johnmoebes
TRANSCRIPT
8/6/2019 JohnMoebes
http://slidepdf.com/reader/full/johnmoebes 1/27
1
Integrated Project Delivery at
Crate&BarrelJohn Moebes, AIA NCARB
Director of ConstructionCrate&Barrel
8/6/2019 JohnMoebes
http://slidepdf.com/reader/full/johnmoebes 2/27
2
Crate&Barrel
Founded in 1962
Headquartered in
Northbrook, IL
145 Stores
$1.4 Billion Annual Sales
7,000 Employees
Retailers of Housewares &
Furniture Emphasis on People,
Product and Presentation
8/6/2019 JohnMoebes
http://slidepdf.com/reader/full/johnmoebes 3/27
3
Crate&Barrel
We don’t use prototypes
Each store is a unique
design. No efficiency
Complex articulation in planand elevation
Neo-Modernist approach todesign and detailing
Difficult materials to source
High sensitivity to deliveredfacility. Building as Brand
End users have powerfulvoices.
8/6/2019 JohnMoebes
http://slidepdf.com/reader/full/johnmoebes 4/27
4
Crate&Barrel
What doesn’t work withtraditional delivery:
Longer production ofContract Documents
Long Lead Items cannotbe procured early
Subcontractors cannotprovide input in detailingand specifications
Team Members stilloperate in their traditionalsilos of risk and reward
8/6/2019 JohnMoebes
http://slidepdf.com/reader/full/johnmoebes 5/27
5
Crate&Barrel
Advantages we havein implementing IPD
Same consultants
Same construction
managers
Same Systems
Same end goalWillingness to absorbmore project risk
8/6/2019 JohnMoebes
http://slidepdf.com/reader/full/johnmoebes 6/276
Crate&BarrelOur process
In House Architecture andDesign produces SchematicDesign package
In House ConstructionDepartment acts as CM atAgency
Outsourced AssociateArchitecture (CDs & CA),Structural Engineering, MEP
Engineering CM at Risk using the 1997
AIA A111 and A201 contract
Large Amount of OwnerFurnished Materials
8/6/2019 JohnMoebes
http://slidepdf.com/reader/full/johnmoebes 7/277
Crate&BarrelOur schedules
6 week conceptual designphase
24 week document schedule 32 – 42 week construction
schedule
4 week commissioningperiod
Start after January 15th
Finish before November 15th
Only open on a Thursday
One opening per week
8/6/2019 JohnMoebes
http://slidepdf.com/reader/full/johnmoebes 8/278
Crate&BarrelCosts
A/E: $450,000
CM@Risk $9,000,000
OFM $1,500,000
FF&E $1,500,000
Misc $550,000Total $13,000,000
8/6/2019 JohnMoebes
http://slidepdf.com/reader/full/johnmoebes 9/279
Crate&Barrel
We like to think of Integrated ProjectDelivery as the difference betweenMixtures, Solutions, andCompounds.
Mixtures: two or more Entities whichhave been organized such thateach Entity retains its owntraditional identity and is active onlyduring certain phases of the
processSolutions: A mixture of two or more
Entities which have been organizedand managed such that each Entityhas a non-traditional identity during
most phases of the processCompounds: A Solution of Entities
which have been organized andmanaged such that each Entity hasan identity defined by the
compound during all phases of theprocess. A compound usually hasproperties unlike those of itsconstituent elements.
8/6/2019 JohnMoebes
http://slidepdf.com/reader/full/johnmoebes 10/2710
Crate&Barrel
Our Basic Principles
Focus on optimizing our
scheduleAdjust traditional projectroles to support the
scheduleOrchestrate meaningfulcollaboration
Eliminate Low Value-AddSteps
8/6/2019 JohnMoebes
http://slidepdf.com/reader/full/johnmoebes 11/2711
Crate&Barrel
Most traditional (non-integrated) delivery
methods produce Mixtures
Most IPD thinking produces
Solutions
At Crate&Barrel, we are tryingto create a process thatproduces Compounds
8/6/2019 JohnMoebes
http://slidepdf.com/reader/full/johnmoebes 12/2712
Crate&Barrel
• Integration Steps
• Performance Metrics
• Workflow Standards
• AECO Team Solution
• Prime SubcontractorAwards
• Long-Lead Systems
• Operations Inclusion
8/6/2019 JohnMoebes
http://slidepdf.com/reader/full/johnmoebes 13/2713
Crate&Barrel
• Performance MetricsIntegration
• What will make this project asuccess to us.
• Presentation of the Owner’sPro Forma and Budget
• Discussion amongst theTeam of all soft costs, fees,general conditions, general
requirements, billing rates,etc.
• Everyone knows whateveryone else’s Risk &
Reward profile is
8/6/2019 JohnMoebes
http://slidepdf.com/reader/full/johnmoebes 14/2714
Crate&Barrel
Workflow StandardsIntegration
• Web-based ProjectManagement for more and
more workflow
• Acrobat file format for alldeliverables
• BIM deliverables• Web conferencing with sync
Audio that is recorded andstored
• Owner-controlled shippingand reprography
• Blackberrys
• Synchronized Travel
8/6/2019 JohnMoebes
http://slidepdf.com/reader/full/johnmoebes 15/2715
Crate&Barrel
• AECO Team Solution
• People will not integrate if theydon’t like or respect each other.
• Use consultants with long-standing relationships to theother team members
• Good integration occurs with ahealthy mix of experience anddiversity on a team.
• Integrated teams will suffer frommembers that are close-mindedand conservative.
• Avoid design-build in theconstruction phase if integrationis improved in the earlier phases.
8/6/2019 JohnMoebes
http://slidepdf.com/reader/full/johnmoebes 16/2716
Crate&Barrel
• Prime SubContractor Integration- Steel
• Early Contract to Owner (Cost
Plus w/GMP), later assigned toCM via a novation agreement.
• Selection criteria includes abilityto work with an AE design team.Software/person-ware
• Require conference-style reviewof shop drawings with AE.
• Fabricator must be included in allMEP/FP coordination.
• A good fabricator-member willwant to educate the team aboutroll dates, Fab-Trol, etc. And willwant you to tour their shop,
which you should takeadvantage of.
8/6/2019 JohnMoebes
http://slidepdf.com/reader/full/johnmoebes 17/2717
Crate&BarrelOne of Our Strongest IDP Partner: SteelFAB
8/6/2019 JohnMoebes
http://slidepdf.com/reader/full/johnmoebes 18/2718
Crate&BarrelOur Greatest Success: Steel, Steel, Steel
Benefits from:
Good SER and Fabricator relationship;
Mutually Beneficial Use of BIM: RAM toTekla; and
A Process-Oriented Fabricator
Have been:
190 tons to 140 tons Average ProjectWeight
Fabrication Times reduced from 6weeks to 2 weeks.Shop Drawings Produced in 3 weeksinstead of 6 weeks.
Erection Times reduced to 3 weeks from6 weeks.
Almost Complete Elimination of FieldRe-Work due to Fabricator Error
8/6/2019 JohnMoebes
http://slidepdf.com/reader/full/johnmoebes 19/2719
Crate&Barrel
• Prime SubContractor Integration – MEP/FP
• Early Contract to Owner (Cost
Plus w/GMP), later assigned toCM via a novation agreement.
• Selection criteria includes abilityto work with an AE design team.Software/person-ware
• Require conference-style reviewof shop drawings with AECM.
• Mechanical Subcontractor musthold the third tier subcontracts
for the plumbing and fireprotection for coordination andscheduling purposes.
• Selected MCs must have digital
design/fabricate/install systemsin place.
8/6/2019 JohnMoebes
http://slidepdf.com/reader/full/johnmoebes 20/2720
Crate&BarrelThe New Kids on the IPD Block: Hill Mechanical, Johnson
Controls, JF Ahern
8/6/2019 JohnMoebes
http://slidepdf.com/reader/full/johnmoebes 21/2721
Crate&Barrel
• Long Lead Systems
• Pre-purchase all materialsthat have lead times thatexceed the CM schedule.
• Systems that containengineering, fabrication,delivery, installation andcommissioning must betreated the same as AEconsultants. We maintainseparate contracts with these
Entities.• Systems Providers provide a
Readiness Checklist for theircomponents that is included
in the Contract Documents.
8/6/2019 JohnMoebes
http://slidepdf.com/reader/full/johnmoebes 22/27
22
Crate&BarrelOur Current Focus: Pre-Fabrication and Modularization
8/6/2019 JohnMoebes
http://slidepdf.com/reader/full/johnmoebes 23/27
23
Crate&Barrel
• Operations Inclusion
• Business Critical SystemsProviders are brought in prior to
SD to begin planning design,procurement, , fabrication,delivery, installation,commissioning, and operationsintegration
These Providers may be Owner-Contracted, some may be CM-Contracted.
Specifications and detailing
conducted with Providers, AEs,CMs, and Operations to integrateall facets of need.
Such integration has led tomodularization and
prefabrication of switchgear anddoors
8/6/2019 JohnMoebes
http://slidepdf.com/reader/full/johnmoebes 24/27
24
Crate&Barrel
Things we have learnedthat do not work with
IPD Activating team memberstoo early
Procuring material tooearly
Focusing Technology of
the wrong trade
Silo-Scheduling
Design-Building the wrongthing
8/6/2019 JohnMoebes
http://slidepdf.com/reader/full/johnmoebes 25/27
25
Crate&Barrel
Things that we will neverrepeat with IPD
AEs that didn’t understandcritical fabrication issues
Assemblies that were
procured too late andcaused overtime
CMs that didn’t
understand operationsconcerns
Spending one month of
time reworking mis-coordinated disciplines
8/6/2019 JohnMoebes
http://slidepdf.com/reader/full/johnmoebes 26/27
26
Crate&Barrel
Success Stories
CD schedules have reducedfrom 24 weeks to 8 weeks
Well Coordinated ContractDocuments
Transparent Workflow
Tonnage reduction from 220to 160 tons.
“Well Liked” HVAC systems
Elimination of overtimecharges due to late deliveries
Happier projects