kadaladi taluk, ramanathapuram district, tamil...
TRANSCRIPT
KADALADI TALUK, RAMANATHAPURAM DISTRICT, TAMIL NADU
MAY, 2016
CONSULTING ENGINEERS
191, ANNA SALAI, CHENNAI - 600006
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO INDEX SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016
- 1 -
FEASIBILITY REPORT
FOR 5 X 800 MW KADALADI SUPER CRITICAL THERMAL POWER PROJECT
AT KADALADI TALUK RAMANATHAPURAM DISTRICT TAMIL NADU
I N D E X Section DESCRIPTION PAGE NO
1.0 INTRODUCTION AND EXECUTIVE SUMMARY 1-15
1.1 Introduction 1
1.2 TANGEDCO – An Overview 2
1.3 Executive Summary 4
1.4 Project at a Glance 8
2.0 NEED FOR THE PROJECT 16-30
2.1 Power Scenario: Introduction 16
2.2 Power Scenario in India 17
2.3 Power Scenario in Southern Region 20
2.4 Power Scenario in Tamil Nadu 23
2.5 Justification of the Project 26
3.0 BASIC REQUIREMENTS 31-44
3.1 Introduction 31
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO INDEX SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016
- 2 -
3.2 Land Area requirement & Availability 32
3.3 Water Requirement 37
3.4 Fuel Requirement 38
3.5 Power Evacuation 42
3.6 Other Infrastructural Requirements 42
4.0 SITE FEATURES 45-56
4.1 Introduction 45
4.2 Justificaiton & Discussion on Selected Site 46
4.3 Feasibility Consideration 51
5.0 TECHNICAL FEATURES 57-124
5.1 Introduction 57
5.2 Thermodynamic Cycle 57
5.3 Main Plant & Equipment 60
5.4 Auxiliary System 72
5.5 Electrical System & Equipment 100
5.6 Control & Instrumentation 110
5.7 Plant Layout 120
5.8 Civil Engineering Aspects 123
6.0 ENVIRONMENTAL ASPECTS 125-142
6.1 Introduction 125
6.2 Environmental Pollution from a Thermal Power Plant & Controlling Measures 127
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO INDEX SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016
- 3 -
6.3 Basic Information for Environmental Clearance 140
6.4 Ash Management Plan 141
6.5 Gypsum Management Plan 142
7.0 PROJECT MANAGEMENT 143-149
7.1 Introduction 143
7.2 Construction Facilities 144
7.3 Organisation Set-up for Plant Construction 147
7.4 Safety & Health Hazard Monitoring 148
7.5 Security 149
7.6 Labour Welfare & Statutory Regulations 149
8.0 PROJECT IMPLEMENTATION& ORGANISATION (O&M) 150-166
8.1 Project Implementation 150
� Introduction
� Project Organisation of the owner
� Project Execution
� Project Monitoring, Co-ordination & Control
� Role of Consultant
� Project Implementation Schedule
8.2 Organisation Structure 160
� Philosophy of Plant Design & Operation
� Organizational Set-up for Plant Operation
� Training of Personnel
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO INDEX SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016
- 4 -
9.0 PROJECT COST ESTIMATE & FINANCIAL ASPECTS 167-173
9.1 Basis of Estimates 167
9.2 Project Cost Estimate 171
9.3 Estimate of Cost of Generation 171
9.4 Recommendations & Follow-up Actions 172
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO INDEX SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016
- 5 -
Annexure - 3.1 � Sea Water Analysis
Annexure - 3.2 � Estimation of Consumptive Water Requirement
Annexure - 3.3 � Analysis of Coal
Annexure – 4.1 � Comparison of Alternate Sites
Drawing No.15ZO3-004-DWG-M-001 � Vicinity Map
Drawing No.15ZO3-004-DWG-M-002 � Site Location Map
Drawing No.15ZO3-004-DWG-M-003 � Plot Plan (2 Sheets)
Drawing No.15ZO3-004-DWG-M-008 � Coal Connectivity Route Map
Annexure – 5.1 � Brief Technical Features of Major Systems & Equipment
Drawing No.15ZO3-005-DWG-M-004 � Heat Balance Diagram (Typical)
Drawing No.15ZO3-005-DWG-M-005 � Water Balance Diagram
Drawing No.15ZO3-005-DWG-M-006 � Flow Diagram – Coal Handling System
Drawing No.15ZO3-005-DWG-M-007 � Flow Diagram – Ash Handling System
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO INDEX SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016
- 6 -
Drawing No.15ZO3-005-DWG-E-001 � Single Line Diagram – Electrical System
Annexure – 6.1 � List of Basic Equipment/
Instruments for Environmental Monitoring & Testing
Drawing No.15ZO3-006-DWG-M-009 � Waste Water Management Scheme
Drawing No. 15ZO3-007-DWG-M-010 � Organisation Chart
Drawing No. 15ZO3-008-DWG-M-011 ��Organisation Chart (O&M Team)
Drawing No. 15ZO3-008-DWG-M-012 � Project Schedule Annexure - 9.1 � Project Cost Estimate
Annexure - 9.2 (2 sheets) � Financial Tables IDC
�
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO SEC - 1 SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016
- 1 -
INTRODUCTION AND EXECUTIVE SUMMARY 1.1 INTRODUCTION: M/s Tamil Nadu Generation and Distribution Corporation
Limited (TANGEDCO) owns and operates a number of thermal
power stations in the state of Tamil Nadu now propose to set up
a thermal station of 5x800MW capacity in Kadaladi Taluk of
Ramanathapuram district. The station would adopt supercritical
technology.
The proposed 5x800MW station would require about 11.47 MTPA
(Million tons per annum) (at 85% PLF) using 100% Imported
coal (Best Coal), 13.65 MTPA (at 85% PLF) using blended coal
(Design Coal) with ratio of 30% Indigenous coal and 70%
Imported coal and 15.59 MTPA (at 85% PLF) using blended coal
(Worst Coal) with ratio of 50% Indigenous coal and 50%
Imported coal. The Imported Coal will be from Indonesia or any
other country and Indigenous coal will be from Talcher, Odisha.
Daily coal requirement at MCR is estimated at 44000 Metric Ton
(considering Design coal) for the plant. The coal will be received
at Thoothukudi sea port and from there it will be transported to
project site by rail route. Consumptive water would be drawn
from the Sea, the coastal line is at aerial distance of around 2.3
km on the Southern side of the proposed project.
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO SEC - 1 SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016
- 2 -
Development Consultants Private Limited has been entrusted by
M/s Tamil Nadu Generation and Distribution Corporation
Limited (TANGEDCO) to prepare Feasibility report and Detailed
Project Report for establishing 5x800MW Kadaladi Super critical
Thermal Power Project.
1.2 TANGEDCO – AN OVERVIEW:
On 1st July 1957, Tamil Nadu Electricity Board came into being
and has remained the energy provider and distributor all these
years. During the period the Government have extended the
electrical network to all the villages and towns throughout the
state. After 53 years of journey on 1st of November 2010 it has
restructured itself into TNEB Ltd; Tamil Nadu Generation and
Distribution Corporation (TANGEDCO) Ltd; and Tamil Nadu
Transmission Corporation (TANTRANSCO) Ltd.
MISSION OF THE GOVERNMENT:
Tamil Nadu Generation and Distribution Corporation limited is
making progress in Generation and Distribution sector. It is
happy to inform that the electrification of all villages and towns
were completed and also electrification of all households are
under progress.
GENERATION:
To satisfy the energy needs of the state, Tamil Nadu Generation
and Distribution Corporation Limited has installed generating
stations of capacity 11884.44 MW which includes State, Central
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO SEC - 1 SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016
- 3 -
share and Independent power producers. Besides, the state has
installations in renewable energy sources like windmill, Biomass
and Cogeneration up to 8219.67 MW. Due to the astronomical
increase in energy demand in future, the state has proposed new
generation projects for the next 5 years.
DISTRIBUTION:
TANGEDCO has a consumer base of about 252.32 lakh
consumers (2013-14). 100% rural electrification has been
achieved. Per Capita consumption of Tamilnadu is 1196 units
(2013-14). To achieve the goal of electrification of all
households, the Government has launched the Rajiv Gandhi
Grameen Vidyutikaran Yojana (RGGVY) scheme. Where grid
connectivity is not feasible or not cost effective, Decentralised
Distributed Generation is permitted. To achieve reliable and
quality power supply and minimise the loss of energy, MOP/GOI
has launched the Restructured APDRP scheme under 11th five
year plan and the same is being implemented by TANGEDCO.
RESTRUCTURING OF ERSTWHILE TNEB: In the G.O Ms No 114 dated 08.10.2008, Government of Tamil
Nadu has accorded approval in-principle for the re-organisation
of TNEB by the establishment of a holding company, by the
name TNEB Ltd and two subsidiary companies, namely Tamil
Nadu Transmission Corporation Ltd (TANTRANSCO) and Tamil
Nadu Generation and Distribution Corporation Ltd (TANGEDCO)
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO SEC - 1 SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016
- 4 -
with the stipulation that the aforementioned companies shall be
fully owned by Government.
1.3 EXECUTIVE SUMMARY: M/s Tamil Nadu Generation and Distribution Corporation
Limited (TANGEDCO), has proposed to establish 5x800MW
Coal based Kadaladi Super Critical Thermal Power Project using
imported coal from Indonesia.
In Section-2 of the report, existing power situation of the
country and the state have been discussed to ascertain the
marketability of power from the proposed station.
In Section-3 of the report, the basic requirement for setting-up
a thermal power station namely – land, water, fuel, power
evacuation, transportation logistics and infra-structure are
discussed.
In Section-4 of this report, Salient features of the different sites
are furnished. The selected Project Site is located in Tharaikkudi,
Kannirajapuram and Narippaiyur villages of Kadaladi Taluk,
Ramanathapuram District. .
In Section-5 of the report, the technical features of the 800
MW set size outlining the design parameters of main plant and
equipment are discussed. A reheat steam cycle with
regenerative feed heating arrangement operating at supercritical
range has been proposed.
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO SEC - 1 SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016
- 5 -
The station envisages supply of imported coal from Indonesia or
by any other country and Indigenous coal from Talcher, Odisha
by ship upto Thoothukudi Port and then by rail to the site. Plant
water supply to the plant is planned from the Gulf of Mannar,
the coast line is at a distance of around 2.3 km on the Southern
side of the project site. Seawater would be directly used for
condenser cooling and the fresh/sweet water requirements
would be met by installation of a RO desalination plant.
Re-circulating cooling water system with natural Draft cooling
towers is envisaged for the station. The fly ash generated is
proposed to be handled pneumatically in dry mode up to fly ash
silos and transported through truck for utilization by end users
and in case of exigency ash from the fly ash silos will be
conveyed to ash pond in slurry form. Salient technical features
of auxiliary systems are furnished in Section-5 of this report.
The electric generators would be 3-phase, 50 Hz, hydrogen-
cooled, 3000 rpm machine with static or brushless excitation
system and would Generator voltage will be in the range of 27
kV or as per manufacturer’s standard at 0.85 power factor
(lagging). The electrical system proposed would be equipped
with adequately sized equipment and with generous redundancy
to ensure uninterrupted operation. In Section-5 of the report,
the electrical equipment and systems are discussed.
The proposed station envisages the state-of-the-art Digital
Distributed Control & Monitoring Information System (DDCMIS),
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO SEC - 1 SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016
- 6 -
which will integrate various closed loop sub-systems, open loop
sub-systems, monitoring and information sub-system covering
the entire plant. The system will also integrate the various
proprietary control packages supplied by the main equipment
vendors for harmonious plant operation. In Section-5 of the
report, instrumentation & control philosophy of the proposed
station is dealt in adequate details.
The Plant layout for the proposed station has been developed
keeping in view optimum use of land available within the
identified land limit, direction of supplies of input, direction of
road access, operational ease and initial investment
requirement. Details of basic plant features and the relevant
layout within the identified plot are furnished in Section-5 of
this report.
To minimise emission of Suspended Particulate Matter (SPM)
along with boiler flue gases Electrostatic Precipitators of
adequate size and fields will be provided at the exit of boiler to
bring down SPM emission level to less than 30 mg/Nm3. Total 3
(Three) stacks with stack height of 275 m (Two twin flue for four
boilers and one single flue high stack for one boiler) is
envisaged for the proposed units. Liquid effluents from the plant
will be properly treated before re-use and/or disposal. A detailed
scheme for the proposed unit has been provided in Section-5.
General discussion on the entire environmental aspects has
been provided in Section-6.
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO SEC - 1 SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016
- 7 -
Implementation of the project is envisaged to be through EPC
contract mode of tendering. Therefore, engineering of facilities
and basic infrastructure at project site are to be arranged in
advance for smooth implementation of the project. The
manpower requirement during construction stage has been
estimated and this may undergo revision as per project
authority and selected contractor’s manpower deployment.
Details of the construction facilities are discussed in Section-7.
In Section-8 of the report, O&M staff requirement for operating
and maintaining the plant is narrated. The manpower
requirement for O&M is around 2880 persons. The Man per MW
ratio works out to 0.72 (as per the Working Group on Power 12th
Plan Manpower projection for XIII plan). This may undergo
revision as per project authority. The training requirements of
O&M personnel are also discussed under this section.
The commercial operation (COD) for different units of the
project from the date of Letter of Award to project Proponent
(zero date) shall be as below.
� Commercial operation of Unit # 1 : 42 months
� Commercial operation of Unit #2 : 45 months
� Commercial operation of Unit #3 : 48 months
� Commercial operation of Unit #4 : 51 months
� Commercial operation of Unit #5 : 54 months
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO SEC - 1 SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016
- 8 -
The Project Execution, Monitoring and Control, Project Schedule
have been discussed under Section-8 of the report.
Based on available quotes and in-house data for various
equipments, the project cost estimate of 5x800MW has been
worked out. The total capital outlay will be of Rs.30,827.65
Crores (Including interest during construction working capital,
working capital margin and other financial charges). The details
are furnished in Section-9 of the report.
1.4 PROJECT AT A GLANCE:
GENERAL:
Project Authority : Tamil Nadu Generation and Distribution Corporation Limited (TANGEDCO). A Government of Tamil Nadu Undertaking.
Project : Imported coal based 5x800MW Kadaladi Super Critical Thermal Power Project.
Selected Location : The selected site is located in Tharaikkudi, Kannirajapuram and Narippaiyur villages of Kadaladi Taluk, Ramanathapuram District in Tamil Nadu State. The coordinates of the selected site is as below
Node Latitude LongitudeB1 908’33.5” N 78022’33.1” E B2 909’15.2” N 78024’5.5” E B3 907’39.4” N 78024’16.9” E B4 906’52.6” N 78022’46.6” E
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO SEC - 1 SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016
- 9 -
Nearest Major Town/City : Ramanathapuram, which is around 65 kms from the proposed site and Thoothukudi city which is at a distance of 55 Kms.
Seismic Zone : Zone II as defined in - IS: 1893 –2002
Access by Road : The site is located on the North side of East Coast Road (ECR) connecting Ramanathapuram and Vembar.
Access by Rail : Ramanathapuram Railway Station, at 65 Kms and Thoothukudi Railway Station at 55 Kms from site
Access by Sea : Thoothukudi Port - 75 km from site.
Access by Air : Domestic airport at Thoothukudi (55 kms approx.)/International airport at Madurai (120kms approx.).
PRELIMINARY PROJECT PARTICULARS:
Main Fuel : Imported Coal with GCV 5642 kcal/kg is proposed to be imported from Indonesia or any other country and Indigenous coal with GCV 2800 kcal/kg from Talcher, Odisha.
Coal Requirement: Best Coal - 11.47 MTPA (Million
tons per annum) at 85% PLF (100% imported coal) 36974 metric T/day, 7394 TPD per unit
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO SEC - 1 SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016
- 10 -
Design Coal - 13.65 MTPA at 85% PLF (70% imported: 30% indigenous) 44000 metric T/day, 8798 TPD per unit
Worst Coal – 15.59 MTPA at 85% PLF (50:50) 50240 metric T/day, 10048 TPD per unit
Fuel Transportation :Imported coal will be transported from the overseas supplier Indonesia or any other country and Indigenous coal from Talcher, Odisha to Thoothukudi Port by ship. For Coal connectivity a combination of existing Rail network, proposed new B.G line project and private railway line to the power plant is proposed. The coal from Thoothukudi port will be transported to site by one of the following rail route.
i) Coal will be transported by the existing railway line from Thoothukudi Port to Milavittan, then through the proposed B.G railway line (Kanyakumari to Karaikudi via Ramanathapuram) which aligns along the southern side of the proposed site and then by private railway line take-off from a location nearer to the Power Plant.
Orii) Coal will be transported by
the existing railway line from Thoothukudi Port to Milavittan, then through the
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO SEC - 1 SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016
- 11 -
proposed new alignment of B.G railway line (Thoothukudi to Madurai via Melamarudur)to Melamarudur. From Melaamarudur to the power plant private railway line is proposed.
: Oil will be transported by road tankers.
Water : The estimated seawater requirement for the proposed Thermal Power Plant is 39,193m3/hr (41,150 m3/hr with 5% margin).
Consumptive water would be
drawn from the Sea and treated in Desalination plant at site. The sea coastline is at an aerial distance of around 2.3 km on the southern side of the proposed plant.
Land : About 1642 acres of land will be required for setting the power station including ash pond, coal stock pile etc. About 522 acres of land is considered for Bottom ash slurry disposal and fly ash slurry disposal. The ash dyke area is considered for the following % disposal of fly ash in slurry form
1st year 100% fly ash 2nd year 75% fly ash 3rd year 50% fly ash 4th year 25% Fly ash 5th Year 0% fly ash About 670 Acres of land is
considered for plant area, lay down area, storage area etc.
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO SEC - 1 SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016
- 12 -
About 300 acres of land area will be required for Green belt and 150 acres land will be required for Township (to be indentified outside plant boundry).
Site Elevation : +6 m above Mean Sea Level (MSL).
TECHNICAL FEATURES OF 5X800 MW UNITS:
Power Generating Unit : Five units of 800 MW turbine generator sets fed by steam from coal fired Pulverised Fuel boilers operating at supercritical range.
Minimum Steam Condition : 255 bar (a) / 565 �C At Steam Turbine Inlet
Cooling System : Recirculating type cooling water system with wet type Natural Draft Cooling Towers using sea water as cooling medium.
Coal Handling System : Imported coal and Indigenous coal will be transported by Railway through BOBRN type wagons to site from Thoothukudi port. Coal storage (considering worst coal) for 30 days approx. and coal mill bunkers storage for 14 hours is proposed.
Ash Disposal System : Dry collection and disposal of Fly Ash, Dry extraction of bottom ash is considered. Ash will be primarily disposed by truck to end users as far as possible. Besides provision will be made to transport fly ash
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO SEC - 1 SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016
- 13 -
(only during emergency) and Bottom ash through pipe line to the ash dump area (located nearby within the Plant boundary).
Power Evacuation : Power generated in the Power Plant would be available at 765 kV level in the station switchyard bus.
Power from this switchyard would be evacuated through two (2) 765kV double circuit lines to the nearest 765 kV pooling station, location to be decided by TANTRANSCO the local STU.
Power Off-take : Through TANTRANSCO.
Environmental Aspects : 3Nos. (Three) stacks with stack height of 275 m (Two twin flue stack and one single flue stack) is proposed for the 5x800MW units to meet the MOEF standard required for dispersion of particulate, SOX and NOX.
Provision of FGD & SCR is
proposed for this project to reduce the SOx & NOx levels (100 mg/Nm3) within the prescribed norms as specified in the latest MOEF notification.
: ESP Multiple field electrostatic precipitators with separation efficiency of around 99.9% is envisaged for steam generator. The limit for emission of particulate matters is 30 mg/Nm3
: The reject water (brines) from R.O desalination plant will be diluted to specified limits and the cooling
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO SEC - 1 SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016
- 14 -
water blow down temperature will be brought down to specified limit. And then RO Reject along with blow down from cooling tower will be pumped back to sea as per Tamil Nadu Pollution Control Board (TNPCB) standards and the Ministry of Environment & Forest's (MOEF) notification. The other effluents from the plant area will be treated in ETP plant and Waste water generated from ETP will be treated and utilized for horticulture development and excess treated water is sent to ETP RO plant to achieve zero waste water discharged as per MOEF notification.
Manpower Requirement : 2880 personnel during plant operation for O&M. The Man per MW ratio works out to 0.72 (as per the Working Group on Power 12th
Plan Manpower projection for XIII plan)
OTHER FACILITIES:
Township : Residential Quarters for employees employed in critical services will be provided.
Mode of Implementation : The project will be executed on Engineering, Procurement & Construction (EPC) basis in one or multiple packages.
Project Time Frame : First unit of 800MW capacity Unit would be put into commercial operation in about 42 months from the date of Letter of Award to project Proponent and
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO SEC - 1 SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016
- 15 -
subsequently the other units would be brought into commercial operation in 3 months interval for each unit
. COD Unit #1 :42 months COD Unit #2 :45 months COD Unit #3 :48 months COD Unit #4 :51 months COD Unit #5 :54 months
PROJECT COST & COST OF GENERATION:
Project Cost : Present day cost including Interest During Construction (IDC), financial charges and Working Capital Margin money is Rs.30,827.65 Crores.
Corporate social responsibility (CSR) : The value considered for the CSR
activities is not less than 0.4 % of the project cost.
Cost of Energy @ 85% PLF & 85% PAF is as below:-
� 1st year of full generation : Rs.3.42perkWh. (all 5 units are in operation)
� 25 years levelised tariff : Rs.5.70per kWh.
�
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO SEC - 2 SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016
- 16 -
NEED FOR THE PROJECT
2.1 POWER SCENARIO: INTRODUCTION: Electricity is the prime mover of growth and is vital to the
sustenance of a modern economy. The projected growth of the
Indian Economy depends heavily on the performance and growth
of the power sector. The contribution of power sector in country’s
growth has grown significantly since independence. Total
installed generation capacity of the country, which was 1362 MW
at the time of independence, has increased to about 288005 MW
as on 31st January, 2016. It is the endeavor of the government
to ensure uninterrupted supply of electricity at affordable rates to
the following categories of consumers to sustain steady economic
growth:-
a. Domesticb. Commercial c. Public Lighting d. Public Water Works e. Irrigation f. Industrial (LT, HT less than 1 MW, HT 1 MW and above) g. Railway Traction h. Bulk Non-Industrial HT supply
Electricity is an essential requirement for all facets of our life. It
is the critical infrastructure on which the socio-economic
development of the country depends. Availability of reliable and
quality power at competitive rates to industry would make it
globally competitive and enable it to exploit the tremendous
potential of employment generation.
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO SEC - 2 SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016
- 17 -
2.2 POWER SCENARIO IN INDIA
The power industry in India is historically being characterized by
energy shortages i.e. demand for electricity far exceeding the
supply. Due to inadequate generation supply and distribution
infrastructure, the per capita consumption of energy in India is
extremely low in comparison to most of the developing and
developed nations. However, as per CEA record, the per capita
consumption of electricity in India in the year 2012-13 stands as
918 kWh (SOURCE: Report on Power Scenario by CEA – SEP-
2014). Over the years, the electricity Industry has made
significant progress. The Present power scenario of India is
shown in the following tables
TABLE - 2.1 ALL INDIA INSTALLED CAPACITY (as on 31.01.2016)
(FIGURES IN MW)
Sect
or
Thermal
Nuc
lear
HYD
RO
R.E
.S
(MN
RE)
Tota
l
Coa
l
Gas
Die
sel
Tota
l
STATE �60550.50�
�6975.30� �438.57� �67964.37�
�0.00� �28052�
�1934.22� �97950.59�
PRIVATE �64707.38�
�9978.00� �554.96� �75240.34�
�0.00� �3120.00�
�36887.29�
�115247.63�
CENTRAL �49980.00�
�7555.33� �0.00� �57535.33� �5780 �11491.42� �0.00� �74806.75�
TOTAL 175237.88 24508.63 993.53 200740 5780 42663.42 38821.51 288004.97
% 60.8 8.5 0.3 69.7 2.0 14.8 13.5 100.00
SOURCE: CEA
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO SEC - 2 SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016
- 18 -
TABLE - 2.2
ACTUAL POWER SUPPLY POSITION Pe
riod
Peak
Dem
and
(MW
)
Peak
Met
(MW
)
Peak
Def
icit
/ Sur
plus
(M
W)
Peak
Def
icit
/ Sur
plus
(%
)
Ener
gy R
equi
rem
ent
(MU
) Mill
ion
Uni
ts
Ener
gy A
vaila
bilit
y (M
U)
Ener
gy D
efic
it /
Surp
lus
(MU
)
Ener
gy D
efic
it /
Surp
lus
(%)
9TH PLAN END 78441 69189 -9252 -11.8 522537 483350 -39187 -7.5
10TH PLAN END 100715 86818 -13897 -13.8 690587 624495 -66092 -9.6
11TH PLAN END 130,006 116,191 -
13,815 -10.6 937,199 857,886 -79,313 -8.5
2012-13 135,453 123,294 -12,159 -9.0 998,114 911,209 -86,905 -8.7
2013-14 135,918 129,815 -6,103 -4.5 1,002,257 959,829 -42,428 -4.2
2014-15 148,166 141,160 -7,006 -4.7 1,068,923 1,030,785 -38,138 -3.6
SOURCE: CEA
It may be noted from the Table 2.2 there is always energy deficit
for all the plan period. The energy deficit in India is mainly
caused by slow progress in the capacity addition which in turn is
attributable to difficulty in land acquisition, shortage of coal, lack
of fund allocation and the clearances involved. The Indian
economy is directed by the successive five year plans that set out
targets for economic development in various sectors, including
power sector. During implementation of the last three (3) Five
Year Plans (the 9th, 10th and 11th Plans), 48%, 52% & 70% of the
targeted additional energy capacity could only be attained.
Capacity addition to the tune of approximately 20,000 MW,
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO SEC - 2 SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016
- 19 -
21,000 MW & 55000 MW was achieved in 9th,10th & 11th Plan
periods. (Source: CEA POWER SCENARIO STATUS NOTE- SEP
2014).
The projection at the end of 13th plan on Indian Power Scenario
is furnished in the following table.
TABLE – 2.3
PROJECTION FOR THE END OF 13TH PLAN
REGION
ENERGY REQUIREMENT
(MU) Million Units
PEAK DEMAND (Mw)
Y e a r Y e a r2021-22 2021-22
Northern 576010 82784 Western 535851 83268Southern 506589 78857 Eastern 231646 33747N-Eastern 22421 3905 Andaman & Nicobar
505 89
Lakshadeep 60 16 All-India 1872517 271795
Source : 18th EPS.
The proposed project of 5x800 MW coal based power station at
Kadaladi taluk, in Ramanathapuram District, Tamil Nadu fits well
in the overall power scenario of the country and plant operation
at high plant load factor can be expected.
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO SEC - 2 SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016
- 20 -
2.3 POWER SCENARIO IN SOUTHERN REGION: For the purpose of power planning and operation of regional grid
the Southern Region consists of the following
states/UT/Command area:
� Andhra Pradesh
� Telangana
� Karnataka
� Kerala
� Tamil Nadu
� Puducherry
All three sectors namely Central, State & Private contribute to
the power generation capability in the region. Power Grid
Corporation of India Limited (PGCIL), the central sector
constructs, operates and maintains transmission and
transformation facilities for inter-state and inter-region transfer
of power. The power generating capability in the region is
predominantly thermal.
The total installed capacity in Southern region as on 31.01.2016
is 71264.85 MW as in indicated in Table 2.4. Energy deficit to
the tune of (-) 35,269 MU (Million Units) and peak demand
deficit of (-) 8619 MW had been anticipated during the period of
2015-2016 in Southern Region refer Table 2.5.
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO SEC - 2 SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016
- 21 -
TABLE - 2.4
SOUTHERN REGION INSTALLED CAPACITY (as on 31.01.2016) (FIGURES IN MW)
Sect
or
Thermal
Nuc
lear
HYD
RO
R.E
.S
(MN
RE)
Tota
l
Coa
l
Gas
Die
sel
Tota
l
STATE �14782.50� �556.58� �362.52� �15701.60�
�0.00� �11518.03� �488.37� �27708.00�
PRIVATE �7150.00�
�5557.50� �554.96� �13262.46�
�0.00� �0.00�
�15724.81� �28987.27�
CENTRAL �11890.00� �359.58� �0.00� �12249.58� �2320 �0.00� �0.00� �14569.58�
TOTAL 33822.5 6473.66 917.48 41213.64 2320 11518.03 16213.18 71264.85
% 47.5 9.1 1.3 57.8 3.3 16.2 22.8 100
SOURCE: CEA
TABLE - 2.5
SOUTHERN REGION ANTICIPATED POWER SUPPLY POSITION DURING 2015-16 AS PER LGBR
Peak
Dem
and
(MW
)
Peak
Ava
ilabl
e (M
W)
Peak
Def
icit
/ Su
rplu
s (M
W)
Peak
Def
icit
/ Su
rplu
s (%
)
Ener
gy
Req
uire
men
t (M
U)
Ener
gy
Ava
ilabi
lity
(MU
)
Ener
gy D
efic
it / S
urpl
us
(MU
)
Ener
gy D
efic
it / s
urpl
us (%
)
43,630 35,011 -8,619 -19.8 313,248 277,979 -35,269 -11.3
SOURCE: LGBR report 2015-16
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO SEC - 2 SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016
- 22 -
TABLE - 2.6
ACTUAL POWER SUPPLY POSITION
Peri
od
Peak
Dem
and
(MW
)
Peak
Met
(MW
)
Peak
Def
icit
/ Su
rplu
s (M
W)
Peak
Def
icit
/ Su
rplu
s (%
)
Ener
gy
Req
uire
men
t (M
U)
Ener
gy
Ava
ilabi
lity
(MU
)
Ener
gy D
efic
it /
Surp
lus
(MU
)
Ener
gy D
efic
it /
Surp
lus
(%)
9TH PLAN END
22757 19201 -3556 -15.6 140516 128095 -12421 -8.8
10TH PLAN END
26176 24350 -1826 -7.0 180091 175197 -4894 -2.7
11TH PLAN END
37,599 32,188 -5,411 -14.4 260,302 237,480 -22,822 -8.8
2012-13 38,767 31,586 -7,181 -18.5 281,842 238,058 -43,784 -15.5
2013-14 39,015 36,048 -2,967 -7.6 277,245 258,444 -18,801 -6.8
2014-15 39,094 37,047 -2,047 -5.2 285,797 274,136 -11,661 -4.1 SOURCE: CEA
As per 18th EPS Committee Notes, electrical energy requirement
for Southern region would be 506,589 MU by the end of 13th
Plan period (Table 2.3). Average peak electrical load for
Southern region forecast is 78857 MW by the end 13th Plan. It is
to be noted that as per 18th EPS Committee survey report (Table
2.3) and the currently installed capacity of the southern region
as per Table 2.4, a rapid capacity addition through large scale
thermal power development program is required.
In this scenario, proposed power station of 4000 MW in Tamil
Nadu is assured of steady demand in the region. It is thus
possible to run the proposed station at high PLF
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO SEC - 2 SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016
- 23 -
2.4 POWER SCENARIO IN TAMIL NADU Being located on the South eastern coast of India the total
geographical area of Tamil Nadu covers 3.95% of the total
geographical area of India and houses 7.21 Crore population as
per latest Census. The Per capita consumption of electricity in
Tamilnadu during the year 2011-12 was 1276.57kWh (Source :
CEA POWER SCENARIO STATUS NOTE- SEP 2014). The following
tables show the present power scenario of Tamil Nadu.
TABLE - 2.7
TAMIL NADU INSTALLED CAPACITY (as on 31.01.2016) (FIGURES IN MW)
Sect
or
Thermal N
ucle
ar
HYD
RO
R.E
.S
(MN
RE)
Tota
l
Coa
l
Gas
Die
sel
Tota
l
STATE �4770.00� �524.08� �0.00� �5294.08�
�0.00� �2182.20� �122.70� �7598.98�
PRIVATE �2350.00� �503.10� �411.66� �3264.76�
�0.00� �0.00� �8741.47� �12006.23�
CENTRAL �4155.10� �0.00� �0.00� �4155.10� �986.5 �0.00� �0.00� �5141.60�
TOTAL 11275.1 1027.18 411.66 12713.94 986.5 2182.2 8864.17 24746.81
% 45.6 4.2 1.7 51.4 4.0 8.8 35.8 100
SOURCE: CEA
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO SEC - 2 SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016
- 24 -
TABLE - 2.8
TAMILNADU ANTICIPATED POWER SUPPLY POSITION DURING 2015-16 AS PER LGBR
SOURCE: LGBR report 2015-16
TABLE - 2.9 TAMILNADU ACTUAL POWER SUPPLY POSITION FROM IX PLAN
SOURCE: CEA
Peri
od
Peak
Dem
and
(MW
)
Peak
Ava
ilabl
e (M
W)
Peak
Def
icit
/ Su
rplu
s (M
W)
Peak
Def
icit
/ Su
rplu
s (%
)
Ener
gy
Req
uire
men
t (M
U)
Ener
gy
Ava
ilabi
lity
(MU
)
Ener
gy D
efic
it /
Surp
lus
(MU
)
Ener
gy D
efic
it /
Surp
lus
(%)
2015-16 14,489 13,710 -779 -5.4 102,653 98,123 -4,530 -4.4
Peri
od
Peak
Dem
and
(MW
)
Peak
Met
(MW
)
Peak
Def
icit
/ Sur
plus
(M
W)
Peak
Def
icit
/ Sur
plus
(%)
Ener
gy R
equi
rem
ent (
MU
)
Ener
gy A
vaila
bilit
y (M
U)
Ener
gy D
efic
it / S
urpl
us
(MU
)
Ener
gy D
efic
it / S
urpl
us
(%)
9TH PLAN END 7158 6218 -940 -13.1 46232 42951 -3281 -7.1
10TH PLAN END 8860 8624 -236 -2.7 61499 60445 -1054 -1.7
11TH PLAN END 12,813 10,566 -2,247 -17.5 85,685 76,705 -8,980 -10.5
2012-13 12,736 11,053 -1,683 -13.2 92,302 76,161 -16,141 -17.5
2013-14 13,522 12,492 -1,030 -7.6 93,508 87,980 -5,528 -5.9
2014-15 13,707 13,498 -209 -1.5 95,758 92,750 -3,008 -3.1
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO SEC - 2 SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016
- 25 -
TABLE - 2.10
TAMILNADU PEAK & ENERGY FORCAST
YEAR ENERGY DEMAND (MU) Million Units
PEAK DEMAND (MW)
2016-17 119251 20816 2017-18 129582 22375 2018-19 139949 24057 2019-20 151145 25876 2020-21 163327 27838 2021-22 171718 29975
SOURCE: 18th EPS As per 18th EPS Committee Notes, energy requirement for Tamil
Nadu at the end of 13th Plan period is estimated/forecast as
171718 MU. Peak electric load at the end 13th Plan is
estimated/forecast as 29975 MW. It is to be noted that as per
18th EPS Committee survey report Table 2.10 and the currently
installed capacity of the state as per the Table 2.7 a rapid
capacity addition through large scale thermal power
development program is required.
In view of shortage of power in the state and in order to bridge
the demand-availability gap of power, Tamil Nadu Generation
and Distribution Corporation Limited (TANGEDCO) is exploring
the possibility of establishing more thermal power projects. The
Government of Tamil Nadu in the budget speech for the year
2015-16 had announced that a 5x800MW Kadaladi Supercritical
Thermal Power Project will be established in Ramanathapuram
District.
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO SEC - 2 SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016
- 26 -
2.5 JUSTIFICATION OF THE PROJECT:
With the present and future mismatch between demand and
supply for Indian power scenario, any capacity addition will be
an welcome relief to attain the growth figures projected in
Electricity Power Survey (EPS) as well as to maintain a steady
growth in Gross Domestic Product (GDP).
The diesel or gas turbine plant plays a vital role in the power
industry as the response of these plants to the fluctuating power
is very high and they can be built anywhere. The use of these
plants in India for power generation is limited due to limited
sources of oil and gas in the country which are essential and
required for industrial and transport purposes.
The hydel power stations are subject to the vagaries of weather
and the availability of water and hence assured power supply
from the same cannot be guaranteed throughout the year.
Therefore, total reliance on hydel stations is not advisable.
The nuclear power plants needs stringent safety precautions and
need more sophisticated safeguards to protect the personnel
and environment.
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO SEC - 2 SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016
- 27 -
Wind contains tremendous amount of energy, it can be
harnessed to generate power on a large scale matching with
conventional sources. The total installed wind capacity in India is
23439.26 (31st March, 2015) of which Tamil Nadu with installed
capacity of 7456.98 MW accounts for 31.81 %.
India is ranked number one in terms of solar energy production
per watt installed. Total installed capacity as on 15th Jan, 2016
is 5,130 MW of which Tamil Nadu with installed capacity of 419
MW accounts for 8.16 %. Land is a scarce resource in India and
per capita land availability is low. Dedication of land area for
exclusive installation of solar arrays might have to compete with
other necessities that require land. The amount of land required
for utility-scale solar power plants currently approximately
1 km2 for every 20–60 megawatts (MW) generated could pose a
strain on India's available land resource.
Installation of wind power plant depends on availability of wind
with required wind speed. Very few locations satisfying above
criteria are identified in Tamil Nadu. Further wind based power
plants are operating at very low PLF of 25-30%, hence
dependence on wind based power plant as base load plant is not
feasible.
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO SEC - 2 SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016
- 28 -
In such a situation, it is prudent to implement base load power
plants using coal as fuel and thermal power generation as the
best preferred alternative. The actual growth in industrial,
agricultural and domestic demand will establish that there is an
appreciable shortfall in the installed capacity and energy
availability as on date.
Electricity consumption in Tamil Nadu is increasing at a rate
faster than over all energy supply. Considering the projected
demand at end of 13th year Plan as per 18th Electricity power
survey report Table 2.10 and the currently installed capacity of
the state a per the Table 2.7, a rapid capacity addition through
large scale thermal power development program is planned
during 13th year Plan (2017-2022).
Pulverized Fuel Firing combustion is the most common and well
proven among all the above technologies. PF fired boilers are
most suited for higher capacity power plants and have the
distinct advantage of better combustion efficiency with less
auxiliary consumption as compared to any other technology in
the market today.
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO SEC - 2 SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016
- 29 -
The choice of unit capacity for the coal fired station depends
largely upon considerations of efficiency and adherence to
environmental norms. Increase in steam parameters namely
pressure and temperature lead to increase in efficiency, which in
turn, reduces emission of greenhouse gases. Increase in steam
pressure beyond 221 bar leads to supercritical conditions in the
thermodynamic steam water cycle and results in sizeable
efficiency improvement. While supercritical steam parameters
have been more effective in capacity range of 600 MW and
above. Any unit size from 660 MW to 800 MW of gross capacity
at generator terminal having supercritical technology for the
proposed plant can be considered. However, keeping in view the
higher efficiency, improve heat rate, low per MW cost, Lower
emission of CO2, SOx & SPM and in current scenario unit
capacity of 800MW Supercritical technology is being widely
adopted throughout India and henceforth the selection of
800MW unit capacity is justified for this proposed project.
This shortfall will continue even after the commissioning of the
proposed power plants in various parts of the state and in the
southern regions. As Tamil Nadu state is the most preferred
state for industrialization, the industrial demand for power will
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO SEC - 2 SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016
- 30 -
be ever increasing. Adding to the industrial demand the
agriculture need as well as domestic consumption coupled with
the improved standard of living of the population will be on the
rise. The location being close to the sea, cooling water is
perennially available in the site for the power plant. Imported
coal is being considered as the main fuel for the proposed power
plant. Further the grid is large enough to accommodate this
proposed 5x800MW coal fired power plant.
Besides Kadaladi Taluk in Ramanathapuram District is a very
backward area and prone to communal disturbances, a power
plant of this 5X800 MW capacity will bring in lot of employment
opportunities both direct and indirect and will pave away for
communal harmony in this area. Taking all these into
consideration, establishment of the proposed power project of
5x800 MW is justified in all aspects.
�
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO SEC - 3
SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016 -31-
BASIC REQUIREMENTS 3.1 INTRODUCTION: The basic requirements for setting up and operating a 5x800MW
coal based thermal power station are -
� Availability of adequate land suitable for setting up the station
� Availability of adequate quantity of water throughout the year
� Guaranteed supply of fuel with effective transportation system to ensure optimum cost of fuel at the plant
� Power evacuation possibility to the identified sub-station(s) of the grid at appropriate voltage level(s).
� Accessibility to the site for start of construction, availability of construction water and power, availability of construction manpower, road connection to airport, seaport, etc.
� Connectivity to population centres with social and civic amenities
This section discusses the requirements vis-à-vis the availability
above basic elements of setting up the proposed power station.
TANGEDCO had identified few potential sites and the proposed
site has been considered for setting up of the Project after
review and consideration of above stated aspects.
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO SEC - 3
SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016 -32-
3.2 LAND - REQUIREMENT & AVAILABILITY: The land requirement for a coal based thermal power project
can broadly be classified under the following five major heads: -
a. Main Plant Area
b. Area required for Roads, Railway siding, Coal stack yard,
pipe corridors, cooling tower, switch yard, Administrative
Building, etc.
c. Ash Disposal Area
d. Other land area requirements for infrastructure facilities
such as land for sea water intake & outfall piping corridor,
power evacuation corridor, environmental requirements, lay
down area etc.
e. Green belt
Depending on the site features, land configuration and related
technical requirements, the tentative break-up of land
requirements for a typical 5x800MW imported coal fired power
plant with provisions of development of relevant infrastructure
and support facilities, may be considered as follows:-
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO SEC - 3
SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016 -33-
LAND REQUIREMENT AREA IN ACRES MAIN PLANT AREA BTG FOR FIVE (5) UNITS 56 ELECTRICAL AREA (TRANSFORMER YARD,SWITCHYARD & CONTROL ROOM) 102
COAL HANDLING PLANT INCLUDING MGR & FUEL OIL AREA 149
ASH HANDLING PLANT, FGD & MILL REJECT SYSTEM 71
PLANT WATER SYSTEM, WASTE WATER SYSTEM AND CW CORRIDOR 144
AUXILLARY BUILDINGS, PLANT FACILITIES AND ROADS 148
ASH POND AREA 522 GREEN BELT 300 TOWNSHIP 150 Total Land Requirement, Acres 1642
PLANT AREA: The above land requirement envisaged for the power plant
considers installation of 5x800 MW capacity imported coal based
thermal power station with relevant facilities. The estimated
space requirement considers a sea water storage, cooling
towers, coal receipt by rail route, coal storage and handling
facility, fuel oil system, 765 kV GIS switchyard, sea water
treatment facilities, desalination plant to meet consumptive
water requirement, Flue gas desulphurisation plant, green belt
to satisfy State PCB/MOEF norms, etc.
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO SEC - 3
SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016 -34-
ASH DISPOSAL AREA: About 4.05 MTPA of ash (considering Worst coal 50% imported:
50% indigenous & at 85% PLF) is likely to be generated in a
year from the proposed power station. An average ash dump
height of 15M is envisaged for estimation of land requirement
for ash dump yard/ash pond. Actual height will, however,
depend on ground condition of dump and its contour. The ash
disposal area is decided considering Bottom ash slurry disposal
for 25 years and fly ash disposal in slurry form in the 1st year-
100%, 2nd year-75%, 3rd year-50% and 4th year-25%. This area
includes the peripheral road and statutory green belt around the
disposal area. As per the Ministry of Environment & Forests
notification dated 3rd November, 2009, 100% fly ash utilisation
from the complex need to be ensured within initial four years of
operation. Thus the land requirement works out to about 522
Acres for fly ash disposal for initial years and 25 years for bottom
ash. It would consider disposal with a dump height of 15m.
OTHER AREA:
The site for the proposed power plant is planned on a plot of
land with no habitation. The site was identified on the basis of
following criteria:-
� Availability of adequate land for locating the power plant with minimum resettlement and rehabilitation issues.
� Land is predominantly flat. However, certain amount of
land filling and cutting would be necessary.
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO SEC - 3
SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016 -35-
� Assured availability of sea water from the Gulf of Mannar located within 2.3 km.
� The proposed site is on the Northern side of East Coast Road (ECR) connecting Ramanathapuram and Vembar. Imported coal will be transported from the overseas supplier (Indonesia or any other country) and indigenous coal from Odisha by sea to Thoothukudi Port and then by the rail Thoothukudi Port.
� Hence the Site is well connected by road/Sea/Rail fortransportation of fuel, construction material, equipment etc., will not be a problem.
� Power generated in the Power Plant would be available at 765 kV level in the station switchyard bus. Power from this switchyard would be evacuated through two (2) 765 kV double circuit lines to the nearest 765 kV pooling station, location to be decided by TANTRANSCO the local STU.
The vicinity map of the area identified is given in Drawing
No.15Z03-004-DWG-M-001. The site location map of area is
given in Drawing No.15Z03-004-DWG-M-002. It may be
seen that the land available is suitable for locating the proposed
power plant with all the auxiliaries and accessories. In the
subsequent section, details of the identified site are discussed in
adequate details. The estimated space requirement considers
closed circulating cooling water system with cooling towers, Rail
way line, Coal storage and handling facility, fuel oil system, 765
kV switchyard, desalination plant to meet consumptive water
requirement, Flue gas desulphurisation (FGD) plant, green belt
to satisfy TNPCB/MOEF norms, etc..
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO SEC - 3
SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016 -36-
Township: Residential accommodation with necessary civic amenities would
be provided for the O &M personnel of the proposed station in a
separate plot of land outside plant boundary to be located nearer
to the project area. The area would include civic amenities
required for such township located at a remote location. The plot
needs to be adequate for provision of green verge. Total area to
be identified outside plant boundary for township is 150 acres.
Water Corridor
Seawater would be directly used for condenser cooling and the
fresh water requirements would be met by installation of a
desalination plant. The sea coastal line is at aerial distance of
around 2.3 km on the Southern side of the proposed project. The
intake well along with intake pump house to be located offshore in
Gulf of Mannar. Two intake sea water pipes from the intake pump
house in off shore to the plant site is planned to cater to the water
requirement for the station and two outfall line. Considering the
submergence requirement for the pumps, Intake Pump House to
be located at a depth of about 5 m (tentative) will be suitable.
The Intake structure shall be suitably designed with necessary
Trash Racks and Stop Logs. This arrangement minimizes
occurrence of silt carry over to the Plant.The outfall to be located
around 1.5 km (approx.) into the sea away from the intake point.
Intake and Outfall pipelines are proposed to be laid over pile
supported RCC deck. A common RCC deck (15 m width) will be
provided for both intake and outfall pipes for about 4 km
(tentative) and separate RCC deck shall be laid beyond this point
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO SEC - 3
SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016 -37-
for outfall about 1.5 km (tentative). For laying water pipeline of
route length of about 2.3 km and the pipeline corridor of width
20 m from sea shore to plant boundary, the land shall be
identified. The tentative location is indicated in the Drawing
No.15Z03-004-DWG-M-003 (sheet 2 of 2). However, the location
of the intake and outfall is to be finalised based on the Marine
EIA/EMP study & the intake and outfall Modelling study.
3.3 Water Requirement: In a conventional fossil fuel-fired thermal power station, water is
used to meet the following consumptive requirements.
a. Cooling water for steam condenser to act as the heat sink for
the thermodynamic cycle. However, for power stations
employing semi-open recirculating cooling systems with
cooling towers, only a small percentage of total circulating
water flow is required as make-up. The cooling water system
in a large sized thermal power plant is the largest consumer
of water and its make-up requirement itself accounts for more
than 70% of the total consumptive water requirement of the
power station.
b. Cooling of electrical and mechanical auxiliary equipment, such
as, generators, transformers, large motors, compressors and
other heat exchangers shall be through closed circuit auxiliary
cooling system using demineralised water as the primary
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO SEC - 3
SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016 -38-
coolant and main circulating cooling water as the secondary
coolant.
c. Make-up water requirement for power cycle (boiler make-up).
d. Water for miscellaneous services such as:-
i) Fire fighting system
ii) General services viz. airconditioning, ventilation, service water, dust suppression, dust extraction, FGD etc.
iii) Potable water for plant and township.
Water required for the station would be drawn from Gulf of
mannar.
The estimated consumptive water requirement based on sea
water analysis shown in Annexure-3.1 for the 5x800 MW
capacity station is at 39193 m3/hr (7839 m3/hr per unit) (~385
cusecs). The break-up of the estimate is given in Annexure-
3.2. The estimates are based on adoption of cycle of
concentration (COC) in the circulating cooling water circuit as
1.3.
3.4 Fuel Requirement:
The proposed site is on the Northern side of East Coast Road
(ECR) connecting Ramanathapuram and Vembar. Imported coal
will be transported from the overseas supplier (Indonesia or any
other country) or indigenous coal from Odisha will be
transported to Thoothukudi Port by ship.
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO SEC - 3
SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016 -39-
For Coal connectivity a combination of existing Rail network,
proposed new B.G line project and private railway line to the
power plant is proposed.The coal from Thoothukudi port will be
transported to site by one of the following rail route.
i. OPTION I - Utilizing the proposed new alignment of B.G railway line from Kanyakumari to Karaikudi via Ramanathapuram. (Status of the new alignment - decision is awaited from Railway Board) Coal will be transported by the existing railway line from Thoothukudi Port to Milavittan, then through the proposed B.G railway line which aligns along the southern side of the proposed site and then by private railway line take-off from a location nearer to the Power Plant.
Or
ii. OPTION II - Utilizing the proposed new alignment of B.G railway line from Thoothukudi to Madurai via Melamarudur. (Status of the new alignment - sanctioned by Railway Board) Coal will be transported by the existing railway line from Thoothukudi Port to Milavittan, then through the proposed new alignment of B.G railway line to Melamarudur. From Melamarudur to the power plant private railway line is proposed.
The coal analysis for imported coal & Indigenous Coal is given in
Annexure-3.3.
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO SEC - 3
SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016 -40-
On the basis of Best coal (Imported Coal 100%) the estimated
coal requirement would be as below :
On the basis of Design coal (Imported Coal 70% : Indigenous
coal 30%) the estimated coal requirement would be as below:
On the basis of Worst coal (Imported Coal 50% : Indigenous coal
50%) the estimated coal requirement would be as below:
Fuel Particulars 5 x 800 MW Per unit
TG Heat Rate 1850 kCal/kWh - Boiler Efficiency 89% - Station Heat Rate @ MCR with margin 2173 kCal/kWh - Hourly coal requirement at MCR 1541TPH 308 TPH Daily coal requirement @ MCR 36974TPD 7394 TPD Annual Coal requirement @ 85% PLF 11.47 MTPA 2.3 MTPA
Fuel Particulars 5 x 800 MW Per unit
TG Heat Rate 1850 kCal/kWh - Boiler Efficiency 88.1% - Station Heat Rate @ MCR with margin 2195 kCal/kWh - Hourly coal requirement at MCR 1833 TPH 367 TPH Daily coal requirement @ MCR 44000 TPD 8798 TPD Annual Coal requirement @ 85% PLF 13.65 MTPA 2.73 MTPA
Fuel Particulars 5 x 800 MW Per unit TG Heat Rate 1850 kCal/kWh - Boiler Efficiency 87.5% - Station Heat Rate @ MCR with margin 2209 kCal/kWh - Hourly coal requirement at MCR 2093 TPH 419 TPH Daily coal requirement @ MCR 50240 TPD 10048 TPD Annual Coal requirement @ 85% PLF 15.59 MTPA 3.11 MTPA
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO SEC - 3
SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016 -41-
Total traffic for coal (Worst Coal) would be between 14-17
rakes/day as per Table given below. A coal stock for about Thirty
(30) days requirement is considered. Imported coal and
Indigenous coal will be transported by Rail through BOBRN type
wagons.
Description Details BOBRNPermissible Carrying Capacity tonnes 62 Cubic capacity of Wagon Cu.m 57.2 Wagons per rake wagons 59 Net tonnes per rake tonnes 3658 Quantity in tonnes per annum (Worst coal 100% PLF)
million Tonnes
18.4
Rakes per year rakes 5030 Rakes per day, on an average rakes 14 Additional 25% rakes 17
Auxiliary fuel for boiler start-up and flame stabilization of the
units will be LDO/HSD and HFO. For the purpose of this report a
specific auxiliary fuel consumption of 1 ml/kWh is considered.
The actual consumption will, however, depend on average daily
plant load factor, grid stability, quality of coal etc. High plant load
factor can be ensured for the proposed power station and thus,
fuel oil consumption can be largely optimized. Fuel oil is planned
to be transported to the power plant by road and stored in tanks.
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO SEC - 3
SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016 -42-
3.5 Power Evacuation: Power generated by the power station shall be stepped up to
765 kV level through three single phase 315 MVA Generator
Step-up Transformers (GT) for each unit. Power generated in the
generator at terminal voltage of 27KV (depend on generator
manufacturer) would be stepped up to 765 kV level by
Generator transformer and shall be available in the station
switchyard bus. Power from the switchyard would be evacuated
through two (2) 765 kV double circuit lines to the nearest
765 kV pooling station, location to be decided by TANTRANSCO
the local STU.
3.6 Other Infrastructural Requirements:
For a grass root station, availability of infrastructural facilities is
essential for successful implementation of the project in a
compact time frame. The facilities which are considered
essential during early stage of construction are:
a. Access roads
b. Railway siding.
c. Housing facility for the construction staff with supply of
water and electricity, community facilities viz. market,
housing, school, water works, construction power, health
care etc.
d. Construction material & critical construction equipments
e. Skilled and unskilled manpower
f. Telecommunication facility.
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO SEC - 3
SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016 -43-
Among the above infrastructural facilities, a two-lane access
road of heavy duty class emanating from the ECR connecting
Ramanathapuram and Vembar is available. Nearest city,
Thoothukudi is having infra-structural facilities useful for the
proposed power project which is 55 Km from the proposed site.
The nearest Domestic airport at Thoothukudi (55 km approx.)
/International airport at Madurai (120kms approx.). Long body
trailers can be employed for haulage of heavy equipments from
port to the plant site. During construction heavy material has to
be transported by rail and some by road.
It is envisaged that about 10 MVA construction power may be
required at 415V level when construction activities takes place
simultaneously in all units and station areas of the plant.
TANGEDCO shall provide two single circuit 33 kV overhead lines
from KADALADI 110KV/33KV SS up to construction site for
construction power requirement.
At construction site suitable 33/11KV substation with 11KV/415V
distribution network with transformers and Distribution board
shall be provided to cater the construction power requirement at
different locations.
Further the Project Proponent shall be instructed to arrange
their own emergency DG sets to continue the construction
activity during grid failure.
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO SEC - 3
SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016 -44-
To accommodate personnel of owner, Project Proponent etc.
during construction of the project, it is envisaged that some
housing facilities such as guest house, bachelor's hostel,
residential quarters etc. may have to be developed along with
some basic civic amenities.
�
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO SEC - 4
SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016 - 45 -
SITE FEATURES
4.1 Introduction:
To ensure efficient and trouble free operation of a thermal
power plant throughout the operating life, selection of a proper
site with required features, infrastructure and inputs, is always
the key factor to optimize on design and cost parameters
involved. Integration of the technological equipment and
systems with the specific features of the project location is
viewed as an important aspect for the site under consideration.
A selected site may not always provide the ideal conditions.
Engineering solutions are usually possible which can still ensure
well designed and operable plants, provided the selected site
meets the basic requirements. Again fulfillment of statutory
requirements in terms of geographical features, MOE&F norms
and priority in land use are the basic criteria for selecting site for
thermal power station using fossil fuels. TAMIL NADU
GENERATION AND DISTRIBUTION CORPORATION
LIMITED (TANGEDCO) has carried out an extensive study to
identify suitable locations for setting-up the proposed Thermal
Power Plant. TANGEDCO had identified few potential sites in
Kadaladi taluk along the Gulf of Mannar for setting up the
Project. Land in Kondunallampatti, Tharaikkudi,
Kannirajapuram, Narippaiyur, Valinokkam and Siraikkulam
villages of Kadaladi Taluk, Ramanathapuram District were
identified.
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO SEC - 4
SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016 - 46 -
4.2 Justification & Discussion on Selected Site
The three potential site details are as given below: The
appropriate site is selected based on economic consideration
and having minimum impacts on ecology & environment
Comparative Details of Sites considered for the proposed project:
SL.
No.PARAMETERS SITE-A SITE-B SITE-C
1 Land Available (Hectares)
803.86.5 902.36 829.93
2 No. of Villages 1 3 2 Name of village Kondunallam
pattiTharaikkudi, Kannirajapuram, Narippaiyur
Valinokkam, Siraikkulam
3Orientation of the land
Marginally irregular boundary
Compact in nature
Irregular boundary
4
Land type Agricultural land
Barren land with scrubs and Palm trees
Barren land with scattered scrubs and marginal agricultural land
5
Suitability of Land
Suitable, leveled area
Suitable, fairly levelled with minimum undulation
Suitable, fairly levelled with minimum undulation
6Distance (aerial) from Sea coast line
8 km 2.3 km 0.7 km
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO SEC - 4
SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016 - 47 -
SL.
No.PARAMETERS SITE-A SITE-B SITE-C
7
Distance (aerial) from 500m HTL
7.5km 1.8 km Project Southernboundaryoverlaps
8
Intake/outfallcorridor over land
To be routed along the site B with overall approx length of 10 km
Approxroute length of 2.3 km
Approxroute length of 1 km
9
Location with respect to District Boundary
Lined along Thoothukudidistrict boundary.
Around 2 km from the Thoothukudi district boundary
Center of Ramanatha-puramdistrict.
10 R&R issue Thinly populated No habitation
Thinly populated
11Coal Transport Thoothukudi port
then by rail Thoothukudi port then by rail
Thoothukudiport then by rail
Infrastructural facilities
12
Road access 2.5 km from Sevalpatti-Tharakudi district road
1km from ECR
2km from ECR
13
Airport access Nearest airport Domestic/International Thoothukudi 70 km / Madurai 100 km
Nearest airport Domestic/InternationalThoothukudi 55 km/ Madurai 120 km
Nearest airport Domestic/International Thoothukudi110 km / Madurai 121 km
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO SEC - 4
SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016 - 48 -
SL.
No.PARAMETERS SITE-A SITE-B SITE-C
14
Railway access Thoothukudi -49km Ramanathapuram-80km
Thoothukudi-55kmRamanathapuram-65km
Thoothukudi -85kmRamanathapuram-41km
15Port access Nearest port
Thoothukudi 66 km
Nearest port Thoothukudi 75 km
Nearest port Thoothukudi 105 km
16Ecological sensitivelocations
GOMBR (Gulf of Mannar Biosphere Reserve)
Part of site falls in the buffer area
Site is within the buffer area
Site is within the buffer area
GOMNP (Gulf of Mannar National Park) Core area
Site is 21 km from Kariashuli Tivu and 19 km from Uppu Tanni Tivu
Site is 23 km from Kariashuli Tivu and 11 km from Uppu Tanni Tivu
Site is 12km from Nalla Tanni Tivu and 5.5 km from Anaipar Tivu
Melselvanoor – Keelselvanoorbird sanctuary
Aerial Distance of 24 km
Aerial Distance of 17 km
Aerial Distance of 12 km
Chitrangudi bird sanctuary
Aerial Distance of 24 km
Aerial Distance of 20 km
Aerial Distance of 21 km
KanjirankulamBird sanctuary
Aerial Distance of 26 km
Aerial Distance of 22 km
Aerial Distance of 22 km
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO SEC - 4
SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016 - 49 -
Site-A:
Located in Kondunallampatti, the site is about 80 km from
Ramanathapuram. Within the vicinity of 10 km range the above
listed sanctuary and national park are not located. However, part
of site falls within the buffer area of GOMBR. This site was not
considered further for:
a) The intake corridor over land to be taken along site-B and the
distance works out to around 10km.
b) The site has maximum agricultural land.
c) The site has few habitats which are likely to cause R&R issues.
Site-C: Located in Valinokkam and Siraikkulam about 40 km from
Ramanathapuram. This site was not considered for:
a) The project site and the intake will be around 5.5 km from the
Anaipar Tivu.
b) The Intake/outfall location with respect to the site location will
be in close proximity with the GOMNP.
c) The project site southern part overlaps with 500m HTL.
d) The site has some agricultural land and habitat which may
cause R&R issues.
Site-B:
Located in Tharaikkudi, Kannirajapuram and Narippaiyur about
65 km from Ramanathapuram. The site falls within the buffer
area of GOMBR. Further assessment on environmental impacts
and the requisite management plans shall be pointed out in
EIA/EMP study.
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO SEC - 4
SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016 - 50 -
From the above mentioned three (3) sites, Site-B is selected due
to the following intrinsic merits:
a. Project area is spread over 3 villages and the orientation is compact in nature.
b. Non Agricultural land.
c. NO R&R issue as there is no habitation.
d. Land is mostly barren partly with patches of bushes and
partly with palm trees.
e. As the site identified is near sea shore, the requirements for
plant water system could be easily met out. However, it is
also reasonably away from the sea coast in compliance with
coastal Zone Regulations.
f. The site is near the proposed alignment of B.G. Railway line
from Kanyakumari to Karaikudi and hence it will facilitate
transport of coal from Thoothukudi port to site.
g. The site is 1KM away from the existing East coast road
h. Closeness to the sea (i.e) about 2.3Km
The vicinity map and site location map of the area identified for
putting up the station are shown in Drawing Nos.15Z03-004-
DWG-M-001 and 15Z03-004-DWG-M-002 enclosed. In
Annexure-4.1 of this report, Land area details of Sites A, B & C
are given in brief.
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO SEC - 4
SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016 - 51 -
4.3 Feasibility Consideration
LAND FEATURES:
LAND AVAILABILITY:
Total land area required for the Thermal Power Plant is about
902.36 Ha. Land has been identified in Tharaikkudi,
Kannirajapuram and Narippaiyur villages of Kadaladi Taluk,
Ramanathapuram District. The land area for the Proposed Power
Plant comprises of both private and Government lands. There is
no habitation in the proposed Power Plant site, hence no
rehabilitation issues.
Plot Plan of the proposed Thermal Power Plant is shown in
Drawing No. 15Z03-004-DWG-M- 003.
ACCESSIBILITY:
The proposed site is on the western side of ECR connecting
Ramanathapuram and Vembar. Also The site is near the
proposed alignment of B.G. Railway line from Kanyakumari to
Karaikudi and hence it will facilitate transport of coal from
Thoothukudi port to site. The nearest city/town Thoothukudi at a
distance of about 55 km and Ramanathapuram at a distance of
about 65 km. The nearest port is Thoothukudi at a distance of
75 km for the site.
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO SEC - 4
SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016 - 52 -
FUEL SOURCE & TRANSPORTATION:
Coal, the main fuel for the proposed Thermal Power Plant is
envisaged to be imported from Indonesia or any other country
to the nearest port Thoothukudi which is 75 km from the
proposed site and from there it will be transported to the project
site. For Coal connectivity a combination of existing Rail
network, proposed new B.G line project and private railway line
to the power plant is proposed.The coal from Thoothukudi port
will be transported to site by one of the following rail route.
i. OPTION I - Utilizing the proposed new alignment of B.G
railway line from Kanyakumari to Karaikudi via
Ramanathapuram.
Coal will be transported by the existing railway line from
Thoothukudi Port to Milavittan, then through the
proposed B.G railway line which aligns along the
southern side of the proposed site and then by private
railway line take-off from a location nearer to the Power
Plant.
Or
ii. OPTION II - Utilizing the proposed new alignment of B.G
railway line from Thoothukudi to Madurai via
Melamarudur.
Coal will be transported by the existing railway line from
Thoothukudi Port to Milavittan, then through the
proposed new alignment of B.G railway line to
Melamarudrur. From Melamarudur to the power plant
private railway line is proposed.
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO SEC - 4
SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016 - 53 -
Details of the Approximate Rail route distance for Coal
connectivity are as given below:
SL.
NO.
DESCRIPTION OPTION I OPTION II
1 Through Existing route from Thoothukudi port to Milavittan
Route length 11 km
Route length 11 km
2 Through the Proposed new B.G line project
The proposed B.G linealigns along thesouthern side of theproposed plant siteconnecting Milavittanto Ramanathapuram. Approx route lengthof 50 km to beutilised in theproposed B.G line.
Milavittan to Melamarudur Approx route length of 14 kmto be utilised in the proposed B.G line.
3 Private railway siding Take-off from the proposed BG line
Approx. route length from take- off point to site 4 km
Approx. route length from take-off point (at Milamarudur) to site 40km
4 Approx. Total route length for coal connectivity
65km 65km
5 Status of proposed BG line Project
Decision is awaited from Railway Board
The proposed alignment has been sanctioned by Railway Board
The Coal connectivity details for the site identified for putting up
the station in shown in Drawing Nos.15Z03-004-DWG-M-
008 - Coal connectivity Rail route map.
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO SEC - 4
SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016 - 54 -
WATER SOURCE & CONVEYANCE:
The consumptive water required for the Power Plant is proposed
to be drawn from Gulf of Mannar, the coastal line is at aerial
distance of around 2.3 km on the Southern side of the proposed
project. Sea water intake pump house will be located off shore
and sea water will be pumped to the proposed site through pipe
lines over RCC deck. The sea water will be used for condenser
cooling and portion of it will be desalinated and used for other
purpose. The blow down water from cooling tower and
desalination rejects will be discharged back to the Gulf of
Mannar. Considering the submergence requirement for the
pumps, Intake Pump House to be located at a depth of about 5
m (tentative) will be suitable. Intake and Outfall are proposed to
be laid over pile supported RCC deck. A common RCC deck (15
m width) will be provided for both intake and outfall for about 4
km (tentative) and separate RCC deck shall be laid beyond this
point for outfall about 1.5 km (tentative). The tentative location
is indicated in the Drawing No.15Z03-004-DWG-M-003
(sheet 2of2). However, the location of the intake and outfall to
be finalised based on the Marine EIA/EMP study & the intake and
outfall Modelling study.
POWER EVACUATION:
Power generated in the Power Plant would be available at
765 kV level and Power from this switchyard would be
evacuated through two (2) 765 kV double circuit lines to the
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO SEC - 4
SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016 - 55 -
nearest 765 kV pooling station, location to be decided by
TANTRANSCO the local STU.
ENVIRONMENTAL ASPECT:
The Gulf of Mannar is a large bay in the Indian Ocean that lies
along the south-eastern tip of Tamil Nadu extending from
Rameswaram in the north to Kanniyakumari in the south. The
Gulf of Mannar Biosphere Reserve was set up in 1989 jointly by
the Government of India and the Government of Tamil Nadu
with a view of protecting marine wildlife and coastal ecosystems
that inhabit the 10,500 square kilometers of the reserve. The
Gulf of Mannar Marine National Park is a protected area, which
is part of the Biosphere Reserve that extends from
Rameswaram to Thoothukudi. It consists of 21 small islands
varying in size from about 0.5 hectares to 125 hectares and
adjacent coral reefs spread over an area of 560 square
kilometers. (source: State Environment report of Tamil Nadu
JAN-2016)
The Kadaladi Talk in Ramanathapuram district is a economically
backward district without any major industries and prone to
communal disturbances, a power plant of this 5X800 MW
capacity will bring in lot of employment opportunities both direct
and indirect and will pave away for communal harmony in this
area. The effect of the proposed project on environment should
be seen in the broader perspective of overall impact on the
neighbourhood. The proposed plant site is basically non-
agriculture in nature. The site area is free of any forest land and
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO SEC - 4
SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016 - 56 -
there is no historical monument within the vicinity. The plant
layout has been prepared keeping in view the CRZ
requirements. Three Bird sanctuaries are located in the vicinity
Melselvanur-Keelselvanur bird sanctuary at around 17 km,
Chitrangudi bird sanctuary and Kanjirankulam bird sanctuary at
around 22 km & 20 km respectively from the selected site (Site-
B). The GOMNP (Gulf of Mannar National park) Vembar zone
Uppu Tanni Tivu is around 11 km and Thoothukudi zone
Kariashuli Tivu is around 23 km from the selected project site.
The site falls within the buffer area of the GOMBR (Gulf of
Mannar Biosphere Reserve). Further assessment on
environmental impacts and the requisite management plans
shall be pointed out in EIA/EMP study separately. The tentative
location of intake / outfall location is around 12 km and 19 km
away from the Uppu Tanni Tivu and Kariashuli Tivu respectively
in Gulf of Mannar.
�
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO SEC - 5
SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016 -57-
TECHNICAL FEATURES 5.1 Introduction
Tamil Nadu Generation and Distribution Corporation
Limited. (TANGEDCO) is planning to set up a coal based 5 x
800 MW capacity power project near Ramanathapuram in the
State of Tamil Nadu. The proposal is mooted to deploy the
state-of-the-art technology using supercritical steam parameters
The basic plant design would consider unitised concept as far as
possible. Judicious provisions would be considered for
reasonable spare capacities in various systems and system
components and interchangeability of equipment/system. State-
of-the-art technology has been considered for design of the
proposed project.
5.2 Thermodynamic Cycle
The fuel considered for the project is coal from the mines in
Indonesia to be transported through Sea cum Rail. The
thermodynamic cycle will consist of the supercritical Boiler, the
Steam Turbine, the condenser, the condensate extraction and
boiler feed systems, the condensate and feed water heaters
along with all other necessary equipment for single reheat
regenerative feed heating system.
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO SEC - 5
SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016 -58-
A single reheat steam cycle with regenerative feed heating
system is proposed for the project. The typical heat balance for
such cycles based on the parameter proposed for the Turbine
inlet steam have been presented in Drawing No.15Z03-005-
DWG-M-004. Heat Balance Diagram is based on ‘zero’ make-
up, 32.5 ºC condenser cooling water inlet temperature with
condenser back pressure of 77mm of Hg.
As shown in the scheme and heat balance diagram, the main
steam from the boiler, after expansion through the HP turbine,
would be sent back to the boiler for re-heating. The reheated
steam, after expansion through the double flow IP turbine and
then through two double flow LP casing would be exhausted into
the main condenser. The exhaust steam from the LP turbine
would be condensed by circulation of cooling water. Vacuum
would be maintained in the condenser by 2x100% (1W+1S)
capacity vacuum pumps. The LP feed heating system would
consist of three(3) to four(4) stages of low pressure heaters,
one(1) gland steam condenser, one(1) drain cooler for the low
pressure heater, drain flash and one(1) deaerator. HP feed
heating system will consist of two(2) 50% parallel trains of high-
pressure heaters. However, number of heaters varies from
manufacturer to manufacturer. The condensate from the hot
well would be extracted by 3x50% capacity condensate
extraction pumps (2 working + 1 standby) and pumped to the
deaerator through Condensate polishing unit to gland steam
condenser, drain cooler and the LP heaters. The feed water after
being de-aerated in the deaerator would be pumped to the
boiler through the high-pressure heaters. Provision would be
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO SEC - 5
SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016 -59-
kept for dosing hydrazine solution in the condensate extraction
pump discharge and in deaerator feed tank or boiler feed
suction line for oxygen scavenging and pH control of the feed
condensate steam cycle. For the unit 2x50% turbine driven &
1x50% motor driven BFP with booster pump mounted on
common shaft is envisaged. Normally the steam-driven pumps
would be in operation. The boiler feed pumps would be
provided with lube oil system, automatic leak off and minimum
flow re-circulation valves. Motor-driven BFW pump would be
provided with modulating variable speed hydraulic coupling.
Condensate drain from the HP heaters would be cascaded to the
deaerator feed storage tank and the condensate drains from the
LP heaters would be cascaded to the condenser through the
drain cooler.
The auxiliary steam for the proposed power station would be
divided into two sub-systems, One Boiler Auxiliary Steam (BAS)
and other Turbine Auxiliary Steam (TAS). Both BAS & TAS
would receive steam supply from CRH inlet and Outlet line of
SH. The auxiliary steam supply system of the unit would supply
steam to the deaerators, turbine gland sealing system during
light load and start-up conditions. Auxiliary steam will also be
supplied for soot blowing, atomisation system etc.
Auxiliary Boiler of suitable rating shall be provided in case the
BTG supplier requires auxiliary steam for cold start-up of the
unit.
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO SEC - 5
SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016 -60-
The units will also be provided with HP and LP Turbine bypass
system for quick start and large load rejections. The turbine
generator units would be so designed that these will be capable
of cyclic duty and frequent start-ups and shutdowns during the
lifetime. The salient features and parameters of major
equipment of the 800 MW sets are furnished hereinafter. The
details of the units may vary to some extent as per vendors’
standard product. The basis of technical parameters of the main
plant and auxiliary equipment for the 5 x 800 MW thermal
power plant are discussed hereunder which describes the
general requirements but is not intended to be exhaustive.
5.3 Main Plant & Equipment
Turbine Generator Unit :
The turbine component and its auxiliaries would be designed and
selected to meet the stringent requirements in respect of
superior thermal performance, excellent product reliability and
operational flexibility. The area provided for the power house is
12.6 acres.
The turbine manufacturer will have turbine designed based on
modular design approach that divides the turbine into three
main parts:
� High-Pressure (HP) section,
� Intermediate-Pressure (IP) section and
� Low-Pressure (LP) section.
The proposed turbine will have one HP, one IP (double flow) and
two double-flow low-pressure casings. All components will be
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO SEC - 5
SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016 -61-
selected based on long-proven records and standardized
modules. The turbines will be of the tandem compound design.
The individual shafts of the cylinders and the generator rotor
shaft will be coupled rigidly together and all the shafts will be
machined from single forgings. The turbo-generator set would
be designed for a maximum throttle steam flow at turbine Valve
Wide Open (VWO) condition of 105% of Turbine Maximum
Continuous Rating (MCR) flow. Brief technical features of major
systems and equipment is given in Annexure-5.1.
The HP turbine will be designed with single flow. This will have a
double-shell casing consisting of inner casing carrier and barrel-
type outer casing. Main steam to the HP turbine will be supplied
through two(2) combined stop and control valves.
The IP-turbine will be designed with double flow. This will have a
double-shelled casing with horizontally split inner and outer
casing. Reheat steam will be admitted through two(2) combined
stop and control valves of the turbine. The valves will be
arranged on either side of IP casing. The steam flows to the LP
Turbine through a cross-around pipe.
The LP-turbine will comprise horizontally split multi shell casing.
The outer casing will consist of two end walls, a bracing system,
the top half and the sidewalls. The inner casing will be double
shell axially split supported by support arms that are bolted to it
and that rests on the bracket supports of the bearing pedestals.
The bearing pedestals will be mounted on the foundation. They
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO SEC - 5
SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016 -62-
will carry the shaft seal casings, which shall be joined to the
outer casing by means of expansion joints.
A fully automatic gland sealing steam supply system will be
provided for the TG Set and the turbine driven BFPs. HP & IP
turbine shaft glands will be sealed to prevent escape of steam
into the atmosphere and the LP turbine glands will be sealed for
preventing leakage of atmospheric air into the turbine. Steam
will be used for sealing these spring backed labyrinth glands.
During start-up and low loads (say 40% load), seal steam will be
supplied to the turbine glands from the auxiliary steam header
or cold reheat line through a seal steam-regulating valve.
During normal operation (above 40% load), the HP and IP
turbines will be of self-sealing type and under that condition the
auxiliary/CRH steam source will be cut off and the leak-off
steam from HP and IP glands will be used for sealing the LP
glands. The excess leak-off steam shall be led to the condenser.
A gland steam condenser will be provided to condense and
return to the cycle, all gland leaks off steam including that from
BFP turbines. A desuperheating type bypass will be provided
during outage of gland steam condenser. 2x100% capacity
vapour exhausters will be provided to remove non-condensable
gases from the gland steam condenser. The exhaust gases will
be led over the TG hall roof level.
The turbine will have throttle or nozzle controlled type
governing. The steam turbine generator unit will be equipped
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO SEC - 5
SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016 -63-
with an electro-hydraulic governing system backed up by 100%
mechanical-hydraulic or electro-hydraulic control system.
HP–LP Bypass Station will comprise 60% (BMCR) HP and LP
Turbine bypass station to act not only as a protection to the
turbine during pressure rise resulting from sudden load throw-
off but also to enable operation of the unit at loads lower than
the control load. Further HP/LP bypass will permit quick,
repeated hot starts of the unit on its tripping.
The LP bypass station will be connected to the hot reheat line
and discharge the steam into the condenser. The hot reheat
steam will be de-superheated by means of condensate injection.
The bypass system shall be in operation when the steam turbine
is not able to receive the entire steam quantity, e.g. during
start-up or in case of a load rejection. The HP and LP bypass
stations will be capable of meeting the following requirements:
� Quick start up of the steam generator from cold, warm & hot conditions.
� Parallel operation of the bypass with turbine under large load throw-off.
� House load operation followed by large load throw-off.
� To keep the steam generator in operation so as to avoid a trip out of the steam generator following full load rejection.
Condensing Equipment & Accessories:
The function of the condenser is to condense the steam
exhausted from the LP cylinders and to produce and maintain as
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO SEC - 5
SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016 -64-
high a vacuum as possible in order to increase the enthalpy
drop, which can be utilised in the turbine.
The condenser will be of single-flow box-type surface condenser
with water boxes on each end for 800 MW sets. The steam
space will be of rectangular cross-section to achieve optimum
utilization of the enclosed volume for the necessary condensing
surface. The condenser will be located below the LP turbine and
form an integral part of it.
Each condenser unit would be transverse mounted and would
condense exhaust steam by circulation of cooling water (inlet
temperature 32.5 °C max.) in a recirculating cooling water
system using wet type cooling tower. Condenser outlet water
temperature may be maintained within 42.5 °C. Sea water
would be the cooling medium in the condenser and other
auxiliary coolers. Condenser tube shall be welded titanium ASME
B-338 GR II and tube support plates shall be carbon steel.
Cathodic protection with Zn or Al sacrificial anode would be
provided, if required. The condenser would be designed as per
HEI code or equivalent. The heat load of the condenser will
correspond to the turbine operating condition with VWO having
105% MCR steam flow, 1.5% make-up, 85% tube cleanliness
factor and a maximum cooling water inlet temperature of 32.5
°C to maintain rated condenser pressure of 77 mm of Hg
(absolute). The condenser should also be capable of accepting
full HP-LP bypass steam flow safely without undue pressure rise,
vibration, noise or other detrimental effects. Oxygen content of
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO SEC - 5
SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016 -65-
condensate leaving condenser hot well will not exceed 0.015 cc
per litre over the entire load range.
Lube Oil System:
The oil system will supply oil for lubrication and cooling of
turbine and generator bearings, and to the hydraulic shaft
turning gear during start-up and shutdown. This system will be
provided with AC & DC powered oil pumps. To improve
lubrication of the bearings during start-up and shutdown, a
jacking oil system will be installed which also supplies motive oil
to the hydraulic turning gear with hydrometric gear motor.
A separate, self-Contained high pressure fluid system with
dedicated pumps will be provided for lubrication & cooling of
turbine & generator bearings. The Lube oil system will
specifically include the following:
� The main oil pump will be centrifugal/gear type. The turbine shaft will directly drive it. It will have sufficient capacity to handle lube oil requirement of the bearings and emergency seal oil requirements.
� 2 x 100% AC Aux. oil pumps for start-up, slowdown of TG unit and as standby to MOP for automatic operation. These pumps will be in service during start up till the main oil pump takes over the supply.
� 1 x 100% DC emergency oil pump for meeting lube oil requirements of bearings during emergency with automatic starting on low lube oil pressure preset value.
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO SEC - 5
SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016 -66-
� One (1x100%) each AC & DC motor jacking oil pumps will be provided to lift the rotor at the bearing during turning gear operation.
Each unit will be provided with an oil tank of sufficient capacity
for oil changes. 2x100% duty vapour extraction fans. The
2x100% capacity oil coolers will be provided for oil cooling.
A lube oil purification unit will be permanently installed for each
unit for the total oil charge on a continuous basis.
Turbine Control Fluid System:
For the governing and control system of the turbine a complete
self-contained control fluid system with oil pumps will be
provided. Fire resistant fluid will be employed to eliminate fire
hazards. The system will comprise:
� A control fluid reservoir of adequate capacity to ensure fluid supply.
� 2 x 100% AC motor driven pumps to pump the fire resistant fluid from the reservoir.
� 2 x 100% capacity control fluid coolers designed for service with DM water.
A control fluid purifying unit will be provided for the turbo-set for
purifying at least 20% of the total oil charge in the system per
hour on a continuous bypass basis. 2x100% capacity AC motor
driven purification pumps to circulate oil through purification
system will be provided. Necessary filters, strainers, piping,
fittings, valves and instruments shall be provided.
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO SEC - 5
SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016 -67-
Air Extraction:
The unit will comprise 2x100% (1 working + 1 standby) vacuum
pumps along with all accessories and instrumentation for
condenser air evacuation. The vacuum pumps and accessories
will be used to create vacuum by removing air and non-
condensable gases from steam condenser during plant
operation. Vacuum pumps will be of single/two-stage liquid ring
type with both stages (if two-stage pump is selected) mounted
on a common shaft. Vacuum pumps will be sized as per latest
HEI requirements.
Condensate Extraction Pumps:
The condensate/feed water cycle would also comprise 3x50%
capacity motor-driven, vertical condensate extraction pumps of
CAN-type construction. Connection between condenser and each
pump will be through a block valve and removable strainer. The
pumps will discharge through check valve and motor operated
stop valves into a common discharge header. Connection for
condensate supply to the following major services will be tapped
off from this condensate discharge header.
a. LP bypass desuperheating spray
b. Turbine exhaust hood spray
c. Gland sealing system desuperheating
Condensate will then pass in series through the gland steam
condenser and drain cooler before being passed through the low
pressure feed water heaters.
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO SEC - 5
SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016 -68-
Boiler Feed Water Pumps:
The feed water heating system will also comprise one(1) motor-
driven (50% capacity) and two(2) turbine-driven (50% capacity)
boiler feed water pumps. The head, capacity and net positive
suction head (NPSH) would be so selected as to permit parallel
operation at all loads and be compatible with the heat cycle
considered to meet the boiler MCR without encroaching on
normal margins. Booster pumps may be considered to ensure
appropriate head at pump inlet. The pumps will be provided with
mechanical seal, flushing arrangement as per API 610. The
supply would be complete with and inclusive of variable speed
hydraulic coupling, lube oil system, automatic leak-off, minimum
flow recirculation valves, bypass valves, base plates, foundation
bolts, couplings, 11 kV, 3 pH, 50 Hz electric motor drive.
The regenerative feed heating system would comprise vertical or
horizontal shell and tube-type high pressure feed water heaters
with bypass arrangement. Three(3)/four(4) stage horizontal U-
tube type low pressure heaters equipped with drain cooling and
condensing zones and individual bypass system is envisaged.
Besides these, separate drain cooler, gland steam condenser
etc. as per suppliers' standard, horizontal spray or spray-cum-
tray type deaerator with integral vent condenser to limit oxygen
content to a maximum limit of 0.005 cc/litre at all operating
conditions with minimum loss of steam are envisaged. The
storage tank should be adequately sized to accommodate at
least 10 minutes water requirement to provide feed water to
respective boiler at the BMCR condition. The two (2x50%) or
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO SEC - 5
SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016 -69-
three (3x33%) nos. high-pressure heaters in parallel path will be
of horizontal/vertical U-tube type having desuperheating,
condensing and drain cooling zones. All steel construction of
condensate/feed water wetted surfaces is desired to facilitate
uniform chemical conditioning of steam-condensate-feed water
system.
Steam Generators:
Super Critical Pressure (“SCP”) power plant is envisaged with a
view to ensure better plant efficiency; minimizing basic fuel
consumption; and most important criteria being the drastic
reduction of emission quantities of SOx, NOx, CO2 and particulate
matters etc.
The SCP technology has been presently accepted in India and is
adopted in some of the major thermal power plants. The area
provided for the boiler and mill bay is 14 acres.
Furnace Type:
Two-pass/tower type spiral wall or vertical wall type are
normally considered.
The principal concern with a variable-pressure/sliding pressure
super critical-pressure design is the requirement for once-
through operation. The mass flow in the furnace-wall tubes must
be sufficiently high to avoid excessive metal temperatures and
uneven steam outlet temperatures when operating at super
critical pressure at higher boiler loads.
The draft system comprises of two(2) nos of FD fans each rated
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO SEC - 5
SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016 -70-
for 60% of BMCR capacity. Two(2) Induced Draft (ID) Fans each
rated at 60% of BMCR flow will be axial inlet vane control type
with variable frequency drive arrangement.
With cold primary air system, it is possible to reduce the
capacity of Primary Air Fans (PAF) compared to hot primary air
system. Cold primary air system is adopted in all cases. Two PA
fans with 60% capacity are considered.
Pulverized Fuel Preparation System:
For firing coal pulverizers of slow speed large capacity bowl mills
will be provided having low auxiliary power consumption; and
relatively high life expectancy of grinding parts and armour
plating. The mills size and numbers will be selected such that on
an average one mill remains standby while one of the mill is
under maintenance.
Considering the grinding fineness required, it is suggested
equipping the mill with rotating classifiers having speed
adjustment to control grinding fineness. The firing system will
employ latest the ‘state-of-the-art’ burners and permit load
variation from 40 to 100% BMCR without use of support fuel.
The ratio of fuel and air flow will be controlled. Due to sufficient
burner wall distance and the burner swirl direction, operation
with low excess air is possible without the risk of wall damage.
Start-up Fuel System:
The fuel oil system will be provided for boiler start up; and for
flame stabilization during low load operation with or without coal
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO SEC - 5
SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016 -71-
Firing. Two (2) types of fuel oils will be used.
� Light Diesel Oil (LDO/HSD) for boiler start-up (upto 10% of
BMCR)
� Heavy Fuel Oil (HFO) for low load operation and flame stabilization (40% of BMCR), as necessary.
Electrostatic Precipitators:
It is proposed to install high efficiency electrostatic precipitators
having an efficiency that will limit the outlet emission to 30
mg/Nm3 while the boiler is operating at its BMCR, firing worst
coal having maximum ash content.
The electrostatic precipitators will have six(6) gas streams,
isolated from each other on the electrical as well as gas side and
will be provided with gas tight dampers at inlets and outlets of
each stream, so as to allow maintenance to be carried out safely
on the faulty stream, while the unit is working. Electrostatic
precipitator will be provided with micro-processor based
programmable type rapper control system and ESP
management system to ensure the safe and optimum operation
of ESP. ESP transformer rectifier sets will use high fire point oil
as the cooling medium. The dust collection hoppers at all
strategic locations will have a minimum storage capacity of
eight(8) hours. The hoppers will have heating arrangements to
prevent ash sticking to the sloping sides and down pipes. Level
indicators to indicate and trip the ESP in case of high ash levels
in the ash hoppers, which will jeopardize the safety of ESP
otherwise. The area provided for the ESP is 12 acres.
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO SEC - 5
SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016 -72-
Flue Gas Desulphurising System (FGD):
FGD system, to be installed behind the chimney. The design and
layout of steam generator and its auxiliaries will be such that a
wet flue gas desulphurisation system can be installed, taking
suction from duct after ID fan and feeding the de sulphurised
flue gases back to the chimney with provision for bypassing the
FGD system. The FGD system would require around 0.2 million
tonnes of limestone per year. The generation of Gypsum is
around 0.3 million tonnes per year. Closed storage area with
storing capacity for 30 days is provided for the limestone and
gypsum in FGD material handling area located at the eastern
boundary of the plant. The total area provided for the FGD
system is around 17 acres. In addition, an open storage area of
50 acres is provided within the plan boundary near the ash dyke
for the disposal of Gypsum.
Chimney:
Total 3 (Three) stacks with stack height of 275 m (two twin flue
and one single flue stack) is envisaged for the proposed units.
5.4 Auxiliary System
The philosophy of design of the auxiliary system would be
predominantly guided by the land features, technology, basic
parameters, infrastructure etc. The other facilities to be
developed are, coal transportation from Tuticorin by railway, coal
storage and handling systems, fuel oil system, 765 kV
switchyard, ash handling facility, etc.
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO SEC - 5
SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016 -73-
All the systems and system components would be designed for
simplicity of operation and ease of maintenance so as to call for
minimum manual labour and low degree of supervision. System
redundancy would be provided as per good engineering
practices. Brief technical features of Major Systems & Equipment
are enclosed as Annexure-5.1.
Plant Water System:
The consumptive water requirement of the proposed 5x800 MW
station is of the order of 39193 m3/hr (approx) (7839 m3/hr per
unit) to be met by drawal of water through an intake well with
pump house to be constructed on off-shore.
The cooling water system is based on recirculating cooling
system using wet type Natural Draft Cooling Tower (NDCT) for
the condenser and auxiliary equipment cooling circuit. Based on
the available sea water analysis it is envisaged that a cycle of
concentration of 1.3 would be achieved. The total area provided
for the plant water system is around 138 acres.
Sea water is the main source of water for the proposed power
station. It is planned to draw 39193 m3/hr of water from sea
through an intake pump house.
For the proposed 5x800 MW station the total sea water
requirement is estimated on the basis of about 1% heat cycle
make-up, make-up to cooling towers usually associated with
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO SEC - 5
SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016 -74-
average daily plant load apportioned on hourly basis and other
consumptive requirements like potable water, RO-DM make up,
sealing water, Service water, HVAC makeup etc. It is proposed
to utilise cooling tower blowdown in ash handling plant slurry
disposal system. The breakdown is detailed in Annexure-3.2
furnished earlier and the water balance diagram is given in
Drawing No.15Z03-006-DWG-M-009.
It is envisaged that Six (6) (4W + 2S) nos. of 10300 m3/hr
capacity intake pumps would be installed in the sea water pump
house.
Sea water from the intake system would be pumped to CT
forebay as CT makeup water, Electro-chlorination plant and a
part of sea water will be clarified in the DAF Clarifier at site to
remove the suspended solid. Clarified water from DAF Clarifier
would be stored in an intermittent clarified water storage tank.
Sea water from cooling tower basin would be pumped to
condenser. Water requirement for Desalination plant would be
pumped from intermittent clarified water storage tank by use of
Desalination plant feed pumps two (2) nos. (1W+1S).
Of these, cooling tower make-up is the largest quantity
involved. Considering the ambient parameters and gestation
period, Natural Draft Cooling Towers (NDCT) have been
proposed. Apart from the condenser cooling, other auxiliary
cooling will be achieved by circulating sea water by a separate
set of auxiliary cooling water (ACW) pumps. These ACW pumps
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO SEC - 5
SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016 -75-
would also be located in the same CW pump house. Sea water in
auxiliary cooling water system would be utilised as a secondary
circuit with DM water as a primary circuit of plate type heat
exchanger to cool the auxiliary coolers.
Cooling water in circulation estimated for the units would include
the requirement of auxiliary cooling circuit. The make-up water
requirement for the Natural Draft Cooling Towers (NDCT) at full
load will be around 33125 m3/hr (6625 m3/hr per unit). The
cooling tower blow down is expected to be about 25380 m3/hr.
For 5x800 MW station fifteen (15) nos. [2W + 1S per unit] CW
pumps and ten (10) nos. [1W + 1S per unit] ACW pumps are
envisaged. DM Closed Cycle Cooling Water Pumps Four(4) [3
working + 1 standby] per unit.
The desalinated / product water from desalination plant would
meet the following requirements:
� BWRO-DM plant
� Sealing and cooling water for ash handling plant
� HVAC System
� F.G.D system
� Potable water for plant & township
� Service water requirements
� Coal Handling Plant Dust suppression
� Fire protection system
Fire water requirement would be supplied from the desalinated /
product water storage tank and a built-in dead storage would be
provided as per Tariff Advisory Committee (TAC) requirement.
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO SEC - 5
SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016 -76-
For potable water supply to the project, a separate set of pumps
drawing water from desalinated / product water storage tank
and with necessary chlorine dozing is envisaged. An overhead
tank of about 50 m3 capacity would be located at the top of
powerhouse and drinking water would be supplied to different
consumption points through piping. On apportioned basis about
100 litre of potable water may need to be supplied per person
per day. BWRO permeate water would be supplied to the
demineralisation plant, which would comprise of three(3)
(2W+1S) chains of 90 m3/hr (each). DM water would then be
stored for 24 hours in Four (4) rubber lined mild steel DM water
storage tanks of each 1100 m3 capacity, located near DM Plant.
The proposed DM plant along with the neutralisation pit,
acid/alkali handling system would be located close to the DM
water consumption point to optimize on DM water pipeline. DM
water from the DM water storage tanks would thereafter be
pumped to the condensate storage tanks located near the boiler
area. Five(5) condensate storage tanks each of 500 m3 capacity
is envisaged. Water from this tank will be supplied as heat cycle
make-up and to the chemical feed system, H2 generation plant.
Make-up requirements for CCCW system and condensate
polishing system.
Demineralisation Plant & Heat Cycle Make-up
System: Assuming average 1.0% make-up for the heat cycle and
accounting for four hours regeneration time, three(3)
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO SEC - 5
SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016 -77-
demineralising chains of 90m3/hr feed flow capacity each have
been envisaged for the proposed unit. In the proposed DM plant
two streams will be in operation and one stream will be as
standby. DM plant will also supply heat cycle make-up, the
make-up requirement for primary water circuit of stator cooling
system, chemical feed system, CPU make-up and DM water
requirement for the hydrogen generation plant.
Desalinated/product water would be pumped to the RO-DM
plant for demineralisation. In the RO-DM plant,
Desalinated/product water will be passed through RO plant
(Stage-II) and then to mixed bed exchangers. The
demineralised water will be stored in DM water storage tanks.
Acid and alkali handling, storage and feeding system will be
installed for the DM plant resin regeneration. The DM water
produced in the plant would then be taken to Four (4) DM water
storage tanks, each of 1100 m3 capacity to meet the total
requirement in case of any exigency. DM water from the storage
tanks would be transferred to unit condensate storage tanks by
2 x 100% capacity DM transfer pumps.
Service Water System:
Service water for the project would be used for floor washing,
air filter cleaning and other non-priority items etc.,
Desalinated/product water shall be taken to an overhead tank
for onward distribution to above consumption points.
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO SEC - 5
SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016 -78-
Coal Handling System:
For the purpose of equipment selection the worst coal
combination (imported 50% & indigenous 50%) has been
adopted. The total area provided for the Coal handling system
including MGR system is around 148 acres.
The scheme of the proposed Coal Handling System is shown in
Drawing No.15Z03-005-DWG-M-006. Adequate redundancy
has been adopted to ensure uninterrupted operation of the
system. The Coal Handling system to be designed based on the
worst coal (50:50).
i) Gross calorific value 4221 kCal/kg ii) Hourly coal consumption 2093 TPH
419 TPH per unit iii) Max. daily consumption of coal
at MCR50240 TPD
10048 TPD per unitiv) Annual requirement for
proposed station @ 85% PLF 15.59 MTPA
3.11 MTPA per unitv) Maximum size of coal delivered
at plant end (-) 50mm
vi) Mode of coal transportation By railway from Tuticorin Port.
Coal for the proposed station would be eventually available from
Indonesia. The coal in (-) 50 mm size would be transported to
the plant site in rake loads. To operate the station at MCR, 14-
17 rakes/day loads of coal need to be received. With the above
in view 24 hr operation of coal receiving facility is envisaged. To
estimate the design capacity of conveyors and coal handling
system a margin of 20% may be considered towards presence
of shale in raw coal. The bunker capacity for the unit is
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO SEC - 5
SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016 -79-
considered to be 14-hours. The balance of plant and equipment
of CHP would be designed for three-shift operation for the
proposed station which will take care of outage requirement and
running maintenance. The handling capacity of receiving and
stacking facilities for the proposed power is of 4500 TPH two
streams (1W + 1S) rated capacity. However, figures on coal
consumption and conveyor capacity may be revised at DPR
stage as per available input data at that time. Merry-go-round
system is envisaged for the proposed project. Three (3) nos.
Track hoppers is provided for handling the 17 rakes/day of
BOBRN type wagons. The coal from the hoppers would be fed to
the crusher house , crushed to the size of (-)25 mm. The coal
stack would be equipped with two (2) nos. reversible stacker-
cum-reclaimer and two (2) nos. single direction stacker-cum-
reclaimer with stacking rated capacity of 4500 TPH and
reclaiming rated capacity of 2000 TPH. The stacker-cum-
reclaimer would be rail-mounted, electrically-driven unit with 50
m boom length having 270° slewing and adequate luffing
provision to stack the coal upto a height of 9 m and reclaiming
the same afterwards. In the normal route coal can be directly
taken to the power-house bypassing the coal stack.
Coal Bunker conveying system, the Unit 1,2 & 3 will be provided
with separate twin stream conveyor system with rated capacity
2000 TPH form the stock pile to bunker. Unit 4 & 5 will have
another independent twin stream conveyor system with rated
capacity 2000 TPH. Interchange coal feed facility is also
provided for the two independent conveying system.
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO SEC - 5
SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016 -80-
Crushed coal would be transported to the bunkers via the
inclined conveyors and the bunker level conveyors. Bunkers
would have a storage capacity of about 14 hours’ fuel
requirement for the boiler. The bunkers will be provided with rod
and slide gates, arch breakers, etc. to facilitate operation.
Necessary belt weighing at bunker level conveyors, electro-
mechanical and capacitance type level indicators, fuel sampling
units, flap gates etc. would be provided in the system as
required. Dust extraction and suppression system will be
provided for all the coal transfer points to control the fugitive
emissions. Special precautions will be taken for pollution control
by providing dust extraction and dust suppression systems at
different transfer points and ventilation system for underground
tunnels. In addition, roof extraction fans will be provided in key
areas like boiler bunker floors. Pressurized ventilation system
with unitary air filtration unit will be provided for control room
and MCC buildings.
Necessary water distribution network for drinking water with
pumps, piping, tanks, valves etc. will be provided for
distributing water at all transfer points, control rooms etc.
Similarly, service water network will be provided.
A centralised control room with microprocessor based control
system is envisaged for operation of the Coal Handling Plant.
Except locally controlled equipment like dust extraction/dust
suppression/ventilation equipment, sump pumps, water
distribution systems etc. all other in-line equipment would have
provision of remote control. However, provision of local control
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO SEC - 5
SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016 -81-
would also be provided. All necessary interlocks, control panels,
MCCs, mimic diagrams etc. would be provided in the main
control room for safe and reliable operation of the Coal Handling
Plant.
The major equipment for the proposed project are listed below:-
1. Track Hopper : 3 nos.
2. Rotary plow feeder : Twelve (12) nos.
3. Belt conveyors : Coal stacking stream conveyors of 4500TPH.
Reclaiming and bunker supply stream conveyors of 2000 TPH
4. Stacker-cum-reclaimer : Four(4) Nos. with stacking capacity of 4500 TPH and Reclaiming capacity of 2000 TPH.
5. Crushers : Four(4) Nos.
6. Metal detectors : Ten(10) Nos.
7. ILMS : Twelve(12) Nos.
8. Belt weighers :Fourteen (14) Nos.
9. Coal sampling unit : Three(2) Nos.
10. Flap gates, rack & pinion gates, etc. : As required.
11. Level indicators : Electronic type.
12. Chute liners and chute : One lot supporting structures
13. Bulldozer : Six(6) Nos.
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO SEC - 5
SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016 -82-
Ash Handling System:
To meet the requirement of the prevailing environmental norms
of the Tamil Nadu Pollution Control Board (TNPCB) and Central
Pollution Control Board (CPCB) guideline, the system considers
Dry collection and disposal of Fly Ash, Dry extraction of bottom
ash. Ash will be primarily disposed by truck to end users as far
as possible. Besides provision will be made to transport fly ash
(only during emergency) and Bottom ash through pipe line to
the ash dump area. The total area provided for the Ash handling
system is around 5 acres. The ash dyke area is around 522
acres.
The quantum of ash generation would depend on the plant load
factor and the quality of coal being fed. In keeping with the
designed system capacity envisaged for CHP, worst coal with
ash percentage of 26% is used for equipment selection of the
Ash Handling Plant. It has been estimated that about 544
tons/hr (max.) of ash would be generated from the proposed
project considering 5 units. Assuming the ratio of fly ash to
bottom ash as 80:20, usually adopted for design of such
application, about 22 tons/hr of bottom ash and 87 tons/hr fly
ash is required to be removed from each unit. Ash generation
rate being moderate, intermittent ash removal arrangement
with necessary storage hoppers (i.e. bottom ash hoppers,
economiser/air pre-heater/ESP hoppers) to hold ash for 8 hours
is envisaged. Bottom ash evacuation in 4 -hours per shift and fly
ash evacuation in 4-4 1/2 hours per shift has been considered.
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO SEC - 5
SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016 -83-
In Drawing No. 15Z03-005-DWG-M-007, the scheme
proposed for the Ash Handling Plant of the project is shown. The
scheme proposes Dry extraction and disposal of bottom ash via
Dry conveyor, crusher, pneumatic conveying system bottom
ash silo. The design capacity of bottom ash evacuation system
would be 45 TPH for each boiler. Fly ash from ESP, air heater
and economiser collection hoppers and stack hoppers would be
conveyed through vacuum system to the intermediate surge
hoppers from where ash would be transmitted by pneumatic
pressurised system to the fly ash storage silo. As shown in the
sketch, conveying air compressors would be used to transfer fly
ash to the silos. De-ashing from fly ash hoppers would operate
on an auto sequence mode with total operation time spanning 4
to 4.5 hours in a shift. Four(4) streams of pneumatic conveying
system of capacity about 100 Tons/hr each have been
considered for each boiler. The ash would be conveyed through
pressure conveying system upto the fly ash silo located near the
boundary of the plant. The design capacity of the pressure
conveying system would be optimized to suit this requirement.
Bottom and dry fly ash would thereafter be transported in
covered trucks from the respective silos for end use. An
additional spare nozzle may be provided below the fly ash
storage silo for slurry disposal lean mode of disposal which is
around 20% ash concentration on volumetric basis. Normally,
dry disposal mode would be operational. Provision is kept for
selling ash from the dry ash disposal spout of silo to the possible
users. A small quantity of water will be sprinkled to moisten the
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO SEC - 5
SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016 -84-
ash in the silo unloaders prior to loading in the trucks for truck
disposal.
For the purpose of the present project report the above system
has been considered for working out the project cost. The Ash
Handling System control room will be located adjacent to ESP
control room for ease of operation.
Fluidizing Air System:
Continuous supply of fluidizing air during ash evacuation has
been envisaged in all the hoppers of the ESP and the stack to
facilitate smooth and effective ash flow. For this, fluidizing air
blowers of adequate capacity (2x100%) and pressure would be
provided. The fluidizing air system would be complete in all
respects with necessary piping, valves and instruments to
ensure satisfactory system operation.
MCC & Control Panel:
415 V MCC (Motor Control Centre) and control panel for the Ash
Handling Plant would be located inside a separate room annexed
to the ESP control room. Ash Handling System operation can be
done in automatic sequential manner and/or remote manual
mode from the PLC based control panel.
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO SEC - 5
SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016 -85-
Fuel Oil Handling System:
The fuel oil handling system would comprise receiving, storage,
pumping and heating of both HFO and LDO. Oil would be
brought to the plant in either rail wagons or by road tankers
from nearby depots. Two(2) HFO storage tanks of 5000 m3 and
two(2) LDO storage tanks of 1250 m3 are envisaged for the
station. The system would be complete with unloading pumps,
filters, pressurizing pumps, pipeline, instruments etc. The total
area provided for the Fuel oil handling system is around 4 acres.
Ventilation & Airconditioning System:
Right environment for operation and maintenance of the plant
as well as for proper functioning of the equipment, controls and
accessories is an important aspect which has been given due
consideration in the proposed Ventilation and Air Conditioning
System.
Ventilation System:
Adequate ventilation system has been considered for the
powerhouse building, Central Control Building, ESP control
building, Air Compressor House, Blower room for Ash Silo &
Vacuum Fly Ash System, Switchyard Control Building and other
areas like A/C plant room, Switch gear room for Cooling Towers,
DM plant building, CW Treatment Building, Chemical House, DG
Building, Hydrogen Generation Plant, Elevator Machine rooms
and various pump houses like CW/ACW pump house, Raw Water
pump house, Ash Slurry pump house, Clarified Water pump
house, Fuel Oil Unloading and Pressurizing pump house etc. with
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO SEC - 5
SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016 -86-
their associated Electrical rooms, Workshop and Store, Fire
Station Building, Kitchen/Pantry and Toilet areas of Canteen
Building, Service building and Administrative Building etc. to
achieve the following :-
i) Dust-free comfortable working environment.
ii) Scavenging out structural heat gain and heat load from various equipment, hot pipes, lighting etc.
iii) Dilution of air polluted due to generation of obnoxious & hazardous gaseous/aerosol contaminants like acid/chemical fumes, dusts etc.
Ventilation system proposed for important areas are described
below:
a. Powerhouse and Central Control Building
Supply/exhaust ventilation system with evaporative cooling
has been recommended for the powerhouse building.
Ambient air would be drawn through air inlet louver,
automatically cleanable water flooded type SS mesh filters,
water wetted fill deck and moisture eliminator and will be
supplied by means of centrifugal fans to powerhouse
through ducting and grilles to achieve proper distribution.
The sprayed water over the SS mesh filter will be re-
circulated by means of centrifugal pumps, piping, valves
and other accessories. Similarly, water dripped over the Fill
Deck will also be re-circulated by means of centrifugal
pumps, piping, valves and other accessories.
'Exhaust' system consists of axial flow wall/roof-mounted
exhaust fans with rain protection cowl/hood, short
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO SEC - 5
SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016 -87-
ductwork, etc. Part of the supplied air will be exhausted
and the rest will ex-filtrate through the various openings in
the structure, preventing infiltration of dusty air.
Various non air conditioned rooms in the Central Control
Building e.g., cable spreader room, switchgear & MCC
rooms, SWAS wet panel rooms and Battery Charger rooms
etc. will be ventilated by means of the same Evaporative
Cooling units for Power House.
Exhaust ventilation system will be provided for the Battery
Rooms to evacuate acid fumes and hydrogen. Bifurcated
type exhaust fans will be employed for this purpose.
Coal tripper floors are proposed to be provided with exhaust
system to eliminate building-up of hazardous gases like
carbon monoxide, methane etc.
Pressurized Ventilation system will be effected for the
Elevator Machine rooms by means of wall mounted Fan-
Filter units and back draft dampers.
All toilets will be ventilated by providing wall mounted
exhaust fans.
b. ESP and AHP Control Buildings
For ventilation of these building (except the control room),
ambient air will be drawn through unitary air filtration unit
comprising fresh air intake louvers, automatically cleanable
SS mesh filters (with water spray) and moisture eliminator
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO SEC - 5
SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016 -88-
and supplied to the space by means of centrifugal fans.
Water sprayed over the filter will be re-circulated by means
of centrifugal pumps.
In addition to filter cleaning, the water spray will have an
evaporative cooling effect too. This will produce some
cooling effect as an additional advantage.
The supplied air will be exhausted through wall mounted
gravity operated dampers (Back Draft Dampers) to
maintain an overpressure of 1-2 mm of water column to
reduce dust ingress.
c. Other Buildings
Other buildings like Air Compressor House, A/C plant room,
DM plant building, CW Treatment Building, Chemical House,
DG Building, MCC/Switchgear room of Switchyard Control
Building, Hydrogen Generation Plant Building, Aeration
Blower room for Ash Silo and Blower Room for Vacuum Fly
Ash System, Various pump houses, like CW/ACW pump
house, Raw Water pump house, Ash Water pump house,
Ash Slurry pump house, Clarified Water pump house, Fuel
Oil Unloading and Pressurizing pump house etc. with their
associated Electrical rooms, Workshop and Store, Kitchen/
Pantry and Toilet areas of Canteen Building, Service
Building and Administrative Building etc. will be ventilated
by means of dry system comprising axial flow fans, dry
filter (wherever required), cowls, ducting (wherever
required), gravity dampers (wherever required) etc. Inside
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO SEC - 5
SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016 -89-
dry bulb temperature (DBT) is expected to be higher than
ambient by about 3 °C.
Air Conditioning System:
Various control rooms in power station, housing a group of
sophisticated and precision control panels and desks call for
controlled environment for proper functioning and for personnel
comfort.
Some other facilities like Administrative Building, Service
Building, Canteen Dining Hall etc will also call for comfortable
environment for the occupants.
The following areas are proposed to be air conditioned:-
a. Control room, control equipment room, Shift Charge Engineers’ rooms, computer room, UPS room SWAS dry panel room, CPU Control room, Laboratory room, located in the Central Control Building/Turbine Building.
b. Electrostatic precipitator control room
c. AHP Control Room
d. Coal Handling Plant Control Room
e. DM plant control room, office and Laboratory area
f. Office areas, lecture rooms etc. in the service building
g. Switchyard Control Room
h. Weighbridge Control Room
i. Fire Station Control Room
j. AC Plant Control Room
k. Hydrogen Generation Plant Control Room
l. Other Control rooms housing PLC panels
m. Different floors of the Administrative Building
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO SEC - 5
SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016 -90-
n. Dining Hall of Canteen Building
To cater to the above requirements the following systems are
proposed:-
i) A central chilled water plant to cater to the air conditioning requirement for the Central Control Building and Service Building, comprising Vapour compression Chiller and stand-by Screw Chillers, condenser cooling water circulating pumps, cooling towers, chilled water circulating pumps, cooling water and Chilled water piping with valves, accessories, fittings, supports, insulation as applicable, steam piping with fittings, supports, insulation, PRDS and associated Electrical items etc. has been envisaged. The chilled water produced in this central Chilled water plant will be circulated through the coils of individual air handling units for the respective air conditioned rooms/areas. This Central Air Conditioning System will be operated and controlled from the AC plant Control room DDC panels and two nos. Workstation PCs.
ii) Individual Water Cooled Precision Air Conditioners (PAC) will be provided for AHP Control room and DM plant Control Room, Office and Laboratory. Condenser Cooling water will be supplied to such PAC units from the Plant ACW system. Such PAC units will be operated and controlled from their built-in Microprocessor based Control console.
iii) Individual Air Cooled Precision Air Conditioners (PAC) will be provided for Switch Yard Control Room and CHP Control
room. Such PAC units will be operated and controlled from their built-in Microprocessor based Control console.
iv) Air Cooled Ductable Split/ Packaged Air Conditioners will be provided for Dining Hall of the Canteen Building and Administrative Building. These Air Conditioners will be operated and controlled from their built-in Microprocessor based Control Console/ hand operated Remote Control Panels.
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO SEC - 5
SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016 -91-
v) Air Cooled Non-Ductable Split Air Conditioners will cater to the AC requirement of ESP Control room, Weighbridge Control room, Fire Station Building Control room, Hydrogen Generation Plant Control room, AC plant Control room and
other small control rooms housing PLC panels. These Air Conditioners will be operated and controlled from their individual hand operated Remote Control Panels.
Compressed Air System:
For the proposed units Twelve (12) (6 Nos (5W+1S) of IA and 6
Nos.(5W+1S) of PA) compressors with 55 Nm3/min would be
provided. The instrument air compressors will be oil-free type,
and will be provided with individual air receivers to absorb
pressure pulsation and for acting as reserve supply of
compressed air to permit continued operation following failure of
the operating compressor until the standby one comes into
service. A desiccant-type dryer unit with 100% standby,
automatic regeneration facility etc. will be provided for each unit
for supply of clean, dry air to Control and Instrumentation
System. Compressor house with area of 90mX40m is provided.
The station service air requirement for normal cleaning
purposes, atomising air medium for warm-up guns and igniters,
motive power for burner drive mechanism, emergency drive for
air pre-heater (in case of regenerative type) etc. will be met
from separate plant-air compressors. The plant air compressors
would be identical to the instrument air compressors and would
run in a manner, similar to that described above for the
instrument air compressors. Capacities of all the instrument
and plant air compressors selected would be similar for both the
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO SEC - 5
SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016 -92-
phases, so as to achieve interchange-ability of parts.
Independent air receivers will be provided for each compressor.
Plant service air system will have suitable inter-connection with
the instrument air header for augmenting instrument air supply
in emergency.
Fire Protection System: For protection of the plant against fire, all yards and plant will
be protected by any one or a combination of the following
systems:-
a. Hydrant system
b. Automatic high velocity and medium velocity sprinkler system
c. HV & MV water spray (Emulsifier system)
d. Fixed foam system for HFO & LDO tanks
e. Portable and mobile chemical extinguishers
f. Inert gas flooding system for Control room, control
equipment area, inverter and battery rooms
The system will be designed as per the guidelines of Tariff
Advisory Committee (TAC) of the Insurance Association of India.
Applicable Codes and Standards of National Fire Prevention
Association (NFPA), USA, would also be followed.
In view of vulnerability to fire and it's importance in the running
of the power station, effective measures are to be taken to
tackle fire in the following susceptible areas :
i) The cable galleries, and
ii) Coal handling areas, mainly the conveyors, transfer points and tunnels.
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO SEC - 5
SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016 -93-
For containment of fire and preventing it from spreading to
cable galleries, unit-wise fire barriers with self-closing fire
resistant doors will be provided. The ventilation systems
provided in the cable galleries, would be so interlocked with the
fire alarm system that in the event of a fire the ventilation
system is automatically switched off. Also to avoid spreading of
fire, all cable entries/openings in cable galleries, tunnels,
channels, floors, barriers etc. would be sealed with non-
inflammable/fire resistant sealing material.
The source of water for the fire water pumps of the hydrant
system, water spray and sprinkler system etc. will be the water
with connection from cooling tower basin (to be used only
during extreme emergency). Two(2) electric motor driven fire
water pumps with one(1) diesel engine driven pump as back-up
for sprinkler system will be provided in the fire water pump
house. In addition to these, jockey pump sets, hydro-
pneumatic tanks, compressors, pipes and fittings as required
will be provided. The hydrant system will feed pressurised water
to hydrant valves located throughout the plant and also at
strategic locations within the power-house.
Automatic high velocity sprinkler protection system will be
provided for cable galleries, cable trenches/vaults, coal
conveyors etc. Automatic medium velocity sprinklers will be
used for protection of burner zone of boiler front.
Automatic type water spray (emulsifier) protection system
would be provided for the following equipment:-
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO SEC - 5
SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016 -94-
a. Generator transformers
b. Unit auxiliary transformers
c. Unit and Station transformers
d. Turbine oil storage tanks
Suitable fire detection system as necessary for all the above
mentioned fire fighting system with adequate supervisory
circuitry will be provided.
In addition to these, adequate number of portable and mobile
(wheel mounted) chemical fire extinguishers of foam and soda
acid type and carbon-dioxide type will be provided. Portable
units would be placed at suitable locations throughout the plant
area. The extinguishers may be used during the early stages of
fire to prevent spreading. Fire station building of area
(80mX25m) is provided for the power plant facility.
FIRE DETECTION & ALARM SYSTEMS:
A fire detection system as per National Fire Protection
Association standards recommended practices shall be provided
Manifestation of fire shall be sensed by the following methods:
� Photoelectric smoke detectors
� Multi sensor type smoke detectors
� Heat detectors (Rate of rise heat type or Fixed heat type).
Both the type of detectors shall be addressable from the
panel and operator interface.
� Infrared Ember Detector
� Non-electrically operated Fibre Optic type LHS Cable
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO SEC - 5
SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016 -95-
Piping, Valves, Fittings & Specialties:
The scheme of various systems such as, steam, condensate,
water, oil, air etc. have been explained above. Piping, valves,
fittings, hangers, anchors, supports, guides etc. would be
provided as required. All high pressure, medium pressure and
low pressure lines will be of proven quality and suitable for
conditions of operation encountered at the specific points.
Pipelines running outside the powerhouse will be routed over
trestles as far as practicable in order to avoid maintenance and
other problems encountered with trench piping and buried
piping. However, for any culvert crossing piping inside trenches
and for large diameter water lines buried pipes with proper
coating and water-proofing would be adopted.
Associated Facilities:
Repair Workshop :
The proposed station will have a well equipped workshop
housing adequate machineries. Besides, instrument, electrical
and maintenance shops are also envisaged. A repair shop for
mobile equipment and motor vehicle repair shop would be
developed. For heavy nature of maintenance, outside agencies
are to be deployed. Work shop of area (150mX70m) is provided
for the power plant facility.
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO SEC - 5
SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016 -96-
General Stores :
Both covered and open space as required for storage of various
materials required for construction as well as operation and
maintenance of the plant. While the construction stores will be
temporary, the other stores will be permanent. Consumables,
tools and tackle and other relevant items required for the
project will be extended. Due to remote location of the plant,
the stores would be well-equipped to handle any contingency
situation. Accordingly, stores planning would be done for the
project. Stores of area 100m X 75m with open yard 110m X
100m is provided for the power plant facility.
The stores will broadly have the following divisions to house
material of different categories:
1. Heavy materials store will house boiler tubes of various
sizes, boiler and auxiliary parts, turbine heavy parts,
stainless steel plates, conveyor belt and other coal handling
equipment spares, dozer spares, motors, transformer
windings, fire fighting equipment, insulators and hardware
connectors, copper and aluminium conductors and similar
heavy items.
2. Mechanical, electrical and instrument stores will accommo-
date small spare parts for mechanical and electrical
equipment and instruments respectively.
3. Fast moving spares viz. electrodes and welding materials,
blow lamps, bulbs and light fittings, grease, soap, battery,
cotton waste and cloth, brooms, motor vehicle spares, gas
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO SEC - 5
SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016 -97-
cylinders, gloves, aprons, safety belts, goggles, ropes, refill
for the fire fighting equipment etc. will be stored in a
separate godown.
4. Chemical stores will house alum, lime, morpholin/hydrazine
resin, spirit and other chemicals required for steam, feed
water and condensate system and chemical laboratory.
5. A civil engineering godown will accommodate cement,
sanitary materials, filtering sand and filters, pipe and pipe
fittings etc. for water supply.
6. Refractories and lubricants will be stored under separate
covered sheds.
Open storage-yard will be provided to store structural steel,
plate materials, pipes, heavy castings, cable reels etc.
Suitable enclosures will be provided for storing the insurance
spares. Arrangements will be made for storing items like relays,
motors, instruments under controlled atmospheric conditions.
Condensate Polishing System:
The proposed 5 x 800 MW project will be provided with 100%
capacity condensate polishing system. Condensate polisher will
comprise four(4) demineralisers per unit each operating in
parallel. Any three(3) of these units will be capable of treating
the full condensate flow at boiler MCR condition. Condensate
polishing will ensure elimination of ammonia, silica, sodium or
potassium from the condensate before being recycled to the
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO SEC - 5
SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016 -98-
feed water system. During normal operation all the polisher
units will remain standby. In case of high condensate
conductivity, it will be pressed in service when three(3) of the
exchanger vessels will be working in parallel and the fourth one
will remain isolated from the system. The fourth vessel will act
as standby and will be brought into operation when regeneration
is required or during any emergency period. The polishing unit
would be located at the powerhouse building. The operation of
the condensate polishing system will be semi-automatic,
remote/manual.
The regeneration system will be external. For regeneration, the
resins from the exhausted exchanger vessel will be transferred
hydraulically to this facility located at DM plant and regenerated
resin sent back in the same way.
Chemical Laboratory & Testing Facilities:
Plant will be provided with Chemical laboratory, C&I laboratory
and Electrical laboratory with necessary test equipments,
considered for the satisfactory and continued operation of power
plant. A fully equipped chemical laboratory would be provided
near the DM plant building. The testing and calibration
laboratories for C&I and relay-metering will also be housed in
the same building. Necessary equipment and standard
instruments for chemical analysis of various items, testing of
electrical items and testing/calibration of instruments would also
be provided. Lab with an area of 35m X 20m is provided for the
power plant facility.
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO SEC - 5
SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016 -99-
Thermal Insulation:
Adequate insulation will be provided to reduce heat losses from
the equipment, piping and ducts and to ensure adequate
personnel protection in critical areas. Insulation would be so
selected that the covering jacket surface temperature does not
exceed the surroundings ambient temperature by more than
15K (15°C).
Pollution Monitoring System:
Monitoring of various environmental aspects is of prime
relevance in setting-up the proposed project. The following
aspects would be critically monitored:-
• To keep watch on the state of pollution • To generate data for predictive and corrective measures • To quantify environmental impacts
The important area requiring periodic/conditions monitoring
are:-
• Stack emission • Ambient air quality • Disposed water quality, if any.
Electronic smoke density analyser and gas analyser equipment
is proposed to be provided for continuous monitoring of
particulate matters at the outlet of ESP. Sample analysis of SO2
and other pollutants from chimney would be carried out. Waste
water would be checked for any harmful pollutants before
discharging to outfall.
An oil/water separation unit has been envisaged near fuel oil
day tank/pump house area in order to keep plant drains free of
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO SEC - 5
SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016 -100-
oil and to reclaim waste oil as far as practicable. Oil thus
separated would be returned to the fuel oil tank after passing
through plate settlers and used or disposed off by incineration.
Coal Handling and Ash Handling Plants will be equipped with
dust extraction/suppression system to combat fugitive dust.
5.5 Electrical System & Equipment
Generation System & Power Evacuation:
The Proposed power plant will have 5x800 MW at Kadaladi
Taluk, Ramanathapuram Dist. in Tamilnadu with turbo
generators rated at 27 kV level. These units will be connected
to 765 kV GIS switchyard at the plant area as shown in the
layout for evacuation of generated power. Also 230KV GIS
switchyard is envisaged to receive start up power in case 765
KV system is not ready to supply start up power The total land
area provided for the Switchyard is around 102 acres.
In compliance with latest CEA Manual on Transmission Planning
Criteria – 2013, considering the large amount of power to be
evacuated, power evacuation from the plant is envisaged at 765
kV level. In order to meet N-1 single contingency condition
stipulated as per CEA planning criteria, minimum of two double
circuit lines will be required to evacuate the net available power
from the plant. Power from this switchyard would be evacuated
through two (2) 765 kV double circuit lines to the nearest 765
kV pooling station, (location to be decided by TANTRANSCO the
local STU). The Start-up power shall be received through station
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO SEC - 5
SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016 -101-
switchyard connected to 765 kV grids. The power from grid shall
be received through Generator Transformer (GT) and Unit
Transformer (UT) to feed the station bus during start-up
operation. The Generator circuit breaker is envisaged between
Turbo generator and Generator Transformer. The bus bar
configuration of the 765 kV GIS switchyard will be one and half
circuit breaker arrangement as stipulated by CEA for better
reliability. The following circuit bays are envisaged in 765 KV
Switchyard:-
Five (5) – 765 kV circuits for generator transformers
Two (2) – 765 kV double circuits for outgoing lines
Two (2) – Spare bay (one equipped and another for future)
Five (5) – Shunt reactor bay (Qty to be decided during detailed
engineering)
Besides 765KV GIS, 230 KV GIS is also envisaged in order to
meet the station start up power requirement in case 765 KV grid
system is not ready to supply start up power. The station
transformers shall be connected to 230 KV system. Double bus
arrangement with buscoupler is envisaged for 230 KV system.
The following circuit bays are envisaged in 230 KV GIS
One (1) no Line in feeder
One (1) no Line out feeder
One (1) no Buscoupler
Five (5) nos station transformer feeder
One (1) no spare transformer feeder
The rating and requirement of line reactors, shunt reactors and
NGR for reactors will be provided in 765KV GIS as per system
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO SEC - 5
SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016 -102-
studies requirement to be done during detailed engineering
stage.
A control room will be located in the switchyard premises to
house switchyard control, metering and protective equipment.
OFGW will be installed in the switchyard for reliable
communication and carrier aided distance protection of 765 kV
and 230KV system remote end breakers.
In the powerhouse each generator will be directly coupled to the
respective steam turbine. The generator will be a two-pole,
three-phase unit rated for 800 MW at 0.85 p.f. lag. 50 Hz. The
nominal voltage rating will be 27 kV or as per manufacturers’
standard with variation of ±10% in voltage, 50 Hz -5% +3%,
3-phase. The excitation system will be brushless type or static
excitation (based on the proven practice of Generator OEM) and
will be selected for an ideal rate of response, accuracy and
sensitivity during normal as well as transient state of operation.
The generator will be connected to the 765 kV GIS Switchyard
through three numbers single phase 330/264/198 MVA,
(765/�3kV)/27 kV, generator transformer (GT). The GT shall be
with OFAF/ONAF/ONAN type cooling and Vector group of YNd11.
The total capacity of each GT will be thus (3x330) 990 MVA. The
connection between GT low-voltage terminals to the generator
will be done by isolated phase bus duct and high voltage
terminals of GT will be connected to the switchyard bay through
ACSR overhead conductors. The fault level of the switchyard 765
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO SEC - 5
SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016 -103-
kV shall be 50 kA for 1 sec at 765 KV level and the switchyard
shall have Main Bus I & II with 5000 Amps rating. The fault level
of 230KV system shall be 40KA for 1 sec and the main bus1 and
main bus 2 rating shall be 2000 Amps
Power Supply Arrangement to the Unit & Station Auxiliaries:
Three voltage levels viz. 11000 V, 6600 V and 415 V have been
envisaged to supply power to unit and station auxiliaries. The
drives for auxiliary equipment, having capacity above 200 kW
up to and including 1500 kW will be fed from 6.6 kV system and
those with capacity above 1500 kW will be fed from 11 kV
system. All motors rated 200 kW and lower will be fed from 415
V systems. Suitable HV and LV switchgears with suitable
auxiliary transformers, as described below, will be provided for
operation of these motors.
Scheme of the electrical power distribution arrangement to the
plant auxiliaries have been shown in Drawing No.15Z03-005-
DWG-E-001 (3 Sheets).
During normal power generating condition of generators, the
power supply to unit auxiliaries will be fed from the generator
terminal through Unit Transformer (UT) with GCB closed. During
unit start up and when generator is not in operation the supply
will be fed from the grid through Generator Transformer (GT) &
Unit Transformer (UT) with GCB open condition. Two (2) nos.
unit transformers have been envisaged per unit. Each UT will be
directly connected to generator bus duct and will be rated for
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO SEC - 5
SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016 -104-
40/32 MVA, 27 kV/11.5 kV and with OFAF/ONAN cooling, Dyn1
vector group. However the actual rating shall be decided during
detail engineering.
Power requirement for unit start-up or shutdown and station
auxiliaries will be drawn from 765 kV Switchyard/Grid through
Generator Transformer (GT) & Unit Transformers (UT). The
station transformer (ST) will be provided with winding of
adequate MVA and voltage ratings and Vector Group as Unit
Transformer. ST will act as a standby back-up in case of UT
fails. Also the start up power can be drawn from 230KV system
in case 765 KV grid system is not ready.
The power supply to unit auxiliaries like ID fan, FD fan, PA fan,
BF pump, CW pump etc. will be from 11 kV Unit Switchgear fed
by UT. Balance HV motors like Mill, CE pump, DMCW pump,
IA/PA compressor etc. will be supplied from 6.6 kV Unit
Switchgear fed by 11/6.6 kV, 16MVA Unit Auxiliary Transformer
(UAT). (UAT rating shall be decided during detail engineering).
The station auxiliary loads will be fed from 11 kV Station
Switchgears located in the powerhouse. Separate 6.6 kV and
415 V switchgears will feed the loads for Coal Handling Plant,
Ash Handling Plant, Water Treatment Plant etc., located in the
respective plants as required. These 6.6 kV switchgears will be
supplied by 11/6.6 kV Station Auxiliary Transformer (SAT) of
suitable rating as required.
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO SEC - 5
SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016 -105-
The 11 kV sides of Unit Transformer (UT) and Station
Transformer (ST) will be connected with the associated
switchgears through adequately rated segregated-phase bus
duct. The 11KV station switchgear is connected to the unit
switchgear by the Tie feeder. The auto bus transfer scheme is
envisaged (BTS system) for closure of tie feeder in case power
supply failure on the unit board.
OLTC panel is envisaged in the switchyard control room for
remote operation of station transformer on load tap changer.
The 6.6 kV side of Unit Auxiliary Transformer (UAT) & Station
Auxiliary Transformer (SAT) will be connected with the
associated switchgears through adequately rated segregated-
phase bus duct.
For PMCC/PCC switch board of 415 Volt system, 11 kV/415
Volts, 3-phase, 50 Hz, dry-type LV auxiliary transformers rated
2.5 MVA, 2 MVA, 1.6 MVA and 1MVA will be provided as
required. The HV side of these transformers will be connected to
11 kV buses by cables and the LV side will be connected to the
respective LV Switchgear/Power Control Centre (PCC)/Power-
cum-Motor Control Centre (PMCC) through non-segregated
phase bus duct.
The 11 kV system will be designed for 50kA fault level with short
time rating 3 seconds & 6.6 kV systems will be designed for 40
kA fault level with short-time rating 1 second. The 415 V
systems will be designed for 50 kA fault level with short-time
rating 1 second.
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO SEC - 5
SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016 -106-
Emergency Power Supply System:
415 V emergency power supply system has been envisaged to
provide power to essential auxiliary loads required to permit a
safe shut down of the unit in the event of a plant blackout. In
addition, emergency power will be provided for auxiliaries and
services required for personnel safety and equipment safety
during the blackout. In order to meet the above requirement
Six (6) nos. 1500 kVA diesel generator sets will be installed,
considering each DG sized for one unit and the Sixth DG set will
act as common standby. The land area allocated for the DG
house is around 15m X 10m.
Plant DC System:
220 V Plant DC system has been envisaged for reliable power
supply to those loads, which are required to function for
security, protection and safe shutdown of plant in the event of
failure of normal AC power supply. Each unit will have two (2)
220 V battery set of adequate capacity. DC power supply
system for each unit comprises:
� 220 Volt DC batteries
� Battery charger (float and float-cum-boost charger)
� DC distribution and sub-distribution boards
Battery will be Lead Acid PLANTE type or Nickel-Cadmium (Ni-
Cd) type and the battery will be sized for one (1) hour back up
time subsequent to tripping of generating units. Separate
battery sets will be provided for 765 kV GIS switchyard, coal
handling system, plant water system and AHP.
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO SEC - 5
SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016 -107-
Uninterrupted Power System:
Two(2) sets of UPS systems of continuous duty have been
envisaged to supply regulated, filtered and uninterrupted 240 V,
50 Hz, single phase power to critical AC loads like
Instrumentation control system, PLC system during normal as
well as emergency conditions. UPS battery will be sized for at
least sixty(60) minutes back up on failure of normal AC supply.
A separate UPS system of continuous duty has been envisaged
for 765 kV GIS switchyard control room Substation Automation
system, coal handling, ash handling and plant water system.
Control of Electrical System:
The Operation and Control of Electrical system/equipment have
been envisaged from the Central Control Room through
Operator work stations.
Control and operation of 765 kV GIS switchyard will be done
from switchyard control room. Accordingly, the 765 kV GIS
switchyard will be provided with complete sub-station
automation system with connectivity to plant DCS system.
DG sets will be controlled from AMF panel in DG room. Remote
control provision will also be provided in plant DCS.
Control panels for service system like coal handling plant, ash
handling plant, plant water system, etc. will be located in the
respective control room.
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO SEC - 5
SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016 -108-
Protection & Metering System:
The necessary protective relaying system based on state of art
numerical technology according to established norms shall be
provided for EHV switchyards, over head lines, generators,
transformers, motors, auxiliary system etc., to minimize
damage to equipment in case of fault and abnormal conditions.
Numerical relays with 100% redundancy will be used for
protection of critical electrical equipment and non critical
electrical items the numerical relays with out redundancy shall
be provided.
Plant electrical parameters will be metered to the extent for
proper operation and monitoring of plant conditions. Separate
check meters and main meters will be provided in 765 kV and
230KV GIS switchyard line feeders for tariff metering of import
and export power.
Illumination System:
Suitable illumination system will be provided to facilitate normal
operation and maintenance activities and to ensure safety of
working personnel. Required illumination levels in different areas
will be as per standards/code of practice. Power supply for the
illumination system will be derived from the following sources:
� Normal AC System – to be powered from 415 V normal AC supply
� Emergency AC System – to be powered from 415 V emergency DG set
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO SEC - 5
SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016 -109-
� Emergency DC System – to be powered from 220 V plant DC system
Illumination system will consist of lighting transformers, lighting
distribution boards, indoor & outdoor type lighting panels,
different types of lighting fixtures suitable for different plant
areas, lighting cables & wires, etc.
Intercommunication System:
Two-channel voice communication system with ‘Paging’ mode as
well as ‘Private’ mode has been envisaged for plant
intercommunication. A microprocessor based Digital Electronic
Private Automatic Branch Exchange (EPABX) is envisaged for the
telephone communication system.
Grounding & Lightning Protection System:
Comprehensive grounding system will be provided in the power
plant which will be achieved by ground mat buried at one (1)
meter depth below ground and provided with ground electrodes
at suitable intervals or as per IEEE80. All metallic parts of power
plant and switchyard equipment/structures will be connected to
the ground mat.
Generator neutral will be grounded through distribution
transformer and secondary loading resistor. 11 kV & 6.6 kV
systems will be high resistance grounded to limit the fault
current to the order of 300 Amp. 415 V power supply system
will be solidly grounded. DC system will be ungrounded.
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO SEC - 5
SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016 -110-
For grounding of electronic equipment, a separate earthing
system totally isolated from the power equipment earthing mesh
will be provided.
Lightning protection system will be installed for protecting the
buildings/structures against lightning discharge. This would be
achieved by providing lightning masts/shield wires on stacks,
NDCT, powerhouse building, floodlight towers, towers in
switchyard etc. and connecting them with the ground grid.
Construction Power
It is envisaged that about 10 MVA construction power may be
required at 415V level when construction activities takes place
simultaneously in all unit and station areas of the plant.
TANGEDCO shall provide two single circuit 33 kV overhead lines
from KADALADI 110KV/33KV SS up to construction site.
At construction site suitable 33/11KV substation with 11KV/415V
distribution network with transformers and Distribution board
shall be provided to cater the construction power requirement.
5.6 Control & Instrumentation
The Control and Instrumentation System envisaged for the
project would be designed using microprocessor based state-of-
the-art technology with adequate redundancy to ensure
� Safe, efficient and reliable operation of the plant under all operating and plant load conditions for the entire plant life.
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO SEC - 5
SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016 -111-
� Minimum human supervision and intervention in the plant operation.
� High Mean Time Between Failure (MTBF) and Low Mean Time To Repair (MTTR) of the Plant Equipment/System.
� Flexibility for ease of maintenance and plant operation and modular expansion capability.
� High degree of automation at all stages of operation.
� Diagnostic capability
Control & Operational Philosophy:
The Operation and Control of Main Plant Equipment of the
project have been envisaged from the Central Control Room.
One control room is envisaged for two units for centralised
control and monitoring of unit equipments.
a) One control room is envisaged for control and monitoring of
Unit 1 & 2 to be located between Unit 1 & 2
b) Second control room shall be used for control and monitoring
of unit 3 & 4 to be located between Unit 3 & 4
c) Third control room shall be used for control and monitoring of
Unit 5 and common monitoring of CHP, AHP, Water treatment
plant, etc to be located adjacent to Unit 5.
A Distributed Control System (DCS) have been envisaged for
the operation and control of Steam Generator (SG), Turbine
Generator (TG) and its auxiliaries.
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO SEC - 5
SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016 -112-
Stand-alone Control System using Programmable Controllers
(PC) have been envisaged for Coal Handling Plant, Ash Handling
Plant (AHP), Pre-water Treatment Plant and DM Plant from the
respective Local Control Rooms/Local Control Panels. Hardware
interfaces shall be established with the DCS for remote
monitoring of critical parameters.
The overall control of the plant shall be carried out from three
control centres and each are divided into following sub plant
controls.
a. All control activities involving steam generators, turbine
generators, electrostatic precipitator and other associated
equipment from unit control room (DCS based system).
b. All control activities involving coal and ash handling plant,
pre-water treatment plant, DM plant from local control room
(PLC based system & interfaced with DCS system for remote
monitoring).
c. The control & monitoring of 765 kV switchyard shall be from
Switchyard control room located near switchyard (SCADA
based system). However monitoring of important parameters
shall be provided in each Main plant control room.
Main Plant & Equipment :
Steam Generator (SG):
The operation and control of the Steam Generator (SG) shall be
achieved through Man-Machine Interface (MMI) Station from
Central Control Room.
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO SEC - 5
SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016 -113-
The various controls such as Furnace Draught, Drum Level, HP
Bypass, Superheater Temperature, Combustion Control etc.
shall be performed through dedicated Controllers in the
Distributed Control System (DCS).
All sequential operations,controls & boiler protection trip for
Boiler Auxiliaries viz. FD Fan/ID Fan/PA Fan, coal mills etc. have
been envisaged through MMI Station and dedicated Controllers
of DCS.
Turbine Generator & its Auxiliaries:
A separate and dedicated microprocessor based ‘Control System’
have been envisaged for the protection of the Turbine and
Control of the Turbine Governing Valves, Automatic Turbine
Run-up, Turbine Stress Evaluator, Automatic Turbine Testing
etc. All other Controls viz. LP Bypass, Lube Oil Pumps, Control
Oil Pump etc. will be implemented in DCS. Turbine Supervisory
System shall be provided along with suitable link to DCS for
monitoring. All sequential operation, necessary interlock
function and Auto/Manual operation of start/stop of the drives/
pumps shall be performed through MMI station of DCS.
The start/stop operation and control of all other major
equipment viz. Condenser, CEPs, LP Heaters, Deaerator, BFPs,
HP Heaters etc. shall be achieved through the MMI Station.
Control/sequential logic function and turbine trip shall be
implemented in DCS. All major drives shall have local start/stop
facility for testing purpose. BFPs shall be provided with local
gauge board and vibration monitoring system. The operation
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO SEC - 5
SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016 -114-
and control for the Common Auxiliaries of the station shall be
achieved through dedicated Controllers and HMI in DCS.
Functional Description of the Monitoring/Control System :
General Technical Requirements :
All equipment, system and accessories considered shall be from
latest proven product range of established manufacturers and
shall conform to applicable national and international standards.
Adequate measures shall be taken into consideration to make
the system fail safe such that loss of signal, loss of power supply
or failure of any component will not lead to hazardous conditions
as well as prevent occurrence of false trips.
Distributed Control System (DCS) :
A latest proven microprocessor based state-of-the-art
Distributed Control System has been envisaged for the project.
Control System shall be open architecture type to make the
system user friendly. Adequate redundancies would be provided
at all possible levels to achieve highest system availability.
The proposed Distributed Control System shall comprise
� Functionally Distributed Controllers, Communication
Processors, I/O Modules, Local Bus, Power Supply, etc.
� The task and duties to be performed are
� Sequential Control/Close Loop Control related to SG, TG
and its auxiliaries.
� Acquisition of data and its validation
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO SEC - 5
SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016 -115-
� The sequence and interlock functions performed by DCS
would be functionally arranged in groups/subgroups for
auto operation
� Real Time Stamping for the inputs related to sequence of
Event Recording
� MMIs and Controllers shall be connected by bi-directional
high-speed redundant data hi-way
� Man-Machine Interface Station and its peripherals shall
perform the following:-
� Operational facility for auxiliaries of SG, TG and balance
of plant
� Displays like Mimic, Loop, Graphics
� Generation of Reports & Annunciation
� Performance and efficiency calculation
� Self-Diagnosis
� Fall back features of MMIs
� Interfacing with Large Video Screen (LVS) in Control
room
� The system shall be provided with User friendly operating
and application software.
� Dual Redundant Programmable Controllers (PC) for various
offsite plants shall be provided.
Steam & Water Analysis System (SWAS):
SWAS shall be designed for continuous monitoring of Steam and
Water quality at salient points of the cycle based on the
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO SEC - 5
SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016 -116-
International Standards. SWAS shall perform the following
functions.
a. Sample handling to perform pressure and temperature
conditioning of the sample to suit the analyzer probes.
b. Analysis of pH, Conductivity, Dissolved Oxygen, Silica etc. at
various points to monitor and control the steam and water
quality at the desired level.
c. Monitoring, recording, annunciation of various parameters
shall be provided for remote DCS as well as for local SWAS
Panel.
All these SWAS related equipment would be housed in the SWAS
Room.
Continuous Emissions Monitoring System:
Continuous Emissions Monitoring System has been envisaged to
meet the statutory requirement. PC based Continuous Emissions
Monitoring System shall be envisaged along with remote
transmission facility through serial link. The particulate matter,
SO²,NOx, Hg shall be monitored in Flue gas at stack as
stipulated by MOEF
Rotating Machinery Supervisory System:
Vibration Monitoring System for major rotary equipment shall be
provided as per the manufacturer’s recommendation. These
vibration and supervisory systems will be complete with
sensors, junction box, special cables, transmitters, analysis
system with monitors & communication capabilities with DCS.
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO SEC - 5
SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016 -117-
Field Instruments:
Field Instruments shall be suitable for area in which these are
located. In general, field instruments shall be weatherproof,
dust tight and corrosion resistant. Field instruments shall be
suitably grouped or clustered area-wise and shall be terminated
in local junction boxes.
Process Transmitters :
All the Process Transmitters will be 2-wire ‘SMART’ type.
Process Gauges :
Pressure Gauges (Bourdon/Bellows type), Temperature Gauges
(Mercury filled-in type with SS armoured capillary/Bimetallic),
Level Gauges (Transparent and Reflex type) etc. shall be
provided for local monitoring.
Temperature Sensors :
All Temperature Sensors will be ‘Duplex’ type, bearing & winding
temperature measurement shall be provided for HT drives as
per the manufacturers’ recommendation.
Process Switches :
For critical alarm and protection/interlock functions direct
process switch contacts will be used.
Flow Elements :
For the measurement of low-pressure flow for clean fluids,
concentric square edge orifice plates shall be provided. Flow
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO SEC - 5
SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016 -118-
Nozzles shall be provided for measurements to control for high-
pressure water/steam service. For fuel oil service, positive
displacement/target-type flow-meters/Vortex flowmeters shall
be used. Aerofoils, annubars and venturies shall be used for air-
flow measurement.
Final Control Elements :
Generally pneumatic type Control Valves shall be provided
except for critical functions where hydraulic type actuator shall
be considered.
Cable & Accessories :
Necessary cables including prefabricated cables, data highway
cable, instrumentation cable, compensating cable, control cable
etc. shall be included. Generally cables will be overall screened,
and with FRLS outer sheath. All interconnecting cables between
cabinets will preferably be prefabricated with connectors at both
ends.
Panels & Cubicles :
Operator’s Console comprising workstations, CRTs would be
provided in the each Central Control Room. The system
cabinets containing hardware would be placed in the Control
Equipment Room. Local panels would be provided for local
monitoring and interfacing of Operators whenever needed.
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO SEC - 5
SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016 -119-
Erection Hardware :
Erection hardware including all process connection and piping
materials like impulse pipe, manifolds, fittings, pneumatic line
tubes and pipes along with necessary fittings, junction boxes,
cable accessories like glands, conduits, trays etc. shall be
provided.
Instrument Insulation Criteria :
All instruments shall have clear access for maintenance,
removal, lay down, calibration etc.
All readable instruments shall be clearly visible unassisted.
Access platforms shall be provided for easy access of
instruments, valves and actuators for maintenance.
Spares & Consumable:
All electronic cabinets shall have installed spares to the extent of
10% to allow expansion and modifications. In addition, 20%
spare capacity is to be provided in the form of rack space for
augmentation & spares shall be judiciously distributed.
All commissioning spares and consumable shall be supplied as
part of main package. This is in addition to spare parts to be
included for three (3) years’ of trouble-free operation.
All failure-prone items shall be clearly identified and adequate
spares are to be provided for such items.
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO SEC - 5
SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016 -120-
Tools & Tackle:
All special tools and tackles shall be considered.
Utility :
In general, the electronic panels shall receive 240 V AC 1-Phase,
50 Hz at the desired locations. Two nos UPS adequately rated
with 1 Hr battery back-up facility shall be provided for the
critical systems.
Separate instrumentation earthing shall be provided for
protection of the system.
Ambient Air Quality Monitoring system (AAQ):
The comprehensive ambient air quality monitoring system with
necessary sample collection system and probes shall be
provided in the project area. The location of the monitoring
station shall be decided taking into consideration the upwind
direction, predominant downwind direction, habitation and other
sensitive receptors. AAQ shall include PM10, PM2.5, SO², NOx,
CO and Mercury measurement and recording.
5.7 Plant Layout
The area identified for locating the grass root power station is
spread over 902.36 Ha of land and is located at a distance of
nearly 65 km South-East of Ramanathapuram town. The plot has
a ECR on the Southern and would be entrance of the road traffic
to the station. The station conceived would be of 4000 MW
capacity five units of 800 MW each deploying state-of-the-art
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO SEC - 5
SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016 -121-
technology with conventional layout. The plant layout of the
proposed thermal power station within the identified space is
shown in Drawing No. 15Z03-004-DWG-M-003.
This layout shows a single terrace plot plan. Thus when the
contour survey will be available a multi-terrace layout will have
to be developed.
A conventional layout for the boiler and the turbine has been
suggested for the power plant with the axis of the TG set
transverse to that of boilers. As such, the plant is laid in East-
West direction as per the shape of the plot. The turbine bay is
followed by the heater bay, the electrical bay, the boiler proper
with side mill bay configuration, electrostatic precipitators and
lastly the chimney. The main plant area houses the turbine
building, steam generator, 765 kV GIS switchyard, circulating
water system, water treatment and DM plant, coal handling
system with Railway siding and the ash disposal system. The
disposition of the different elements has been decided on the
basis of their functional inter-relations and the direction of
incoming or outgoing materials.
Unitised concept has been followed in the plant design as far as
practicable. The unloading-cum-erection bays are considered at
the beginning of the powerhouse building while the coal
conveyor entry planned suitably for side mill configuration.
Since the units would be implemented with a time gap of three
(3) months in between, this will not cause any hindrance in
construction of later units. The main power block with the
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO SEC - 5
SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016 -122-
switchyard is located along the north south axis of the plot with
the direction of evacuation to the south. Water treatment
facility will be located on the south-east of the power block. It is
proposed to deploy wet type Natural Draft Cooling Towers in
the recirculating cooling water circuit. The cooling towers are
located to the west of the powerhouse building with a designed
gap, to optimise on length of C.W. piping.
The coal yard along with other auxiliaries would be located on
the north of the plot. Four pair of stacks of coal storage with
handling facility have been planned at this location. The coal
yard will be equipped with four stacker-cum-reclaimers. Coal
stack lies in East-West direction. These would cater 30 days’
requirement of coal for the station.
Three Track Hoppers have been envisaged for receiving rake
loads of coal. Merry-go-round system is envisaged for the
proposed project. However, details of coal transportation and
unloading facilities would be finalised based on study reports.
The power plant along with the area earmarked for auxiliaries
and accessories would be located within the common security
wall of the complex. The access road would enter the plant from
the south, which is connected to the ECR. Another access for
receiving material is shown at the north-eastern end and will
lead to FGD material handling area, ash silos and fuel oil area.
The Administrative Building (60m X 20m), for the entire
complex is located at the entry to the plant and would have a
boundary wall around with suitable entry. Service building (75m
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO SEC - 5
SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016 -123-
X 75m) provided adjacent to the TG building All the senior
executives of the power station will be located in this building.
The entry to the Power Plant will be flanked by security gate,
time office. It is proposed to construct one Crèche (24m X
11m), Dispensary(30m X 10m) and canteen (30m X 30m)
facility.
Provision of disposing fly ash by trucks from ash silos located
on the western side of the plot is kept for gainful usages. The
layout considers green verge as per MoEF norms.
5.8 Civil Engineering Aspects
Plant Grading:
The elevation of the selected site is about 6 m above MSL. This
may be further worked upon when survey map of the plot is
available and shall be duly addressed in DPR stage. Leveling
and grading shall be carried out by selected cutting and filling
of existing ground surface and earth. The cutting and filling
requirements should balance each other to avoid earth from
borrow pits as far as possible. Different grade levels may be
adopted for different areas.
Soil Characteristics & Foundations:
The soil investigation of the plot is yet to be conducted. It was
noticed during reconnaissance visit to the area, the top cover is
composed of moorum followed by fragmented rock underneath.
Detail soil investigation of the plot identified is necessary for
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO SEC - 5
SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016 -124-
deciding on the type of foundation. For the purpose of the
report, raft foundation with RC raft has been considered.
Seismic Consideration:
The power station area is located in Zone-II as per the
demarcation of IS:1893-2002 of Indian Code of Practice.
Analysis and design of structures would be carried out
accordingly taking into consideration the factors related to soil
characteristics and importance of the structure together with
the basic seismic co-efficient as per provision of Indian Code.
Wind Conditions: The maximum wind pressure including winds of short duration
as specified in Indian Standard Code of Practice IS:875-1987
(Part-3) will be adopted for the zone where the proposed power
station is located. The site is located in the zone as per above
standard having design wind speed of 40 m/sec.
The provision of Indian Standard Code of Practice IS:875 with
appropriate co-efficient for variation of heights and shape will
be considered for detail design.
�
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO SEC - 6
SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016 -125-
ENVIRONMENTAL ASPECTS 6.1 Introduction
The selected plant site is encompassed by the villages
Tharaikkudi, Kannirajapuram and Narippaiyur villages of
Kadaladi Taluk, Ramanathapuram District. The site is around
2.3KM from sea coast line and at a distance of 65km from
Ramanathapuram town. The area has typical tropical climate
with hot summer and moderate winter.
Supply of electricity is a basic need to support modern society
and sustenance of economic and commercial activities. Imported
coal from Indonesia any other country and Indigenous coal from
Talcher, Odisha. Electricity generated in this power project would
be transmitted to State Grid. Availability of quality power on
sustained basis at a competitive price would be the main focus of
the project. High investment in infrastructures together with
availability of power in the area would attract other ancillary
industries to be set up in the vicinity which in turn would have
spin off effect on the community at large.
Besides Kadaladi Talk in Ramanathapuram District is a very
backward area and prone to communal disturbances, a power
plant of this 5X800 Mw capacity will bring in lot of employment
opportunities both direct and indirect and will pave away for
communal harmony in this area.
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO SEC - 6
SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016 -126-
The effect of the proposed project on environment should be
seen in the broader perspective of overall impact on the
neighborhood. There are no archeological monuments within
25km radius of the proposed sites. The site does not include
any forest land. Three Bird sanctuaries are located in the
vicinity Melselvanur-Keelselvanur bird sanctuary at around 17
km, Chitrangudi bird sanctuary and Kanjirankulam bird
sanctuary at around 22 km & 20 km respectively from the
selected site (Site-B). The GOMNP (Gulf of Mannar National
park) Vembar zone Uppu Tanni Tivu is around 11 km and
Thoothukudi zone kariashuli Tivu is around 23 km from the
selected project site. The site falls within the buffer area of the
GOMBR (Gulf of Mannar Biosphere Reserve). Further
assessment on environmental impacts and the requisite
management plans shall be pointed out in a separate EIA/EMP
study. The tentative location of intake and outfall is around 12
km and 19km away from the Uppu Tanni Tivu and Kariashuli
Tivu in Gulf of Mannar. The location details are included in the
Site Location Map of the proposed Thermal Power Plant
Drawing No. 15Z03-004-DWG-M- 002 (sheet 2 of 2).
Industrial growth is always associated with some effects on
environment. Attempts will, however, be made both at macro
level as well as micro level to minimise detrimental effect of the
proposed project on the surrounding area. The proposed power
station would be equipped with state-of-the-art pollution control
devices to bring down the emission/discharge of pollutants
within the acceptable norms of the country.
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO SEC - 6
SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016 -127-
It may be noted that the project area is vacant land without
agriculture and free from R&R issues. As there is no habitation,
no major eviction is involved. Project authorities would make
adequate arrangement for rehabilitation and resettlement, if
required as per the R&R norms laid down by the state
government. Separate arrangement to address corporate social
responsibilities (CSR) would be taken up by the project
authority (For CSR activities the value considered is not less
than 0.4% of the project cost).
6.2 Environmental Pollution from a ThermalPower Plant and Controlling Measures
To evaluate the effect of the proposed project on the
surrounding environment, various factors such as population
distribution in the vicinity, type of land use, possibility of
pollution from various sources etc. would be taken into
consideration.
� Optimum blend of coal to reduce the consumption.
� Super Critical technology to have higher boiler efficiency
and reduced GHG emission.
� Closed cooling water system with cooling towers
envisaged, thus reducing significantly the makeup water
requirement for the plant.
� Low NOx Burners and provision of Selected Catalytic
Reduction (SCR) for NOX control
� ESP to minimize the PM emissions
� Stack of height 275 m to get better flue gas dispersion.
� Provision of FGD for SOX control
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO SEC - 6
SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016 -128-
� Dust Control System to minimize the fugitive dust
emission dust extraction / Dust suppression system in
CHP.
� Provision of wind shield around coal stock yard
� It is proposed to use closed trucks for fly ash
transportation in order to avoid dust nuisance. To reduce
the dust nuisance while loading the ash into the trucks
from fly ash and bottom ash silos, the ash is conditioned
with water spray.
� Water sprinkling system to be envisaged in the ash
disposal area and Gypsum disposal area to restrain flying
of fine to atmosphere.
A thermal power station utilising coal as its source of energy
may pollute the environment in a number of ways. The major
pollutants likely to affect the environment of the neighborhood
are:-
a. Suspended particulate matters (stack emission & material
handling plant)
b. Toxic gases viz. SOx, NOX (stack emission)
c. Thermal pollution (stack, cooling tower etc.)
d. Liquid effluent from plant services, power house drains, oil handling run off, run off from coal pile area, DM & CPU plant regeneration waste, Sea water clarifier sludge, Side stream filter backwash waste, ash pond run off and domestic waste.
e. Noise generated during plant operation
f. Dust emission in CHP and ash generated by burning fuel.
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO SEC - 6
SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016 -129-
The various pollution control measures envisaged for the
proposed project are as follows:-
i) Emission from Stack
Deployment of supercritical technology in the steam
generator ensures lesser specific fuel consumption vis-à-vis
generation of particulates, NOx and SOx compared to sub-
critical technology. Since ash content of the fuel is
expected to be in the range of 26% (considering worst
coal), a sizeable quantity of fly ash in the form of
particulate matter would be generated. An efficient
electrostatic precipitator will be provided to limit the
emission of particulate matters to 30 mg/Nm3 (MOEF
norm). The design would have provisions to augment and
ensure lesser emission in the event of change of statute.
High two twin-flue and one single flue stack are proposed
to limit ground level concentration of SOx, NOx, etc. within
acceptable limits by proper dispersion. With a properly
designed furnace and burner system, generation of CO and
NOx would be minimised.
Heat loss through the stack is only about 8-10% of the
total heat input to the furnace. This is nominal when
compared with the capacity of earth as the heat sink and
this would be adequately dispersed with the plume from
the high stack. Moreover, majority of the heat in cooling
tower is rejected in the form of evaporation loss. This does
not cause any appreciable thermal pollution to the
surrounding area.
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO SEC - 6
SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016 -130-
ii) Liquid Effluent from Water Treatment & Other Areas
The heat cycle make-up water requirement under stabilized
condition for the 5 X 800MW power station would be of the
order of 125 m3/hr of demineralised water. The
demineralising process would generate alternately acidic
and basic effluents after regeneration of such type of
exchangers. These effluents would be neutralised in a
neutralising basin where proper neutralising arrangements
for the effluent fluids would be provided. The neutralized
effluent water would be discharged into the equalization
basin termed as Guard Pond. In Drawing No.15Z03-006-
DWG-M-009 waste-water generated from the plant and
their treatment scheme are shown.
In the recirculating cooling water system, the make-up
water would be sea water. There will be blow down from
the circulating cooling water system. This blowdown would
largely be utilised in ash handling system. Sidestream
filtration shall be envisaged to control the Total suspended
solids (TSS) level at sea outfall in order to meet the MOEF
norms.
Other wastes from the processes include clarifier sludge &
side stream filter backwash sludge waste which would be
sent to sludge pond/pit and clean water as overflow would
go to clear well and sludge would be pumped to ash pond.
Other wastes from the processes like CPU regeneration
would be neutralised in a neutralising basin where proper
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO SEC - 6
SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016 -131-
neutralising arrangements for the effluent fluids would be
provided. The neutralized effluent water would be
discharged into the equalization basin termed as Guard
Pond in Effluent treatment plant. AHP seal water system
drains, waste from floor cleaning of plant area would be
discharged into the Guard pond.
In the power plant, some specific locations in turbine area
and boiler area require washing, to maintain good plant
housekeeping and prevent build up of dirt and waste
material, which generate waste water. This waste water
along with process drain will be led to an oil water
separator for separation of oil. The clear water will be led to
the Guard pond/central monitoring basin in Effluent
treatment plant. The dirty oil will be recovered separately
in a drum and sold to local users.
The Guard Pond in Effluent treatment plant will act as an
equalization basin for all treated/untreated liquid effluents.
Provision will be there for use of this treated and equalized
effluent partly in horticulture and green belt development.
For the excess quantity, attempts will be made to attain
‘zero waste water discharge’ through RO plant.
The sewage will be collected from the Administrative
building and canteen area, powerhouse area and fire
station area. Sewage waste from the administrative
building and canteen area will be collected by gravity into
an oil grease trap. After the oil removal, sewage is
collected in a bar screen chamber, where the floating
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO SEC - 6
SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016 -132-
particles are removed from the sewage. From the bar
screen chamber sewage is collected in a septic tank for
anaerobic treatment. Sewage is then allowed to pass
through an upflow filter. During the process, most of the
COD, BOD and TSS in the sewage are removed. Overflow
from upflow filters is collected in an oxidation pond where
sodium hypochlorite solution is added for disinfection.
Then treated effluent will be pumped for horticulture
purposes.
iii) Noise Emission
Noise emission from equipment will have to be controlled at
source. Adequate silencing equipment will be provided at
various noise sources to attenuate the noise to acceptable
level. Also plantation would be developed in plant area,
which would help in reducing noise level to some extent.
In Annexure-6.1, a list of basic equipment/instruments
for environmental monitoring and testing for the proposed
station is given.
iv) Guard Pond
It is envisaged to develop a guard pond to be located
suitably in the low lying area of the plot for collecting the
liquid wastes. The capacity of the pond would be adequate
to store 24-hours’ design liquid effluent discharge from the
station. Treated and equalized effluent from the Guard
Pond will be treated in the effluent treatment plant by
alkali/acid dozing and let off to be reused in horticulture
and green belt development within the plant. Balance
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO SEC - 6
SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016 -133-
treated effluent conforming to the norm will be discharged
to the RO plant to achieve zero waste water discharged
satisfying the requirement as stated in MOEF notification,
Govt. of India.
The storm water and catchment water which are not
effluent from the plant would be drained by a separate
drainage system.
v) Green Belt
Adequate green belt would be developed in and around the
project area and the ash disposal area satisfying the
requirement of state as well as Ministry of Environment and
Forest (MOEF), Govt. of India. Plantation near coal stacks
and the ash disposal area to arrest fugitive dust are also
proposed. These green belts, apart from arresting air-borne
dust particles and acting as noise-barrier, would help in
improvement of ecology and aesthetics of the area. The
area provided for Green belt is around 300 acres.
vi) Rain Water Harvesting System
Rain water harvesting system would be followed for the
proposed project. In this scheme, roof water and surface
water of the plant area would be collected through open
storm water drain networks. The discharge outlet of these
drain networks would be connected to a recharging pit from
where water would be allowed to percolate into the ground.
The basic purpose of this scheme is to assist the ground
water table stability. Also, it is a compulsory scheme as per
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO SEC - 6
SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016 -134-
the recommendations of the statutory/environmental
bodies.
vii) Solar Power Harvesting
TANGEDCO proposes to harness solar power on the roof
tops of main power plant building, switchyard control room
building, water treatment building etc. The estimated area
to be available for setting up solar power plant on above
roof tops would be 3000 sq. m. Solar Technologies
available are as follows :
a. Solar photovoltaic cells
b. Crystalline silicon
c. Thin slim modules
The quantum of solar power expected to be generated is in
the order of 1200-1300kW.
It is proposed to utilize solar power for control room
lighting, switchyard area and switchyard control room
lighting and water treatment/chemical analysis laboratory.
Its integration with plant area electrical system would be
examined at appropriate stage.
Viii) DRY COOLING SYSTEM (Alternate option):
Dry Cooling system is considered as an alternate option for
the proposed project. Dry cooling systems are of two types
Direct and Indirect.
In direct dry cooling system, exhaust steam from LP turbine
is directly cooled in a system of finned tubes by ambient
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO SEC - 6
SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016 -135-
air. Mechanical draft to be used to move the air through fin
tube heat exchange elements. To reduce pressure drop in
steam conveying system, it needs to be installed close to
the turbine hall.
In an indirect dry cooling system, exhaust steam from the
turbine is cooled by water in a condenser which can be of
surface type, and hot water is cooled by air in finned tube
bundles utilizing natural draft tower. The air cooled
condenser units can be located away from the main plant.
The cooling system shall be selected based on optimization
of water requirement vis a vis plant efficiency. The type of
cooling system shall be decided during detailed project
preparation stage based on economic consideration.
TABLE-6.1COMPARATIVE DETAILS OF WET AND DRY COOLING SYSTEM
Sl. No
PARAMETERS
WET COOLINGSYSTEM (NDCT)
DRYCOOLINGSYSTEM
REMARKS
1 Heat rate (Design Coal) kcal/kWh
2195 2349 Increase in differential rate by 7%
2 Plant Water requirement (m3/hr)
39193 7839 Decrease by 80%
3 Auxillary Power ConsumptionFor single unit
48 MW (6%) 54.5 MW (6.8%) -
4 Area Foot print 15 acres 20 acres Note* 5 Project Capital
cost excluding IDC
Rs 26,165 Crores
Rs 28,782 Crores -
6 Cost per MW 7.70 Crores 8.47 Crores
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO SEC - 6
SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016 -136-
In case of dry cooling system the Raw Water requirement for the
plant shall be arranged from nearby desalination plant proposed
at Kudhuraimozhi (TWAD Board). However, the adoption of dry
cooling system will make the project economically unviable.
IX) Flue Gas Desulphurization Plant (FGD)
As per the sulphur content in coal as mentioned in
Annexure-3.3 of the report, no flue gas desulphurization
is necessary. However, as per guidelines of MoEF, the
installation of FGD plant at the rear side of ESP or chimney
is considered in the layout. The prescribed level for SOx is
within 100 mg/Nm3 as specified in the latest MOEF
notification.
Wet FGD system is proposed for the project. In wet FGD
system, limestone (CaCO3) is used as reagent.
Alternatively Dry FGD / Seawater FGD systems may be
adopted. The FGD system shall be selected based on
optimization of water requirement and plant efficiency and
shall be decided during detail engineering stage. The
performance / characteristics of different available FGD
technologies are given in Table – 6.1 below:
The makeup water requirement for wet (limestone) FGD
plant shall be met from desalinated product water. The
tentative quantity of makeup water requirement for the
proposed project is estimated at 1500m3/hr. The tentative
quantity of limestone slurry preparation for the proposed
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO SEC - 6
SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016 -137-
project is estimated at 120m3/hr. Limestone slurry
preparation quantity (120m3/hr) is met from desalinated
water (60m3/hr) and recycled water (60m3/hr) from FGD
waste water treatment plant.
The slurry/waste water generated in Wet FGD system shall
be passed through hydrocyclone followed by a filtration
plant to separate gypsum flakes and filtrate. The filtrate
is recycled back to the FGD makeup system. Zero liquid
discharge (ZLD) plant to treat waste water shall be
envisaged (if required). The FGD system would require
around 0.2 million tonnes of limestone per year. The
generation of Gypsum is around 0.3 million tonnes per
year. Closed storage area with storing capacity for 30 days
is provided for the limestone and gypsum in FGD material
handling area located at the eastern boundary of the plant.
The total area provided for the FGD system is around 17
acres. In addition, an open storage area of 50 acres for the
disposal of Gypsum is provided within the plan boundary
near the ash dyke.
F
easi
bilit
y R
epor
t fo
r 5 x
800
MW
Kad
alad
i Sup
er C
ritic
al
Ther
mal
Pow
er P
rojec
t at
Kada
ladi
Tal
uk,
Ram
anat
hapu
ram
Dist
rict,T
amil
Nad
u
Job
No:
15Z
03
5x8
00 M
W-K
UM
TPP
-FR
-TA
NG
ED
CO
SEC
- 6
SE
/E/T
H(P
)/EE
/E/K
DI/F
.DP
R/P
.O.N
O.3
/D.3
/201
6 -1
38-
Tab
le 6
.2 –
The
per
form
ance
/ c
hara
cter
istic
s of
FG
Ds
DES
CR
IPTI
ON
UN
ITW
ET F
GD
DR
Y F
GD
S
EA-W
ATE
R F
GD
Hig
h S
ulp
hu
r in
Gas
Econ
omic
al.
Mos
t w
idel
y us
edN
ot e
cono
mic
al.
Not
pra
ctic
al for
hig
h S c
oal
(>1%
S)
Rea
gen
ts u
sed
Lim
esto
neLi
me
(Lim
e is
mor
e ex
pens
ive
than
lim
esto
ne)
Sea
wat
er
SO
2 r
emov
al
effi
cien
cy%
Rem
oval
effic
ienc
y up
to
98%
Rem
oval
effic
ienc
y up
to
94%
Rem
oval
effic
ienc
y up
to
90%
Pow
er
Con
sum
pti
on
(% P
ower
Pla
nt
Cap
acit
y)
%U
se 1
– 1
.5%
of
elec
tric
ity g
ener
ated
Use
0.5
– 1
.0%
of
elec
tric
ity g
ener
ated
, le
ss t
han
Wet
FG
D
Use
0.8
– 1
.6%
of el
ectr
icity
ge
nera
ted
Sp
ace
req
uir
emen
t %
10
0 60
-70
70-8
0 A
bso
rben
t co
st
%
100
400
Nil
By-
pro
du
cts
gen
erat
ion
an
d
dis
pos
alG
ypsu
mD
ry C
alci
um S
ulph
ite,
Cal
cium
Sul
phat
e M
ixtu
reSul
phat
e Io
ns
Util
ized
in C
emen
t an
d G
ypbo
ard
appl
icat
ions
Dis
posa
l cos
t ca
n be
hi
gh.
No
by-p
rodu
cts
F
easi
bilit
y R
epor
t fo
r 5 x
800
MW
Kad
alad
i Sup
er C
ritic
al
Ther
mal
Pow
er P
rojec
t at
Kada
ladi
Tal
uk,
Ram
anat
hapu
ram
Dist
rict,T
amil
Nad
u
Job
No:
15Z
03
5x8
00 M
W-K
UM
TPP
-FR
-TA
NG
ED
CO
SEC
- 6
SE
/E/T
H(P
)/EE
/E/K
DI/F
.DP
R/P
.O.N
O.3
/D.3
/201
6 -1
39-
Com
mer
cial
gra
de
by-p
rodu
ct
Land
-fill
ing
Non
e. D
isch
arge
of Sea
Wat
er a
spe
r st
ipul
ated
con
ditio
n is
cr
itica
l. Im
pact
s on
mar
ine
envi
ronm
ent
need
to
be c
aref
ully
exa
min
ed
(e.g
., r
educ
tion
of p
H,
inpu
ts o
f re
mai
ning
hea
vy m
etal
s, fly
ash
,te
mpe
ratu
re,
sulfa
te,
diss
olve
d ox
ygen
, an
d ch
emic
al o
xyge
n de
man
d).
Inve
stm
ent
cost
100
70-8
0 70
-80
Pla
nt
Cap
ital
cos
t in
crea
se11
– 1
4%
9 -
12%
7
- 10
%
Feasibility Report
for 5 x 800 MW Kadaladi Super Critical Thermal Power Project at Kadaladi Taluk,
RamanathapuramDistrict,Tamil Nadu Job No: 15Z03
5x800 MW-KUMTPP-FR-TANGEDCO SEC - 6 SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016
-140-
X) SCR (Selective Catalytic Reduction):
SCR system is envisaged for the proposed system to
control of NOx emission. The prescribed level for NOx is
within 100 mg/Nm3 as specified in the latest MOEF
notification.
6.3 Basic Information for Environmental Clearance:
The background pollution level, in terms of SPM, SOx, and NOx
etc. of the area is expected to be well within the prescribed
limits of MOEF.
Project authority will institute a separate study on
Environmental Impact Assessment (EIA) to identify the effect of
the project on the surrounding environment. The site does not
include any forest land. Three Bird sanctuaries are located in
the vicinity. Melselvanur-Keelselvanur bird sanctuary at around
17 km, Chitrangudi bird sanctuary and Kanjirankulam bird
sanctuary at around 22 km & 20 km respectively from the
selected site (Site-B). The GOMNP (Gulf of Mannar National
park) Vembar zone Uppu Tanni Tivu is around 11 km and
Thoothukudi zone Kariashuli Tivu is around 23 km from the
selected project site. The site falls within the buffer area of the
GOMBR (Gulf of Mannar Biosphere Reserve). Further
assessment on environmental impacts and the requisite
management plans shall be pointed out in EIA/EMP study. The
tentative location of intake / outfall location is around 12 km
Feasibility Report
for 5 x 800 MW Kadaladi Super Critical Thermal Power Project at Kadaladi Taluk,
RamanathapuramDistrict,Tamil Nadu Job No: 15Z03
5x800 MW-KUMTPP-FR-TANGEDCO SEC - 6 SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016
-141-
and 19 km away from the GOMNP Uppu Tanni Tivu and
Kariashuli Tivu respectively in Gulf of Mannar. As such the plot
identified for the project does not involve any eviction and thus
no rehabilitation would be necessary. Thus, no adverse
economic impact is foreseen.
As mentioned earlier, there would be no encroachment of any
water body by the proposed project. The project also considers
establishing all the major cost intensive items for pollution
control viz. ESP, chimney, low NOx burner for furnaces, waste
water treatment and recycling, afforestation etc.
6.4 Ash Management Plan
A plot of 522 Acres has been identified for ash pond for
dumping ash generated from the proposed project. Considering
Bottom ash slurry disposal for 25 years and fly ash disposal of
1st year-100%, 2nd year-75%, 3rd year 50% and 4th year 25%.
This area includes the peripheral road and statutory green belt
around the disposal area. The Ministry of Environment & Forests
notification dated 3rd November, 2009, 100% fly ash utilisation
from the complex need to be ensured within initial four years of
operation. The ash generated can be gainfully utilized for filling,
land filling of low lying areas located in closed vicinity and in
cement plant. Possibility to minimize the requirement of ash
dumping in the ash pond to be established. The high utilisation
rate can be achieved by a comprehensive program for the
standardization of by-products and active marketing of the by-
Feasibility Report
for 5 x 800 MW Kadaladi Super Critical Thermal Power Project at Kadaladi Taluk,
RamanathapuramDistrict,Tamil Nadu Job No: 15Z03
5x800 MW-KUMTPP-FR-TANGEDCO SEC - 6 SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016
-142-
products. Co-operation between the power plant and the
Utilising Industry contributes to the high utilisation rate.
6.5 Gypsum Management Plan
The successful environmental management strategy, which
initiate the concept of sustainable development, is the
maximum utilisation of the residue. Gypsum from a wet
scrubbing system can be a substitute for natural gypsum. The
areas of utilization of gypsum are in building materials for
products like wall boards, plasterboards, mortars, cement etc.
There should be a consideration of utilising the gypsum as close
to the power plant as possible, which can be achieved by
envisaging construction material production near power plant.
Possibility of selling the gypsum for other uses would also be
explored to minimize the requirement of dumping. The
generation of Gypsum is around 0.3 million tonnes per year.
Closed storage area with storing capacity for 30 days is
provided for gypsum in FGD material handling area. An open
storage area of 50 acres for the disposal of Gypsum is provided
within the plan boundary near the ash dyke.
�
Feasibility Report
for 5 x 800 MW Kadaladi Super Critical Thermal Power Project at Kadaladi Taluk,
Ramanathapuram District,Tamil Nadu Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO ANN – 3.1 SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016
- 1 -
SEA WATER ANALYSIS
S.No. Parameters Value (ppm)
1. Total Solids 35,000
2. Dissolved solids 21,620
3. Suspended Solids 580
4. Ignited residue 17,500
5. Volatiles Solids 4,700
6. Acid Insolubles 112
7. Chlorides (as Cl) 20,232
8. Sulphates (as SO4) 1,457
9. Iron (as Fe) 70
10. Total alkalinity (as CaCO3) 525
11. Alkalinity due to Normal Carbonates (as CaCO3) Nil
12. Alkalinity due to bi-Carbonates (as CaCO3) 525
13. Total hardness (as CaCO3) 8,155
14. Permanent hardness (as CaCO3) 6,200
15. Temporary hardness (as CaCO3) 1,955
16. Calcium hardness (as CaCO3) 1,255
17. Magnesium hardness (as CaCO3) 6,900
18. PH 8.2
�
F
easi
bilit
y R
epor
t
for
5 x
800
MW
Kad
alad
i Sup
er C
ritic
al
T
herm
al P
ower
Pro
ject a
t Kad
alad
i Tal
uk,
Ram
anat
hapu
ram
Dist
rict,
Tam
il N
adu.
A
nnex
ure
– 3.
2 Sh
eet 1
of 2
Jo
b N
o: 1
5Z03
5x80
0 M
W-K
SCTP
P-FR
-TA
NG
EDC
O
E/TH
(P)/E
E/E/
KD
I/F.D
PR/P
.O.N
O.3
/D.3
/201
6
ES
TIM
AT
ION
OF
CO
NS
UM
PT
IVE
WA
TE
R R
EQ
UIR
EM
EN
T
Sl.
No.
C
onsu
mpt
ion
Poin
ts
Des
alin
ated
Pro
duct
wat
er u
sage
(m
3 /hr
) Se
a w
ater
usa
ge (m
3 /hr
)
DM
W
ater
(m
3 /hr)
Pota
ble
Wat
er
(m3 /h
r)
Serv
ice
wat
er
(m3 /h
r)
Des
alin
atio
n fe
ed w
ater
(m
3 /hr)
CT
Mak
eup
wat
er
(m3 /h
r)
Elec
tro-
chlo
rina
tion
feed
wat
er
(m3 /h
r)
Rem
arks
1.
a. H
eat C
ycle
Mak
e-up
b.
Mak
e-up
Req
uire
men
t for
C.C
.C.W
Sys
tem
c.
Che
mic
al F
eed
Syst
em
d. H
2 G
ener
atio
n Pl
ant
e. C
onde
nsat
e po
lishi
ng u
nit
f. R
egen
erat
ion
of D
M P
lant
e.
Rej
ect f
rom
BW
RO
125
10
10
15
10
10
60
@
1%
mak
e-up
Sub-
Tota
l (a
to e
) 24
0
240
2.
a.
Pot
able
Wat
er R
eqm
t. fo
r Pla
nt
b. P
otab
le w
ater
Req
mt.
For T
owns
hip
7 13
Sub-
Tota
l (a
)
20
20
F
easi
bilit
y R
epor
t
for
5 x
800
MW
Kad
alad
i Sup
er C
ritic
al
T
herm
al P
ower
Pro
ject a
t Kad
alad
i Tal
uk,
Ram
anat
hapu
ram
Dist
rict,
Tam
il N
adu.
A
nnex
ure
– 3.
2 Sh
eet 2
of 2
Jo
b N
o: 1
5Z03
5x80
0 M
W-K
SCTP
P-FR
-TA
NG
EDC
O
E/TH
(P)/E
E/E/
KD
I/F.D
PR/P
.O.N
O.3
/D.3
/201
6
3.
a. S
ervi
ce W
ater
b.
AH
P (C
oolin
g &
Sea
ling)
c.
ASH
Con
ditio
ning
d.
HV
AC
pla
nt m
akeu
p e.
To
Fire
pro
tect
ion
syst
em
f. FG
D s
yste
m m
akeu
p g.
FG
D L
imes
tone
slur
ry p
repa
ratio
n h.
CH
P D
ust S
uppr
essi
on
100
200
20
50
20
1500
60
55
+55
m3 /
hr to
CH
P D
S
+60
m3 /
hr re
cycl
ed fr
om F
GD
+45
m3 /
hr re
cycl
ed fr
om E
TP
Sub-
Tota
l (a
to h
)
20
05
2005
3a
D
esal
inat
ed p
rodu
ct w
ater
requ
irem
ent (
sub-
tota
ls 1
+ 2
+ 3
) 22
65 m
3 /hr
3b
Recy
clin
g of
Per
mea
te w
ater
from
ETP
RO
pl
ant
245
m3/
hr
3c
Tota
l Des
alin
ated
pro
duct
wat
er re
quir
emen
t (s
ub-to
tals
3a
– 3b
) 20
20 m
3/hr
4.
a. 4
8.5
MLD
Des
alin
atio
n pl
ant r
ejec
t wat
er
b. U
ltra-
filtr
atio
n re
ject
c.
Cla
rifie
r slu
dge
wat
er
d. C
lear
wat
er re
cycl
ed b
ack
from
Slu
dge
hand
ling
plan
t
30
30
561
174
742
Sub-
Tota
l 4 (a
to c
) - 4
(d) +
3c
50
43
5.
C
T M
akeu
p w
ater
33
125
6.
Si
de s
trea
m fi
lters
bac
kwas
h sl
udge
was
te
650
7.
Elec
tro-
chlo
rina
tion
plan
t fee
d w
ater
375
G
RA
ND
TO
TAL
(sub
tota
ls o
f 4+5
+6+7
)
3919
3 38
5 C
usec
With
5%
mar
gin
41
150
404
Cus
ec
Not
e: T
he a
bove
val
ues a
re in
dica
tive
and
subj
ect t
o ch
ange
as p
er B
idde
r’s r
equi
rem
ent d
urin
g de
tail
engi
neer
ing
stag
e.
Feasibility Report
for 5 x 800 MW Kadaladi Super Critical Thermal Power Project at Kadaladi Taluk,
Ramanathapuram District,Tamil Nadu Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO ANN – 3.3 SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016
- 1 -
ANALYSIS OF IMPORTED COAL (AS RECEIVED BASIS)
PROXIMATE ANALYSIS
COMPONENT (% BY WEIGHT)
Moisture 16.50
Volatile Matter 36.45
Ash 6.62
Fixed Carbon 40.43
Total 100.00
ULTIMATE ANALYSIS
Carbon 60.12
Hydrogen 4.38
Nitrogen 1.48
Oxygen 10.37
Sulphur 0.53
Ash 6.62
Moisture 16.50
Carbonates -
Phosphorous -
Others -
Total 100.00
Gross Calorific Value - 5642Kcal/Kg
HGI - 51
Feasibility Report
for 5 x 800 MW Kadaladi Super Critical Thermal Power Project at Kadaladi Taluk,
Ramanathapuram District,Tamil Nadu Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO ANN – 3.3 SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016
- 2 -
ANALYSIS OF INDIGENOUS COAL (AS RECEIVED BASIS)
PROXIMATE ANALYSIS
COMPONENT (% BY WEIGHT)
Moisture 16.00
Volatile Matter 19.00
Ash 45.00
Fixed Carbon 20.00
Total 100.00
ULTIMATE ANALYSIS
Carbon 27.70
Hydrogen 2.60
Nitrogen 0.52
Oxygen 7.26
Sulphur 0.50
Ash 45.00
Moisture 16.00
Carbonates 0.38
Phosphorous 0.04
Others -
Total 100.00
Gross Calorific Value - 2800Kcal/Kg
HGI – 45 to 55
Feas
ibili
ty R
epor
t
for
5 x
800
MW
Kad
alad
i Sup
er C
ritic
al
T
herm
al P
ower
Pro
ject a
t Kad
alad
i Tal
uk,
Ra
man
atha
pura
m D
istric
t, Ta
mil
Nad
u
A
nnex
ure
– 4.
1 Sh
eet 1
of
3
Jo
b N
o: 1
5Z03
5x80
0 M
W-K
SCTP
P-FR
-TA
NG
EDC
O
E/TH
(P)/E
E/E/
KD
I/F.D
PR/P
.O.N
O.3
/D.3
/201
6
S
ITE
-A
Loca
tion
: K
adal
adi,
Ram
anat
hapu
ram
Dis
tric
t C
onne
ctiv
ity to
Site
:
The
site
is 5
km fr
om S
eval
patti
-Tha
raku
di d
istr
ict r
oad
Wat
er S
ourc
e :
Gul
f of M
anna
r
Gri
d C
onne
ctiv
ity
: TA
NTR
AN
SCO
Coa
l C
onne
ctiv
ity
: Fr
om T
hoot
huku
di p
ort
by R
ail
S.n
o N
ame
of t
he
Vil
lage
Pro
pose
d A
rea
Tot
al A
rea
in H
a P
orom
boke
Lan
d in
Ha
Pat
ta L
and
in H
a
Dry
W
et
1.
Kon
dana
llam
patti
19
.9.5
78
4.67
.0
___
803.
86.5
T
O T
A L
:
19
.9.5
784
.67
___
80
3.86
.5
This
site
was
not
con
side
red
furt
her f
or:
1.
The
inta
ke c
orri
dor o
ver l
and
to b
e ta
ken
alon
g si
te-2
and
the
dist
ance
wor
ks o
ut to
aro
und
10km
. 2.
The
site
has
max
imum
agr
icul
tura
l lan
d.
3.Th
e si
te h
as fe
w h
abita
ts w
hich
are
like
ly to
cau
se R
&R
issu
es.
Feas
ibili
ty R
epor
t
for
5 x
800
MW
Kad
alad
i Sup
er C
ritic
al
T
herm
al P
ower
Pro
ject a
t Kad
alad
i Tal
uk,
Ra
man
atha
pura
m D
istric
t, Ta
mil
Nad
u
A
nnex
ure
– 4.
1 Sh
eet 2
of
3
Jo
b N
o: 1
5Z03
5x80
0 M
W-K
SCTP
P-FR
-TA
NG
EDC
O
E/TH
(P)/E
E/E/
KD
I/F.D
PR/P
.O.N
O.3
/D.3
/201
6
SIT
E-B
Lo
catio
n :
Kad
alad
i, Ra
man
atha
pura
m D
istr
ict
Con
nect
ivity
to S
ite
: By
Roa
d, 1
Km
from
Eas
t Coa
st R
oad
Wat
er S
ourc
e :
Gul
f of M
anna
r G
rid
Con
nect
ivity
:
TAN
TRA
NSC
O
Coa
l C
onne
ctiv
ity
: Fr
om T
hoot
huku
di p
ort
by R
ail
S.n
o N
ame
of t
he
Vil
lage
Pro
pose
d A
rea
Tot
al A
rea
in H
a P
orom
boke
L
and
in H
a P
atta
Lan
d in
Ha
Dry
W
et
1.
Thar
aiku
di
___
401.
91.5
__
_ 40
1.91
.5
2.
Kan
nira
japu
ram
230.
26.0
__
_ 23
0.26
.0
3.
Nar
ippa
iyur
4.
41.5
26
5.77
.0
___
270.
18.5
T O
T A
L :
4
.41.
5 89
7.94
.5
___
90
2.36
.0
This
site
has
bee
n co
nsid
ered
as
best
sui
tabl
e du
e to
: 1.
Pr
ojec
t are
a is
spr
ead
over
3 v
illag
es a
nd th
e or
ient
atio
n is
com
pact
in n
atur
e.m
ostly
bar
ren
part
ly w
ith p
atch
es o
f bus
hes a
nd p
alm
tree
s.
2. A
vaila
bilit
y of
ade
quat
e va
cant
land
with
out a
gric
ultu
re a
nd fr
ee fr
om R
&R
issu
es.T
he o
rien
tatio
n is
com
pact
in n
atur
e 3.
As
the
site
is n
ear t
o se
a sh
ore
(i.e)
abo
ut 2
.3 K
m ,
the
requ
irem
ents
for p
lant
wat
er s
yste
m c
ould
be
easi
ly m
et o
ut. H
owev
er, i
t is
also
re
ason
ably
aw
ay fr
om th
e se
a co
ast i
n co
mpl
ianc
e w
ith C
RZ.
4. T
he s
ite is
nea
r the
pro
pose
d al
ignm
ent o
f B.G
. Rai
lway
line
from
Kan
yaku
mar
i to
Kar
aiku
di a
nd h
ence
it w
ill fa
cilit
ate
tran
spor
t of c
oal
from
Tut
icor
in p
ort t
o si
te.
5. T
he s
ite is
nea
rer t
o th
e ex
istin
g Ea
st c
oast
road
6.
The
pro
ject
site
and
the
inta
ke /
out
fall
loca
tion
is 1
1km
& 1
2km
aw
ay f
rom
the
Upp
u Th
anni
Thi
vu Is
land
in
Gul
f of M
anna
r. Th
e te
ntat
ive
corr
idor
rout
e an
d la
nd fa
ll po
int i
s in
dica
ted
in th
e D
RG.1
5ZO
3-00
4-D
WG
-M-0
03, t
he te
ntat
ive
area
for t
he c
orri
dor i
s ar
ound
12
acre
s.
Feas
ibili
ty R
epor
t
for
5 x
800
MW
Kad
alad
i Sup
er C
ritic
al
T
herm
al P
ower
Pro
ject a
t Kad
alad
i Tal
uk,
Ra
man
atha
pura
m D
istric
t, Ta
mil
Nad
u
A
nnex
ure
– 4.
1 Sh
eet 3
of
3
Jo
b N
o: 1
5Z03
5x80
0 M
W-K
SCTP
P-FR
-TA
NG
EDC
O
E/TH
(P)/E
E/E/
KD
I/F.D
PR/P
.O.N
O.3
/D.3
/201
6
SIT
E-C
Lo
catio
n :
Kad
alad
i, Ra
man
atha
pura
m D
istr
ict
Con
nect
ivity
to S
ite
: Th
e si
te is
aro
und
2km
from
EC
R W
ater
Sou
rce
: G
ulf o
f Man
nar
Gri
d C
onne
ctiv
ity
: TA
NTR
AN
SCO
C
oal
Con
nect
ivity
:
From
Tho
othu
kudi
por
t by
Rai
l
S.n
o N
ame
of t
he
Vil
lage
Pro
pose
d A
rea
Tot
al A
rea
in H
a P
orom
boke
Lan
d in
Ha
Pat
ta L
and
in H
a
Dry
W
et
1.
Val
inok
kam
2.
89.0
52
1.20
.5
___
524.
09.5
2.
Sira
ikku
lam
4.
76.0
30
1.07
.5
___
305.
83.5
T
O T
A L
: 7.
65.0
82
2.28
.0
___
82
9.93
.0
This
site
was
not
con
side
red
for:
1.Th
e pr
ojec
t site
and
the
inta
ke is
5.5
km fr
om th
e G
OM
NP
Kee
laka
rai z
one.
2.
The
Inta
ke/o
utfa
ll lo
catio
n w
ith re
spec
t to
the
site
loca
tion
will
be
in c
lose
pro
xim
ity w
ith th
e G
OM
NP.
3.
The
proj
ect s
ite so
uthe
rn p
art o
verl
aps w
ith 5
00m
HTL
. 4.
The
site
has
som
e ag
ricu
ltura
l lan
d an
d ha
bita
t whi
ch m
ay c
ause
R&
R is
sues
.
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO ANN – 5.1 SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016
-1-
1. Turbine Generator & Auxiliaries
� Type : Single/double reheat multi cylinder tandem compound, Condensing steam turbine directly driving a 3000 rpm, 2-pole, 50 Hz, synchronous generator.
� Nominal Capacity : 800,000 kW
� Normal Operating Frequency : 47.5 to 51.5 Hz Range
� Inlet Steam Parameters: - Main Steam Hot Reheat
• Pressure, bar (abs.) : 255 54 • Temperature, �C : 565 593 • Steam flow at MCR t/hr. : 2510 * (approx.)
� Exhaust Pressure : 77 mm of Hg (abs.)
� Steam Extractions : CRH + 5 to 7 Nos. stages from HP, IP and LP turbines for condensate/ feed water heating (depends on manufacturer).
� Type of governing : Electro-hydraulic governing with fire resistant fluid.
� Turbine HP-LP bypass system : Capacity : 60% of BMCR (or lower capacity commensurate with mini-mum main steam flow correspond-ing to
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO ANN – 5.1 SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016
-2-
sustained rated main steam temp.)
� Condensing Equipment : Shell and tube type, surface condenser, of single/double flow design operating on re-circulating cooling water with evaporative cooling towers.
� Regenerative feed heating : Three / four stages of LP heat arrangement (U-tube design). One spray-
cum-tray type deaerator, two parallel chains of HP heaters.
� Boiler feed water pumps : 2x50% capacity steam turbine-driven BFP with booster pump & 1x50 % electric motor driven, horizontal, centrifugal BFP.
� Condensate extraction pumps : 3x50% capacity vertical, centri-fugal CAN type construction, 3.3 kV motor driven.
� Generator : 945,000 kVA output at 0.85 power factor (lagging) 3 pH, 50 Hz at 27 kV voltage.
2. Steam Generator & Auxiliaries
� Type : Pulverized fuel, once through, two-pass/tower type, semi-outdoor type, dry bottom, coal-fired unit prefe-rably with tangential firing and with associated auxiliaries suitable for both constant pressure and sliding mode operation.
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO ANN – 5.1 SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016
-3-
� Nominal Outlet Steam Parameters at BMCR :-
Main Steam Hot Reheat
� Pressure (bar (a)) : 259.5 55.6 � Temperature, �C : 569 596 � Steam flow, t/hr. (approx.) : 2710 *
- Steam temp. control range: 40-100% BMCR or better.
- Super-heater/Re-heater : Attemperation and tilting burner
temperature control control.
� Nominal Air Heaters Capacity : 2 x 60% of BMCR.
� Draft Fans : � 2x60% capacity axial flow forced draft (FD) fans with blade pitch control with VFD.
� 2x60% capacity axial induced draft (ID) blade pitch control fans with variable frequency drive.
� 2 x 60% capacity P.A. Fans.
� Pulverizing Mills : Slow speed large bowl e type in **N+2 configuration.
� Coal Firing System : Direct suspended firing with state-of-the-art low NOXburners giving stable fire between 40-100% MCR or better.
� Start-up/Auxiliary Fuel : Light Diesel Oil/HSD for cold start and for support (capacity up to 10% BMCR).
Heavy Fuel Oil (HFO) for flame support upto 40% of BMCR.
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO ANN – 5.1 SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016
-4-
� Ash Removal : Dry extraction and disposal for Bottom Ash and dry extraction and dry disposal of fly ash to silos. Provision would be kept for Bottom Ash and Fly Ash disposal in Lean mode to ash pond.
Note : *Vendor to specify. **N-denotes the number of mills required to reach boiler MCR with
design coal and 85% mill loading.
3. Plant Water System :
Intake Sea Water Pumps:
� Source : From Gulf of Mannar.
� Type : Vertical wet pit mixed flow multi-stage.
� Fluid Handled : Sea water
� Capacity : 10300 m3/hr (each)
� Head : To be decided at detail engineering stage.
� Suspension Height : To be decided at detail engineering stage.
� Number : Six(6) [4 working + 2 standby)
� Drive : Electric motor, 415 V, 3 Ph., 50 Hz.
Clariflocculator:
� Type : Clarifier with concentric flocculator.
� Capacity : 1390 m3/hr (each).
� Number : five(5), overall 120% capacity.
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO ANN – 5.1 SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016
-5-
� Construction : RCC
Clarified Water Storage Tank:
� Type : RCC (Partly underground) twin-chamber
� Capacity : 8 hours (overall)
Ultrafiltration system:
� Feed flow : 5611 m3/hr
� Recovery : 90% (min)
� Flux : > 60 LMH
Desalination (SWRO) plant:
� Feed flow : 5050 m3/hr
� Recovery : 40% (min)
� Outlet TDS : < 500 ppm
� Flux : 25 LMH (max)
Product / Desalinated water cum fire water storage tank:
� Type : RCC, Semi-underground partitioned.
� Capacity : 24 hours (overall)
� Number : One(1)
BWRO-DM plant: (i) BWRO plant:
� Feed flow : 240 m3/hr
� Recovery : 75% (min)
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO ANN – 5.1 SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016
-6-
� Outlet TDS : To suit supercritical boiler heat cycle makeup system
(ii) DM plant:
� No. of streams : Three (3) (2W+1S)
� Feed flow : 90 m3/hr (each)
� Control Room : Indoor
� Capacity : Three(3) streams of 90 m3/hr, each stream consisting of mixed bed exchanger. The system would also include acid and alkali handling and storage facilities for exchanger regeneration.
� Operation : PLC based from control room.
DM Water Storage Tanks:
� Type : Vertical cylindrical steel tank with inside rubber lining.
� Capacity : 1100 m3
� Numbers : Four (4)
Condensate Storage Tank:
� Type : Vertical steel tank with inside rubber lining.
� Capacity : 500 m3
� Numbers : Five (5)
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO ANN – 5.1 SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016
-7-
Cooling Water Circuit:
Cooling Tower:-
� Type : Natural Draft
� Nos. : Five (5)
� Cooling Water Quality : Sea water
� Total circulating water flow : 92,800 m3/hr. (approx) per unit
� Design cooling range : 42.5 °C to 32.5 °C i.e. 10 °C
� Approach : 5 °C
Circulating Cooling Water Pumps:-
� Type : Vertical wet pit installation.
� Fluid Handled : Sea water
� Capacity : 45,000 m3/hr. each (approx)
� Head : To be decided during detail engineering stage.
� Number : Fifteen (15) [2W + 1S per unit].
Auxiliary Cooling Water Pumps:-
� Type : Vertical wet pit installation.
� Flow : 10,000 m3/hr. each (approx)
� Fluid : Sea water
� Number : Ten(10) [1W + 1S per unit].
Auxiliary DM Closed Cycle Cooling Water Pumps:-� Type : Horizontal volute casing, indoor.
� Flow : 850 m3/hr. each (approx)
� Head : 60 mlc
� Fluid : DM water
� Number : Four(4) [3 working + 1 standby] per unit.
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO ANN – 5.1 SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016
-8-
Plate Type Heat Exchanger:-
� Primary Coolant : DM water
� Flow : 2600 m3/hr. (approx)
� Secondary Coolant : Sea water
� Flow : 3500 m3/hr. (approx)
� Plate Material : AISI 316 � Number per unit : Four(4) (3 working + 1 standby) per
unit.
Side stream filtration:
� Capacity in m3/hr : To be decided by bidder to meet TSS discharge norms of <100 ppm at sea outfall.
� Suspended Solids in CW & ACW circuit : < 2 NTU
ETP RO plant: (to achieve zero waste water discharged) RO plant:
� Feed flow : 290 m3/hr
� Recovery : 85% (min)
� Outlet TDS : < 150 ppm
4. Coal Handling Plant
Conveying System :
� Type : Twin stream conveying system
� Capacity : Rail wagons handling & stacking system 4500 TPH and two independent conveying twin stream system (for conveying to coal bunker) for unit 1,2,3 & unit 3,4 with capacity each 2000 TPH
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO ANN – 5.1 SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016
-9-
Stacker-cum-Reclaimer :-
� Type : Electric-driven rail-mounted rever-sible having slewing and adequate lifting arrangement.
� Stacking Capacity : 4500 TPH
� Reclaiming Capacity : 2000TPH
� Number : Four(4)
5. Solid Waste Handling System Equipment
Ash Handling System:
� Basic Design Parameters : Max. Bottom Ash generation 22 Tons per hour per boiler.
Max. Fly Ash generation – 87 TPH per boiler.
� Type : Dry extraction and disposal for Bottom Ash and dry extraction and dry disposal of fly ash to silos. Provision would be kept for Bottom Ash and Fly Ash disposal in Lean mode to ash pond.
� Bottom Ash cleaning : Dry Ash Extractor.
� Fly Ash cleaning : Auto-sequential operation with 4.5 hours of operation per shift.
6. Fuel Oil System Oil System
LDO Storage Tanks:
� Capacity : 1250 m3
� Number : Two(2)
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO ANN – 5.1 SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016
-10-
LDO Unloading/Transfer Pump:
� Type : Positive displacement.
� Number : Two(2) [1 working + 1 standby]
HFO Storage Tanks :
� Capacity : 5000 m3
� Number : Two(2)
HFO Unloading/Transfer Pump :
� Type : Positive displacement.
� Number : Two(2) [1 working + 1 standby]
7. Auxiliary Equipment:
Turbine Hall EOT Crane :
Capacity:-
� Main Hook : 275 Tons
� Auxiliary Hook : 55Tons
� Number : Four(4)
Elevators:
� Type : Cabin type, driven by coil rope drum, electric drive
� Location & Number : Boiler Area - 5 Power House - 5 Stack - 3
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO ANN – 5.1 SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016
-11-
Fire Protection System: Fire Hydrant System:-
� Type : Pressurised piping network both under-ground and overground kept pressurised by hydro-pneumatic tank and jockey pump etc. with hydrant valves as per the requirements of Tariff Advisory Committee (TAC) of National Insurance Association of India.
� Hydrant Pumps : Three(3) nos.(2 electric motor driven + 1 DG driven).
Air Compressor:
� Type : Screw type.
� Number : 12 (IA-6 (5W+1S) & PA-6(5W+1S) )
� Free air capacity at normal: 55 Nm3/min. each pressure and temperature
� Rated discharge pressure : 8.0 kg/cm2) (g)
� Location : Indoor
� Assumed inlet air temp. : 45 °C (max.)
� Air Receiver : One(1) per compressor.
� Air Drying Plant : One stream of capacity 55 Nm3/min. fully automatic type for each compressor.
Airconditioning System:
Central Control Room:-
� Type : Central chilled water plant with high and low side equipment.
ESP Control Room :-
� Type : Direct Expansion
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO ANN – 5.1 SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016
-12-
DM Plant :-
� Type : Direct Expansion
CHP Control Room :-
� Type : D-X type
� Other areas : Packaged Airconditioning units.
Ventilation System:
Powerhouse Building:-
� Type : Air washer unit with centrifugal fans.
ESP Switchgear & MCC Room:-
� Type : Unitary air filtration with centrifugal fan.
Hydrogen Generation Plant:
� Type : Bipolar Electrolytic module.
� Electrolyte : KOH
� Capacity : 2 units of 10 m3/hr.
� Accessories : Bottling arrangement of H2 in cylinders.
Turbine Oil Purification Unit:
� Type : Centrifuge Type.
� Capacity : 20% per hour of total oil in TG network.
Condensate Polisher:
� Type : Ion Exchange type.
� Capacity : 100% of condensate flow per unit with by-pass. Four(4) units of mixed bed exchange (3 W + 1 S) per unit.
Feasibility Report for 5 x 800 MW Kadaladi Super Critical
Thermal Power Project at Kadaladi Taluk, Ramanathapuram District,Tamil Nadu
Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO ANN – 5.1 SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016
-13-
On-Load Condenser Tube Cleaning System:
� Type : Continuous, sponge rubber ball type with ball recirculation arrangement.
� Capacity : Ball recirculation pump with drive, ball collectors and regulators, automatic ball sorters, ball collecting strainers, debris filters, piping, valves etc.
�
Feasibility Report
for 5 x 800 MW Kadaladi Super Critical Thermal Power Project at Kadaladi Taluk,
Ramanathapuram District,Tamil Nadu Job No: 15Z03
5x800 MW-KSCTPP-FR-TANGEDCO ANN – 6.1 SE/E/TH(P)/EE/E/KDI/F.DPR/P.O.NO.3/D.3/2016
- 1 -
LIST OF BASIC EQUIPMENT/INSTRUMENT FOR ENVIRONMENTAL MONITORING & TESTING
1. Respirable Dust Sampler 2. Stack Monitoring Kit 3. Spectro-Photometer 4. Single Pan Balance 5. pH Meter 6. BOD Incubator 7. Air Oven 8. Water Distillation Assembly 9. D.O. Meter 10. Orsat Apparatus 11. Kjeldahl Nitrogen Assembly 12. Gas Liquid Chromatograph 13. Standard Laboratory Equipment and Appliances 14. Continuous weather monitoring station (for monitoring
of wind speed, wind direction, air temperature, R.H. solar radiation and rainfall)
15. Atomic Absorption Spectrophotometer
SL.NO PROJECT COMPLETION COST RS, LAKHS ANNEX.NO1 PRELIMINARY EXPENSES 375.00 15.1-FORM-5B2 LAND COST 4000.00 15.1-FORM-5B3 CIVIL/ CONSTRUCTION COST 195666.91 15.1-FORM-5B4 MAIN PLANT COST
MECHANICALELECTRICAL & C&I
5 ESTABLISHMENT CHARGES 41647.36 15.1-FORM-5B6 TRAINING 100.00 15.1-FORM-5B7 TOOLS & TACKLE 20823.68 15.1-FORM-5B8 CONTIGENCIES 41647.36 15.1-FORM-5B9 AUDIT & ACCOUNTS 5205.92 15.1-FORM-5B10 SITE SUPERVISION 1960.00 15.1-FORM-5B11 FINANCIAL CHARGES 10727.33 15.1-FORM-5B
1871826.11 15.1-FORM-5B
12 CONSULTANCY CHARGES 5205.92 15.1-FORM-5B13 CONSTRUCTION INSURANCE 2663.76 15.1-FORM-5B14 START UP FUEL 975.00 15.1-FORM-5B15 LOSSES ON STOCK 5205.92 15.1-FORM-5B16 IDC 392612.46 15.1-FORM-5B17 WORKING CAPITAL MARGIN MONEY 63022.27 15.1-FORM-5B18 OPTIONAL PACKAGES 408600.00 15.1-FORM-5B19 CSR 10500.00 15.1-FORM-5B
TOTAL PROJECT COST 3082765.00
COST PER MW 770.69
DEBT/EQUITY 70.30DOMESTIC LOAN 2164304.82FOREIGN LOAN 0.00EQUITY 918460.19TOTAL 3082765.00