l. greiner 1fee 2014 – star pxl vertex detector star hft lbnl leo greiner, eric anderssen, giacomo...

31
L. Greiner 1 FEE 2014 – STAR PXL Vertex Detector STAR HFT STAR HFT LBNL Leo Greiner , Eric Anderssen, Giacomo Contin, Thorsten Stezelberger, Joe Silber, Xiangming Sun, Michal Szelezniak, Chinh Vu, Howard Wieman, Sam Woodmansee UT at Austin Jerry Hoffman, Jo Schambach PICSEL group of IPHC- Strasbourg (Marc Winter et al.,) Experience from construction and operation of the first Vertex Detector based on MAPS

Upload: naomi-hall

Post on 17-Jan-2016

226 views

Category:

Documents


3 download

TRANSCRIPT

Page 1: L. Greiner 1FEE 2014 – STAR PXL Vertex Detector STAR HFT LBNL Leo Greiner, Eric Anderssen, Giacomo Contin, Thorsten Stezelberger, Joe Silber, Xiangming

L. Greiner 1FEE 2014 – STAR PXL Vertex Detector

STAR HFTSTAR HFT

LBNLLeo Greiner, Eric Anderssen,

Giacomo Contin, Thorsten Stezelberger, Joe Silber, Xiangming Sun, Michal Szelezniak, Chinh Vu,

Howard Wieman, Sam Woodmansee

UT at AustinJerry Hoffman, Jo Schambach

 PICSEL group of IPHC-Strasbourg    (Marc Winter et al.,)

Experience from construction and operation of the first Vertex Detector

based on MAPS

Page 2: L. Greiner 1FEE 2014 – STAR PXL Vertex Detector STAR HFT LBNL Leo Greiner, Eric Anderssen, Giacomo Contin, Thorsten Stezelberger, Joe Silber, Xiangming

2FEE 2014 – STAR PXL Vertex DetectorL. Greiner

STAR HFTTalk Outline

• STAR vertex detector upgrades at RHIC.• Pixel detector design and characteristics.• Sensors and mechanics.• Detector assembly and integration with lessons

learned.• Installation for 2014 run and first results.• Lessons learned and outlook.

Page 3: L. Greiner 1FEE 2014 – STAR PXL Vertex Detector STAR HFT LBNL Leo Greiner, Eric Anderssen, Giacomo Contin, Thorsten Stezelberger, Joe Silber, Xiangming

3FEE 2014 – STAR PXL Vertex DetectorL. Greiner

STAR HFTPXL in STAR Inner Detector UpgradesTPC – Time Projection Chamber(main tracking detector in STAR)

HFT – Heavy Flavor Tracker SSD – Silicon Strip Detector

r = 22 cm IST – Inner Silicon Tracker

r = 14 cm PXL – Pixel Detector

r = 2.8, 8 cm

We track inward from the TPC with graded resolution:

TPC SSD IST PXL~1mm ~300µm ~250µm <30µm

Direct topological reconstruction of Charm

vertex

Page 4: L. Greiner 1FEE 2014 – STAR PXL Vertex Detector STAR HFT LBNL Leo Greiner, Eric Anderssen, Giacomo Contin, Thorsten Stezelberger, Joe Silber, Xiangming

4FEE 2014 – STAR PXL Vertex DetectorL. Greiner

STAR HFTPXL Detector Design

Mechanical support with kinematic mounts (insertion side)

Insertion from one side2 layers5 sectors / half (10 sectors total)4 ladders/sector

Aluminum conductor Ladder Flex Cable

Ladder with 10 MAPS sensors (approx. 2×2 cm each)

carbon fiber sector tubes (~ 200 µm thick)

20 cm

Page 5: L. Greiner 1FEE 2014 – STAR PXL Vertex Detector STAR HFT LBNL Leo Greiner, Eric Anderssen, Giacomo Contin, Thorsten Stezelberger, Joe Silber, Xiangming

5FEE 2014 – STAR PXL Vertex DetectorL. Greiner

STAR HFT

2 m (42 AWG TP)11 m (24 AWG TP)

100 m (fiber optic)

Highly parallel system

4 ladders per sector 1 Mass Termination Board (MTB) per sector 1 RDO board per sector 10 RDO boards in the PXL system

RDO motherboard w/ Xilinx Virtex-6 FPGA

RDO PC with fiber link to RDO board

Mass Termination Board (signal buffering) + latch-up protected power

PXL Detector Basic Unit (RDO)

Clk, config, data, powerClk, config, data

PXL built events

Trigger, Slow control,Configuration,etc.

Existing STAR infrastructure

PXLSector

Page 6: L. Greiner 1FEE 2014 – STAR PXL Vertex Detector STAR HFT LBNL Leo Greiner, Eric Anderssen, Giacomo Contin, Thorsten Stezelberger, Joe Silber, Xiangming

6FEE 2014 – STAR PXL Vertex DetectorL. Greiner

STAR HFTDetector Design Characteristics

DCA Pointing resolution (12* 24 GeV/pc) m

Layers Layer 1 at 2.8 cm radius

Layer 2 at 8 cm radius

Pixel size 20.7 m X 20.7 m

Hit resolution 3.7 m (6 m geometric)

Position stability 6 m rms (20 m envelope)

Radiation length first layer X/X0 = 0.39% (Al conductor cable)

Number of pixels 356 M

Integration time (affects pileup) 185.6 s

Radiation environment 20 to 90 kRad / year

2*1011 to 1012 1MeV n eq/cm2

Rapid detector replacement ~ 1 day

356 M pixels on ~0.16 m2 of Silicon

* Simple geometric component, cluster centriod fitting gives factor of ~1.7 better.

Page 7: L. Greiner 1FEE 2014 – STAR PXL Vertex Detector STAR HFT LBNL Leo Greiner, Eric Anderssen, Giacomo Contin, Thorsten Stezelberger, Joe Silber, Xiangming

7FEE 2014 – STAR PXL Vertex DetectorL. Greiner

STAR HFTPXL detector Ultimate-2 Sensor• Reticle size (~ 4 cm²)

• Pixel pitch 20.7 μm • 928 x 960 array ~890 k pixels

• Power dissipation ~170 mW/cm² @ 3.3V (air cooling)• Short integration time 185.6 μs• In pixel CDS• Discriminators at the end of each column (each row

processed in parallel)• 2 LVDS data outputs @ 160 MHz• Zero suppression and run length encoding on rows

with up to 9 hits/row.• Ping-pong memory for frame readout (~1500 hits

deep)• 4 sub-arrays to help with process variation• JTAG configuration of many internal parameters.• Individual discriminator disable, etc.• Built in automated testing routines for sensor probe

testing and characterization.• High Res Si option – significantly increases S/N and

radiation tolerance.• Sensors thinned to 50 µm.

Developed by PICSEL group of IPHC-Strasbourg

Optimized for the STAR environment

Page 8: L. Greiner 1FEE 2014 – STAR PXL Vertex Detector STAR HFT LBNL Leo Greiner, Eric Anderssen, Giacomo Contin, Thorsten Stezelberger, Joe Silber, Xiangming

8FEE 2014 – STAR PXL Vertex DetectorL. Greiner

STAR HFTPXL Ladder AssemblyPrecision vacuum chuck fixtures to position sensors by hand.

Sensors are positioned with butted edges. Acrylic adhesive prevents CTE difference based damage.

Weights taken at all assembly steps to track material and as QA.

Assembled ladder

Cable reference holes for assembly

Hybrid cable with carbon fiber stiffener plate on back in position to glue on sensors.

Sensor positioning

FR-4 Handler

Page 9: L. Greiner 1FEE 2014 – STAR PXL Vertex Detector STAR HFT LBNL Leo Greiner, Eric Anderssen, Giacomo Contin, Thorsten Stezelberger, Joe Silber, Xiangming

9FEE 2014 – STAR PXL Vertex DetectorL. Greiner

STAR HFTSector and detector half assembly

Metrology picture

SectorsLadders are glued on carbon fiber sector tubes in 4 stepsPixel positions on sector are measured and related to tooling ballsAfter touch probe measurements, sectors are tested electrically for damage from metrology

Detector halfSectors are mounted in dovetail slots on detector halfMetrology is done to relate sector tooling balls to each other and to kinematic mounts Detector half mapped

Sector assembly fixture

A detector half

Sector in the metrology setup

Page 10: L. Greiner 1FEE 2014 – STAR PXL Vertex Detector STAR HFT LBNL Leo Greiner, Eric Anderssen, Giacomo Contin, Thorsten Stezelberger, Joe Silber, Xiangming

10FEE 2014 – STAR PXL Vertex DetectorL. Greiner

STAR HFTYieldssensor yield

sensors after thinning probe testedafter probe testing (tier 1&2) Probe testing yield

batch 1 1152 1003 1003 464 0.46

batch 2 1152 1139 1056 546 0.52

batch 3 1248 1174 357 217 (new probe card) 0.608

yield 0.934 0.508

ladder yield

ladders assembled

after assembly + bonding

after encapsulation

after sector mounting after metrology

Tot 113 103 85 53 48

Tested 92 59 53 48Good 84 54 48 48

yield 0.91 0.92 0.91 1.00

Production is still ongoing.

Page 11: L. Greiner 1FEE 2014 – STAR PXL Vertex Detector STAR HFT LBNL Leo Greiner, Eric Anderssen, Giacomo Contin, Thorsten Stezelberger, Joe Silber, Xiangming

11FEE 2014 – STAR PXL Vertex DetectorL. Greiner

STAR HFTPXL insertion

• Mechanics

PXL has a unique mechanical design. The PXL detector is inserted along rails and locks into a kinematic mount on the insertion end of the detector. This allows for rapid (1 day) replacement with a characterized spare detector.

Yes – we push it in by hand

Kinematic mounts Insertion of PXL detector

Page 12: L. Greiner 1FEE 2014 – STAR PXL Vertex Detector STAR HFT LBNL Leo Greiner, Eric Anderssen, Giacomo Contin, Thorsten Stezelberger, Joe Silber, Xiangming

12FEE 2014 – STAR PXL Vertex DetectorL. Greiner

STAR HFTDetector Installation

Pxl installation pics1.Clean room2.Installed and cabled

PXL assembled in the STAR clean room

PXL inserted into the STAR TPC inner field cage, cabled and operational.Total installation time = 2 days.

Page 13: L. Greiner 1FEE 2014 – STAR PXL Vertex Detector STAR HFT LBNL Leo Greiner, Eric Anderssen, Giacomo Contin, Thorsten Stezelberger, Joe Silber, Xiangming

13FEE 2014 – STAR PXL Vertex DetectorL. Greiner

STAR HFTLessons learned during construction and installation

• Sensors– Build testing functionality into the sensor design from the start optimized for probe testing/module testing.

We developed the parametric testing requirements first and implemented them in the design with IPHC.

• Readout – Co-develop the RDO with the sensor. It is then guaranteed to work and you have time to find and fix

incompatibilities and quirks.

• Probe testing– Proper probe pin design for curved thinned sensors.

– Spend time on whole probe system yield (ours varied between 46% - 60%).

– Administrative control of sensor ID worked well for us.

• Engineering run– Do a proper full system test (if possible) in the correct environment with partial full detector and

infrastructure.

– We discovered mechanical problems even in a fully solid modeled system (interferences, kinematic mount insertion, etc.).

• Assembly– Spend time optimizing full yield through all production steps. Original ladder and sector yields were much

lower until all the problems were worked out.

– Acrylic adhesive works well as a CTE stress decoupling method.

Things that worked well and things that didn’t

Page 14: L. Greiner 1FEE 2014 – STAR PXL Vertex Detector STAR HFT LBNL Leo Greiner, Eric Anderssen, Giacomo Contin, Thorsten Stezelberger, Joe Silber, Xiangming

14FEE 2014 – STAR PXL Vertex DetectorL. Greiner

STAR HFTCosmic Ray Running

• PXL was installed with all sensors (400) working. < 2k bad pixels out of 356M.

• All pixel positions on each detector half were mapped in CMM prior to installation.

• PXL RDO and integration with STAR DAQ, trigger, etc. complete and working well.

• Automated threshold setting scripts applied (1600 thresholds need to be set). Noise rate is ~1-2 x 10-6 per sensor for most of the sensors. Last few sensors were tuned manually.

• All parameters are stable and preliminary alignment with cosmic ray tracks was made.

• Some misalignment in the kinematic mounts (~1mm).

• Sensor positions on detector halves appear to be as measured in the CMM before installation.

Page 15: L. Greiner 1FEE 2014 – STAR PXL Vertex Detector STAR HFT LBNL Leo Greiner, Eric Anderssen, Giacomo Contin, Thorsten Stezelberger, Joe Silber, Xiangming

15FEE 2014 – STAR PXL Vertex DetectorL. Greiner

STAR HFTPXL preliminary half-to-half pointing residuals

Consistent with expectations for alignment and momentum of muons.

Preliminary Preliminary Preliminary

Preliminary Preliminary Preliminary

Preliminary alignment by Alex Schmah

Inner layer

Outer layer

Page 16: L. Greiner 1FEE 2014 – STAR PXL Vertex Detector STAR HFT LBNL Leo Greiner, Eric Anderssen, Giacomo Contin, Thorsten Stezelberger, Joe Silber, Xiangming

16FEE 2014 – STAR PXL Vertex DetectorL. Greiner

STAR HFT15 GeV/c and 200 GeV/c running - status

15 GeV start

Jan25

PXL install

Feb14

200 GeV start

Mar14

now

May21

Jul7

• The HFT (PXL + IST) was used only intermittently in the 15 GeV/c Au+Au run.

• The HFT (PXL + IST) has been operated in the 200 GeV/c Au+Au since the start.

• The SSD is still commissioning and is expected to join the data taking in some weeks.

• We have 700M events stored and are on track to take >1G events in this run. This should meet the physics requirements.

End of run

Projection of current data rate to end of run

Page 17: L. Greiner 1FEE 2014 – STAR PXL Vertex Detector STAR HFT LBNL Leo Greiner, Eric Anderssen, Giacomo Contin, Thorsten Stezelberger, Joe Silber, Xiangming

17FEE 2014 – STAR PXL Vertex DetectorL. Greiner

STAR HFTPreliminary DCA Pointing resolution

Preliminary750 MeV Kaon

750 MeV Kaon

* Alignment still not complete

200 GeV/c Au-Au dataSimulation with Al Cable

TPC + IST + PXL

CD-4 requirement

Page 18: L. Greiner 1FEE 2014 – STAR PXL Vertex Detector STAR HFT LBNL Leo Greiner, Eric Anderssen, Giacomo Contin, Thorsten Stezelberger, Joe Silber, Xiangming

18FEE 2014 – STAR PXL Vertex DetectorL. Greiner

STAR HFTLessons learned from operation

• Perform full LU/rad environment testing of thinned production sensors/modules for all expected conditions.

– Sensors were being damaged in radiation field. We have lost ~15/400 sensors.– Damage apparently halted by limiting the energy available to a latch-up event (set LU

current thresholds to ~120mA over the ladder running current).– This is still under investigation. We will be performing additional LU testing in the near

future with thinned production sensors.

• Have backup solutions – e.g. Cu rather than Al conductor cables– Our aluminum conductor flex PCBs had problems during fabrication and, due to late

delivery, only 2 ladders with aluminum conductor were installed in the first run of the detector.

• Implement as much remote configuration of sensor/module and detector operating parameters as possible to allow for remediation of surprises.

– We implemented remote setting of ladder LU thresholds, voltage supplied to the ladders, voltage read, current read after first engineering run tests.

– This allowed us to diagnose and stop the damage described above.

Page 19: L. Greiner 1FEE 2014 – STAR PXL Vertex Detector STAR HFT LBNL Leo Greiner, Eric Anderssen, Giacomo Contin, Thorsten Stezelberger, Joe Silber, Xiangming

19FEE 2014 – STAR PXL Vertex DetectorL. Greiner

STAR HFToutlook

• The PXL detector at STAR was installed for the 2014 Au-Au run.

• The detector system appears to operate as designed, integration with STAR infrastructure is complete.

• The DCA pointing resolution performance of the installed HFT detectors appears to be as expected.

• Sensor damage related to the radiation field was observed. The damage appears to be able to be halted by using operational methods. Based on our observations, we should hopefully be able to prevent damage to the next installed detector.

• We expect to be able to deploy the spare detector (with Al conductor cable on the inner ladders) for the next run and repair the damage to the existing detector with the spare ladders being fabricated.

• At this point, it appears that the installed PXL detector will be able to complete the physics goals for this run.

• The spare detector should be ready in ~1 month.

• MAPS appear to be working well as a technology for vertex detectors.

Page 20: L. Greiner 1FEE 2014 – STAR PXL Vertex Detector STAR HFT LBNL Leo Greiner, Eric Anderssen, Giacomo Contin, Thorsten Stezelberger, Joe Silber, Xiangming

20FEE 2014 – STAR PXL Vertex DetectorL. Greiner

STAR HFT

• Extra slides

Page 21: L. Greiner 1FEE 2014 – STAR PXL Vertex Detector STAR HFT LBNL Leo Greiner, Eric Anderssen, Giacomo Contin, Thorsten Stezelberger, Joe Silber, Xiangming

21FEE 2014 – STAR PXL Vertex DetectorL. Greiner

STAR HFTPossible Mechanisms• Non-ionizing (Neutron) damage? – Dislocation of atoms in the matrix generally

results in permanent damage to silicon. This is consistent with what we observe. In discussions with Matt Durham who worked on the Phenix FVTX detector, he indicated that the beam tune into Phenix had some component of scraping against a magnet or beam pipe surface that caused spallation neutron based damage in their detector and that the neutron rate was nearly 3 orders of magnitude above what was calculated. In our case, we have no information about the neutron flux at low radii from the beamline.

• Ionizing radiation damage? – The primary source of ionizing radiation damage is expected to come from the transit of MIPs through the sensors. This is expected to show up in hits registered in sensor pixels. The occupancy of charged tracks is approximately what was projected in the simulations ( ~300 hits per frame on the inner ladders and ~100 hits per frame in the outer ladders). The likelihood of normal beam activities causing the damage observed is judged to be low. There have been, however, a significant number of non-standard events during this run. Particularly during the 15 GeV run period.

• LU related damage? – It is possible that LU events could cause damage in the silicon. This would need to be a phenomenon particular to thinned silicon and/or high resistivity epi. We did extensive testing of full thickness sensors at the BASE facility at the 88” cyclotron at LBNL where we exposed sensors to many thousands of LU events to measure the LU LET onset and cross-section.

Page 22: L. Greiner 1FEE 2014 – STAR PXL Vertex Detector STAR HFT LBNL Leo Greiner, Eric Anderssen, Giacomo Contin, Thorsten Stezelberger, Joe Silber, Xiangming

22FEE 2014 – STAR PXL Vertex DetectorL. Greiner

STAR HFT

Digital current on the inner ladders

NOW

Before operational optimizations

Amps

Amps

Page 23: L. Greiner 1FEE 2014 – STAR PXL Vertex Detector STAR HFT LBNL Leo Greiner, Eric Anderssen, Giacomo Contin, Thorsten Stezelberger, Joe Silber, Xiangming

23FEE 2014 – STAR PXL Vertex DetectorL. Greiner

STAR HFTPXL increased current consumption

23

Page 24: L. Greiner 1FEE 2014 – STAR PXL Vertex Detector STAR HFT LBNL Leo Greiner, Eric Anderssen, Giacomo Contin, Thorsten Stezelberger, Joe Silber, Xiangming

24FEE 2014 – STAR PXL Vertex DetectorL. Greiner

STAR HFTProposed Testing Plan

Proton IrradiationThe testing done for ionizing radiation dose was done with gamma rays. This is a generally accepted method of assessing the radiation tolerance of silicon designs. The proton irradiation more closely mimics the environment at the operating STAR experiment and adds displacement damage to the mix. We propose to expose an existing powered PXL ladder to proton beams at the 88” cyclotron at LBNL at various rates up to 300 kRad as well as testing the latch-up cross section due to proton irradiation (if possible, the primary proton LU mechanism of energy deposition from recoil only turns on at ~100 MeV).Latch-up TestingIt is possible that the damage observed is related to latch-up. The fact that the sensors are now thinned to 50um could give opportunity for other failure mechanisms such as micro-fracturing due to higher LU point temperature excursions. We propose to expose an existing PXL ladder and thinned sensor on testing cards to heavy ion beams at the 88” Cyclotron BASE facility for up to 5k latch-up events on a sensor. We will also measure the voltage discharge profile on the ladder to understand the profile of energy deposition in the silicon LU area. The production sensors have high resistivity epi and the initial LU test sensors were standard epi.Neutron IrradiationIt is possible that we are being exposed to a much higher neutron flux than has been anticipated. We propose to irradiate some sensors to doses of 1013, 1014 and 1015 1MeV Neq / cm2 . These sensors have already been sent to Sandia for irradiation with a batch of ATLAS sensors.

Page 25: L. Greiner 1FEE 2014 – STAR PXL Vertex Detector STAR HFT LBNL Leo Greiner, Eric Anderssen, Giacomo Contin, Thorsten Stezelberger, Joe Silber, Xiangming

25FEE 2014 – STAR PXL Vertex DetectorL. Greiner

STAR HFTRun 15090063 - Mon Mar 31 21:16:0

Sector 10 L1 = 1.57 AL2 = 0.78 AL3 = 0.78 AL4 = 0.78 A

Page 26: L. Greiner 1FEE 2014 – STAR PXL Vertex Detector STAR HFT LBNL Leo Greiner, Eric Anderssen, Giacomo Contin, Thorsten Stezelberger, Joe Silber, Xiangming

26FEE 2014 – STAR PXL Vertex DetectorL. Greiner

STAR HFTLadder assembly work flow chart

Probe tested sensors

Electrically tested low mass cables

Electrically tested driver boards

Dimensionally checked composite backer

Ladder assembly

Ladder wire bonding

Wire bond encapsulation

Quick test

Full functionality test

Complete ladder

• Ladder characterization

• Reworking and troubleshooting

• Quality assessment• Initial validation

1 day without problem

sFull functionality testbias optimizationThreshold scanNormal readout mode testAccidental hit rate scan

Quick testThreshold scan @ nominal bias settings

Page 27: L. Greiner 1FEE 2014 – STAR PXL Vertex Detector STAR HFT LBNL Leo Greiner, Eric Anderssen, Giacomo Contin, Thorsten Stezelberger, Joe Silber, Xiangming

27FEE 2014 – STAR PXL Vertex DetectorL. Greiner

STAR HFTSector/half-detector work flow chart

TestedLadders

SizedSector Tubes

machined Dovetail/D-tube

Elect testedMTB/cables/insertion

Sector assembly

Full functionality test

Quick test

Half detector headassembly

Sector metrology

½ HFT PXL

Quick test

Half detector head metrology

Full Half detector assembly

Quick test

Page 28: L. Greiner 1FEE 2014 – STAR PXL Vertex Detector STAR HFT LBNL Leo Greiner, Eric Anderssen, Giacomo Contin, Thorsten Stezelberger, Joe Silber, Xiangming

28FEE 2014 – STAR PXL Vertex DetectorL. Greiner

STAR HFTLadder Design

Ladder cable concept

Page 29: L. Greiner 1FEE 2014 – STAR PXL Vertex Detector STAR HFT LBNL Leo Greiner, Eric Anderssen, Giacomo Contin, Thorsten Stezelberger, Joe Silber, Xiangming

29FEE 2014 – STAR PXL Vertex DetectorL. Greiner

STAR HFTRadiation length in low mass area

Si 50um (0.0529%)

acrylic 50um (0.0148%)

Encapsulant + bond wires (0.070%)

Capacitors + solder (0.0035%)

Coverlay (0.0075%)

Coverlay (0.0075%)

Al 30um – both sides (0.0248%)kapton 50um (0.0148%)

acrylic 50um (0.0148%)

Carbon composite 125um (0.0293%)

0.0677%

0.128%

0.0441%

fromolderestimate Carbon composite 250um (0.1017%)

Si adhesive 100 um (0.0469%)

0.1486%

Total = 0.388%NOTE: Does not include sector tube side walls

Page 30: L. Greiner 1FEE 2014 – STAR PXL Vertex Detector STAR HFT LBNL Leo Greiner, Eric Anderssen, Giacomo Contin, Thorsten Stezelberger, Joe Silber, Xiangming

30FEE 2014 – STAR PXL Vertex DetectorL. Greiner

STAR HFTPXL insertion mechanics

Interaction point view of the PXL insertion rails and kinematic mount points

Carbon fiber rails

Kinematic mounts

Page 31: L. Greiner 1FEE 2014 – STAR PXL Vertex Detector STAR HFT LBNL Leo Greiner, Eric Anderssen, Giacomo Contin, Thorsten Stezelberger, Joe Silber, Xiangming

31FEE 2014 – STAR PXL Vertex DetectorL. Greiner

STAR HFT

• Probe card with readout electronics – derived from individual sensor test card

• Analog and digital sensor readout• Full speed readout at 160 MHz• Full sensor characterization at full speed

– Test results used for initial settings in ladder testing and PXL detector configuration

• 2nd generation probe card for production testing– only digital readout pins loaded

Yield modeling makes probe testing critical to the goal of assembling functional 10 sensor ladders.

We test thinned and diced 50 µm thick sensors (curved). This is not easy.

Assembling sensors into ladders – Probe Testing