  1. 1. JCCBI 2015 Project Report Repair and Maintenance Program Technical briefing for media SAFETY. MOBILITY. LONGEVITY. December 2, 2015 #OurProjects
  2. 2. Spokespeople Glen P. Carlin Chief Executive Officer Sandra Martel Chief Operating Officer Franois Demers Senior Director, Champlain and NCBC Catherine Tremblay Senior Director, Projects, Construction and Operations Steve Tselios Senior Director, Engineering #OurProjects
  3. 3. Briefing Outline Word of welcome 2015 in review Champlain Bridge 360 Structural repair and maintenance Planning and longevity Q&A Individual interviews #OurProjects
  4. 4. Large-scale Challenges! #OurProjects
  5. 5. Champlain Bridge 360 EXCEPTIONAL MEASURES #OurProjects
  6. 6. A dedicated Champlain Project Office Office resources: 12 JCCBI employees Engineering firms (design and technical support) Supervision team To support this dedicated team, an Expert Committee is in place. Its role is to challenge the solutions proposed by consultants in order to ensure we choose the most appropriate approach for users and workers safety. #OurProjects
  7. 7. Instrumentation from shore to shore Continous, real- time monitoring provided through instrumentation #OurProjects
  8. 8. Comparitive load tests Monthly inspection patrols Trucks with 30 and 48 tonne loads Slowed traffic Direct surveillance of bridge behaviour Comparitive analyses with historical data 0 5 10 15 20 25 30 35 P1 Girders Ave Jul-15 Aug-15 Sep-15 Oct.-15 Nov.-15 #OurProjects
  9. 9. Data entered into integrated system Software integrating all bridge condition assessment and monitoring steps #OurProjects
  10. 10. Accelerated inspection schedule #OurProjects
  11. 11. Replacement of 6 expansion joints #OurProjects
  12. 12. Lane management traffic lights Optimization of load distribution over the structure to reduce stress on girders #OurProjects
  13. 13. 90% of work done from under bridge Repair of 9 piers 2,165 m3 of concrete #OurProjects
  14. 14. #OurProjects
  15. 15. Installation of modular trusses 34 trusses installed to date 43 to come in 2016, 15 in 2017 4m high 78m long 56,000 kg! #OurProjects
  16. 16. Champlain today Trusses installed Lane management traffic lights installed Intensive transport of materials #OurProjects
  17. 17. And planning for tomorrow #OurProjects
  18. 18. Repair and maintenance JCCBI STRUCTURES #OurProjects
  19. 19. Bonaventure Expressway Deck Work to be completed in December Replacement of 6 spans and 2 ramps 80 girders in all 1,165 m concrete poured on site 18 hrs a day / 7 days on average #OurProjects
  20. 20. Jacques Cartier Bridge Painting the structure above the seaway Approximate area: 8,000 m Three-layer paint system: galvanized zinc, epoxy resins and polyurethane resins #OurProjects
  21. 21. Under the bridge: Steel and pier repair #OurProjects
  22. 22. St. Helens Island Pavilion OBJECTIVE Secure and reinforce this structural element #OurProjects
  23. 23. Champlain Ice Control Structure Reinforce deck capacity 2,3 km 70 spans 630 reinforcement cables 200 workers on-site #OurProjects
  24. 24. Champlain Ice Control Structure New separate bike lane 3 m wide Anti-skid surface LED lighting system #OurProjects
  25. 25. Honor Mercier Bridge (federal section) 64 pre-fab deck slabs +100 Mohawk workers 19,140 steel bolts Compressed work schedule: 20 hrs / 7 days Slab life = 75 years 15 days ahead of schedule! #OurProjects
  26. 26. Biodiversity protection Proactive management of surrounding fauna Nesting structures for falcons and swallows Mitigation measures for the Copper red horse Environmental benefits Creation of an enclosure and hibernacle for brown garter snakes Research and development for amphibians and reptiles Creation of additional habitat for birds Reforesting around the bypass bridge Full inventory of biodiversity upcoming #OurProjects
  27. 27. Daily monitoring and coordination JCCBI works 365 days a year to maintain smooth network operations Team of maintenance employees on-site overseeing our structures every day Management of traffic hindrances, with close to 8,000 interventions in 2015 Exploration of innovative practices for lane maintenance during winter #OurProjects
  28. 28. Planning and longevity VISION FOR 2016 AND BEYOND #OurProjects
  29. 29. Planning and partnerships JCCBI MTQ SSL City of Montral South shore municipalities (10+) Kahnawake Band Council Environnement Qubec & Environment Canada AMT Transit authorities Police Emergency services Media Exhaustive planning of work to reduce impact on users and optimize efficiency of our structural interventions Blitz 3, Champlain Bridge 3 major partners, 1 impact 2016 work in planning stages #OurProjects
  30. 30. Responsible, preventive management JCCBI ensures that Montral's most symbolic and representative infrastructures remain safe, fully functional and attractive. General, detailed, and special inspections Load-bearing studies Instrumentation Master plans Combine structural data, long-term vision and economic information to determine the best actions to take and opportune timing Studies and planning Engineering (drawings and specs) Execution of work Maintenance and operations Inspection #OurProjects
  31. 31. 85 years old already! OBJECTIVE Give a second life to the structure, with a view to extending its life for 50 more years while at the same time improving safety and its integration into the urban environment #OurProjects
  32. 32. Lighting Beginning of technical trials #OurProjects
  33. 33. Lighting JCCBI is pleased to draw on its expertise to lead the project to illuminate the Jacques Cartier Bridge as part of the festivities marking the 150th anniversary of Canadian Confederation and the 375th anniversary of Montreal. The $39.5 million budget includes concept development, design, execution, as well as operating and maintenance costs for a 10-year period Engineering and site supervision contract awarded to WSP-Aecom Design in progress by Moment Factory and our teams Calls for tenders for equipment planned for this winter, and for installation work this summer Installation planned for August through December Lighting work complete by end of February 2017 #OurProjects
  34. 34. Questions #OurProjects
  35. 35. Follow us! www.JCCBI.ca @PJCCI @pontJCBridge @pontChampBridge @pontHMBridge OurProjects