument. Thelocation, duration and the noise pollution parameters to be monitored and theresponsible institutional arrangements are detailed in the Environmental MonitoringPlan (Table 8.5)

Table 8.4 Noise level standards (CPCB)Type Noise level for Day

Time Leq dB (A)Noise level for

Night Time dB (A)Industrial area 75 70Commercial area 65 55Residential area 55 45Silence zone 50 40Day time - 6.00 am - 9.00 pm (15 hours)Night time - 9.00 pm - 6.00 am (9 hours)

The monitoring plan along with the environmental parameters and the time frame ispresented in the Table 8.5 environmental monitoring plan

Page 48: Janapriya Engineers Syndicate Pvt. Ltd.environmentclearance.nic.in/writereaddata/FormB/EC/Risk...RAMP DOWN TO CELLAR RAMP UP TO GROUND FLOOR M.H RAMP DN TO CELLAR 33.00M M.H M.H M

Janapriya Engineers Syndicate Pvt. Ltd. Environment Management Plan

Team Labs and Consultants8 - 21

Table 8.5 Environmental Monitoring Plan

Envi

ronm

ent

com

pone

nt

Proj

ect S

tage MONITORING Institutional

Responsibilities

Parameters

SpecialGuidanc

e

Standards Location Frequen

cyDuratio

nImplementation

Supervision

Air

Cons

truc

tion

stag

e

PM10,PM2.5,SO2, NOX,CO, HC

Highvolumesamplerto belocated50 mfrom theplant inthedown-winddirec-tion. Usemethodspecifiedby CPCBforanalysis

Air(Preven-tion andControlof Pollu-tion)Rules,CPCB,1994

Whereverthecontractordecides tolocate theCrusher ata distanceof 100 mfrom thecrusher.

Onceeveryseasonfor 2years

Continuous 24hours/or for 1fullworking day

Contractorthroughap-provedmoni-toringagency

EnvironmentalEngineer, GHMC

Cons

truc

tion

stag

e

PM10,PM2.5,

HighVolumeSamplerto belocated40 mfrom theROW inthedown-winddirec-tion. Usemethodspecifiedby CPCBforanalysis

Air(Preven-tion andControlof Pollu-tion)Rules,CPCB,1994

Locationofconstruction area

Onceeverymonthfor 2years

Continuous 24hours/or for 1fullworking day

Contractorthroughap-provedmoni-toringagency

EnvironmentalEngineer, M/sJanapriyaEngineersSyndicate Pvt.Ltd.

Page 49: Janapriya Engineers Syndicate Pvt. Ltd.environmentclearance.nic.in/writereaddata/FormB/EC/Risk...RAMP DOWN TO CELLAR RAMP UP TO GROUND FLOOR M.H RAMP DN TO CELLAR 33.00M M.H M.H M

Janapriya Engineers Syndicate Pvt. Ltd. Environment Management Plan

Team Labs and Consultants8 - 22

Envi

ronm

ent

com

pone

nt

Proj

ect S

tage MONITORING Institutional

Responsibilities

Parameters

SpecialGuidanc

e

Standards Location Frequen

cyDuratio

nImplementation

Supervision

Occ

upat

ion

stag

e

PM10,PM2.5,SO2, NOx,CO, Pb, HC

HighVolumeSamplerto belocatedat 15 mfrom theedge ofpave-ment

Air(Preven-tion andControlof Pollu-tion)Rules,CPCB,1994

1. Site Thriceinoccupationstage.December 2018,January2019andJanuary2021

Continuous24 hours

Society Society

Wat

er Q

ualit

y

Cons

truc

tion

stag

e

pH, BOD,COD, TDS,TSS, DO,Oil &Greaseand Pb

Grabsamplecollectedfromsourceandanalyseas perStandardMethodsforExamination ofWaterandWastewater

Waterqualitystandards byCPCB

KapraLake

End ofsummerbeforetheonset ofmon-sooneveryyear for2 years

- Contractorthroughap-provedmoni-toringagency

EnvironmentalEngineer, M/sJanapriyaEngineersSyndicate Pvt.Ltd.

Page 50: Janapriya Engineers Syndicate Pvt. Ltd.environmentclearance.nic.in/writereaddata/FormB/EC/Risk...RAMP DOWN TO CELLAR RAMP UP TO GROUND FLOOR M.H RAMP DN TO CELLAR 33.00M M.H M.H M

Janapriya Engineers Syndicate Pvt. Ltd. Environment Management Plan

Team Labs and Consultants8 - 23

Envi

ronm

ent

com

pone

nt

Proj

ect S

tage MONITORING Institutional

Responsibilities

Parameters

SpecialGuidanc

e

Standards Location Frequen

cyDuratio

nImplementation

Supervision

Wat

er Q

ualit

y

Occ

upat

ion

stag

e

pH,BOD,COD,TDS,TSS,DO, Pb,Oil andGrease.

Grabsamplecollectedfromsourceandanalyseas perStandardMethodsforExamination ofWaterandWastewater

Waterqualitystandards byCPCB

1 Kapralake

3. STPInfluent4.STP

treatedEffluent

End ofsummerbeforetheonset ofmon-soon in2018,2019and2021Daily

Daily

- M/sJanapriyaEngineersSyndicate Pvt.Ltd.

Society

Society

JanapriyaEngineersSyndicate Pvt.Ltd.

Society

Society

Page 51: Janapriya Engineers Syndicate Pvt. Ltd.environmentclearance.nic.in/writereaddata/FormB/EC/Risk...RAMP DOWN TO CELLAR RAMP UP TO GROUND FLOOR M.H RAMP DN TO CELLAR 33.00M M.H M.H M

Janapriya Engineers Syndicate Pvt. Ltd. Environment Management Plan

Team Labs and Consultants8 - 24

Envi

ronm

ent

com

pone

nt

Proj

ect S

tage MONITORING Institutional

Responsibilities

Parameters

SpecialGuidanc

e

Standards Location Frequen

cyDuratio

nImplementation

Supervision

Noi

se le

vels

Cons

truc

tion

stag

e

Noiselevels ondB (A)scale

Freefield at 1m fromtheequipmentwhosenoiselevelsarebeingdeter-mined.

Noisestan-dards byCPCB

Atequipment yards

Onceeverymonth(max)for twoyears,asrequired by theengineer

Readings to betakenat 15seconds inter-val for15minutes everyhourandthenaveraged.

Contractorthroughap-provedmoni-toringagency

EnvironmentalEngineer, M/sJanapriyaEngineersSyndicate Pvt.Ltd.

Noiselevels ondB (A)scale

Equivalent noiselevelsusing aninte-gratednoiselevelmeterkept at adistanceof 15from theinternalroads

Noisestan-dards byCPCB

Asdirectedby theEngineer(Atmaximum5locations)

Thrice ayear for2 yearsduringtheconstructionperiod.

Readings to betakenat 15seconds inter-val for15minutes everyhourandthenaveraged

Contractorthroughap-provedmoni-toringagency

EnvironmentalEngineer, M/sJanapriyaEngineersSyndicate Pvt.Ltd.

Page 52: Janapriya Engineers Syndicate Pvt. Ltd.environmentclearance.nic.in/writereaddata/FormB/EC/Risk...RAMP DOWN TO CELLAR RAMP UP TO GROUND FLOOR M.H RAMP DN TO CELLAR 33.00M M.H M.H M

Janapriya Engineers Syndicate Pvt. Ltd. Environment Management Plan

Team Labs and Consultants8 - 25

Envi

ronm

ent

com

pone

nt

Proj

ect S

tage MONITORING Institutional

Responsibilities

Parameters

SpecialGuidanc

e

Standards Location Frequen

cyDuratio

nImplementation

Supervision

Occ

upat

ion

stag

e

Noiselevels ondB (A)scale

Equivalent noiselevelsusing aninte-gratednoiselevelmeterkept at adistanceof 15fromedge ofpavement

Noisestan-dards byCPCB

1. At allboundaries of thesite.

Thricein op-erationperiod,inDecember 2018,January2019andJanuary2021

Readings to betakenat 15seconds inter-val for15minutes everyhourandthenaveraged.

Societythroughanapprovedmonitoringagency

Society

Soil

Cons

truc

tion

stag

e

Monitoring of Pb,Cr, Cd

Sampleof soilcollectedtoacidifiedandanalysedusingabsorptionspectropho-tometry

Threshold foreachcontami-nant setby IRISdatabase ofUSEPAuntilnationalstan-dardsarepromulgated.

Atproductiveagricultural lands intheprojectimpactarea to beidentifiedby theenvironmentalengineer

Once ayear for2 years

- Contractorthroughanapprovedmonitoringagency

EnvironmentalEngineer, M/sJanapriyaEngineersSyndicate Pvt.Ltd.

Page 53: Janapriya Engineers Syndicate Pvt. Ltd.environmentclearance.nic.in/writereaddata/FormB/EC/Risk...RAMP DOWN TO CELLAR RAMP UP TO GROUND FLOOR M.H RAMP DN TO CELLAR 33.00M M.H M.H M

Janapriya Engineers Syndicate Pvt. Ltd. Environment Management Plan

Team Labs and Consultants8 - 26

Envi

ronm

ent

com

pone

nt

Proj

ect S

tage MONITORING Institutional

Responsibilities

Parameters

SpecialGuidanc

e

Standards Location Frequen

cyDuratio

nImplementation

Supervision

Occ

upat

ion

stag

e

Monitoring of heavymetals, oilandgrease

Sampleof soilcollectedtoacidifiedandanalysedusingabsorptionspectropho-tometry

Threshold foreachcontami-nant setby IRISdatabase ofUSEPAuntilnationalstan-dardsarepromulgated.

Ataccident/spilllocationsinvolvingbulktransportcarryinghazardousmaterials(5locationsmaximum)

As pertheoccurrence ofsuchincidents

Thricein op-erationstageformonitoringturbidity

Society Society

Soil

Eros

ion

Cons

truc

tion

stag

e

Turbidityin Stormwater

Silt load inponds

Visualobser-vationsduringsitevisits

Asspecifiedby theWaterqualitystandards

At thedrains,andKapraLake

Pre-monsoon andpost-mon-soonseasonsfor 2years

Engineer M/sJanapriyaEngineersSyndicate Pvt.Ltd.

Occ

upat

ion

stag

e

Turbidityin Stormwater

Silt load inponds

Visualobser-vationsduringsitevisits

Asspecifiedby theWaterqualitystandards

At waterKapraLake

Thricein pre-monsoon andpost-monsoonseasonsin 2018,2016and 2019.

Society Society

Page 54: Janapriya Engineers Syndicate Pvt. Ltd.environmentclearance.nic.in/writereaddata/FormB/EC/Risk...RAMP DOWN TO CELLAR RAMP UP TO GROUND FLOOR M.H RAMP DN TO CELLAR 33.00M M.H M.H M

Janapriya Engineers Syndicate Pvt. Ltd. Environment Management Plan

Team Labs and Consultants8 - 27

Envi

ronm

ent

com

pone

nt

Proj

ect S

tage MONITORING Institutional

Responsibilities

Parameters

SpecialGuidanc

e

Standards Location Frequen

cyDuratio

nImplementation

Supervision

Cons

truc

tion

Site

s and

Con

stru

ctio

n Ca

mps

Cons

truc

tion

Stag

e

Monitoring of:1. Storage

Area2.

DrainageArrangements

3.Sanitation inConstructionCamps

Visualobser-vationswillsuffice.Theseare to becheckedasspecifiedin theEMP.

To thesatisfac-tion ofthe M/sJanapriyaEngineersSyndicate Pvt.Ltd.and the

stan-dardsgiven inthereporting form.

At Storagearea andcon-structioncamps

Quarterly in theconstructionstage.

SupervisionEngineer/consultant

M/sJanapriyaEngineersSyndicate Pvt.Ltd.

8.9 REPORTING SYSTEMReporting system provides the necessary feedback for project management to ensurequality of the works and that the program is on schedule. The rationale for a reportingsystem is based on accountability to ensure that the measures proposed as part of theEnvironment Management Plan get implemented in the project.

The reporting system will operate linearly with the contractor who is at the lowest rungof the implementation system reporting to the Supervision Consultant, who in turnshall report to the Janapriya Engineers Syndicate Pvt. Ltd.. All reporting by thecontractor and Supervision Consultant shall be on a quarterly basis. The M/s JanapriyaEngineers Syndicate Pvt. Ltd.shall be responsible for preparing targets for each of theidentified EMAP activities. All subsequent reporting by the contractor shall bemonitored as per these targets set by the M/s Janapriya Engineers Syndicate Pvt.Ltd.before the contractors move on to the site. The reporting by the Contractor will bea monthly report like report of progress on construction and will form the basis formonitoring by the M/s Janapriya Engineers Syndicate Pvt. Ltd.either by its ownEnvironmental Cell or the Environmental Specialist hired by the Supervision Consultant.

Monitoring of facilities at construction camps Monitoring of air, noise, soil and water parameters including silt load Monitoring of survival rate of plantation. Monitoring of cleaning of drains and water bodies.

Page 55: Janapriya Engineers Syndicate Pvt. Ltd.environmentclearance.nic.in/writereaddata/FormB/EC/Risk...RAMP DOWN TO CELLAR RAMP UP TO GROUND FLOOR M.H RAMP DN TO CELLAR 33.00M M.H M.H M

Janapriya Engineers Syndicate Pvt. Ltd. Environment Management Plan

Team Labs and Consultants8 - 28

8.10 ENVIRONMENTAL MANAGEMENT BUDGETThe environmental budget for the various environmental management measuresproposed in the EMP is detailed in table 8.6. There are several other environmentalissues that have been addressed as part of good engineering practices, the costs forwhich has been accounted for in the Engineering Costs. Moreover, since environmentalenhancements have not been finalized at this stage, the table projects the typical costsaspect wise and the detailed cost estimate is presented in Annexure A.

Table 8.6 Environmental Budgets for Project

S.NO. Description

Capital cost in Rs. Lakhs Recurring cost in Rs. Lakhs

ConstructionPhase

OccupationPhase

ConstructionPhase

OccupationPhase

1 Air PollutionControl 24.0 -- 1.5 7.1

2 Water PollutionControl 193.7 22.5 18.8 80.0

3 Noise PollutionControl 6.0 0.0 2.4 1.3

4EnvironmentalMonitoring &Management

0.5 32.0 0.6 --

5Green belt &Open areadevelopment

19.5 3.9 0.3 2.9

6 Solid Waste 5.0 0.5 0.7 7.5

7 Others 129.6 -- 2.5 4.9

Total 378.3 58.9 26.8 103.7

8.11 Horticultural and Landscaping Works(a) ScopeThe Horticultural and Landscaping works may be entrusted to a contractor or may betaken by the horticulture department of the M/s Janapriya Engineers Syndicate Pvt.Ltd.It would generate local employment if the plantation, upkeep and maintenance ofthe green belt is entrusted to local VSS bodies. Detailed drawings and designs oflandscaping will be drawn after completion of the detailed designing. The followingprecautions must be taken while undertaking horticulture and landscaping works. TheM/s Janapriya Engineers Syndicate Pvt. Ltd.project will have greenery by way of avenueplantation and central green. The scheme of plantation and the figures are presentedin mitigation chapter. The upkeep and the management of the greening are presentedas follows;

Page 56: Janapriya Engineers Syndicate Pvt. Ltd.environmentclearance.nic.in/writereaddata/FormB/EC/Risk...RAMP DOWN TO CELLAR RAMP UP TO GROUND FLOOR M.H RAMP DN TO CELLAR 33.00M M.H M.H M

Janapriya Engineers Syndicate Pvt. Ltd. Environment Management Plan

Team Labs and Consultants8 - 29

(b) MaterialsPlant MaterialsPlant Materials shall be well formed and shaped true to type, and free from disease,insects and defects such as knots, sun-scaled, windburn, injuries, abrasion ordisfigurement.

All plant materials shall be healthy, sound, vigorous, free from plant diseases, insect’spests, of their eggs, and shall have healthy, well-developed root systems. All plants shallbe hardy under climatic conditions similar to those in the locally of the project. Plantssupplied shall to confirm to the names listed on both the plan and the plant list. Noplant material will be accepted if branches are damaged or broken. All material must beprotected from the sun and weather until planted.

Any nursery stock shall have been inspected and approved by the EnvironmentalSpecialist or the Engineer.

All plants shall conform to the requirements specified in the plant list. Except thatplants larger then specified may be used if approved, but use of such plants shall notincrease the contract price. If the use of the larger plant is approved, the spread of rootor ball of earth shall be increased in proportion to the size of plant.

Deliver plants with legible identification labels.

Top Soil (Good Earth)Topsoil or good earth shall be a friable loam, typical of cultivated topsoils of the localitycontaining at least 2% of decayed organic matter (humus). It shall be taken from a well-drained arable site. It shall be free of subsoil, stones, earth skids, sticks, roots or anyother objectionable extraneous matter or debris. It shall contain no toxic material. Notopsoil shall be delivered in a muddy condition. It shall have pH value ranging between6 and 8.5.

FertilizerMeasurement of sludge shall be in stacks, with 8% reduction for payment. It shall befree from extraneous matter, harmful bacteria insects or chemicals. (Subjected tosafety norms)

Root SystemThe root system shall be conducive to successful transplantation. While necessary, theroot-ball shall be preserved by support with Hessian or other suitable material. On soilswhere retention of a good ball is not possible, the roots should be suitably protected insuch a way that the roots are not damaged.

ConditionTrees and shrubs shall be substantially free from pests and diseases, and shall bematerially undamaged. Torn or lacerated roots shall be pruned before dispatch. Noroots shall be subjected to adverse conditions such as prolonged exposure to dryingwinds or subjection to water logging between lifting and delivery.

Page 57: Janapriya Engineers Syndicate Pvt. Ltd.environmentclearance.nic.in/writereaddata/FormB/EC/Risk...RAMP DOWN TO CELLAR RAMP UP TO GROUND FLOOR M.H RAMP DN TO CELLAR 33.00M M.H M.H M

Janapriya Engineers Syndicate Pvt. Ltd. Environment Management Plan

Team Labs and Consultants8 - 30

(c) Supply and SubstitutionUpon submission of evidence that certain materials including plant materials are notavailable at time of contract, the contractor shall be permitted to substitute with anequitable adjustment of price. All substitutions shall be of the nearest equivalentspecies and variety to the original specified and shall be subjected to the approval ofthe Landscape Architect.

(d) PackagingPackaging shall be adequate for the protection of the plants and such as to avoidheating or drying out.

(e) MarkingEach specimen of tree and shrub, or each bundle, shall be legibly labelled with thefollowing particulars: Its name. The name of the supplier, unless otherwise agreed. The date of dispatch from the nursery.

(f) Tree PlantingPlants and ShrubsTrees should be supplied with adequate protection as approved. After delivery, ifplanting is not to be carried out immediately, balled plants should be placed back toback and the ball covered with sand to prevent drying out. Bare rooted plants can beheeled in by placing the roots in prepared trench and covering them with earth, whichshould be watered into, avoid air pockets round the roots. Trees and shrubs shall beplanted as shown in architectural drawings and with approval of site supervisionengineer.

Digging of PitsTree pits shall be dug a minimum of three weeks prior to backfilling. The pits shall be120 cm in diameter and 120 cm deep. While digging the pits, the topsoil up to a depthof 30 cm may be kept aside, if found good (depending upon site conditions), and mixedwith the rest of the soil.

If the side of the below, it shall be replaced with the soil mixture as specified furtherherein. If the soil is normal it shall be mixed with manure; river sand shall be added tothe soil if it is heavy. The bottom of the pit shall be forked to break up the subsoil.

Back FillingThe soil back filled watered through and gently pressed down, a day previous toplanting, to make sure that it may not further settle down after planting. The soil shallbe pressed down firmly by treading it down, leaving a shallow depression all rounds forwatering.

PlantingNo tree pits shall be dug until final tree position has been pegged out for approval. Careshall be taken that the plant sapling when planted is not be buried deeper than in the

Page 58: Janapriya Engineers Syndicate Pvt. Ltd.environmentclearance.nic.in/writereaddata/FormB/EC/Risk...RAMP DOWN TO CELLAR RAMP UP TO GROUND FLOOR M.H RAMP DN TO CELLAR 33.00M M.H M.H M

Janapriya Engineers Syndicate Pvt. Ltd. Environment Management Plan

Team Labs and Consultants8 - 31

nursery, or in the pot. Planting should not be carried out in waterlogged soil. Planttrees at the original soil depth; soil marks on the stem is an indication of this and shouldbe maintained on the finished level, allowing for setting of the soil after planting. Allplastic and other imperishable containers should be removed before planting. Anybroken or damage roots should be cut back to sound growth.

The bottom of the planting pit should be covered with 50mm to 75mm of soil. Bareroots should be spread evenly in the planting pit; and small mound in the centre of thepits on which the roots are placed will aid on even spread. Soil should be placed aroundthe roots, gently shaking the tree to allow the soil particles to shift into the root systemto ensure close contact with all roots and prevent air pockets. Back fill soil should befirmed as filling proceeds, layer by layer, care being taken to avoid damaging the roots,as follows:

The balance earth shall be filled in a mixture of 1:3 (1 part sludge to 3 part earth byvolume) with 50 gm potash, (Mop) 50gms of Super Phosphate and 1Kg. Neem oil cake.Aldrin or equivalent shall be applied every 15 days in a mixture of 5ml in 5 litres ofwater.

StakingNewly planted trees must be held firmly although not rigidly by staking to prevent apocket forming around the stem and newly formed fibrous roots being broken bymechanical pulling as the tree rocks.

Methods:The main methods of staking shall be:(a) A single vertical shake, 900mm longer than the clear stem of the tree, driven 600mm

to 900mm into the soil.(b) Two stakes as above driven firmly on either side of the tree with a cross bar to which

the stem is attached. Suitable for bare- rooted or Ball material.(c) A single stake driven in at an angle at 45 degrees and leaning towards the prevailing

wind, the stem just below the lowest branch being attached to the stake. Suitablefor small bare- rooted or Ball material

(d) For plant material 3m to 4.5m high with a single stem a three- wire adjustable guysystem may be used in exposed situations.

The end of stake should be pointed and the lower 1m to 1.2m should be coated with anon-injurious wood preservative allowing at least 150mm above ground level.

TyingEach tree should be firmly secured to the stake so as to prevent excessive movement.Abrasion must be avoided by using a buffer, rubber or Hessian, between the tree andstake. The tree should be secured at a point just below its lowest branch, and also justabove ground level; normally two ties should be used for tree. These should beadjusted or replaced to allow for growth.

Page 59: Janapriya Engineers Syndicate Pvt. Ltd.environmentclearance.nic.in/writereaddata/FormB/EC/Risk...RAMP DOWN TO CELLAR RAMP UP TO GROUND FLOOR M.H RAMP DN TO CELLAR 33.00M M.H M.H M

Janapriya Engineers Syndicate Pvt. Ltd. Environment Management Plan

Team Labs and Consultants8 - 32

WateringThe Landscape Contractor should allow for the adequate watering in of all newlyplanted trees and shrubs immediately after planting and he shall during the followinggrowing season, keep the plant material well watered.

FertilizingFertilising shall be carried out by application in rotation of the following fertilisers, every15 days from the beginning of the monsoon till the end of winter:

(1) Sludge or organic well-rotted dry farm yard manure: 0.05 cum or tussle.(2) Urea 25 gm.(3) Ammonium sulphate 25 gm.(4) Potassium sulphate 25 gm.

All shrubs, which are supplied pot grown, shall be well soaked prior to planting.Watering in and subsequent frequent watering of summer planted container- grownplants is essential.

(g) Shrub Planting In Planter BedsAll areas to be planted with shrubs shall be excavated, trenched to a depth of 750 mm,refilling the excavated earth after breaking clods and mixing with sludge in ratio 8:1 (8parts of stacked volume of earth after reduction by 20%: 1 part of stacked volume ofsludge after reduction by 8%.)Tall shrubs may need staking, which shall be provided if approved by the contractingconsulting engineer, depending upon the conditions of individual plant specimen.

For planting shrubs and ground cover shrubs in planters, good earth shall be mixed withsludge in the proportion as above and filled in planters.

Positions of planters shall be planted should be marked out in accordance with thearchitectural drawing. When shrubs are set out, precautions should be taken to preventroots drying. Planting holes 40 cm in diameter, and 40 cm deep should be excavated forlonger shrubs. Polythene and other non-perishable containers should be removed andany badly damaged roots carefully pruned. The shrubs should then be set in holes sothat the soil level, after settlement, will be original soil mark on the stem of the shrub.The holes should be back filled to half of its depth and firmed by treading. Theremainder of the soil can then be returned and again firmed by treading.

(h) GrassingPreparationDuring period prior to planting the ground shall be maintained free from weeds.Grading and final weeding of the area shall be completed at least three weeks prior tothe actual sowing. Regular watering shall be continued until sowing by dividing the areainto portions of approximately 5m squares by constructing small bunds to retain water.These 'bunds' shall be levelled just prior to sowing of grass plants; it shall be ensuredthat the soil has completely settled.

Page 60: Janapriya Engineers Syndicate Pvt. Ltd.environmentclearance.nic.in/writereaddata/FormB/EC/Risk...RAMP DOWN TO CELLAR RAMP UP TO GROUND FLOOR M.H RAMP DN TO CELLAR 33.00M M.H M.H M

Janapriya Engineers Syndicate Pvt. Ltd. Environment Management Plan

Team Labs and Consultants8 - 33

SoilThe soil itself shall be ensured to the satisfaction of Landscape Architect to be a goodfibrous loam, rich in humus.

Sowing the grass rootsGrass roots (cynodon, dectylon or a local genus approved by the Landscape Architect)shall be obtained from a grass patch, seen and approved before hand.The grass roots stock received at site shall be manually cleared of all weeds and watersprayed over the same after keeping the stock in place protected from sun and drywinds.

Grass stock received at site may be stored for a maximum of three days. In casegrassing for some areas is scheduled for a later date fresh stock of grass roots shall beordered and obtained.

ExecutionSmall roots shall be dibbled about 5 cm apart into the prepared grounds. Grass willonly be accepted as reaching practical completion when germination has provedsatisfactory and all weeds have been removed.

MaintenanceAs soon as the grass is approximately a 3cm high it shall be rolled with a light woodenroller – in fine, dry weather – and when it has grown to 5 to 8 cm, above to groundweeds must be removed and regular cutting with the scythe and rolling must be begun.A top-dressing of an ounce of guano to the square yard or well decomposed wellbroken sludge manure shall be applied when the grass is sufficiently secure in theground to bear the mowing machine, the blades must be raised an inch above thenormal level for the first two or three cuttings. That is to say, the grass should be cut sothat it is from 4 to 5 cm in length, instead of the 3 cm necessary for mature grass.

In the absence of rain, in the monsoon, the lawn shall be watered every ten daysheavily, soaking the soil through to a depth of at least 20 cm.

Damage failure or dying back of grass due to neglect of watering especially for seedingout of normal season shall be the responsibility of the contractor. Any shrinkage belowthe specified levels during the contract or defect liability period shall be rectified at thecontractor's expense. The Contractor is to exercise care in the use of rotary cultivatorand mowing machines to reduce to a minimum the hazards of flying stones andbrickbats. All rotary mowing machines are to be fitted with safety guards.

RollingA light roller shall be used periodically, taking care that the area is not too wet andsodden.

EdgingThese shall be kept neat and must be cut regularly with the edging shears.

Page 61: Janapriya Engineers Syndicate Pvt. Ltd.environmentclearance.nic.in/writereaddata/FormB/EC/Risk...RAMP DOWN TO CELLAR RAMP UP TO GROUND FLOOR M.H RAMP DN TO CELLAR 33.00M M.H M.H M

Janapriya Engineers Syndicate Pvt. Ltd. Environment Management Plan

Team Labs and Consultants8 - 34

FertilizingThe area shall be fed once in a month with liquid manure prepared by dissolving 45gmsof ammonium sulphate in 5 litres of water.

WateringWater shall be applied at least once in three days during dry weather. Wateringwhenever done should be thorough and should wet the soil at least up to a depth of20 cm.

WeedingPrior to regular mowing the contractor shall carefully remove rank and unsightly weeds.

CultivatingThe Landscape Contractor shall maintain all planted areas within Landscape contractboundaries for one year until the area is handed over in whole or in phases.Maintenance shall include replacement of dead plants, watering, weeding, cultivating,control of insects, fungus and other diseases by means of spraying with an approvedinsecticide or fungicide, pruning, and other horticulture operations necessary for propergrowth of the plants and for keeping the landscape sub-contract area neat inappearance.

Pruning and RepairsUpon completion of planting work of the landscape sub-contract all trees should bepruned and all injuries repaired where necessary. The amount of pruning shall belimited to the necessary to remove dead or injured twigs and branches and tocompensate for the loss of roots and the result of the transplanting operations. Pruningshall be done in such a manner as not to change the natural habit or special shape oftrees.

Tree GuardsWhere the tree guards are necessary, care should be taken to ensure that they do notimpede natural movement or restrict growth. Circular iron tree guards shall be providedfor the trees at enhancement locations. The specifications for which one given below:

Circular Iron Tree Guard with Bars

The tree guard shall be 50 cm. in diameter.

The tree guards shall be formed of (i) 3 Nos. 25x25x3mm angle iron verticals 2.00m longexcluding splayed outward at lower end up to an extent of 10 cms. (ii) 3 Nos. 25x25mmMS flat rings fixed as per design (iii) 15 Nos. 1.55 metres long 6mm dia bars. Each ringshall be in two parts in the ratio of 1:2 and their ends shall be turned in radially for alength of 4 cm at which they are bolted together with 8mm dia and 30mm long MSbolts and nuts.

The vertical angle irons shall be welded to rings along the circumference with electricplant 15 Nos. bars shall be welded to rings at equal spacing along the circumference ofring. The lower end of the angle iron verticals shall be splayed outwards up to an extentof 10cm. The lower end of the flat of lower ring shall be at a height of 45cm. and upper

Page 62: Janapriya Engineers Syndicate Pvt. Ltd.environmentclearance.nic.in/writereaddata/FormB/EC/Risk...RAMP DOWN TO CELLAR RAMP UP TO GROUND FLOOR M.H RAMP DN TO CELLAR 33.00M M.H M.H M

Janapriya Engineers Syndicate Pvt. Ltd. Environment Management Plan

Team Labs and Consultants8 - 35

end of the flat of top ring shall be at the height of 2.00 metres. The middle ring shall bein the centre of top and lower ring. The bars shall be welded to rings as shown in thedrawing. The entire tree guard shall be given two coats of paint of approved brand andof required shade over a priming coat of ready mixed primer of approved brand.

(i) Nursery StackPlanting should be carried out as soon as possible after reaching the site. Whereplanting must be a necessity and/or be delayed, care should be taken to protect theplants from pilfering or damage from people animals. Plants with bare-roots should beheeled- in as soon as received or otherwise protected from drying out, and others setclosely together and protected from the wind. If planting is to be delayed for more thana week, packaged plants should be unpacked, the bundles opened up and each group ofplants heeled in separately and clearly labelled. If for any reason the surface of theroots becomes dry the roots should be thoroughly soaked before planting.

(j) Protective FencingAccording to local environment, shrubs shall be protected adequately from vandalismuntil established.

(l) CompletionOn completion, the ground shall be formed over and left tidy.

8.12 Water Conservation MeasuresWater conservation measures must be adopted during the occupation stage that wouldconserve the natural resource and also reduce the pressure on other users. A typicallist of water conservation measures are presented as follows;

Household Water Saving Measures1. There are a number of ways to save water and they all start with you.

2. When washing dishes by hand, don't let the water run while rinsing. Fill one sink withwash water and the other with rinse water.

3. Check your sprinkler system frequently and adjust sprinklers so only your lawn iswatered and not the house, sidewalk, or street.

4. Run your washing machine and dishwasher only when they are full and you couldsave 3785 liters a month.

5. Avoid planting turf in areas that are hard to water such as steep inclines and isolatedstrips along sidewalks and driveways.

6. Install covers on pools and check for leaks around your pumps.

7. Use the garbage disposal less often.

8. Plant during rainy season and or winter when the watering requirements are lower.

9. Check your water meter and bill to track your water usage.

10. Always water during the early morning hours, when temperatures are cooler, tominimize evaporation.

Page 63: Janapriya Engineers Syndicate Pvt. Ltd.environmentclearance.nic.in/writereaddata/FormB/EC/Risk...RAMP DOWN TO CELLAR RAMP UP TO GROUND FLOOR M.H RAMP DN TO CELLAR 33.00M M.H M.H M

Janapriya Engineers Syndicate Pvt. Ltd. Environment Management Plan

Team Labs and Consultants8 - 36

11. Wash your produce in the sink or a pan that is partially filled with water instead ofrunning water from the tap.

12. Use a layer of organic mulch around plants to reduce evaporation and savehundreds of liters of water a year.

13. Use a broom instead of a hose to clean your driveway and sidewalk and save up to303 liters of water every time.

14. If your shower can fill 4 liters bucket in less than 20 seconds, and then replace itwith a water-efficient showerhead.

15. Collect the water you use for rinsing produce and reuse it to water houseplants.

16. Water your lawn in several short sessions rather than one long one. This will allowthe water to be better absorbed.

17. We’re more likely to notice leaky faucets indoors, but don’t forget to check outdoorfaucets, pipes, and hoses for leaks.

18. Only water your lawn when needed. You can tell this by simply walking across yourlawn. If you leave footprints, it’s time to water.

19. When you shop for a new appliance, keep in mind that one offering severaldifferent cycles will be more water and energy-efficient.20. Time your shower to keep it under 5 minutes. You’ll save up to 3785 liters a month.

21. Install low-volume toilets.

22. When you clean your fish tank, use the water you’ve drained on your plants. Thewater is rich in nitrogen and phosphorus, providing you with a free and effectivefertilizer.

23. Water small areas of grass by hand to avoid waste.

24. Put food coloring in your toilet tank. If it seeps into the toilet bowl, you have a leak.It's easy to fix, and you can save more than 2271 liters a month.

25. Plug the bathtub before turning the water on, then adjust the temperature as thetub fills up.

26. Use porous materials for walkways and patios to keep water in your yard andprevent wasteful runoff.

27. Designate one glass for your drinking water each day. This will cut down on thenumber of times you run your dishwasher/wash your utensils.

28. Instead of using a hose or a sink to get rid of paints, motor oil, and pesticides,disposes of them properly by recycling or sending them to a hazardous waste site.

29. Install a rain shut-off device on your automatic sprinklers to eliminate unnecessarywatering.

30. Don’t use running water to thaw food.

31. Choose water-efficient drip irrigation for your trees, shrubs, and flowers. Wateringroots is very effective, be careful not to over water.

32. Grab a wrench and fix that leaky faucet. It’s simple, inexpensive, and can save 530liters a week.

Page 64: Janapriya Engineers Syndicate Pvt. Ltd.environmentclearance.nic.in/writereaddata/FormB/EC/Risk...RAMP DOWN TO CELLAR RAMP UP TO GROUND FLOOR M.H RAMP DN TO CELLAR 33.00M M.H M.H M

Janapriya Engineers Syndicate Pvt. Ltd. Environment Management Plan

Team Labs and Consultants8 - 37

33. Cut back on the amount of grass in your yard by planting shrubs and ground coveror landscaping with rock.

34. When doing laundry, match the water level to the size of the load.

35. Teach your children to turn the faucets off tightly after each use.

36. Remember to check your sprinkler system valves periodically for leaks and keep theheads in good shape.

37. Before you lather up, install a low-flow showerhead. They’re inexpensive, easy toinstall, and can save your family more than 1900 liters a week.

38. Soak your pots and pans instead of letting the water run while you scrape themclean.

39. Don’t water your lawn on windy days. After all, sidewalks and driveways don’t needwater.

40. Water deeply but less frequently to create healthier and stronger landscapes.

41. Make sure you know where your master water shut-off valve is located. This couldsave gallons of water and damage to your home if a pipe were to burst.42. When watering grass on steep slopes, use a soaker hose to prevent wasteful runoff.

43. To get the most from your watering time, group your plants according to their waterneeds.

44. Remember to weed your lawn and garden regularly. Weeds compete with otherplants for nutrients, light, and water.

45. While fertilizers promote plant growth, they also increase water consumption.Apply the minimum amount of fertilizer needed.

46. Avoid installing ornamental water features unless the water is being recycled.

47. Use a commercial car wash that recycles water.

48. Don’t buy recreational water toys that require a constant flow of water.

49. Turn off the water while you brush your teeth and save 15 liters a minute. That’s760 liters a week for a family of four.

50. Encourage your school system and local government to help develop and promote awater conservation ethic among children and adults.

51. Teach your family how to shut off your automatic watering systems so anyone whois home can turn sprinklers off when a storm is approaching.

52. Set a kitchen timer when watering your lawn or garden with a hose.

53. Make sure your toilet flapper doesn’t stick open after flushing.

54. Make sure there are aerators on all of your faucets.

55. Next time you add or replace a flower or shrub, choose a low water use plant foryear-round landscape color and save up to 2085 liters each year.

56. Spot spray or remove weeds as they appear.

57. Use a screwdriver as a soil probe to test soil moisture. If it goes in easily, don’twater. Proper lawn watering can save thousands of liters of water annually.

Page 65: Janapriya Engineers Syndicate Pvt. Ltd.environmentclearance.nic.in/writereaddata/FormB/EC/Risk...RAMP DOWN TO CELLAR RAMP UP TO GROUND FLOOR M.H RAMP DN TO CELLAR 33.00M M.H M.H M

Janapriya Engineers Syndicate Pvt. Ltd. Environment Management Plan

Team Labs and Consultants8 - 38

58. Install a drip irrigation system around your trees and shrubs to water moreefficiently.

59. Mow your lawn as infrequently as possible. Mowing puts your lawn underadditional stress, causing it to require more water.

8.13 Energy Efficiency Measures in a Typical Household8.13.1 Hot Water Repair leaky faucets. Reduce the temperature setting of your water heater to warm (120 F). Add an insulating blanket to your water heater. Install low-flow showerheads Wash clothes in warm or cold water using the appropriate water level setting for theload. Replace water heater, when needed, with an energy efficient model.

8.13.2 Major Appliances and Other Appliances Maintain refrigerator at 37 to 40 F and freezer section at 5 F. Maintain stand-alone freezer at 0 F. Choose a refrigerator/freezer with automatic moisture control. Use toaster ovens or microwave ovens for cooking small meals. Adjust the flame on gas cooking appliances so it’s blue, not yellow. Replace a gas-cooking appliance with a unit with an automatic, electric ignition

system. Run the dishwasher only with a full load of dishes. Air-dry dishes in a dishwasher. Shut down home computers when not in use. Select appliances (i.e., curling irons, coffee pots, irons) with time limited shut off

switches. Replace aging major appliances, TVs and VCRs when needed, with energy efficient

models. Replacing a 1970s refrigerator with an energy efficiency refrigerator. Thiscan save over 2,000 kWh per year. This will also reduce carbon dioxide emissionsby over 2,000 pounds every year.

Increase Air Conditioner thermostat by 3 degrees F. This can save over 900 kWh peryear, annually and over 900 pounds of carbon dioxide each year. Depending on thesize of your home, you can save 3% on your cooling costs for every degree you raiseyour thermostat in the summer. Raising the thermostat from 73 to 78 F degrees canreduce cooling costs by 15%.

Make sure your air conditioner is the proper size for the area you are cooling. An airconditioner that is too large will use more electricity than needed, an air conditionerthat is too small will have to work harder to cool a space. The recommended Airconditioners based on the room size are as follows:

Page 66: Janapriya Engineers Syndicate Pvt. Ltd.environmentclearance.nic.in/writereaddata/FormB/EC/Risk...RAMP DOWN TO CELLAR RAMP UP TO GROUND FLOOR M.H RAMP DN TO CELLAR 33.00M M.H M.H M

Janapriya Engineers Syndicate Pvt. Ltd. Environment Management Plan

Team Labs and Consultants8 - 39

Area To Be Cooled (sq. ft.) Capacity (BTU/HR)100 to 150 5,000150 to 250 6,000250 to 300 7,000300 to 350 8,000350 to 400 9,000400 to 450 10,000450 to 550 12,000500 to 700 14,000

700 to 1,000 18,000 Only run the washing machine, dryer, and dishwasher when you have full loads.

Cool only the rooms you use and utilize fans when the temperature is moderate.

8.13.3 Lighting Turn off lights when not in use. Use task lighting whenever possible instead of brightly lighting an entire room. Install compact fluorescent lamps in the fixtures which receive high use. Replace the

five most frequently used incandescent light bulbs with compact fluorescent bulbs.This will save over 500 kWh per year, and over 500 pounds of CO2.

Electricity Savings, and Carbon Dioxide Emissions Avoided For ImplementingEfficiency and Conservation Measures in One Household

Household Measure Electricity saved for onehousehold (kWh/yr)

CO2 avoided in for onehousehold (lbs/yr)

Replace a 1970s refrigeratorw/a new ENERGY EFFICIENTrefrigerator

2,197 2,190

Increase AC thermostat by 3Fdegrees for cooling 937 934

Replace 5 incandescent lightbulbs with compact fluorescent 562 560

Page 67: Janapriya Engineers Syndicate Pvt. Ltd.environmentclearance.nic.in/writereaddata/FormB/EC/Risk...RAMP DOWN TO CELLAR RAMP UP TO GROUND FLOOR M.H RAMP DN TO CELLAR 33.00M M.H M.H M

Janapriya Engineers Syndicate Pvt. Ltd. Environment Management Plan

Team Labs and Consultants8 - 40

Electricity Savings: Incandescent vs. Compact Fluorescent LightsThe following table shows the result of replacing one incandescent bulb with a

compact fluorescent bulb in one household.

Bulb Type 60 wattincandescent

11 watt compactfluorescent

Savings Over OneYears By

Replacing BulbPurchase Price Rs. 25 Rs. 50Life of the Bulb 750 hours 10,000 hoursNumber of Hours Burnedper Day

4 hours 4 hours

Number of Bulbs Needed About 2 over 1years 1 over 6.8 years

Lumens 1,690 1,500Total Cost of Bulbs Rs. 50 Rs. 50Total energy used over 1years

87.6 kWh perhousehold60 w (4hrs/day)(365days/year)(1 years) = 87600watt-hours or87.6kWh

16.06 kWh perhousehold11 w (4hrs/day)(365days/year)(1 years) = 16060watts-hours or16.06kWh

71.54 kWh perhousehold

Total CO2 emissions over 1yrs (avg emission rate:996.7 lbs/MWh or 0.9967lbs/kWh)

39.6 kg perhousehold87.6kWh (.9967lbs/kWh) = 87.31 lbs

7.26 kg perhousehold16.06 kWh (.9967lbs/kWh) = 16lbs

32.34kg perhousehold

Total SO2 emissions over 1yrs (avg emission rate: 5.1lbs/MWh or 0.00511lbs/kWh)

0.203 kg perhousehold87.6 kWh (.00511lbs/kWh) = 0.447 lbs

0. 037 kghousehold16.06kWh(.00511 lbs/kWh)= 0.082 lbs

0.166 kg perhousehold

Total NOx emissions over1 years (avg emission rate:1.9 lbs/MWh or 0.0019lbs/kWh)

0.075kg perhousehold87.6 kWh (.0019lbs/kWh) = 0.166 lbs

0.014 kg perhousehold16.06 kWh (.0019lbs/kWh) =0.0305 lbs

0.061 kg perhousehold

It is proposed to provide CFL units in the common areas, bathrooms, and central greenarea to conserve electricity by the project authorities. The average usage of 4 CFLs ineach dwelling, and the total energy savings from the project and the overall reductionin pollutants is presented in the following table;

8.14 Risk Assessment and Disaster ManagementConstruction sites in general do not handle toxic and or hazardous chemicals in largequantities, and the usage of the same is temporary for specific tasks. However theconstruction activity has a number of hazards resulting injuries and fatalities, and arenot reported widely due to the unorganized nature of construction professions. The

Page 68: Janapriya Engineers Syndicate Pvt. Ltd.environmentclearance.nic.in/writereaddata/FormB/EC/Risk...RAMP DOWN TO CELLAR RAMP UP TO GROUND FLOOR M.H RAMP DN TO CELLAR 33.00M M.H M.H M

Janapriya Engineers Syndicate Pvt. Ltd. Environment Management Plan

Team Labs and Consultants8 - 41

proposed project shall ensure the safety of workers and equipment to reduce andmitigate hazards. The hazards and mitigation measures due to various constructionactivities, and hazards to specific professions of construction are discussed as follows;

Site planning and layoutSite planning is essential to ensure safety and health of workers, in urban work siteswhich have space constraints. Site planning shall reduce and or help avoiding accidentsdue to collision of men with material and equipment etc. It is essential to plan thesequence of construction operations, access for workers on and around the site withsignage, location of work shops for welding, carpentary etc., location of first air facility,adequate lighting for work areas, site security by provision of fence or barricades,arrangements to keep the site tidy and for collection and removal of wastes.

Site tidinessAll the construction workers are briefed about the importance of keeping the site tidy,by clearing the rubbish and scrap at the end of the day, to keep the work area clear ofequipment and material, by depositing the waste in a designated location, by cleaningup spills of materials.

ExcavationExcavation for foundation and trenches involves removal of soil and rock. Excavation ortrenching plan shall consider underground services if any. The hazards related toexcavation are face collapse and injury or burial of workers by soil and rock, fall and slipof people in excavated pits and trenches, and injury to workers due to falling materialor equipment. The precautions to be taken are protection of excavation faces bysupport material, erection of shoring along trenches.Urban areas have building properties adjacent to the developing site, in such cases it isnecessary to shore the face of adjacent property to avoid fall or collapse of neighboringland or wall. Vehicular movement surrounding the excavated area needs to berestricted so as to avoid face collapse, and possible injury to workers. Excavation areasshall be provided with adequate lighting.

ScaffoldingOne of the important and serious safety risk in construction activity is fall of personfrom a height and fall of materials and objects from height resulting in injury toworkers. Scaffold is a supporting structure connecting two are more platforms used foreither storage of materials or as a work place. Guard rails and toe boards shall beprovided at every place where the height of scaffolding is more than 2 m. It shall beensured that scaffold is anchored and tied to the building, it is not overloaded with menand material, it is examined (both bamboo or wood and rope) frequently for infectionby insects, and that timber, if used, is not painted.

LaddersLadders are most commonly used equipment, as it is readily available and inexpensive,and is used widely. However the limitations of ladders are overlooked resulting ininjuries and fatalities. Ladders have limitations; allows only one person to work, climb,and carry materials or work with one hand, restricts movement, should be secured allthe time either using ropes or other people. It is essential to secure the ladder before

Page 69: Janapriya Engineers Syndicate Pvt. Ltd.environmentclearance.nic.in/writereaddata/FormB/EC/Risk...RAMP DOWN TO CELLAR RAMP UP TO GROUND FLOOR M.H RAMP DN TO CELLAR 33.00M M.H M.H M

Janapriya Engineers Syndicate Pvt. Ltd. Environment Management Plan

Team Labs and Consultants8 - 42

use. The safe use of ladder involves; ensuring that there are no overhead power lines,ladder extends at least one meter above the landing place, never use props to extendthe height of ladder, facing the ladder while climbing or descending, making sure footware of ladder user is free of mud and grease, not to over balance or over reach andusing a hoist line instead of carrying materials.

Steel ErectionSteel erection of building frames requires construction work at heights and in exposedpositions. However planning at the design stage, setting the sequence of operations,supervising during construction, and usage of personal protective equipment like safetybelts in addition to provision of safety nets, anchorage points etc.

Confined SpacesConstruction work in confined spaces like open manholes, sewers, trenches, pipes,ducts etc. may have dangerous atmosphere due to lack of oxygen or due to presence offlammable or toxic gases. Work confined space is always conducted under supervision,with adequate safety measures like; checking the atmosphere in confined space beforeentry, provision of rescue harness to everyone, involvement of minimum of twopersons – one person for monitoring and ready for rescuing if needed, provision ofsafety equipment like atmospheric testing device, safety harness, torch light, first aidequipment, fire fighting apparatus, and resuscitation equipment.

VehiclesThe construction area shall have multiples of vehicles moving material with in the siteand from out side the site. The most common causes of onsite traffic incidents are;bad driving technique, carelessness, carrying unauthorized passengers, poormaintenance of vehicles, site congestion, overloading, and uneven ground and debris.It is proposed to ensure that all drivers have appropriate driving license, routes areplanned, marked and leveled, enlisting additional workers during reversing, switchingoff the engine during idling, and periodic maintenance schedule for all vehicles.

Movement of materials – Cranes and HoistsCranes and hoists are used for movement of materials within the site. The operators ofthese machines are qualified and the cabins will have a signal chart to understand thesignals given by site workers. The site workers are trained in signals for transmitting tothe operators of these machines. Stability of these machines and overloading aremajor concerns while operating these machines, hence it is necessary to avoidoverloading, and to ensure structural stability of these machines before use. Thecranes will have safety hooks, and the workers are trained in using the same, andcriticality of the hook. In case of hoists, it will be ensured that a gate is provided at eachplatform, travel of passengers is avoided, and platforms are always aligned with landingpoints.

Lifting and CarryingConstruction work involves a lot of manual labour resulting in stress and injury to theworkers. It is proposed to provide wheel burrows, trolleys etc., to avoid manualcarrying of materials. In situations where manual lifting of materials is needed, the

Page 70: Janapriya Engineers Syndicate Pvt. Ltd.environmentclearance.nic.in/writereaddata/FormB/EC/Risk...RAMP DOWN TO CELLAR RAMP UP TO GROUND FLOOR M.H RAMP DN TO CELLAR 33.00M M.H M.H M

Janapriya Engineers Syndicate Pvt. Ltd. Environment Management Plan

Team Labs and Consultants8 - 43

workers are trained in safety related to correct lifting technique, throwing technique inaddition to provision of personal protective equipment.

Working positions tools and equipmentThere is an increased reliance of tools and equipment in the construction industry in thepast 15 years resulting in reduced risk of physical exhaustion. However the equipment,working positions in using the equipment have its own hazards, which need to beavoided to reduce risks like musculoskeletal disorders. It will be ensured that workerspreferably work in sitting posture with necessary tools handy, to avoid physicalexertion, the right tools are provided, and carrying tools in pockets avoided, and wornout tools are replaced in time. In case of power driven tools, the dangerous part of themachinery is always covered, the tool is never left in operation when not in use, andpower is switched off immediately in case of any incident, to avoid physical injury toworkers.

Working EnvironmentMany chemical substances like adhesives, cleaning agents, floor treatments, fungicides,cements, grouts, insulants, sealants, paints, solvents etc. Solvents are criticalsubstances which require due attention as they are flammable and or toxic in few cases.The usage of these chemical substances is always ensured to follow the instructionsmentioned by the manufacturers. Solvents will not be used for removal of paints andgrease from skin. Personal protective equipment is provided by the proponent and orthe contractor and the site safety executive shall ensure the same. Construction sitesare also major sources of noise resulting in hearing impairment. Hence it will beensured that all emission sources are provided with mufflers or silencers, motors arecovered, machinery panels are secured and are not allowed to rattle, and noiseattenuating screens are provided to segregate noisy working areas, in addition toprovision of personal protective equipment. Gloves are used when using Vibrationcausing equipment. Adequate lighting is provided in work areas to mitigate hazards.

Health Hazards on Construction SitesConstruction works involve various trades with variable times of operation.Construction operations have a number of potential hazardous operations and resultingin health hazards to workers. Exposure differs from trade to trade, from job to job, bythe day, even by the hour. Exposure to any one hazard is typically intermittent and ofshort duration, but is likely to reoccur. A worker may not only encounter hazardsrelated to his profession, but also encounters hazards related to other professions inthe vicinity. This pattern of exposure is a consequence of having many employers withjobs of relatively short duration and working alongside workers in other trades thatgenerate other hazards. The hazard severity is contingent on concentration andduration of exposure in a specific construction work. A list of hazards present forworkers in various trades is presented in table 8.7.

Table 8.7 list of hazards present for workers in various tradesOccupations Hazards

Brick masons Cement dermatitis, awkwardpostures, heavy loads

Stonemasons Cement dermatitis, awkward postures, heavy loads

Page 71: Janapriya Engineers Syndicate Pvt. Ltd.environmentclearance.nic.in/writereaddata/FormB/EC/Risk...RAMP DOWN TO CELLAR RAMP UP TO GROUND FLOOR M.H RAMP DN TO CELLAR 33.00M M.H M.H M

Janapriya Engineers Syndicate Pvt. Ltd. Environment Management Plan

Team Labs and Consultants8 - 44

Occupations HazardsHard tile setters Vapour from bonding agents, dermatitis, awkward

posturesCarpenters Wood dust, heavy loads, repetitive motionDrywall installers Plaster dust, walking on stilts, heavy loads, awkward

posturesElectricians Heavy metals in solder fumes, awkward posture,

heavy loads, asbestos dustElectrical power installers andrepairers

Heavy metals in solder fumes, heavy loads, asbestosdust

Painters Solvent vapours, toxic metals in pigments, paintadditives

Plasterers Dermatitis, awkward posturesPlumbers Fumes and particles, welding fumesPipefitters Fumes and particles, welding fumes, asbestos dustCarpet layers Knee trauma, awkward postures, glue and glue

vapourSoft tile installers Bonding agentsConcrete and terrazzofinishers

Awkward postures

Glaziers Awkward posturesInsulation workers Asbestos, synthetic fibers, awkward posturesPaving, surfacing and tampingequipment operators

Asphalt emissions, gasoline and diesel engineexhaust, heat

Sheet metal duct installers Awkward postures, heavy loads, noiseStructural metal installers Awkward postures, heavy loads, working at heightsWelders Welding emissionsSolderers Metal fumes, lead, cadmiumDrillers, earth, rock Silica dust, whole-body vibration, noiseAir hammer operators Noise, whole-body vibration, silica dustPile driving operators Noise, whole-body vibrationHoist and winch operators Noise, lubricating oilCrane and tower operators Stress, isolationExcavating and loadingmachine operators

Silica dust, histoplasmosis, whole-body vibration,heat stress, noise

Grader, dozer and scraperoperators

Silica dust, whole-body vibration, heat noise

Highway and streetconstruction workers

Asphalt emissions, heat, diesel engine exhaust

Truck and tractor equipmentoperators

Whole-body vibration, diesel engine exhaust

Demolition workers Asbestos, lead, dust, noiseHazardous waste workers Heat, stress

Page 72: Janapriya Engineers Syndicate Pvt. Ltd.environmentclearance.nic.in/writereaddata/FormB/EC/Risk...RAMP DOWN TO CELLAR RAMP UP TO GROUND FLOOR M.H RAMP DN TO CELLAR 33.00M M.H M.H M

Janapriya Engineers Syndicate Pvt. Ltd. Environment Management Plan

Team Labs and Consultants8 - 45

Construction HazardsHazards for construction workers are typically of four classes: chemical, physical,biological and social.

Chemical hazardsChemical hazards are mainly due to inhalation of dusts, fumes, mists, vapours or gases,although some airborne hazards may settle on and be absorbed through the intact skin(e.g., pesticides and some organic solvents). Chemical hazards also occur in liquid orsemi-liquid state (e.g., glues or adhesives, tar) or as powders (e.g., dry cement). Skincontact with chemicals in this state can occur in addition to possible inhalation of thevapor resulting in systemic poisoning or contact dermatitis. Chemicals might also beingested with food or water, or might be inhaled by smoking.

Several illnesses have been linked to the construction trades, among them: Silicosisamong sand blasters and rock drill operators; Asbestosis (and other diseases caused byasbestos) among asbestos insulation workers, steam pipe fitters, building demolitionworkers and others; Bronchitis among welders, Skin allergies among masons and otherswho work with cement: Neurologic disorders among painters and others exposed toorganic solvents.

Physical hazardsPhysical hazards are present in every construction project. These hazards include noise,heat and cold, radiation, vibration and barometric pressure. Construction work oftenmust be done in extreme weather conditions. The usage of machines for constructionis resulting in noise. The sources of noise are engines of all kinds (e.g., on vehicles, aircompressors and cranes), winches, paint guns, pneumatic hammers, power saws,sanders, planers and many more. It affects not only the person operating the machine,but all the workers close-by. This may not only cause noise-induced hearing loss, butalso may mask other sounds that are important for communication and for safety.Pneumatic hammers, many hand tools and earth-moving and other large mobilemachines also subject workers to segmental and whole-body vibration. Heat and coldhazards arise primarily because a large portion of construction work is conducted whileexposed to the weather, the principal source of heat and cold hazards. Heavyequipment operators may sit beside a hot engine and work in an enclosed cab withwindows and without ventilation. Those that work in an open cab with no roof have noprotection from the sun. A shortage of potable water or shade contributes to heatstress as well. The principal sources of non-ionizing ultraviolet (UV) radiation are thesun and electric arc welding. Lasers are becoming more common and may cause injury,especially to the eyes, if the beam is intercepted. Strains and sprains are among themost common injuries among construction workers. These, and many chronicallydisabling musculoskeletal disorders (such as tendinitis, carpal tunnel syndrome and low-back pain) occur as a result of either traumatic injury, repetitive forceful movements,awkward postures or overexertion. Falls due to unstable footing, unguarded holes andslips off scaffolding and ladders are very common.

Biological hazardsBiological hazards are presented by exposure to infectious micro-organisms, to toxicsubstances of biological origin or animal attacks. Excavation workers, for example, can

Page 73: Janapriya Engineers Syndicate Pvt. Ltd.environmentclearance.nic.in/writereaddata/FormB/EC/Risk...RAMP DOWN TO CELLAR RAMP UP TO GROUND FLOOR M.H RAMP DN TO CELLAR 33.00M M.H M.H M

Janapriya Engineers Syndicate Pvt. Ltd. Environment Management Plan

Team Labs and Consultants8 - 46

develop histoplasmosis, an infection of the lung caused by a common soil fungus. Sincethere is constant change in the composition of the labour force on any one project,individual workers come in contact with other workers and, as a consequence, maybecome infected with contagious diseases-influenza or tuberculosis, for example.Workers may also be at risk of malaria disease if work is conducted in areas wherethese organisms and their insect vectors are prevalent.

Social hazardsEmployment in construction sector is intermittent, and control over many aspects ofemployment is limited because construction activity is dependent on many factors overwhich construction workers have no control, such as the state of an economy or theweather. Because of the same factors, there can be intense pressure to become moreproductive. Since the workforce is constantly changing, and with it the hours andlocation of work, and many projects require living in work camps away from home andfamily, construction workers may lack stable and dependable networks of socialsupport. Features of construction work such as heavy workload, limited control andlimited social support are the very factors associated with increased stress in otherindustries. These hazards are not unique to any trade, but are common to allconstruction workers in one way or another.

Decreasing exposure concentrationThree general types of controls can be used to reduce the concentration ofoccupational hazards. These are, from most to least effective: engineering controls atsource, environmental controls that remove hazard from environment, personalprotection equipment provided to the worker.

Engineering controlsHazards originate at a source. The most efficient way to protect workers from hazards isto change the primary source with some sort of engineering change. For example, a lesshazardous substance can be substituted for one that is more hazardous. Water can besubstituted for organic solvents in paints. Similarly, non-silica abrasives can replacesand in abrasive blasting (also known as sand blasting). Or a process can befundamentally changed, such as by replacing pneumatic hammers with impacthammers that generate less noise and vibration. If sawing or drilling generates harmfuldusts, particulate matter or noise, these processes could be done by shear cutting orpunching. Technological improvements are reducing the risks of some musculoskeletaland other health problems. Many of the changes are straightforward-for example, atwo-handed screwdriver with a longer handle increases torque on the object andreduces stress on the wrists.

Environmental controlsEnvironmental controls are used to remove a hazardous substance from theenvironment, if the substance is airborne, or to shield the source, if it is a physicalhazard. Provision of flexible Local exhaust ventilation (LEV) may be used. The simpleand effective method for controlling exposure to radiant physical hazards (noise,ultraviolet (UV) radiation from arc welding, infrared radiant (IR) heat from hot objects)is to shield them with some appropriate material. Plywood sheets shield IR and UVradiation, and material that absorbs and reflects sound will provide some protection

Page 74: Janapriya Engineers Syndicate Pvt. Ltd.environmentclearance.nic.in/writereaddata/FormB/EC/Risk...RAMP DOWN TO CELLAR RAMP UP TO GROUND FLOOR M.H RAMP DN TO CELLAR 33.00M M.H M.H M

Janapriya Engineers Syndicate Pvt. Ltd. Environment Management Plan

Team Labs and Consultants8 - 47

from noise sources. Major sources of heat stress are weather and hard physicallabour. Adverse effects from heat stress can be avoided through reductions in theworkload, provision of water and adequate breaks in the shade and, possibly, nightwork.

Personal protectionWhen engineering controls or changes in work practices do not adequately protectworkers, workers may need to use personal protective equipment (PPE). In order forsuch equipment to be effective, workers must be trained in its use, and the equipmentmust fit properly and be inspected and maintained. Furthermore, if others who are inthe vicinity may be exposed to the hazard, they should either be protected orprevented from entering the area.

Eating and sanitary facilitiesA lack of eating and sanitary facilities may also lead to increased exposures. Often,workers cannot wash before meals and must eat in the work zone, which means theymay inadvertently swallow toxic substances transferred from their hands to food orcigarettes. A lack of changing facilities at a worksite may result in transport ofcontaminants from the workplace to a worker’s home. It is proposed to provideseparate temporary canteen and changing place for employees.

8.15 Fire Protection Plan/SystemDescription

The fire protection system consists of the following:a) Hydrant system for entire housings with each floor having a hydrant.b) High Velocity Water Spray System (HVWS) for Generator, Transformers, etc.c) Water sump (capacity of 30 KL) for the hydrants will be at the top of each building.d) Portable fire extinguishers in different areas of the housing.e) Microprocessor based intelligent addressable fire detection and alarm system will

be provided at all floors of the buildings and silt area.

Design, Construction & Operating ConditionsWater supply for the fire protection system will be provided from the clarified waterstorage tank. Adequate dead storage will be provided for fire protection system.Common pumps for hydrant and spray systems will be provided with provision forinterconnection between the two. Booster pumps of 900-litres/minute capacity will beprovided at top of the building for drawing water from the sump of 30 Kl capacityThe hydrant system will be provided for all the areas of the housing project. Hydrantsystem will consist of the underground ring headers, mains (piping) upto the individualhydrant outlets, risers and above ground branch headers (terminal mains) with isolatingvalves in case of landing valves/internal hydrants, stand posts, single headed or doubleheaded hydrant valves depending on the hazard covered, hoses, hose couplings, branchpipes and nozzle assemblies, etc. All accessories required for external and internalhydrants will be stored in hose boxes located alongside each hydrant. The system willbe adequately designed to maintain the required pressure in the hoses operated fromthe farthest hydrant ring main.

Page 75: Janapriya Engineers Syndicate Pvt. Ltd.environmentclearance.nic.in/writereaddata/FormB/EC/Risk...RAMP DOWN TO CELLAR RAMP UP TO GROUND FLOOR M.H RAMP DN TO CELLAR 33.00M M.H M.H M

Janapriya Engineers Syndicate Pvt. Ltd. Environment Management Plan

Team Labs and Consultants8 - 48

Portable extinguishers of suitable capacity, rating and medium (water, sand, CO2, foam,etc.) in adequate numbers covering all the buildings in the power plant premises will beprovided.

Suitable alarm system with audiovisual indicators for personnel safety shall be providedin the event of fire and extinguish discharge. Suitable extinguish gas detectors shall alsobe provided for detecting presence or discharge of extinguishant and provide warningto personnel. The system provided shall be of the highest order and testing on routinebasis shall be possible.

Codes & StandardsThe applicable codes & standards will be the latest version of the following:IS: 1978 – Line PipesIS: 1367,GL – 4B,4 – Technical supply conditions for threaded steel fastenersIS:1239 – Mild steel tubes, tubular and other wrought steel fittingsIS: 10221 – Code of practice for coating and wrapping of underground mild steelstructuresIS: 903 – Fire hose delivery couplings, branch pipe, nozzles and nozzle spannerIS: 4927 – Unlined flax canvas hose for fire fightingIS: 8423 – Controlled percolating hose for fire fightingIS: 5290 – Landing valvesIS: 2878 – Specification for fire extinguisher, carbon-do-oxide type (portable and trolleymounted)IS: 933 – Portable chemical foam fire extinguisherIS: 2171 – Portable fire extinguishers, dry powder(cartridge type)IS: 4308 – Specification for dry powder for fire fightingIS: 4861 – Dry powder for fire fighting in burning metalsIS: 2871 – Specification for branch pipe, universal for fire fighting purposesIS: 2189 – Selection, installation and maintenance of automatic fire detection and alarmsystemIS: 636 – Non- percolating flexible fire fighting delivery hoseIS: 3034 – Fire safety of industrial buildings: electrical generating and distributingstations.IS:9137 - Code for acceptance tests for centrifugal, mixed flow and axial pumps – Class CIS:10981 – Class of acceptance test for centrifugal flow and axial pumpsTariff Advisory Committee (TAC) of India/NFPA standardsOISD – 117 – Oil Installations

System DescriptionThe fire protection system contains; Firewater pumping system, Wet riser system andHose reel system, Yard hydrant system, Automatic sprinkler system, The Pressurisationsystem, Portable First Aid fire extinguishers, Fire safety plans, Analogue addressableAutomatic fire detection and alarm system.

Firewater pumping systemFirewater to the complete fire protection system shall be catered through an RCCUnderground (UG) storage tank of capacity 300 cum located at the ground floor of theoffice building. Water to this tank shall be fed by gravity tapped off from the bore well

Page 76: Janapriya Engineers Syndicate Pvt. Ltd.environmentclearance.nic.in/writereaddata/FormB/EC/Risk...RAMP DOWN TO CELLAR RAMP UP TO GROUND FLOOR M.H RAMP DN TO CELLAR 33.00M M.H M.H M

Janapriya Engineers Syndicate Pvt. Ltd. Environment Management Plan

Team Labs and Consultants8 - 49

water supply line. The following are the motor driven and diesel driven firewater pumpsthat shall be located adjacent to the UG storage tank.

i) Fire Hydrant pump (Motor driven) -1 No. 2850 lpm @100m head.

ii) Sprinkler pump (Motor Driven) – 1 No. 2850 lpm @ 100 m head

iii) Common standby pump (Engine driven) 1 No. 2850 lpm @ 100m head.

iv) Jockey pump (Motor driven) -1 No.180 lpm @ 100m head shall be provided formaintaining system pressure at all times and to compensate the minor losses.

v) Terrace level booster pump (motor driven) – 1No. 900 lpm @35m head.All the pumps will be of horizontal centrifugal end suction type. These pumps shalldraw water from the underground RCC static tank of capacity 300 cu.mtrs for hydrantand sprinkler system.

The level switches shall be provided in the Underground tank and terrace tank.Breaching inlet shall be provided at the inlet of the storage tank for quick filling by firebrigade.

Wet riser and Hose reel systemWet riser shall be provided at all floor landings of the staircase of the office building.Water supply to the wet risers shall be fed directly from the motor driven wet riserpump. This system shall consist of double hydrant outlet landing valve installed at aheight of 1000 mm above finished floor level and a separate tap off for hose reelassociated with hoses, branch pipe and nozzles for office building at each floor on eachriser. The system shall be designed hydraulically to meet the flow and pressurerequirements as per NBC. Hydrant accessories such as hose reel, branch pipe andnozzles etc. shall be provided in separate enclosures/cabinet with glass panels.

Four way breaching inlet with sluice check valve shall be installed and connected toeach wet risers. The breaching inlets shall be located at 1000 mm above the groundfloor level.

The pipe material for Wet risers shall be Galvanised Iron (GI) "C" class as perrequirements of the local fire officer from pump house to discharge to Wet riser andhose reel system topmost hydrant/ hose reel.In the event of fire, if the hydrant or hose reel are opened, the pressure in the wet risermain will drop due to the resulting flow, thereby the booster pump comes in tooperation at a preset low pressure. If the pressure drops further, at a preset lowpressure in the wet riser, the wet riser pump shall start automatically by getting animpulse from a pressure switch provided on the main.

In case the wet riser pump fails to start, the pressure in the main will drop further andat a pre-set low pressure, the common standby pump diesel shall come into operationby getting an impulse from a pressure switch provided. Stopping of the pump shall bemanual.

Page 77: Janapriya Engineers Syndicate Pvt. Ltd.environmentclearance.nic.in/writereaddata/FormB/EC/Risk...RAMP DOWN TO CELLAR RAMP UP TO GROUND FLOOR M.H RAMP DN TO CELLAR 33.00M M.H M.H M

Janapriya Engineers Syndicate Pvt. Ltd. Environment Management Plan

Team Labs and Consultants8 - 50

Automatic Sprinkler SystemsAutomatic sprinkler system shall be provided to cover all the floors of the officebuilding. Sprinklers shall be provided in two layers in all the floors of the office area,upright type sprinkler at RCC ceiling level and pendent type sprinkler with rosette plateat false ceiling level. Water supply to the sprinkler system shall be fed from the motordriven sprinkler pump. This system shall be designed hydraulically to meet the flow andpressure requirements as per codes and standards. This system shall comprise ofnetwork of piping, valves, sprinkler heads, flow switches etc. The sprinklers shall bedesigned to produce spherical type of discharge with a portion of water being thrownupwards to the ceiling. Sprinklers shall be of satin-chromed finish to architect'srequirement. Ceiling plates shall be of steel construction and shall be either chromed orpainted to architect's requirement. Sprinkler pipes shall be so installed that the systemcan be thoroughly drained.

Four Way breaching inlet with check valves shall be provided and connected to the eachsprinkler riser.

The mode of operation of the sprinkler system is as follows:In the event of fire in any section of the area to be protected by the sprinkler system,the sprinklers in that particular section shall open initiating the flow of water andannunciating the flow of water through flow switch provided at each sprinkler tap offriser. The motor driven sprinkler pump shall start automatically due to consequentialpressure drop in the sprinkler system piping. In case motor driven sprinkler pump failsto start, standby diesel engine driven pump shall come into operation by getting animpulse from a pressure switch provided at a preset low pressure. During sprinklersystem operation a local alarm shall be raised by activation of flow switch. Stopping ofthe pumps shall be manual.

Yard Hydrant SystemThe yard hydrant shall be located at various places around the building. The watersupply for yard hydrant shall be tapped off from wet riser system headers. Each singleheaded yard hydrant shall be provided with hoses, nozzles and accessories. All Hydrantaccessories shall be located in a Hose box adjacent to Hydrant valve. Brick masonryvalve chambers with cast iron covers shall be provided wherever required for isolatingthe system to enable maintenance if any without affecting the complete system.

The mode of operation of the hydrant system is as follows. In the event of fire, hydrantvalves are opened, at the preset low pressure the wet riser pumps shall start asfurnished in Wet riser system. In case of failure of wet riser pump stand by commonpump shall come into operation.

Pressurization SystemThe common pressurization system of wet riser system shall comprise of one (1) Jockeypump operating automatically. In the event of minor system leakages either in wet risersystem the Jockey pump will start automatically by getting an impulse from pressureswitch provided on the discharge header of the Jockey pump. The Jockey pump shallstop automatically once the mains pressure is restored to original set value. All pressureswitches shall have two (2) contacts -one for starting / stopping the Jockey pump andthe other for Jockey pump running annunciation in the panel. The control panel shall

Page 78: Janapriya Engineers Syndicate Pvt. Ltd.environmentclearance.nic.in/writereaddata/FormB/EC/Risk...RAMP DOWN TO CELLAR RAMP UP TO GROUND FLOOR M.H RAMP DN TO CELLAR 33.00M M.H M.H M

Janapriya Engineers Syndicate Pvt. Ltd. Environment Management Plan

Team Labs and Consultants8 - 51

have all necessary control and interlock for operation and control of the pumps. Jockeypump shall not be running when main pump/booster pump are under operation.

Portable First Aid Fire ExtinguishersPortable extinguishers such as carbon-di-oxide extinguishers, dry chemical powders etc.shall be provided in all areas of the building. The type of portable fire extinguishers andtheir numbers shall be as per NBC. Service tags shall be provided and attached on allextinguishers installed.

4.5kg extinguisher to be provided for every 500sqft of work area, every electrical room,and in every AHU room. A 22.5kg DCP cylinder on trolley for every DG set and UPS.

All safety equipments like fire buckets with one spare filled cylinder shall be provided.

Fire Safety PlansFire escape route printed in signal red colour shall be fixed near fire exit staircases,which shall show directions to the inmates for escape in case of fire.

Fire order as per NBC shall be fixed near lift/lift lobby, which shall guide action to betaken in case of fire.

Analogue Addressable Automatic Fire Detection and Alarm systemAutomatic fire alarm and detection and alarm system shall be provided for the officecomplex.

The fire detection and alarm system proposed consists of: Multi sensor Smokedetectors which shall be provided in the electrical switchgear room, electricalriser/ducts, lift shaft, lift machine room, BAS, communication room, and in office areaof all the floors above and below the false ceiling. Heat detectors shall be provided inpantry, DG room and kitchen. Manual call points shall be provided at all the entrancesand exits. Hooters with strobe lights shall be provided at all the entrances and exits,staircases and also inside office areas.

Mimic panel shall be located in the smoke free lobby at each floor of office building toindicate the location of fire. A central fire alarm panel shall be located at the Firecommand centre. This panel shall have the indication to identify the location of fire inthe building.

Fire alarm panel shall be located at the reception area and the repeater panel shall belocated in the guardhouse.

The provisions shall conform to the requirements of the National Building Code (NBC)1983, AMD3 (SP-7 1983, part- IV).

Fire Suppression SystemFM200 Gas fire suppression system is recommended for the server rooms.

Inspection and TestingInspection & testing will be carried out as per the Approved Quality Assurance plan.Minimum requirement will be as indicated below.

Shop Tests on Hydrant Valves:

Page 79: Janapriya Engineers Syndicate Pvt. Ltd.environmentclearance.nic.in/writereaddata/FormB/EC/Risk...RAMP DOWN TO CELLAR RAMP UP TO GROUND FLOOR M.H RAMP DN TO CELLAR 33.00M M.H M.H M

Janapriya Engineers Syndicate Pvt. Ltd. Environment Management Plan

Team Labs and Consultants8 - 52

a) Dimensionalb) Hydro test of bodyc) Flow test on 5% of valvesd) Seat leakage Teste) Operational check

Shop Tests on hose cabinets:a) Hydro Test of hose pipe/coupling/nozzleb) Percolation testc) Burst test (Type test or Type test report)

Dimensional InspectionOn completion of erection, at Site, Pipes will be hydro tested at 1.5 times the pumpshut-off head, or twice the operating pressure, whichever is higher.

Page 80: Janapriya Engineers Syndicate Pvt. Ltd.environmentclearance.nic.in/writereaddata/FormB/EC/Risk...RAMP DOWN TO CELLAR RAMP UP TO GROUND FLOOR M.H RAMP DN TO CELLAR 33.00M M.H M.H M

Janapriya Engineers Syndicate Pvt. Ltd. Environment Management Plan

Team Labs and Consultants8 - 53

Annexure – ADetailed Cost Estimate

DescriptionCapital cost in (Rs. Lakhs) Recurring cost in (Rs.Lakhs)

ConstructionPhase

OccupationPhase

ConstructionPhase

OccupationPhase

Air PollutionControl

DG Stack 4.8 1.0Personal protective equipments 0.4 0.5 0.2Equipment maintenance 0.5 0.1 0.1Sprinkling of water 20.6 8.2

Total 26.3 0.6 9.5

Water PollutionControl

Sedimentation tank 0.3 0.1Rain water harvesting pits 0.6 0.1Rain water harvesting sump (KL) 0.6 0.2Sewage treatment plant (KLD) 152.4Temporary Toilets 0.6 0.1Dual Plumbing 134.3 67.2STP maintenance 160.0

Total 288.8 0.0 67.6 160.0Noise Pollution

ControlPersonal protective equipments 0.4 0.4 0.1Acoustic enclosures 1.9 0.6 0.4

Total 2.3 0.9 0.5

Environmentalmonitoring

Ambient air quality studies -Once in six months - 2 locations 0.14 0.2Water quality studies - Once ayear - 2 Locations 0.03 0.1Noise studies - Once in sixmonths - 2 Locations 0.04 0.1STP Lab 32.0 6.4

Total 0.2 32.0 0.3 6.4Green belt &

Open areadevelopment

Green belt 13.4 2.7 0.3Horticulturists & Gardeners 1.4

Total 13.4 2.7 0.3 1.4

Solid Waste

Construction waste storage 2.5 0.3 1.0Garbage Segregation point 3.0 0.3 0.3Garbage 28.1

Total 5.5 0.6 1.3 28.1

Others

Solar lighting 3.0 0.6 0.6Solar Heaters 106.8 2.1 2.1Barricade 15.5Safety Signage 0.3 0.1 0.1LED Lighting 0.2 0.1 0.0Roof insulation 46.9 4.7Training & Mobilization 0.1 0.1Solar lighting 172.6 0.0 3.0 7.6

Total 509.0 35.2 74.1 213.5Grand Total 4.8 1.0

Page 81: Janapriya Engineers Syndicate Pvt. Ltd.environmentclearance.nic.in/writereaddata/FormB/EC/Risk...RAMP DOWN TO CELLAR RAMP UP TO GROUND FLOOR M.H RAMP DN TO CELLAR 33.00M M.H M.H M

Janapriya Engineers Syndicate Pvt. Ltd.SURVEY NOS. 663(P), 668(P) AND 671(P),KAPRA, MEDCHAL - MALKAJGIRI DISTRICT

Studies and Documentation by:M/s Team Labs and ConsultantsB-115 to 117 & 509, Annapurna Block,Aditya Enclave, Ameerpet,Hyderabad- 500 038Phone: 91-040-23748555/616Fax : 91-040-23748666e-mail: [email protected]