plan for major repairs and maintenance work on jccbi structures
TRANSCRIPT
2016 ProjectsPlan for major repairs and maintenance work on JCCBI structures
April 2016#OurProjects
2
#OurProjects
PLANNING WORKAhead of time and on time
4
COORDINATION AND OPTIMZATION
JCCBI
MTMDET
SSL
Ville de Montréal
South Shore municipalities
(+10)
Mohawk Council of
KahnawakeEnvironnement
Québec & Canada
AMTPublic transit corporations
Police authorities
Emergency services
Media
USERS USERS
USER
S
USERS
USER
S
USERS
THOROUGH PLANNING WITH PARTNERS
+ Numerous inter-organizational work meetings
+ Work concentrated at night and on weekends
+ Work optimized to reduce impact on users
#OurProjects
5
STRUCTURES 2015(completed)
2016(budgeted)
Champlain Bridge $89M $126M
Jacques Cartier Bridge $50M $85M
Honoré Mercier Bridge $19M $46M
Environment $1M $18M
Melocheville Tunnel $7M $9M
Bonaventure Expressway $22M $8M
Champlain Bridge Ice Control Structure $28M $8M
Highway 15 $7M -
Île des Sœurs Bypass Bridge $3M -
TOTAL $226M $300M
Major work on our structures
FORECASTED INVESTMENT
#OurProjects
6
+ Nearly 8,000 interventions were coordinated on our network in 2015+ Maintenance crews patrol each structure every day+ Holidays and events taken into consideration
CLOSURE AND MAINTENANCE MANAGEMENT
DAILY COORDINATION AND MONITORING
7
KEY EVENT INFRASTRUCTURE
lll Tour de l’Île (June 5) lll Fireworks (July) lll Montreal Marathon (September 25)
The Corporation ensures that infrastructure under its management remains safe, fully functional and aesthetically pleasing, today and in the future.+
#OurProjects
8
VISION: JACQUES CARTIER BRIDGE
SAFETY, MOBILTY AND SUSTAINABILITYMajor infrastructure projects
10
Structural reinforcement and repairs
CHAMPLAIN BRIDGE
48 trusses to be installed 11 joints to be replaced6 piers to be repaired+
#OurProjects
Installation of trusses; repairs to piers, slab and deck joints
11
TRAFFIC CLOSURES+ Full closure towards the South Shore
(April 30 - May 1)+ Full closure towards Montreal
(May 7 - 8)+ Integration of Turcot work and the
New Champlain Bridge Corridor
SCHEDULE+ First two weekends in May
SPRING BLITZ
#OurProjects
12
TRAFFIC CLOSURES
+ Traffic in both directions combined on one side of the bridge (2 weekends)
+ Complete closure towards the South Shore (2 weekends)
+ Integration of Turcot work and the New Champlain Bridge Corridor
SCHEDULE
+ September and October 2016
FALL BLITZ
lll Deck joint replacement (11)
#OurProjects
Scenario and dates to be confirmed
13
Monthly inspection patrols+ Trucks carrying a 48-tonne
load+ Slowed traffic + Real-time monitoring of bridge
behaviour+ Comparative analysis with
historical data
COMPARATIVE LOAD BEARING TESTS
14
DECK REPLACEMENT
HONORÉ MERCIER BRIDGE
Deck replacement
#OurProjects
15
DECK REPLACEMENT
FEDERAL SECTION+ Île Maline+ Seaway+ Mixed section (remaining section)+ Ramps 2-3-4
2013-20142015
2008-2011
2016
#OurProjects
Highly complex work Aggressive timeline +
16
DECK REPLACEMENTTRAFFIC CLOSURES+ Preparatory work (4 weekends at the
end of May and in June)+ Phase 1 (downstream): 1 lane for
each direction of traffic (4 weeks)+ Phase 2 (upstream): 1 lane for each
direction of traffic (4 weeks)+ Truck restrictions
SCHEDULE+ June 24 to end of August 2016
#OurProjects
17
+ Precast concrete panels that weigh 25 to 55 tonnes each+ Panels are preconnected at the factory; unique panel dimensions+ Estimated lifespan of 75 years
#OurProjects
18
Phase 14 weeks
19
Phase 24 weeks
20
TRAFFIC+ Close monitoring to balance traffic from Highway 132 and Route 138+ Policing authorities, the SAAQ and towing teams on site+ Installation of VMS in the local region to inform users
PUBLIC TRANSIT+ Same number of cars on the Candiac train line (no summer reduction)+ Reserved bus lane at the bridge approaches
TRUCKS+ Trucks are prohibited during rush hour during Phase 1; no trucks allowed during Phase 2+ Detour via the new A-30 and the Champlain Bridge
Mitigation measures
DECK REPLACEMENT
#OurProjects
21
MELOCHEVILLE TUNNEL
lll Repairs to the tunnel structure#OurProjects
Alternating traffic until December 2016
22
Major work from abutment to abutment
JACQUES CARTIER BRIDGE
Repairs to the Île Sainte-Hélène pavilion
Pier repairsReplacement of bearing supports
and steel work
Lighting work
#OurProjects
23
REPLACEMENT OF SUPPORTS AND STEEL WORK
TRAFFIC CLOSURES
+ Complete closures at night (±15)
+ Partial weekend closures (7)
+ Closure of one lane on René-Lévesque Boul. East towards downtown (180 days in 2 phases)
+ Some closures on the local network (for short and long periods)
SCHEDULE
+ April 2016 to April 2017#OurProjects
24
LANE CLOSURE René-Lévesque Boul. East
#OurProjects
25
ÎLE SAINTE-HÉLÈNE PAVILIONTRAFFIC CLOSURES
+ Closure of one access ramp to the Île Sainte-Hélène
+ Partial closure of the multipurpose path
+ Closure of one lane on the bridge
SCHEDULE
+ Closures planned on 3 weekends in May
+ Ongoing work until June 2016lll Building repairs#OurProjects
26
TRAFFIC CLOSURES
+ Complete closures at night (10)
+ Partial lane closures
+ Short-term closures in the local network
SCHEDULE
+ July 2016 to April 2017
LIGHTING PROJECT
#OurProjects
27
BONAVENTURE EXPRESSWAY
Repair of non-elevated section
Construction of a retaining wall
TRAFFIC CLOSURES
+ Closure of one out of three lanes towards downtown
+ Night and weekend closures in the local network
SCHEDULE
+ Lane reduction from June to December 2016
+ Pavement work from August to October 2016
#OurProjects
28
New dedicated bicycle path
CHAMPLAIN BRIDGE ICE CONTROL STRUCTURE
lll Inauguration this spring #OurProjects
29
APRIL MAY JUNE JULYM T W T F S S M T W T F S S M T W T F S S M T W T F S S
1 2 3 2 3 4 5 6 7 8 1 2 3 4 5 1 2 3
4 5 6 7 8 9 10 9 10 11 12 13 14 15 6 7 8 9 10 11 12 4 5 6 7 8 9 10
11 12 13 14 15 16 17 16 17 18 19 20 21 22 13 14 15 16 17 18 19 11 12 13 14 15 16 17
18 19 20 21 22 23 24 23 24 25 26 27 28 29 20 21 22 23 24 25 26 18 19 20 21 22 23 24
25 26 27 28 29 30 1 30 31 27 28 29 30 25 26 27 28 29 30 31
AUGUST SEPTEMBER OCTOBER NOVEMBERM T W T F S S M T W T F S S M T W T F S S M T W T F S S
1 2 3 4 5 6 7 1 2 3 4 1 2 31 1 2 3 4 5 6
8 9 10 11 12 13 14 5 6 7 8 9 10 11 3 4 5 6 7 8 9 7 8 9 10 11 12 13
15 16 17 18 19 20 21 12 13 14 15 16 17 18 10 11 12 13 14 15 16 14 15 16 17 18 19 20
22 23 24 25 26 27 28 19 20 21 22 23 24 25 17 18 19 20 21 22 23 21 22 23 24 25 26 27
29 30 31 26 27 28 29 30 24 25 26 27 28 29 30 28 29 30
OVERALL PLANNING FOR MAJOR PROJECTS Champlain Honoré-Mercier Jacques-Cartier #OurProjects
Subject to change
ONGOING INFORMATIONTransparent communication and mobile tools
31
+ Ongoing communication with traffic reporters and the media, interviews and on-site tours
+ Exhaustive ad campaigns for the blitzes
+ Tweets about closures and information about each structure @pontJCBridge @pontChampBridge @pontHMBridge
+ Collaboration with municipal agencies and partners to communicate information to the public
+ Dialogue with users and nearby residents
+ Presence on multiple social networks
+ New website www.JacquesCartierChamplain.ca
To keep people informed
ONGOING UPDATES
#OurProjects
#OurProjects