    BRIEFINGTOTHE ARTS, CULTURE

    & LIBRARIES COMMITTEE

    JUNE 18, 2012

    PROGRESS REPORTONTHE

    CITY PERFORMANCE HALL1

  • 7/31/2019 June 2012 City Performance Hall Briefing

    3/26

    PURPOSEOFTHE BRIEFING

    Update the Arts, Culture & Libraries Committee

    on the status of the construction of the City

    Performance Hall

    Provide an overview of the plans for the opening

    celebration

    2

  • 7/31/2019 June 2012 City Performance Hall Briefing

    4/26

    KEY MILESTONES COMPLETED

    Since our last briefing to the Committee

    (10/17/2011), the following construction

    milestones have been completed:

    All mechanical systems are in place and functioning

    Wood floors have been installed in the public areas

    (lobby, performance chamber)

    Concrete floors in the lobby and public corridors have

    been polished to reveal the aggregate

    Seating has been installed in the performancechamber

    The rigging system is installed and functioning

    Internal wayfinding signage installed

    Landscaping is 80% complete3

  • 7/31/2019 June 2012 City Performance Hall Briefing

    5/26

    Exterior

    view from

    the corner of

    Routh &

    Flora

    4

  • 7/31/2019 June 2012 City Performance Hall Briefing

    6/26

    View of the

    Audience

    Chamber

    from Stage

    Center

    5

  • 7/31/2019 June 2012 City Performance Hall Briefing

    7/26

    View of

    Audience

    Chamber

    from Stage

    Right

    6

  • 7/31/2019 June 2012 City Performance Hall Briefing

    8/26

    View of the

    Lobby

    7

  • 7/31/2019 June 2012 City Performance Hall Briefing

    9/26

    View of

    West Side

    Landscaping

    from the

    Loading Dock

    (Site for

    Phase II

    construction)

    8

  • 7/31/2019 June 2012 City Performance Hall Briefing

    10/26

    View of the

    West

    Faade

    9

  • 7/31/2019 June 2012 City Performance Hall Briefing

    11/26

    UPCOMING KEY MILESTONES

    Certificate of Occupancy (expected June 21)

    Delivery and installation of the theatrical

    equipment

    Complete the commissioning of the buildingsystems

    Move-in and staff training on various building

    systems

    Branding plan

    10

  • 7/31/2019 June 2012 City Performance Hall Briefing

    12/26

    BRANDING PLAN

    Working with SparkFarm and El Creative

    Dallas-based companies

    SparkFarm worked on the grand opening of the

    AT&T Performing Arts Center

    El Creative has worked on branding for Bahama

    Beach and the Love Field Modernization Program

    Develop the brand concept and marketing for

    the grand opening event

    11

  • 7/31/2019 June 2012 City Performance Hall Briefing

    13/26

  • 7/31/2019 June 2012 City Performance Hall Briefing

    14/26

    GRAND OPENING WEEKEND (CONT.)

    Saturday & Sunday, September 15 & 16, 2012

    Community Open House

    Free programming targeting families

    Brief performances throughout the day by local

    groups (dance, theater, music)

    Information booths for local arts and cultural groups

    Ticketed jazz concert featuring North Texas jazz

    artists on Saturday night

    13

  • 7/31/2019 June 2012 City Performance Hall Briefing

    15/26

    2012-2013 PROGRAMMING HIGHLIGHTS

    Exciting and varied schedule of performances by

    Dallas arts and cultural groups

    Lone Star Wind Orchestra (October 2012)

    Resounding Harmony (November 2012)

    Turtle Creek Chorale (February 2013)

    Dallas Black Dance Theater (March 2013)

    Please note these are just highlights; additional performances are booked through the year

    14

  • 7/31/2019 June 2012 City Performance Hall Briefing

    16/26

    QUESTIONS? 15

  • 7/31/2019 June 2012 City Performance Hall Briefing

    17/26

    APPENDICES

    Appendix I City Performance Hall Background

    Appendix II Project Development

    16

  • 7/31/2019 June 2012 City Performance Hall Briefing

    18/26

    APPENDIXI

    CITYPERFORMANCE HALL BACKGROUND

    The City Performance Hall is one of five venuesincluded in the Dallas Center for the PerformingArts Master Plan Winspear Opera House

    Wyly Theater

    Annette Strauss Square Sammons Performance Park

    City Performance Hall

    A development agreement with the Dallas Center

    for the Performing Arts Foundation wasauthorized on 9/28/2005 Foundation developed four venues (AT&T Performing

    Arts Center)

    City designing and constructing the City PerformanceHall

    17

  • 7/31/2019 June 2012 City Performance Hall Briefing

    19/26

    APPENDIXI

    CPH BACKGROUND (CONT.)

    Need for the facility identified in the Master

    Planning process for the performing arts center

    Referred to as the third venue

    Conceived to serve the needs of small and medium

    arts groups reflecting the diverse communities ofDallas

    Inclusion in the Master Plan received broad

    support from the cultural community

    18

  • 7/31/2019 June 2012 City Performance Hall Briefing

    20/26

    APPENDIXI

    CPH BACKGROUND (CONT.)

    Project Funding

    Performing arts facilities developed throughpublic/private partnership with the Dallas Centerfor the Performing Arts Foundation

    $68 million -- City bond contribution for landacquisition, infrastructure, Annette Strauss Square& City Performance Hall (1995, 1998, 2003 & 2006Bond Programs)

    $330 million -- Foundation private sector support for

    Winspear Opera House, Wyly Theater, SammonsPark, 2 underground garages

    19

  • 7/31/2019 June 2012 City Performance Hall Briefing

    21/26

    APPENDIXI

    CPH BACKGROUND (CONT.)

    City Performance Hall represents the largestpublic sector contribution to the public/privatepartnership responsible for the development ofthe performing arts center

    2003 Bond Program $2.25 million to for program and design

    2006 Bond Program

    $38.2 million for design and construction of

    Phase I

    20

  • 7/31/2019 June 2012 City Performance Hall Briefing

    22/26

    APPENDIXII

    PROJECT DEVELOPMENT

    Programming 2004-2006

    Design (Conceptual, Schematic) 2006-2008

    Construction 2009-present

    Opening September 2012

    21

  • 7/31/2019 June 2012 City Performance Hall Briefing

    23/26

    APPENDIXII

    PROJECT DEVELOPMENT (CONT.)

    Programming process included over 70 arts

    groups Identified need for 124,000 sq. ft. facility that included a

    750seat theater, two flexible theaters, with full complement

    of public and support spaces

    Conceived to be implemented in multiple phases

    Currently under construction is Phase I (60,000

    sq. ft), the 750seat theater approved in the 2006

    Bond Program

    Completion of the rest of the 124,000 sq. ft.

    program to be supported in future bond programs

    22

  • 7/31/2019 June 2012 City Performance Hall Briefing

    24/26

    APPENDIXII

    PROJECT DEVELOPMENT (CONT.)

    Phase I consists of:

    Full lobby fronting Flora with event mezzanine

    Wood floors

    Theater seating (750 seats in two levels, orchestra &

    balcony)

    Stage pit

    Stage lighting and controls

    Performance audio and video system

    Concert enclosure and acoustical reflector panels Stage rigging and drapery system

    Motorized acoustical banners

    23

  • 7/31/2019 June 2012 City Performance Hall Briefing

    25/26

    APPENDIXII

    PROJECT DEVELOPMENT (CONT.)

    City Council approved Construction Manager At-Risk

    Guaranteed Maximum Price (GMP) construction contract

    to McCarthy Building Companies on April 22, 2009 (CR 09-

    1106)

    Construction trade contracts procured to construct the

    building within the established GMP

    City Performance Hall construction schedule coordinated

    with the AT&T PAC Silver Garage (privately funded and

    located below the City Performance Hall)

    24

  • 7/31/2019 June 2012 City Performance Hall Briefing

    26/26

    Schematic for the

    full buildout.

    Phase I (currently

    under

    construction)

    shown inside the

    red dashed line.

    Additional phases

    pending future

    bond programs.

    25