Page 1: King Street Station 3.31.11 slide show

Phase 2AIn this slide show:

Jackson Plaza construction progression

March 31, 2011

Page 2: King Street Station 3.31.11 slide show

The white sealant help fill in cracks in the concrete slab to prevent movement and cracks in the new terrazzo floor to be installed above.

Page 3: King Street Station 3.31.11 slide show

The design team is researching on a safe method to clean the original marble walls.

Page 4: King Street Station 3.31.11 slide show

New gypboard ceiling installation for the baggage area under Jackson Plaza has started.

Page 5: King Street Station 3.31.11 slide show

The gypboard ceiling hides the mechanical and electrical distribution systems.

Page 6: King Street Station 3.31.11 slide show

Looking southwest from the new interior space under Jackson Plaza.

Page 7: King Street Station 3.31.11 slide show

The new massive beam and column shown supports the 2nd Avenue sidewalk above and Jackson Street above.

Page 8: King Street Station 3.31.11 slide show

New mechanical room construction.

Page 9: King Street Station 3.31.11 slide show

A close up view inside a planter before cherry trees and daffodils are planted.

Page 10: King Street Station 3.31.11 slide show

Rubber like expansion joint separated 2nd Ave Extension sidewalk from Jackson Plaza.

Page 11: King Street Station 3.31.11 slide show

Close up view of the new expansion joint.

Page 12: King Street Station 3.31.11 slide show

New sidewalk at the northeast corner of Jackson Plaza.

Page 13: King Street Station 3.31.11 slide show

Part of the sidewalk will also be repaved.

Page 14: King Street Station 3.31.11 slide show

The bridge rail will be repaint, green moss concrete block removed, and expansion joint inserted.

Page 15: King Street Station 3.31.11 slide show

New plaza court yard light post installed.

Page 16: King Street Station 3.31.11 slide show

Concrete masonry unit serves as bench support for salvaged granite seating bench.

Page 17: King Street Station 3.31.11 slide show

New brick paver walkway in place.

Page 18: King Street Station 3.31.11 slide show

Close up view of solid brick pavers.

Page 19: King Street Station 3.31.11 slide show

The grand staircase has been wrapped to prevent water intrusion prior to restoration.

Page 20: King Street Station 3.31.11 slide show

Salvaged granite blocks will fill in the balustrade gap, steps will be set with precast terrazzo tiles, marble walls will be repaired and cleaned, and new stainless steel rails will be installed.

Page 21: King Street Station 3.31.11 slide show

Restored historic windows under Jackson Plaza has been painted white.