jess albino fac cf [email protected] april 16, 2007 meeting of the lcls facilities...
Post on 21-Dec-2015
214 views
TRANSCRIPT
Jess Albino
FAC CF Overview [email protected]
April 16, 2007
Meeting of the LCLS Facilities Advisory Committee
LCLS Conventional Facilities
Jess Albino
Jess Albino
FAC CF Overview [email protected]
April 16, 2007
Conventional Facilities
•Major Developments
•Project Team
•Status of Construction
•Construction Schedule
•6 Month Look-ahead
•Summary
Jess Albino
FAC CF Overview [email protected]
April 16, 2007
Major Developments
• Construction Underway–Beam Transfer Hall
–Undulator Hall Tunnel
–Electron Beam Dump/Front End Enclosure
–Near Experimental Hall
–Access Tunnel
Jess Albino
FAC CF Overview [email protected]
April 16, 2007
Major Developments – cont’d
• Relocation of CM/GC
•Preparation of Laboratory Functionality Strategy
•Contractor Claim
Jess Albino
FAC CF Overview [email protected]
April 16, 2007
PROJECT TEAM
Additional Hires in CF
CM/GC Personnel Changes
ES&H / SME Support
Consultants for Quality Control Testing
Jess Albino
FAC CF Overview [email protected]
April 16, 2007
CONSTRUCTION SCHEDULEMARCH 2007 UPDATE
BEAM TRANSFER HALLConcrete Work ahead 6 daysExcavation at East end subject to Undulator Tunnel late start.
UNDULATOR HALL TUNNELDelayed Start 11 days – late submittals and temporary power
ELECTRON BEAM DUMP – Excavation may be delayed by Undulator Tunnel and Utilities
Jess Albino
FAC CF Overview [email protected]
April 16, 2007
CONSTRUCTION SCHEDULEMARCH 2007 UPDATE
FRONT END ENCLOSURE – Excavation may be delayed by Utilities – partial excavation completedNEAR EXPERIMENTAL HALL – Ahead of schedule 7daysX- RAY TUNNEL – No Activity this monthFAR EXPERIMENTAL HALL – No Activity this monthACCESS TUNNEL – late start; late submittals and temporary power – approx. 100 ft mined to date
Jess Albino
FAC CF Overview [email protected]
April 16, 2007
CONSTRUCTION SCHEDULEMARCH 2007 UPDATE
RECOVERY OPTIONSAccelerate Undulator Hall Tunnel
Value Engineer Predecessor Activities
Begin Second Shift of Mining
Value Engineer Excavation / Support Sequence
Jess Albino
FAC CF Overview [email protected]
April 16, 2007
6 MONTH LOOK-AHEAD
CONSTRUCTIONComplete BTH
Complete UH tunnel
Excavate and Pour Electron Beam Dump
Excavate and Pour CUP base slab
Excavate and Pour FEE
Complete Access Tunnel
Jess Albino
FAC CF Overview [email protected]
April 16, 2007
6 MONTH LOOK-AHEAD (cont.)
Construction (cont.)Start Excavation of Far Experimental Hall
Start Excavation of X-Ray Tunnel
Jess Albino
FAC CF Overview [email protected]
April 16, 2007
Summary
Construction is underway for all major areasCF staff has been strengthened / tailored for construction phaseContractor Staff Changes Schedule Recovery Plans are in processContinue to Value Engineer Interface with SLAC, Tech. Systems, CM/GCRe-double efforts to support TCCo and Construction to prevent delays – keep to the schedule.