job well done—ahead of schedule - data center chilled water plant and distribution system

1
The content of this document is not intended as an endorsement. www.mckenneys.com © 2015 McKenney’s, Inc., Atlanta, Georgia. All rights reserved. Printed in the U.S.A. McKenney’s, Inc. and the McKenney’s, Inc. logo are registered trademarks of McKenney’s, Inc. All other trademarks are the property of their respective owners. 404-622-5000 [email protected] 1056 Moreland Industrial Boulevard Atlanta, Georgia 30316 704-357-1200 [email protected] 3601 Performance Road Charlotte, North Carolina 28214 M cKenney’s installed a 900-ton air-cooled chilled water plant and associated distribution system for a new 1.5MW data center in Alpharetta, Georgia. THE CHALLENGE Turning an abandoned warehouse into a 20,000-square-foot data center was no sim- ple task given the aggressive schedule. The McKenney’s team had to contend with limited space under the raised floor throughout the facility. Careful planning and coordination was essential to avoid losing capacity from reduced airflow to the computer room air handler (CRAH) units. THE SOLUTION Leveraging BIM capabilities, the team coordi- nated mechanical and electrical services to maximize heat rejection capacity at the serv- ers. McKenney’s prefabricated most of the chilled water plant, connections to the major pieces of equipment and distribution piping. Concurrent operation ensured the piping sys- tems were installed as soon as the structure was ready, minimizing field installation time to meet the compressed construction schedule. THE RESULTS A seamless start-up, and commissioning accelerated the turnover of the Peak 10 data center to the owner. Job Well Done—Ahead of Schedule PROJECT NAME Peak 10 Data Center Chilled Water Plant and Distribution System PROJECT LOCATION Alpharetta, Georgia PROJECT TEAM Owner: Peak 10, Inc. General Contractor: Balfour Beatty Architect: Reynolds, Smith & Hills, Inc. Engineer: Reynolds, Smith & Hills, Inc. Subcontractor: McKenney’s, Inc. SPECIALIZATIONS Building Information Modeling Plumbing Shop Prefab Pipe Shop Prefab MARKETS Mission Critical

Upload: mckenneys-inc

Post on 06-Nov-2015

14 views

Category:

Documents


0 download

DESCRIPTION

McKenney’s installed a 900-ton air-cooled chilled water plant and associated distribution system for a new 1.5MW data center in Alpharetta, Georgia.

TRANSCRIPT

  • The content of this document is not intended as an endorsement.

    www.mckenneys.com 2015 McKenneys, Inc., Atlanta, Georgia. All rights reserved. Printed in the U.S.A.

    McKenneys, Inc. and the McKenneys, Inc. logo are registered trademarks of McKenneys, Inc. All other trademarks are the property of their respective owners.

    404-622-5000 [email protected] 1056 Moreland Industrial Boulevard Atlanta, Georgia 30316

    704-357-1200 [email protected]

    3601 Performance Road Charlotte, North Carolina 28214

    McKenneys installed a 900-ton air-cooled chilled water plant and associated distribution system for a new 1.5MW data center in Alpharetta, Georgia.

    The ChallengeTurning an abandoned warehouse into a 20,000-square-foot data center was no sim-ple task given the aggressive schedule. The McKenneys team had to contend with limited

    space under the raised floor throughout the facility. Careful planning and coordination was essential to avoid losing capacity from reduced airflow to the computer room air handler (CRAH) units.

    The SoluTionLeveraging BIM capabilities, the team coordi-nated mechanical and electrical services to maximize heat rejection capacity at the serv-ers. McKenneys prefabricated most of the

    chilled water plant, connections to the major pieces of equipment and distribution piping. Concurrent operation ensured the piping sys-tems were installed as soon as the structure was ready, minimizing field installation time to meet the compressed construction schedule.

    The ReSulTSA seamless start-up, and commissioning accelerated the turnover of the Peak 10 data center to the owner.

    Job Well DoneAhead of SchedulePRojeCT name

    Peak 10 Data Center Chilled Water Plant and Distribution System

    PRojeCT loCaTion

    Alpharetta, Georgia

    PRojeCT Team

    Owner: Peak 10, Inc.

    General Contractor: Balfour Beatty

    Architect: Reynolds, Smith & Hills, Inc.

    Engineer: Reynolds, Smith & Hills, Inc.

    Subcontractor: McKenneys, Inc.

    SPeCializaTionS

    Building Information Modeling

    Plumbing Shop Prefab

    Pipe Shop Prefab

    maRkeTS

    Mission Critical