kt psdm process application leony y. singson june,2010
TRANSCRIPT
KT PSDM Process Application
LEONY Y. SINGSON JUNE ,2010
KT PSDM Process Application
ISO 14001:2004CI/3414I/03/12/361
CIP/3414I/03/12/361
ISO 9001:2000
KT PSDM Process Application
Universal Robina Corporation
Packaging Division - BOPP Films
KT PSDM Process Application
COMPANY PROFILECOMPANY PROFILEPackaging Division
UNIVERSAL ROBINA CORPORATION – PACKAGING DIVISIONIS AN ISO 9001:2008 & 14001:2004 CERTIFIED PLANT CAPABLE OF PRODUCING MORE THAN 30,000 MT OF
BI-AXIALLY ORIENTED POLYPROPYLENE (BOPP) FILMS PER YEAR.
• APPLICATIONS
- PLAIN FILM for Printing, Lamination & flower packaging
- TAPE FILM for Pressure sensitive adhesive tape application
- HEATSEALABLE FILM for printing, lamination and over wrap
- CIGARETTE FILM for Tobacco Industries
- WHITE FILM for soap, chocolate wrapping & labels
- MATT FILM FOR Printing & lamination for brochures & poster.
- METALLIZABLE FILM for Vacuum Metallizing
KT PSDM Process Application
Packaging Division
OVERVIEW OF THE PROCESSOVERVIEW OF THE PROCESS
Two Station TurretMain line
Ageing Rack Main Slitter
KT PSDM Process Application
PROBLEM STATEMENTPROBLEM STATEMENT
On time and in full (OTIF) delivery commitment On time and in full (OTIF) delivery commitment
below the target below the target
INSTRUCTIONS
KT PSDM Process Application
Date Schedule of Item
Actual Delivery
On Time % OTIF %Oct-09 227 221 97.36% 191 84.10%Nov-09 395 394 99.75% 217 54.90%Dec-09 374 374 100.00% 273 73.00%Jan-10 289 287 99.31% 181 62.63%Feb-10 460 458 99.57% 328 71.30%Mar-10 331 301 90.94% 231 69.79%Apr-10 305 305 100.00% 245 80.33%May-10 327 323 98.78% 262 80.12%Average 338.50 332.88 98.21 241 72.02
DELIVERY COMMITMENT MONITORING OCT2009 – MAY2010
KT PSDM Process Application
BACKGROUND OF THE PROBLEMBACKGROUND OF THE PROBLEM (What is the current scenario and assumptions regarding the problem? What was the situation or concern that had developed prior to the application of KT process? How were you dealing with this issue prior to the application of KT process?)
•Perceived unreliable supplier
•Projected opportunity loss per month = Php5.18M
CHALLENGE
KT PSDM Process Application
APPLICATION OF KT PROCESSAPPLICATION OF KT PROCESS (How was the challenge addressed? What KT processes and supporting methodologies were used? How were they implemented by KT and by you? How has KT made a difference or changed the way issues are resolved?)
After the problem analysis, we established a method that keep analysis visible to everybody. Then we identify Possible
Causes using DA.
RESPONSE TO THE CHALLENGE
KT PSDM Process Application
Line Component
Reason for downtime
No. of Occurrences
No. of Hours lost Remarks
Jan Feb Mar Apr Jan Feb Mar Apr
Edge trim grinder
Grinder overloadEdge trim grinder motor drive fuses blows
0 9 10 21 0 30.
546.7
63.8
Fixed on April 18 – no recurrence since
Pre-dosing system
System faultSystem shows negative weight then stops fill/refill cycle and eventually shuts down the line
0 0 2 11 0 0 7 16
Still a recurring problem – we have asked for Bruckner's help to improve cooling in the area and improving cooling of electronics
Main dosing system
Valve MalfunctionMain dosing slide valve goes out of position due to mechanical blockage in the slide guides mainly due to PP powder accumulation
10 0 1 2 45.2
0 7.4 9.2
Fixed in January by reshaping slide valve
Chiller #3
Chiller #3 was not workingThis cause high temperature of Chill roll and water bath
3 0 0 0 10 0 0 0
Fixed in February after rehabilitation work of chiller #3
Chill rolling walker displacing motor
Motor based detachedThis caused wrong position of water bath vs Chill roll
4 0 0 0 18.8
0 0 0 Fixed
MAJOR / CHRONIC DOWNTIME FOR LINE 2 FROM JANUARY TO APRIL 2010
KT PSDM Process Application
Line Component
Reason for downtime
No. of Occurrences
No. of Hours lost Remarks
Jan Feb Mar Apr Jan Feb Mar Apr
Pull rolling walker system
Loose drive belt of pull rolling walker systemBelt was already worn out
0 3 0 0 0 11 0 0Fixed, replaced belt and adjusted tension
Hot Oil burner Burner faultFound defective relay for the burner firing sequence
0 0 5 0 0 0 14.4
0Fixed
WATER REMOVAL BLOWER
Stuck up blowerUpon inspection; it was found that the blower was running above the rated speed – leading to frequent failures
0 0 1 0 0 0 8 0
FixedWe ran slow speed in March while the blower was out
COMPUTER SERVERHard disk for server defective
1 0 0 0 352
0 0 0
FixedServer and disk drive imported from Germany
KT PSDM Process Application
Risk Probability Weight
Plant Unscheduled Shutdown
10 10 100
In House Rejects above target of 5%
5 5 25
Realistic and Workable Mainline Scheduling
5 4 20
No Sales Order due to Credit Concerns
10 5 50
KT PSDM Process Application
Risk Probability Weight
Hold Delivery 10 4 40
Truck Availability
10 2 20
Conclusion:
Plant unscheduled shutdown is the main root cause of OTIF delivery commitment lower than target
KT PSDM Process Application
List of possible causes
POSSIBLE CAUSES RISK PROBABILITY WEIGHT
1. Ageing Machineries 7 6 42
2 Lack of dedicated personnel to handle Maintenance
Planning5 5 25
3. No established Preventive Program 8 8 64
KT PSDM Process Application
ACTION PLANS
Corrective ActionsRESPONSIBLE
PERSONTIME FRAME
1. Complete audit of Machines performance
RPM July 2010
2. Rehabilitation of machines RPM 6
months to 1 year
3. Assign a dedicated maintenance planner
HPCJune 2010
4. Implementation of comprehensive preventive maintenance program
Planning Engineer
ongoing
KT PSDM Process Application
Potential Problem Analysis
Potential Problem Contingent Action Triggers
1. Incomplete Audit of Machines Performance
Hire competent Consultant
No accomplishment
2. No available Spare Parts
Consult for Parts modification
Failure to comply
KT PSDM Process Application
FINAL RESULTS (What solution was chosen? What results were achieved? What were some key learnings from the experience?)
Audit and evaluate machine condition, continuously implement comprehensive maintenance program that
will eventually lead to minimum unscheduled downtime and optimize plant operations.
Action plans that make good score and produced results were generated and implemented within define
time frame.
RESULTS
KT PSDM Process Application
THANK YOU