Page 1: Plan for major repairs and maintenance work on JCCBI structures

2016 ProjectsPlan for major repairs and maintenance work on JCCBI structures

April 2016#OurProjects

Page 2: Plan for major repairs and maintenance work on JCCBI structures

2

#OurProjects

Page 3: Plan for major repairs and maintenance work on JCCBI structures

PLANNING WORKAhead of time and on time

Page 4: Plan for major repairs and maintenance work on JCCBI structures

4

COORDINATION AND OPTIMZATION

JCCBI

MTMDET

SSL

Ville de Montréal

South Shore municipalities

(+10)

Mohawk Council of

KahnawakeEnvironnement

Québec & Canada

AMTPublic transit corporations

Police authorities

Emergency services

Media

USERS USERS

USER

S

USERS

USER

S

USERS

THOROUGH PLANNING WITH PARTNERS

+ Numerous inter-organizational work meetings

+ Work concentrated at night and on weekends

+ Work optimized to reduce impact on users

#OurProjects

Page 5: Plan for major repairs and maintenance work on JCCBI structures

5

STRUCTURES 2015(completed)

2016(budgeted)

Champlain Bridge $89M $126M

Jacques Cartier Bridge $50M $85M

Honoré Mercier Bridge $19M $46M

Environment $1M $18M

Melocheville Tunnel $7M $9M

Bonaventure Expressway $22M $8M

Champlain Bridge Ice Control Structure $28M $8M

Highway 15 $7M -

Île des Sœurs Bypass Bridge $3M -

TOTAL $226M $300M

Major work on our structures

FORECASTED INVESTMENT

#OurProjects

Page 6: Plan for major repairs and maintenance work on JCCBI structures

6

+ Nearly 8,000 interventions were coordinated on our network in 2015+ Maintenance crews patrol each structure every day+ Holidays and events taken into consideration

CLOSURE AND MAINTENANCE MANAGEMENT

DAILY COORDINATION AND MONITORING

Page 7: Plan for major repairs and maintenance work on JCCBI structures

7

KEY EVENT INFRASTRUCTURE

lll Tour de l’Île (June 5) lll Fireworks (July) lll Montreal Marathon (September 25)

The Corporation ensures that infrastructure under its management remains safe, fully functional and aesthetically pleasing, today and in the future.+

#OurProjects

Page 8: Plan for major repairs and maintenance work on JCCBI structures

8

VISION: JACQUES CARTIER BRIDGE

Page 9: Plan for major repairs and maintenance work on JCCBI structures

SAFETY, MOBILTY AND SUSTAINABILITYMajor infrastructure projects

Page 10: Plan for major repairs and maintenance work on JCCBI structures

10

Structural reinforcement and repairs

CHAMPLAIN BRIDGE

48 trusses to be installed 11 joints to be replaced6 piers to be repaired+

#OurProjects

Installation of trusses; repairs to piers, slab and deck joints

Page 11: Plan for major repairs and maintenance work on JCCBI structures

11

TRAFFIC CLOSURES+ Full closure towards the South Shore

(April 30 - May 1)+ Full closure towards Montreal

(May 7 - 8)+ Integration of Turcot work and the

New Champlain Bridge Corridor

SCHEDULE+ First two weekends in May

SPRING BLITZ

#OurProjects

Page 12: Plan for major repairs and maintenance work on JCCBI structures

12

TRAFFIC CLOSURES

+ Traffic in both directions combined on one side of the bridge (2 weekends)

+ Complete closure towards the South Shore (2 weekends)

+ Integration of Turcot work and the New Champlain Bridge Corridor

SCHEDULE

+ September and October 2016

FALL BLITZ

lll Deck joint replacement (11)

#OurProjects

Scenario and dates to be confirmed

Page 13: Plan for major repairs and maintenance work on JCCBI structures

13

Monthly inspection patrols+ Trucks carrying a 48-tonne

load+ Slowed traffic + Real-time monitoring of bridge

behaviour+ Comparative analysis with

historical data

COMPARATIVE LOAD BEARING TESTS

Page 14: Plan for major repairs and maintenance work on JCCBI structures

14

DECK REPLACEMENT

HONORÉ MERCIER BRIDGE

Deck replacement

#OurProjects

Page 15: Plan for major repairs and maintenance work on JCCBI structures

15

DECK REPLACEMENT

FEDERAL SECTION+ Île Maline+ Seaway+ Mixed section (remaining section)+ Ramps 2-3-4

2013-20142015

2008-2011

2016

#OurProjects

Highly complex work Aggressive timeline +

Page 16: Plan for major repairs and maintenance work on JCCBI structures

16

DECK REPLACEMENTTRAFFIC CLOSURES+ Preparatory work (4 weekends at the

end of May and in June)+ Phase 1 (downstream): 1 lane for

each direction of traffic (4 weeks)+ Phase 2 (upstream): 1 lane for each

direction of traffic (4 weeks)+ Truck restrictions

SCHEDULE+ June 24 to end of August 2016

#OurProjects

Page 17: Plan for major repairs and maintenance work on JCCBI structures

17

+ Precast concrete panels that weigh 25 to 55 tonnes each+ Panels are preconnected at the factory; unique panel dimensions+ Estimated lifespan of 75 years

#OurProjects

Page 18: Plan for major repairs and maintenance work on JCCBI structures

18

Phase 14 weeks

Page 19: Plan for major repairs and maintenance work on JCCBI structures

19

Phase 24 weeks

Page 20: Plan for major repairs and maintenance work on JCCBI structures

20

TRAFFIC+ Close monitoring to balance traffic from Highway 132 and Route 138+ Policing authorities, the SAAQ and towing teams on site+ Installation of VMS in the local region to inform users

PUBLIC TRANSIT+ Same number of cars on the Candiac train line (no summer reduction)+ Reserved bus lane at the bridge approaches

TRUCKS+ Trucks are prohibited during rush hour during Phase 1; no trucks allowed during Phase 2+ Detour via the new A-30 and the Champlain Bridge

Mitigation measures

DECK REPLACEMENT

#OurProjects

Page 21: Plan for major repairs and maintenance work on JCCBI structures

21

MELOCHEVILLE TUNNEL

lll Repairs to the tunnel structure#OurProjects

Alternating traffic until December 2016

Page 22: Plan for major repairs and maintenance work on JCCBI structures

22

Major work from abutment to abutment

JACQUES CARTIER BRIDGE

Repairs to the Île Sainte-Hélène pavilion

Pier repairsReplacement of bearing supports

and steel work

Lighting work

#OurProjects

Page 23: Plan for major repairs and maintenance work on JCCBI structures

23

REPLACEMENT OF SUPPORTS AND STEEL WORK

TRAFFIC CLOSURES

+ Complete closures at night (±15)

+ Partial weekend closures (7)

+ Closure of one lane on René-Lévesque Boul. East towards downtown (180 days in 2 phases)

+ Some closures on the local network (for short and long periods)

SCHEDULE

+ April 2016 to April 2017#OurProjects

Page 24: Plan for major repairs and maintenance work on JCCBI structures

24

LANE CLOSURE René-Lévesque Boul. East

#OurProjects

Page 25: Plan for major repairs and maintenance work on JCCBI structures

25

ÎLE SAINTE-HÉLÈNE PAVILIONTRAFFIC CLOSURES

+ Closure of one access ramp to the Île Sainte-Hélène

+ Partial closure of the multipurpose path

+ Closure of one lane on the bridge

SCHEDULE

+ Closures planned on 3 weekends in May

+ Ongoing work until June 2016lll Building repairs#OurProjects

Page 26: Plan for major repairs and maintenance work on JCCBI structures

26

TRAFFIC CLOSURES

+ Complete closures at night (10)

+ Partial lane closures

+ Short-term closures in the local network

SCHEDULE

+ July 2016 to April 2017

LIGHTING PROJECT

#OurProjects

Page 27: Plan for major repairs and maintenance work on JCCBI structures

27

BONAVENTURE EXPRESSWAY

Repair of non-elevated section

Construction of a retaining wall

TRAFFIC CLOSURES

+ Closure of one out of three lanes towards downtown

+ Night and weekend closures in the local network

SCHEDULE

+ Lane reduction from June to December 2016

+ Pavement work from August to October 2016

#OurProjects

Page 28: Plan for major repairs and maintenance work on JCCBI structures

28

New dedicated bicycle path

CHAMPLAIN BRIDGE ICE CONTROL STRUCTURE

lll Inauguration this spring #OurProjects

Page 29: Plan for major repairs and maintenance work on JCCBI structures

29

APRIL MAY JUNE JULYM T W T F S S M T W T F S S M T W T F S S M T W T F S S

1 2 3 2 3 4 5 6 7 8 1 2 3 4 5 1 2 3

4 5 6 7 8 9 10 9 10 11 12 13 14 15 6 7 8 9 10 11 12 4 5 6 7 8 9 10

11 12 13 14 15 16 17 16 17 18 19 20 21 22 13 14 15 16 17 18 19 11 12 13 14 15 16 17

18 19 20 21 22 23 24 23 24 25 26 27 28 29 20 21 22 23 24 25 26 18 19 20 21 22 23 24

25 26 27 28 29 30 1 30 31 27 28 29 30 25 26 27 28 29 30 31

AUGUST SEPTEMBER OCTOBER NOVEMBERM T W T F S S M T W T F S S M T W T F S S M T W T F S S

1 2 3 4 5 6 7 1 2 3 4 1 2 31 1 2 3 4 5 6

8 9 10 11 12 13 14 5 6 7 8 9 10 11 3 4 5 6 7 8 9 7 8 9 10 11 12 13

15 16 17 18 19 20 21 12 13 14 15 16 17 18 10 11 12 13 14 15 16 14 15 16 17 18 19 20

22 23 24 25 26 27 28 19 20 21 22 23 24 25 17 18 19 20 21 22 23 21 22 23 24 25 26 27

29 30 31 26 27 28 29 30 24 25 26 27 28 29 30 28 29 30

OVERALL PLANNING FOR MAJOR PROJECTS Champlain Honoré-Mercier Jacques-Cartier #OurProjects

Subject to change

Page 30: Plan for major repairs and maintenance work on JCCBI structures

ONGOING INFORMATIONTransparent communication and mobile tools

Page 31: Plan for major repairs and maintenance work on JCCBI structures

31

+ Ongoing communication with traffic reporters and the media, interviews and on-site tours

+ Exhaustive ad campaigns for the blitzes

+ Tweets about closures and information about each structure @pontJCBridge @pontChampBridge @pontHMBridge

+ Collaboration with municipal agencies and partners to communicate information to the public

+ Dialogue with users and nearby residents

+ Presence on multiple social networks

+ New website www.JacquesCartierChamplain.ca

To keep people informed

ONGOING UPDATES

#OurProjects

Page 32: Plan for major repairs and maintenance work on JCCBI structures

#OurProjects