know your city final report- lusaka

Upload: mrunal69

Post on 02-Jun-2018

225 views

Category:

Documents


1 download

TRANSCRIPT

  • 8/10/2019 Know Your City Final Report- Lusaka

    1/32

    1

    KNOW YOUR CITY: A CITY OF 2030 WITHOUT SLUMSLUSAKA REPORT

    Table of Contents

    Introduction ............................................................................. 4

    1. General Project Background ....................................................... 4

    1.1 Project Aim ................................................................................ 4

    1.2 Project Organisation.5

    1.3 Project Activities and Results ....................................................... 5

    Know Your City Lusaka ............................................................. 52. Methodology and Technical Tools ............................................... 8

    2.1 Key tools ................................................................................... 9

    3. Project Process ......................................................................... 11

    3.1 Community mobilisation, engagement and training .................... 11

    3.2 Establishing a social fund for the urban poor: Womens Savings

    Schemes. 11

    3.3 Enumeration and mapping process ........................................... 12

    3.4 Utilisation of Collected information .......................................... 14

    3.5 Summary of Project Progress ................................................... 16

    4. Challenges ............................................................................... 195. Key Lessons Learned ............................................................... 21

    5.1 Lessons Surrounding Participation .............................................. 21

    5.2 Lessons Surrounding Partnerships .............................................. 22

    6. Assessment of Results ............................................................. 23

    Appendixes ............................................................................. 25

    Appendix 1: Summary of the enumeration reports ....................... 25

    Executive summary: Zingalume Compound ...................................... 25

    Executive summary: George Compound .......................................... 30

    Appendix 2: Household Survey Questionnaire .............................. 34Appendix 3: Mapping forms used ................................................. 43

    Kalikiliki Household Mapping Form ................................................... 43

    Kalikiliki Enumeration: Water and Sanitation Form .......................... 44

    Appendix 4: Sample Map .............................................................. 45

    Appendix 5: Logical Framework for Scaling Up Project in Lusaka 46

    Appendix 6: Draft Lusaka Informal Settlement Upgrading Strategy

    .................................................................................................... 49

  • 8/10/2019 Know Your City Final Report- Lusaka

    2/32

    2

    Introduction

    This final report outlines the process and results of the Know Your City

    project jointly implemented in Lusaka by the Lusaka City Council (hereafter

    the LCC) and informal settlement dwellers, of the Zambia Homeless and Poor

    Peoples Federation (ZHPPF) of Lusaka city. The project sought to foster a

    sustainable working relationship between local authorities and informal

    settlement dwellers in a bid to expedite the creation of inclusive cities in

    Zambia.

    1. General Project Background

    1.1 Project Aim

    Established under the Memorandum of Understanding (MoU) entered into by

    Slum Dwellers International (SDI) and the United Cities and Local

    Governments of Africa (UCLGA), these organizations sought to pilot a joint-

    work project encouraging local government-community cooperation around

    issues of inclusive city planning and slum upgrading. Through the Know Your

    City joint work programme, and the nature of UCLGA and SDIs networks,

    local governments and organized slum dweller communities were brought

    together through the enumeration exercise an SDI tested tool tobuild the

    capacity of urban poor communities to enter a constructive dialogue with

    local authorities and collect information about the informal settlements and

    their development needs.

    Addressing the urgent need enhance the collective knowledge and data about

    slums and informal settlements in Africa, the project aims to provide slum

    communities and local municipalities with the tools they need to better plan

  • 8/10/2019 Know Your City Final Report- Lusaka

    3/32

    3

    and manage their cities in an inclusive manner. In order to do this, the city in

    question must recognize that informal settlements and their populations are

    part of the city and that the poor urban communities have fundamental

    rights to be included in the planning process and strategic decisions

    surrounding city planning and the provision of public services. Knowledge

    starts with information gathering and correct statistics, thus the Know Your

    City campaign is the first step towards inclusive planning and development in

    African cities.

    1.2 Project Organisation

    This project was implemented under partnership between the United Cities

    and Local Governments of Africa (UCLG-A) and the Slum Dwellers

    International (SDI).

    The UCLG-A is the umbrella organization and a united voice and

    representative of local governments in Africa. It is an institution that gathers

    40 national associations of local government from all regions of Africa as well

    as over 2000 cities that have more than 100,000 inhabitants each. UCLGA

    represents nearly 350 million citizens. The Executive Committee of UCLGA

    passed a resolution to carry out joint work programme with SDI at the

    UCLGA meeting held in Dakar, Senegal, 26 April, 2011. Through a

    consultative process, the UCLG-A selected two of its members, the Lusaka

    City Council (Zambia), in the Southern Africa region, and the city of

    Ouagadougou (Burkina Faso), in West Africa, to participate in the pilot

    project.

    The SDI is an umbrella organization of federations formed by urban poor to

    engage in initiatives to upgrade slums and squatter settlements, secure

    tenure, develop new housing that low income households can afford and

    improve provision for infrastructure and services. SDI has a range of well-

    developed and tested tools that support communities from informal

    settlements to form community organizations, build the capacity of urban

    poor communities to enter a constructive dialogue with local authorities and

    collect information about the informal settlements and their development

    needs.

    The project was funded by the Cities Alliance (CA) through a grant of

    $74,825.00 with a focus to catalyze urban transformation processes that

    promote more inclusive cities; and advance collective know-how through

  • 8/10/2019 Know Your City Final Report- Lusaka

    4/32

    4

    learning distilled from project experiences. The United Cities and Local

    Governments World Secretariat headquartered in Barcelona was the fund

    recipient and disbursed on behalf of the Joint Work Programme.

    1.3 Project Activities and Results

    The core activities implemented through this project include:

    Engaging poor urban communities to work with the participating

    local authorities to develop inclusive cities;

    Mapping & enumerating all households in settlements within

    participating cities that are under threat of eviction and or identified

    for upgrading;

    Increasing the public knowledge & information of poor urban

    settlements & scaling up the programme;

    Designing and establishing an urban poor investment fund;

    Embarking on a home improvement project in George compound.

    Working jointly with local authorities, this programme consists of

    communities collecting information about their own slum communities, which

    will then build the knowledge capacity of slum dweller communities, local

    authorities, city planners and other stakeholders on the realities of informal

    settlements in the city where the Know Your City Project is implemented.

    Together, these groups can then use this information to examine critical

    issues such as the management and development of cities and re-evaluate

    the current policies to ensure that slums and slum dwellers are integrated

    into broader city development plans.

    Projected results for the pilot project also included:

    Availability of data and information for planning;

    Enhanced capacity for slum upgrading for local authorities and

    communities;

    Networking and knowledge management and sharing on slum

    upgrading;

  • 8/10/2019 Know Your City Final Report- Lusaka

    5/32

    5

    Established social investment fund for urban poor communities

    This report covers the Lusaka component of the Know Your City project.

    Know Your City Lusaka:

    The Lusaka component of the project had three main partners, Lusaka City

    Council; Peoples Process on Housing and Poverty in Zambia (PPHPZ); and

    Zambia Poor Peoples Federation (ZHPPF).

    As one of the two chosen cities for the implementation of the Know Your City

    Project, Lusaka embraced the project. With an already established

    federation, Zambia Homeless and Poor Peoples Federation (ZHPPF) and

    support NGO, Peoples Process on Housing and Poverty in Zambia (PPHPZ),

    the implementation of the Know Your City project took root quickly.

    Beginning enumerations in George Compound, the largest settlement in

    Lusaka, ZHPPF, PPHZ and participating community leaders began discussions

    with the Lusaka City Council (LCC) on how the city and slum communities

    can begin working together through this project. After the official opening of

    the Know Your City project in Zambia and the signing of a MoU between

    ZHPPF, PPHPZ and the LCC on 30 March 2012, the steering committee

    entitled the project steering committee was established. Composed of 4

    representatives from the informal settlements, 3 local authority staff and 2

    PPHPZ representatives, the committee met every month to manage the

    coordination and implementation of the Know Your City project in Lusaka,

    ensuring that each stakeholder plays his or her part in the process.

    Together the Project Steering Committee identified ten slum communities in

    which to roll out this project; however, within the projects 10-month

    timeframe only seven settlements were fully enumerated in the Lusaka

    region. Working hand-in-hand through joint-work team, community

    enumerators with the support of Lusaka city planners collected socio-

    economic information from slum dwellers in George Compound, Kalikiliki,

    Chipata, Mtendere East Compound, Zingalume compound, Chazanga and

  • 8/10/2019 Know Your City Final Report- Lusaka

    6/32

    6

    Chaisa compound. In addition to the enumeration information, the teams

    were able to compile and complete GIS maps in two of these settlements

    George and Kalikiliki compounds and a nearly complete map of the Mtendre

    East Compoundestablishing the spatial layout of housing units, water and

    sanitation facilities as well as other basic services facilities.

    The information collected under this project has equipped communities, as

    well as local authorities and other stakeholders, with a collective knowledge

    to strategically design, plan and implement programmes that address the

    needs of slum dwellers in these communities. Armed with this information,

    the LCC, PPHPZ, ZHPPF and these newly enumerated informal settlements

    have already begun discussions and designs for joint-work slum upgrading

    initiatives beginning with water and sanitation one of the greatest needs for

    all the communities where information was collected. Communities are

    dynamic and therefore keeping track of changes occurring within the

    community is important as well as remaining strategic in responding to

    urbanization and other factors that exacerbate poverty in these communities.

    2 Methodology and Technical Tools

    Under the paradigm that knowledge is power, the Know Your City Projectworks under the premise that a better knowledge of cities will help local

    authorities and slum dweller communities plan the future of their cities.

    However, it is more than just accessing knowledge but the process of

    gathering knowledge that is key. The previous, and all too common trend,

    has been the Lusaka city council research team imposing themselves on slum

    communities to collect information, which was often used against these

    populations rather than in an effort to assist the struggles faced by these

    communities. These professionals often approach these communities as

    merely beneficiaries and objects of study rather than city citizens with

    valuable knowledge and input about their own communities and innovative

    ideas to contribute to the development of slums. This invasion is often met

    with mistrust, misunderstanding and often hostility between the city and

  • 8/10/2019 Know Your City Final Report- Lusaka

    7/32

    7

    slum dweller communities, which in turn leads to false information or

    omissions because the slum populations fear the threat of forced eviction

    and/or other actions that detrimentally effect informal settlement

    communities.

    Moving away from this approach, the Know Your City project aims to

    reconcile these conflicts through joint-work partnerships between the city

    and slum dweller communities. Adopting the SDI core rituals of community-

    led enumerations, GIS mapping and savings schemes, the Know Your City

    project stimulates equal engagements between local authorities and slum

    dweller communities through these mobilizing tools, highlighting the value of

    the slum communities taking an active role in their own community

    upgrading. By starting at the beginning together, mobilizing and collecting

    information together, generates a level of trust and respect between these

    two parties, leading to changes in city practices that advocate the active

    participation of slum dwellers throughout the city planning process.

    Furthermore, through these mobilisation and information gathering tools,

    communities are empowered through the ownership of information they

    collected

    2. 1

    Key Tools:

    Community-led enumerations: these enumerations are led by trained

    community members who are responsible for going door-to-door throughout

    the whole informal settlement, ensuring that data is collected from every

    household and structure. The houses are grouped and numbered to ensure

    that data-collection is done correctly and completely inclusive of the full

    informal settlement. Using community created questionnaires, community

    enumerators are able to calculate: the general population of the settlement,

    average family size, education, economic activities, infrastructure, security of

    tenure, number of households, etc. The information from these

    questionnaires are then entered into a database where it is then sent through

    the statistical package for social sciences to produce manage, analyze and

    summarize the data. (Please refer to Appendix 1: Summary of Enumeration

  • 8/10/2019 Know Your City Final Report- Lusaka

    8/32

  • 8/10/2019 Know Your City Final Report- Lusaka

    9/32

    9

    of all the above, these savings schemes often become the heart of change in

    slum communities.

    3

    Project Process

    3.1 Community mobilisation, engagement and training

    Informal settlement dwellers were tasked with the responsibility to engage

    community members in the targeted settlements around the need to

    participate in the project. Mobilising communities around womens saving

    schemes and community-run enumerations, ZHPPF and PPHPZ were able to

    identify and recruit community leaders and enumerators in each of the

    identified informal settlements. Conducting door-to-door information

    sessions, ZHPPF and community-identified leaders mobilized community

    practitioners encouraging people to participate in the household surveys.

    They identified community stakeholders, who also helped them to identify

    potential participants and organize those who demonstrated interest in

    volunteering during the process.

    Federation members, who demonstrated expertise in the enumeration

    process, specifically questionnaire administration, trained a total of 210

    community enumerators in seven of the identified settlements. Community

    enumerators were introduced to the key survey tools and given an

    opportunity to practice before the actual enumeration exercise took place.

    Realizing that the community practitioners would be expected to map the

    targeted informal settlements, the community decided to request for support

    from the federation members in Zimbabwe to hold a workshop on GIS

    mapping. Six community practitioners were trained in GIS mapping, covering

    topics, including but not exclusive to: a basic introduction to GIS; the use of

    GIS information (spatial information); digitizing; and map production.

    3.2 Establishing a social fund for the urban poor: Womens Savings

    Schemes

  • 8/10/2019 Know Your City Final Report- Lusaka

    10/32

    10

    As one of the main objectives of the Know Your City Project, throughout the

    enumeration and mapping processes the enumerators and community

    mobilisers helped motivate the establishment of 10 new women-run savings

    schemes of about 50 members each in George and Chipata compounds.

    These 10 schemes have joined already existing savings schemes in pooling

    their collective savings into one account entitled the Swalisano Urban Poor

    Fund. This fund will then be used to finance the contributing slums upgrading

    projects.

    Through weekly meetings, each respective savings scheme calculates the

    savings collected, separating the funds into three categories: daily savings,

    health savings and the Swalisano Urban Poor Fund (UPF). Funds from daily

    savings are set-aside until members collectively decide to either evenly split

    the money or use the funds for a groups priority needs. Health savings are

    specifically collected to support group members if illness falls upon them or

    their family members. However, each member is required to contribute $2.00

    a month to the group Swalisano fund, which will then be added to a collective

    Urban Poor Fund (UPF) which is then used to finance slum upgrading projects

    in the slum communities. The money is then revolved back into the fund

    after the completion of one project to then finance future slum upgrading

    initiatives. In the final Know Your City reporting period, it was estimated that

    the 10 savings groups from George and Chipata Compound had already

    saved: $1478.00 in the collective Swalisano UPF, $84.00 in health funds and

    $400.00 in daily savings.

    3.3 Enumeration and mapping process

    Prior to the enumeration exercise, the targeted settlements would be zoned

    in sections and households would be given a special coding system to ensure

    that each household of the settlement is included in the enumeration. The

    team of enumerators would then be divided into two teams of 15 members

    each. Meeting each morning at the agreed upon hour, the 30 enumerators

    would collect the community-created questionnaires and any other materials

    they required. One of the teams would be tasked to go in the settlement

  • 8/10/2019 Know Your City Final Report- Lusaka

    11/32

    11

    numbering the structures, while the other would follow behind administering

    the questionnaire. At the end of each days work enumerators would meet to

    discuss the challenges that they face in the field so that the next days work

    would be better. It should be highlighted that all seven enumerations were

    entirely conducted by community practitioners in collaboration with Lusaka

    City Council community development officers.

    At the start of the project, enumerators were provided with a daily transport

    refund for those coming from outside the targeted community to meet

    together in a central area where they would collectively prepare their

    afternoon meals between suverying. This helped to create group cohesion

    and discussions among enumerators as well as improving the quality of the

    data that was being collected because they took these opportunities to go

    through each questionnaire together, beginning to screen and analyse the

    data.

    It was later discovered that this approach was both costly and time

    consuming. Enumerators commented on the time lost moving to and from

    this central area. To save time, it was agreed that enumerators would be

    given an amount equivalent to the cost of the food previously taken at the

    start of the project and the transport refund.

    Due to delays in availability of necessary satellite images and GIS equipment,

    the mapping aspect of the project was delayed until well after the

    enumeration process was under way in the seven settlements. After months

    of negotiations and engagement with the Lusaka City Council to acquire

    these satellite images, these images proved to be unclear and difficult to

    work with. The committee then decided that the attempt to use these

    satellite images should be abandoned and replaced by Google images. The

    mapping exercise finally began in October 2012, starting with the Kalikiliki

    settlement. Headed by the 6 member mapping team, who had been trained

    in Zimbabwe in April 2012 and retrained through a refresher course in

    October, community members were sensitized on the importance of mapping

    and how to map settlements using GIS.

  • 8/10/2019 Know Your City Final Report- Lusaka

    12/32

    12

    With the support of the GIS specialist who prepared and distributed the

    images to the community mapping team members, mapping teams made

    up of newly trained community members and one or two of the original six

    trained in Zimbabwe went out into the settlement, identifying individual

    structures on the ground and capturing additional information on the layout

    and building found in the settlement. The mapping team would normally be

    divided into groups of two where one person would read the map the other

    would capture information about the structures. Returning to the PPHPZ

    offices the teams would then digitize the maps in ArcGis and enter the

    corresponding data into the system.

    After entering all of the information into database, the community

    enumerators and mappers compiled and analyzed the data into settlement

    reports, which were then shared with the rest of the community, city

    planners, LCC, the Mayor of Lusaka and other stakeholders. Furthermore, the

    analysed data, reports and completed analysed GIS maps have been shared

    with the rest of the public through the LCC database.

    3.4 Utilisation of collected information

    Recognizing the value of the partnership between LCC and organized slum

    communities and the work taking place on the ground through the join-work

    teams, monthly meetings between all parties were conducted throughout the

    enumeration and mapping process discussing: updates on the work taking

    place, challenges, success and the way forward in terms of the Know Your

    City Project. These conversations, along with the resulting information

    developed from enumeration and mapping processes, incited discussions of

    future joint work slum upgrading projects between the city and slum dweller

    communities, the Lusaka City Council and Zambian Federation. Furthermore,the city of Lusaka, Peoples Process on Housing and Poverty in Zambia, and

    federation are taking steps to scale-up this project to a city-wide scale,

    completing the enumerations, mapping, profiling and reporting of the

    remaining slum communities in Lusaka.

  • 8/10/2019 Know Your City Final Report- Lusaka

    13/32

    13

    Upon the completion of the Know Your City Project, the alliance held a

    dialogue forum with the Lusaka City Council, community practitioners, and

    Ministry of Local Government officials to discuss the impact of the project as

    well as come up with a draft slum upgrading strategy. A total of 20 people

    attended this 2-day long forum. Continuing to work hand-in-hand with the

    LCC, PPHPZ and ZHPPF drafted the Lusaka Informal Settlement Upgrading

    Strategy. This document intends to provide a road map to improve the

    livelihoods of people living and working in Zambias informal settlements

    through the provision of security of tenure, housing improvement, income

    generation and physical and social infrastructure. The aim of this strategy

    document is to consolidate the efforts of all the relevant stakeholders

    involved in slum upgrading projects in Lusaka and develop a commonstrategy and implementation agenda in order to be able to move forward

    with the programme.(Please refer to Annex 5: Lusaka Informal Settlement

    Upgrading Strategy for more information).

  • 8/10/2019 Know Your City Final Report- Lusaka

    14/32

    14

    3.5Summary of project progress

    Project Title: Know Your City Project LusakaSummary of Project outcomes

    Activities planned No. Deliverables Deviation from

    original project

    design

    Reason for

    deviation

    Comment of assumptions

    constraints

    Preparation and

    signing of the

    Memorandum of

    understanding

    1 Signed M.o.U

    Between the

    Lusaka city

    council and

    informal

    settlement

    dwellers

    Planning meeting in

    all the ten informal

    settlements to beenumerated

    10 Detailed

    implementation

    plan and budgets

    Project Steering Committee was

    ambitious assuming that 10 settlements

    could be enumerated and mapped in 10-months. LCC and ZHPPF plan to finish

    the remaining 3 settlements even after

    the end of the Know Your City Pilot

    Project in Lusaka.

    Training of

    enumerators in

    each in each

    10 Trained

    enumerators

    It was assumed that the same

    community members would volunteer

    for the entire time it takes to enumerate

  • 8/10/2019 Know Your City Final Report- Lusaka

    15/32

    15

    settlement a settlement; however this proved to be

    impossible. So refresher courses on

    enumerations for those participants who

    joined the enumeration process later.

    Rolling out

    enumerations in

    each of the ten

    informal

    settlements

    7 Enumeration

    report

    Up to the end of the

    project, only two

    reports were

    produced

    Enumerations were

    conducted in 7

    settlements, but only

    managed to enter

    data for 2 settlements

    during the project

    timeframe

    Community participation was sometimes

    sporadic because some community

    members were demanding allowances

    and if not given they would withdraw

    their participation and this dragged

    implementation

    Preparation of

    maps related to

    enumerations

    2 Map samples for

    George

    Compound,

    Kalikiliki and

    Mtendere East

    It was planned that

    each of the 10-

    targeted informal

    settlements would be

    mapped.

    Within a limited

    timeframe proved a

    significant constraint

    on the projects

    progress. In the end

    only two settlement

    maps have been

    completed in full.

    Acquiring satellite images with an

    excellent resolution was a challenge and

    this made it difficult to do mapping at

    the same time with enumerations.

    Map and Geo-referenced data in

    10 settlements

    2 Geo-referencedmaps

    It was planned that10 selected informal

    settlements will be

    mapped and Geo-

    referenced

    It was discovered thatto be able to produce

    all the 10 maps, the

    alliance would require

    more time to

    implement because

    some of these

    settlements are quite

    big and mapping is

    Acquiring satellite images with anexcellent resolution was a challenge and

    this made it difficult to do mapping at

    the same time with enumerations.

  • 8/10/2019 Know Your City Final Report- Lusaka

    16/32

    16

    very time consuming.

    Set up savings

    schemes:

    Community Savings

    Schemes

    10 Establishment of

    functional saving

    schemes

    The concept of community savings is

    sold on the basis of members willingly

    saving money for various needs and

    community members are free to join or

    not.

    Forums of slum

    dwellers and local

    authority officials to

    meet to discuss

    outcomes, agree on

    priority upgrading

    intervention

    3 Prioritized

    intervention for

    upgrading

    It was planned that

    after every

    enumeration and

    mapping, community

    members would

    meet with their local

    authority leaders to

    discuss.

    Both parties unable to

    meet together for

    more than the brief

    meetings on the

    project progress. Only

    three of these priority

    need intervention

    meetings took place.

    Know Your City

    Sensitization

    Workshop -

    1 Increased

    awareness on

    informal

    settlements

    It was assumed that the project would

    formal change city planning practices

    and policy; however, this type of change

    takes time and many negotiations. The

    Know Your City Sensitization Workshop

    was an opportunity to share ideas andbegin these negotiations for policy

    change that is pro-poor and inclusive of

    slum dweller communities. The Project

    Steering Committee drafted theLusaka

    Informal Settlement Upgrading

    Strategy, which was discussed during

    the workshop.

  • 8/10/2019 Know Your City Final Report- Lusaka

    17/32

    17

    4.

    Challenges

    As a pilot project, it is expected that unforeseen challenges and obstacles would

    arise. Some of these challenges were met with simple solutions, while others faced

    long periods of reflection before a sustainable solution was found. However, these

    obstacles serve to improve upon the Know Your City Project and similar

    programmes.

    The main challenges faced during this pilot were:

    Limitations of timeframe:As mentioned earlier, the 10-month timeframe

    allocated for the pilot project proved limited, not taking into the amount of

    time taken for mobilisation, enumerations, profiling and mapping. All these

    activities take time and require patience; if rushed, the resulting information

    will prove inadequate to base the success of future slum upgrading

    programmes. Furthermore, due to the unforeseen obstacles that were

    presented during the pilot in Lusaka, the project steering committee was

    unable to enumerate and map the 10 settlements originally identified.

    Limited materials: During the project implementation thousands of

    questionnaires had been generated and were supposed to be entered and

    analyzed. The major challenge had been that data entry has been so slow

    simply because there were few computers and people to enter it and it was

    taking long to finish and produce reports. There were only three slum youths

    entering data since there were only three computers dedicated to the Know

    Your City project. This affected the pace at which progress was being made.

    To remedy this problem the Lusaka City Council seconded two of their

    members of staff from the research department to beef up the data entry

    team. It had also been proposed that data be entered manually to produce

    draft results that the community and the council could use but will have to be

    correlated with the ones to be produced at the later stage through the

    statistical Package for Social Sciences (SPSS).

  • 8/10/2019 Know Your City Final Report- Lusaka

    18/32

    18

    Obstacles surrounding community mobilisation and training: Another

    challenge that the project faced was lack of consistent community

    participation especially from members that are not part of the federation of

    the urban poor. The project was being piloted in settlements where major

    international organisations have been operating and have been giving

    incentives to induce community participation. This made it very difficult to

    solicit for community participation where no allowances would be given. To

    address this challenge the federation had to re-sensitize non federation

    members on the importance of community participation in their own

    development processes and managed to get more non federation members

    to participate. They had to appeal to the development value of the

    enumerations and mapping in order to get non-federation communitymembers to get on board.

    In addition, it was discovered that the community mapping team did not

    thoroughly understand the mapping process and its technicalities hence

    errors were noticed in the data that was being generated. The exercise was

    then halted to reorient the mapping team on the type and quality of spatial

    data that they should collect. After the mapping team members were

    reoriented, the alliance was able to correctly map Kalikiliki and Mtendere

    compound.

    Insufficient funds and irregular fund disbursement: With a budget

    limited to just over USD35,000.00 for each pilot city participating in the

    Know Your City Project, it was a challenge for the Lusaka team to meet all

    the objectives and deliverables for the project on a limited budget. Lusaka

    was unable to enumerate and map the 10 slum communities they originally

    hoped to implement the Know Your City Project and when the money was not

    sufficient SDI pre-financed activities. It was also highlighted that mapping,

    enumerations and survey drafting all take time and a certain level of

    technological support that is often out of reach for slum communities.

  • 8/10/2019 Know Your City Final Report- Lusaka

    19/32

    19

    Furthermore, the extended delays in disbursement of project funds that were

    faced during the pilot projects had a negative affect on the project.

    Community members became discouraged and dropped out of the process

    returning to their daily activities. This then caused project activities to be

    suspended due to the lack of funds and volunteers; however, when activities

    were to be resumed it was necessary to remobilise enumerators and

    surveryers to regain their commitment to the project.

    5. Key Lessons Learned

    Community participation has proved to be vital in the sustainability of this and any

    future partnerships between informal settlements and municipalities. This project

    has managed to change that kind of perception and demonstrate that informal

    settlement dwellers have a role to play in their development process if only they

    are respected for who they are and what they can contribute to the process.

    Although the overall project was successful on multiple levels, there are key lessons

    that were learned through this pilot project in Lusaka that can help refine the

    project for replication and scaling up:

    5.1

    Lessons surrounding Participation: Mobilising communities:The mobilisation of community members to

    participate in the enumeration process takes time and often times, the

    community has a hard time understanding the importance of volunteering

    because they have been used to being paid by other international NGOs to

    develop their communities. These obstacles can delay project timeframes

    and can be discouraging; however, by using already mobilised community

    members and members of savings schemes as community mobilisers, with

    time slum communities will begin to see the benefits of community-run

    enumerations and mapping.

    Rotation of community enumerators:Maintaining the same community

    enumerators throughout the enumeration and profiling process of a slum

  • 8/10/2019 Know Your City Final Report- Lusaka

    20/32

    20

    settlement can cause some of the enumerators to request payment for the

    enumeration work. Since these volunteers are abandoning their other jobs or

    income generating activities to participate in the enumeration process,

    expecting them to work on community enumerations continuously until its

    completion is unreasonable unless they receive a daily or weekly stipend

    besides lunch. After experiencing this situation in some of the slum

    communities being enumerated, the Lusaka team began to rotate their

    community enumerators, recruiting and training new identified community

    enumerators to work for a week or so and then repeating this process with a

    new selection of community members. However, this process requires that a

    number of enumeration and mapping trainings take place to train the newly

    recruited enumerators or refresh community enumerators who had to leavethe process for a time to return to their income generating activities.

    5.2 Lessons surrounding Partnerships:

    Importance of transparency:One of the major lessons that this project

    has presented is that transparency in any partnership is critical to the

    success of any project embarked on. Throughout the process in Lusaka, the

    project budget was shared with the relevant stakeholders, helping to address

    unnecessary expectations from both the community members and council

    staff. The council has even gone an extra mile to provide their staff with the

    support necessary to enable them work with communities during this current

    and future projects. This of course was after the realization that the project

    could not meet all the costs and that the information that is being collected

    will be beneficial to both the council and the community hence the need to

    commit resources to it.

    Collaboration between the formal and informal:The second lesson is

    that the project has revealed that it is very possible for professionals to work

    side by side with non-professionals and produce work that is professional.

    The project has proved once again that when communities work side by side

    with city officials it helps to address apprehensions from community

  • 8/10/2019 Know Your City Final Report- Lusaka

    21/32

    21

    members about the council coming to survey their community for a possible

    eviction especially in communities with undefined legal status. The duality of

    the authority of the city planners validated the profiling and enumeration

    being conducted by community members while the participation and

    explanations presented by community enumerators about the project and

    why this information was being gathered gave comfort to the rest of the

    community that the information would not be used to do harm and disrupt

    the lives of these informal populations. The roles of each party compliment

    one another and provided a well-rounded approach to information gathering.

    6.

    Assessment of results

    One of the deliverables of the project is to generate information that can be used

    for planning through sustained partnerships between the informal settlements and

    their respective municipalities and the project is slowly achieving that. The project

    has fostered a partnership between the council and informal settlements that

    guarantees future collaboration on any slum-upgrading project. The community

    feels comfortable working hand-in-hand with professionals as equals.

    Changing the perception of slum dwellers in the eyes of local authorities, this

    project has created a sense of trust and respect between both parties. In terms of

    meeting the project objectives and deliverables, the pilot project in Lusaka has met

    the main objective and developed the core deliverables required. However, more

    than just the listed objectives, this project has achieved the ultimate objective by

    inspiring a partnership between the Lusaka City Council and slum dweller

    organizations and communities. This partnership has not only fostered working

    relationships between communities and local authorities, but has created a space

    for slum dwellers to play an active role in city development and planning.

    Future plans are for this partnership to continue through other slum upgrading

    initiatives, using the data collected through the Know Your City project as the basis

    for future programmes in Lusaka. Currently the slum dweller communities, PPHPZ

    and the LCC are designing projects around water and sanitation, lack of secure

  • 8/10/2019 Know Your City Final Report- Lusaka

    22/32

    22

    tenure and poor structured housing - all community-identified priority problems in

    the slums of Lusaka. Beginning with George Compound the first informal

    settlement enumerated and mapped during the Know Your City Project designs

    and plans for affordable sanitation facilities and home improvement joint-work

    projects are underway, along with negotiations for land tenure for identified slum

    communities.

    Furthermore, the LCC, PPHPZ, ZHPPF and participating slum communities plan to

    continue with the project on their own, enumerating and mapping all the informal

    settlements in the Lusaka area. In addition to this initiative, all parties hope to

    scale-up this programme to a nation-wide scale, where Lusaka would serve as a

    learning centre for other municipalities and slum dwellers interested in

    implementing a similar programme in their own cities. It is hoped that these

    initiatives will lead to the adoption of formal policy change and inclusive city

    planning initiatives, which were outlined and presented in the Lusaka Informal

    Settlement Upgrading Strategydrafted by the project steering committee.

  • 8/10/2019 Know Your City Final Report- Lusaka

    23/32

    23

    Appendix 1: Summary of Enumeration Reports

    Executive summary: Zingalume compound

    This paper presents the summary of the findings of the community-led informationgathering in Zingalume compound about the social and economic condition of the

    settlement. Community members carried out the exercise with support from the

    Lusaka City Council community development officers.

    Zingalume compound started as an overspill of the neighbouring George compound

    in the late 1980s. It was established to accommodate households that were being

    displaced in George compound to pave way for infrastructure development such as

    roads and water pipes.

    Preliminary findings of the survey indicate that the settlement has an estimated

    population size of 6118 residents with 874 households. 76 percent of the housing

    units are mostly built from concrete blocks with a few built from anthill clay. The

    survey also revealed that 79.1 percent of the households are renting the houses in

    which they are staying. 61.8 of those who own houses or land have secure tenure

    in form of occupancy certificates that give them land use rights for a period of 30

    years and only 13 percent have full title deeds.

    51 of the total number of respondents are either in full time or part time

    employment while 49 percent are engaged in self help economic activities such as

    vending. The preliminary results also show that 86 percent of the interviewed

    households are sharing 21 water points that are religiously controlled to just allow

    60 litres of water per household per day.

    The survey also found out that 98 percent of the respondents said that they are

    using a traditional pit latrine as a form of sanitation option and in most cases theyare either full or poorly built. The settlement has only 86 pit latrines and these are

    shared between 5 to 15 persons per pit latrine.

  • 8/10/2019 Know Your City Final Report- Lusaka

    24/32

    24

    50 percent of the residents have access to electricity which is sporadically supplied

    and so during blackouts residents resort to using charcoal and paraffin as

    alternative sources of heating and lighting energy respectively.

    There is no proper waste management system in the areas and so residents just digand bury their waste. The settlement has experienced partial floods during heavy

    rainy seasons that sometimes have washed away poorly constructed houses and

    toilets. The community identified increased access to clean water, more schools,

    proper roads and improved quality of houses and toilets as priority development

    challenges that need to be addressed urgently.

    Given the above findings, the study made the following recommendations as the

    road map to addressing the challenges identified.

    There is need for community members to engage their ward councilor over

    access to occupancy certificates that will encourage them to invest in their

    structures and sanitation facilities.

    Community members should get mobilized and start up community based

    enterprise that will address waste management in the community as well as

    create income for those doing formally employed.

    There is need to increase access to proper sanitation in the settlement so

    that there is decency in the settlement.

  • 8/10/2019 Know Your City Final Report- Lusaka

    25/32

    25

    Figure 1 Summary of enumeration results for Zingalume

    Thematic Area Information collected Statistics

    Settlement profileZINGALUMECOMPOUND

    Location (City/Country)LUSAKA

    ZAMBIA

    ValuePercentage (%)

    Total Number of structures Enumerated: 1761 100

    Total number of households captured 874 100

    Total number of households enumerated 874 92.6

    Population profile Total number of people in enumerated households 6118 92.6

    Household details gender of head of household 599 Male68.5

    274Female

    31.4

    number of people in household 6118

    Estimated population 7000

    Residential structuredetails

    Average household size 6

    average number of rooms per household 2

    Proportion of concrete dwellings 664 76.0

    Proportion of ant-hill clay dwellings 26 3

    Tenure details Number of households renting 691 79.1

    Number of households owned by occupants 138 15.8

    Number of households with certificates of occupancy 540 61.8

    Number of households with formal title deeds 114 13

    Employment/Income Proportion of households with head in formal employment 332 38

  • 8/10/2019 Know Your City Final Report- Lusaka

    26/32

    26

    Proportion of households with head in informal employment 120 13.7

    Water Access Proportion of households accessing water from borehole 69 7.9

    Shallow wells 6 0.7

    Yard taps 35 4

    Kiosks 28 3.2

    Proportion of households sharing water point 754 86

    Proportion of households owning water point 113 12.9

    Sanitation Proportion of households using pit latrine 857 98.1

    Proportion of households sharing pit latrine with neighbors 56 6.4

    Average number of people/households per toilet 15 69.7

    Number of pit latrines toilets available86

    Other servicesAvailability of formal electricity connection in dwelling (number ofHH)

    467 50

    Available markets 1

    Available clinics 1

    Availability of other lighting energy sources (if no formalconnection)

    Waste disposal mechanism dig and bury

    infrastructure Available state schools 2

    Available churches 4

    Available bars 41

    Available playing space none

    Available shops(Grocery shops, butcheries etc) 19

    Disaster historyMain environmental hazards (floods, mudslides, heavy rains,collapsed houses)

    Floods

    Developmental priorities Most urgent needs

    water

    roads

    schools

    Improvedhousing

  • 8/10/2019 Know Your City Final Report- Lusaka

    27/32

    27

  • 8/10/2019 Know Your City Final Report- Lusaka

    28/32

    28

    Executive summery George compound

    This paper presents the summary of findings of the enumeration carried out in

    George compound to establish the living conditions, the socio-economic aspects of

    community life as well as access to basic service delivery. The survey was

    managed, controlled and propelled by the community members who received

    capacity on how to collect data and analyze the data.

    The findings of the study reveal that the settlement has a total of 11,023

    households with an estimated population of 66,138. The houses in the settlement

    are predominantly built from concrete blocks, mud bricks and anthill clay and are

    generally poorly constructed. The findings show that the common type of sanitation

    is the traditional pit latrine making up 99.2 % of households. This presents a

    serious sanitation and environmental problem in the settlement in the sense that

    many households are sharing traditional pit latrines as many families especially

    tenants have no access to their own toilets. Specifically, the enumeration report

    indicates that 62.9 % of households share sanitation facilities between 6 and 15

    members. This places users at a risk of contracting diseases due to the unhygienic

    nature of the sanitation. On the other hand, the use of traditional pit latrines poses

    a serious environmental hazard as ground water is susceptible to pollution.

    The common water sources for the community are communal water taps and the

    settlement has about 185 water kiosks. These water points are controlled and

    residents are only allowed to get about 100 litres of water per day. The study

    revealed that residents need more litres of water than what they are currently

    accessing and so they are forced to get water from shallow wells which are

    contaminated.

    In summary the report makes the following recommendations about the settlement

    The community needs improved access to reliable and safe water source.

    There is need to increase capacity of residents to implement and manage

    sanitation infrastructure other than pit latrines and other conventional

    sanitation facilities.

  • 8/10/2019 Know Your City Final Report- Lusaka

    29/32

    29

    The community need to be mobilized to enable them to start saving for their

    toilets as well as connections to water

    There is need to extend the period that households have access to communal

    taps and also increase the amount of water they get per day.

    The community has very poor sanitation facilities, which are in deplorable

    conditions; this challenge is likely to trigger a serious outbreak of diseases in

    the settlement.

  • 8/10/2019 Know Your City Final Report- Lusaka

    30/32

    30

    Figure 2 Summary of enumeration results for George

    Thematic Area information collected Statistics

    Settlement profileGEORGE

    COMPOUND

    Location (City/Country) LUSAKA ZAMBIA

    Value Percentage(%)

    Total Number of structures Enumerated: 16,520 100

    Total number of households captured 11,908 100

    Total number of households enumerated 11,023 92.6

    Population profile Total number of people in enumerated households 66,138 92.6

    Household details gender of head of household 40,476 Male 68.

    25,000 Female 37.8

    number of people in household 66,138

    Estimated population 71448

    Residentialstructure details

    Average household size 6

    average number of rooms per household 2

    Proportion of concrete dwellings 7,665 69.5Proportion of ant-hill clay dwellings 259 2.3

    Tenure details Number of households renting 7,930 71.9

    Number of households owned by occupants 1,752 15.9

    Number of households with certificates of occupancy 6,019 54.6

    Number of households with formal title deeds 1,605 14.6

    Employment/Income

    Proportion of households with head in formal employment 3,720 33.7

    Proportion of households with head in informal employment 1,216 11.0

    Water Access Proportion of households accessing water from borehole 287 2.6

  • 8/10/2019 Know Your City Final Report- Lusaka

    31/32

    31

    Thematic Area information collected Statistics

    Shallow wells 211 1.9

    Yard taps 403 3.7

    kiosks 800 7.3

    Proportion of households sharing water point 6,620 60.1

    Proportion of households owning water point 695 6.3

    Sanitation Proportion of households using pit latrine 8,906 80.8

    Proportion of households sharing pit latrine with neighbours 825 7.5

    Average number of people/households per toilet 16

    Number of pit latrines toilets available3153

    Other servicesAvailability of formal electricity connection in dwelling (number ofHH)

    5,080 46.1

    Available markets 1

    Available clinics 1

    Availability of other lighting energy sources (if no formal connection) 3,363 30.5

    Waste disposal mechanism dig and bury

    infrastructure Available state schools 2

    Available churches 27

    Available bars 45

    Available playing space 16

    Available shops(Grocery shops, butcheries etc) 243

    Disaster historyMain environmental hazards (floods, mudslides, heavy rains,collapsed houses)

    Floods 2009

    Developmental

    prioritiesMost urgent needs

    Toilets

    Water

    Roads

    schools

  • 8/10/2019 Know Your City Final Report- Lusaka

    32/32